HOME > SUBSTATIONS > LISTENING FOR EARLY SIGNS OF EQUIPMENT FAILURE
ListeningforEarlySignsOfEquipmentFailure
Connect
MarkN.Theyerl,AlliantEnergy|T&DWorldMagazine
SHARE
Tweet
Nov1,2001
COMMENTS 0
Industrycompetitivepressureshaveforcedutilitiestooptimizeoperationandreduce
maintenancecosts,inotherwords,domorewithfewerresources.In1993,utilitiesmade
amajorefforttoreevaluatepreventivemaintenanceactivitiesbasedonextensive
personnelexperience,andelectricalanddiagnostictestingmethodsavailableatthattime.
Mostutilitiesuseatimebasedpreventiveapproachtosubstationmaintenance.This
approachdictatesmaintenanceschedulingstrictlyrelatedtotimeinserviceratherthan
equipmentcondition.Frequently,fundsaremisdirectedformaintenanceperformedon
equipmentthatdoesnotrequiremaintenance.Thismisdirectionoffundscreatedthe
needforanonlineconditionassessmentofpowertransformersandassociatedsubstation
equipment.
TheEPRIM&DCenter,workingincooperationwithpredictivemaintenance(PDM)
memberutilities,implementedaPDMprogramthatincorporatedthefollowing
technologies:
LatestNews
VibrationAnalysis
UltrasonicNoiseAnalysis
PartialDischargeDetection(PDD)
PortableGasinOilAnalysis
JUN21,2016
ARTICLE
TakeCareof
Reliability,TakeCare
ofCustomers
InfraredThermography
SoundLevelTesting
UltrasonicBearingWearDetection.
ProjectOverview
Researchersdevelopedaformalplan,whichincludedthenewlyproposedpreventive
maintenanceactivitiesandfrequenciescombinedwithPDMconditionmonitoring
technologies.ThismaintenanceoptimizationeffortincludedaPDMprogram
developmentandimplementationprojectcontainingthefollowingtasks:
JUN21,2016
ARTICLE
RateImpactofClean
PowerPlan
NEWS
JUN21,2016
Schweitzer
Engineering
LaboratoriesExpands
OperationinBrazil
Theevaluationandenhancementofknownonlineperiodicequipmentcondition
monitoringtools.
ARTICLE
Thedemonstrationandevaluationofvariousnewresearchtechnologies.
UtilitiesExploreNew
MotorEfficiencies
JUN21,2016
TheenhancementoftheprogrammaticaspectsofthePDMprogram.
Proceduredevelopment.
http://tdworld.com/substations/listeningearlysignsequipmentfailure
LatestonT&DHow
1/5
6/22/2016
earlysignsofequipmentfailure
Onsitetrainingfordatacollectionandreductionassociatedwithnewtechnologies.
VIDEO
JUN8,2016
CablePullinChicago
Documentationofcostbenefitanalysis.
PartialDischargeDetection
AspartoftheSubstationPredictiveMaintenance(SPDM)program,researchersinitially
performedPDDontransformers,loadtapchangersandcircuitbreakersusingtypical
offtheshelfPDDequipment.Thistypeofdetectorcountsactivityatapproximately150
KHz.Althoughthistechniqueisusefulforquantifyingactivitylevels,mosttransformers
donothavelevelsofinternalactivityhighenoughtotriggerthedetectors.Thedifficulty
thenisthatnodataissavedfortrendingand,therefore,nojudgmentoftransformer
conditioncanbemadeovertime.
VIDEO
1
VIDEO
TransformerProblems
Asignificantfindwasona138/69kV93.3MVApowertransformer.Thelocationofthis
transformerinthetransmissionsystemmadethisdiscoveryacostbenefit.Itisanormal
procedureforAlliantPDMtechnicianstolistentotheonloadtapchangerswhile
changingitsposition(stepping).Thetechnicianshearthearcingasthetapchangergoes
throughthestep.Aftercompletingthestep,thereshouldbenoarcing.Inthiscase,the
arcingcontinuedatafrequentrateandahighlevel.Whenopeningthetapchanger,crews
discoveredacrackinthebridgecastingsupportingthedrivemechanism.Thisallowedthe
gearstoslipandthemechanismtogetoutoftimeononephase.Thisisapotentialfailure
pointforthetransformerasthestepsdonotcompleteandthearcingcontinues(Fig.1).
Alliantcrewsperformedasurveyonanother138/69kV33MVApowertransformerwith
theTriple5faultdetector.TheinstrumentdetectedapartialdischargebelowtheX1
bushingataboutthe5ft(1.5m)level.Thedischargewasintermittent(about2to3
minutesapart)andatahighlevel.
Thecrewsdecidedtoseeiftheproblemwasloaddependent.Whileincreasingtheload,
thelevelandfrequencyofthepartialdischargerespondedinalinearfashion.Dissolved
gasanalysis(DGA)testsdeterminedtheconcentrationofacetylenegaswasincreasing.
