Sie sind auf Seite 1von 22

Vol.

2 Trading Operations in the Philippine WESM


AUGUST 2015

WESM Handbook

A Guide to All Members and Applicants of the


Philippine Wholesale Electricity Spot Market (WESM)

The Philippine Electricity Market Corporation (PEMC) provides this document (the Document)
for general information purposes only. The information contained in this Document is correct
to the best of PEMCs knowledge at the time of publishing but may change over time. The
Document is reviewed and updated from time to time. If you have further inquiries regarding this
Document, please contact PEMCs Participant Support Section via e-mail at helpdesk@wesm.ph,
or through telephone at (+632) 631.8734 loc. 229/239.
Disclaimer/Waiver:
All information in this document may still be subject to change after final verification by the
PEMC. This publication is meant to provide a timely overview of the trading operations in the
WESM. As such, PEMC does not make any representation or warranties as to the completeness
or accuracy of the information. PEMC, likewise, accepts no responsibility or liability whatsoever,
for any loss or costs incurred by the reader arising from, or in relation to, any contributions or
assumptions derived from the information.

Editorial Team

CONTRIBUTORS

Phillip C. Adviento
Josephine C. Corpuz
Cerise M. Cabactulan
Eric Nio U. Louis
Menachem Reykarl B. Loyola
Katrina A. Garcia-Amuyot
Daisy Jane C. Alfafara
Arnesh Y. Inostro
Theresse Joy V. Calo

Edwin N. Mosa
Arthur P. Pintado
Edward I. Olmedo

Layout Artist
Rhlee B. Amojilar

Adviser
Robinson P. Descanzo

Table of contents

WESM Operations

Introduction

Scheduling and Dispatch in the WESM

WESM Timetable

During Normal Conditions

During Emergency Conditions

Sample Cases of Market Interventions

Market Suspension

Sample Normal Dispatch Process

Load Forecasting

10

Introduction

10

Demand Forecasting for Market Projections

11

Demand Forecast for the Real-time Dispatch Runs

12

Operational Market Reports

13

Introduction

13

Procedure

13

Daily Operation Reports

15

Market Participant Interface

17

Scheduling and Pricing

19

WESM OPERATIONS

INTRODUCTION


A clear definition and delineation of responsibilities are necessary to ensure the reliable operation of
the grid, especially with the Market Operator (MO) and the System Operator (SO) being two separate
entities.
As a result, the WESM Manual on the Dispatch Protocol was formulated after rigorous discussions
between MO and SO.
The Dispatch Protocol
Clearly establishes the WESM Timetable for the execution of specific processes (WESM Rules 3.4.2
and 10.4.8.1)
Establish scheduling and dispatch procedures to be followed in
-- Normal Conditions
-- Emergency Conditions
that should be consistent with the WESM Timetable and features of the MMS

Scheduling and Dispatch in the WESM





WESM was established as the trading platform of energy transactions.


WESM was also established as the central platform for the dispatch scheduling of generating facilities.
SO is still responsible in the dispatch of generating units at real-time.
MO has the responsibility of forecasting demand, and prepares a Security Constrained Economic
Dispatch (SCED) schedule of generators and loads based on the hourly demand bids and generation
offers.
MO also maintains a Market Network Model (MNM) which shall be used by the Market Dispatch
Optimization Model (MDOM), which shall be able to consider transmission constraints and losses.

