Beruflich Dokumente
Kultur Dokumente
PANAGARH-PALSIT-DANKUNI SECTION FROM KM. 520.103 TO 649.072 (NEW CH.) OF NH-2 IN WEST BANGAL
3. Concessionaire
4 Date of Commencement of Services
5 Date of Commercial Operation
6 Annuity payments 30 installments
7 Concession Period
5.0
Maintenance Requirements:
All the road work and pavement contained in the project facilities during
operation period shall be maintained in traffic worthy condition as per
intervention levels 1 and 2 provided in the table 1-2 of Concession
Agreement for various maintenance activities.
The Concessionaire is fulfilling his contractual obligations in this regard
and ensures smooth and uninterrupted flow of traffic during normal
operating conditions for all 24 hours of a day by doing routine
maintenance works such as.
Routine Maintenance
In order to ensure smooth and uninterrupted flow of traffic during normal
operating conditions for all 24 hours of a day routine maintenance of the
Project facilities is being carried out by the Concessionaire such as.
5.1.
5.2.
Strengthening/Rehabilitation:
It is Concessionaires responsibility to fulfill the Contractual
obligations as per Concession Agreement.
5.3
Work Plan
UNIHORN INDIA PVT. LTD.
Page -5
The Tests
The Concessionaire has carried out traffic Count and Axle Load Test for
Panagarh-Palsit and Palsit- Dankuni section. Report submitted. Slide
presentation conducted regarding Pavement Evaluation on 07.03.2014.
5.5
Right of Way
The Right of Way ROW generally varies from 45meters and 60 meters
and is in the order of 90 meters in respect of Palsit-Dankuni section and
Palsit- Panagarh section.
5.6
5.7
Pavement Composition
Thickness
Adopted
(LHS)
Thickness
Adopted
(RHS)
50+40mm
50+40mm
240
240
150mm
250mm
200mm
150mm
150mm
250mm
200mm
150mm
255
195
150
245
200
155
Total
840mm
840mm
840
840
Bituminous Concrete
100 msa
20 Years for Flexible Pavement
30 Years for Concrete Pavement/
Rigid Pavement.
Un authorized parking of such heavy vehicles may also cause damages to the
Pavement and hard shoulders due to Lack of adequate parking area.
Significant distress/or Fatigue stress is not seen on the surface but it looks like
surface fungus or scabby and gradually getting deteriorated.
Also, it is notable that the entire Project Highway is passing through
predominantly Agricultural (Durgapur Expressway) Paddy field with irrigation
canals on either side of the Highway.
Proper camber shall be provided to the earthen shoulders as per cross section.
May be 3%
Proper open Drainage is cut on either side of the Project Highway and is well
maintained. The Earthen shoulders are not dressed properly to the required
camber and cross fall of 3% and compacted properly. Reverse slope is seen at
many places resulting in Pool of rain water on the Bituminous surface damaging
the Pavements.
Any lapses, deficiency and defects noticed shall be rectified forthwith by
the Concessionaire at his own cost and risks as per the Concession
Agreement.
The thickness of periodic over lay in Palsit to Dankuni Section is 50 mm
thick and in Panagarh- Palsit section it will be 40 mm on both sides.
This periodic overlay shall be maintained and executed at the end of
5th,10th and 15th year from the date of completion COD as per the original
Pavement Design.
However, THE Concessionaire is requested to do the Benkelman Beam
Deflection test after the monsoon preferably to identify the worst condition
of the Pavement.
All Quality control testing as required shall be conducted as per section
900 of MORT&H Specifications and in compliance with Concession
Agreement.
Stability Voids and Density shall be checked for compliance. Bitumen
Content must be optimized while carrying out the overlay.
5.8
Maintenance Requirements
5.9
Stage construction as per IRC: 37: 2001 Clause 3.3.3.3 and the Pavement is
designed for a life period of 20 years.
A) Trial Pit Details for Panagarh to Palsit (Taken on 9th & 10th January 2014)
SI.
Pavement
As per as built
As per as
As per Trial
Actual at
No.
Composition
Drawing
thickness on
LHS mm
built Drawing
thickness on
RHS mm
Pit at KM
570+467 (LHS)
mm
Trial Pit
at Km
524+950
(RHS)
existing
(Old
Road)
mm
1.
90mm
(50+40)
mm (A)
90mm
(40+40)
mm (A)
240 mm
(A+B)
(50+40)
240 mm
(A) + (B)
(40+40)
Dense
Bituminous
Macadem (DBM)
Wet Mix Macadem (WMM)
Granular Sub-Base (GSB)
Granular Sub-Base (GSB)
Drainage layer (Graded
Aggregate)
150mm
(B)
250mm
200mm
150mm
150mm
(B)
250mm
200mm
150mm
255mm
195mm
150mm
255mm
200mm
155mm
Brickbats
2.
3.
4.
5.
Total
Subgrade CBR >7%
6
840mm
840mm
840mm
840mm
500mm
Selected
soil from approved
borrow area with
soaked CBR > 7%
500mm Selected
soil
from
approved borrow
area with soaked
CBR > 7%
500
mm
Brick Bats +
sand
mixed.
1
1.
2.
3.
4.
5.
