Design Manual
EXECUTIVE SUMMARY
This Kansas Department of Transportation (KDOT) Design Manual has been compiled for the
Bureau of Structures and Geotechnical Services from the existing design manuals of the Roads
Section, Coordinating Section, Bridge Section, and the Bureau of Right of Way. Although these
manuals have been consolidated for consistency of style and format, the essential integrity of each
volume has been maintained. This manual should allow each employee and consultant of the
Bureau of Structures and Geotechnical Services to contribute to a uniform and consistent application of KDOT procedures.
In all four volumes, many of the subjects simply highlight the design criteria and procedures;
however, it is not intended the manuals be all-inclusive. An individual using these manuals is still
responsible for their own understanding of their functions.
KDOT DESIGN MANUAL ORGANIZATION
The KDOT Design Manual is organized into the following four volumes:
Volume I, Road Section, is divided into three parts: Part A, "Procedures for Preparation of Highway Plans"; Part B, "Instructions to Road Designers"; and Part C, "Elements of Drainage and Culvert Design." Part A addresses procedures for the preparation of Grading Plans or Grading and
Surfacing Plans Combined and the preparation of Surfacing Plans. The order of topic discussion
of this part corresponds closely to the order of occurrence of the activities required in the process
of plan preparation. The chapters in Part B discuss General Instructions, Drafting, Grading, and
Surfacing. Part C provides the technical information and procedures required for the design of
culverts, median drains, channels, and erosion protection, which are necessary for the control of
highway surface waters.
Volume II, Coordinating Section, covers subjects ranging from KDOT policy regarding
employee conduct toward the general public; safety issues related to handling tools and the problems common to the outdoor work environment (exposure to the elements, insects, snakes, poison
ivy, etc.); general surveys; and horizontal control surveys.
Volume III, Bridge Section, provides general guidelines, including detailed procedures and
instructions, for the design and preparation of bridge plans and specifications. The topics intro-
Bridge Section
ES - 1
Design Manual
duced in this volume include plans for Preliminary Design; Analysis and Design; Bridge Load
Rating; and Falsework Design, Analysis, and Inspection.
Volume IV, Bureau of Right of Way, offers KDOT procedures and policy for acquisition of
properties, whether by purchase, condemnation, or other forms of possession. This volume shows
example maps, plats, plans, computer programs, descriptions, and surveys to be used as guidance
for personnel in the Bureau of Right of Way.
Over time, KDOT procedures and policies may change as a result of the introduction of new technologies, new findings in research, or the development of new products. As these changes occur,
the KDOT Design Manual will be revised to reflect current conditions and practices.
KDOT is a multi-modal transportation agency, with its primary objective the construction and
maintenance of Kansas highways. The Bureau of Structures and Geotechnical Services plays an
essential role in achieving objective. Nevertheless, it must be recognized the citizens of the state
of Kansas possess ultimate authority over the Department of Transportation.
Bridge Section
ES - 2
Design Manual
Bridge Section
ES - 3
Design Manual
Page #
Bridge Section
R-1
Design Manual
AASHTO
ABUTMENT
ACI
AADT
ADTT
AHW
ANSI
APRON
AISC
AREMA
ASTM
AWS
BACKWATER
Bridge Section
AB - 1
Design Manual
BASE FLOOD
BASE SHEETS
Drawings used by the Bridge Office which can be inserted into a set
of plans with minor modifications.
BATTER PILE
BEARINGS
BEARING
STIFFENER
BENCH MARK
BLOCKING
DIAGRAM
BRASS
BRIDGE
BRIDGE
APPROACH
BRIDGE LOG
A listing of all the bridges on the State System and City Connecting
Links in Kansas. Basic information on each bridge is given.
A listing of pertinent information on bridges located on the State
System. Information includes bridge location, structural data,
inspection and appraisal data, roadway information, feature
crossed, repair projects and Sufficiency and Load Rating.
Bridge Section
AB - 2
Design Manual
BRIDGE PACKET
BROMS
BUTT SPLICE
CAISSON
CAMBER
CAPWAP
CAUSEWAY
CE
CFR
CHANGE ORDER
CLASS I
EXCAVATION
Bridge Section
AB - 3
CLASS II
EXCAVATION
CLASS III
EXCAVATION
Design Manual
C-I-P
Cast-in-Place
CMS
COFFERDAM
COMPOSITE
SECTION
COMPRESSION
SEALS
CONSTRUCTION
JOINT
CONTRACT
CONTRACTION
JOINT
CPMS
CREEP
CROSS FRAMES
Bridge Section
AB - 4
Design Manual
CROWN GRADE
CULVERT
CURB
DEADMAN
DE-BONDED
STRANDS
DECK
STRUCTURE
DEFLECTION
JOINT
DEIS
DESIGN CHECKER -
DESIGNER
DOA
DWR
DRAPED
STRANDS
Bridge Section
AB - 5
Design Manual
DRIFT PIN
DRIP GROOVE
DUMMY JOINT
EPOXY COATED
Elastic Modulus
EA
Environmental Assessment.
ENR
EWS
EXCAVATION
BOUNDARY
PLANE
EXPANSION
BEARINGS
EXPANSION
DEVICE
EXPANSION
JOINTS
FBFM
FEIS
FEMA
Bridge Section
AB - 6
Design Manual
FENL-H
FHBM
FHPM
FHWA
FILLER
PLATE
FIRM
FIS
500 SERIES
FLAT SLAB
FLOOD
FLOOR BEAM
FONSI
FORM 310
FORM 883
Bridge Section
AB - 7
Design Manual
GEOTEXTILES
GIRDER
GRADE
SEPARATION
GRINDING
GROOVING
HAC
HAMMERHEAD
PIER
A pier which has only one column with a cantilever cap and is
somewhat similar to the shape of a hammer.
HANGER PLATE
HAUNCH
HAUNCHED SLAB -
HEC-2
HEC-18
HEC-20
HEC-23
Bridge Section
AB - 8
HINGE
Design Manual
HINGED BEARING -
HOLDDOWN
DEVICE
HYBRID GIRDER
HW
High Water
INLET CONTROL
INTEGRAL
ABUTMENT
INTERMEDIATE
STIFFENER
KDA
KDHE
LAMINATED
ELASTOMERIC
BEARING
LATERAL
BRACING
LEADS
The vertical members of a pile driver which steady the hammer and
pile during the driving.
LFD
Bridge Section
AB - 9
Design Manual
LIQUID
PENETRANT
INSPECTION
LONGITUDINAL
STIFFENER
LOW RELAXATION
STRANDS
LRFD
MAG PARTICLE
INSPECTION
MODULAR EXP.
JOINTS
MSE
MUD SILL
NCHRP
NEGATIVE
MOMENT
NEGATIVE
REINFORCEMENT
NEPA
NEW
NHI
NHS
Bridge Section
AB - 10
NON-REDUNDANT STRUCTURE
NRCS
Design Manual
ORDINARY HIGH WATER-The ordinary high water is the line on the shore established by the
fluctuation of water and indicated by physical characteristics such as
a clear, natural line impressed on the bank, shelving, changes in the
character of soil, destruction of terrestrial vegetation, the presence
of litter and debris, or other appropriate means that consider the
characteristics of the surrounding area. Ordinary high water will
normally be established by a field survey of the site. Where ordinary
high water is not determined by survey of the physical
characteristics, it may be established by use of the Alternate
Procedure.
Taken from Elements of Drainage & Culvert Design, Road Section Design Manual, Volume I
(Part C). Kansas Department of Transportation. May 2011 Edition.
OUTLET
CONTROL
PS&E
PARAPET
PCI
PDA
PE
Professional Engineer.
PIER
Bridge Section
AB - 11
Design Manual
PILE
PILE BENT
PILE CAP
POSITIVE
MOMENT
A pier where the piles are extended to the pier cap to support the
structure. See 11.5.2 Pile Bent Piers
A slab, usually of reinforced concrete, covering the tops of a group
of piles for the purpose of tying them together and transmitting to
them as a group the load of the structure which they are to carry.
In a girder the moment causing compression in the top flange
and tension in the bottom flange.
POSTTENSIONED
PRESTRESS
CAMBER
PRESTRESSED
CONCRETE
PRETENSIONED
PROFILE GRADE
The road grade along a consistently defined point on the road crosssection.
PROJECT
SPECIAL
PROVISIONS
PVC
Q 500,Q100, Qn
Bridge Section
AB - 12
RADIOGRAPHIC
INSPECTION
Design Manual
RCB
Reinforced Concrete Box. See 12.1.1 Definitions
RECURRENCE INTERVAL - (1) The average time interval between floods that equal or exceed
OR RETURN PERIOD
a specified magnitude, or (2) the reciprocal of the probability that
a flood of a specified magnitude will occur in any given year.
The first definition, the partial duration series, is used for rainfall
depth-duration-frequency estimates such as those published in the
NWS rainfall
frequency atlases and the KDOT Rainfall Tables
for Counties in Kansas.
The second definition, the annual exceed an ce probability interval.
is used for flood discharge-frequency applications. The two
definitions are essentially equivalent for recurrence intervals of 10
years or greater.
