SUMMARY REPORT FOR

Godawari Power & Ispat Limited, Raipur

PROJECT UDAAN
By

Renoir Consulting (India) Pvt Ltd


Project Team:
Nilutpol Borah, Operations Manager
Ajay Vaze, Project Manager
Aashish Kr. Singh, Sr. Consultant
Ashish Vashisth, Consultant
Arpit Banga, Consultant
Project Start: August 4, 2014
Project Completion: February 28, 2015
Duration: 30 weeks

GPIL, Raipur, Confidential

Page 1

Executive Summary
Background
Godawari Power & Ispat Ltd. (GPIL) a public Ltd. Co., formally Ispat Godawari Ltd
(IGL), a pioneer constituent belonging to HIRA Group of Industries, Raipur, C.G. was
incorporated in 1999 to set up an integrated steel plant with captive power
generation.GPIL is a flagship Company of Raipur-based Hira Group of Industries
having dominant presence in the long product segment of the Steel industry, mainly
into mild steel wire. Today, GPIL is an end-to-end manufacturer of mild steel wires. In
the process, the company manufactures sponge iron, billets, Ferro alloys, captive
power, wires rods (through subsidiary company), steel wires, Oxygen gas, fly ash
bricks.
GPIL has come a long way since it started its operation in Raipur, Chhattisgarh as a
sponge iron manufacturer in the year 2001. Over the last few years, the company
has scaled up its capacity five-fold and has become one of the largest players in the
mild steel wires segment. Consistency has been a hallmark of GPILs product and in
Steel Melting Shop convert the dream into reality by producing one of the finest
quality of BILEETS in the Industry. This ranges from customized size of 110 x 110
which confirms to BIS standards 2830 & 2831 to the extended range of 200 x 250
thereby any size and composition with ease and balance.
Billets are produced out of pellets based sponge Iron resulting significantly positive
impact on re-rolling process due to its surface finish and chemical property which
holds good at testing parameters. It surpasses any criticality and complexity of the
rolling mills with extended competitive edge in such process integration.
Billets meant for re-rolling of strips, wire, bar, hexagons and profiles, available in
variety of sizes.

In Aug 2014, GPILs management engaged Renoir Consulting for an Operational


Excellence Programme christened Udaan with a focus to improve the output by

GPIL, Raipur, Confidential

Page 2

improving the efficiency and utilisation. The duration of the project was decided as 30
calendar weeks to identify opportunities, design the solutions, implement the same
and ensure sustainability. A taskforce was formed consisting of GPIL employees who
worked with Renoir Consulting to identify the opportunities and implement the
solutions concurrently in the three areas namely Process, Maintenance and Quality.
Department wise MATs were created which were chaired by the MAT chairman. MAT
members having the desired skills, knowledge and experience were chosen to
validate the studies and solutions to ensure not only the quality but also the
acceptability of the solution.
In SMS MAT, below are some of the issues identified and systems implemented to
resolve them, so that the department and the company can achieve the desired
KPIs.

GPIL, Raipur, Confidential

Page 3

Management
Action Team

Key Issues

Systems Implemented

(MAT) Area
Linkage

of

Monthly

production plan with


shift wise schedule

Process

Daily Production Planning


Production Deviation report
KPI Dashboard

KPI Tree
KPI Dashboard
Shift handover
Daily Review Meeting
Weekly Review Meeting
Monthly Review Meeting
Comprehensive Production logsheet
This mentions relevant standards

Lack of structured

which are to be followed such as Tap

review mechanism

temperature, empty ladle temperature,


pitside temperature, Monitoring of load

Key Process
Parameter variations
Process

Absence of information
for evaluation of

GPIL, Raipur, Confidential

Page 4

ramp up
RACI matrix

systems
KWH/MT
Cycle Time
Empty ladle temperature
Tap temperature
Pit side temperature
Purging time
Temperature at CCM
Carbon level in bath sample
Specific solutions themes to control the

variations (short term and long term)


Productivity
Critical Equipment listing
Bad Actors identification
Maintenance MIS (frequency, MTTR

for

all

implemented

Management
Action Team

Key Issues

Systems Implemented

(MAT) Area
Maintenance

etc.)
Reliability Centred Maintenance

Approach
Breakdown Management System
PM Schedule
Equipment History and criticality list
Shift handover system
Line Walk
RCA Policy and RCA (corrective and

preventive actions
FGDs (Purchase)

Daily Review Meeting


Weekly Review Meetting
Monthly Review meeting

Sponge pellet requirement Vs

fulfilment
Quality checklist in production

Shift handover system comprising of

Performance
Maintenance
Lack of structured
Maintenance systems

Lack of Review
Maintenance

Mechanism
Non conformance in
the quality standards

Quality

Ineffective Shift

all departments such as production,

Handovers

quality , maintenance, RM, CCM

RCAs and

enhancement of

RCA for quality issues


Macro test

current systems

In order to drive the implementation, weekly MAT meetings and fortnightly Steering
Committee Meetings were conducted. The purpose of these meetings was to
eliminate any impediments that the Project Team may face during implementation.
The actions derived from these meetings were communicated to all concerned and

GPIL, Raipur, Confidential

Page 5

they were directed to initiate actions, track the same and review periodically for
achieving the desired benefits.
Major activities carried out by the Project Udaan team were:
1. Value Drivers mapping for key performance improvements for each plant
2. Standard operating procedure prepared and same has been mentioned in the
production logsheet, which is referred by the melter and shift in charge
3. Implementation of Reliability Centred Maintenance Approach across all plants
4. Improved daily review meeting and analysis of issues through root cause
analysis and implementation of CAPA
5. Interface improvements between the Power Plant and consumer departments
for reduction in export of power
6. Optimum utilization of resources to achieve desired level of targets

Some of the areas, where the actions need to be fast-tracked are:


1. Actual weighment of molten metal and charge mix added in each heat
2. Resolution of issues in Furnace no 06
3. Resolution of shortage and fluctuation in power supply to SMS
Having said this, to ensure sustained implementation of above systems, a structured
three-stage audit mechanism was implemented (Compliance, Understanding and
Usage). The results are as of week 26
MAT
SMS

Compliance (%)
93%

Understanding (%)
96%

Usage (%)
84%

The below mentioned table enumerates the results that were achieved by the
Management Action Teams for the period of implementation. The following were the
results achieved as comparison between Baseline and Actuals:

GPIL, Raipur, Confidential

Page 6

Target and baseline was revised considering managements decision to run only 3
furnaces 8-10 till week 26. From week 27 onwards target and baseline were further
revised considering operation of furnace 6-10 and 3-5(depending on power
availability)
Considering Revision 2 : Furnace 8-10 Week 16 to week 26
Annualized benefit
Dec13
Sr.
No.

Description

May14

to

based

Improvement
Target

(Baseline

(Actuals)

on

comparison

with

Baseline

and

agreed evaluation

period)

methodology
Production 1.

Average
production

252

290

275

8370

MT / day
2.

KWH/MT

925.3

880

871

54,29,176 units
saved

Conclusion
The improvement program needs to be continued with full compliance to ensure that
the benefits are reaped on a sustainable basis. The necessitated major cultural shift
in the way of functioning of the organization should be sustained.
The management should drive the initiatives inspite of challenges of this industry
such as raw material unavailability, consistency of raw material grade, changing
market conditions (prices, demand) etc.

GPIL, Raipur, Confidential

Page 7

It is desirable that the management takes decisive actions in a timely manner to


improve the operations in the plant, as this will go a long way in improving the
efficiency and utilization of SMS Plant.

