Beruflich Dokumente
Kultur Dokumente
Contents
1.
INTRODUCTION
8
1.1
Background
8
1.2
Field Investigations
9
1.3
Bathymetry
9
1.4
2.
SITE CONDITIONS
10
2.1
Site Appreciation
10
2.2
Climate
12
2.4
3.
WATER QUALITY
14
3.1
Seawater Quality
14
3.1.1
3.1.2
Field Investigations
Page 1
Interim Report
15
3.1.4
3.2
3.2.1
Boron
22
3.2.3
4.
Design Life
24
4.2
RO Rack Configuration
24
4.3
Primary Flows
25
5.
SEAWATER INTAKE
27
5.1
Primary Flows
27
5.2
5.3
5.5
Interim Report
32
5.6
Pipe jacking
33
5.6.2
Inter-jacks
34
5.6.4
Slurry System
34
6.
PRETREATMENT SYSTEM
35
6.1
Pretreatment Process
35
6.2
6.2.1
6.2.2
6.3
pH Correction
37
6.4
Coagulation
37
6.5
Flocculation
38
6.6
Lamella Settlers
39
6.7
Ultrafiltration (UF)
43
Page 3
Interim Report
6.9
7.
Overview of RO Plant
45
7.2
Cartridge Filtration
47
7.4
Oxidant Control
47
7.5
Scale Control
47
7.6
RO Rack Design
52
7.8
Permeate Storage
56
POST TREATMENT
8.
57
8.1
Re-mineralization/Stabilization
57
8.1.1
8.1.2
Page 4
Interim Report
8.2
Disinfection
61
9.
CHEMICAL SYSTEMS
67
9.1
Antiscalant
68
9.2
Carbon Dioxide
69
9.3
Chlorine Gas
69
9.4
Ferric Chloride
71
9.5
Hydrated Lime
71
9.6
Sodium Hydroxide
73
9.8
Sodium (Meta)bisulphite
74
9.9
Sulphuric Acid
75
Cleaning-in-place (CIP)
77
9.11.2
Flushing
78
Interim Report
11.
SEAWATER OUTFALL
80
11.1 Outfall Pipeline
80
11.2 Diffusers
80
Background
81
12.1.2
Design Considerations
81
12.1.3
12.1.4
12.1.6
Electrical Equipment
83
12.2.2
12.2.3
Interim Report
85
General
87
13.1.2
Lifting Devices
88
14.1.2
14.1.3
14.1.4
Interim Report
108
Executive Summary
Survey Data
Significant findings in respect of Field Work and Historical Data gathering
including the data of existing 100 MLD Neemeli SWRO are as following:
1.
Intake water quality data from Nemmeli plant was provided for the period
from and including May 2013 to early December 2013. The data shows
poor water quality on a number of occasions as evidenced by frequent
spikes in turbidity. These spikes in turbidity resulted in plant shutdown on
13 days in the period of record ie a loss of production on 7% of days of
record.
In July 2013 the Nemmeli plant was closed for 5 days; the water quality
data shows that there was no discernible change in salinity in this period.
In the first week of December 2013 the plant was closed for 4 consecutive
days; the water quality data shows that the salinity dropped significantly
over this period indicating the influx of fresh water, which contained high
levels of suspended solids.
There is strong evidence that jelly fish are frequently in abundance along
the Chennai coast and have caused considerable nuisance in power
station intakes.
Page 8
Interim Report
In literature, algal blooms have been documented along both the west and
east coasts of India. It can be expected that algal blooms will impact upon
a desalination plant at Perur from time to time.
3.
The influence of
littoral drift is significant and the annual net drift takes place in a northerly
direction.
Pre-treatment Processes
High levels of TSS, algae and jelly fish are expected to be drawn in at the
intake to the plant, either constantly or cyclically, and the pre-treatment
plant must be designed to maintain a high quality feed to the desalination
plant, over the long term.
Because of the jelly fish, at the intake offshore a vertical screen with 100
mm c/c have been proposed to have an approach velocity not exceeding
0.1 m/s at peak flows. A fish net is proposed to be placed outside the
vertical mesh screens to reduce the intake of jelly fish.
Fine screens will be provided before the sea water pumps to capture the
jelly fish and minimise the chance of breaking up the jelly fish, which
would make it harder to remove jelly fish particles.
The fine screens will be provided with 3 mm apertures, targeting jelly fish.
.
DAF process may be capable of handling 10-20 mg/L of TSS, but would not
be capable of handling greater than 75 mg/L of TSS.
Interim Report
filtration processes.
A DAF loading rate of 8 m/hr has been nominated, when operating with 20%
recycle. The nominated recycle rate is high, cf 10 to 12 m/hr at other plants,
so as to be able to handle the anticipated high solids loading rate. Lower
recycle rates will be available to the operator when the water quality is good.
The DAF will be followed by Ultrafiltration (UF), due to space constraints. The
gross flux shall be 50LMH.
RO Plant
Membrane Flux and Overall Recovery
The RO plant is a single stage/single pass design with an overall recovery of
46% specified.
SWRO membrane elements of 8-inch diameter have been selected.
Each
pressure vessel will house eight membrane elements. The design treated water
TDS for the RO plant is 300 mg/L. In sizing the RO plant, an average membrane
flux of approximately 13.5 L/m2/hour (LMH) has been selected. The provision
of 8% spare space for more membranes provides the flexibility to reduce the
flux if warranted, to reduce cleaning frequency or reduce power consumption.
Pumping System Design and Pressure Control
Based on preliminary membrane projections for DOW and Hydranautics
membranes, it is anticipated that the required membrane pressure will range
between 51.6 bar and 65.3 bar, depending on feed water and membrane
conditions, and depending on the membrane selected. In order to provide the
above pressure range, and based on the design temperature and salinity
ranges set out depicted in the report, a combination of VSD driven booster
pumps and fixed speed RO HP pumps has been selected to provide operational
flexibility and minimise electrical energy costs.
With this design the RO Booster pumps will provide feed pressure adjustments
Page 10
Interim Report
Potabilisation
This design nominates a target alkalinity of 40 to 60 mg/L as oppose to the ISO
standard of 200 mg/L (Desirable). This is because at this alkalinity, a positive
Langelier Index is achieved, which is the minimum requirement for addressing
the risk of corrosive water. Higher target alkalinity, while desirable (as it would
further reduce the risk of corrosive water by minimising pH change in the final
water) would require additional stabilisation chemicals, and therefore additional
cost.
Page 11
Interim Report
1.
1.1
INTRODUCTION
Background
1133.0 MLD
Industries
37.0 MLD
28.0 MLD
Sriperumpudur
17.7 MLD
14.0 MLD
329.0 MLD
1559 MLD
Supply
831 MLD
GAP
728 MLD
1.2
Field Investigations
Page 12
Interim Report
1.3
Bathymetry
The data collected from the survey reports of existing of 100 MLD Neemeli and the
oceanographic survey carried out for the proposed 400 MLD SWRO to be located
next to Neemeli, the bathymetry chart shows that the depth contours are generally
running parallel to the coast. The seabed exists with the gradient of 1:40-1:70 till 7
m depth and downstream showed the gradient of 1:150-1: 250.
1.4
Page 13
Interim Report
2.
2.1
SITE CONDITIONS
Site Appreciation
The proposed site for 150 MLD desalination Plant is located within the premises of
existing 100 MLD Sea Water Desalination Plant at Nemmeli along East Coast Road,
Kancheepuram District, Tamilnadu, India. The site is located at eastern side of East
Coast Road (ECR) at 12 42' 08" North, 80 13' 29" East and is approximately 40 km
of south of Chennai city.
The climatic conditions are characterised by warm dry winters (27 OC average daily
max) and hot wetter summers (39 OC average daily max) with an annual average
rainfall of 1200mm. Cyclones are common in the area and the site is expected to be
effected by approximately 3 per year.
Page 14
Interim Report
Fig 2:Site Location with respect to proposed 400 MLD Perur Desalination
Plant
The site for the proposed 150 MLD is spread over an area of around 9 acre,
placed within the premises of existing 100 MLD SWRO Neemeli. The area has
non-uniform width with around 100 m frontage on the sea side, which increases in
the middle of the site towards the ECR, however again on the road frontage is
tapered due to presence of existing Burial ground.
Therefore with the above site conditions, the uniformity of area available is a major
constraint, which in turn condenses the effective space utilization for engineering
and planning of the facility. Therefore with the above physical constraints, the plant
with membrane pre-treatment is proposed for an output capacity of 150 MLD.
Page 15
Interim Report
2.2
2.3
Climate
Chennai, Tamil Nadu has a tropical wet and dry/ savanna climate (Kppen-Geiger
classification: Aw) with a pronounced dry season in the low-sun months, no cold
season, wet season is in the high-sun months. According to the Holdridge life
zones system of bioclimatic classification Chennai, Tamil Nadu is close to
the tropical dry forest biome.
Page 16
Interim Report
remains
more
dynamic
Fig
and
and the annual net drift takes place in a northerly direction. The near-shore waters
support certain type of demersal fisheries with moderate bottom animal
community. Tourism and beach resorts are developing rapidly in this region.
Page 17
Interim Report
3.
WATER QUALITY
3.1
Seawater Quality
3.1.1
Interim Report
3.1.2
3.1.3
Field Investigations
Water quality data was collected off Perur (Next to Neemeli) in late July - early
August 2013. The data was collected at the surface and at the bottom, on six
transects, at locations at 750 m, 1000 m and 1250 m to sea.
has been analysed and the average results for the various analytes are tabulated
below, in Table 1
Page 19
Interim Report
Table 1
Parameter
Unit
Average at Surface
Average at
Bottom
1
2
3
4
5
6
7
8
9
10
Temp. (C)
TDS (mg/l)
Salinity (ppt)
pH
DO (mg/l)
BOD (mg/l)
COD (mg/l)
Colour, Hazen Units
Odour
Taste
28.4
35,100
34.7
8.20
6.61
2.51
25.0
17.7
Odourless
Salty
27.9
35,200
34.7
8.21
5.89
1.83
39.3
18.7
Odourless
Salty
11
12
111.7
6137
116.0
6038
13
14
15
16
17
18
19
20
21
22
Bicarbonate (mg/l)
TSS (mg/l)
Turbidity (NTU)
NO2-N (mg/l)
NO3-N (mg/l)
Total Nitrogen (mg/l)
PO4-P (mol/l)
Total phosphorus (mol/l)
NH3-N (mol/l)
Magnesium as Mg (mg/l)
127.8
48.7
1.10
0.45
2.68
11.8
0.76
1.45
0.20
1191
126.3
73.3
1.88
0.97
4.08
14.5
0.93
1.36
0.18
1258
23
24
25
26
27
28
29
30
31
32
33
Calcium as Ca (mg/l)
Chloride as Cl (mg/l)
Potassium as K (mg/l)
Sulphate as SO4 (mg/l)
Sulphide as H2S (mg/l)
Colloidal Silica (mg/l)
Reactive Silica as SiO2 (mg/l)
Free Residual Chlorine (mg/l)
Fluoride as F (mg/l)
Oil & Grease (mg/l)
Phenolic compounds as C6H5OH
367
18302
375
2758
<0.01
<0.02
0.84
<0.2
1.49
<2
<0.01
467
18502
391
2878
<0.01
<0.02
1.38
<0.2
1.63
<2
<0.01
<0.5
3.25
<0.5
3.17
(mg/l)
34
35
Barium as Ba (mg/l)
Boron as B (mg/l)
Page 20
Interim Report
36
37
38
39
40
41
42
43
Cadmium as Cd (mg/l)
Cyanide as Cn (mg/l)
Iron as Fe (mg/l)
Lead as Pb (mg/l)
Manganese as Mn (mg/l)
Selenium as Se (mg/l)
Total Arsenic as As (mg/l)
Zinc as Zn (mg/l)
<0.01
<0.05
<0.01
<0.01
<0.05
0.022
<0.01
0.092
<0.01
<0.05
<0.01
<0.01
<0.05
0.023
<0.01
0.088
Page 21
Interim Report
3.1.4
The sea water quality adopted for design purposes is tabulated in and
is based on the water quality sampling program as cited above
Table 3 and
In the Normal values are based on the average data gathered from the field. The
Minimal and Maximum adopted values draw upon data gathered from the area, as
set out above, and upon the experience of the designers.