REDUNDANT
STRUCTURE
REGULATED
FLOODWAY
REHABILITATION
REPAIR
RFB
REPLACEMENT
RIPRAP
RMS
Bridge Section
AB - 13
Design Manual
ROLLED GIRDER
STRUCTURE
R/W
SBO
Right of Way
State Bridge Office
SHEAR
CONNECTOR
SHEET PILE
SHRINKAGE
SHRP
SKEW OR SKEW
ANGLE
SILICA FUME
OVERLAY (SFO)
SLD
SPECIAL
PROVISIONS
SPECIFICATIONS (CONSTRUCTION)
SPECIFICATIONS
(DESIGN)
Bridge Section
AB - 14
Design Manual
SPREAD FOOTING -
SPUR DIKE
(or GUIDE BANK)
SRO
SSPC
STANDARD
SHEETS
STRESS
RELIEVED
STRANDS
STIRRUP
STRIP SEAL
JOINT
SUBSTRUCTURE
The part of the structure below the bridge seats or below the tops of
the caps of piling.
SUPER-
That part of the structure above the bridge seats or above the
STRUCTURE
SUPPLEMENTAL
SPECIFICATIONS
Bridge Section
AB - 15
Design Manual
SURCHARGE
TCLP
TECH 11
TECH 40
TO
THALWEG
TRB
TENDON
TINING
THROUGH
STRUCTURE
TRANSFER
STRESSES
ULTRASONIC
INSPECTION
Bridge Section
AB - 16
Design Manual
UPLIFT
USACE
USGS
WEARING
SURFACE
WEAP
WEEP HOLE
WEIR
WELD
INSPECTION
WELDED WIRE
FABRIC
WINGWALL
WSE
WSPRO
Bridge Section
AB - 17
Design Manual
REFERENCES
The following pages contain a list of manuals, specifications and codes used by the KDOT Bridge Office in the
design of structures.
Annual Interim Specifications are generally used by the States after their adoption by the Subcommittee. Orders for
these annual Interim Specifications may be placed by visiting our web site, bookstore.transportation.org; calling the
AASHTO Publication Sales Office toll free (within the U.S. and Canada), 1-800-231-3475; or mailing to P.O. Box
96716, Washington, DC 20906-6716. A free copy of the current publication catalog can be downloaded from our
website or requested from the Publications Sales Office.
Attention is directed to the following publications prepared and published by the Subcommittee on Bridges and
Structures:
AASHTO LRFD Bridge Design Specifications 6th Edition, 2012
AASHTO Guide for Commonly Recognized (CoRe) Structural Elements. 1998.
AASHTO Guide Specifications for Horizontally Curved Steel Girder Highway Bridges with Design Examples for I-Girder and Box-Girder Bridges. 2003.
AASHTO Guide SpecificationsThermal Effects in Concrete Bridge Superstructures. 1989.
AASHTO LRFD Bridge Construction. 1998.
AASHTO LRFD Movable Highway Bridge Design. 2004.
Bridge Data Exchange (BDX) Technical Data Guide. 1995.
Bridge Welding Code: AASHTO/AWS-D1.5M/D1.5: 2002, an American National Standard. 2002.
Construction Handbook for Bridge Temporary Works. 1995.
Guide Design Specifications for Bridge Temporary Works. 1995.
Guide for Painting Steel Structures. 1997.
Guide Manual for Condition Evaluation and Load and Resistance Factor Rating (LRFR) of Highway
Bridges. 2003.
Guide Specifications and Commentary for Vessel Collision Design of Highway Bridges. 1991.
Guide Specifications for Alternate Load Factor Design Procedures for Steel Beam Bridges Using Braced
Compact Sections. 1991.
Guide Specifications for Aluminum Highway Bridges. 1991.
Guide Specifications for Bridge Railings. 1989.
Guide Specifications for Design and Construction of Segmental Concrete Bridges. 1999.
Guide Specifications for Design of Pedestrian Bridges. 1997.
Guide Specifications for Fatigue Evaluation of Existing Steel Bridges. 1990.
Guide Specifications for Highway Bridge Fabrication with HPS070W Steel. 2000.
Guide Specifications for Seismic Isolation Design. 1999.
Guide Specifications for Strength Design of Truss Bridges (Load Factor Design). 1986.
Guide Specifications for Strength Evaluation of Existing Steel and Concrete Bridges. 1989.
Guide Specifications for Structural Design of Sound Barriers. 1989.
Guide Specifications for the Design of Stress-Laminated Wood Decks. 1991.
Guidelines for Bridge Management Systems. 1993.
Manual for Condition Evaluation of Bridges. 2000.
Movable Bridge Inspection, Evaluation and Maintenance Manual. 1998.
Standard Specifications for Movable Highway Bridges. 1988.
Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals. 2001.
Additional bridges and structures publications prepared and published by other AASHTO committees and
task forces are as follows:
Guide Specifications for Cathodic Protection of Concrete Bridge Decks. 1994.
Guide Specifications for Polymer Concrete Bridge Deck Overlays. 1995.
Guide Specifications for Shotcrete Repair of Highway Bridges. 1998.
Inspector's Guide for Shotcrete Repair of Bridges. 1999.
Manual for Corrosion Protection of Concrete Components in Bridges. 1992.
Bridge Section
AB - 18
Design Manual
Two Parts: Guide Specifications for Concrete Overlay Pavements and Bridge Decks. 1990.
AASHTO Maintenance Manual: The Maintenance and Management of Roadways and Bridges. 1999.
The following bridges and structures titles are the result of the AASHTO-NSBA Steel Bridge Collaboration
and are available for free download from the AASHTO web site, bookstore.transportation.org:
Design Drawing Presentation Guidelines. 2003.
Guidelines for Design Constructibility. 2003.
Guide Specification for Coating Systems with Inorganic Zinc-Rich Primer. 2003.
Shop Detail Drawing Presentation Guidelines. 2003.
Shop Detail Drawing Review/Approval Guidelines. 2003.
Steel Bridge Fabrication Guide Specification. 2003.
Steel Bridge Fabrication QC/QA Guide Specification. 2003.
Bridge Section
AB - 19
Design Manual
Abbreviated
Table of Contents
1 INTRODUCTION
2 PRELIMINARY DESIGN
3 LOADS AND LOAD FACTORS
4 ANALYSIS
5 CONCRETE
6 STEEL
8 BRIDGE DECK DRAINAGE
9 DECK SLAB
10 FOUNDATION
11 AUTMENTS, PIERS AND WALLS
12 BURIED STRUCTURES
13 RAILINGS
14 EXPANSION JOINTS AND BRIDGE BEARINGS
15 BRIDGE LOAD RATING
16 FALSEWORK DESIGN, ANALYSIS AND INSPECTION
APPENDIX
Detailed Table of Contents precede each section.
Figures, tables are denoted by their home article number and an extension,
for example Figure 3.2.1-1 is the first figure in section 3.2.1.
Bridge Section
Table of Contents - I
Design Manual
1 INTRODUCTION
Table of Contents
1.0 Purpose and Scope ..................................................................................................................1
1.1 LRFD Development ................................................................................................................2
1.2.1 K.S.A. 68-1101 Definitions; concrete overflow bridge or ford as a bridge. .........5
1.2.2 K.S.A. 68-1108 Standard specifications. ..............................................................5
1.2.3 K.S.A. 68-1109 Roadway and grade of bridges and culverts on county and township roads and on highways over railroad tracks. .........................................6
1.2.4 K.S.A. 68-1111 Approval of plans by county engineer or state engineer. ............6
1.2.5 Approval of Plans by Federal Highway Administration .......................................6
1.2.5.1 Section 1805. Use of Debris from Demolished Bridge and Overpasses................... 8
1.2.5.2 Overdimensional Load Information ..........................................................................9
List of Attachments
Attachment 1.2.6-1 Overhead Submittal Checklist. .....................................................................12
List of Figures
Figure 1.2.6-1 Railroad Protective Liability Insurance ...............................................................16
Figure 1.4-1 BR025a RCB Auxiliary Details (Embedded Structure) .......................................... 25
Figure 1.4-1 Corps of Engineers, Kansas City District ................................................................29
Figure 1.4-2 Divisions and Districts for Regulatory Activities .................................................... 30
Figure 1.6-1 Structure Codes ........................................................................................................33
Figure 1.6-2 AASHTO Denfinition of Bridge Preservation .........................................................34
Bridge Section
1-i
Design Manual
1 INTRODUCTION
1.0 Purpose and Scope
The KDOT LRFD Design Manual was developed to provide guidance on design activities for the
various levels of federal aid streets and highways in Kansas, from the Interstate system to local
streets and highways. The layout of the chapters follows the layout of the AASHTO LRFD Bridge
Design Specifications. This layout is intended to highlight and emphasize articles were applicable
within each section and define differences or preferred methods were more than one method is
available.
The purpose of the Bridge Manual is to provide general guidelines, including procedures and
instructions, for the design and preparation of bridge plans and specifications for the Kansas
Department of Transportation (KDOT). While it is the intent for the manual to provide uniformity
in design and define bridge design policy, it does not preclude exceptions and deviations where
justified; however, these are subject to the approval. For an appropriate structure to be selected
for a particular site, a combination of sound engineering principles, experience, and judgment is
required.
The design practices in this Manual have been established primarily for application to short
and medium span bridges and other highway related structures using conventional construction
methods. These practices may not, in some cases, be applicable to long spans, major river crossings or multi-level interchange complexes. For design requirements not described in this Manual,
the designer should refer to the AASHTO LRFD Bridge Design Specifications and Guide Specifications.
Design guidance consists primarily of information on minimum standards to be followed in
design work for the department. General guidance from federal or national
organizations, such as the FHWA or AASHTO, is included in the manual for reference.