Standard Operating Proced


Production and Specific Power Consumption

Project Udaan
GPIL, Raipur, ConfidentialGodawari
Page 8Power

and Ispat Limited

Godawari Power and Ispat Limited


Siltara, Raipur

Project Udaan: Operational Excellence Manual

Title: Standard Operating Procedure Production and Specific


Power consumption

Revision Number: 000


Issue Date:
Effective Date:
This Copy Printed :
Pages: 91
Document Reference/File: Standard Operating Procedures Production and Specific Power
consumption
Location:
Issued by: Controller to be determined by GPIL
Approved by: Auditor to be determined by GPIL

GPIL, Raipur, Confidential

Page 9

Master Revision Table


For ISO 9001 purposes records of previous revisions are to be recorded here. The issuer of
this document should be contacted for verification of the latest release version. All earlier
release versions must be destroyed.
Revision Number:

Issue Date:

Effective Date:

Issued by:

Approved by:

Effective Date:

Issued by:

Approved by:

Effective Date:

Issued by:

Approved by:

Effective Date:

Issued by:

Approved by:

Summary of Changes:
Revision Number:

Issue Date:

Summary of Changes:
Revision Number:

Issue Date:

Summary of Changes:
Revision Number:

Issue Date:

Summary of Changes:
Disclaimer
This is a reference manual for Production and Management control systems and processes
designed and installed in Godawari Power and Ispat Limited, Siltara, Raipur.
These systems have been implemented after discussion and approval from the Steel Melting
Shop Management Action Team (MAT).
This document is a ready reckoner for all existing employees and new joinees to get a good
view of the systems and processes used by Production team.

GPIL, Raipur, Confidential

Page 10

Table of Contents
Executive summary..2
Background.2
Conclusion...................................................................................................................
Master Revision Table................................................................................................................
Background...............................................................................................................................
Project Objectives......................................................................................................................
Project Approach.......................................................................................................................
Project Structure........................................................................................................................
Focus Process...........................................................................................................................
Design and Development...........................................................................................................
Solution Development Approach............................................................................................
Implementation and Sustainability.............................................................................................
Implementation Production and Planning Systems.................................................................
Shift Handover.31
Daily Review Meeting.............................................................................................................
Weekly Review Meeting.........................................................................................................
Purchase Focus Group Discussion........................................................................................
Annual Preventive Maintenance Program..............................................................................
Breakdown Slip......................................................................................................................
Breakdown Management System...........................................................................................
Line Walk...............................................................................................................................
Root Cause Analysis..............................................................................................................
Production Deviation sheet....................................................................................................
Before casting checklist..........................................................................................................
Comprehensive Production Logsheet....................................................................................
Equipment Criticality Ranking................................................................................................
Quality Checklist(Quality gate)...............................................................................................
QC checklist in production......................................................................................................
Sequencing between CCM and furnace.................................................................................
Sponge pellet and ore requirement Vs Fulfilment...................................................................
Operational Benefit Tracker and KPI Dashboard..73
Standard Operating Procedure77
GPIL, Raipur, Confidential

Page 11

Daily caster Maintenance Checklist....77


Process quality checks..79
Inventory Tracking..83
Tool Box standardization and Audit.83
Bad Actor List..85
Sustainability phase...................................................................................................................
Step by Step Instruction.88
Appropriate Management style.90
Responsibility and Frequency..90

GPIL, Raipur, Confidential

Page 12

Background
In 2013, GPIL planned to take the next leap in throughput improvement by implementing
robust systems with the help of Renoir Consulting. Renoir undertook a dip stick study to
identify areas of potential improvement. The major areas of opportunity were improvement in
plant utilization, efficiency, and systems for production and planning, maintenance,
communication and training.

Project Objectives
The main objective was to facilitate an increase in production by deployment of Management
Control Systems.
To achieve this, a project team was set up which consisted of a Project Manager and two
consultants under the guidance of an Operations Manager. A separate Management Action
Team (MAT) for Production and Planning was installed to identify gaps in the Production and
Planning areas and drive systemic changes in this function to improve the Production. The 3
MAT teams were well supported by 6 taskforce members who were picked from the
respective sections of GPIL. The Project structure comprised of one MAT at each for
Production and Planning, Maintenance and Communication and Training. The MAT work
was reviewed by company level Steering Committees headed by the Managing Director.
Within SMS MAT the primary objective was to:

Improve Production through Utilization and Efficiency

Reduction in the Specific Power consumption

GPIL, Raipur, Confidential

Page 13

Project Approach

Carry out series of studies

Identify the gaps in performance

Quantify main areas of opportunities

Develop detailed approach on delivering the results

Identify resources, time and cost of moving to project phase

Set up Management Action Team for each function. Select leader for each function.

Define objective for each Team.

Empower each MAT member to lead an objective

Define /acceptance of roles and responsibilities of each member.

Carry out detailed study together with company staff members to ensure
understanding on issues and opportunities of improvements

Develop Solutions to areas identified during focus process

Prioritize the implementation and make implementation plan.

Dry run and wet run of solutions to be carried out

Install solutions in all the areas

Provide training to all the employees with regards to the approach of solutions

To sustain result, conduct audit to monitor the compliance of new system

Monitor the results to see the benefits accrued

GPIL, Raipur, Confidential

Page 14

Project Structure
Chairman: Mr. Abhishek
Agrawal
Vice Chairman: Mr. Vivek
Agrawal / Mr. S.K. Mishra

Steering Committee

Pellet MAT

SID MAT

Power MAT

SMS MAT

MAT Chairman:

MAT Chairman:

MAT Chairman:

MAT Chairman:

Mr. Raveendra

Mr. J.K. Sahu

Mr. Shandilia

Mr. Bansal

Taskforce

Taskforce

Taskforce

Taskforce

Aditya P. Singh
Hari Shankar
Manish Mandal

Sabyasachi

ShashiKant
Sharma

Bhanu P Singh

Umesh Shukla

Consultant

Consultant

Consultant

Consultant

Arpit Banga

Ashish Vashisth

Ashish Vashisth

Aashish Singh

GPIL, Raipur, Confidential

Page 15

Project Manager: Ajay Vaze, Operation Manager: Nilutpol Borah

Evaluation MAT

Steering Committee
The steering committee comprised of ED Mr. Abhishek Agrawal, and all MATs Chairman.
During the SCM meeting, MATs chairman updated the SCM about the progress of their
MATs as against the Management Action Plans (as finalized after the Focus ProcessTM ).
Management Action Teams
The management action teams (MATs) comprised of a MAT Chairman Mr. G S Bansal, Vice
Chairman Mr. Sanjay Mundada and 5 other team members. The primary objective of the
MAT was to identify the opportunities for improvement, design solutions to fill those gaps and
implement the same. The role of MATs also includes coaching and mentoring the other
concerned people in the plant about new installed systems / processes.

GPIL, Raipur, Confidential

Page 16

Focus Process
During the initial phase studies were conducted by the project team and the Management
Action team to identify, areas for improvement, new systems / processes. We first looked
into the capacity utilization. We calculated the capacity of the plant based on the quartile 3
methodology and mapped the production which was achieved by the plant. Gaps were
categorized under following categories :
1. Breakdown Losses
2. Shutdown losses
3. Performance losses
Value driver tree was envisaged to map the journey to financial benefit. The root of the tree
germinated from profitability. Three area were contemplated through which we can attain
benefit as shown in the chart below :

Illustrative

In order to validate the gaps or opportunities we focused on following parameters:

GPIL, Raipur, Confidential

Page 17

1) Data analysis (plants capacity utilization, breakup of % downtime loss, %

performance loss, key process parameters variation analysis)


2) Observational Studies to map the effectiveness of practices followed in the
plant
3) MCS (Management Control System) to map the effectiveness of managing the
business by managing the activities, information and people
4) Issue tree and probable cause analysis

Breakdown Losses
Maintenance System

Breakdown and shutdown losses was analysed for the baseline period and it was found that
same constituted to 4 % of the ideal capacity (calculated on the basis of quartile -3 of the
actual production)

GPIL, Raipur, Confidential

Page 18

SMS Plant - Capacity Utilization - Dec' 13 - May'14


250,000
200,000
150,000

121,212
4,386

100,000
50,000

1,058

Illustrative

102,805
12,964

To find the gap we mapped the As Is system of maintenance management as shown in the
chart given below:

Illustrative

It can be seen that maintenance system was very weak and following opportunities were
evident:
1. Lack of Preventive maintenance
a) Lack of effective PM Plan
b) Lack of system for handing over of equipment during PM
c) Lack of standard checklist

GPIL, Raipur, Confidential

Page 19

Same was validated through data analysis and issue tree.

Illustrative
Illustrative

Baseline - Electrical and Mechanical Breakdown

Illustrative
Mechanical
68%

32%

Electrical
100%

Electrical breakdowns constituted 68 % which is quite high. Over all % uptime of furnace
was 97 %.

