Beruflich Dokumente
Kultur Dokumente
LEARNING OBJECTIVES
What is building
commissioning
What are the steps required by
LEED
Why is it important
What results can we expect
NEW BUILDING CX
LEED Credits
Deals mainly with construction and getting the building operating before
hand-over
VISION OF COMMISSIONING
Take the owners needs and wants
Similar to a QC
process for cars
Note similarities in:
Work area
Tools
Assembly
techniques
Workers
responsibilities
UP-TO-DATE KNOWLEDGE
Innovation moving extremely fast
Innovative equipment and
systems are relatively unfamiliar
to designers, contractors,
operators and even
manufacturers agents
Energy efficiency, integrated
systems, imported design
concepts and computerization
have multiplied levels of
complexity
WHAT IS INNOVATION
MULTIPLE MARRIED TECHNOLOGIES
ADDED COMPLICATIONS
Radiant heating
Radiant cooling
Condensing boiler
Water-side economizer
Building automation systems
CONVENTIONAL COMMISSIONING
Start-up and basic check out of equipment
Testing, Adjusting and Balancing (TAB)
Begins after systems in and ready for
start-up
Verify individual components function as
components
Performed by installing contractor or
manufacturers rep
COMMISSIONING COMPARISON
TOTAL COMMISSIONING
TRADITIONAL COMMISSIONING
VALUE OF Cx
Largest study to date
Mills, LBNL July 2009
http://cx.lbl.gov/2009-assessment.html
643 buildings, 26 US states
561 existing and 82 new buildings
37 Cx firms
99 M ft2, $2.2 B construct
90.4 M ft2 existing, 8.8 M ft2 new construction
$43 M Cx costs
AREAS OF BENEFIT
LEED Cx OUTLINE
Design and Construction Phases
EAp1 Fundamental Cx
EAc3 Enhanced Cx
Design
Construction Documents
50% CD
Installation
Start-up
Post Construction
Occupancy
Cx DURING DESIGN
Cx PLAN
Overview of Cx Process
List of equipment and systems to be Cx
Cx Team and responsibilities
Management, Communication and Reporting Overview
Cx Process Overview (Outline above)
List of deliverables
Milestones
Consultants
Provide documentation as required for review
Attend commissioning meetings as required
M&E CONTRACTORS
Completes start-up, installation verification lists
Operates equipment for Performance Testing
Produces O&M manuals, Provides owner training
CONTROLS CONTRACTOR
Operate controls for Performance Testing, produce
O&M materials for controls
Cx SPECIFICATIONS
Contractor responsibilities
Submittal review process
Meetings
IVC process
Start-up process
Balancing reviews
FPT process
O&M manuals requirements
Training requirements
Warranty review
Cx DURING CONSTRUCTION
TRAINING TOPICS
General purpose of system
Use of O&M manuals
Operation of systems under all conditions
Interaction with other systems
Adjustments and optimization for efficiency
Health and safety
Special maintenance and replacement resources
Occupant interaction
Controls training
SYSTEMS MANUAL
Final BoD
System single line diagrams
As-Built sequences, set-points, etc.
System operating instructions
Maintenance schedule
Retesting schedule
Cx AFTER OCCUPANCY
FINAL REPORT
OPR
Design and shops review summary
Cx specifications
IVC results
FPT results
O&M evaluation
Value achieved through Cx
Outstanding issues
MULTI-FUNTION AHU
DESIGN ISSUES
Dehumidifying only
outdoor air reduces size of
equipment and increases
efficiency of equipment
Using heat recovery to
reduce load on cooling coil
Using indirect evaporative
cooler to increase HX effy
humidity carried outdoors
MULTI-FUNCTION AHU
INSTALLATION ISSUES
No radiation shield on sensor by flame
No maintenance access to some
sensors
Installation of single point sensor
where averaging required
Reset button set tight and vibration
causing unit to cut out
Overloads not set properly
BOILERS
DESIGN ISSUES
BOILER
INSTALLATION ISSUES
RETIREMENT RESIDENCE
HVAC SYSTEM
RETIREMENT HOME
DESIGN ISSUES
AIR HANDLER
SHOP DRAWING REVIEW FINDINGS
1. 3 re-submittals of heat wheel shop drawings required
before a workable defrost strategy provided.
2. Shop drawing coil performance based on water while
system will used propylene glycol.
3. Coils have greater air-side and water-side pressure
drops than specified.
4. Controls sequences were carbon copy of engineers
general wording rather than converting to specifics that
can be programmed.
Heat wheel, heating coil and cooling coils shall be
sequenced to provide energy efficient operation
HVAC SYSTEM
Ground Source Heat Pump
Radiant floor heating
Dedicated outdoor air ventilation with heat recovery
Supplemental fan coils for cooling
Functional Testing
System relied on heat pump circulator but never
programmed to operate when heat pump off
PID loops needed tuning to provide stable operation
Radiant floor valve found with wire not connected leaving
valve open and space overheating
Heat pump constantly tripping. Supplier blamed system but did not
measure any parameters. Cx measurements showed water flows
ok. Heat pump diagnostics finally found faulty TX valve and low
refrigerant.
REAL PERFORMANCE
What is the energy use of typical buildings?
800
700
600
Annual
Energy
ekWh/m2
500
400
300
200
100
Alldata(exceptGoG)from
NRCanSurvey(CIBEUS,2000).
0
AllBldgs C&IAccom Offices
(ON)
(ON)
(ON)
Offices
(CAN)
GoG
RETIREMENT RESIDENCE A
Actual Performance
300
Annual
Energy
ekWh/m2
250
200
150
100
50
Simulated
Actual
0
Dec'04(SL)
Nov'05(SL)
Nov'05(CBIP)
Jul'06(Review) Apr'07toMar'08
RETIREMENT RESIDENCE B
Actual Performance
250
200
Annual
Energy
ekWh/m2
150
100
50
Simulated
Actual
0
Aug'04(SL)
Feb'06(CBIP)
Aug'06(Review)
Aug'07toFeb'08
LABORATORY BUILDING
Actual Performance
500
Simulated
Actual
400
Annual
Energy
ekWh/m2
300
200
100
0
Aug'04(SL)
Aug'06(CBIP)
Feb'07(Review)
Dec'07toFeb'08
MartoMay'08
COMPARISON
Actual energy use compared to typical buildings
800
700
600
Annual
Energy
500
ekWh/m2 400
300
200
100
0
AllBldgs C&IAccom Offices
(ON)
(ON)
(ON)
Offices
(CAN)
GoG
Building
VA
A
Building
SSJ
B
Building
KPHQ
C
Building
TRCA
D