These chapters provide a means of conveying the departments experience in the various aspects
of design, with the expectation that this information used together with good judgement
will enable employees, consultants, or other parties doing design work to develop detail plans
with a minimum of effort and indecision. It is intended that the designer, where possible, use
KDOT Bridge Design Standard Drawings, Standard Designs and Base Sheets as starting points
for plan development, this provides the Contractor consistencies and the department with construction efficiencies through repetition and uniformity.
Many of the subjects presented only highlight some of the design criteria and procedures. It is not
intended topic discussions in the manual be all-inclusive; however, the Bridge Designer, the
Design Checker and the Detailer are responsible for a complete analysis and design for a safe,
economical, and maintainable structure. The contents of this manual should not supplant or interfere with individual incentive or the development of new concepts in the design and preparation
of plans for bridges.
1-1
Bridge Section
Design Manual
Finally, to reflect the findings in research, new products or changes in design concepts, new or
revised design and detail sheets will be issued for this manual as they are developed.
where:
R n i Q i
i = Load Factors
LRFD extends the LFD philosophy by considering the variability in the properties of structural
elements in addition to the load variability. In LRFD Design, the load and resistance factors are
chosen by the code writers based upon the theories of probability and reliability. In developing the
design specifications, considerable effort was made to keep the probabilistic aspects transparent
to the designer, and no knowledge of reliability theory is necessary to apply the specifications.
The following two major improvements on the LFD methodology result in this conversion into
probability-based LRFD:
1- 2
Bridge Section
Design Manual
Limit states (a condition beyond which a structural component ceases to fulfill its intended
function in an acceptable manner) to be considered by the designer are very similar. Some of
these are strength-oriented; typically even more are serviceability-oriented, and
Load and resistance factors (equivalent in concept to those currently specified in the Standard
Specifications) are chosen by the code writers based upon the theories of probability and reliability.
The LRFD method of design accounts for variability in both resistance and load, achieves uniform levels of safety for different limit states and bridge types, and provides a rational and consistent method of design.
R n i i Q i
where:
i = Load Modifier, Article. 1.3.2
i =Resistance Factors, Article. C3.4.1
1.1.1 Calibration
The Service limit States within the LRFD Specifications have not been calibrated and therefore
some design elements, such as foundations design are still in transition. The remainder of the
LRFD Specifications have been calibrated using a reliability index (also called the safety
index) taken as the distance (the number of standard deviations away from the mean) to the overlap of the tails. The overlap, the area bounded by the two curves, is the probability of failure of the
element being designed.
The shift in the load and resistance probabilities to obtain compliance to the Standard Specifications uses a factor equal to 3.5 which equates to a probability of failure of about 1/10,000
bridges. When more is known about the load, as in the case for a overload permit, this probability
based specification can be adjusted by changing the factor to a lesser value, for example,
because the level of uncertainty of the particular load is reduced are higher probability of failure
1-3
Bridge Section
Design Manual
may be acceptable. For conditions of where the uncertainty is reduced a factor of 2.5 may be
appropriate.
1- 4
Bridge Section
Design Manual
Structures falling outside AASHTOWare Bridge Design modeling capabilities should follow
these steps to the first workable solution.
AASHTOWare Bridge Design model acceptable workaround.
BRASS model: girder line with distribution factors listed for single and multi lane, include
truck and sections library file.
Other software: provide a STAAD model plus satisfy the rating requirements.
1-5
Bridge Section
Design Manual
1- 6
Bridge Section
Design Manual
The exemption process removes FHWA from oversight of design activities, PS&E approval and
concurrence in award and construction activities. On NHS projects, Federal requirements apply to
these activities and are to be followed (documentation of design exceptions, materials requirements, approval of change orders, etc.) although specific FHWA review, approval or concurrence
as appropriate is not required. As stipulated in 23 USC 109, Standards, on non-NHS projects, the
KDOT will follow State laws and procedures as they would for State funded only projects.
Bridge projects are administered in accordance with the current edition of the Bureau of Local
Projects Project Development Manual for Non-National Highway System Local Government
Road and Street Projects.
The FHWA Headquarters Bridge Division is responsible for the approval of preliminary plans for
unusual bridges and structures on the Interstate System.
Unusual bridges include those the FHWA Divisions determine have: (1) difficult or unique foundation problems, (2) new or complex designs with unique operational or design features, (3)
bridges with exceptionally long spans, or (4) bridges being designed with procedures which
depart from currently recognized acceptable practices. Examples of unusual bridges include
cable-stayed, suspension, arch, segmental concrete, movable, or truss bridges. Other examples are
bridge types which deviate from the AASHTO bridge design standards, or AASHTO guide specifications for highway bridges; major bridges using load and resistance factor design specifications; bridges requiring abnormal dynamic analysis for seismic design; bridges designed using a
three-dimensional computer analysis; bridges with spans exceeding 500 feet; and bridges with
major supporting elements of "ultra" high strength concrete or steel.
Unusual structures include tunnels, geotechnical structures featuring new or complex wall systems or ground improvement systems, and hydraulic structures involving complex stream stability countermeasures, or designs or design techniques are atypical or unique.
If FHWA approval is required, they should be involved as early as possible in the project development.
Preliminary documents submitted to FHWA Headquarters should include the preliminary design
plans and supporting data along with the Kansas FHWA Divisions review comments and recommendations. Supporting information should include bridge/structures related environmental concerns and suggested mitigation measures, studies of bridge types and span arrangements,
approach bridge span layout plans and profile sheets, controlling vertical and horizontal clearance
requirements, roadway geometry, design specifications used, special design criteria, special provisions and cost estimates. Hydraulic and scour design studies/reports should also be submitted
showing scour predictions and related mitigation measures. Geotechnical studies/reports should
be submitted along with information on substructure and foundation types. Early and complete
submissions will facilitate meaningful and expeditious reviews and approvals.
FHWA no longer requires alternate designs on major structures. However, on major structures
(over $10 million), substantial savings in bridge cost could result. Alternate plans will be considered on a project-by-project basis.
1-7
Bridge Section
Design Manual
1- 8
Bridge Section
Design Manual
It is our understanding the intent of the law is for shore erosion and marine creation. Which
KDOT does not have. Also the law states in sections (a) federal, state OR local government.
Or is the keyword here; if the intent is for Midwest states (not coastal) then in our opinion we still
are in compliance because we offer it to us (KDOT) and therefore this meets the OR portion of
the tort. It does not say AND ,meaning we would be required, if this is truly intended for the Midwest, to offer it to all the above group.
1-9
Bridge Section
Design Manual
(2) A vehicle transporting a non-divisible load in which any group or groups of axles exceed
the limitations of the standard permit.
(n) Transporting requirements - The following transporting requirements shall apply to oversize
or overweight loads.
(5) Except for incidental movements, all oversize or overweight construction machinery or
equipment shall be transported on a truck-tractor trailer, truck-tractor semi-trailer, or
truck combination. Incidental driving of construction machinery on state highways shall
be allowed, provided that the section of highway to be used is adjacent to or entirely
within the project limits or the distance traveled is less than or equal to one mile and no
bridge structures are being crossed.
1 - 10
Bridge Section
Design Manual
1 - 11
Bridge Section
Design Manual
1 - 12
Bridge Section
Design Manual
1 - 13
Bridge Section
Design Manual
1 - 14
Bridge Section
Design Manual
1 - 15
Bridge Section
Design Manual
1 - 16
Bridge Section
Design Manual
1 - 17
Bridge Section
Design Manual
Below is a list of project permits and other activities which may require design information.
(1) U.S. Coast Guard Section 9 Bridge Permit - Rivers and Harbors Act of 1899
(2) U.S. Army Corps of Engineers Section 10 Permit - Rivers and Harbors Act of 1899
(3) U.S. Army Corps of Engineers Section 404 Permit - Clean Water Act of 1977
(4) Kansas Department of Health and Environment Water Quality Certification - Clean
Water Act of 1977
(5) Kansas Department of Agriculture, Division of Water Resources; Dams, Stream
Obstructions and Channel Changes Permit - K.S.A. 82a-301-305a, and levees and floodplain fills K.S.A. 24-126.
(6) Threatened and Endangered Species Permits and Consultations: State Threatened and
Endangered Species K.A.R. 115-15-3 Action Permits and the Federal Endangered Species Act (ESA) of 1973.
(7) Environmental Documentation and correspondence involving Environmental Assessments (EA), Findings of No Significant Impact (FONSI), Categorical Exclusions (CE),
historic bridges and Environmental Impact Statements (EIS) - National Environmental
Policy Act of 1969 and Department of Transportation Act of 1966.
To determine what permits are required, it is necessary to furnish the Environmental Services
Section, at the earliest practicable date, information concerning the project type, scope and location. Additional information is required for bridge projects to include the quantity of dredge or fill
which will be discharged below ordinary highwater elevation (OHW), location and design of
shoofly detours, and proposed channel relocation work. Bridge site channel clearing, shaping and
slope protection should also be shown.
An overview of the permit process and the correspondence requirements of NEPA for highway
projects are included on the following pages.
OVERVIEW OF THE PERMIT PROCESS
The following is a recapitulation of conditions and circumstances requiring certain permits or
other actions for highway projects in Kansas.
(1) Coast Guard Section 9 Bridge Permit - Section 9, Rivers and Harbors Act of 1899.
