1.0
SITE SERVICES
These services shall be rendered by SEC as part of the overall project
management service. The services shall broadly include but not be limited
to the following:
Erection and commissioning supervision staff has to be deployed by
SEC from start of erection of main plant equipments till completion of
the project . Deployment schedule for supervisory staff shall be
mutually discussed and agreed between JSWEVL & SEC
PG test for boiler, turbine and generator & any other site test shall be
carried out by SEC or its equipment vendor. Any special tools ,tackles
and instrument shall be arranged by SEC.
SITE ORGANISATION
The Contractor shall maintain a site organisation of adequate strength in
respect of manpower, and other implements at all times for smooth
execution of the contract. This organisation shall be reinforced from time
to time, as required, to make up for slippages from the schedule without
any commercial implication to the Owner .The site organisation shall be
headed by a competent construction manager having minimum 20 years
experience in supervision of construction of power plants and adequate
authority to take decisions at site.
*
3.0
3.1
Deleted
Deleted
3.2
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 2 OF 7
TITLE
SITE SERVICES
The Contractor shall provide his own on-site / off-site telephone facilities.
The Contractor shall obtain permission, from the appropriate authorities
before any radio wave emanating system is used at the site. This includes
radio telephones and pagers, transceivers, cordless and cellular
telephones and such any other systems. Both partiesThe Contractor shall
ensure that the radio communication systems do not cause interference to
control and instrumentation and communication systems installed in the
power plant.
EMPLOYEE FOOD SERVICE
A food facility shall be provided on the site by the Contractor for the
reasonable use of both his and his sub-Contractors employees
SITE RECORDS OFFICE
The Contractor shall maintain a suitable records office to maintain
updated records of all relevant documentation and test certificates
and to ensure that these are available to meet obligations to all
statutory bodies and to any commissioning committee, working
parties or test teams which are established to meet the needs of the
contract. These records shall be maintained and retained until hand
over on completion of all works at site and shall be subject to Audit
by the Owner.
(a)
Commissioning documents
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 3 OF 7
TITLE
SITE SERVICES
(j)
(k)
(l)
SITE RESTRICTIONS
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 4 OF 7
TITLE
SITE SERVICES
SEC and his employees shall not trespass beyond the boundary limits of
the site on to any adjoining land and SEC shall take necessary action to
prevent trespassing.
5.0
SITE ACCESS
It is the responsibility of JSWEVL.Void
6.0
6.1
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 5 OF 7
TITLE
SITE SERVICES
6.2
SEC shall co-operate with the JSWEVL and any other Contractors /
Agencies working at site and arrange to perform his work in a manner so
as to minimise interference with other Contractors / Agencies works. The
JSWEVL shall be notified promptly of any defect in other Contractors /
Agencies works that could affect SECs work. If rescheduling of
Contractors work is requested by the JSWEVL in the interest of overall
site activities, the same shall be complied with by SEC. In all cases of
controversy, the decision of the JSWEVL shall be final and binding on SEC
without any commercial implication.
6.3
The JSWEVL may hold meetings of all SECs / Agencies at site at a time
and a place to be designated by the JSWEVL. SEC shall attend such
meetings if called upon to do so, take note of the decisions of the JSWEVL
and shall strictly adhere to those decisions in performing his work.
6.4
6.5
6.6
SEC shall comply with all the rules and regulations of the local authorities,
all statutory laws including Minimum Wages, Workmen Compensation, etc.
6.7
6.8
6.9
7.0
7.1
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 6 OF 7
TITLE
SITE SERVICES
The system of notifying all employees of the site safety plan, method
statements and site safety rules
The Contractor shall ensure the safety of all workmen, materials and
equipment either belonging to him or to others working at site. He shall
observe safety rules & codes applied by the Owner at site without
exception.
SEC shall notify the JSWEVL of his intention to bring to site any equipment
or material which may create hazard. The JSWEVL shall have the right to
prescribe the conditions under which such equipment or material may be
handled or prohibit the use of the same for safety reasons. Contractor
shall abide by JSWEVLs decision in such cases.
No claim for
compensation due to such prohibition will be entertained by the JSWEVL.
SPEC.NO.
TCE-4857A-C-510-
Vol. II ; Part - I
Sec. C 9
Sh. 7 OF 7
TITLE
SITE SERVICES
The Contractor shall be responsible for safe storage of his and his subContractors radioactive sources
.
All combustible waste and rubbish shall be collected and removed from the
work site at least once each day. Use of undercoated canvas, paper,
corrugated paper, fabricated carton, plastic or other flammable materials
shall be restricted to the minimum and promptly removed. All electrical
appliances used in the work shall be in good working condition and shall
be properly earthed. No maintenance work shall be carried out on live
equipment. The Contractor shall maintain adequate number of qualified
electricians to maintain his temporary electrical installation
All
workmen of SEC working in construction site shall wear safety helmets,
safety boots and safety belts. SEC shall take appropriate insurance cover
against accidents for his workmen as well as third party.
7.2
8.0
8.1 SEC The Contractor shall provide all necessary information to JSWEVL for
JSWEVLs requirements to properly handlinge, storinge, utilisinge and
disposinge of any Project materials considered hazardous under any
governmental or local law, regulation, statute, or ordinance in effect at the job
site8.
8.2
SEC
shall
provide
supervision
services
to
JSWEVL
in
unloading,inspection,storage and preservation of materials and equipment in the
scope of supply of SEC. Necessary storage handling preservation manuals shall
be provided by SEC.