Page 22
Interim Report
Table 2
Criteria Description
Water Temperatures
- surface
- bottom
Turbidity
Total Suspended Solids
pH
Total Dissolved Solids
Unit
C
C
NTU
mg/L
mg/L
Normal based
on field
measurements
Minimum adopted
Maximum adopted
28.4
27.9*
<10
75
8.2
35,200
26.0
25.0
10
50
7.7
32,000
30.0
32.0*
125
200
8.5
38,000
Note: * The design of the RO Plant will make provision for a rise in seawater temperature of 1 oC
resulting from the energy input at the pumps.
In
Table 3, the design values for the proposed plant are stated herewith.
Table 3
Criteria Description
Unit
Normal based on
average field
measurements
Temperature
Total Dissolved Solids
Bicarbonate (HCO3)
Magnesium as Mg
Calcium as Ca
Chloride as Cl
Potassium as K
Sulphate as SO4
Reactive Silica as SiO2
Fluoride as F
Barium as Ba
Boron as B
Sodium Na
Nitrate NO3
Ammonium
C
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
27.9
35,200
126.3
1258
467
19,247
391
2,878
1.38
1.63
0
3.17
10,789
4
0.2
Page 23
Interim Report
3.2
Substance or characteristic
Requirement
Essential Characteristics
(Desirable
i.
ii.
Odour
Unobjectiona
iii.
Taste
ble
Agreeable
iv.
v.
pH value
6.5 to 8.5
vi.
300
vii.
0.3
viii.
250
ix.
0.2
x.
1.5
Desirable Characteristics
xi.
500
xii
75
xiii.
30
xiv.
0.05
xv.
0.1
xvi.
200
xvii.
45
xviii.
0.001
xix.
0.001
xx.
0.01
xxi.
0.01
xxii.
0.01
xxiii.
0.05
xxiv.
0.05
Page 24
Interim Report
xxv.
xxvi.
0.2
xxvii.
xxix.
0.01
xxx.
Absent
Substance or characteristic
xxxi
Radioactive materials *
a) Alpha emitters Bq/l, Max
0.1*
1*
xxxi.
200
xxxii.
0.03
xxxiii.
xxxiv
positive
3.2.1
3.2.2
Boron
Boron emerged as a water quality issue with the increasing use of desalinated
seawater for both municipal drinking water supply purposes and for irrigation. The
human health effects of boron have been debated for some time with increasing
confidence, and higher allowable concentrations, from studies over the last 10
years. This is reflected by increases in guideline standards, whereby WHO have
changed their guidelines over the last ten years from 0.3, to 0.5 (2008) and now to
2.4 mg boron/L in the most recent (fourth) edition of the guidelines. A summary
statement on the World Health Organisations (WHO) recommended boron
Page 25
Interim Report
guideline value has been posted on the WHO Water Sanitation and Health website
at:
www.who.int/water_sanitation_health/dwq/chemicals/boron/en/.
The
new
guideline value of 2.4 mg/L was based on a human health point of view. The level
was derived based on an assumption that 40 per cent of a 60 kg adults total daily
intake of boron is a result of drinking 2 litre of water having a boron concentration
of 2.4 mg/L and a safety factor of 60x.
While sodium and chloride ions are well rejected by RO membranes, boron is not
well rejected because a high portion of the boron species is uncharged. The
rejection of boron is strongly dependent on feedwater pH. Under optimal neutral to
alkaline conditions, boron rejection is 70 to 80%, reducing to as low as 50 to 60%
under more acidic feed conditions.
IS 10 500 states that one of the desirable characteristics of drinking water is that
the maximum concentration of boron be not greater than 1 mg/L.
Modelling
indicates that single pass RO can reduce the concentration of boron to between
0.4 and 1.0 mg/L, assuming a maximum feedwater concentration in the source
water of 3.4 mg/L, depending on the age and type/brand of the membranes.
For the purposes of this report the design target for boron has been set at 0.75
mg/L at commissioning, ie with new membranes. The concentration of boron in
the permeate is expected to rise as the membranes approach their AMLT, and it is
expected that minor variations to the process operation, primarily adjustment of the
pH and the addition of anti-scalant, will allow the concentration of boron to be
maintained below the long term goal of < 1.0 mg/L.
3.2.3
Interim Report
or by letting them pass freely. To prevent jelly fish from flowing in with water
current, fish netting is proposed to be installed in front of the water intake where
inlet velocity is low. This method is adopted at many power stations including
Tarapur Atomic Power Station including existing SWRO plants.
4.
DESIGN
LIFE
AND
AVAILABILITY;
PRIMARY
FLOWS
4.1
Design Life
Interim Report
4.2
15 years instruments;
4.2.1
RO Rack Configuration
The size of the RO train impacts on the number of trains, all equipments as well
as the pipework required, along with pump set efficiencies. To have the most
optimal of above, the RO racks have been selected within each train having the
following characteristic:
Details
RO Configuration
13
20
260
240
8% (20 PVs)
1920
Page 28
Interim Report
As shown in Table 5 space has been provided in the RO racks for additional PVs,
which may be installed to respond to operational and environmental changes, as
well as to compensate for deviations from the design of the plant or equipment
performances. The additional PVs would not be installed to increase the capacity
of the trains above the design value, but should be used to ensure maintenance of
the design capacity of the trains.
The RO building will be designed to house six trains, in a single row. There shall
be no standby train.
4.3
Primary Flows
Based on the proposed operation and availability of the plant as described above,
primary flows have been calculated and are tabulated below in Table 6. It is to be
noted that these flows are not the final design flows and can be expected to vary
slightly as the designs are developed.
Table 6 Primary Flows 150 MLD Plant
Section
Product Water Tank to Chennai
150 MLD
3 MLD
Permeate Production
25.5 MLD
30.0 MLD
7.0 MLD
To Pre-treatment
Screened
Sea
Water
to
treatment
Intake Flow
394 MLD
242 MLD
Page 29
Interim Report
5.
5.1
SEAWATER INTAKE
Primary Flows
The intake system will be designed to have a hydraulic capacity of 394 MLD,
whereas the sea water pumping station will be designed to have a peak capacity of
395 MLD, wherein 1.0 MLD required for screen washing will be returned upstream
of screen.
The intake conduits shall be sized with 10% additional capacity to take care for
bio-growth which shall result in reduction of carrying capacity. Therefore the inlet
pipe shall be sized for a flow of 435 MLD.
The intake conduit shall be of 2100 mm (ID) diameter and the outlet conduit shall
Page 30
Interim Report
5.2
A fish net with will be provided to minimise the ingress of jelly fish to the intake.
The fish net will be required to be inspected and replaced from time to time, as the
same is likely to be damaged by marine lives. The head loss through the intake
system will also be monitored, and in any increase in system losses indicating
fouling at the intake, or the growth of biomass within the intake conduit, the same
shall be cleaned through divers.
5.3
Interim Report
The advantage of providing the screens before the pumps is to capture the jelly
fish that bypass the off shore screen and fishing net on the shore alive, thus
preserving the same and returning them to the sea in order to have a sustainable
ecosystem.
A typical band screen installation is shown in Figure 8 below.
Band screens have been in service for screening sea water for many years. They
provide efficient removal with relatively low maintenance costs and also have
Construction costs that are relatively low as compared to the total plant cost.
Through-flow band screens have been proposed herewith. Typically mesh sizes
vary from 2 mm to 10 mm, and, in view of the marine biomass problems at
Nemmeli, a mesh size of 3 mm has been selected.
Table 7 : Band Screen Design Parameters
Parameter
Units
Value
Seawater flow
MLD
395
Page 32
Interim Report
5.4
Duty
Stand by
MLD
198
mm
4.0
2.8-3 m
m/s
0.85-0.90
2.2
1.8
L/s
15-20
The tides at Perur, next to the Nemeeli as well as site ( data taken from DPR of
Existing 100 MLD SWRO Neemeli) are as follows, in metres above Chart Datum,
and relative to the site datum:
Chart Datum
RL
1.15
RL 0.5
0.84
RL 0.19
0.65
RL 0.0
Page 33
Interim Report
0.43
RL 0.22
0.14
RL 0.51
Onshore survey levels are recorded as metres above Mean Sea Level. Thus
Mean High Water Springs is 1.15 0.65 = RL 0.5, and Mean Low Water Springs is
0.14 0.65 = RL 0.51.
The low no flow level in the pump well has been taken as RL 0.50. At a flow of
395 MLD in intake conduit, the hydraulic grade line entering the proposed pumping
station will be approximately 1.7 m lower, at RL 2.2. A head loss of 0.8 is
provided/allowed for loss through screens resulting in low-low water levels in sump
cum pump station as RL-3.0.
Three (3) metres has been provided to the bottom of the pumps, which has been
assumed to be 0.5 m above the bottom of the pumping station at RL 6.5 to
ensure sufficient submergence for the pumps, and to allow for surging in the intake
line. Subject to the detailed design of the intake conduits, it is anticipated that the
intake conduit will enter the pumping station at between RL 6.5 and RL 4.5.
Therefore, the static lift at Mean Low Water Springs will be from RL -3.0 to around
RL 14.5, ie around 17.5 metres; and the static lift at Mean High Water Springs will
be from RL -2.0 to around RL 14.5, i.e. around 16.5 metres.
Pump Configuration
There shall be 3 W + 2 S pumps sets in wet well delivering as cited below
Three working pumps, delivering to a common manifold of 2.0 m diameter, with
a two pump as standby
With 3 pumps in operation each pump must be capable of delivering 132 MLD
(1528 L/s), at a head of around 25 metres.