Section 9 permits are required for bridges and causeways constructed on or in "navigable waterways in the United States." Navigable streams in Kansas are the Missouri River bordering Kansas
and the lower Kansas River. Coast Guard authority extends upstream into the tributaries of the
Missouri River to an elevation equal to the ordinary highwater elevation of the river. The permit
covers the bridge, piers, abutments, and related work in the channel. However, it does not cover
1 - 18
Bridge Section
Design Manual
the dredge and fill activities associated with the bridge or causeway. Requirements of Section 404
permits (U.S. Army Corps of Engineers) would apply to these activities; however, a nationwide
404 permit has been issued to cover the bridge activities approved by the Coast Guard under Section 9 permits.
While subject to change, exceptions to Section 9 present requirements are as follows:
(a) Repairs to a bridge which involves replacement in kind (example, US-59 bridge at Atchison);
(b) Bridges to be constructed over waterways which have been placed in the advance approval
category by the Commandant, U.S. Coast Guard - there are none in Kansas;
(c) Proposed Federal aid bridge projects which are to be funded under the provisions of Title
23, United States Code, as amended, by the Surface Transportation Assistance Act of 1987.
All exceptions are documented.
Information needed from Road and Bridge Design for Section 9 Permit
A. Preliminary Information
(1) Location of proposed project
(2) Scope of work - bridge replacement, shoofly detours, channel changes, slope protection, etc.
(3) Quantities of fill and area of impact below OHW.
1 - 19
Bridge Section
Design Manual
2. U.S. Army Corps of Engineers Section 10 Permits - Section 10, Rivers and Harbors Act of
1899
Section 10 permits are required for construction of obstructions, including dredge and fill, affecting the navigable capacity of streams designated as navigable (Missouri River and lower Kansas
River) except bridges or causeways (these are under the jurisdiction of the Coast Guard Section 9
Permit). This refers to anything constructed in, over or under a navigable stream such as drainage
structures, utility lines, jetties, etc. A Section 404 permit may also be required for fill activities
beneath ordinary high water associated with the project.
Information Needed from Road and Bridge Design for Section 10 Permits:
A. Information
(1) Location of proposed project
(2) Scope of Work - bridge replacement, shoofly detours, channel changes, slope protection, channel clearing, etc.
(3) Quantities of fill and area of impact below OHW.
Note: No asphaltic materials are allowed below OHW.
B. For Permit Application
(1) Drawings as specified in Corps' handbook
(2) Environmental Documentation
(a) Flood information (bridge)
(b) Alternatives studied (road)
(3) Name of adjacent property owners.
3. U.S. Army Corps of Engineers Section 404 Permits - Section 404, Clean Water Act of 1977.
Section 404 permits are required for all work involving the discharge of dredged or fill materials
into waters of the United States (WUS). Waters of the United States are connected waters having
an ordinary high water (OHW) mark, including streams, rivers, ponds, and lakes. Wetlands are
also considered WUS unless they are isolated. As a guide, streams shown as a blue line on United
States Geological Survey topography maps are Corps of Engineers (COE) jurisdictional. However, some ephemeral blue line streams lack a defined bed and bank and OHW mark and are not
jurisdictional. The COE has the final say on jurisdictional determinations.
Section 404 authorizes two types of permits, General permits and Individual permits (IPs).
1 - 20
Bridge Section
Design Manual
General Permits: General permits are for discharges which are considered to cause minimal
adverse environmental impacts. A Nationwide permit (NWP) is a form of General permit designed to authorize a discharge for a specific purpose, with little delay or paperwork required by the Corps. Currently there are forty-four different NWPs. Each is
intended to apply to a specific situation such as oil and gas structures, or utility line
activities. Transportation projects commonly use two NWPs, NWP 14 (road crossings), and NWP 23 (approved categorical exclusions). Nationwide Permit 14 was created for linear transportation crossings and is subject to a acre WUS loss limit.
Nationwide Permit 23 may be used for projects having an approved categorical exclusion. Nationwide permits are subject to change as they are reviewed every five years.
In 2000 one NWP was eliminated, five new NWPs were issued, six were modified,
and several NWP general conditions were altered. The trend in NWPs is toward additional environmental restrictions. Each COE District may add restrictions and/or conditions to NWPs. In Kansas the COE Kansas City District (KCD) has issued NWP
Regional Conditions and NWP Standard Operating Procedures. In 2012 NWP will
now require that all culverts, with erodible beds and greater than 48 in. in rise,be
embedded 12 and pass bankfull (Q1.0 - Q1.7) without velocity increases.
2.3.3.3 Special Requirements: USACE (US Army Corps of Engineers)
Individual Permits: Individual permits authorize discharges which are larger and are thought to
have significant effects on the environment over those authorized under NWPs. Individual permit applications require more detailed information than NWP applications.
Following acceptance of an IP application the COE issues a public notice to solicit
comments from state and federal agencies and the public. The public notice includes a
brief description of the project and gives agencies and the public 21 days to respond.
Generally, when substantive negative comments are received the COE will not issue
the IP until issues are resolved. From the time an IP application is submitted it usually
takes at least 6 months to receive the permit.
Information needed from Road and Bridge Design for Section 404 Permits:
Environmental Services staff review project plans and field inspect the location of the project
to determine if there are jurisdictional impacts. An Information Request spreadsheet identifying the station and structure is then sent to Road and Bridge. Corps of Engineers permit applications require the following information:
A. Nationwide permits Plan title sheet, cross sections, avoidance and minimization
statement, linear feet of stream work, area of impact below ordinary high water
(BOHW), footprint of fill in acres, footprint of excavation in acres if outside area of
fill, slope protection BOHW (linear feet, volume), volume (cubic yards) of other
impacts BOHW (structural fill boxes, piers, etc.), (earth fill or excavation earth,
rock, sand, etc.), area of temporary fill or excavation BOHW, existing channel to
remain open (length feet, area acres).
B. Individual permit Plans (including cross sections), avoidance and minimization statement, project purpose, reason for discharge, types of material being discharged and
1 - 21
Bridge Section
Design Manual
amount in cubic yards, surface area in acres of wetlands or other WUS filled, addresses
of adjacent property owners.
Mitigation of impacts to waters of the United States
With few exceptions the COE, KCD requires on-site mitigation for impacts to streams and wetlands. On-site means in the same watershed and as close to the impact as feasible. Wetland mitigation normally requires the construction of a replacement wetland of like kind, such as emergent,
shrub/scrub, or forested. Stream channel mitigation usually requires new channels to be of equal
length if possible. Riffles, runs, and pools are often designed into replacement stream channels.
(4) Kansas Department of Health and Environment Water Quality Certification - Clean Water
Act of 1977.
If a Section 404 individual permit is needed, water quality certification is required; that is, the
Kansas Department of Health and Environment (KDHE) must be satisfied KDOT's projects will
not degrade the quality of water which may leave the project site. However, the information
required for either the Section 404 or Department of Agriculture Permit will suffice for this certification. The KDHE has issued blanket water quality certification for nationwide and general 404
permits (see below).
National Pollution Discharge Elimination System (NPDES)
The KDHE administers the NPDES program under Section 401 of the Clean Water Act of 1977.
The program is intended to have storm water runoff from construction sites not being a source of
water pollution. A Construction Storm Water NPDES permit is required for construction activity
disturbing one acre or more.
Information needed from Road and Bridge include:
Location, project description, basin, sub-basin, first receiving waters, is any part of the project
located on Indian lands, total project area, impervious area after construction, and total disturbed area in acres.
(5) Kansas Department of Agriculture Permits - K.S.A. 82a, 301-305a and K.S.A. 24-126.
The Division of Water Resources (DWR) issues permits for dams, bridges, culverts, and channel
changes (K.S.A. 82a-301-305A), and floodplain fills (K.S.A. 24-126).
Bridge construction, modification, or repair projects normally require a DAMS, STREAM
OBSTRUCTIONS and CHANNEL CHANGES regular permit from DWR. Regular permits go
through a 30 day comment period required by the Environmental Coordination Act (ECA). The
DWR bases the need for DAMS, STREAM OBSTRUCTIONS and CHANNEL CHANGES permits on drainage area. A permit would normally be required if the drainage area above the structure is
1 - 22
Bridge Section
Design Manual
(A) One or more square miles in zone one, which includes all geographic points located east of
Washington, Clay, Dickson, Marion, Harvey, Sedgwick or Sumner counties; (B) two or more
square miles in zone two, which includes all geographic points located west of zone one and in or
east of Smith, Osborne, Russell, Barton, Stafford, Pratt or Barber counties; or (C) three or more
square miles in zone three, which includes all geographic points located west of zone two., see
the attached map.
1 - 23
Bridge Section
Design Manual
If the bridge or culvert is being replaced, a General Permit may be used if the project meets the
more limiting criteria. These criteria include: proposed change in stream cross section within 15%
of existing, proposed change in channel length within 10% of existing, proposed rise in average
road grade less than 1 foot, and other restrictions. Projects qualifying for a General Permit are
subject to a 7 day ECA period. A permit will not be issued if the structure causes over one foot of
backwater on an adjacent landowner unless a flowage easement or ownership of the property is
acquired.
When fill is placed in the floodplain below base flood elevation (Q100) to an average height of
greater than one foot above the existing ground a PLANS FOR CONSTRUCTION or MAINTENANCE of LEVEES or FLOODPLAIN FILLS permit will be required.