ISSUE TREE - Electrical Breakdown - Furnaces


Level 1

Level 2

Level 3

Level 4

Level 5

Bus Bar
cooling
tube
leakage

Sparkin
g in
Busbar

Due to dust
accumulation on busbar
Due to rupture of
cooling pipe which
results in leakage of
water
Loosening of busbar
bolts

Panel is not dust


proof
Loosing of clamp

Poor maintenance

Wear and tear in


pipe

Lack of periodic
checks

Due to frequent
cooling heating of
busbars
DM water inlet
temperature should
be less than 32
degree

Lack of periodic
checks for tightening

Illustrative

Electrical
Breakdown
in furnaces

Brazing
opens

Temperature of busbar
should be below 65
degree C.

Sparking in busbar

Increase in busbar

GPIL, Raipur, Confidential

Page 20

Due to dust
accumulation on
busbar
Due to rupture of
cooling pipe which
results in leakage of
water

Level 6

Cooling tower is not


efficient, which
resulted in poor heat
exchange and
higher DM water
temperature
Panel is not dust
proof
Loosing of clamp

Poor
maintenance

Wear and tear in


pipe

Lack of periodic
checks

temp.

Temperature of
busbar should be
below 65 degree C.

DM water temp inc.


beyond 38 degree,
which should be
below 32 degree.

Due to loose nut


bolts

Due to frequent
cooling heating of
busbars

Cooling tower is
not efficient,
which resulted in
poor heat
exchange and
higher DM water
temperature
Lack of periodic
checks

Main issues which resulted in electrical breakdown were as following:


1. Lack of preventive maintenance
2. Lack of standard checklist
3. In effective cooling due to inefficient cooling tower
Performance Loss/ Productivity Loss
Performance loss was analysed for the baseline period and it was found that same
constituted to 4 % of the ideal capacity (calculated on the basis of quartile -3 of the actual
production)

SMS Plant - Capacity Utilization - Dec' 13 - May'14


250,000
200,000
150,000

121,212

100,000

4,386

1,058
102,805

50,000

12,964

Illustrative

To find out the reason for the gap between capacity and actual production we mapped
production management system MCS on a brown paper. The Management Control System
(MCS) is a unique kind of business management tool. Whereas a normal process map
catalogues events in a chronological order and uncovers operational inefficiency, a MCS
catalogues the data flow of all the concurrent events and identifies if the appropriate
information is available to make appropriate and correct business decisions.

GPIL, Raipur, Confidential

Page 21

It is a two axis diagram, one axis being a chronological scale of systems elements under the
column headings of:

Forecast
This is forecasting expenses related to production (production budget)

Plan
This involves defining monthly / quarterly expenses plan related to production

Control
Coordination between plant head, shift managers, production heads and operators

Report
o
Providing numerous valuable point of information in a structured manner
o
Roll up operational activities through weekly operational and monthly balanced
scorecards
The other axis is a frequency scale of elements at which the above activities of Forecast,
Plan, Control and Report should be performed. The As Is MCS for Production and
Planning is depicted below:

As Is Management Control System

GPIL, Raipur, Confidential

Page 22

Critiques classification
1. System = 56
2. Process = 55
3. Behaviour = 8

Illustrative

Critiques formed the baseline for the


formulation of the solutions and fill
the gap of As Is MCS

As Is process was mapped and critiquing was done to find gaps in the present production
system.
Following were critical points
1. Lack of effective production plan
2. Lack of standard parameters
3. Lack of understanding among workmen about SOP

As-Is Management Control System Critiques Classification- Steel Melting Shop

Category

Loss in
productivity

System

Priority for
Implementat
ion
High

Control

Production
loss due to
equipment
unavailability
Rejection,
increase cycle
time

System

High

System

High

Less
opportunity to
review
breakdown
reasons
Production
loss due to
unavailability
of required
power
Ineffective PM,
repeated
failures

System

Medium

Control

Interface with Power


department for
availability of power

Control

Critical equipment list


needs be refined
(basis history of
breakdowns, MTTR,
MTBF, PM non
compliance etc.)
Yearly shutdown plan
for caster to be made

Plan

Illustrative

Role of Quality
department to freeze
standards and ensure
compliance.
There is no system of
generating Bad Actor
list

Approach
temSys

Leads to
(Impact)

isticStat

Maintenance of caster
is to be done on daily
basis and hence
schedule is needed
Caster PM checklist to
be revisited.

Related to which
MCS Element?
(Forecast/Plan/Co
Control

soniRea

N
1

Critique

ItJust
Do

Sr

Report

Plan

GPIL, Raipur, Confidential

Ineffective PM,
repeated
failures

Page 23

Medium

System

High

High

Strict supervision
required at caster and
furnace to ensure
adherence to SOPs.

Control

SOPs to be refined

Control

Production
loss due to
non
compliance of
SOP
Impact on
effectiveness
of jobs
performed

High

Process

Medium

Bottleneck analysis was done to estimate the capacity of the process

Illustrative

Illustrative

Through capacity estimation it was found that furnaces are the bottleneck and caster need to
subordinate furnace.

GPIL, Raipur, Confidential

Page 24

Further to this, issues pertaining to caster, which resulted in tonnage loss, were analysed.
Main reason for the same were as following:
1.
2.
3.
4.
5.

Loss due to chemistry issue


Loss due to non - adherence to the standard parameters
Sequencing issues
Lack of short interval control
Lack of quality gate

Power Saving KWH/MT


Specific power consumption was analysed in the baseline period and regression analysis
was done to predict the specific power consumption at target production. Gaps were
analysed which could result in reduction in power consumption.
1. Improvement in the productivity of furnace
2. Operation of furnace at full capacity
3. Adherence to standard parameters such as Tap temperature, ladle preheat, load
rampup,
4. Optimized charge mix
5. Short Interval Control
6. Effective planning
7. Review mechanism
8. Effective sequencing between furnace and CCM
Data analysis was done to validate the hypothesis. In data analysis productivity of furnaces
was mapped.
( ** Baseline Dec13 May14)

GPIL, Raipur, Confidential

Page 25

Illustrative
16

Productivity - MT/Heat
15

14
12

12.4

12

15
12.5

11

10

MT/heat

8
6
4
2
0

Furnace 08

Furnace 09
Baseline

Furnace10

Standard

There was shortage of 17% in furnace 9 and 10 and 8 % in furnace 08. Similar exercise was
done for all furnaces to estimate the potential improvement in the power consumption.
Regression analysis was done on existing KWh/MT data to establish ideal KWH/MT

Design and development SOLUTIONS


Breakdown Losses

GPIL, Raipur, Confidential

Page 26

Illustrative

Solution was designed to strengthen the preventive maintenance system. Following systems
were installed :
1.
2.
3.
4.
5.
6.

Preventive maintenance system


Breakdown management system
Root cause analysis and CAPA
Equipment criticality ranking
Monthly bad actor list
Line Walk

GPIL, Raipur, Confidential

Page 27

Reliability Centred Maintenance Philosophy

Illustrative

OUTCOME

Illustrative

OUTCOME

Illustrative

Baseline Dec13 May14

Illustrative

GPIL, Raipur, Confidential

Page 28

Design and Development


Project team started to thrash out issues identified during focus process and
channelize substantial improvement. Steering committee was formed to guide the
overall implementation plan. A dedicated team, comprising the task force and cross
functional Management Action Teams', was appointed for the design and
implementation of systems.
The MATs started working on design and implementation as per the Management
Action Plan. Gaps in the MCS were plugged in and new systems mapped to increase
the effectiveness. Their progress was monitored in the Steering Committee Meeting
every alternative week. Various systems and process changes were implemented.
The new systems implemented have been added here as a procedure manual to
help as future reference or training guide for new employees.
To be MCS

Performance Loss
Solution tree was envisaged for reduction in the performance and boost productivity of the
plant. This solution tree was originated from the value drivers