Each pump will have a delivery line 1.1 metres in diameter (V = 1.60 m/s),
connected to the manifold 2.0 metres in diameter.
Page 34
Interim Report
Isolation valves along with flow meters shall be installed main and branch
manifolds.
These pumps are Vertical Turbine pumps with large clear passages. The intake
screen and net at the intake will prevent the ingress of material like to cause a
blockage.
Parameter
Units
Value
MLD
395
Wet Wells
Duty Pumps
Standby
RL
0.5
RL
- 0.51
1.7-1.8
1.1
2.0
RL
7.0
Equipment per pump unit: isolation valves, non-return valve and magnetic flow
meter,
5.5
Pump station control: by plant PLC based upon target flow rate,
Interim Report
pump station and pressure main. Criteria adopted for the shock chlorination
system are summarised below;
5.6
BS5911 Specification for reinforced concrete jacking pipes with flexible joints.
Interim Report
to delivery.
5.6.1
Pipe jacking
The tunnel shall be constructed by pipe jacking techniques using a purpose made
TBM for excavation. The TBM shall be designed as a slurry machine offering
controlled support pressure to the tunnel face and allowing for the use of bentonite
Slurry where required. The complete system shall be purpose designed for the
project and shall include TBM, slurry, circuit, main jacking station, interjack stations
and automatic bentonite injection system for lubrication of the pipe annulus.
The jacking pipes for this project shall be 2100mm and 1400 mm I/D. They shall
be using steel (Super Duplex : PERN>43) banded joints with full section contact
between adjacent pipes. The design of the pipes shall be sufficient to withstand
the jacking and overburden pressures assuming that inter jack stations are
installed at 100m spacing. The design should also allow for driving the tunnel at a
100-150m radius.
5.6.2
5.6.3
Inter-jacks
Interjack stations shall be designed to provide sufficient jacking force to overcome
the frictional resistance to pipe motion over the distance between them. The
interjack stations should have a minimum capacity of 1200 tonnes and a maximum
Page 37
Interim Report
spacing of 300 m. The seal shall be adjustable to exclude the ingress of ground
water and bentonite and shall be capable of withstanding working pressures in
excess of 4bar.
Hydraulic power to operate the inter jack stations shall be provided by power packs
situated in both the TBM and in the launch shaft. In order to minimise hose lengths
and subsequent power losses, the forward inter jacks shall be fed from the TBM
power pack and the rear inter jacks, from the shaft power pack.
On completion of tunnelling operations all interjack cylinders and seal assemblies
shall be removed. The exposed steelwork shall be properly cleaned and treated
with epoxy paint suitable for sea water conditions and the pipes shall be closed to
eliminate the gap. The adjustable interjack sealing systems shall be manufactured
to facilitate easy removal by hand within the tunnel.
5.6.4
Slurry System
The slurry system shall be designed to be capable of functioning with bentonite
slurry where required as a support medium. The slurry circuit shall be designed for
a minimum flow rate of 400m3/hr. The slurry circuit shall include flow meters on
both feed and discharge lines.
Feed pipes shall be 250mm nominal internal diameter and slurry discharge 200mm
internal diameter. Automatic valves shall be included at the shaft top to allow for
immediate closure by the operator in the event of burst system hoses. The
separation plant shall be sized to be 25% over capacity to account for any possible
flow surges within the slurry circuit.
All controls and indicators for running the slurry system shall be available at TBM
operators console.
6.
6.1
PRETREATMENT SYSTEM
Pretreatment Process
The pre-treatment process has been sized assuming that there are 6 membrane
trains in operation to produce 150 MLD permeate.
Page 38
Interim Report
6.2
Turbidity
Capex
Opex
Ease of operation
Robustness
6.2.1
Interim Report
surface indicates that the suspended solids have a density slightly higher than sea
water.
Since the seawater intake is located near the seabed, the bottom
suspended solids readings are quite relevant to the design of the pre-treatment
system.
Marine Biomass
Marine biomass includes jelly fish, larvae and algae.
Organic Pollutants
The presence of organic pollutants is indicated by measurements such as BOD,
COD, NO2, NO3, and NH3. BOD is relatively low, however, COD is much higher;
the reason for high COD is not clearly correlated, but may be related to the high
suspended solids.
6.2.2
Page 40
Interim Report
6.3
pH Correction
The seawater will be dosed with acid to achieve the optimum pH for coagulation.
The dosing system will consist of duty and standby dosing lances into each pretreatment train. The pH correction design parameters are summarised in
Table
9 below.
Table 9
Parameter
Units
Value
MLD
395
Dosing location
At
head
of
Common
Coagulation/Flocculation
Type of pH correction chemical
Sulphuric Acid
Target pH
6.80
Dose rate
Number of dosing pumps
6.4
mg/L
35 approx.
2 duty / 1 standby lances
Coagulation
Seawater turbidity is usually low around 0.5 to 1.0 NTU, however at the proposed
site is high. Turbidity normally indicates the presence of mineral particles which
can cause colloidal-particle fouling of RO membranes, thus reducing the flux rate
of the membranes. For this reason it is important to reduce the turbidity to an
acceptable level, i.e. to less than 0.5 NTU, perhaps as low as 0.1 NTU.
A widely used test is the Silt Density Index (SDI). The test is a laboratory filtration
test detailed in an ASTM standard.
produce filtered seawater with a Silt Density Index (15 minute test as per ASTM
D4189 95-2002) of less than 3.0 for 95%tile and less than 3.5 for 100%tile of the
time, under all operating conditions, to produce 150 MLD of permeate.
Interim Report
Thereafter the flocs are removed by processes such as floatation and filtration.
Coagulant will be dosed at the head of Lamella Settler block. Rapid mixing will be
implemented within a concrete structure with at least 30 seconds of detention time.
The coagulation and rapid mixing design parameters are summarised in Table 10
below.
Table 10: Coagulation and Rapid Mixing Design Parameters
6.5
Parameter
Units
Value
MLD
395
Type of coagulant
Ferric chloride
Mixer type
Flash mixer
s-1
600 minimum
Mixing time
30
Flocculation
Flocculation will be provided again at the head of each Lamella Settler.
Flocculation will be achieved in two flocculation tanks in series with each tank
consisting of one or two vertical mixers so as to have the mixing energy tapered.
Flocculent (flocculation aid) will be dosed at the entry to each flocculation tank.
Due to the warm temperature, 20 minutes of flocculation is proposed. The longer
flocculation time is proposed so as to compensate for the lower suspended solids
concentration expected as feed to RO. The flocculation and flocculent design
parameters are summarised in Table 11 below.
Table 11 Flocculation and Flocculation Aid Design Parameters
Parameter
Units
Value
MLD
395
polyelectrolyte
mg/L
0.1
mg/L
0.5
No.
min
20
Page 42
Interim Report
Type of mixers
6.6
s-1
70 100
s-1
30 - 50
Lamella Settlers
Lamella settlers consist of a series of inclined parallel plates or tubes through
which the water passes.
The
Units
Value
MLD
395
Page 43
Interim Report
No. of settlers
Nos.
8
Plates/Tubes made from FRP
with 550-600 inclination with
horizontal
Lamella
Surface
loading
rate m/hr
<15
Concrete
Chain and flight scrapers or
hydraulic vacuum; material of
construction to be suitable for
seawater
Concrete
troughs
with
portion of the clarified water is drawn off and passed through a pressure vessel
where the water is saturated with air at high pressure. The pressurized water,
supersaturated with air, is released into the water as it enters the bottom of the
basin. The sudden release of pressure causes the formation of micro-bubbles
which attach to the preformed floc and carry it to the surface where it forms a thick
floating layer. The float is skimmed off, and the clarified water passes to filtration.
DAF in general adequately removes TSS of 75 mg/L, but above 100 mg/L there is
likely to be a higher carryover of solids to the filters, resulting in shorter run times.
The potential for short filter runs can be offset to some extent by designing the
filtration system at an optimal flux. Therefore to mitigate the said situation; the
membrane filtration has been designed at an optimal flux of 50 LMH, while
producing the required SDI.
DAF would be effective in the removal of algae, and should be reasonably effective
in the removal of other marine biomass, such as larvae and jelly fish particulate
matter. DAF would be effective in the removal of oils and greases.
Ideally, loading rates for DAF would be set after pilot plant testing, and if time
Page 44
Interim Report
permits, pilot plant testing at site, should be carried out to provide data on the most
suitable loading rate.
DAF a form of physical treatment of water that involves coagulating impurities then
removing these solids by using dissolved air to float them to the surface of the
water. Residual fine particles that are not floated off are removed by the filtration
downstream.
The flotation cell also requires occasional sludge removal to remove settled solids.
The DAF process is proven across the globe for a range of water treatment
applications including as a pre-treatment process in sea water desalination plants
for removal of fine solids and organics. It also copes well with algae because it is
removed in the flotation step, eliminating the possibility of filter blinding. A
simplified cross sectional schematic is as shown below.
Raw
water
Flotation
Flocculation
Filtration
Air
saturated water
Sludge
Filtered water
Table 123
Parameter
Units
Value
MLD
MLD
No.
22
m/hr
8 (with recycle)
m/hr
m2
95
20
mg/L
10
rate
One unit offline
Page 45
Interim Report
Parameter
Units
Value
90
kPa
800 (nominal)
No.
22
Saturator volume
DAF recycle water will be drawn from the RO fed tank i.e. UF filtered water.
6.8
Ultrafiltration (UF)
Membrane filtration involves passing the water to be treated through a thin polymer
film called the membrane. The filtration process is loosely referred to as
microfiltration if the size of pores in the membrane is about 0.2 micron.
If the pores are smaller than approximately 0.1 micron the filtration process is
referred to as ultra filtration.
One of the key advantages of membrane filtration is that due to the small pore size
compared to media filtration, membrane filters usually require less coagulant to
achieve the required filtered water quality. Further since being a pressurized
membrane system the area required is generally 25-30% less than non-membrane
filtration.
The
pressure
arrangement
is
similar to an RO
plant
with
ultra-
filtration membranes
installed in pressure
vessels.
Feed
Page 46
Interim Report
possible in UF like RO. Pressure systems are typically supplied as modular skid
mounted systems with skids varying in size depending on the duty requirement.
Table 14
Flow to Self-
MLD
388
99.5%
MLD
386
92.5%
Flux
LMH
50
Total Number of
Nos.
32
Duty
Nos.
30
Standby
Nos.
Flow Rate to RO
MLD
356
m2
17.5 x 4.5 m
Initial TMP
Bar
0.5
Cleansing filters
Assumed recovery from filters
Flow inlet to UF
UF Recovery Rate
skids
6.9
Units
Value
MLD
388
Page 47
Interim Report
Number of tanks
No.
Fill time
min
20
Capacity
ML/tank
5.5
Page 48
Interim Report
7.
