Beruflich Dokumente
Kultur Dokumente
RTW
for the control system
Hypersim
(real-time or off-line)
Design
Optimization
Detailed
Power System
&
Controls
488
0-7803-7322-7/02/$17.00 (c) 2002 IEEE
Phasor solution method. This technique used by transient stability softwares for study of electromechanical
oscillations (in the 0.02Hz - 2 Hz range) is the fastest method. Differential equations are used to represent the
low frequency modes related to generators, prime movers and regulators, whereas the network and voltagesourced converters are simulated by a set of algebraic equations and voltage or current sources at fundamental
frequency. For these low frequencies a time step of one cycle is sufcient.
Average modeling technique. For study of switching transients and interaction of controls with power system
(10 Hz to a few kHz), state-space modelling must be used for the entire system. In addition, each time a switch is
operated the state-space model of the linear system must be reevaluated. One particularity of FACTS and PQ
devices is the large number of switchings required at every cycle, thus increasing the computation load. For
example, a UPFC using two 48-pulse, 3-level GTO converters requires a minimum of 72 switches operated at
every cycle. For custom power devices the converter topology is much simpler but the switching frequency is
relatively high (For example, in an IGBT, PWM, 2-level inverter using 6 switches operated at 1.8 kHz, there are
up to 180 switchings per cycle). If the high order harmonics generated by voltage-sourced converters is not
important, these devices can be replaced by simple voltage sources producing the same average voltage over one
cycle of the switching frequency. This method allows using relatively large time steps (in the order of 50s).
Detailed modelling. The most accurate method requiring simulation of all switches is obtained at the expense of
reduced time step. For example, with a PWM converter using a 2 kHz switching frequency, harmonics are modelled with an acceptable accuracy with ideal switches and 2s time steps. If switching losses have to be simulated precisely, detailed switch models such as those available in PSpice must be used, requiring time steps as
low as 0.1 s.
During this presentation, the three solution methods will be illustrated with a FACTS controller (SVC using the phasor solution method) and with a custom power controller (DSTATCOM using the average and detailed modelling).
3. Example of transient stability study using the Phasor solution method
The PSB diagram of Figure 2 shows a simple 500-kV transmission system with two power plants and a 200-Mvar
SVC providing voltage support at the middle point of the 700-km transmission line.The two hydraulic power plants
are modeled by equivalent machines including detailed representation of turbine, speed regulator, voltage regulator
and power system stabilizer (PSS). The phasor approach has been used to study the transient stability of this system
and to optimize SVC controls and rating.
A
Pm
L1 350 km
Fault
AG
SVC
200 Mvars
C
Vf
Pref
0.9526
2
3
L2 350 km
A
B
C
U(E)
A
B2
M1 1000 MVA
1000 MVA
13.8 kV/500 kV
1
3
V1meas(pu)
C
m_pu
A
A
B
CB
bc
C
bc
Vf
B(pu)
Pm
U(E)
Load
5000 MW
Vabc
Mag & Angle
Pm
Fault Breaker
V SVC (pu)
Pref1
Vf
Turbine &
Regulators M1
w1 w2
Vt1 Vt2
5000MVA
13.8 kV/500 kV
d_theta1_2 (deg)
Vf
w1 w2 (pu)
Pref
0.8110
Pref2
Machines
stop
Machine
Signals
M2 5000 MVA
Pm
d_theta1_2
B
m_pu
SVC
Powergui
Phasors
Turbine &
Regulators M2
STOP
Stop Simulation
if loss of synchronism
Figure 2 PSB diagram of a 500-kV transmission system used for transient stability study
of two power plants with SVC and PSS
Simulation results obtained with SVC and without SVC for a 3-phase, 6-cycle fault applied at the machine 1 side of
the transmission line are compared on Figure 3. Waveforms show that the system is unstable without SVC. In order to
show how the phasor solution dramatically speeds up simulation, the same simulation without SVC has been performed both with the phasor solution method (variable time step with a maximum time step of 1 cycle) and with the
detailed model using discretization (50 s time steps). For simulating 5 seconds on a Pentium III 500 MHz, simulation times are 10 s and 218 s respectively, corresponding to a 22X gain speed for the phasor method.