Information needed from Road and Bridge for DAMS, STREAM OBSTRUCTIONS and CHANNEL CHANGES permit applications include:
Plans (including cross sections), basin size, hydraulic assessment checklist,% change channel
cross section, Q100 hydraulics - water surface existing elevation and proposed, velocity existing
and proposed, Q2 hydraulics - water surface existing elevation and proposed, velocity existing
and proposed, original channel length, proposed channel length, acres or number of trees or vegetation removed, average rise in road grade more than one foot, method used in determining
hydrology, and total cut and fill below Q100 of FEMA floodplain zone. Plans must also show
benchmark references. Channel changes require cross sections of the existing and proposed channel.
Floodplain fills applications require:
Plans, cross sections, FEMA Zone, purpose, dimensions, cubic yards of fill, channel constriction,
backwater, legal description, watercourse, and cross sections at the appropriate stationing showing proposed Q100 across the floodplain.
For assistance with Permit Information Requests see the KDOT web site (www.kdsot.org),
Bridge Design, Bridge Office Standard Documents, Environmental Spreadsheet Advisory, Permit
Information Request Descriptions.
1 - 24
Bridge Section
Design Manual
Culverts. The permittee must notify the District Engineer in accordance with the
Notification general condition of the NWPs (general condition 27) for any regulated activity
which involves the construction of a new or replacement culvert on an expected aquatic life use
water or restricted aquatic life use water located in the Kansas Water Register. The Kansas
Water Register is available on request from the Corps or can be found at
http://www.kdheks.gov/befs/download/Current_Kansas_Water_Register.pdf. All culverts must
be designed to allow the natural passage of aquatic organisms. The culvert design must mimic
the natural shape and flow of the channel. For all box culverts with three or more cells on
expected aquatic life use waters or restricted aquatic life use waters, the opening of the center
culvert must be slightly lower than the adjacent culverts to concentrate low flows for the passage
of aquatic organisms.
The link to the entire document from the Kansas City District U.S Army Corps of Engineers website:
http://www.nwk.usace.army.mil/regulatory/2007nwps/
2007%20NWP%20Regional%20Condition%20PN.pdf
KDOT has developed a base drawing, BR025, titled Embedded Structure, which both buries
the entire structure 12 inches and adds baffles to the outer cells, thus creating favorable conditions. This drawing should be used as guidelines to comply with the above conditions.
1 - 25
Bridge Section
Design Manual
1 - 26
Bridge Section
Design Manual
1 - 27
Bridge Section
Design Manual
water to be classified as a stream or wetland. If there is doubt whether an area is classified as a wetland, notify Environmental Services at (785) 296-0853 and the area in
question will be inspected and determination of its classification will be completed.
(2) Placing material along banks for erosion control
Recommendation: Avoid the use of asphalt for this purpose. Rock and concrete rubble are
acceptable if protruding steel reinforcing rods are removed. If this activity is not covered by a permit, Environmental Services should be contacted if material is placed
below ordinary high water (OHW) elevation.
(3) Construction of shoofly detour through stream valleys and low area
(4) Construction of causeway or construction platform in a stream
Recommendation: If KDOT personnel are completing the work, a (USACE) Section 404
permit is required and Environmental Services should be contacted at (785) 296- 0853.
If the contractor wishes to construct a causeway as part of construction operations, he
is responsible for the Section 404 and (DWR) permits. Environmental Services will
provide assistance if needed.
(5) Channel changes or modifications
(6) When sites are selected for borrow material, archeological clearances should be
obtained in accordance with Section 107.12, KDOT's Standard Specifications for State
Road and Bridge Construction. If channel modification (widening) results from development of a borrow area, the Contractor should acquire a permit. Permits will usually
be acquired by Environmental Services for State furnished borrow, if required.
1 - 28
Bridge Section
Design Manual
DEFINITIONS
The words and terms used in this volume or subsequent volumes are defined as follows:
Dredge Material - Material which is excavated or dredged from waters of the United States.
Fill Material - All fill material should be free from or contain only trace amounts of toxic pollutants. Fill material is material including concrete placed in tight forms, slope protection and used
for the primary purpose of replacing an aquatic area.
Navigable River - In Kansas, Coast Guard Permits for Section 9 and U.S. Corps of Engineers Permits for Section 10 involves all of the Missouri River bordering Kansas and extends upstream into
the tributaries of the river to an elevation equal to the ordinary highwater elevation of the river
and the lower Kansas River.
Ordinary high water mark - The line on the shore established by the fluctuation of water and indicated by physical characteristics such as a clear, natural line impressed on the bank, shelving,
changes in the character of soil, destruction of terrestrial vegetation, the presence of litter and
debris, or other appropriate means which consider the characteristics of the surrounding areas.
Waters of the United States - (1) The territorial seas; (2) wetlands; and (3) all connected waters
which are part of a surface tributary system to and including navigable waters of the United
States.
Wetlands - Those areas inundated or saturated by surface or groundwater at a frequency and duration sufficient to support, and under normal circumstances do support, a prevalence of vegetation
typically adapted for life in saturated soil conditions. Wetlands generally include swamps,
marshes, bogs, oxbows, fringes of ponds and lakes, mud flats, fringes of rivers and streams, playas, seeps and meadows. Wetlands are also considered waters of the United States.
1 - 29
Bridge Section
Design Manual
1 - 30
Bridge Section
Design Manual
1 - 31
Bridge Section
Design Manual
1 - 32
Bridge Section
Design Manual
1 - 33
Bridge Section
Design Manual
Superstructure/Structure Type
AR = Arch
AT = Soil Nail/Tie-Back
BC = Box Girder, Composite Design
BG = Box Girder
BM = Beam
BN = Bin
CB = Box Culvert
CS = Concrete Slab
CT = Cantilever
DG = Deck T-Girder or Orthotopic
DT = Deck Truss
ER = Earth
FA = Filled Spandrel Arch
FB = Rigid Frame Box
FC = Girder-Floorbeam, Composite Design
FG = Girder Floorbeam System
GB = Gabion
GV = Gravity
GC = Rigid Frame, Composite Design
HL = High Mast Lighting Tower
HT = High Truss
HY = Sign (Highway), Bridge Mounted
IS = Illinois Bulletin Slab
IT = Inverted T-Girder
LP = Long Span Pipe
LT = Low Truss
LW = Low-Water Crossing
MA = Mast Arm Structure
MB = Mechanically Stabilized Earth, Block
MC = Rolled Beam, Composite Design
ML = Mechanically Stabilized Earth, Panel
MP = Pipe
NK = Unknown (for BROMS temporary use)
OA = Open Spandrel Arch
ON = None (for BROMS temporary use)
PF = Panel Frame
PO = Privately Owner Overhead Structure
RC = Riveted Plate Girder, Composite Design
RF = Rigid Frame
RG = Rivet Plate Girder
SB = Sign Structure, Butterfly
SC = Girder-Stringer-Floorbeam, Composite Design
SD = Soldier Pile
SG = Girder, Stringer Floorbeam System
SH = Sheet Pile
SL = Sign Structure, Cantilever
SP = Structural Plate Pipe
SO = Sign Structure, Span Truss with Cantilever
SS = Structural Slab
ST = Sign Structure, Span Truss
SV = Semi-Gravity
TA = Through Arch
TG = Through Girder
TS = Single Tapered Tube Span
TU = Tunnel
VS = Voided Slab
WC= Welded Plate Girder, Composite Design
WG= Welded Plate Gider
1 - 34
Design Type
= Not Applicable: superstructure types of
Arch, RCB, RFB, all Pipes, Tunnel,
and Low-Water Crossing
A = Aesthetic (Wall)
B=
C = Continuous: superstructure designed to
extend continuously over one or more
supports
D = Drop-Panel: vertical change in member
height
E = None (for BROMS temporary use)
F = Fixed: superstructure members are
rigidly connected to the substructure
G=
H = Continuous and Parabolic Haunch:
slab or girder beams deepened at
supports and decrease in size at the
center
I=J
= K
=
L = Linear Haunch: straight-line variation in
member height
M =
N =
O=
P = Encased: steel beams encased in
concrete
Q=
R = Circular Haunch: circular variation in
member height
S = Simple: unrestraining support at each
span end
T = Tied: arched superstructure members
Bridge Section
Design Manual
)URP$$6+725HVROXWLRQ-XO\OO
Bridge Preservation
$FWLRQVRUVWUDWHJLHVWKDWSUHYHQWGHOD\RUUHGXFHGHWHULRUDWLRQRIEULGJHVRUEULGJHHOHPHQWV
UHVWRUHWKHIXQFWLRQRIH[LVWLQJEULGJHVNHHSEULGJHVLQJRRGFRQGLWLRQDQGH[WHQGWKHLUXVHIXO
OLIH3UHVHUYDWLRQDFWLRQVPD\EHSUHYHQWLYHRUFRQGLWLRQGULYHQ
Commentary:
(IIHFWLYHEULGJHSUHVHUYDWLRQDFWLRQVDUHLQWHQGHGWRDGGUHVVEULGJHVZKLOHWKH\DUHVWLOOLQJRRGRU
IDLUFRQGLWLRQDQGEHIRUHWKHRQVHWRIVHULRXVGHWHULRUDWLRQ
$QHIIHFWLYHEULGJHSUHVHUYDWLRQSURJUDP