7.1
Overview of RO Plant
The RO plant will be a single stage/single pass design with an overall recovery of
46%.
The plant will be configured as six numbers of individual trains. Each of the six RO
trains will consist of one RO rack each, with dedicated pumping system and
Energy Recover Devices (ERDs).
production can be achieved through six trains. The trains will be configured to
allow for each individual train to be isolated for cleaning, maintenance, or
membrane replacement. However 2 sets of standby ERD, HPP and booster
pumps have been proposed.
SWRO membrane elements of 8-inch diameter have been selected.
Each
Page 49
Interim Report
Under such design the RO Booster pumps would provide feed pressure
adjustments suitable to cover the required membrane pressures for average to
maximum salinity events. For feed waters with below average salinities further
controls would be required in form of a HP throttling valve, essentially reducing
(burning-off) excess energy created by the pumping system upstream. It should
be noted that correct sizing of the RO pumping system is critical, as under-sizing
will not achieve the required permeate flows and over-sizing may require excess
pressure to be burnt-off at the throttling valve.
An alternate option would be equipping the HP pumps with a VSD, while the
booster pumping system would be equipped with a fixed speed drive, only
providing sufficient pressure to overcome friction and head-losses within the
cartridge system, as well as ensuring adequate NPSH is available. Reasoning
behind not further pursuing this alternate option was informed by the following
matters:
The cost of large high voltage variable speed drives for high wattage HP
pumps is significant
Inclusion of a variable speed drive would (permanently) reduce the energy
efficiency of the associated drive by 2% to 3%
Page 50
Interim Report
Cartridge Filtration
To protect the RO membranes, cartridge filtration will be provided for each RO train
downstream of the filtered water transfer pumps. The cartridge filters shall be of 5
microns.
7.4
Oxidant Control
The provision of sodium bisulphite (SBS) dosing is included in the design to
neutralize residual oxidants present in the feedwater due to intake shock dosing.
This will be controlled by measurement of oxidation reduction potential of the
SWRO feedwater. The details of the bisulphite dosing system are sated in
approaching sections.
7.5
Scale Control
Provision for scale control by means of antiscalant dosing is included in the design.
The sulphuric acid addition as part of the pre-treatment system will also assist with
prevention of scaling. Refer to chapter 9 for details of the antiscalant and acid
dosing systems.
7.6
Page 51
Interim Report
Unit
Pump
No.
L/s
295
346
ML/d
25.5
29.9
bar
14.5
6.0
Variable speed
Variable Speed
MLD module
Maximum flow capacity
(per train)
Delivery Pressure
(are dependent on final membrane and ERD
selection and performance)
Type of drive
Stainless
(Super duplex)
Pump impeller
Shaft
Stainless
steel Stainless
steel
(Super duplex)
steel Stainless
steel
(Super duplex)
(Super duplex)
Stainless steel
Stainless steel
Design parameters for the high pressure RO pumps are shown in Table above.
Since the High Pressure RO pump is a fixed speed pump it is important that the
pressure capability is not too high as that could lead to significant power wastage
with new membranes and warm/low salinity feed water.
Page 52
Interim Report
Table 16
Parameter
Unit
Value
No.
No.
ML/d
25.5
L/s
295
bar
55.3
Delivery Pressure*
Type of drive
Fixed speed
Stainless
steel
(Super
steel
(Super
duplex)
Pump impeller
Stainless
duplex)
Shaft
Stainless steel
Page 53
Interim Report
Parameter
Unit
Value
No.
No.
No.
No.
40
Type of system
Isobaric System
DWEER
Manufacturer of device
Calder AG
MLD
L/s
69
bar
62
~ 95+
Stainless
steel
(Super
duplex)
Piston
Other
parts
in
contact
with
Non Metallic
Stainless
seawater/concentrate
steel
(Super
duplex)
Unit
Value
No.
Page 54
Interim Report
No.
MLD
29.9
L/s
346
bar
5.7
Variable speed
Stainless
steel
(Super
steel
(Super
duplex)
Pump impeller
Stainless
duplex)
Shaft
7.7
Stainless steel
RO Rack Design
The membrane design parameters are shown in Table 19. Normal production will
be using 6 racks for 150 MLD module at a flux of approximately 13.5 LMH.
Table 19 RO Membrane Design Parameters
Parameter
Unit
Value
No.
No.
Page 55
Interim Report
Number of RO racks
No.
RO Plant Recovery
46
Material of membranes
Polyamide
Type of membrane/module
Membrane manufacturer
Hydranautics, Dow
m2
41 (440 ft2)
Normal
LMH
13.5
Maximum
LMH
15.5
Salt rejection
Nominal
> 99.8
Boron retention
Nominal
> 93
%/a
10
Flux Decline
%/a
3.5
No.
240
No.
No.
1920
1440
Average
Membrane
Life
(AMLT)
permeate
Total number of membranes for 150 MLD No.
11520
permeate
Reserve space provided for installation of %
Page 56
Interim Report
Table 20
Material
Stainless
steel,
super
super
7.8
steel,
steel,
pressure vessels
Product headers
Stainless steel
Product piping
Stainless steel
GRP
GRP
super
Caustic soda
Sodium Bisulphite
Hydrochloric Acid
Phosphoric Acid
Citric acid
Detergents (surfactant)
Ammonia solution
Cleaning occurs intermittently and all of these chemicals would not be used at the
Page 57
Interim Report
same time. The amount and type of cleaning chemical required would vary
depending upon the degree of membrane fouling and the nature of the fouling.
Depending on the membrane selected, the system may be designed to enable
cleaning of the RO system from both directions, i.e. from the front to the back and
from the back to the front. This would allow employing specific cleaning
procedures for a particular type of fouling / scaling. The CIP system will be sized
to clean each individual RO rack separately. The system, including the chemicals
for the CIP will be located in a dedicated building located next to the main RO
building.
All wastes from the CIP process will be neutralized prior to being directed to the
outfall and for the same a Neutralization Tank has been provided.
After chemical cleaning and prior shutdown of membrane trains, the brine and
spent cleaning solution will be flushed out of the RO and ERD racks using RO
permeate. Flushing prior train shutdown will reduce potential for scale build up
and corrosion, and will also reduce fouling and the amount of high TDS water
produced on start up. The flushing system would consist of flushing pumps and
pipework allowing each RO train to be flushed individually.
Design parameters of the chemical cleaning preparation tank are shown in Table
21.
Table 21 Chemical Cleaning Preparation Tank Design Parameters
Parameter
Unit
Value
Number of tanks
No.
300
Body / ends
GRP
Pipes / valves
GRP/PVC/SS
Material:
Form of construction
Circular
Design parameters for the chemical cleaning pumps are shown in Table 22.
Table 22 Chemical Cleaning Pumps Design Parameters
Page 58
Interim Report
Parameter
Unit
Value
Number of pumps
No.
2W+1S
L/s
300
Pumping head
bar
10
Number of stages
No.
Design parameters for the flushing pumps are shown in Table 23.
Table 23 Flushing Pumps Design Parameters
7.9
Parameter
Unit
Value
Number of pumps
No.
1W+1S
L/s
295
Pumping head
Number of stages
No.
Permeate Storage
One permeate storage tanks will be located immediately downstream of the RO
plant. The tanks have been sized for at least 20 min storage at the maximum
permeate flow of 153 MLD. The design parameters for the Permeate Storage Tank
are summarised in Table 24.
Table 24 Permeate Storage Design Parameters
Parameter
Units
Value
Number of tanks
No.
ML/tank
2.125
Page 59
Interim Report
Page 60
Interim Report
8.
POST TREATMENT
Post treatment of permeate is required to meet the statutory product water quality
requirements.
Re-mineralization/Stabilization
8.1.1
Item
Requirement
Stabilization Process
Target pH range
7.5 to 8.5
Positive
500 mg/L
Page 61
Interim Report
8.1.2
Left to Right: Lime Silo, Limewater Clarifier, Carbon Dioxide Storage Vessels
Carbon dioxide gas is added to the water. It reacts with the dosed lime to form
calcium bicarbonate, which buffers the water and increases the resistance to
changes in pH and thus reduces the corrosivity of the water. Carbon dioxide and
lime are currently in common use all parts of the world for treatment of drinking
water supplies for the said purpose. The Perth Seawater Desalination Plant (130
MLD) uses the said process for portabalization.
Equipment typically required for dosing of lime would consist of: lime storage silos,
mixing vats, limewater clarifier, lime-water storage tank and dosing pumps. Carbon
dioxide would be stored and dosed using a proprietary package plant consisting of
storage vessels, evaporators and dosing venturis.
The remineralization using lime and carbon dioxide follows the chemical reaction
presented below:
2CO2 + Ca (OH)2 Ca (HCO3)2
0.74 mg/L of hydrated lime (0.56 mg/L of quicklime) and 0.88 mg/L of carbon
dioxide would need to be added in order to increase desalinated water hardness
Page 62
Interim Report
each.
recommended dosage of alkalinity and hardness in the product water of 100 mg/L,
the water produced by the desalination system will need to be treated with 74 mg/L
of lime and 88 mg/L of carbon dioxide.
The lime product used for remineralisation is usually delivered and stored at the
desalination plant site in silos as either powdered hydrated lime or as
pebble-lime (CaO), which is than slaked to generate hydrated lime [Ca(OH)2].
This lime slurry is blended with the fresh water produced by the desalination
process and is thoroughly mixed in lime saturator tanks to create saturated
limewater, which is then injected into the unconditioned desalinated water.
Carbon dioxide is typically delivered to the desalination plant site in a liquefied
form and is stored under pressure in metal storage tanks.
The majority of desalination plants are designed to produce finished water of total
(calcium and magnesium) hardness of 80 to 120 mg/L as CaCO3. Since
desalinated water usually contains less than 2 mg/L of magnesium, over 90
precent of the total hardness of drinking water conditioned with lime is calcium
hardness.
8.1.3
Page 63
Interim Report
Component/Parameter
Specifications/Design Criteria
Carbon dioxide dosage (as 100% For lime/CO2 systems88 mg/L For
pure product)
of
alkalinity
and
100
tank
(refrigerated)
Storage pressure/ temperature, 20 bars/20C
bars/C
Diameter, m
Length/Height, m
Storage time, days
Structurematerial type
Vaporizer
Type
Capacity,
horsepower/kg
0.83.0
515
1560
Carbon steel
Electric
0.030.05
CO2.day
Delivery pressure/temperature, 3 bars/12C
bars/C
Vapor Heater
Type
Capacity,
Electric
horsepower/kg 0.010.02
CO2.day
Key design Criteria Carbon Dioxide and Feed System
The dosage of carbon dioxide fed to the desalinated water is adjusted
Page 64
Interim Report
proportionally to the desalinated water flow rate by flow control valves installed on
the gas feed lines from the vaporizer to the point of chlorine dioxide gas injection in
the desalinated water conveyance pipe.
