Sie sind auf Seite 1von 20

Deviation Statement

NAME OF THE WORK:Construction of CC road from ele pole No.SS 55/B1for formation of Bhimavaram Bypass road in Tadepalligudem Municipality.
Adminstrative Sanction Rs.: 20.00 Lakhs,vide District Collector, West Godavari Proceedings No.88/Dy
04-12-2015
Agency : Sri.P.Surya Bhaskara rao, Tadepalligudem.
Agreement.No : S.E(PH) RJY ,Agt.No.12/2015-16, DT:
03.02.2016. & Value Rs.15,87,596.27
Technical Sanction : 30.00 Lakhs vide SE(PH), SER No.04/2015-16,Dt 05-12-2015
E.C.V : Rs.27,80,851.96 Tender Percentage : (-) 15.26%
Work Entrusted vide S.E(PH) RJY ,Agt.No.12/2015-16, DT: 03.02.2016. & Value Rs.15,87,596.27
As per Sanctioned Estimate
S.
No

As per Revised Estimate(Execution)

Description of work

Earthwork in excavation for structures as per drawing and


echnical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious aterial and disposal upto a lead of 50 m,
dressing of sides and ottom and backfilling in trenches with
excavated suitable material as per Technical Specification
1 305 MORD / 304 MORTH for foundations etc., complete as
per S.S and as directed by the departmental officer in
charge of the work.
Qty V.P No.38 of 1015 B

Carting of excavated earth with a lead of 1 KM including


nloading etc., complete as per S.S and as directed by the
2 departmental fficer in charge of the work.
Qty V.P No.
of 1015 B
Providing, laying, spreading and compacting Construction of
granular
sub-base
by
providing
Stone
dust
laying,spreading with motor grader in uniform layers on
prepared surface in sub-base/base course on a well
prepared sub-base and compacting with smooth wheel
roller of 80 to 100kN / Vibratory Roller 80-100 kN weight to
achieve the desired density including lighting, barricading
and maintenance of diversion,hire charges of machinery ,
3 fuel charges, wages of driver etc complete as per Tables
400.11 & 400.12 and Technical Specification Clause 406
MORD / MORTH. and as directed by the departmental fficer
in charge of the work.But excluding cost of seigniorage
charges.
Qty V.P No.40 of 1015 B

Qty

Rate in Rs Per

Amount in (Rs)

Qty

Rate in Rs

Per

Amount in (Rs)

199.00

158.81

1 Cum

31603.19

198.85

158.81

1 Cum

31579.37

59.70

31.00

1 Cum

1850.70

0.00

31.00

1 Cum

0.00

129077.90

96.98

1330.70

1 Cum

129051.29

97.00

1330.70 1 Cum

Providing Concrete for Plain /reinforced cement concrete


in open foundations using 40mm nominal size Graded hard
stone aggregate , mechanically mixed , placed in
founadation and compacted by vibration including curing for
14 days complete as per drawings and technical
specifications clause 802,803,1202 & 1203 MORD and 1500,
4 1700 & 2100 MOTH and other incidental charges etc.,
complete and as directed by the departmental fficer in
charge of the work.But excluding cost of seigniorage
charges.P.C.C(1:3:6)
Qty V.P No.41 of 1015 B
Construction of
un-reinforced, plain cement concrete
pavement, thickness as per design, over a prepared sub
base, with 43 grade cement or any other type as per Clause
1501.2.2 M35 (Grade) Design Mix, coarse and fine
aggregates conforming to IS : 383, maximum in a concrete
mixer of not less than 0.2 cum capacity and appropeiate
weigh batcher using approved mix design, laid in approved
fixed side formwork (steel channel, laying and fixing of 125
mictron thick polythene film, wedges, steel plates including
levelling the formwork as per drawing), spreading the
5 concrete with sholvels, rakes, compacted using needle,
scareed and plate vibrators and finished in continuous
operation including provision of ntraction and expansion,
construction joints, applying debonding strips, primer,
sealant, dowel bars, near approaches to bridge / culvert and
construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per
drawing and Technical Specification Clause 1501 MORD.
item RBR-CCPV-5 of standard data etc., complete as per S.S
and as directed by the departmental officer in charge of the
work.But excluding cost of seigniorage chaegrs.
Qty V.P No. 45 of 1015 B
Supply and delivery of M.S dowel bars of S 240 grade
including cost and conveyance to site and placing in position
as per S.S and as directed by the departmental officer in
charge of the work.
6 A) Cross 94/20=4.70 joints 25 mm dia @ 27 cm C/C
5.80/0.27 21 x5x0.50x3.858 Kg=202.545 Kg
B) Tie bars-10 mm dia @ 30 cm C/C 45 cm length
(9400/30=313.33) 313.33x0.45*0.617 Kg=87.00 Kg
Qty V.P No.26 of 1015 B