HPSOR\VORQJWHUPQHWZRUNVWUDWHJLHVDQGSUDFWLFHVWKDWDUHDLPHGWRSUHVHUYHWKH
FRQGLWLRQRIEULGJHVDQGH[WHQGVWKHLUXVHIXOOLIH
KDVVXVWDLQHGDQGDGHTXDWHIXQGLQJVRXUFHV
KDVDGHTXDWHWRROVDQGSURFHVVHVWRHQVXUHWKDWWKHDSSURSULDWHWUHDWPHQWVDUHDSSOLHGDW
WKHDSSURSULDWHWLPH
$QHIIHFWLYHEULGJHSUHVHUYDWLRQSURJUDPPD\LQFOXGHEXWLVQRWOLPLWHGWRWKHIROORZLQJFRPSRQHQWV
$ 4XDOLI\LQJSDUDPHWHUVIRUEULGJHW\SHVDQGUHODWHGFRQGLWLRQVLHEULGJHHOHPHQWVRU
FRPSRQHQWVWKDWDUHLQIDLUWRJRRGFRQGLWLRQVXFKDVFRQFUHWHGHFNVFRDWHGVWHHO
HOHPHQWVVXEVWUXFWXUHHOHPHQWVLQDPDULQHHQYLURQPHQWHWF
% $SSURSULDWHWUHDWPHQWVVXFKDVFOHDQLQJLQVWDOODWLRQRIGHFNRYHUOD\VFRDWLQJRIVWHHO
HOHPHQWVLQVWDOODWLRQRIFDWKRGLFSURWHFWLRQDQGSUHYHQWLRQV\VWHPVHWF
& 5HJXDUQHHGVDVVHVVPHQWWRLGHQWLI\SULRULWL]HDQGHVWLPDWHWKHFRVWRISODQQHGZRUN
%HVWSUDFWLFHVIRU%ULGJH3UHVHUYDWLRQLQFOXGH
7KHPHWKRGRILGHQWLILFDWLRQRIQHHGVLVXQLIRUPVSHFLILFDQGUHSHDWDEOHDQGEDVHGRQ
HOHPHQWOHYHOFRQGLWLRQGDWD
)LUVWOHYHOQDWLRQDOSHUIRUPDQFHPHDVXUHVDUHXVHGWRVHWSURJUDPIXQGLQJOHYHOVDQG
VHFRQGOHYHODJHQF\VSHFLILFSHUIRUPDQFHPHDVXUHVDUHXVHGWRVHWREMHFWLYHVIRUWKHIXOO
UDQJHRIDFWLRQVPDLQWHQDQFHSUHVHUYDWLRQUHKDELOLWDWLRQUHSODFHPHQWWRRSWLPL]H
EULGJHFRQGLWLRQV
3ULRULWL]DWLRQSURFHVVLQWHJUDWHVDJHQF\REMHFWLYHVIRUQHWZRUNFRQGLWLRQOHYHOVDQG
LQGLYLGXDOEULGJHULVN
9HULILFDWLRQDQGIHHGEDFNRQZRUNFRPSOHWHG
$VLJQLILFDQWSRUWLRQRIUHVRXUFHVGHWHUPLQHGE\DJHQF\QHWZRUNJRDOVDUHGLUHFWHGWR
SUHVHUYDWLRQDFWLRQV
$JHQF\PDQDJHPHQWFKDPSLRQVWKHSUHVHUYDWLRQRIDVVHWV
1 - 35
Bridge Section
Design Manual
1 - 36
Bridge Section
Design Manual
2 PRELIMINARY DESIGN
Table of contents
2.1 GENERAL ...............................................................................................................................1
Bridge Section
2-i
Design Manual
List of Tables
Table 2.1.1-1 Efficient Length of Span Range ............................................................................4
Table 2.1.5-1 Structure Responsibilities .......................................................................................26
Table 2.3.3.1-1 Desirable Minimum Overtopping Frequencies ...................................................50
List of Attachments
Attachment 2.3.3.1-1 Risk Assessment for Encroachment Design ..............................................54
Attachment 2.3.3.2-1 Coordination with FEMA on Floodplain Encroachment ...........................61
Attachment 2.3.4-1 Hydraulic Assessment Checklist for Drainage Design .................................70
Attachment 2.3.4-2. Hydraulic Data for Open Span Bridges .......................................................76
Attachment 2.3.4-3 Hydraulic Data For Culvert Bridges .............................................................82
Attachment 2.3 Example-Bridge Site Report ............................................................................115
List of Figures
Figure 2.1.3-1Reinforced Concrete Riprap (Std BR130) ...............................................................7
Figure 2.1.3-2 Bridge Berm and Slope Protection - Straight Wingwall (Std BR132A) .................8
Figure 2.1.3-3 Bridge Berm and Slope Protection - U-Type Abutment (Std BR132B)................. 9
Figure 2.1.3-4 Bridge Seat Clearance ...........................................................................................10
Figure 2.1.4-1 Joint Movement vs. Skew .....................................................................................15
Figure 2.1.4-2 Special Concrete Approach Slab < 60 ft. ..............................................................16
Figure 2.1.4-3 Special Concrete Approach Slab > 60 ft. ..............................................................17
Figure 2.1.4-4 Std. RD712 ............................................................................................................18
Figure 2.1.4-5 Std. RD713 ............................................................................................................19
Figure 2.1.4-6 Std. RD713A .........................................................................................................20
Figure 2.1.4-7 Std. RD714 ............................................................................................................21
Figure 2.1.4-8 Std. RD714A ......................................................................................................... 22
Figure 2.1.4-9 Std. RD715 ............................................................................................................23
Figure 2.1.6-1 Typical Section for Girder Labeling .....................................................................28
Figure 2.1.6-2 Plan View Girder Labeling ...................................................................................28
Figure 2.1.6-3 Elevation Splice Labeling .....................................................................................28
Figure 2.2.2-1 Vertical Clearance Diagram ..................................................................................29
Figure 2.2.2-2 Clear Zone Distance Curves .................................................................................32
Figure 2.2.2-3 Clear Zone Distances ............................................................................................33
Figure 2.2.3-1 Design Guide for Track Protection .......................................................................37
Figure 2.2.3-2 Construction Clearance Details (Railroad) ...........................................................38
Figure 2.2.3-2a Construction Clearance Diagram (Railroad) .......................................................39
Bridge Section
2 - ii
Design Manual
Bridge Section
2 - iii
Design Manual
2 PRELIMINARY DESIGN
2.1 GENERAL
The structure site should be studied in detail and evaluated to determine the best alternate for the
structure. In many cases, it can be determined readily whether a bridge or a culvert should be
adopted at a particular site. Once it has been determined that a bridge should be adopted, the preliminary design should include a cost analysis and study of at least two appropriate material alternatives to effect economy. However, there may be sites in which limiting conditions would
discourage the use of all but one type of structure. The prime consideration in the cost analysis
will be the initial construction cost; however, other factors to be included in the economic comparison are material availability, specific site problems, construction time and sequence, traffic
problems, and detour costs. While all bridges must be planned within the constraints of site
requirements, more than minimum first cost may be justified when the result will be a safer structure, a lower overall highway project cost, or reduced annual maintenance cost. The preliminary
cost analysis of the alternate structures should be documented and become a part of the project
report.
Further detailed designs may be necessary if the preliminary cost estimates do not indicate a distinct advantage for any alternate considered.
Factors that need to be considered in selecting a structure for a particular site include the geometry, economics, appearance, waterway crossing requirements or grade separations for railway and
highway crossing requirements, and clearances.
Bridge aesthetics should be considered in the preliminary design of structures which are highly
visible to the traveling public. The designer will consult the Bridge Squad Leader at field check to
determine if the structure should be considered for any aesthetic treatment. Unless prior approval
from the State Bridge Office, the costs for aesthetic treatment will be limited to 3% of the bridge
costs when compared to the same structure without aesthetic considerations. An agreement is
required with the locals for the maintenance of all aesthetic items, KDOT will not maintain aesthetics.
In selecting the type of bridge for a particular site, the designer has several factors to consider.
Based upon experience over the past several years, the reinforced concrete haunched slab bridge
has proven to be the most efficient and maintenance-free bridge that KDOT uses. This type of
bridge provides a minimum clearance requirement and should be given consideration at all sites
for stream crossings having a drainage area greater than about 5 square miles. However, the
haunched slab bridge may be used efficiently for stream crossings with a low clearance requirement even for large drainage areas such as the Chikaskia and Ninnescah Rivers. For sites in which
the drainage area is less than 5 square miles, the reinforced concrete box bridge should be considered, except at locations where geometrics (grade line) dictate that a span bridge would be more
efficient. Also, for sites with more than 5 square miles of drainage area, multi-span boxes may be
dictated by the grade.
Bridge Section
2-1
Design Manual
Drift is a concern for all structures, especially in the selection of RCB bridge opening. The problem of drift must be considered in pier selection, such as open pile bents versus encasements or
columns with web walls. If the channel flowline is on sufficient grade, the use of a drop-taper
reinforced concrete box (RCB) bridge should be considered.