Responsibilities in WESMs Scheduling and Dispatch


The MO, SO, and Trading Participants (TPs) are the three entities involved in the scheduling and dispatch of
generating facilities in WESM
MO Responsibilities in Scheduling and Dispatch


2
2

Maintenance of the MNM in coordination with the SO


Generation of dispatch schedules using the MDOM
Transmittal of dispatch schedules to the SO for implementation

SO Responsibilities in Scheduling and Dispatch


Submission of overriding constraints to ensure the reliable operation of the grid


Outage Schedule - List of Equipment (e.g. generators, lines, transformers, breakers, etc.) that will be
out of service for a certain defined period.
Contingency List - List of Equipment enlisted for contingency analysis (as per Grid Code: N-1
Contingency Requirement).
Security Limits - List of Generators and Branch Groups that will have its limits overridden for security
purposes (e.g. MRU/testing/commissioning).
Transmission Limits - list of transmission capacities of lines and transformers to be consider in the
scheduling process
Implementation of the dispatch schedules provided by MO
Issuance of deviation report to MO (actual vs. schedule)

TP Responsibilities in Scheduling and Dispatch



Submission of bids and offers to WESM consistent with the WESM Timetable
Comply to the dispatch instructions of SO
Figure 1. Scheduling and Dispatch in the WESM

3
3

WESM Timetable

Trading activities in WESM operate at different time frames


Week Ahead Projection (WAP)
Day Ahead Projection (DAP)
Hour-Ahead or Real-Time Dispatch (RTD)
Real-Time Ex-post (RTX)

WESM Timetable: WAP


The Week-Ahead Projection (WAP) gives indicative hourly dispatch schedules and spot prices for the
next seven days.
Its results serve as a guide to the following entities:
Participants when bidding transactions in the market for the next seven days
SO in the determination of the cost impact of planned outages
It considers the following information, which shall be used by the Market Management System (MMS) to
generate schedules:
Demand bids and energy offers from Trading Participants
Demand forecasts
Outage Schedules
Security Limits
Latest available system snapshot

WAP
executed every
day today
produce
results for theresults
next seven
days.
WAP is isexecuted
every
to produce
for
the next seven days

WESM timetable: WAP

Figure 2. WESM Timetable: WAP


Execution of
WAP at Day D

D-1

D+1

Study Period of WAP at Day D


(From D+1 to D+7)
D+2
D+3timetable:
D+4
D+5
D+6WAP
D+7
WESM

D+8

D+9

TRADING DAYS

WAP
at 0900H
each

WAPis
is executed
executed at 0900H
of each of
trading
day trading

day

trAdiNG dAyS

Prior to 0900H, the


following activities are
made for D+1 to D+7

Gathering of weather
forecasts

Preparation of demand
forecasts

Submission or revision
of bids and offers

4
4

10

11

12

13

14

15

WAP Results and Analysis


Coordination with SO
WAP Execution

16

17

18

19

Basic WESM 2014

Publish WAP
Results in WEB
The latest information provided by
SO prior to 0900H shall be used
System Snapshot
Outage Schedule
Security Limit
Transmission Limit
Contingency List
Basic WESM 2014

WESM Timetable: DAP




The Day-Ahead Projection (DAP) gives indicative hourly dispatch schedules and spot prices covering the
succeeding hours of the day up to the end of the following day.
It allows the SO to prepare a more accurate contingency plan for the relevant intervals.
It considers the following information, which shall be used by the Market Management System (MMS) to
generate schedules
Demand bids and energy offers from Trading Participants
Revisions of bids and offers for consideration in the DAP run can be done until a cut-off time
(four hours prior to the trading hour)
Demand forecasts
Outage Schedules
Security Limits
Latest available system snapshot
DAP is executed every four hours to produce results for the succeeding hours until the end of the
following day.

WESM timetable: dAP

DAP is executed every four hours to produce results for the succeeding hours until the end of the
Figure 3. WESM Timetable: DAP
following day
trAdiNG dAyS

0800H DAP

0400H DAP

DAP Results Analysis


Coordination with SO

10

11

12

13

14

1200H DAP

15

16

17

18

19

1600H DAP

DAP Results Analysis Coordination with SO is


done up until 1 hour after the DAP execution

The latest information provided by SO prior to each DAP run shall be used
The latest bids and offers shall be used. Submission or revision of bids and offers relevant to the succeeding hours can
be made prior to the execution of the DAP run.
Demand forecasts for each of the succeeding hours evaluated by the DAP run should be provided prior to its execution.
Revisions may still be implemented prior to the DAP run