97.00

4341.98 1 Cum

421172.06

96.60

4341.98

1 Cum

419435.27

179.00

6646.32 1 Cum

1189691.28

177.26

6646.32

1 Cum

1178126.68

15425.46

215.92

50.41

1 Kg

10884.53

306.00

50.41

1 Kg

Providing High Yield Strength Deformed (HYSD)/ Thermo


Mechanically Treated (TMT) / Mild steel (MS) steel bars (Fe
415/ Fe 500 grade as per IS 1786-1979) of different
diameters for RCC works , including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials
and size and tying and lap-splicing with binding wire of 18
SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps,
7 couplings, chairs, spacer bars including cost and 1561.00
conveyance of binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending,
placing in position, tying including sales and other taxes on
all materials etc., complete for finished item of work in all
floors. ( APSS No.126) for Dewel Bars) (Mild steel dowel bar
25mm dia of grade S 240. 500 mm long @ 25 cm c/c for
expansion and longitudinal joints and at construction joint
including 5 per cent wastage)
For road= longitudinal direction- 8 mm dia @ 30 cm c/c 20
(575/30=19.16 ) x94x0.395 Kg= 711.651 Kg.
For road =Trans direction - 8 mm dia @ 30 cm c/c 500
Granular
sub-base/base/surfaceKg=711.651
course with Kg
local materials
(9400/30=313.33)x5.75x0.395
(Table
mix Bin place method normal Construction
Qty V.P400.13)
No.43 ofby1015
of granular sub-base by providing local material spreading in
uniform layers with motor grader on prepared surface,
mixing by mix in place method with with hand roller
com[lete as per Technical Specification Clause 408 MORD
8 and other incidental charges etc complete as per SS and as
13.00
directed by the departmental officer in charge of the work.
(For Berms)
Qty V.P No.50 of 1015 B

Sub Total
Supplimentary Items.
Filling in foundation trenches as per drawing and technical
9 specification Clause 305.3.9 MORD & 304 MORTH - Crusher
stone dust
Vaccum Dewatered Flooring.Fixing of channels, levelling the
concrete with beam vibrator, vacuum dewatering power
trowelling to finish as per the directions of Engineer-in
-Charge, rate inclusive of labour charges all complete for
10
finished item of work.
Qty V.P No.27 of 1015 B

50.89

1 Kg

79439.29

1503.00

50.89

1 Kg

76487.67

402.32

1 Cum

5230.16

12.74

402.32

1 Cum

5125.56

1873490.04

1850690.37

10.00

934.14

1 Cum

9341.40

355.74

36.12

1 Sqm

12849.33

Carrying cut groove cutting 75mm deep with petrol driven


saw as per the directions of Engineer-in-Charge, rate
12 including of labour charges, machinery charges all complete
for finished item of work.
Qty V.P No.46 of 1015 B(116.00 Rm)
16
Total Value Cement Concrete M20 mix using 20mm graded
13 Reinforced
crushed
granite from approved quarry
Tendermachine
Percentage
@15.26%(Less)
14 hard
including cost and conveyance of all materials like cement,
15 Total Value
sand, coarse aggregate, water etc. to site, including
16 Provision
for charges,
VAT @ 5%
seigniorage
sales and other taxes on all materials
17 and
Provision
for seigniorage
charges.
including
all charges
for machine mixing, laying
concrete
foundations
andBoard
under carrying
flooring bed,
in
Provision infor
MPLADSsign
the ramming
description
15cm
layers
finishing
top
surface
to
the
required
level
18 "MPLADS WORK" with the name of honourable MP, including
curingdetails.
etc. complete for finished item of work (APSS No.
funds
402) .RBR-FNDN-4C(i) with 10% form work for culver slabs
Provision for Innaguration.
19 V,P.No.40 of 1043 B

Nil

5757.73 1 Cum

LS

1 Sqm

566.37

0.00

5757.73

1 Cum

1873490.04
93674.50
22100.00

0.00
1873447.47
-285888.00
1587559.47
92535.00
22100.00

3000.00

3000.00

0.00
1873490.04

3000.00

4734.00

4734.00

1999998.54

Total Value

Assistant Engineer(PH)
Tadepalligudem Section.