8.2
Disinfection
Disinfection has been used for over a hundred years, when it was first regularly
used to kill germs in the 1900s. Chlorination was first used in London in 1905 and
ozone was first used in Nice in 1908. From there, disinfection developed further
and was widely accepted as a method to treat water. Chlorination is the most
widely used method with ozone slowly becoming more popular. Chlorine dioxide is
also another disinfectant in the water treatment industry, but because of its high
cost not used commonly. UV disinfection is a relatively new disinfection method
even though it was also discovered approximately at the same time as the other
techniques.
Requirement for Disinfection
Disinfection is the process whereby water is treated to kill microorganisms in the
water, including essentially all pathogenic (disease-causing) bacteria. In addition
disinfection is undertaken to prevent bio-film (slime) growth inside the pipes and
mitigate the risk of recontamination.
Chlorine based disinfection (i.e. chlorination) has been considered for said project.
This is because this process is by far the most common form of disinfection in the
country and has a shell life as compared to other disinfection process which
usually doesnt have the required shell life in distribution system.
Chlorine is the most widely used water disinfection method. Chlorine kills the
micro-organisms by immobilising their metabolism rendering them harmless.
Chlorine is a slow stable reaction thus its main advantage of chlorine is the
formation of residuals which remain in the water for longer periods of time
protecting the system from bacterial contamination.
Interim Report
No =
0.4343 K
Page 66
Interim Report
Rearranging the formula to determine the time required for the adequate disinfection is
expressed as:
t = (1/k) log(No/ Nt)
Since the number of micro-organisms can never be zero no matter how much
disinfected the water is, the percentage of removing micro-organisms can never be 100%.
However, majority of the water treatment plants must be able to remove or inactivate
99.9% (3-log) of Giardia cysts and 99.99% (4-log) of viruses (Critttenden et al., 2005).
Some micro-organisms are more vulnerable and have less resistance to certain
disinfectants therefore only 90% (1-log) reduction is required.
For effective disinfection there are numerous parameters that are required for killing
or inactivating micro-organisms. This includes the residual concentration, the time at
which the water is in contact with the disinfectant, the water temperature, the pH balance,
and the type of disinfection used.
If the concentration of disinfectant, C, measured in milligrams per litre (mg/l), and
the contact time, T, measured in minutes, are multiplied together it will produce a
value known as the CT value. This value is required to produce adequate parameters in
order to achieve the required log requirements. Different micro-organisms will require
different CT values therefore, in general, the contact time and the concentration of the
disinfectant must be able to remove the most resistant of the micro-organisms. It is
important for the water system to have an adequate CT value so that the water is treated
properly before being distributed.
In alkaline conditions, chlorine is more
effective and in acid conditions, the
hypochlorous acid is more effective.
Therefore it is recommended that the
typical pH for disinfection should be
lessmthan 8 and if chlorine is used,
then a lower pH is better.
Chloramine, which can be formed
during
chlorine
and
ammonia
Interim Report
Interim Report
Greenish Yellow
Physical state
27.48 mm Hg at 20oC
-101C
2.49
1.47 at 20oC
Solubility in water
0.7 % at 20oC
Odour
Others
Soluble in alkalis
Specifications
Chlorine Content Min.V/V
99.8%
Moisture
Residue on Evaporation
Interim Report
780
930
9.
19.9
760
Shell Thickness, mm
10
9.6 (Min.)
2085
620
Valve Outlet
5/8
Thread
14 tpi bsp
CHEMICAL SYSTEMS
The following chemicals will be required as part of the pre- treatment process:
Table 28 Desalination Plant Chemicals List
Chemical Name
Chemical Use
Antiscalant
RO scale prevention
Carbon Dioxide
Interim Report
Chlorine Gas
Post
treatment
for
disinfection
Coagulant
Hydrated Lime
RO CIP
Clarification/Filtration
Aid
Polyelectrolyte
Sodium Hydroxide
(Caustic Soda)
Sodium Hypochlorite
(prepared
solution
Shock dosing for intake biofilm control
from
Sodium chlorine/hydroxide)
Metabisulphite
Sulphuric Acid
RO CIP
pH adjustment and scale control
RO CIP only
Miscellaneous Chemicals
(eg: Biocide, Detergent, Ammonia, Acids: Hydrochloric, Phosphoric, etc)
9.1
Antiscalant
Antiscalant is required to be dosed into the reverse osmosis system to manage the
formation of mineral scale on the surface of the membranes. Design parameters of
the antiscalant system are shown in Table below.
Table 29 Antiscalant System Design Parameters
Parameter
Units
Value
ML/d
356
Interim Report
flow rate
Antiscalant concentration
Form of supply
100
1000 L IBC
Dose rate
mg/L
Dosing point
0.7
RO
High
Pressure
kg/day
250
1.2
solution
Dosing
flow
rate
of
L/hr
Duty
No.
Standby
No.
L/hr
No.
None
antiscalant
Number of dosing pumps
direct
feed
from IBC
It is not proposed to dilute the antiscalant as the flow rates involved can be easily
dosed accurately and dilution can lead to degradation of the antiscalant. Adequate
mixing will be achieved by other means. At this stage the type of antiscalant to be
used has not been determined. This will be assessed at the next design stage.
9.2
Carbon Dioxide
Carbon Dioxide is required to be dosed in association with Hydrated Lime for pH
control and stabilisation of the permeate water. The chemical dosing design
parameters are summarised in Table 30.
Table 30 Carbon Dioxide Dosing Design Parameters
Carbon Dioxide Dosing
Units
Value
Interim Report
mg/L
90
Average
mg/L
70.4
Average
kg/hr
575
Number Of
No.
Capacity
tonnes
25
days
Carbon
Dioxide
Storage
Period
9.3
Chlorine Gas
Chlorine is required for disinfection of the product water and for shock chlorination
Chlorine will be supplied as liquefied gas in 900 kg drums. The unloading of
chlorine drums from transport trucks will occur within the chlorine building, thereby
reducing the risk of a chlorine leak occurring outside the building. The system will
be configured as a vacuum gas draw system with vacuum valves connected
directly to the chlorine drums.
Design parameters for the proposed chlorination system are summarised in 31.
Table 31 Chlorination Design Parameters
Parameter
Units
Value
Minimum
mg/L
Maximum
mg/L
Nominal
ML/d
153
Nominal
kg/hr
12.75
Maximum
kg/hr
19.125
Maximum
kg/day
459
Average
kg/day
306
Chlorine Consumption
Chlorine Storage
Interim Report
Maximum
kg/day
459
kg
900
No.
days
15
On Site
Drum Storage Period
9.4
average
Ferric Chloride
Ferric Chloride is to be dosed to coagulate particles prior to the DAF. The design
parameters are summarised in Table 32.
Table 32 Ferric Chloride System Design Parameters
Parameter
Units
Value
ML/d
395
% w/w
42.6
Specific
gravity
of
dosing
1.45
Solution
Dose rate
9.5
Typical
mg/L
16
Maximum
Mg/l
25
Typical
t/day
15.0
Flash Mixers U/S of
DAF
Hydrated Lime
Lime will be supplied to site as hydrated lime (Ca(OH)2) and converted onsite to
Interim Report
lime water before dosing to permeate upstream of product water. Lime does not
dissolve quickly in water and is difficult to handle. Lime is mixed with water to
obtain lime water, and then the lime water is passed through a clarifier to remove
the un-dissolved lime; if not removed the product water will not meet specification.
Equipment for handling lime requires regular maintenance, and adequate standby
provisions must be made. Two lime water clarifiers will be provided. Lime is not
pure and significant amounts of sludge are produced and must be dewatered and
removed from site. The commercial lime available has a purity of 80% or less; a
purity of 75% has been adopted for design.
The lime dosing design parameters are summarised in Table 33.
Table 33
Parameters
Lime Properties
Units
Value
75
Utilisation of pure %
90
Purity
component
Lime Consumption
Lime Silos
Utilisation overall
67.5%
Typical
mg/L
50 as Ca(OH)2
Maximum
mg/L
75 as Ca(OH)2
Average
tonnes/day
11.35 t/day
Maximum
tonnes/day
17 t/day
Number
No.
Capacity
of
each tonnes
50
silo
Lime
of
Milk
Concentration
9.6
Interim Report
flocculation tank. The specific polymer to be used will be determined during a later
design stage. The dosing design parameters are summarised in table 34
Table 34
Parameters
Units
Value
ML/d
395
% w/v
0.1 0.5
Nominal
Dosing Location
U/s of Lamella
U/s of DAF
mg/L
0.05
Maximum
mg/L
0.25
Average
mg/L
0.1
point)
9.7
Sodium Hydroxide
Sodium hydroxide is required to neutralize acids used in the cleaning of the UF
membranes and may also be used for cleaning of the RO membranes. Sodium
hydroxide may also be required to increase the pH of the RO feed water in order to
meet boron target levels.
Units
Value
Hydroxide concentration
% w/w
50
1.53
Interim Report
9.8
No. of Tanks
No
Tank Volume
KL/tank
150
Dosage location
Dosage
25 m/l average
Sodium (Meta)bisulphite
Sodium bisulphite (SBS) (NaHSO3) will be prepared by dissolving sodium
metabisulphite (SMBS) (Na2S2O5) in water. Dosing of bisulphite is required to
remove residual chlorine from the system resulting from intake shock dosing as
well as to neutralise oxidants used for cleaning of the UF membranes. Bisulphite
may also be used for the RO CIP process.
The redox potential (ORP) will be measured downstream of the dosing point to
ensure that the dosing is effective. The sodium bisulphite design parameters are
summarised in Table 36.
Ventilation shall be provided to manage any fumes that may be evolved in the
chemical area.
Table 36 : Sodium (Meta)bisulphite System Design Parameters
Parameter
Units
Value
% w/v
40
1.34
ML/d
395
Maximum
mg/L
30
Typical
mg/L
15
Dosing point
Interim Report
9.9
No of Dosing pump
9 W+4 S
125 L/hr
Sulphuric Acid
The sulphuric acid will be used to provide pH correction for optimum seawater
coagulation. In addition sulphuric acid is required for chemical enhanced
backwashing and cleaning of the UF membranes. The design parameters are
summarised in Table 37.
Table 37
Parameter
Value
gravity
of
% w/w
dosing
98
1.84
solution
Seawater pH Correction
Design seawater flow
395
Dose rate
Typical
35
Typical
350 L/hr.
Dosing point
Seawater
intake
pipeline
Interim Report
9.10
Table 38
Parameter
Oxidant
Value
backwash
with
Once a day
NaOCl (10%)
Number of tanks
One
Volume
Acid
M3 300
backwash
with
HCL
(35%)
Number of tanks
Volume
9.11
One
m3
Proposed Acid
HCl
Proposed Alkali
NaOH
Proposed Oxidant
NaOCl
Dosing Frequency
Once in 60 days
5 m3
Miscellaneous Chemicals
This section covers miscellaneous chemicals used only for the purpose of cleaning
the RO membranes (i.e. RO CIP). Examples of these chemicals include (but may
not be limited to):
Biocide;
Detergent;
Interim Report
General storage space only has been included for these chemicals because:
It will not be known until the first year (or two) of operation which of the
chemicals are required;
The chemicals are used infrequently (say once per year); and
The facility will be designed to meet the requirements of all of the chemicals that
may be used. Between uses, the facility will need to be drained and flushed.