DAP Study Period

Basic WESM 2014

Table 1. DAP Study Period


Study Horizon

DAP Run at
Current Day D

From

To

0400H

0500H of D

2400H of D

0800H

0900H of D

2400H of D

1200H

1300H of D

2400H of D+1

1600H

1700H of D

2400H of D+1

2000H

2100H of D

2400H of D+1

2400H

0100H of D+1

2400H of D+1

5
5

WESM Timetable: RTD





The Hour-Ahead or Real-Time Dispatch (RTD) publishes schedules that shall be implemented by SO,
and spot prices that shall be used in the settlement of market transactions.
The RTD schedules are subject to the final screening of SO before a dispatch instruction is issued to a
Trading Participant.
The dispatch schedule is the target MW loading of all Trading Participants at the end of a trading interval.
RTD is executed every 55th minute of the hour.

WESM timetable: rtd

RTD is executed every 55th minute of the hour

Figure 4. WESM Timetable: RTD


RTD Execution for
Trading Hour HH

The latest information


provided by SO prior to each
RTD run shall be used
Gate Closure for
bids and offers

40

50

00

10

20

Trading Interval HH

30

HH-2

Trading Interval HH

40

50

10

20

30

HH-1

40

50

00

10

HH

Transmit RTD Schedules and


MOT to SO
Publish results in WEB

20

30

40

HH+1

Dispatch Implementation for HH


to meet Target Schedule
Basic WESM 2014

WESM Timetable: RTX





The Real-Time Ex-Post (RTX) represents the duration of the trading interval.
It is not used by the SO in the dispatch implementation since it is merely used for price discovery, in
which its results represent the actual events that transpired for the duration of the trading interval
Its results are used to settle imbalances in the market (schedule vs. actual)
RTX is executed every 1st minute of the hour

WESM timetable: rtX

RTD is executed every 55th minute of the hour


Figure 5. WESM Timetable: RTX
RTX Execution for
Trading Hour HH

The latest information


provided by SO prior to each
RTX run shall be used

Trading Interval HH

40

50
HH-2

6
6

00

10

20

30

40
HH-1

50

10

20

30

40

HH

50

00

10

20

30

HH+1

Basic WESM 2014

40

During Normal Conditions


Majority of the day-to-day activities in the market fall under the category of normal conditions
Table 2. WESM Tasks During Normal System Conditions
Procedure in the Dispatch Protocol

Activities

Responsible Group
MO

SO

Bids and Offers

Appendix A.1

Demand Forecasting

Appendix A.2

Outage Scheduling

Appendix A.3

Contingency Planning

Appendix A.4

Pre-Dispatch Market Projections

Appendix A.5

Real-Time Dispatch Schedule

Appendix A.6

Dispatch Implementation

Appendix A.7

System Status Report

Appendix A.8

Post Dispatch Report

Appendix A.9

Market Information Publication

Appendix A.10

Daily Operational Report

Appendix A.11

During Emergency Conditions


WESM Rules 6.3.1.1 states that an emergency condition is a situation which has an adverse effect on
electricity supply or which poses a significant threat to system security
Table 3. Clasification of Emergency Events
Activities Procedure in the Dispatch Protocol
Market Failure

MMS Failure

System Operations
SO

MO

Medium-term
supply deficiency

Communication
network
Breakdown

Total system
Collapse

Communication
network
Breakdown

Effects of force
majeure events

Computer
systems failure

Grid Islanding or
Isolation

Computer
systems failure

Site-related
Emergencies

Multiple forced
Outages

Site-related
Emergencies

Threat to system
Security

7
7

WESM Rules 6.3.1.1 states that an emergency condition is a situation which has an adverse effect on
electricity supply or which poses a significant threat to system security
Table 4. WESM Tasks During Emergency System Conditions
Procedure in the Dispatch Protocol