GPIL, Raipur, Confidential

Page 29

Solution Tree Productivity & Performance Loss

Illustrative

Approach for Improvement

GPIL, Raipur, Confidential

Page 30

Im p le m e n
t a t io n

Illustrative
To - B e
(S o lu tio n
D e s ig n in g
)
O p p o rt u n it
y
I d e n t ifi c a t i
on
A s -Is
M a p p in g
P ro d u c t io n
M C S (b ro w n
p a p e r)
P ro c e s s
M a p p in g
( h ig h le v e l &
s u b le v e l)

A re a , A c t iv it y
a n a ly s is ,C r it q u e
o n b ro w n p a p e r
M CS
Id e n t ifi c a t io n o f
k e y c o n t rib u t o r s
in v a r ia n c e .
M e a s u r in g k e y
p ro c e s s
in d ic a t o r s ( S P C )
In t e r v ie w in g ,
b ra in s t o rm in g ,
RCA
P ro c e s s M a t u r it y
& S y s te m
E ff e c t iv e n e s s
s t u d ie s

R e fi n e /D e v e l
o p S t a n d a rd s
& K P Is
W h it e P a p e r
P ro d u c t io n
MCS
D ry ru n
D e v e lo p
Te r m s o f
R e f e re n c e ,
a g e n d a e tc .
fo r re v ie w
m e e t in g s

R u n t r a in in g
w o rk sh o p s
In s t a lla t io n
of M CS and
re v is e d
p ro c e s s e s
Im p le m e n t
and cascade
in itia t iv e s
P ro d u c tio n
re v ie w
m e e t in g s
R e v is e
S O P s , S T S

S y ste m
A u d it
S y s te m a n d
e ff e c tiv e
m e e tin g
a u d its
in c lu d in g
nonc o m p lia n c e
re p o r t in g
A n a ly s is o f
a u d it s c o re s

Implementation Phase
KPI based operational scorecard for each MAT will ensure continuous improvement
in operational Performance for the entire business.
Standard Operating Procedures (SOPs) detailing new systems and streamlined
processes are handed over to respective process owners to ensure sustainability.
The audit system procedure has been developed to ensure the system elements.

GPIL, Raipur, Confidential

Page 31

GPIL, Raipur, Confidential

Page 32

Standard Operating Procedures Process, Maintenance and Quality


Shift Handover Report
Objective

Systematic handover of work responsibility between two shifts in charges


to ensure proper coordination between incoming and outgoing shift in
charge
Responsibility

Annotated Format RACI Shift Handover

Frequency
Every Shift changeover
Procedure

Below is the diagrammatic representation of shift handover process

GPIL, Raipur, Confidential

Page 33

Annotated Process Flow Shift Handover Report

Shift Handover Report (Format)


Common Shift Handover has been implemented in SMS, wherein shift in charge of
production, maintenance, CCM, quality and RM will meet and carry out handover take over
process

Shift Handover Report

GPIL, Raipur, Confidential

Page 34

A
B

H
C

I
E

J
F

Shift Details:
A. Mention Plan vs Actual Production and actual KWH/MT
B. Mention % scrap added
C. Mention % PI added
D. Any deviation in carbon bath sample and corrective action taken
E. Any major issues in the shift pertaining to furnace, CCM or safety
F. PM done or to be done in next shift
G. Signature of incoming Shift in charge
H. Any critical observation related to quality, Raw material or communication to incoming
shift in charge
I. Any breakdown or breakout issues in CCM and corrective action taken
J. Status of daily PM of CCM
K. Signature of Out going Shift in charge

GPIL, Raipur, Confidential

Page 35

Implementation Production and Planning Systems


Daily Review Meeting
Objective
Proper co-ordination between individual department (Mechanical, Electrical, Process, &
Quality), Improve Productivity, Establish Standards, Reducing Shutdown and breakdown, &
Improving Yield
Responsibility
RACI

Annotated Format RACI Review Meeting

Frequency
Every Day
Procedure

Explanation and Information flow. Kind of a process flow diagram.

GPIL, Raipur, Confidential

Page 36

HOD - SMS

HOD
Operation
Operation
Head

Electrical
Head

Preparation of
Action Log

GPIL, Raipur, Confidential

Maintenance
Head

Action Log

Page 37

Quality
Head

Corrective
Action

Annotated Process Flow Daily Review Meeting

Annotated Terms of Reference Daily Review Meeting

Terms of Reference

Daily Production and Maintenance Review Meeting SMS

Time:

11:00 AM to 11:30 AM

Duration:

30 minutes

Location:

Office of Sr. Vice President

Frequency: Daily

Objective:

Improve Productivity
Reduce Shutdown and breakdown
Reduce Power consumption per Metric Ton
Improve Quality

Attendees:

Operations Head Furnace

GPIL, Raipur, Confidential

Page 38

Operations Head - Caster


Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head

Agenda:

Review of previous action logs and taking corrective action for deviations
Plan Vs actual Production and Productivity
Raw material consumption for charge Mix
Power consumption per Ton
Daily production and plan
Allotment of RCA for major loss, breakdown and quality deviation
PM plan Vs Actual
Availability of raw material
Releasing equipments for PM
Specific consumption

Inputs:

Production Plan Compliance


Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report
Breakdown management system
RCA Policy
PM Plan

Outputs:

Action Log

GPIL, Raipur, Confidential

Page 39

Terms of Reference

Weekly Production and Maintenance Review Meeting SMS

Time:

3:00 PM to 4:00 PM

Duration:

1 Hour

Location:

Office of Sr. Vice President

Frequency: Weekly

Objective:

Improve Productivity
Reduce Shutdown and breakdown
Reduce Power consumption per Metric Ton
Improve Quality

Attendees:

Operations Head Furnace


Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head

Agenda:

Review of previous action logs


Plan Vs actual Production and Productivity. Corrective action for any deviation
Raw material consumption for charge Mix
Power consumption per Ton
Daily production and plan
Allotment of RCA for major loss, breakdown and quality deviation
PM plan Vs Actual
Availability of raw material

GPIL, Raipur, Confidential

Page 40

Breakdown and uptime of equipments


Conversion cost, Actual Vs Plan

Inputs:

Production Plan Compliance


Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report
Breakdown management system
RCA Policy
PM Plan

Outputs:

Action Log

Terms of Reference

Monthly Production and Maintenance Review Meeting SMS


Time:

3:00 PM to 4:00 PM

Duration:

1 hour

Location:

Office of Sr. Vice President

Frequency: Monthly
Objective:

Improve Productivity
Reduce Shutdown and breakdown
Improve Power consumption per Metric Ton

GPIL, Raipur, Confidential

Page 41

Improve Quality

Attendees:

Operations Head Furnace


Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head

Agenda:

Review of previous action logs


Plan Vs actual Production and Productivity
Raw material consumption for charge Mix
Power consumption per Ton
Monthly PM compliance and plan for next month
Breakdown review, RCA and CAPA status
Monthly breakdown management system and Bad actor list
Availability of raw material
Safety Review - CAPA on near miss and incident
Quality deviations
Udaan system compliance
Conversion cost

Inputs:

Production Plan Compliance


Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report
Breakdown management system
RCA Policy
PM Plan

Outputs:

Action Log

Annotated Process Flow Daily Review Meeting

GPIL, Raipur, Confidential

Page 42

Purchase Focus Group Discussion


Objective:
Proper co-ordination of Purchase Department & SMS Department to ensure that the critical
spares and production consumables are available in time. Discussions between Purchase
and SMS Department also ensures that the other issues are surfaced and thereby resolved.
It also ensures that the SMS team plans for the spares in a proper timely and a phased
manner.
Responsibility:
Representatives from SMS Team and Purchase Team

Terms of Reference

Purchase Focus Group Discussion SMS


Terms of Reference

Time:

03:00 PM to 03:30 PM

Day:

Saturday

Duration:

30 minutes

Location:

Office of Sr. Vice President

Frequency: Weekly

Objective:

Streamline Purchase activities


Reduce instances of material stock out situation
Reduce slow moving inventory
Improve Quality of material purchased

Attendees:

Operations Head Furnace


Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head

GPIL, Raipur, Confidential

Page 43

Manager and Deputy Manager - Production


Quality Head
Purchase Manager
Purchase - HOD

Agenda:
Review of previous action logs
Review status of open POs and PRs
Review vendor performance
Concern pertaining to quality of material
Inputs:

Details of POs and PRs


Material quality report
Vendor list

Outputs:

Action Log

Annotated Terms of Reference Weekly Purchase meeting

Frequency:
Weekly once

Procedure:
SMS
Chairman

GPIL, Raipur, Confidential

Page 44

Action Log

Preparation of
Action Log

Follow up of
critical items

Spares
Received
Annotated Process Flow Production Loss Book

Annual Preventive Maintenance Program Review


It is a tool to assess the adequacy of existing maintenance program, incorporate new
machines and lesson learnt,
Objective:

To optimize the maintenance program with available resource and downtime target.