Design details are provided in the following table.
Table 39 Miscellaneous CIP Chemical Dosing System Design Parameters
Parameter
Units
Value
Dosing point
RO CIP Tank
varies
Duty
No.
Standby
No.
kL/hr
Number of tanks
No.
Tank volume
kL/tank
9.11.1
Cleaning-in-place (CIP)
To manage membrane fouling and scaling, periodical cleaning is required.
Depending on the performance of the pre-treatment system and on the actual
operational envelope, it is anticipated that four cleanings per year per train are
necessary. Typical cleaning solutions include low pH, and high pH solutions and
special detergents. Preservation solution would also be prepared within the CIP
system.
Interim Report
features:
Make-up tank;
Chemical storage and dosing facilities for the preparation of various cleaning
solutions (typically includes Caustic Soda, Citric Acid, NaDDS, Sodium
Bisulphite);
Recycling pumps;
9.11.2
Flushing
After chemical cleaning and prior shutdown of membrane trains the brine and
spent cleaning solution should be flushed out of the RO and ERD racks using RO
permeate. Flushing prior train shutdown will reduce potential for scale build up and
corrosion.
The flushing system would consist of flushing pumps and pipework allowing each
RO train to be flushed individually.
Interim Report
10.2
Number of units : 1 x 6.25ML (1 hours storage for 150 MLD average flow),
Covered
11.
SEAWATER OUTFALL
11.1
Outfall Pipeline
The desalination plant will discharge rejected seawater concentrate and other
waste streams into the ocean via an outlet pipeline.
The criteria adopted for Section 1 of the outlet pipeline are as follows;
Interim Report
Note *
The head required to discharge seawater concentrate is provided by the residual seawater
concentrate pressure after the reverse osmosis process. This pressure would otherwise be fully
recovered and therefore has to be supplemented to make up for the loss of head to the outlet
pipeline. The outfall pipeline can therefore be considered as consuming energy (as with a pump
station) with an associated operating cost.
11.2
Diffusers
The outlet pipeline will discharge seawater concentrate and other waste flows into
the ocean via a system of diffusers. These comprise a large number of small
diameter nozzles discharging jets of seawater concentrate from the seabed into
the water body to entrain dilution flows. Wider dispersion of the saline plume is
achieved through the action of wind, waves and currents. Both the seawater
concentrate jets and the dispersion will be modelled using appropriate computer
models. The adopted criteria for the diffuser design is summarised as follows;
Discharge
salinity
range:
32,500mg/l
-34,500mg/l
above
ambient,
Power supply
Interim Report
12.1.1
Background
The power supply arrangement for the desalination plant is based on provision of
one nos (1 no.) 110 kV feeders from a substation next (very adjacent) to the
existing Neemlai SWRO to be procured and operated by TNEB.
The major areas for power demand are the seawater supply pumps, the RO
treatment plant and the process water transfer pump station.
The substation for the proposed plant has been placed on the north end of the site
along the ECR front, since the area embarked for the plant doesnt have sufficient
space to accommodate the electrical sub-station.
12.1.2
Design Considerations
It is anticipated that the concept design and cost estimate of the HV infrastructure
and electrical plant will include and take into consideration the following:
System security;
System reliability;
Determination of appropriate voltages and load currents for the main pump
motors and other large motors as appropriate;
Redundancy requirements;
Energy losses;
Environmental impacts;
Lifecycle costs.
A level of security and redundancy will be determined for the reference design.
The appropriate Indian Standards will form the basis for the design of electrical
works including standards for:
Interim Report
Earthing
Protection
Switchgear, etc.
12.1.4
Interim Report
12.1.6
Electrical Equipment
Electrical equipment design will be in compliance with IEC Standards.
The electrical cable trays shall be GRP.
Cables of different voltages will generally be laid on separate trays. Where this is
not possible, cables may be installed on the same trays with suitable barriers.
The transmission cables of analogical signals will be laid on trays different than the
power cables to avoid any electromagnetic interference.
Where there is a possibility of mechanical damage or fire hazard, cable trays will be
protected by sheet steel covers. The cable inlet to the equipment will be protected
with tight stuffing boxes IP-65, which guarantees a perfect tightness.
12.2
12.2.1
Control System
General Design Criteria
The control system for the desalination plant will be compatible with the overall
Interim Report
control system and the design will take into account the following requirements:
The Process Control System (PCS) architecture covering the connection of field
instruments, controllers and associated input/output (I/O), Human Machine
Interfaces (HMI), communication networks and network equipment will be
designed for a process plant availability of at least 98%. This implies that that
the control system itself will have a system availability of at least 99.9%;
Fibre optic will be provided as the primary bearer to link all units.
I/O & instrument voltages selected to suit equipment and provided with battery
backup.
All on site power, control and communication cables to be run in accordance with
current industry practices, codes, standards and regulations;
Field instrumentation will be rated IP56 and will have outdoor housing protection
from weather.
12.2.2
the
control
communications.
system,
alarm
system,
supervisory
system
and
system
Interim Report
All plant operations will be designed for automatic operation and minimal
requirement for manual intervention;
The desalination plant and process water pump station will be monitored 24
hours per day;
Outside of the manned hours of the desalination plant and pump station,
operations or maintenance will only be in response to automated alarm
notification to nominated personnel on call;
For backup to the automated alarm notification outside of manned hours, the site
will also have 24 hour monitoring of all operating parameters and alarms;
Operating protocols will be established such that only the desalination plant will
have control ownership of the complete water supply system.
12.2.3
The desalination plant will be controlled by its own stand alone control system.
This will include all equipment, cabling, buildings and services necessary for a
complete system;
The Process Control System (PCS) will be of the same manufacturer, make,
model, firmware as that used for the magnetite process plant and will follow the
same configuration/ programming criteria and standards;
The HMI interface system on site will be suitable for the application, control
system requirements in terms of functionality, speed, durability, local support;
All HMI systems will display alarms, alarm histories and trends. All data must be
stored for more than twelve months;
All PCS and communication systems will have at least 20% spare memory, I/O
and communication capacity;
Each controllable drive will have a local control station comprising an emergency
Interim Report
stop (hard wired in the emergency stop circuitry for the drive which is not
disabled in auto mode), a local stop button and a local start button (for starting
the motor under maintenance /manual mode of operation). This local control
station will include a jog button when appropriate for some mechanical
equipment;
The PCS will incorporate monitoring of key alarms for other plant auxiliaries such
as the main low voltage electrical reticulation, building services and fire
suppression system.
Interim Report
Plant Buildings
13.1.1
General
The desalination plant will include the following buildings:
Chlorine Building;
Buildings will generally be of concrete foundation slabs, sheet metal clad, insulated
and suitable for cyclonic conditions with a design life of 30 years. Buildings shall
comply with the relevant Indian Building Code.
Interim Report
Equipment buildings will be provided with appropriate doors to suit the operation of
the plant including removal and replacement of all equipment. Some buildings will
be provided with precast concrete walls to reduce noise levels and provide heat
insulation.
13.1.2
wherever possible.
13.1.3
Lifting Devices
Lifting devices will be included in the design where necessary. These will include
electrically operated Cranes (EOTs) for removal of pumps and air blowers etc.
Gantry cranes will be provided RO buildings and the Chlorine building. Mobile
cranes will be required to move pumping and other equipment to a suitable truck
loading area.
13.2
Road works
The desalination plant area will be designed as a large, evenly graded area with
provision for adequate access to the plant such that vehicles will not need to cross
open drains. Grading around the plant will be arranged to ensure drainage away
from the plant at an appropriate grade to minimise the potential for ponding or
flooding.
Working areas around the desalination plant will be surfaced in a road base or
appropriate capping layer to provide all-weather hard standing areas for
maintenance traffic. Areas of significant traffic, such as around workshops and
offices and roads between facilities plus roads surrounding and internal to the
process plant shall be bitumen sealed. Any areas that are sensitive to vehicle
impact, in particular building edges, workshop door openings etc, exposed items
such as fire hydrants and other vulnerable infrastructure, shall be protected by 150
mm diameter steel bollards painted or marked (in reflective material) and, filled
with concrete or by roadside type guardrail.
Interim Report
All underground electrical cable in ducts /conduit will have concrete cable pits at
changes of direction. These pits will be provided with removable concrete covers at
plate level capable of taking the load from the outrigger of a 50 t rough terrain
crane. The covers will be levelled to the fished road level.
All Internal roads shall have a minimum carriage width of 6.0 m. Roads will be
wider in areas adjacent to chemical storage facilities to allow a chemical truck to be
unloading without restricting through traffic. Road widening will also be required at
bends to provide sufficient room for turning of a trailer. Road cross fall shall
generally be designed at 2% for sealed pavements and 5% for unsealed with
vertical and horizontal alignment to be designed in accordance with MORTH
publications.
13.3
Site Services
All electrical and communication services will be located in suitable underground.
Site pipework will be buried where feasible.
13.4
13.5
Fire Systems
Fire services will be compatible with the requirements of Health, Safety and
Environment and relevant standards.
Interim Report
main
is
normally
consumption
are
then
Interim Report
maintained in the pipe. Hence, for closed conduits the hydraulic grade line slopes
according to the head loss.
Therefore, pipe sizing is based upon taking consideration of following factors:
Interim Report
overcome the increase in head losses, and the other way round. As a result, one
pipe diameter will represent the least cost choice taking into account the initial
costs (capital investment), maintenance costs and the energy costs for pumping.
The total cost, i.e. the capitalized taking both capital and operational cost as the
least and economical, shall be the basis for selecting the most economical pipe
diameter. Therefore, pipe sizing is based upon engineering standards for
acceptable energy (i.e. friction loss = loss of pressure) loss related to the intended
use of the pipe transmission main.
For this analysis, the
calculated costs for
different pipe sizes
shall be are plotted
as in a graph shown
as side. Therefore,
when the capital cost
and
the
operation
Carbon Steel
Interim Report
Based on historical performance, life expectancy and durability, the use of cement
lined and bitumen lined, and coated DIP and fittings will provide an excellent
conveyance mechanism for all segments of the proposed transmission main for the
portions considered for open cut construction.
In selecting the most appropriate pipe material for the said scheme/project the
following consideration shall be made:
o
o
o
The ground conditions along the pipeline route, mainly conditions such as
traffic overload, proximity to sewer lines, and crowded residential areas.
The cost and local availability of different types of pipe
Durability,
Resistance to Chemical Attack,
Corrosion and Abrasion. (Suitable external and internal coating shall be made and
if required cathodic protection).
