Sie sind auf Seite 1von 5

Mfg OH Fixed, Mfg OH Variable these two activities is a combination of setup,

machine & labor times.


When you change machine/labor time we are expecting that the system will recalculate Mfg OH fixed & Mfg OH Variable.

Reply:
I have changed the routing with work center WCTEST3. In that I have used the
standard value key is ZOH1 having the activities SET UP, MACHINE ,LABOUR AND
OH

Formula defined for OH

CO11N: Actual qty is 328, according to that the activity values were calculated.

Now I have changed the qty to 100, then accordingly calculated the OH based on
set up time,machine time etc according to the formula

Note: The activity values changed upon the yield quantity only. If you want to
change the activity values and according to OH will not be changed.

Das könnte Ihnen auch gefallen