Activities

Responsible Group
MO

SO
x

System Emergency and Restoration

--

Market Suspension and Intervention

Appendix B.2

EMS Disaster Recovery Procedures

--

MMS Disaster Recovery Procedures

--

Report and Documentation of Events

--

Sample Cases of Market Intervention


(06 February 2012: 1200H to 1400H)

Figure 6. Sample Case: Market Intervention

Emergency Market intervention was declared due to tripping


of several power plants affected by magnitude 6.9 earthquake
in the Visayas Region.
The intervention was initiated by the Visayas
System Operator.
The Market Intervention Report prepared by the National Grid
Corporation of the Philippines (NGCP) is attached.
(WESM Rules clause 6.3.1.2 (c))

8
8

Market Suspension
(14 July 2010)

Figure 7. Sample Case: Market Suspension

Pursuant thereto and by reason of the power system disturbance brought by typhoon BASYANG,
the commission has suspended the operations of
the WESM effective on 14 July 2010 at 1200H, as
contained in the notice of Market Suspension issued by this commission which is attached hereto
and made an integral part hereof as Annex A

Sample Normal Dispatch Process

FOR THE 0900H TARGET TRADING INTERVAL (08:01 AM UNTIL 09:00 AM)
Figure 8. Sample Normal Dispatch Process

FOR THE 0900H TARGET TRADING INTERVAL (08:01 AM UNTIL 09:00 AM)

9
9

LOAD FORECASTING

INTRODUCTION
Forecasting is a process of predicting market condition using historical data. In the WESM, we predict the
energy to be consumed in a certain area for a specific trading interval incorporating historical data, real time
grid system status, weather condition and events.This process is known as Load Forecasting. The provision
of load demand is necessary for the calculation of market prices and dispatch schedules. It is an integral
requirement of the market dispatch optimization model. The WESM Rules provide the calculation of market
projections and real-time schedules which require accurate load demand forecast information. The load
forecasting in the market has three time frames; namely hour-ahead, day-ahead and week-ahead
forecasting.
Hour-Ahead Forecast
The process of forecasting the load energy demand for next top of the hour. It is conducted every hour and
uses the latest real time grid system status, weather condition and events. The Ex-ante (Real-Time Dispatch
or RTD) utilizes this forecast.
Day-Ahead Forecast
The process of forecasting the load energy demand for the next day and is being updated every four hours
to accurately reflect the near real time load energy demand. The Day-Ahead Projection (DAP) utilizes this
forecast.
Week-Ahead Forecast
The process of forecasting the load energy demand for the next seven days. It is being updated daily. The
forecast output is an indicative figure for Market Participant bidding strategy and generator maintenance
scheduling. The Week-Ahead Projection (WAP) utilizes this forecast.

10
10

DEMAND FORECAST FOR MARKET PROJECTIONS


Week-Ahead and Day-Ahead Demand Forecasts

Hourly Demand Forecasts for each Forecast Area from the current day to the next seven days shall be
determined by the Market Operator using the Similar Day Load Forecast (SDLF) module of the Market
Management System (MMS).

The Demand Forecasts obtained in the week ahead forecast shall be used as Input Demand Forecasts
to obtain the WAP and the DAP.

The summation of the Net Load Forecast plus the losses computed for a Forecast Area after the
optimization process in the relevant market run (i.e. WAP or DAP) constitutes the Final Demand
Forecast for that Forecast Area.

Figure 9. SDLF Methodology Load Forecasting

11
11

DEMAND FORECAST FOR THE REAL-TIME DISPATCH RUNS

Hour-Ahead Forecasts

Demand Forecasts for the next hour in each Forecast Area shall be determined by the Market Operator
using the Load Predictor (LDP) module of the Market Management System.

The Demand Forecasts obtained in the hour-ahead forecast shall be used as Input Demand Forecasts to
obtain the Real-Time Dispatch (RTD).