Pavement Composition
As per as built
Drawing
thickness on
RHS mm
As per as built
Drawing Actual
Thickness on
LHS mm
As per as buil
Drawing
thickness on
RHS mm
Bituminous
Concrete
(BC) using 60/70 Grade
Bitumen
Dense
Bituminous
Macadem (DBM)
Wet
Mix
Macadem
(WMM)
Granular
Sub-Base
(GSB)
Granular
Sub-Base
(GSB)
Drainage layer (Graded
Aggregate)
100mm
(50+50)
mm (A)
150mm
(50+50)
(100mm)
(50+50)
100mm
(50+50)
100mm
150mm
150mm
150mm
250mm
250mm
250mm
250mm
200mm
200mm
200mm
200mm
150mm
150mm
150mm
150mm
Total
6.
As per as built
Drawing
thickness on
LHS mm
850mm
850mm
850mm
850mm
500mm
Selected
soil
from approved
borrow area or
sand
500 mm 80%
Flyash+20%
sand
500 mm sand
500 mm sand
6.6. Based on ADT of commercial Vehicles obtained/day and Axle Load survey
carried out at KM 578 Truck Lay By. The Axle Load configurations identified and
noted for different categories of commercial Vehicles.
The Vehicles weighed (each type) on Axle Load Pad for Front and Rear Axles
and compared with Standard Load.
The Maximum permissible Weight for a particular Vehicle Configuration is carried
out and found to be 16.2 Tones as per standards where as the actual weight of
the same vehicle in loaded condition presently found to be 26.98 Tones.
Accordingly, the total damaging weight of the vehicle or vehicle Damage factor is
thus derived at is 32.386(sample of 6 vehicles at random sampling basis) Tones.
Based on the above, the Vehicle Damage Factor VDF calculated for all types of
vehicle is found out.
The VDF thus arrived at is used as a multiplier to convert the number of
commercial vehicles of different Axle Loads and Axle configurations in to number
of repetitions of Standard Axle Load of magnitude 80 KN.
It is defined as ESA (Equivalent Standard Axles) per commercial Vehicle
The VDF varies with Axle configuration and Axle Loading.
Accordingly, the VDF & Axle Load calculation for a 2 Axle Truck was found to be
37.900/6 Nos.
Average of 6.317
For various types of vehicles like LCV, 2 Axle Truck, 3 Axle Truck and Multi Axle
vehicle checked. It was calculated and found to be much higher than the VDF
adopted at the time of Pavement Design
Consequently, the projected MSA (Maximum Standard Axle Load) based on the
present VDF& ADT on the (LHS) and (RHS) is worked out to be higher
respectively on completion of the Concession period from the date of COD.
Accordingly, the projected Design MSA arrived at with the present data for the
Year ending is as follows with a Growth Factor of 0.05
Year
MSA
Cu MSA
Design MSA
LHS
2014
22.75
22.75
22.75
2019
29.04
154.75
132.00
2024
37.06
323.21
168.46
It is on the higher side than the Axle Load survey conducted at the time of
Design of Pavement before during the preparation of Detailed Project Report.
Similarly for the right hand side (RHS)
Year
MSA
Cu MSA
2014
12.50
12.50
Design MSA
12.50
LHS
2019
2024
15.96
20.37
85.04
177.63
72.54
92.59
Based on the above findings, the VDF is found to be much on higher side.
Correspondingly, the Projected MSA is on the higher side due to higher
VDF.
Atmospheric temperature variation from 10 0 C to 400 C, may be polluted
with salt or sulphur content causing Bitumen losing its binding property.
Also, moisture in Air, due to rain and ingress and egress of water from
bottom and sides of Embankment and percolation effect from top surface
may also cause such damages to the Road surface.
The Benkelman Beam Deflection tests reveal varied deflection of
0.50 mm to 0.80 mm
Axle Load survey reveals MSA is > 100msa.
IRC : 81 : 1997 is applicable for overlay design up to 0.50 mm deflection
only (Overlay of 40mm with BC (Bituminous Concrete) with MSA<
100MSA where as in this case the deflection is > 0.50mm and varies up to
0.85mm MSA > 100MSA.
If tested after the rainy season, it may be much more.
6.0
Interpretation
Based on the above, AASHTO-1993 method of overlay may not be
adequate as the Bituminous Concrete surface is not withstanding the
Abrasive effect of Wheel Loads of various type of heavy vehicles with
multi axles plying on this Project Highway and hence (Resistance to
Abrasion Effect of Wheels) wear and tear is more resulting in
damages/cracks or failure of the Bituminous Concrete surface. The
structural condition of the flexible Pavement of the Project Highway is
getting deteriorated further and further.
However, the scope of the Project is limited to the specified periodic
overlay of 40mm on Panagarh- Palsit section and 50mm on PalsitDankuni section respectively.
6.1
Recommendations
In such eventuality, the Concessionaire is advised to carry out Pavement
condition survey, Benkelman Beam Deflection Test for evaluation of
existing structural conditions and its residual strength soon after the
monsoon to identify and make up the structural deficiency if any as per
IRC: 81:1997.
6.2
Suggestions
6.3 Conclusion
This may be treated as a preventive and proactive action please.
The Concessionaire is responsible for Quality, soundness, durability,
Safety and the overall Project requirements, Operate & Maintain the
Project facilities as per the terms and conditions of the Concession
Agreement.
The defects, deficiencies and lapses if any noticed have got to be rectified
by the Concessionaire at its own cost and expenses and make good the
riding Quality of the surface with a crack proof layer.
An early action in this regard would be highly appreciated.
6.4
Enclosures:
Photographs showing typical damages of the BC overlay surface at
various location of the Project Highway on LHS and RHS of PanagarhPalsit-Dankuni section of NH-2 during Operation and Maintenance period.
N.Dhamarajan
(Senior Pavement Specialist)
Unihorn India Pvt. Ltd.
Burdwan, West Bengal