The above aspects are considered in conjunction with the cost of procurement and
installation to provide the most economical solution.
Ductile iron and steel are the strongest pipe materials, making them the best
choice when very high operating pressures are to be expected. These pipes are
almost impossible to tap without special tools and equipment, which is an
advantage in cases where illegal connections pose a real threat for the urban local
body. However, the costs of fittings, valves, etc. increase rapidly for higher pipe
pressure classes and it is therefore often advisable to reduce the maximum internal
pipe pressure through the provision of a pressure reducing valve or break-pressure
tank/ intermediate pumping. A break-pressure tank is generally more reliable than a
pressure reducing valve.
In spite of higher investment costs, ductile iron pipes are a better alternative than
cast iron pipes because they have a longer service life, are lighter and more
flexible and require hardly any maintenance. The pipe is practically corrosion
Interim Report
resistant due to coatings applied inside and outside. Moreover, this pipe material
may be subject to scale bursts when tapped without sufficient skill. Alternative
materials are in this case High-density polyethylene (PE).
High-density polyethylene (PE) is a very suitable pipe material for small-diameter
mains because it can be supplied in coil. The potential of laying this pipe in longer
lengths reduces the number of necessary joints. Particularly in cases where rigid
pipe materials would necessitate a considerable number of special parts such as
elbows and bends, the flexible PE makes for an ideal pipe material. Polyethylene
does not deteriorate when exposed to direct sunlight. Conventional jointing of the
PE-pipes may cause leakage and welding is considered to be a better alternative.
However PE pipes greater than 1600 mm diameter are not commercial available in
the local market, hence is a big constraint in selecting the said pipe material for
commercial use when the diameter requirement is above 1600mm OD.
To summarize, for pipelines of small-diameter (less than 300 mm) PE may
generally be the best alternative unless high working pressures are expected
(above 60 mwc). These pipes can also be used for medium- to large-sized
pipelines (diameters up to 500-600 mm) where lower pressures can be maintained.
However, Cast iron, Ductile iron and Carbon steel are generally only used for largediameter mains and also in cases where very high pressures necessitate their use
in small- or mid-range diameter pipes. Due to heavy weight and lower flexibility, CI
pipes are becoming less advantageous than DI, despite lower prices. Moreover CI
pipes are brittle as compared to DI pipes. Stringent measures that have to be
introduced while handling these pipes involve the prevention of the production and
inhalation of fibre dust (use of special saws cutting under wet conditions, protection
masks for the workers, etc).
Since DI pipe above 1.1m dia are not available commercially, hence all pipes
above 1.1m dia shall be Carbon Steel as per IS 3589 with internal Cement
Concrete Lining (CC) lining in accordance with Is11906 or ISO 4179 and outside
fusion bonded epoxy coating for prevention for corrosion and all pipes below or
Interim Report
equal to 1.1 m shall be DI with internal CC lining and outside fusion bonded epoxy
coating as per IS 8329.
The water pumped from the proposed facility shall be conveyed to existing or new
ground storage tanks for further distribution in the city. This shall be confirmed in
the interim stage, when all surveys are in place.
Water:
Product water
Interim Report
14.1
Annexure
14.1.1
Capacity
LENGTH
C
TOTAL STATIC HEAD (H)
PIPE MATERIAL (MS)
DESIGN VELOCITY
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
60000
0.8
6
IS 2062
UNIT
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
M/S
550.00
MLD
6.37
M/S
M
M
CALCULATED DIA
( M)
SELECTED
DIA ( M)
ACTUAL
VELOCITY
(M/S)
(Q/C)^1.81
2.846947987
2.714458399
2.598896054
2.496938563
2.406110204
2.324523298
2.250710005
2.183509431
2.121989743
2.06539315
2.013096227
1.964580755
1.919411941
1.877221912
1.837697024
2.9
2.8
2.6
2.5
2.5
2.4
2.3
2.2
2.2
2.1
2.1
2
2
1.9
1.9
0.96
1.03
1.20
1.30
1.30
1.41
1.53
1.67
1.67
1.84
1.84
2.03
2.03
2.25
2.25
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
42.69
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
994.62
D^4.81
167.5461
141.524
99.08817
82.05243
82.05243
67.42424
54.94281
44.36629
44.36629
35.47111
35.47111
28.05138
28.05138
21.9182
21.9182
STATIC
HEAD
(H)
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
15.37
18.20
25.99
31.39
31.39
38.20
46.88
58.05
58.05
72.61
72.61
91.81
91.81
117.51
117.51
REQUIRED PUMP
HEAD INCLUDING
MINOR LOSS (10 %)
IN 'M'
SELECTED
PUMP HEAD (M)
22.91
26.02
34.59
40.53
40.53
48.02
57.56
69.86
69.86
85.87
85.87
107.00
107.00
135.26
135.26
23.00
27.00
35.00
41.00
41.00
49.00
58.00
70.00
70.00
86.00
86.00
107.00
107.00
136.00
136.00
Page 99
HEAD IN
Kg/Cm
2.346
2.754
3.57
4.182
4.182
4.998
5.916
7.14
7.14
8.772
8.772
10.914
10.914
13.872
13.872
Interim Report
S.No.
A
Particulars
Formula/Symbol
Unit
option-i
option- ii
optioniii
optioniv
option-v
optionvi
option-vii
optionviii
optionix
option-x
option-xi
optionxii
optionxiii
optionxiv
optionxv
A.1
Selected pipe ID
ID
mm
2900
2800
2600
2500
2500
2400
2300
2200
2200
2100
2100
2000
2000
1900
1900
A.2
Pipe OD
OD
mm
2940
2840
2634.4
2534.4
2534.4
2434.4
2332
2232
2232
2132
2132
2032
2032
1928.4
1928.4
A.3
Design Pressure
Dp
kg/sqcm
2.346
2.754
3.57
4.182
4.182
4.998
5.916
7.14
7.14
8.772
8.772
10.914
10.914
13.872
13.872
A.4
Design
Temperature
Td
deg.C
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
A.5
Allowable stress
Sa
kg/sqcm
(g)
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
A.6
Corrosion
allowance for
carbon steel
cm
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
A.7
Weld joint
efficiency for
ERW pipes
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
A.8
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
A.9
Minimum
calculated pipe
thickness
Tc = ((Dp x OD x
0.1)/(2 x (y x Dp +
Sa x J)) + C) x 10
mm
8.19
7.96
7.50
7.28
7.28
7.05
6.82
6.59
6.59
6.37
6.37
6.14
6.14
5.90
5.90
A.10
Mill negative
tolerance for pipe
thickness
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
A.11
Minimum required
wall thickness
(after considering
mill tolerance)
T* = Tc / ( 1 (M/100))
mm
9.36
9.10
8.57
8.31
8.31
8.06
7.79
7.53
7.53
7.28
7.28
7.02
7.02
6.75
6.75
A.12
Selected
thickness of pipe
(based on internal
load thickness
calculation)
Ts
mm
20
20
17.2
17.2
17.2
17.2
16
16
16
16
16
16
16
14.2
14.2
Page 100
Interim Report
Page 101
Interim Report
14.1.2
Capacity
LENGTH
C
TOTAL STATIC HEAD (H)
PIPE MATERIAL (MS)
60000
0.8
6
IS 2062
275.00
3.18
MLD
M/S
M
M
NOTE
1
SELECTED
DIA ( M)
ACTUAL
VELOCITY
(M/S)
(Q/C)^1.81
994.62
D^4.81
STATIC
HEAD (H)
TWO PIPES EACH ACCOMODATING 275 MLD , THE ENTIRE SYSTEM (2 x 275 MLD ) COMPRISING
PUMPS. REFER SCHEMATIC DIAGRAM PROVIDED IN THE SHEET.
4W + 2S
REQUIRED PUMP
HEAD INCLUDING
MINOR LOSS (10 %)
IN 'M'
SELECTED
PUMP
HEAD (M)
HEAD
IN
Kg/Cm
DESIGN VELOCITY
UNIT
CALCULATED
DIA ( M)
M/S
2.013096227
2.1
0.92
12.18
994.62
35.47111
20.71
28.78
29.00
2.958
1.1
M/S
1.919411941
1.01
12.18
994.62 28.05138
26.18
34.80
35.00
3.57
1.2
M/S
1.837697024
1.9
1.12
12.18
994.62
21.9182
33.51
42.86
43.00
4.386
1.3
M/S
1.76560219
1.8
1.25
12.18
994.62 16.89899
43.47
53.81
54.00
5.508
1.4
M/S
1.701376842
1.8
1.25
12.18
994.62 16.89899
43.47
53.81
54.00
5.508
1.5
M/S
1.643686187
1.7
1.40
12.18
994.62 12.83687
57.22
68.94
69.00
7.038
1.6
M/S
1.591492307
1.6
1.58
12.18
994.62 9.589967
76.59
90.25
91.00
9.282
1.7
M/S
1.543974326
1.6
1.58
12.18
994.62 9.589967
76.59
90.25
91.00
9.282
1.8
M/S
1.500473337
1.6
1.58
12.18
994.62 9.589967
76.59
90.25
91.00
9.282
1.9
M/S
1.460453502
1.5
1.80
12.18
994.62 7.030706
104.47
120.92
121.00
12.342
M/S
1.423473994
1.5
1.80
12.18
994.62 7.030706
104.47
120.92
121.00
12.342
2.1
M/S
1.389168374
1.4
2.07
12.18
994.62 5.045171
145.59
166.15
167.00
17.034
2.2
M/S
1.3572292
1.4
2.07
12.18
994.62 5.045171
145.59
166.15
167.00
17.034
2.3
M/S
1.327396343
1.4
2.07
12.18
994.62 5.045171
145.59
166.15
167.00
17.034
2.4
M/S
1.299448027
1.3
2.40
12.18
994.62 3.532381
207.94
234.73
235.00
23.97
Page 102
Interim Report
S.No.