Responsibility:

GPIL, Raipur, Confidential

Page 45

Annotated Format RACI - Preventive Maintenance Program Review

Frequency:

Preventive maintenance program is reviewed every year in the month of March

Procedure:
Annotated process flow: Procedure for Preventive Maintenance Program Review

GPIL, Raipur, Confidential

Page 46

An annotated format for equipment criticality ranking is outlined below

A. Enter the serial number


B. Enter the name of the equipment e. g. Furnace 15 T, 5.5 MW
GPIL, Raipur, Confidential

Page 47

C. Enter the weighted average score from the equipment criticality ranking review
D. Write whether PM exists, Yes/No
E. Write PM frequency in months
F. State whether we have checklist for PM, Yes/No
G. State whether we are doing maintenance as per checklist, Yes/No
H. State whether we are doing maintenance as per checklist, Yes/No
I.

Remarks, if any

J. List down the actions identified to close the gaps


K. Name of the person who is responsible to close the actions
L. Date by which actions should be completed. This date must be agreed with the person
responsible

Annual Preventive Maintenance Schedule


A structured approach to prepare and track the preventive maintenance of each equipment.
Objective:

To ensure timely completion of planned maintenance

This also serves as master list of equipment under maintenance

This also gives the visibility of maintenance due in future so that advance planning and
preparation can be done to execute the due maintenance jobs on time
Responsibility:

Annotated Format RACI - Preventive Maintenance Schedule


Frequency:

Daily, Weekly, Monthly, Quarterly and yearly

GPIL, Raipur, Confidential

Page 48

Procedure:

Annotated process flow : Procedure for Preventive Maintenance Schedule

GPIL, Raipur, Confidential

Page 49

Standard Checklists

GPIL, Raipur, Confidential

Page 50

GPIL, Raipur, Confidential

Page 51

Breakdown Slip
Objective:
1. This is the first document generated for any breakdown observed in operation. It will
initiate the corrective action from maintenance/operation department to rectify the
problem at the earliest.
2. The work against breakdown slip will be carried out by technician or can be outsourced
to the contractor. The data in the breakdown slip will form the primary information for
breakdown

management

system.

This

document

registers

and

communicates

breakdowns occurring in machines.

Frequency:

Annotated Format RACI Breakdown slip

As and when the breakdown happens

Procedure:
1. Breakdown of the equipment occurs on site
2. Once the breakdown occurs, shift engineer (operations) informs the shift engineer
(mechanical and electrical maintenance)
3. He fills the relevant entries in the breakdown slip (before attending the breakdown)
such as breakdown start time, machine on which the breakdown has occurred and
problem description, section, date, shift etc.
4. The maintenance team arrives at the site and discuss regarding the issue
5. Details during the breakdown are written in the slip by the maintenance team (job
start time, response time, root cause for breakdown etc.)
GPIL, Raipur, Confidential

Page 52

6. Repair or replacement job is complete and plant starts


7. Operation & responsible department having breakdown meets and fills the remaining
details of the breakdown slip (after attending the breakdown) such as job end time,
equipment handover condition etc.
8. Respective section heads (operations and maintenance) review and sign the
breakdown slip
9. Breakdown slip is sent to the IT person and details are entered in Breakdown register

GPIL, Raipur, Confidential

Page 53

Annotated Process Flow Breakdown Slip

Breakdown Slip (Format)

GPIL, Raipur, Confidential

Page 54

C
B

E
F
Annotated Format Breakdown
Slip

A. Basic Details: Mention the basic details such as section, date, shift
B. Before attending the breakdown: Mention the details such as breakdown start time,
machine on which breakdown has occurred, problem description
C. During Breakdown: Mention the activities done during the process of resolving the
breakdown (job start time, response time, reason for delays, team attending the
breakdown, root cause of the breakdown)
D. After attending the breakdown: Mention the details of activities post repair or replacement
by the maintenance team (job end time, equipment handover condition, details of the job
done on the equipment, spares used.
E. Remarks: Enter remarks, if any
F. Signoff: Sign-off by the staff and section heads (maintenance and operations team)

Breakdown Management System


Objective:
1. Enter the details of the breakdown slip in soft form. Conduct analysis of the data
weekly and monthly and send across to the concerned stakeholders for review and
action
2. Review frequency of equipments, mean time taken to repair, cases of feed loss
3. To provide relevant information related to bad actors so that the list can be looked into
and revised, if needed

GPIL, Raipur, Confidential

Page 55

Responsibility:

Procedure

Breakdown Management System (Format):

D
E

Annotated Format Breakdown Management System

A. Basic Details: Mention the basic details such as section, date, shift, slip no

GPIL, Raipur, Confidential

Page 56

B. Before attending the breakdown: Mention the details such as breakdown start time,
machine on which breakdown has occurred, problem description, breakdown category
C. During Breakdown: Mention the activities done during the process of resolving the
breakdown (job start time, response time, reason for delays, team attending the
breakdown, root cause of the breakdown)
D. After attending the breakdown: Mention the details of activities post repair or replacement
by the maintenance team (job end time, equipment handover condition, details of the job
done on the equipment, spares used.
E. Remarks: Enter remarks, if any

1. Production shift in charge will call maintenance staff to attend the breakdown
2. Maintenance staff will assess the situation and inform the production shift in charge
about the expected time to repair the machinery
3. In case repair time is more than 15 minutes, production personnel will raise
breakdown slip
4. On repair maintenance staff will fill the necessary details on the breakdown slip
5. Production personnel verify the repair work and acknowledge same by counter
signing on the slip
6. Manager Maintenance will review the slip on the next day
7. Manager Maintenance captures the details from slip to excel sheet.
8. Manager maintenance to carry out analysis of MTTR, % uptime from the excel sheet
9. In case breakdown does not lead to production loss or equipment belongs to utility,
maintenance personnel will raise and close the breakdown ensuring all details are
captured in the slip.

Explanation and Information flow. Kind of a process flow diagram.

GPIL, Raipur, Confidential

Page 57

Is breakdown resulted in
production loss

Maintenance
shift in charge
No

Raise the
breakdown in the
slip

Yes
Production shift
in charge

Raise the
breakdown in
the slip

Resolving
Breakdown

Breakdown slip

GPIL, Raipur,
Confidential
entered in
PC

Page 58
Report of
analysed&
Analysis
HOD
ReviewMTTR
& do
& corrective
MTBF,
%
Uptime
analysis
Closing
action
to be
done
by Engineer
breakdown
slip

GPIL, Raipur, Confidential

Page 59

Below is sample analysis


Breakdown Analysis - Dec'14
Breakdown(Min.) - Crane 06
CT Motor Fault

CT Power contac tor is sue


60
70

Magnet cable cut

Min.

195

900
800
700
600
500
400
300
200
100
0

850

835

120%
100%

79%

475
68%
360
53%

220

27%

80%
60%
205

170

70

40%
20%
0%

120

LT W heel problem

Breakdow n time(Min.)

Break down (Min.) - Furnac e 10

115

4020

675

Bus bar sparked

SCR Fault

Pow er cable leakage

Sparking

Breakdown(Min.) - Crane 05

55

Load gear shaft damaged

45

30

Contactor broken

Magnet cable cut

705

GPIL, Raipur, Confidential

Page 60

Master controler lock broken

Line Walk
Objective:
1. Line walk is a systematic way to identify abnormalities through observations (LLF: Look,
Listen, Feel) through a daily walk in the plant area. First-hand information/observation
provides great insights into the current state of various equipment and the plant
environment.
2. This system can potentially improve the plant reliability as it reduces the forced
deterioration of the equipments which are major causes of failures. The abnormalities
found can be rectified immediately by the observer or can be forwarded to maintenance
planner for further planning.
3. Line walk summary sheet is used to register observations during a line walk on the shop
floor. Line walk sheet is divided into CBM (Condition based maintenance), 5S and Safety
NMS.

