Sie sind auf Seite 1von 12

Excavation work for indus hospital

Standard work norms


per 100 cubic yard
Soil type
Medium

dipper size
1 cubic yard

applicable for 6ft depth


supervisor
1.5

manhour
oiler
1.5

Site Requirement
B1
total area 10,600sq meter
depth
19ft

so excavation will be 20ft


total volume to be excavated
total volume to be excavated
Number of hrs reqd.
hrs / shift
Number of days reqd.
number of teams
days for each team

driver
1.5

Total
4.5
Site Requirement
total area
depth # 1
depth # 2

as per
BOQ
64660m3 27000
84575.3y335370
1269hrs 530.55
10hrs
10hrs
127days 53days
2
2
63.5days 27days
6.1m

6m
45000
58858
882.9hrs
10hrs
88.3days
2
44days

Block Works

ble for 6ft depth

100y3
1.5hrs
1y3
0.015hrs
84575.3y31268.6hrs
1m3
1.31y3

ite Requirement
B2
7500sq meter
19.7
46 tank

D1
D2
Area
H.House

8m

AS per BOQ

38525.76
35000 1966m3
50468
45850 2575y3
752hrs
687.8
38.6
10hrs
10
10
75.2days
68.8 3.9days
2
2
1
38days 35days
4days

63.7
75.6
4815.72

Roof Plan
Length
131600
Width
49200
height
Sub station at roof
Length
17.5
Width
9
height
other constructions
Machine Room 1
Length
8400
Width
5000
height
Machine Room 2
Length
8400
Width
5000
height

Basement plan

RYK KHAADI
Demolition Works
Activity
Concrete slab
Brick Masonry

Units

labor

helper

total

total QTY.

T.Mhrs

1cu yd.
cu ft.
cu yd.

2.5

0.5

130Cft

15

1.35

3
27cft
1.35

cu ft.

0.74

0.74

130Cft

96.2

Construction Work
Tiling Works
Paint works
(internal)

100Sq. Ft

1.1

2.5

3.6

3765

0.55

0.4

1.46

2.41

Primer
Coat

2nd Coat

3rd Coat

11700

136

282

Unit conversions
1
T. Md

# of workers

W.Duration

10.7

15

2 teams

31

10

cu. Y

27

cu. Ft

General requirments
1 Demolition
2 Dewatering
3 Site Grading
4 Piling
5 Excavation
6 Soling
7 Screeding
8 Raft making
9 Retaining wall making
10 Columns for basement
11 beams & lintels
12 Block works
13 surface finishing
14 painting
15 Doors & Windows
16 Floor finishes
17

Excavation estimation
per 100 cubic yard

excavation with back hoe


Soil type
light
Medium
hard

dipper size
1 cubic yard
.75cubic yard
.5cubic yard

manhour
supervisor
oiler
1.4
1.4
1.5
1.5
2
2

driver
1.4
1.5
2

Total
3.3
4.5
6

xcavation estimation
applicable for 6ft depth

1yard=
1yard=

0.91m
3ft (int.)

1cubic yard=
1cubic yard=

.765m3
27ft3

1m3=

35.32ft3

manhours
Block works / 1000bricks
4" walls
ground upto 5' elev.
ground upto 10' elev.

Mason

Labor

Mortar
(cubic feet)

13.71
13.88

11.21
11.37

18
18

hours

Per 1000 bricks


Brick / sq. foot of wall
6.35
6.35

brick size
6"* 12* 8"

Das könnte Ihnen auch gefallen