65.10

3000.00

20 Provision for unforeseen items.


As per sanctioned estimate
As per Execution
Difference

8.70

1999998.54
1712928.47
287070.07

Deputy Executive Engineer(PH)


Eluru Sub-Division.

1712928.47
Excess
Less
Difference

22757.10
309827.17
287070.07

tion Statement

mavaram Bypass road in Tadepalligudem Municipality.


.: 20.00 Lakhs,vide District Collector, West Godavari Proceedings No.88/Dy SO/TSRL/MPLADS/2015-16,Dt

Lakhs vide SE(PH), SER No.04/2015-16,Dt 05-12-2015


H) RJY ,Agt.No.12/2015-16, DT: 03.02.2016. & Value Rs.15,87,596.27
Difference Amount in
(Rs.)
Remarks
Excess

Less
Aas per site
conditions.
(Agt
Qty:199.00
Cum)

23.82

Aas per site


conditions.

1850.70
Aas per site
conditions(
Agt
Qty:97.00
Cum).

26.61

Aas per site


conditions.
(Agt
Qty:97..00
Cum)

1736.79

Aas per site


conditions.
(Agt
Qty:179.00
Cum)

11564.60

Aas per site


conditions.
(Agt
Qty:306.00
Kg)

4540.93

2951.62

As per site
requireme
nt
for
providing
culvert
bed
blocks,cov
er slabs.
(Agt
Qty:1561.
00 Kg)

Aas per site


conditions.
(Agt
Qty:13.00
Cum)

104.60

0.00

22799.67

9341.40

12849.33

Additional
item is
adopted for
obtaining
better strength
and better
finish

566.37
0.00
22757.10
22757.10

Groove cutting is
required
for
better alignment
of
expansion
joint and
BT
sealing

22799.67
285888.00
308687.67
1139.50
0.00
0.00
0.00
0.00

22757.10

309827.17

Executive engineeer(PH)
Eluru Division

Superintending Engineer(PH)
Rajamahendravaram Circle.

Deviation Statement
NAME OF THE WORK: Formation of CC road along with CC drains on either side of
Municipality.
Agency : Sri.G.N.Sasanka, Tadepalligudem.
Agreement.No : S.E(PH) RJY ,Agt.No.11/2015-16, DT: 03.02.2016. &
Value Rs.23,57,884.41
E.C.V : Rs.27,80,851.96 Tender Percentage : (-) 15.21%

S.N
o

proposed Bhimavaram Bypass road (150 mts length) between l4th

Adminstrative Sanction Rs.: 30.00 Lakhs,vide District Collector, West Godavari Proceedin
15,Dt 26-11-2015

Technical Sanction : 30.00 Lakhs vide SE(PH), SER No.03/2015-16,Dt 05-12-2015


Work Entrusted vide S.E(PH) RJY ,Agt.No.11/2015-16, DT: 03.02.2016. & Value Rs.23,57
As per Sanctioned Estimate

Description of work
Qty
Earthwork in excavation for structures as per drawing and echnical
specifications Clause 305.1 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
aterial and disposal upto a lead of 50 m, dressing of sides and
ottom and backfilling in trenches with excavated suitable material
as per Technical Specification 305 MORD / 304 MORTH for 310.00
foundations etc., complete as per S.S and as directed by the
departmental officer in charge of the work.
Qty V.P.No.13 of 1203 B

Carting of excavated earth with a lead of 1 KM including nloading


etc., complete as per S.S and as directed by the departmental
fficer in charge of the work.
Qty V.P.No.
of 1203 B

and 17

93.00

Providing, laying, spreading and compacting Construction of


granular sub-base by providing Stone dust laying,spreading with
motor grader in uniform layers on prepared surface in subbase/base course on a well prepared sub-base and compacting
with smooth wheel roller of 80 to 100kN / Vibratory Roller 80-100
kN weight to achieve the desired density including lighting,
barricading and maintenance of diversion,hire charges of
machinery , fuel charges, wages of driver etc complete as per
Tables 400.11 & 400.12 and Technical Specification Clause 406 143.00
MORD / MORTH. and as directed by the departmental fficer in
charge of the work.But excluding cost of seigniorage charges.
Qty V.P.No.45 of 1203 B

As per Execution

Rate in Rs

Per

Amount in
(Rs)