Responsibility:

Frequency:
As per the line walk schedule
Procedure:
Below is the diagrammatic representation of Line Walk system and how it is followed:

GPIL, Raipur, Confidential

Page 61

Annotated Process Flow Line Walk

Line Walk: Format

Below is the line walk format and its description

GPIL, Raipur, Confidential

Page 62

B
C

E
D

A
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.

Basic Details: Mention the basic details such as line walker name, date and designation
Department and Section: Mention the department name and section
Equipment Name: Please mention the equipment name on which line walk was done
Code: It is essentially the category code (under which category it lies) such as 5S, safety,
condition based monitoring, spillages/leakages etc.
Observations: Mention the observation of the line walker
Priority Level: Please mention the priority level (low/medium/high)
Actions Required: Mention the desired actions that need to be taken
Responsibility: Person responsible for taking the action
Target Date: Target date by when the action needs to be completed
Status: Updated status of the activity (delayed, in progress, completed, to be taken in
shutdown)

Root Cause Analysis


Objective:
1. The purpose of Why Why Analysis/ (Root Cause Analysis) (RCA) is to identify reasons
why reactive maintenance is occurring and to instigate appropriate steps to eliminate the
root causes. The fundamental message is that: If a business does not have a Root

GPIL, Raipur, Confidential

Page 63

Cause Analysis (RCA) methodology, the business will remain in a fire fighting (reactive)
mode.
2. This will be conducted as a tool to arrive at a root cause in a cross functional
(Maintenance and Production) manner as and when a breakdown occurs. The action
plan will be made for correcting the problem identified which will have both a short term
and a long term plan. The action plan will be reviewed in the weekly meeting for
correctness and horizontal deployment.
Responsibility:
Below is the snapshot of RCA policy which should be followed for conducting a RCA. It gives
the information on the team representation for RCA, criteria for conducting the RCA, owner
of the RCA, lead time in hrs for first draft of RCA preparation

Frequency:
As per the RCA policy
Procedure:
Below is the diagrammatic representation of the process flow for carrying out a RCA.

GPIL, Raipur, Confidential

Page 64

RCA Template (Format):


Below is the format for the RCA (root cause analysis)

GPIL, Raipur, Confidential

Page 65

A.
B.
C.
D.

Problem Statement: Mention the problem statement on which RCA needs to be done.
1st Why: Mention the first element of the root cause which could have led to the problem.
2nd Why: Mention the second element (2nd why) that led to occurrence of 1st Why.
3rd Why: Mention the third element (3rd why) that led to the occurrence of 2nd Why. Follow
the steps along with findings/data to eliminate the probable causes and arrive at a root
cause

GPIL, Raipur, Confidential

Page 66

E. Actions taken / identified: Actions taken in the form of corrective and preventive actions.
While mentioning the CAPA, please make sure that the expected date of completion for
corrective and preventive action is mentioned
F. Members name: Mention the name of the members doing the RCA and sign off

Production Deviation sheet


It is a tool to capture actual production and highlight deviation against the target. Further to
this, losses are categorized under various heads such as production loss, loss due to power
shortage, loss due to breakdown loss.
Objective:

Tool to provide details of deviation against target production and category of losses
Responsibility:

Annotated Format RACI Production Deviation sheet

Frequency:

Daily

Procedure:

GPIL, Raipur, Confidential

Page 67

Format 1: Procedure for completing the document

MIS Manager will


collect documents
such as production
log sheet,

MIS Manager
enters the
details in the
deviation sheet

HODs
review for
corrective
action

An annotated format for Production deviation sheet is outlined below

PRODUCTION DEVIATION SHEET

GPIL, Raipur, Confidential

Page 68

A : Mention plan for power availability


B: Mention actual Heat achieved, total production of furnace 1-10, total power consumption
by furnace only and specific power consumption without auxiliary
C: Mention actual power consumed, Power export and specific power consumption with
auxiliary. Particular cell will be highlighted red if SPC is greater than target value and green if
SPC is lesser than target value
D: Mention following details for furnace 6 -10
i)
ii)
iii)
iv)
v)
vi)
vii)

Target production
Target KWH/MT
Target heat
Actual heat achieved
Actual production
Actual Power consumed
Actual KWH/MT

E: Mention Losses such as loss due to furnace /crane breakdown, loss due to CCM. Loss
due to shortage of power and hidden loss will be calculated on its own
F: Mention charge mix i.e. Scrap and PI

GPIL, Raipur, Confidential

Page 69

G: Mention chemistry of ore, pellet and Mix


H: Mention monthly PM of furnace and cranes

Before casting checklist


Objective
To standardize the checks done before carrying out casting on CCM. Also this would ensure
that all CCM is in desired condition to carry out casting of one campaign without any issue
Responsibility

As per RACI

Frequency
Before casting

Checklist

GPIL, Raipur, Confidential

Page 70

Implementation Production and Planning Systems


Comprehensive Production Log sheet
Objective
To provide standard values of parameters required to be followed in a recipe for producing
molten metal
To capture actual parameters and charge mix added in the recipe
Responsibility

GPIL, Raipur, Confidential

Page 71

RACI

Annotated Format RACI Production log sheet

Frequency
Every Day
Procedure
Production log sheet has standard values of the parameters, which are must to be followed
during melting process.

GPIL, Raipur, Confidential

Page 72

** Post installation of liquid metal weight measurement system, actual figure of


production per heat to be noted in the log sheet.

Melter will refer to these values while preparing recipe in a furnace.


A: Mention the plan for number of heat, production, PI and scrap
B: Mention pan for Simn, KWH/MT, coke and ladle preheat temperature
C: Mention standard value of furnace temperature, Pit side temperature of transfer ladle
and slide gate ladle, CCM temperature
D: Mention furnace life and its condition
E: Mention start and end time of heat
F: Mention actual consumption of scrap and PI
G: Mention actual temperature of empty ladle, furnace temperature and filled ladle
temperature
H: Mention actual value of frequency and voltage
I: Mention load ramp up values at 30 minutes, 1.5 hours and 2.5 hours
J: Mention production data. After installation of molten metal weighing system actual
value of production to be mentioned
K: Mention actual KWH and KWH/MT
L: Name and signature of shift manager
M: Signature of melter and in remark column any special communication which led to
deviation from standard values

Steps to be followed:

GPIL, Raipur, Confidential

Page 73

1. Melter will charge scrap into furnace as per the plan mentioned in the log sheet.
Melter will also mention whether he has used charge basket for charging. Melter will
also mention the start time of the furnace
2. Melter then add PI and DRI as per the plan given by the production planner
3. Melter then follow the process of adding DRI and remove slag subsequently.
4. Melter will write power ramp up value of furnace at 30 minutes and he will repeat
same exercise after 1.5 hour and 2.5 hour.
5. Melter will provide details of furnace frequency, voltage in the log sheet
6. Melter will also mention amount of SiMn added in the recipe. For this he will refer to
the standard value given at the top of the log sheet. For any deviation he will consult
shift in charge and mention in remark column
7. Melter then mention empty ladle temperature taken through temperature gun and
ensure same is as per the standard value mentioned in the log sheet.
8. Melter will then take the furnace temperature and if same is in the standard range, he
will tap it into the ladle
9. Melter will then monitor fill ladle temperature (pit side) and same must adhere to the
standard. In case of any issue with the temperature he will consult shift supervisor
and CCM in charge and take necessary action and mention same in the remark
column.
10. At the end he will mention end time of the process and production as per reading
shown by load cell in the crane and mention unit of power consumed.
11. Melter then signs against his column.
Later in a shift, shift supervisor and manager will check the log sheet for any deviation.
Necessary action to correct issues like high KWH/MT, cycle time, Si-Mn, load ramp up will be
taken and they signed against their name.
Same process to be followed in the next shift.
Next day Production AGM and GM production will analyse the sheet for any deviation
against the target and initiate corrective and preventive action.