For an overpass structure, KDOT policy precludes the use of cast-in-place concrete construction
for almost all new bridges over railroads and highways. Slab construction may be used for township or county roads where the construction clearance requirements would not be excessive. The
use of steel or concrete should be considered. Minimum clearance can be obtained by the use of
steel beams or shallow welded plate girders. In cases where clearance is not a problem, prestressed girder beams may be more efficient, since the joints are located at the piers rather than at
points of contra flexure. Prestressed panels should be considered when prestressed beams are used
on overpasses. Because of FHWA policy on the use of composite steel beams, short span composite steel beams probably would not be economical. Construction problems do exist on composite
steel beam bridges designed on a skew due to the interference of the transverse reinforcing steel
placed perpendicular to the centerline conflicting with the shear studs.
To minimize redesign, the following items should be determined as early as practicable:
1.
2.
Type of structure
3.
4.
5.
6.
Pier locations
7.
8.
Maintenance of traffic
9.
10.
Drift
When rehabilitating an existing bridge, refer to the bridge maintenance packets to determine if
previous maintenance or rehab work has been done to the bridge. The maintenance packets are
located in the Bridge Management Section.
Bridge Section
2-2
Design Manual
There are two types of maintenance packets, Regular and Special Inspection.
Regular Packets: Bridge Management keeps a packet for each bridge on the system. The
packets contain inspection information, bridge plans, contract costs, hydraulic
assessment checklists, etc. Designers can check the packets out, but it is critical to
check them out properly as these packets are the only copy. Designers will not
keep packets longer than two weeks.
Special Inspection Packets: Bridge Management creates separate individual packets for
special inspections. Special inspections include underwater, pin and hanger,
fracture critical and routine snooper. Bridge packets which have a supplementary
inspection have a colored sticker attached to them indicating that another packet
with special inspection information exists. The color code is:
Green
Red
Blue
Yellow
Fracture Critical
Pin and Hanger
Underwater
Special Snooper
The special inspection packets are in separate files in the Special Inspection Office. These
packets may be checked out for the day only. Please inform someone in Special
Inspections if a packet is checked out.
The Underwater Inspection packets may be very useful when setting footing depths.
Use the following guideline when widening a LFD designed steel girder bridge:
Bridge Section
2-3
Design Manual
As a guideline for selecting span lengths and bridge types, the following table is presented to
indicate the "Efficient" Range of span lengths. The table is based upon past experience.
Table 2.1.1-1 Efficient Length of Span Range
Length of Span
Concrete
30 to 100 ft.
1:1.4
80 to 240 ft.
1:1.25 Uniform
1:1.33 Haunched
Steel
Rolled
(Composite)
40 to 120 ft. **
1:1.25
Reinforced
Deck Girder
Beam
** Rolled Beam may be extended by cover plating. Coordinate with the State Bridge Design
Office on this concept.
Reinforced Concrete
Box Girder
40 to 100 ft.
K-2 Prestressed
Concrete Girder (Composite)
40 to 60 ft.
1:1
50 to 70 ft.
1:1
60 to 100 ft.
1:1
80 to 120 ft.
1:1
Reinforced
Concrete
Haunched Slab
30 to 65 ft.
1:1.33
Post-tensioned Concrete
Haunched Slab
50 to 90 ft.
1:1.33
Bridge Section
2-4
Design Manual
Reinforced
Concrete
Box Culvert (Single or
Multi-cell)
5 to 28 ft.
1:1
40 to 70 ft.
1:1
20 to 50 ft.
1:1
25 to 50 ft.
1:1
40 to 80 ft.
1:1
*The span ratio for continuous bridges ideally balances design moments (0.4 point end
span to 0.5 point interior span); for prestressed beams the ratio is governed by economics.
Bridge Section
2-5
Design Manual
Bridge Section
2-6
Design Manual
Bridge Section
2-7
Design Manual
Figure 2.1.3-2 Bridge Berm and Slope Protection - Straight Wingwall (Std BR132A)
Bridge Section
2-8
Design Manual
Figure 2.1.3-3 Bridge Berm and Slope Protection - U-Type Abutment (Std BR132B)
Bridge Section
2-9
Design Manual
Bridge Section
2 - 10
Design Manual
Free-standing Abutments
Bridge Section
2 - 11
1.
Concrete Pavement:
a.
b.
c.
d..
e.
f.
2.
Design Manual
Use Standard Drawing for 33 ft. Concrete Bridge Approach with the 13 ft.
slab attached to the bridge abutment.
If abutment is skewed, make the 13 ft. slab parallel to the abutment and
make the end of the 20 ft. section normal to the centerline of the roadway.
Use abutment aggregate drains or use strip drains for Standard RCSHs.
Use Road Standard RD712 for the joint between the 13 ft. and 20 ft.
concrete approach slabs, and for the pressure relief joint at the End of
Approach Slab (EAS).
Use 4" curb under guard fence unless parallel wings are used.
Superelevated slabs may require a special flume design.
Asphalt Pavement:
a.
b.
c.
d.
e.
f.
g.
Concrete Pavement
a.
b.
c.
d.
e.
Use Standard Drawing for 33 ft. Concrete Bridge Approach with the 13 ft.
slab attached to the bridge abutment. Use abutment aggregate drains or use
strip drains for Standard RCSHs.
Use Road Standard RD712 for the joint between the 13 ft. and 20 ft.
concrete approach slabs, and for the pressure relief joint at the End of
Approach Slab (EAS).
If skewed, reduce the maximum length of expansion by 3% for every 10
degrees of skew. (i.e. for a 35 degree skew steel bridge the maximum
length of expansion is 340)
Use 4" curb under guard fence unless parallel wings are used.
Superelevated slabs may require a special flume design.
Bridge Section
2 - 12
2.
3.
Design Manual
Asphalt pavement, with thermal movement greater than 1/2, or abutment skewed
greater than 10
a.
b.
c.
Use Standard Drawing for 33 ft. Concrete Bridge Approach with the 13 ft.
slab attached to the bridge abutment.
Use abutment aggregate drains or use strip drains for Standard RCSHs.
Use Road Standard RD712 for the joint between the 13 ft. and 20 ft.
concrete approach slabs and no pressure relief joint at the End of Approach
Slab (EAS).
d.
e.
Use 4" curb under guard fence for 8 ft.() unless parallel wings are used.
Superelevated slabs may require a special flume.
Bridge Section
2 - 13
Design Manual
New Construction:
KDOT will use a Membrane Sealant for all joints at the end of the 13-0 approach slab and in
pressure relief joint location at the end of the 20-0 approach slabs. KDOT has decided to use a
standardized joint material size of 3x4. The length of thermal expansion defines the range of
applicability for this joint. Use Road Standard RD712 detailing Membrane Sealant for a length
of expansion less than 410 for concrete bridges and 380 for steel bridges. Reduce this length by
3% for every 10 degree of skew angle. The length of expansion used for these structures is either
a fixed point, such as a bolster, or the center of stiffness of the structure.
Create a temperature gap table based information found in 14.2.1 Membrane Sealant. The intent is
to construct, in the same manner with the same material, all structures falling within the length of
expansion described above. Place the gap table on the Construction Layout Sheet.
This uniformity of joint material, size, type, construction methods and use by KDOT is intended
to improve the overall performance and durability. KDOTs maintenance forces are able to repair
or replace this type of joint with minimal traffic disruptions, and a long-term review of this joint
type has yielded satisfactory results when installed and sized accordingly.
Maintenance Work:
KDOT has limited the types of approach slab joints to; two part silicon with backer rod, preformed elastomeric neoprene (Jeene Type) & strip seal type joints. These joints are located at the
end of the 13-0 attached approach slab. In general, joints shall be sized according to the Figure
2.1.4-1 Joint Movement vs. Skew . If the joint exceeds the value(s) in the chart and a special
design is required the designer will investigate the manufactures literature to determine appropriate joint size. The maximum opening at the coldest design temp will be 4. Joints with openings >
3 should be an armored type joint. Strip seals have been used successfully for total bridge opening, up to 4
Bridge Section
2 - 14
Design Manual
Bridge Section
2 - 15
Design Manual
Bridge Section
2 - 16
Design Manual
Bridge Section
2 - 17
Design Manual
Bridge Section
2 - 18
Design Manual
Bridge Section
2 - 19
Design Manual
Bridge Section
2 - 20
Design Manual
Bridge Section
2 - 21
Design Manual
Bridge Section
2 - 22
Design Manual
Bridge Section
2 - 23
Design Manual
54-87-12.24(274)
Right Bridge=5.14
Right Bridge=5.14
Right Bridge=5.14
Bridge Section
2 - 24
Design Manual
a.
b.
c.
Use the following rules to decide whether to change the year built on new bridge number plates:
If the Serial Number changes, the year built changes.
If the Serial Number doesnt change, the year built doesnt change, except
Change the year built, if the entire superstructure is replaced, even if the Serial Number
doesnt change.
For rail replacement, remove and reset the original bridge number plate.
Note: Approach is defined as traveling in the direction of increased stationing, for two lane roadways.
* For state route over state route (i.e. K-4 over US-24) there will be two bridge number plates, one
on the column and one on the bridge rail (Abutment No. 1 on the right) both will reference the
bridge.
Note: For local side road over the state route will be referenced.
Bridge Section
2 - 25
Design Manual
Serial No.
Br. No.
Plate
Agreement
needed
Responsibility
Project Type
Open Span
State Bridge
RT-CO KA-XXXX-XX
RT-CO KA-XXXX-XX
*State Wall
RT-CO KA-XXXX-XX
2000 No.
KTA
KTA - XXXX
Y.