Qty

Rate in Rs

Per

158.81

1 Cum

49231.10

255.94

158.81

1 Cum

31

1 Cum

2883.00

0.00

31

1 Cum

141.79

1330.70

1 Cum

1330.70 1 Cum 190290.10

Providing Concrete for Plain /reinforced cement concrete in open


foundations
using 40mm nominal size Graded hard stone
aggregate , mechanically mixed , placed in founadation and
compacted by vibration including curing for 14 days complete as
per drawings and technical specifications clause 802,803,1202 &
1203 MORD and 1500, 1700 & 2100 MOTH and other incidental
charges etc., complete and as directed by the departmental fficer 143.00
in charge of the work.But excluding cost of seigniorage
charges.P.C.C(1:3:6)
Qty V.P.No.48 of 1203 B

Construction of un-reinforced, plain cement concrete pavement,


thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M35 (Grade)
Design Mix, coarse and fine aggregates conforming to IS : 383,
maximum in a concrete mixer of not less than 0.2 cum capacity
and appropeiate weigh batcher using approved mix design, laid in
approved fixed side formwork (steel channel, laying and fixing of
125 mictron thick polythene film, wedges, steel plates including
levelling the formwork as per drawing), spreading the concrete with
sholvels, rakes, compacted using needle, scareed and plate
vibrators and finished in continuous operation including provision 265.00
of ntraction and expansion, construction joints, applying debonding
strips, primer, sealant, dowel bars, near approaches to bridge /
culvert and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified)
and water finishing to lines and grade as per drawing
and
Technical Specification Clause 1501 MORD. item RBR-CCPV-5 of
standard data etc., complete as per S.S and as directed by the
departmental officer in charge of the work.But excluding cost of
seigniorage chaegrs.
Qty V.P.No.12 of 1064 B

Supply and delivery of M.S dowel bars of S 240 grade including


cost and conveyance to site and placing in position as per S.S and
as directed by the departmental officer in charge of the work.
A) Cross 143/20=7.15 joints 25 mm dia @ 27 cm C/C 5.80/0.27
21.48 x7x0.50x3.858 Kg=290.06 Kg
B) Tie bars-10 mm dia @ 30 cm C/C 45 cm length
(14300/30=476.66) 476.66x0.45*0.617 Kg=132.346 Kg
Qty V.P.No.32 of 1203 B

450

4341.98 1 Cum 620903.14

137.90

4341.98

1 Cum

6646.32 1 Cum 1761274.80

261.66

6646.32

1 Cum

449.89

50.41

1 Kg

50.41

1 Kg

22684.50

Providing High Yield Strength Deformed (HYSD)/ Thermo


Mechanically Treated (TMT) / Mild steel (MS) steel bars (Fe 415/ Fe
500 grade as per IS 1786-1979) of different diameters for RCC
works , including labour charges for straightening, cutting, bending
to required sizes and shapes, placing in position with cover blocks
of approved materials and size and tying and lap-splicing with
binding wire of 18 SWG, forming grills for reinforcement work as
per approved designs and drawings, including cost and conveyance
of steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as 2372.00
cutting, bending, placing in position, tying including sales and other
taxes on all materials etc., complete for finished item of work in all
floors. ( APSS No.126) for Dewel Bars) (Mild steel dowel bar 25mm
dia of grade S 240. 500 mm long @ 25 cm c/c for expansion and
longitudinal joints and at construction joint including 5 per cent
wastage)
For road= longitudinal direction- 8 mm dia @ 30 cm c/c 20
(575/30=19.16 ) x143x0.395 Kg=1082.25 Kg.
For road =Trans direction - 8 mm dia @ 30 cm c/c
500
(14300/30=476.666)x5.75x0.395 Kg=1082.63 Kg
Qty V.P.No.50 of 1203 B
Granular sub-base/base/surface course with local materials (Table
400.13) by mix in place method normal Construction of granular
sub-base by providing local material spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place
method with with hand roller com[lete as per Technical
Specification Clause 408 MORD and other incidental charges etc
32.00
complete as per SS and as directed by the departmental officer in
charge of the work.(For Berms)
Qty V.P.No.50 of 1203 B

Sub Total
Supplimentary Items.
Vaccum Dewatered Flooring.Fixing of channels, levelling the
concrete with beam vibrator, vacuum dewatering power trowelling
to finish as per the directions of Engineer-in -Charge, rate inclusive
of labour charges all complete for finished item of work.
Qty V.P.No.34 of 1203 B