Equipment Criticality Ranking


Objective:

1. To rank the equipments in order of the criticality.


2. Based on the criticality of the equipments, maintenance planning (PM, line walk) can be
modified to suit the equipments (highly critical to be given more importance and
attention)
3. Also, based on the criticality, critical spares can be identified and min-max levels along
with consumption planning can be done accordingly.
Responsibility:

GPIL, Raipur, Confidential

Page 74

Below is the RACI for preparation and review of Equipment Criticality Ranking

Annotated Format RACI Equipment Criticality List

Frequency:

Prepared once and reviewed yearly or in case of installation of new equipment

Procedure:

GPIL, Raipur, Confidential

Page 75

Equipment Criticality Ranking (Template):

Below is the sample snapshot for equipment criticality ranking sheet

GPIL, Raipur, Confidential

Page 76

** All pressure and temperature gauges to be calibrated once in a year or on need basis.
However critical gauges to be calibrated once in six month

A.
B.
C.
D.
E.

Plant: Plant in which these equipments and sub-equipment are installed


Equipment Tag No. : Equipment tag number to be mentioned
Description: Equipment description such as name, make and rating to be mentioned
Maintenance interval to be maintenance such as yearly, monthly
Criticality Criteria: Rankings has to be done from (0-5, 5 being the highest and 0 being
the lowest). Rankings have to be given by operations, maintenance, quality and spares
availability)
F. Overall Weightage: 25% weightage is given to all the four departments rankings
(operations, maintenance, quality, safety). Based on the weighted average, one score is
calculated
G. Sections ranking: Based on the overall weightage, section ranking is calculated

Quality Checklist - Quality Gate


Objective
Quality gate is a system which is aimed at identifying problem and stopping at that at the
stage of identification so that it does not lead to bigger problem at later stage of a process.
Based on this philosophy we designed quality gate templet for the molten metal by checking
quality parameters of batch sample of a heat.
Responsibility

GPIL, Raipur, Confidential

Page 77

Format :

Procedure:
1. Once first batch pool is ready, melter will send the sample to quality lab. Quality lab
person then checks the sample for carbon value and mention same on the sheet
along with the standard range.
2. Helper carries this sheet back to melter, who will check the sheet for carbon value. In
case carbon value is not in the standard value, he will consult shift supervisor to
lower the carbon and keep it within range
3. Melter will again send second bath sample to quality along with the quality checklist.
GPIL, Raipur, Confidential

Page 78

4. Melter will refer to the standard values against each bath sample and correct the
value before sending the molten metal to CCM
QC Checklist in Production
Objective:

1. To capture the actual heat parameters


2. To review these parameters against the standard and take necessary corrective action
Responsibility:
Below is the RACI for the same

Frequency: Daily

Format:

Sequencing between furnace and caster


Objective:
1. To have effective sequencing plan, which would result in subordination of CCM to
furnace
2. To have sufficient time between campaign for daily caster maintenance
3. Utilization of CCM and associated consumables at fullest to ensure reduction in cost

GPIL, Raipur, Confidential

Page 79

Responsibility:
Below is the RACI for the same

Sequencing Plan:

Sponge Pellet and ore Requirement Vs Fulfilment


Objective:
1. To streamline planning of pellet and ore requirement

GPIL, Raipur, Confidential

Page 80

2. To establish service level agreement between SID and SMS departments


Responsibility:
RACI for the same is as below :

Format

A
B

A: Date to be mentioned
B: Pellet chemistry and quantity to be mentioned
C: Fines chemistry and quantity to be mentioned
D: Iron ore chemistry and quantity to be mentioned
E: Remark for any deviation
F: This to be filled by SID

Operational Benefit Tracker and KPI Dashboard


Objective:

GPIL, Raipur, Confidential

Page 81

3. To review plan vs actual KPI achievement daily and week on week basis
4. To ensure that the gaps in achieving the target production are reviewed stringently and
action are taken to resolve the issues preventing the plant to achieve the desired KPI
Responsibility:
Below is the RACI for operational benefit tracker and KPI Dashboard
RACI-Operational Benefit tracker and KPI Dashboard

Frequency:

Data Updation: Daily


KPI dashboard generation and performance review: Weekly

Procedure:
Below is the process flow for Operational Benefit tracker and KPI dashboard

GPIL, Raipur, Confidential

Page 82

OOperation
p e ra tio n
s team
te a m to
to
pprovide
ro v id e
ddaily
a ily
pproductio
ro d u ctio
nn
aachieved
ch ie v e d
aand
nd
re
a so n s
reasons
fo
ed
forr fe
feed
lo
ss,
loss, if
aany
ny

M
a in te n a n
Maintenan
ce
a m to
ce te
team
to
pprovide
ro v id e
in
fo on
on
info
fe
e d lo
ss
feed
loss
ddue
u e to
to
bbreakdow
re a k d o w
nns,
s, aaction
ctio n
ta
ke n ,
taken,
RRCA
C A etc.
e tc.

QQuality
u a lity
tea
m to
to
team
pprovide
ro v id e
ddata
a ta wrt
w rt
qquality
u a lity
pparameter
a ra m e ter
s su
ch as
as
such
Fe
(t), LOI
LO I
Fe(t),
(%
),
(%),
bblaine
la in e etc.
e tc.

RRecord
e co rd
th
a ta
thee ddata
in
th e
in the
te
m p la te ,
template,
ppopulate
o p u la te
th
PI
thee KKPI
ddashboard
a sh b o a rd

RReview
e v ie w
th
PI
thee KKPI
ddashboard
a sh b o a rd
w
e e k ly,
weekly,
ta
ke
take
aactions
ctio n s
aand
nd
sig
n o ff
signoff
th
thee
ooperation
p e ra tio n
aall bbenefit
e n e fi t
tra
cke r
tracker

Operational Benefit tracker and KPI Dashboard (Template):

First Sheet: Below is the snapshot of the first sheet of the template. Same template is
followed for both the Pellet Plants (0.6 MTPA and 1.5 MTPA)

A. Project Week: Mention the project week


B. Date: Mention the date for which production is being tracked
C. Baseline and target production: The cells refer to the baseline production, avg. ball mill
feed % Fe(t) during the baseline period and target production
D. Actual production details: Mention the actual ball mill feed Fe(t) %, baseline LOI %,
actual LOI % and reported production
E. Production improvement: Tracks the target incremental daily tonnage against the actual
achieved incremental daily tonnage

Second Sheet: Below is the snapshot of the second sheet of the template (weekly tracker)
C

D
B
A

GPIL, Raipur, Confidential

Page 83

A. KPI: Mention the KPI being tracked


B. KPI details: For each day, baseline production, target production, actual production,
operational benefit, remarks for exclusion if any are being tracker
C. Week no and its details: Mention the week no and the dates in the particular week
D. Cumulative data for the week: Mention the cumulative production for the week after
exclusions
E. Remarks: Mention the details of the exclusion because of which the day is not taken in
the operational tracker
F. Exclusion: Mention the exclusion code because of which the day is not taken in the
operational tracker such as Planned shutdown, forced shutdown, issues faced in other
departments hampering SMS Plants production, power supply failure etc.

Third Sheet: Below is the snapshot of the third sheet of the template (overall weekly tracker)

Fourth Sheet: Below is the snapshot of the KPI dashboard

GPIL, Raipur, Confidential

Page 84

KPI dashboard contains:


1) Production Furnace 6-10 and furnace 1-5. Red bar shows that production is below
target and green shows production above the target value
2) KWH/MT Furnace 6-10 and furnace 1-5. Red bar shows that KWH/MT is above
target and green shows below the target
3) Loss due to power, breakdown and production inefficiency
4) Productivity MT/Heat
5) Percentage heat achieved

Process Standard operating procedure (SOP)


Objective:

GPIL, Raipur, Confidential

Page 85

To standardize the process i.e melting process, casting process, ladle preparation
Responsibility:
RACI has been defined in the SOP and same to be followed

SOPs :
1.
2.
3.
4.
5.
6.
7.

