Beruflich Dokumente
Kultur Dokumente
Cause:
Operating error,breaker head flash over ,control ckt mal function or combination of
these cause accidently energizing generator off line.
Three phase energizing of generator at stand still cause accelerate similarly to
induction motor
Generator at this point represented by sub-transient reactance to system and it will
drawn 1.0 to 4.0 p.u current(100-400%) depend on system impedance.
High current produced in rotor due to behavior of generator as induction motor
may thermally damage motor in few sec.
Protection:
This condition for generator monitors max. phase current and max.ph-ph voltage of
generator.
voltage supervised over current protection base
Protect generator from this is to operate over current function supervised by
UNDER VOLTAGE function.
Over current function disabled when machine machine is online and if any over
current is detected when machine is OFF line for specific duration, than it will
issue a trip
Setting guide line:
I>Largest current produced during accidental energizing
I>To be less than 0.8 Ienergisation
Ienergisation
atmosphere of gas remains between the open contacts, a breaker can withstand the
2 pu voltage for a time sufficient to take it out of service in an orderly fashion.
However, if the failure is on an air breaker or the gas between the contacts is
displaced by air, a flashover is probable. Because field excitation is applied, the
generator responds to a flashover as it would to an out-ofphase synchronization. At
the instant of energization, the generator exhibits positive-sequence impedance
equivalent to its subtransient reactance (Xd)
DEDICATED ENERGIZATION PROTECTION
It is apparent that native schemes do not provide adequate protection for
energization events. These schemes are either too slow or lack sensitivity. Another
major disadvantage with these schemes is that they are associated with online
protections and as such are routinely removed from service during shutdown.
These schemes are also disabled unintentionally when the generator relay voltage
transformer fuses are removed or when schemes are tested or modified during a
generator outage. For these reasons, it has become standard practice to install
dedicated inadvertent energization and open breaker flashover schemes.
Dedicated schemes should trip the appropriate high-voltage switchyard breakers,
the generator field breaker and the breaker(s) at the low side of unit auxiliary
transformer. The schemes should also be designed with control circuitry segregated
from online protection to assure these schemes are not disabled during unit
shutdown.
DEDICATED INADVERTENT ENERGIZATION SCHEMES
These schemes are intended to detect an energization that occurs with the generator
at standstill. Such energization would be the result of a breaker, gang-operated, or
single-phase disconnect switch closure. Consequently, an inadvertent energization
scheme must detect both three-phase and single-phase events. The scheme shown
in Figure is armed when the generator is taken offline and all three-phase voltage
elements drop out. These elements are typically set about 85% nominal voltage.
Arming is delayed 2 to 5 sec by the delayed pickup of the timer. This delay is
necessary to ensure that the scheme is not activated by voltage dips associated with
system faults. Once armed, tripping is initiated without delay if any one of the
phase instantaneous overcurrent elements actuate. Overcurrent elements are
normally set about 50% of the minimum anticipated energization current. The
minimum current is usually a result of a single-phase energization.
The scheme is taken out of service automatically when the generator is returned to
service and the terminal voltage rises above the undervoltage element settings.
Deactivation of the scheme is delayed 10 to 15 cycles by the delayed dropout of
the timer. This delay is required to assure the scheme will operate for an actual
energization, which would also reset the undervoltage elements. Because this
scheme deactivates before the generator reaches rated voltage, it will not provid
breaker flashover protection.
INADVERTENT ENERGIZATION SCHEME SETTINGS
The inadvertent energization scheme is intended to operate for energizations when
the generator is at rest. Such energization would be caused by accidental closure of
the high-voltage breaker or the disconnect switch. A breaker closure would result
in a three-phase energization, while a switch closure would produce either threephase or single-phase energization depending on the type of switch. Consequently,
the current detectors in the inadvertent energization scheme must be capable of
detecting both conditions.
When energized at standstill, the generator will display positive-sequence
impedance closely approximated by its negative-sequence impedance. The initial
three-phase energization current is calculated using sample system data from
Chapter 1, Generator data sheet and Equation (15.4) neglecting R2.
Since impedances are on the generator base current at the high-voltage terminals of
the GSU is
Current at the high-voltage terminals of the GSU transformer are found from
Equation (15.8) and
the constraint that I1 =I2 = I0. This yields
Current at the generator terminals is found by including the +30 phase shift
imposed on the negative- and positive-sequence currents respectively by the wyedelta connection of the GSU transformer, Equation (15.9).
Clearly, the phase-to-ground case produces the minimum energizing current and is
therefore chosen as the basis for the instantaneous element settings. The 50IE
should be set no higher than 50% the minimum energization current. The 50IE
setting is then calculated as:
The time delay pickup of timer 62IE sets the delay in arming the scheme after the
generator is taken offline and the 27 element dropout. This setting is not critical,
but must allow sufficient time to override voltage transients caused by system
faults that would drop out the 27 elements and erroneously arm the scheme. The
transmission lines adjacent to the sample system generator employ two-zone stepdistance phase protection and time and instantaneous overcurrent ground
protection. The time delay on the second zone phase protection is 0.5 sec, so both
ends of a faulted line would clear in less than a second. Although the overcurrent
ground protection could take several seconds to clear, a ground fault would not
drop out all three 27 elements to arm the scheme. A delay on arming of
2.0 sec should be more than sufficient.
During an energization from standstill, generator damage would likely occur in the
generator rotor as a result of induced currents. The generators negative-sequence
short time capability (K = I2 2 t) is an indicator of rotor thermal capability and can
be used to estimate time to the onset of damage. The data sheet for the sample
system generator (Appendix A) lists an I t limit equal to 30. At standstill, both
positive- and negative-sequence currents contribute equally to rotor heating and the
time until damage is estimated as
For the instance under study, a three-phase energization produces a positivesequence current of 3.61 pu, while a single-phase energization produces positiveand negative-sequence currents each with a magnitude of 1.17 pu. The resulting
withstand times are as follows.