Crewstookthetransformeroutofserviceandperformedadegasificationprocessonthe
transformeroil.Thetransformerwasthenputbackinservicewithloadconstraintsand
monitoredbyDGA.Thistransformerremainedinserviceforthreemoreyears,allowing
AlliantEnergytoplan,budgetandengineerthesubstationupgrade.
http://tdworld.com/substations/listeningearlysignsequipmentfailure
MAY11,2016
HowtoInspect
ResidentialSolar
Power 1
Assumingthatinternalarcingmightbelowlevelrandomactivitycontainingmultiple
frequencies,usersdecidedtoacquiredataintwodifferentfrequencybandsandlistento
thedatainadditiontologgingoverallrootmeansquare(RMS)levels.Triple5Industries
(Yardville,NewJersey,U.S.)developedasonic/ultrasonicfaultdetectorthatmeasures
RMSlevelsinbothfrequencybands.Applyingthistechniqueprovidestheabilityto
documentthedetectionoflowlevelrandomevents.OfftheshelfPDDequipment
detectedthisactivity,evenatverylowlevels.However,theeventswereusuallylessthan
100countsanddifficulttodetectinanymodeexceptpeakholdbecauseofits
randomness.Withthisinmind,AlliantnowusesthePDD(150KHz)equipmentfor
quantifyinglevels.Otherequipment(Triple5Model5550FD)hasbeensuccessfulin
identifyingpartialdischargeactivity.Combiningtheusageofthesedevicesyields
UltrasonicNoiseAnalysis/PDD.
Partialdischargeproducesacousticsignalsthataredetectablewithanacousticsensor
heldagainstthetransformerwallwiththetransformerinservice.Theacousticemission
emanatingfromthepartialdischargesourceswithinapowertransformerdisplayaburst
typesignal(Fig.2)withacharacteristicfrequencyof150KHz.Theamplitudeofthestress
waveofthepartialdischarge,whichexcitesthesensor,determinesthenumberof
oscillationscontainedwithineachburst.Thenumberofoscillationsoccurringwithina
onesecondintervalcontainsinformationrelativetothenumberandamplitudeofthe
discharges.Keepinmindtheoilofthetransformerattenuatestheamplitudeofthestress
wave.Thecountingtechniqueforthesesignalsisthemethodusedtodeterminethe
approximatelocationofapartialdischargesourceaswellasitsseverity.
MAY25,2016
UndergroundSplice
VIDEO
MAY2,2016
HowtoInstalla
Recloser
WhitePapers
TransformerTestingTechniquesandStandard
Development
ThermalImaging,PowerQualityandHarmonics
FlexPackTMPrecisionVoltageDividing
Transformer(PVDTTM)System
MOREWHITEPAPERS
T&DWLearningCenter
HandbookofEnergyEngineering
Calculations
SOLVEENERGYPROBLEMS
QUICKLYANDACCURATELY
AmericanElectrician'sHandbook
SixteenthEdition
Foracentury,theAmericanElectricians'
Handbookhasservedasthedefinitive
industryreferencefor...
TemporaryGroundingfor
LineworkerProtection
Thisessentialsafetyreferenceshows
howtoinstallgrounds...
VIEWCATALOG VIEWSHOPPINGCART
2/5
6/22/2016
earlysignsofequipmentfailure
ADGAperformedona69/13.09kV11.3MVAtransformershowedsomeincreasein
combustiblegases.Aprofilingofthetransformerwiththefaultdetectorrevealedsome
loudcoronaactivitynearthetopofthetankatthenoloadtapchanger(NLTC)location.
Afteropeningthetransformertankmanhole,thecrewdiscoveredablack,crustydeposit
onthemovableandstationarycontactsoftheNLTC(Figs.3and4).Ananalysisrevealed
thedepositstobeasulfurcontaminationonthecopperpartsinthetransformer.Knowing
atleastoneidenticaltransformerfailedbecauseoftheNLTC,allthesimilartransformers
withinthecompanywerechecked.Allthetransformershadthesameproblem.
OtherEquipmentProblems
FeaturedJobs
Themonitoringoflightningarrestorswiththe5550FDwasdiscoveredbychance.While
approachinga138/69kVtransformerforanannualprofilesurvey,anultrasonicnoise
washeardintheheadphonesandseenonthelevelmeterofthefaultdetector.Thisnoise
washeardontheradiatorslocatedonthe138kV(high)sideofthetransformer,aswellas
onthetransformersideoftheoilcircuitbreakerfeedingthetransformer.Careful
investigationdeterminedthenoisewasgeneratedexternallyfromthetransformer.The
bottomoftheH2arrestoronthe138kVhighsidewasthesourceofthenoise.
