Beruflich Dokumente
Kultur Dokumente
C O N T R A C T
Dear Sir,
We are very pleased to submit herewith our best offer for the supply of materials, fabrication,
delivery and installation of the above subject, in accordance with the plan prepared by your office,
subject to the following terms and conditions.
SCOPE OF WORKS
Item
I
II
Description
Unit
GENERAL REQUIREMENTS
1. Mobilization /Demobilization
2. Temporary Facilities
3. Delivery Charge
4. Administration/Supervision
5. Contingencies/Miscellaneous
6. Power Consumption
7. Clearing, Line & Grade Survey
Sub-Total (General Requirements)
lot
lot
lot
lot
lot
lot
lot
m
m
m
CONCRETE WORKS
1. Column Footings
2. Columns
3. Footing Tie Beams
4. Slab on Grade/Fill
m
m
m
m
m
m
m
REBAR WORKS
1. Footings - 16mm
2. Columns - 10mm
kg
kg
kg
kg
kg
kg
16mm
3. Footing Tie Beams - 10mm
16mm
4. Slab on Grade/Fill - 10mm
5. Suspended slab (2nd Floor and Roof) - Option 1
10mm
6. Girders/Beams - 10mm
20mm
7. Stair - 10mm
12mm
16mm
kg
kg
kg
kg
kg
kg
FORM WORKS
1. Column Footings
2. Columns
m
m
Page 1
m
m
m
m
m
kg
kg
kg
kg
kg
pcs
kg
pcs
kg
kg
Sub-Total (Structural steel Works)
VII.
set
lot
m
m
l.m.
l.m.
m
lot
12% VAT
GRAND TOTAL AMOUNT (Labor and Materials)
Php
TERMS OF PAYMENT: Forty Percent (40%) Downpayment & Balance upon Progress Billing
WORKS EXCLUDED:
TERMS & CONDITIONS:
1. Owner shall provide adequate Water Supply for the Construction at no cost to the
Contractor. Owner shall also provide water & power supply @ barracks area.
2. Any item or scope of work not stated above but ordered by the owner shall be incurred
additional charge by the contractor.
3. Estimated project cost is based on the plans provided by the owner, any changes such as
increase or decrease in specifications shall subject to change order.
4. Any defects that is caused by the design factor is not the liability of the contractor.
CONFORMED BY:
__________________________
SUBMITTED BY:
_______________________
Page 2
OWNER
Date Signed:________________
Arch. Tennessee Ng
Ever Pacific Steel Ind. Inc.
Page 3
June 7, 201
Unit Cost
Qty
Materials
Amount
Labor
Materials
Labor
1.00
1.00
1.00
1.00
1.00
1.00
1.00
52.23
39.05
7.50
950.00
500.00
350.00
300.00
7,125.00
26,115.00
13,667.50
2,250.00
6.91
11.75
7.65
9.60
31.92
22.10
2.79
3,900.00
3,900.00
3,900.00
3,900.00
3,900.00
3,900.00
3,900.00
1,350.00
1,350.00
1,350.00
1,350.00
1,350.00
1,350.00
1,350.00
26,949.00
45,825.00
29,835.00
37,440.00
124,488.00
86,190.00
10,881.00
9,328.50
15,862.50
10,327.50
12,960.00
43,092.00
29,835.00
3,766.50
807.43
1395.12
1723.18
323.79
759.33
306.9
40.00
40.00
40.00
40.00
40.00
40.00
10.00
10.00
10.00
10.00
10.00
10.00
32,297.20
55,804.80
68,927.20
12,951.60
30,373.20
12,276.00
8,074.30
13,951.20
17,231.80
3,237.90
7,593.30
3,069.00
3649.88
1304.44
3951.02
38.76
17.2
282.62
40.00
40.00
40.00
40.00
40.00
40.00
10.00
10.00
10.00
10.00
10.00
10.00
145,995.20
52,177.60
158,040.80
1,550.40
688.00
11,304.80
36,498.80
13,044.40
39,510.20
387.60
172.00
2,826.20
34.56
122.40
400.00
400.00
150.00
150.00
13,824.00
48,960.00
5,184.00
18,360.00
Page 4
61.20
4.00
140.00
223.00
21.24
400.00
400.00
400.00
400.00
400.00
150.00
150.00
150.00
150.00
150.00
24,480.00
1,600.00
56,000.00
89,200.00
8,496.00
9,180.00
600.00
21,000.00
33,450.00
3,186.00
184.48
593.12
40.00
40.00
30.00
30.00
7,379.20
23,724.80
5,534.40
17,793.60
461.58
54.87
93.28
6.00
35.61
168.00
40.00
40.00
40.00
120.00
40.00
5.00
30.00
30.00
30.00
20.00
30.00
5.00
18,463.20
2,194.80
3,731.20
720.00
1,424.40
840.00
13,847.40
1,646.10
2,798.40
120.00
1,068.30
840.00
452.16
343.64
40.00
40.00
30.00
30.00
18,086.40
13,745.60
13,564.80
10,309.20
2.00
3,500.00
1,000.00
7,000.00
2,000.00
1,650.00
400.00
800.00
500.00
450.00
400.00
200.00
200.00
49,500.00
11,688.00
1,680.00
28,500.00
18,810.00
12,000.00
5,844.00
420.00
1.00
57.00
41.80
30.00
29.22
2.10
1.00
BMITTED BY:
_______________________
Page 5
h. Tennessee Ng
r Pacific Steel Ind. Inc.
Page 6
June 7, 2016
Total
Amount
26,115.00
13,667.50
9,375.00
49,157.50
36,277.50
61,687.50
40,162.50
50,400.00
167,580.00
116,025.00
14,647.50
486,780.00
40,371.50
69,756.00
86,159.00
16,189.50
37,966.50
15,345.00
182,494.00
65,222.00
197,551.00
1,938.00
860.00
14,131.00
727,983.50
19,008.00
67,320.00
Page 7
33,660.00
2,200.00
77,000.00
122,650.00
11,682.00
333,520.00
12,913.60
41,518.40
32,310.60
3,840.90
6,529.60
840.00
2,492.70
1,680.00
31,651.20
24,054.80
157,831.80
9,000.00
55,000.00
28,500.00 Existing canal elevation = -1m from road elevation to top of rcp
18,810.00
61,500.00
17,532.00
2,100.00
80,000.00
272,442.00
2,027,714.80
243,325.78
2,271,040.58
Page 8
Page 9