SOP for Ladle


SOP for melting process
SOP for quality
SOP for tundish
SOP for CCM
SOP for coil insulation
SOP for attaining higher life of Ladle

Daily Caster Maintenance Checklist


Objective
1. To standardize the checks on Caster
2. To avoid breakdown in caster
Responsibility:
Below is the RACI for daily caster maintenance checklist

GPIL, Raipur, Confidential

Page 86

Format :

GPIL, Raipur, Confidential

Page 87

A : Mention date and shift in which checks were carried out


B: Checks, which are to be referred
C: Standard parameters against which checks to be mapped
D: Status of the equipment to be mentioned
E: Remark to be mentione din case of any deviation
F: Concerned person needs to sign on the sheet
Process quality checks
Objective:
1. To meet quality parameters as per BIS
Responsibility:
RACI for the same is as below:

GPIL, Raipur, Confidential

Page 88

Format :

GPIL, Raipur, Confidential

Page 89

Procedure:
A: Mention heat number
B: Mention campaign number
C: Mention furnace number
D: Mention tapping time
E: CCM on which casting done
F: Mention chemistry in terms of % Carbon, % Mn, % Si, % Sulphur and % Phosphorous

GPIL, Raipur, Confidential

Page 90

Inventory Tracking
Objective:
1. To ensure smooth supply of raw material and avoid stock out situation
Responsibility:
Below is the RACI for the inventory tracking

GPIL, Raipur, Confidential

Page 91

Format

Tool Box standardization and Audit


Objective:
1. To ensure right tools are available and to avoid time wastage in searching tools
Responsibility:

GPIL, Raipur, Confidential

Page 92

RACI for the Tool Box standardization and audit

GPIL, Raipur, Confidential

Page 93

Format

Bad Actor list


Objective:

1. To identify the bad actors affecting production (feed loss or plant hold) with frequent
breakdowns/failures
2. To take actions on the bad actors and do probable cause analysis to resolve the issues
3. Reduction in failures of major equipments would reduce spares consumption/MT

GPIL, Raipur, Confidential

Page 94

Responsibility:

Below is the RACI for Bad Actor list preparation and probable cause analysis

Frequency:

Breakdown management system analysis: weekly and monthly


Bad actor list review: Monthly

Bad Actor List (Snapshots):

Procedure:
GPIL, Raipur, Confidential

Page 95

Below is the procedure for Bad Actor list preparation

PPerform
erfo rm
BBreakdow
re a k d o w
nn
MManagem
a n a g em
eent
nt
sy
ste m
system
aanalysis
n a ly sis

PPreparatio
re p a ra tio
nn of
o f BBad
ad
aactor
cto r list
bbased
a se d oonn
th
thee
BBreakdow
re a k d o w
nn
m
anagem
managem
eent
nt
sy
ste m
system
aanalysis
n a ly sis

RReview
e v iew
aand
nd
aapprove
p p ro v e
th
bad
thee bad
aactor
cto r list

Ta
ke
Take
aactions
ctio n s oonn
th
ad
thee bbad
aactors
cto rs or
or
co
n d u ct
conduct
RRCA
C A oorr
pprobable
ro b a b le
ca
u se
cause
aanalysis
n a ly sis

RReview
e v ie w
aand
nd
uupdate
p d a te
th
ad
thee bbad
aactors
cto rs
m
o n th on
on
month
m
o n th
month

Sustainability Phase
The System Audit is a tool to verify that all the appropriate system elements are
being installed and to check that they continue to be pursued.
For the purpose of the audit, every single component of a system is listed three times
and is interrogated in different ways to assess the overall status of implementation.
The four states that are taken into account are:
S1 Compliance
S2 Understanding
S3 Usage
S4 Culture
Only the first three states of this model are measured since the Culture state
already represents full ownership of the system.
S1: Compliance. The system element has been introduced and it is being used by
ensuring compliance. Direct supervision is required. After a few weeks no element
should have a pending S1 status unless a very good reason is available.

GPIL, Raipur, Confidential

Page 96

S2: Understanding. The system element is being used, but people in question do
not see yet the whole benefit of using the element. If the review process was taken
away system elements usage would probably stop. Short interval controls and
review process are vital to ensure continuous compliance through proactive
coaching.
S3: Usage. People now realize the whole benefits of the system and how to use it to
improve their performances. But they still see it as a new system and need support.
S4: Culture. Having complied with and understood the purpose of the systems,
people now own it. The full benefits are derived and modifications / improvements
may also be volunteered. It can be assumed that the system element will continue to
be used. At this stage the management can begin to rely on delegation of system
elements rather than any direct review or supervision. In this manner the risk of
having elements dropped out is minimized as the ownership will not be lost or would
be tackled at an inappropriate management level.

Step by Step Instructions


Please find below following key guidelines:
Audited by the name of the manager who conducted the latest audit.
A position that is being audited should be captured as appropriate.
Status and Score the sheet is divided into 3 status sections. The scoring method is
also indicated here.
Audit Level Number S1, S2, S3
System Element each system element is listed out under each section.
Target the person/position to which the auditor should focus their investigation
Engineer, Sr. Engineer, Manager, Sr. Manager, AGM, DGM
Section In charge
Shift In charge
Supervisor
Questions Questions that need to be asked to audit the behavioural changes.
Score under each status the score, 0, 1 or 3 is indicated:
GPIL, Raipur, Confidential

Page 97

S1: Use score 0 for not installed, not correct. Use score 1 for installed and partially
correct. Use score 3 for installed or completely correct.
S2 and S3: Use score 0 for not correct. Use score 1 for partially correct. Use score 3
for completely correct.
These cells auto-format red for score 0, yellow for score 1, green for score 3.
P.S: If a category is not applicable then leave the cell blank so it will not be counted
as 0.
Weekly scores would be measured. For the system elements the audit is conducted
on Daily basis, the Weekly Score will be the arithmetic average of Daily Scores
Total Score the total score divided by the maximum possible score expressed as a
percentage.
Question for S2 and S3 in place of actions the audit questions should be closed
ended questions.
These questions should be updated on Quarterly basis in order to ensure overall
system adoption.

Annotated Format: Audit Template


Annotated Format: Audit Result

The audit scores must be reviewed on a weekly basis until a performance of S1


ninety percent (90%) S2 eighty percent (80%) and S3 seventy percent (70%) are
achieved. Until these performance levels are attained, the system is not fully installed
and or in use. It is the responsibility of the associated Management Action Team

GPIL, Raipur, Confidential

Page 98

(MAT) to identify any relevant problems/issues and initiate actions to resolve this as
quickly as possible.

GPIL, Raipur, Confidential

Page 99

Appropriate Management Styles


In line with the Leader Behaviour Analysis Model, the outcome of the audit helps
dictate the kind of actions that are required see table 1 for details.
Table 1: Appropriate Management Styles
Stat
e

System
Adoption

State of Mind

Appropriate
Management
Style

Required Contact Time

S1

Compliance

Unaware and
unable

Direct

Full time or very high increase


attention if score is low or falls
back.

S2

Understandin
g

Aware and unable

Coach

Significant time focus on


assurance and positive feedback.

S3

Usage

Aware and able

Support

Moderate as S1 and S2 scores


stabilize step back from direct
involvement as much as possible.

S4

Culture

Unaware and able


(taken for
granted)

Delegate

Minimal

All action logs should contain the appropriate type of activities to ensure that the
issues faced with any one particular element are addressed. Examples:
If a previously installed element has completed dropped from usage, people need to
be told exactly why this is wrong and what they must do (directive).
If an installed element is not being filled out correctly, you should get the appropriate
owner to go and invest significant time and detail in understanding why it was not
filled out and making sure that the user understands how to use it correctly (coach).
If the actions coming out of a meeting are not as good as they should be then the
appropriate area owners need encouragement and support to build on the current
status.
If the system is not throwing out any concerns under S1, S2 and S3 then the results
should be coming through. In this case the amount of time invested in the review
process can be lessened.
Responsibility and Frequency
The Audit must be conducted on all MCS elements at least once a week. In the initial
stages of roll-out audits will be conducted once per week by the consultants as well
as the taskforce members assigned and results will be forwarded to the MAT for
GPIL, Raipur, Confidential

Page 100

review. In later stages the Team Leaders will be responsible for conducting the audit
for their Team on all the MCS elements and forward it to their Department Head as
well as to an auditor outside the concerned Department. Results will be reviewed
both at the MAT meeting and Steering Committee.

GPIL, Raipur, Confidential

Page 101