The summation of the Net Load Forecast plus the losses computed for a Forecast Area after the
optimization process in the relevant RTD run constitutes the Final Demand Forecast for that Forecasted
Area.

Figure 10. LDP Methodology Load Forecasting

12
12

Operational Market Reports

INTRODUCTION
The Market Operator (MO) regularly publishes operational market reports to the public required by the
WESM Rules in accordance with the WESM Timetable. Using a web-based report system, operational
market reports are easily made available online to the trading participants and the general public.

PROCEDURE
Market Participant Interface (MPI)
Registered Trading Participants (TPs) shall have access to the Market Management System (MMS) or
WESM through a Market Participant Interface (MPI). The MPI is connected to the MMS through the worldwide web. The MPI shall be used by all TPs to bid and retrieve market information from the WESM-MMS.
The MPI may be accessed through: www.mms.wesm.ph

Information to be Published
System Messages
The System Messages display is the primary link between the Trading Participant and the WESM
Market Operator. The TP is notified of all kinds of system events such as report publication and
availability, market suspension or re-activation, and the like.
System Messages are classified as:
----

Normal: These are generally system-generated messages displayed in GREEN


Urgent: Urgent Messages are displayed in BLUE
Emergency: Emergency Messages are displayed in RED

Market Status Display


The Market Status Display shows the status of Hourly Energy Markets e.g. if the Market is still Open
or had already Closed.
Market Participant Interface Data
Using MPI, the Trading Participants will be able to access the following information:
---------

Market Participant Registration


Bids and Offers Data
Market and System Advisories
Updates on Market Prices, Dispatch and Pre-dispatch schedules
Demand Forecasts
Real-Time Ex-post (RTX) Prices
Market Participant Specific, All Market Participants, and ADHOC Reports
Settlement (Prudential Requirements)

13
13

WESM Website
The WESM website contains technical information on the WESM as well as all recent WESM development
and announcements.
The WESM website is: www.wesm.ph

Information to be Published
All Market information required to be published by the Market Operator under the WESM rules shall be
made accessible to the WESM members, DOE, ERC and the general public through the WESM website.
Access to the Market information other than the WESM website shall be the responsibility of the parties
concerned.
Systems and Procedures
The following are standard operating procedures that are to be observed during WESM operation:
------

WESM Timetable
WESM Operating Procedures during Normal System Condition
Emergency Procedures jointly developed by System Operator and Market Operator.
Detailed procedures developed by the System Operator in relation tocompetitive tendering
process for Ancillary Services.
Dispatch and pricing procedures in the event of load shedding and excess generation developed
in consultation with the System Operator.

Other WESM Reports


The following are the relevant reports that are to be prepared as required by the different provisions
of the WESM rules:
----

14
14

Findings and recommendation of the PEM auditor regarding changes in WESM rules consequent
to annual audit, review, check, or otherforms of review.
Suspension notice issued to a WESM participant. It shall also be published in a newspaper of
general circulation, as soon as practicable.
Revocation of suspension issued to a WESM Participant. It shall also be published in a
newspaper of general circulation, as soon as practicable.

Operational Market Reports


DAILY OPERATIONS REPORT
The Market Operator shall closely monitor Market Operations on an hourly basis within the trading day.
Likewise, the MO shall record and verify all significant events that are not recorded in the MMS. The MODOR shall be reviewed and approved by the Operations Unit Head.
At the end of every trading day, the Market Operator shall prepare a report containing the summary of its
operations on an hourly basis of the previous day which includes the contents of the Post Dispatch Report.
The following are the daily Operations report being published by the Market Operator:
WESM WEB SITE (https://www.wesm.ph)







WAP_DAY_LUZON
WAP_DAY_VISAYAS
NEXT_DAY_LUZON
NEXT_DAY_VISAYAS
PREVIOUS_DAY_LUZON
PREVIOUS_DAY_VISAYAS
RTD Marginal Plant
RTX Marginal Plant

Market Participant Interface (MPI)






RTD OUTAGE SCHEDULE


RTX OUTAGE SCHEDULE
PEN REPORT
DAP Pmin
PSM REPORT-Hourly Price Substitution occurrence if any for RTD and RTX

Next Week Summary (NWS)


A summary of the results of WESMs Week-Ahead Projection (WAP).
The Next Week Summary (NWS) report contains a daily summary of the following results for each of the
trading days included in the relevant WAP workflow run.
1.
2.
3.
4.