2
489
0-7803-7322-7/02/$17.00 (c) 2002 IEEE
d theta12 (deg)
200
No SVC ; PSS
(unstable)
100
0.5
w1 (pu)
1.02
1.5
2.5
No SVC
(unstable)
3.5
4.5
4.5
4.5
4.5
Speed of Machine 1
with SVC
0.98
1.5
0.5
3.5
2.5
V SVC (pu)
No SVC
with SVC
0.5
1.5
2.5
3.5
SVC Susceptance
with SVC
No SVC
0
1.5
0.5
2.5
Time (s)
3.5
Figure 3 Impact of SVC on stability of the two-machine system for a 3-phase fault
4. DSTATCOM simulation using the average and detailed modeling techniques
The second example uses a custom power controller to compare the average and detailed modeling techniques. The
PSB diagram shown in Figure 4 represents a 25-kV distribution network with a load connected at bus B4 (600 V). A
3-Mvar D-STATCOM is connected at bus B3. The D-STATCOM is used to regulate the bus voltage by absorbing or
generating reactive power to the network.The PSB diagram shows the following components:
a 25/2.5-kV coupling transformer which ensures the coupling between the PWM inverter and the network
a voltage-source PWM inverter consisting of two IGBT bridges. This twin inverter conguration produces less
harmonics resulting in smaller lters and improved dynamic response. In this case, the inverter modulation frequency is 1.68 kHz so that the rst harmonics will be around 3.36 kHz.
a group of lters consisting of a series inductance of 800 H connected at the output of Bridge 1 and a capacitor of 100 F in series with a resistance to provide a quality factor of 40 at 60 Hz. This RC lter is connected to
the secondary side of the coupling transformer.
a 10000-F capacitor acting as a DC voltage source for the inverter
a voltage regulator that controls the voltage at Bus B3
a PWM pulse generator using a modulation frequency of 1.68 kHz
anti-aliasing lters used for voltage and current acquisition
D STATCOM
25kV, +/ 3Mvar
Ts=1/60/360/8
B1
B2
Tr1
A A
A A
B B
B B
C C
C C
B3
1 MW
Variable
Load
C1
C C
C2
C1+
B C+
B2
B1
A B
C2+
B1+
C+ B+
A2
A1
B2+
A1+
B+ A
Filter
pulses
pulses
Bridge1
Iabc
Bridge2
VaIa
P2
1
Multimeter
(DC Link)
Load
(Y)
Vabc
P1
Iabc_B3
A+ A+
A2+
3 MW
0.2 Mvar
Vabc_B3
A A
B B
C C
A
B
C
BB
CC
Feeder
2 km
Feeder
21 km
AA
25 kV, 100MVA
System
A
B
C
PSB
Prog. Source
B4
a
b
c
n
A
B
C
Discrete system
Ts=5.787e006
Vdc
DC Link
Va_Inv
Iq_Iqref
Statcom
controller
PQ
Vdc
m
VaIa (pu)
Va Inv (V)
P,Q (MVA)
Vdc (V)
m
Data Acquisition
Sig1
Iq,Iqref (pu)
Sig2
Waveforms of Figure 5 show the dynamic performance of the DSTATCOM when a voltage step is applied on the 25kV equivalent .The reactive current component Iq and the instantaneous current waveform are shown respectively on
traces 1 and 3. Trace 2 shows the DC bus voltage variation and trace 4 shows the output voltage of the voltage converter. Two simulations have been performed: 1) simulation using the average modeling technique (IGBT converter
simulated by voltage sources, using a 5.8 s time step and 2) detailed simulation including all IGBT switches using a
time step 8 times larger (46.3 or s). Results are compared on each trace of Figure 5. The difference between the two
simulation methods is clearly shown on the last trace showing the PWM chopped voltage superimposed with its average value. Result show no noticeable difference during transients, proving that the average modeling technique provides a substantial speed gain, while preserving the network/control interactions.
Iq (pu)
Vdc (V)
1
0.18
2600
0.185
0.19
0.195
0.2
0.205
0.21
0.215
0.22
0.225
0.23
0.185
0.19
0.195
0.2
0.205
0.21
0.215
0.22
0.225
0.23
0.185
0.19
0.195
0.2
0.205
0.21
0.215
0.22
0.225
0.23
0.185
0.19
0.195
0.2
0.205
0.21
0.215
0.22
0.225
0.23
2400
2200
0.18
Ia STAT
Va Inv (V)
1
0.18
2000
2000
0.18
4
491
0-7803-7322-7/02/$17.00 (c) 2002 IEEE