Carrying cut groove cutting 75mm deep with petrol driven saw as
per the directions of Engineer-in-Charge, rate including of labour
10 charges, machinery charges all complete for finished item of work
Qty V.P.No.13 of 1064 B

50.89

1 Kg

120711.08

2509.36

50.89

1 Kg

402.32

1 Cum

12874.24

29.64

402.32

1 Cum

825.47

36.12

1 Sqm

13.05

65.10

! Sqm

2780851.96

Culverts
Dismantling of exisiting structurs like culverts , bridges, retaining
walls and other structure comprising of masonry , cement concrete,
wood work, steel work, including T&P and scaffolding wherever
necessary , sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
11
all lifts and lead of 1000m as per Technical specification , RBRSTCL-5(B), taking out put=1.25cum.
Qty V.P.No.46 of 1203 B

Plastering 20 mm thick single coat in CM 1:4 including cost and


conveyance of all materials like cement, sand, water etc. to site
including seigniorage charges, sales and other taxes on all
materials, and all operational, incidential charges on materials and
12 including cost of all labour charges for mixing motor, finishing,
curing as directed by engineer-in-charge etc. complete for finished
item of work (SS 901, 903 & 904)
Qty V.P.No.47 of 1203 B
Removal of wet silt and sludge from sullage drains with aid of
baskets and vessels.
13 10 Cum Rs.1755.00 (Page No.289/372 of Common S.O.R 2015-16)
Sl No.40
Qty V.P.No.46 of 1203 B

Assistant Engineer(PH)
Tadepalligudem Section.

1 Cum

75.92

201.85

1 Sqm

2780851.96
0.00
2780851.96
139043.00
39100.00
4000.00

20

As per sanctioned estimate


As per Execution
Difference

453.73

12.70

14 Total Value
15 Tender percentage @15.21%(Less)
16 Total Value
17 Provision for VAT @ 5%
18 Provision for seigniorage charges.
Provision for MPLADSsign Board carrying the description "MPLADS
19 WORK" with the name of honourable MP, including funds details.
Provision for Innaguration.
Vide Pageno.18 of 1064 B
21 Provision for unforeseen items.
22

6.98

4000.00
33005.00
2999999.96

Total Value
2999999.96
2555883.27
444116.69

Excess
Less
Difference

Deputy Executive Engineer(PH)


Eluru Sub-Division.

175.50 1 Cum

Superintending Engineer(PH),
Rajamahendravaram circle.

eviation Statement

proposed Bhimavaram Bypass road (150 mts length) between l4th

and 17th Wards in Tadepalligudem

ve Sanction Rs.: 30.00 Lakhs,vide District Collector, West Godavari Proceedings No.224/Dy SO/GGR/MPLADS/2014-2015

nction : 30.00 Lakhs vide SE(PH), SER No.03/2015-16,Dt 05-12-2015


ted vide S.E(PH) RJY ,Agt.No.11/2015-16, DT: 03.02.2016. & Value Rs.23,57,884.41
Difference Amount in
(Rs.)

As per Execution
Amount in
(Rs)

Excess

Remarks

Less
As per site
requiremen
t.

40645.83

8585.27

As per site
requirement

0.00

2883.00
As per site
requiremen
t

188679.95

1610.15

As per site
requirement

598759.04

22144.10

As per site
requirement

1739076.09

22198.71

As per site
requirement

22678.95

5.55

As per site
requiremen
t
for
providing
culvert bed
blocks,cove
r slabs.

127701.33

-6990.25

As per site
requirement
considering
on one side
of the road.

11924.76

2729465.95

29815.98

849.56

949.48

0.00

29815.98

849.56

51386.01
Additional item
is adopted for
obtaining better
strength
and
better finish

Groove cutting is
required
for
better alignment
of
expansion
joint and
BT
sealing

3167.04

15324.45

2228.85

Reconstructio
n of existing
culvert
is
required for
maintaining
the
proper
levels of the
road

3167.04

As per site
requiremen
t over
culvert vent
portion.

15324.45

Necessiated to
carry out
plastering over
inside of culvert
surface.

2228.85

2780851.83

51385.88

-422967.56
2357884.27
117894
39100.00

422967.56
51385.88 474353.57
21149.00
0.00

51386.01

4000.00

0.00

4000.00

0.00

33005.00
2555883.27

0.00
51385.88 495502.57

51385.88
495502.57
444116.69
Executive engineeer(PH)
Eluru Division

Superintending Engineer(PH),
Rajamahendravaram circle.