Demand and Reserve Requirement


Market Participant Bids and Offers Summary
Energy and Reserve Schedules
Market Price Summary

The WAP is executed daily to project the hourly results for the next seven days (e.g. Monday WAP run
contains hourly results from the next day (Tuesday) up to the following Monday).

15
15

Next Day Summary (NDS)


A summary of the results of WESMs Day-Ahead Projection (DAP).
The NDS report contains a summary of the following results projected for the following day as obtained in the
relevant DAP workflow run.
1.
2.
3.
4.

Demand and Reserve Requirement


Market Participant Bids and Offers Summary
Energy and Reserve Schedules
Market Price Summary

The DAP is executed every four hours to project the hourly results from the next hour of the same day, up
until the end study period of a particular run (some DAP runs end at 2400H of the same day while other DAP
runs end at 2400H of the next day). The following table shows the study periods of the different DAP runs.
Table 5. DAP Runs
DAP RUN

FROM

TO

0400H

0500H of DAY D

2400H of DAY D

0800H

0900H of DAY D

2400H of DAY D

1200H

1300H of DAY D

2400H of DAY D+1

1600H

1700H of DAY D

2400H of DAY D+1

2000H

2100H of DAY D

2400H of DAY D+1

2400H

0100H of DAY D+1

2400H of DAY D+1

Previous Day Summary


A summary of the results of WESMs Hour-Ahead or Real-Time Dispatch (RTD) and Real-Time Ex-Post
(RTX)
The Previous Day Summary (PDS) report contains a summary of the following results that transpired
during the previous day involving the RTD and RTX workflows in the market.
1.
2.
3.
4.

Demand and Reserve Requirement


Market Participant Bids and Offers Summary
Energy and Reserve Schedules
Market Price Summary

The information contained herein are those obtained at real-time for the RTD and RTX workflows, and it
does not reflect any pricing corrections that may be involved in cases of pricing errors.
The Market Operator regularly publishes market reports to the public that contains a summary of the
markets results, primarily involving the RTD and RTX.

16
16

Operational Market Reports


Marginal Plants
The Marginal Plant (MP) data presents information on the hourly Marginal Plants and their corresponding
price offers in the market.
The MP is the generating unit or plant whose price offer corresponds to the system marginal price for a given
trading interval.
In an unconstrained system, the market price is set by one MP (i.e., the system marginal price). This price is
adjusted for each node to consider transmission losses and/or congestion costs to come up with a resulting
value called the Locational Marginal Price (LMP).
Where the system is constrained, the relevant flows of electricity are affected as the line limitations arising
from the congestion may impede the supply of cheaper electricity from one area to another. In such cases,
there may be more than one MP setting the marginal price for the different nodes on either side of the
constraint.
Available Market Data in the WESM Website
The following list shows a variety of market information made available to the general public in the WESM
public website.
1. Market Bids and Offers
2. Market Prices and Schedules
3. Ex-ante and Ex-post LWAP
4. Market Re-Run Results
5. Marginal Plants
6. Administered Price
7. HVDC Schedule
8. Net Settlement Surplus
9. Must-Run Unit Generation Price Index
10. Price Substitution Methodology for Congestion
11. Daily PEN-MRR-PSM-AP Summary
12. Final Market Prices

MARKET PARTICIPANT INTERFACE


The results of the Real Time Dispatch (RTD and RTX) shall be published in the Market Participant Interface
(MPI). The following information shall be published (for each Resource of a Trading Participant)
Table 6. RTD & RTX Results Published in the MPI
Information