Thetransformerwastakenoutofservice,andthelightningarrestorswerepowerfactor
tested.Theresultsshowedthesuspectarrestorhadsignificantlyhighercurrentandwatt
readingsthantheothertwoidenticalarrestors.Replacingthelightningarrestor
eliminatedtheultrasonicnoise.
AlliantEnergyhasfoundseveralmoresimilarproblemswithlightningarrestorsusing
thismethod.Therealadvantagesofthismethodaretheonlinetestingofthearrestorsat
theiroperatingvoltageandtheabilitytodetectpartialdischargingatanearlystagebefore
failuremode.
Anotherpracticalandprovenuseforthefaultdetectoristheonlinemonitoringof
instrumenttransformers.Ononeoccasion,theinspectorlistenedtothreesinglephaseto
ground69kVpotentialtransformers(PTs).TwoofthePTshadultrasoniccountsof28,
whichisthebaselinenumberseenonanormaloperatingpieceofequipment.Thethird
PThadcountsof1000andhigher.Also,theinspectorcouldhearthepartialdischargein
theheadphonesataconstantrate.
ElectricUtilityELECTRICIAN
TownofWallingford
Wallingford,Connecticut
HIGHVOLTAGEELECTRICIAN/OPERATOR
UniversityofWashington
Seattle,Washington
LineDispatcherSpecialistIII
PortlandGeneralElectric
Tualatin,Oregon
MoreJobs>>
ThepositioningofthePTscreatedasituationsuchthatatotalbusoutagewouldoccurif
thePTfailed.AlliantcrewstookthePToutofserviceimmediatelyandchangeditout
withinacoupleofhourswithoutanoutage.Anoilsamplerevealedveryhighlevelsof
combustiblegases,particularlyAcetyleneatalevelover900ppm.Theearlydetectionof
thepartialdischargepreventedapotentiallyhazardoussituationandprolongedoutage
foranentirecommunity.
Itisimportanttogiveyourmaintenanceprogramareallygoodlook.Askyourselfthese
questions:
Areyoucomfortablewithyourcurrentsubstationreliability?
Haveyouhadanyrecentequipmentfailures?
Istheresomewayyoucouldhavepredictedtheprobabilityofthesefailures?
Wouldyouliketoknowwherethemostatriskequipmentisonyoursystem?
MarkN.TheyerlhasbeenwithAlliantEnergy(formerlyWisconsinPower&Light)for
18years,workinginsubstationconstruction,maintenanceandtestingforthelast16
years.Theyerlbeganworkinginthefieldofsubstationpredictivepreventivemaintenance
in1996.HeisanAVOcertifiedsubstationmaintenancespecialistandinfrared
thermographer.
SHARE
Tweet
http://tdworld.com/substations/listeningearlysignsequipmentfailure
3/5
6/22/2016
earlysignsofequipmentfailure
DiscussthisArticle
NAME:
Anonymous
SignInorregistertouseyourTDWorldID
Signuptoreceiveourfreenewsletters
Energizing(Weekly)ViewSample
TheSmarterGrid:Initiatives,Insights,
Innovations(BiWeekly)ViewSample
EMAIL:
Test,Monitor&Control(BiWeekly)
ViewSample
YOURCOMMENT:*
ProjectsinProgress(Monthly)View
Sample
Etrain(BiWeekly)ViewSample
SUBMITCOMMENT
GridOptimization(Weekly)View
Sample
VegetationManagementInsights
(Monthly)ViewSample
Related Articles
ProductInsider(Monthly)View
Sample
PECOReapsRewardsofDiagnosticMaintenance
ExperienceStationNewsletter
(Monthly)ViewSample
SymposiumforLTCTransformerFailureAddressesDissolvedGasesinOilAnalysis
BCHydroTracksTransformerHealth
DailyEnergyFix(Daily)View
Sample
FocusonSubstationPredictiveMaintenanceMaintenance
IEEEPESShowUpdate(ShowDaily)
ViewSample
NamibiaEmbracesCompleteTransformerProtectionPackage
TheEnergyTimes(Weekly)View
Sample
Lineman'sRodeoNews(Weekly)
ViewSample
EMAIL*
Company*
COUNTRY*
UnitedStates
Enteryouremailabovetoreceivemessagesabout
offeringsbyPenton,itsbrands,affiliatesand/orthird
partypartners,consistentwithPentonsPrivacyPolicy.
TDWorld.com
OverheadDistribution OverheadTransmission UndergroundT&D Substations SmartGrid Business SmartEnergyConsumer
Renewables
Site Features
Penton Corporate
MediaCenter
AboutUs
Subscribe
Advertise
Newsletters
TermsofService
RSS
PrivacyPolicy
Sitemap
Follow Us
http://tdworld.com/substations/listeningearlysignsequipmentfailure
Search TDWorld.com
4/5
6/22/2016
earlysignsofequipmentfailure
ViewMobileSite
Copyright2016Penton
http://tdworld.com/substations/listeningearlysignsequipmentfailure
5/5