A
Particulars
Formula/Symbol
Unit
option-i
option- ii
optioniii
optioniv
option-v
optionvi
optionvii
optionviii
optionix
optionx
optionxi
optionxii
optionxiii
optionxiv
optionxv
A.1
Selected pipe ID
ID
mm
2100
2000
1900
1800
1800
1700
1600
1600
1600
1500
1500
1400
1400
1400
1300
A.2
Pipe OD
OD
mm
2140
2040
1934.4
1834.4
1834.4
1734.4
1632
1632
1632
1532
1532
1432
1432
1428.4
1328.4
A.3
Design Pressure
Dp
kg/sqcm
2.958
3.57
4.386
5.508
5.508
7.038
9.282
9.282
9.282
12.342
12.342
17.034
17.034
17.034
23.97
A.4
Design
Temperature
Td
deg.C
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
A.5
Allowable stress
Sa
kg/sqcm
(g)
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
cm
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
A.6
A.7
Corrosion
allowance for
carbon steel
Weld joint
efficiency for
ERW pipes
A.8
A.9
Minimum
calculated pipe
thickness
Tc = ((Dp x OD x
0.1)/(2 x (y x Dp
+ Sa x J)) + C) x
10
mm
6.39
6.17
5.93
5.71
5.71
5.48
5.25
5.25
5.25
5.02
5.02
4.79
4.79
4.78
4.55
A.10
Mill negative
tolerance for
pipe thickness
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
T* = Tc / ( 1 (M/100))
mm
7.31
7.05
6.78
6.52
6.52
6.26
6.00
6.00
6.00
5.74
5.74
5.48
5.48
5.47
5.20
Ts
mm
20
20
17.2
17.2
17.2
17.2
16
16
16
16
16
16
16
14.2
14.2
A.11
A.12
Minimum
required wall
thickness (after
considering mill
tolerance)
Selected
thickness of
pipe (based on
internal load
thickness
calculation)
Page 103
Interim Report
14.1.3
Page 104
Interim Report
Capacity
LENGTH
C
TOTAL STATIC HEAD
(H)
PIPE MATERIAL
(MS)
60000
0.8
M
-
400.00
4.63
MLD
M/S
IS 2062
(Q/C)^1.81
994.62
D^4.81
STATIC
HEAD
(H)
REQUIRED
PUMP HEAD
INCLUDING
MINOR LOSS
(10 %) IN 'M'
SELECTED
PUMP
HEAD (M)
DESIGN VELOCITY
UNIT
CALCULATED DIA
( M)
SELECTED
DIA ( M)
ACTUAL
VELOCITY
(M/S)
M/S
2.427885401
2.5
0.94
23.99
994.62
82.052429
17.64
25.40
26.00
2.652
1.1
M/S
2.314897901
2.4
1.02
23.99
994.62
67.424242
21.46
29.61
30.00
3.06
1.2
M/S
2.216346002
2.3
1.11
23.99
994.62
54.942813
26.34
34.97
35.00
3.57
1.3
M/S
2.129396361
2.2
1.22
23.99
994.62
44.366288
32.62
41.88
42.00
4.284
1.4
M/S
2.051937677
2.1
1.34
23.99
994.62
35.471112
40.80
50.88
51.00
5.202
1.5
M/S
1.982360129
1.47
23.99
994.62
28.051383
51.59
62.75
63.00
6.426
1.6
M/S
1.919411941
1.47
23.99
994.62
28.051383
51.59
62.75
63.00
6.426
1.7
M/S
1.8621031
1.9
1.63
23.99
994.62
21.918197
66.03
78.63
79.00
8.058
1.8
M/S
1.809638933
1.9
1.63
23.99
994.62
21.918197
66.03
78.63
79.00
8.058
1.9
M/S
1.761373197
1.8
1.82
23.99
994.62
16.89899
85.64
100.20
101.00
10.302
M/S
1.716774231
1.8
1.82
23.99
994.62
16.89899
85.64
100.20
101.00
10.302
2.1
M/S
1.675400097
1.7
2.04
23.99
994.62
12.836875
112.74
130.01
131.00
13.362
2.2
M/S
1.636880004
1.7
2.04
23.99
994.62
12.836875
112.74
130.01
131.00
13.362
2.3
M/S
1.600900225
1.7
2.04
23.99
994.62
12.836875
112.74
130.01
131.00
13.362
2.4
M/S
1.567193288
1.6
2.30
23.99
994.62
9.5899671
150.91
172.00
173.00
17.646
HEAD IN
Kg/Cm
Page 105
Interim Report
S.No.
A
Particulars
Formula/Symbol
Unit
option-i
option- ii
optioniii
optioniv
option-v
optionvi
option-vii
optionviii
optionix
option-x
option-xi
option-xii
optionxiii
optionxiv
option-xv
A.1
Selected pipe ID
ID
mm
2500
2400
2300
2200
2100
2000
2000
1900
1900
1800
1800
1700
1700
1700
1600
A.2
Pipe OD
OD
mm
2534.4
2434.4
2334.4
2232
2132
2032
2032
1932
1932
1832
1832
1728.4
1728.4
1728.4
1628.4
A.3
Design Pressure
Dp
kg/sqcm
2.652
3.06
3.57
4.284
5.202
6.426
6.426
8.058
8.058
10.302
10.302
13.362
13.362
13.362
17.646
A.4
Design
Temperature
Td
deg.C
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
A.5
Allowable stress
Sa
kg/sqcm
(g)
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
cm
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
A.6
A.7
Corrosion
allowance for
carbon steel
Weld joint
efficiency for ERW
pipes
A.8
A.9
Minimum
calculated pipe
thickness
Tc = ((Dp x OD x
0.1)/(2 x (y x Dp
+ Sa x J)) + C) x
10
mm
7.28
7.05
6.83
6.60
6.37
6.15
6.15
5.92
5.92
5.69
5.69
5.46
5.46
5.46
5.23
A.10
Mill negative
tolerance for pipe
thickness
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
A.11
Minimum required
wall thickness
(after considering
mill tolerance)
T* = Tc / ( 1 (M/100))
mm
8.32
8.06
7.80
7.54
7.28
7.02
7.02
6.77
6.77
6.51
6.51
6.24
6.24
6.24
5.98
A.12
Selected thickness
of pipe (based on
internal load
thickness
calculation)
Ts
mm
17.2
17.2
17.2
16
16
16
16
16
16
16
16
14.2
14.2
14.2
14.2
Page 106
Interim Report
Page 107
Interim Report
14.1.4
Capacity
LENGTH
C
TOTAL STATIC HEAD (H)
PIPE MATERIAL (MS)
DESIGN VELOCITY
60000
0.8
M
-
6
IS 2062
UNIT
CALCULATED DIA
( M)
NOTE
1
SELECTED DIA
( M)
150.00
1.74
MLD
M/S
ONE PIPE ACCOMODATING 150 MLD , THE ENTIRE SYSTEM WILL COMPRISE 3W + 2S PUMPS. REFER
SCHEMATIC DIAGRAM PROVIDED IN THE SHEET.
ACTUAL
VELOCITY
(M/S)
(Q/C)^1.81
994.62
STATIC
HEAD
(H)
D^4.81
REQUIRED
PUMP HEAD
INCLUDING
MINOR LOSS
(10 %) IN 'M'
SELECTED
PUMP
HEAD (M)
M/S
1.486770097
1.5
0.98
4.06
994.62
7.030706299
34.88
44.36
45.00
HEAD IN
Kg/Cm
4.59
1.1
M/S
1.417579666
1.5
0.98
4.06
994.62
7.030706299
34.88
44.36
45.00
4.59
1.2
M/S
1.3572292
1.4
1.13
4.06
994.62
5.045170546
48.60
59.46
60.00
6.12
1.3
M/S
1.303983636
1.4
1.13
4.06
994.62
5.045170546
48.60
59.46
60.00
6.12
1.4
M/S
1.256550073
1.3
1.31
4.06
994.62
3.532380874
69.42
82.36
83.00
8.466
1.5
M/S
1.213942701
1.3
1.31
4.06
994.62
3.532380874
69.42
82.36
83.00
8.466
1.6
M/S
1.175394966
1.2
1.54
4.06
994.62
2.403597776
102.02
118.22
119.00
12.138
1.7
M/S
1.140300611
1.2
1.54
4.06
994.62
2.403597776
102.02
118.22
119.00
12.138
1.8
M/S
1.108173001
1.2
1.54
4.06
994.62
2.403597776
102.02
118.22
119.00
12.138
1.9
M/S
1.078616395
1.1
1.83
4.06
994.62
1.581607864
155.04
176.54
177.00
18.054
M/S
1.051305217
1.1
1.83
4.06
994.62
1.581607864
155.04
176.54
177.00
18.054
2.1
M/S
1.025968838
1.1
1.83
4.06
994.62
1.581607864
155.04
176.54
177.00
18.054
2.2
M/S
1.002380195
1.1
1.83
4.06
994.62
1.581607864
155.04
176.54
177.00
18.054
2.3
M/S
0.98034717
2.21
4.06
994.62
245.21
275.73
276.00
28.152
2.4
M/S
0.959705971
2.21
4.06
994.62
245.21
275.73
276.00
28.152
Page 108
Interim Report
S.No.
A
Particulars
Formula/Symbol
Unit
option-i
optionii
option-iii
option-iv
optionv
optionvi
optionvii
optionviii
optionix
option-x
option-xi
optionxii
optionxiii
optionxiv
optionxv
A.1
Selected pipe ID
ID
mm
1500
1500
1400
1400
1300
1300
1200
1200
1200
1100
1100
1100
1100
1000
1000
A.2
Pipe OD
OD
mm
1540
1540
1434.4
1434.4
1334.4
1334.4
1232
1232
1232
1132
1132
1132
1132
1028.4
1028.4
A.3
Design Pressure
Dp
kg/sqcm
4.59
4.59
6.12
6.12
8.466
8.466
12.138
12.138
12.138
18.054
18.054
18.054
18.054
28.152
28.152
A.4
Design
Temperature
Td
deg.C
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
A.5
Allowable stress
Sa
kg/sqcm
(g)
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
1311.43
A.6
Corrosion
allowance for
carbon steel
cm
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
0.16
A.7
Weld joint
efficiency for ERW
pipes
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
A.8
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
A.9
Minimum
calculated pipe
thickness
Tc = ((Dp x OD x
0.1)/(2 x (y x Dp +
Sa x J)) + C) x 10
mm
5.05
5.05
4.81
4.81
4.58
4.58
4.35
4.35
4.35
4.12
4.12
4.12
4.12
3.88
3.88
A.10
Mill negative
tolerance for pipe
thickness
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
12.5
A.11
Minimum required
wall thickness
(after considering
mill tolerance)
T* = Tc / ( 1 (M/100))
mm
5.77
5.77
5.50
5.50
5.24
5.24
4.97
4.97
4.97
4.71
4.71
4.71
4.71
4.44
4.44
A.12
Selected
thickness of pipe
(based on internal
load thickness
calculation)
Ts
mm
20
20
17.2
17.2
17.2
17.2
16
16
16
16
16
16
16
14.2
14.2
Page 109
Interim Report
Page 110
Interim Report
15.
Increasing efficiency;
Saving time.
Some of these objectives may be contradictory. For example, it may not be possible to
extract the greatest financial value and, at the same time, reduce rates. Similarly, it may
not be able to realize significant cost reductions and, at the same time, protect
employees entirely. These choices are predicated on trade-offs, i.e. what can be
exchanged for the guarantees afforded by an O&M agreement. The stability and
continuity of a 10- 15-year contract is quite clear over greater immediate financial gains
possible through a short-term agreement.
The essence of public-private partnerships is the type and breadth of guarantees that are
rare and difficult to achieve under public operation and management. Essentially, the
guarantee aspect translates to an enhanced risk-management advantage. The more
responsibility given to the private sector, the better the risk profile from the government's
viewpoint. Guarantees in long-term O&M contracts often include:
Page 111
Interim Report
Page 112