RTD

RTX

Energy

Dispatch Target

Actual Energy / Delivered /


Consumed

Nodal Price

Ex-Ante Price

Ex-Post Price

Other system data that will be published includes the following:





Total energy dispatched


Total dispatchable load
Total system losses
Locational Marginal Prices
17
17

Publication of Results
The results of the Real Time Dispatch shall be published in accordance with the WESM timetable.
The results of the Real Time Dispatch shall be published in the Market Participant Interface (MPI) and
correspondingly submitted to the System Operator on the following schedules:
Table 7. RTD & RTX Results Schedule in the MPI
Process

Study Horizon

Execution Frequency

RTD Results Publication

1 Hour-ahead

Hourly, at the start of Trading


Interval

RTX Results Publication

24 Hours of the previous Day

1200H of the following Day

RTD Outage Schedule


The RTD Outage Schedule data presents information on the hourly Outage Schedules for the RTD run for
the 24-hour interval within a trading day.
RTX Outage Schedule
The RTX Outage Schedule data presents information on the hourly Outage Schedules for the RTX run for
the 24-hour interval within a trading day.
PEN Report
The PEN Report data presents information on the summary of all the Pricing Error Notice (PEN) issued
within the trading day.
DAP Pmin
The DAP Pmin data presents information on the computation of the total Pmin of the generators resulted
from the 1600H DAP run of the trading Day. It aims to see whether there shall be a possibility of an over
generation for the next trading day.
PSM Report
The PSM Report data presents information on the hourly price substitution occurrence if any for RTD and
RTX.

18
18

SCHEDULING
OperationalAND
Market
PRICING
Reports

Scheduling and Dispatch upon Establishment of WESM Operations


WESM was established as the central trading platform for the scheduling, dispatch, and net settlement of
generating facilities and loads in grids with WESM operations.

The Market Operator (MO), System Operator (SO), and Trading Participants (TPs) are the three entities
involved in the scheduling and dispatch of generating facilities in WESM.

The SO is responsible for the dispatch of generating units at real-time.

The MO has the responsibility of forecasting demand and the scheduling of generators and loads
based on hourly generation offers and demand bids through a Security-Constrained Economic Dispatch
(SCED).
The SCED of generators and loads are obtained using WESMs MDOM, which utilizes the MNM
maintained by the MO. As such, pricing and scheduling calculations are able to consider transmission
losses and constraints.

TPs are responsible for the following:


Submission of generation offers and/or demand bids.
Comply with the dispatch instructions.

19
19

USEFUL CONTACTS
Philippine Electricity Market Corporation
Participant Support Section
9F Robinsons Equitable Tower, ADB Avenue
Ortigas Center, Pasig City, Philippines 1600
Tel. No.: (+632) 631.8734 loc. 239 / 229 / 220 / 302
Facsimile: (+632) 636.0802 / 634.0985
Email: helpdesk@wesm.ph

Department of Energy
DOE Information Center
Information Technology & Management Services
Energy Center, Merritt Road
Fort Bonifacio, Taguig, Philippines 1201
Tel. No.: (+632) 840.2120
Email: info@doe.gov.ph
National Electrification Administration
57 NEA Building, NIA Road, Government Center
Diliman, Quezon City, Philippines 1001
Tel No.: (+632) 929.1909 local 124
Facsimile: (+632) 929.2171

National Grid Corporation of the Philippines


Quezon Avenue corner BIR Road
Diliman, Quezon City, Philippines
Trunk-line (connecting all Departments): (+632) 981.2100

Energy Regulatory Commission


Pacific Center Building, San Miguel Avenue
Ortigas Center, Pasig City, Metro Manila, Philippines 1600
Tel. No.: (+632) 914.5000 local 114
Facsimile: (+632) 631.5816
Email: info@erc.gov.ph

Das könnte Ihnen auch gefallen