**W&P
K900-CO K-XXXX-01
Local
CO C-XXXX-XX
Local Bridge
Built by KDOT
RT-CO KA-XXXX-XX
4000 No.
RT-CO KA-XXXX-XX
3000 No.
Local 10 ft - 20 ft
Culvert Built by
KDOT
RT-CO KA-XXXX-XX
5000 No.
*Only for retaining walls greater than 6-0 tall measured from the top of the footing
Bridge Section
2 - 26
Design Manual
Structures built on State or Turnpike Projects will remain on that system (NBI Number
includes Serial Number)
Structures assigned Serial Numbers for tracking will be transferred to a Local entity (Transfer
State NBI to Local NBI Number) (Serial Number is not reused)
W&P will be notified of Additions, Removals and Modifications to their structures (Assign
W&P NBI Number) (Keep Serial Number for future tracking)
The above applies to bridges, culverts
** For Wildlife and Parks Structures Maintained by KDOT and use of K-900 number
Show Route K-900 on:
Correspondence and Field Check Reports
Request for service from others
Shop details, falsework plans, shoring and erection plans
Pontis/Broms/Cansys (internal data base)
Bridge restriction
Contract plans (Except- Project Number and Title Sheet)
NBI Structure Number KDOT 9999 900 021 0941 same as W&P R-2MILR-01
Do not show K-900 on:
Form 883 Project Numbers
CMS and CPMS Project Numbers
Structure Log and Route Numbers (a separate listing is available)
The K-900 route number is not used on the 883 so therefore, it should not appear on the title
sheet of the bridge plans since it is not part of the official project number.
Bridge Section
2 - 27
Design Manual
Bent Layout: Piers and abutments shall be numbered according to Figure 2.1.6-2.
Figure 2.1.6-2 Plan View Girder Labeling
Splice Layout: Bolted and weld splices shall be number according to Figure 2.1.6-3.
Figure 2.1.6-3 Elevation Splice Labeling
Bridge Section
2 - 28
Design Manual
Bridge Section
2 - 29
Design Manual
Bridge Section
2 - 30
Design Manual
Bridge Section
2 - 31
Design Manual
Bridge Section
2 - 32
Design Manual
Bridge Section
2 - 33
Design Manual
Bridge Section
2 - 34
Design Manual
Top of footings within 25 ft. from centerline of track shall be a minimum of 6 ft. below the base of
rail. Drilled shafts with a diameter not greater than 2 ft. plus the column diameter are exempt from
the 25 ft. clearance requirement.
For new construction, KDOT design policy for railroad structures shall be as follows:
Based on BNSF / UP Guidelines for Railroad Grade Separation Project, May 2007
Horizontal Clearances:
1.
A horizontal clearance of 20-0" from the centerline of the tracks to the abutment slopes
will be required. The reference point for measurement on the abutment slope is the
location on the slope with the same elevation as the top of the tracks. However, drainage
and other special conditions may justify additional clearance. A railroad policy or practice
of providing greater clearance does not in itself provide adequate justification. The
additional horizontal clearance beyond the 20-0" are to be justified by hydraulic analysis
or be demonstrated as being necessary at this location.
2.
Off-track maintenance may extend the 20-0" criteria an additional 8-0" when justified by
need.
3.
All piers should be placed at least 9-0 horizontally from the centerline of the track and
preferably beyond the drainage ditch. Clearance of 25-0 to the obstruction precludes the
use of crash walls. The Bridge Section will request an exception from the railroad when
the clearance is 20-0 or greater and/or when a substantial pier is used. (See Figure 2.2.34 Desirable Design Clearances (Railroad))
4.
New structures may be sized with the appropriate clearances listed above for future tracks
if the railroad in question can show a definite demand and plans for installation are within
a reasonable time frame.
Vertical Clearances:
1. The minimum permanent vertical clearance, per Code of Federal Regulation, shall be 23 - 4
measured from the top of the highest rail to the lowest obstruction under the structure.(See 23
CFR 650, Subpt. B, Appendix.) KDOT will use a preliminary design vertical clearance of 23-6
to allow for minor track fluctuations after the field survey, and to allow for minor profile grade
and structure depth changes during design. The 23- 4 permanent vertical clearance must not be
violated due to deflection of the superstructure. Additional vertical clearance may be required for
items beyond those stated above. These items include: correction of sag in the track, construction
requirements and future track raise. The profile of the existing top-of-rail, measured 1000 feet
each side of proposed Overhead Structure, shall be shown on the plans. If the profile indicates sag
at the proposed bridge location, the vertical clearance from the top of the highest rail to the bridge
shall be increased sufficiently to permit raising the track to remove the sag. A note should be
added to the profile stating, The elevation of the existing top-of-rail profile shall be verified
before beginning
2.
The following vertical clearances will be required when the railroad has documented their
intentions to add electrification to the lines in question:
Bridge Section
2 - 35
25 KV
50 KV
Design Manual
24-3"
26-0"
Candidate rail routes for electrification may be established by submitting the following data:
a.
A copy of the formal plan adopted by the railroad to identify routes to be electrified. Each
route is to be cover a logical independent segment. Maps and drawings are required.
b.
A time schedule for implementation. No fixed time frame is required, but it must be
reasonable within business planning parameters.
c.
Railroad communication lines require 2-0" clearance minimum from the bridge structure.
2.
See Figure 2.2.3-2 Construction Clearance Details (Railroad) for construction clearances.
Rehabilitation projects involving railroads will be examined on a case-by-case basis. Special site
conditions may demand clearances differing from those listed above. The FHWA intends to
provide funds if the clearances provided appropriately address the site conditions and meet the
approval of the State involved.
For additional requirements and regulations concerning Railroads see 1.2.6 Railroad Agreement
Lighting:
All new or modified Overhead Structures exceeding 80 feet in width shall provide a lighting system to illuminate the track area. However, subject to the Railroad Local Representative, lighting
shall be provided for all structures less than eighty (80) feet in width in areas where switching is
performed or where high vandalism and/or trespassing have been experienced. Care shall be taken
in lighting placement such that trains will not mistake the lights for train signals nor shall they
interfere with the train engineers sight distance for existing signal aspects. All lights shall be
directed downward.
Provide temporary lighting for all falsework and shoring areas.The minimum lighting design criteria shall be an average of one (1) foot-candle per square foot of structure at the Railroad tracks.
Use Holophane module 600 underdecking type luminaries or equal as required. Fixtures shall be
installed on the column walls or caps of the Overhead Structure without reducing the minimum
horizontal and vertical clearances. Maintenance of lights shall be the responsibility of the Applicant. Access to perform any maintenance for lights shall be coordinated with the local Railroad
operating unit. Structures with separation over ten (10) ft. from each other shall be considered as
independent structures for the purposes of lighting.
Bridge Section
2 - 36
Design Manual
Bridge Section
2 - 37
Design Manual
Bridge Section
2 - 38
Design Manual
Bridge Section
2 - 39
Design Manual
Bridge Section
2 - 40
Design Manual
Bridge Section
2 - 41
Design Manual
Bridge Section
2 - 42
Design Manual
Bridge Section
2 - 43
Design Manual
Bridge Section
2 - 44
Design Manual
Bridge Section
2 - 45
Design Manual
2.3.2 Policy
As noted in the KDOT Road Section Design Manual, Part C, the criteria for drainage design will
be "....based on the concept of reasonable measures." To further clarify this concept, the following
excerpt from the AASHTO Drainage Guideline (1987), Section 4.1.2.6, is quoted, which explains
the application and liabilities associated with the "Reasonable Use Rule."
"Under the reasonable use rule, a possessor of land is legally privileged to make a
reasonable use of his land even though the flow of surface waters is altered thereby
and causes some harm to others. The possessor of land incurs liability, however,
when his harmful interference with the flow of surface waters is unreasonable. The
issue of reasonableness or unreasonableness is a question of fact to be determined
in each case upon consideration of all relevant circumstances. In determining the
question of reasonableness under the reasonable use rule, it is proper to take into
consideration such factors as the amount of harm caused, the foreseeability of the
harm which results, the purpose or motive with which the possessor acted, and
other relevant matters such as whether the ability of the possessor's use of his land
outweighs the gravity of the harm which results to his neighbor from alteration of
the flow of the surface waters."
It is a responsible approach to drainage design which, based on long-term experience, provides an
economical solution with a minimum of problems for the great majority of drainage installations.
It is the practice of KDOT that the drainage design will include an evaluation of "reasonableness"
which shall include factors relating to the highway facility and to the adjacent non-highway
property as well. "Reasonable" design practice will include a documented assessment of harm or
damages to all property.
It is also noted that highway drainage structures do not cause or create flooding. Flooding is
caused by rainfall events in excess of the stream channel capacity. It is apparent that property is
subject to flooding with or without the presence of highways. It should be considered that only the
incremental increase in flow conditions above natural or existing flood conditions should be used
in the evaluation of "reasonableness" of highway crossings.
Bridge Section
2 - 46
Design Manual
Bridge Section
2 - 47
Design Manual
would cause harm. Exceptions to this are embankments that function as flood control levees
or embankments that are structures for permanent impoundments.
Design Traffic Count to evaluate the magnitude of the problems associated with interruption
of highway service caused by overtopping.
Land use of adjacent private property including utilities; identification and elevations of
residences and buildings in the affected reach of the drainage structure; the extent of land
(area) that will be subject to flooding.
Estimated length of time the area is flooded and, where possible, a representative depth of
flooding for the flooded area. Normal collection of field data may not provide sufficient
information to estimate the flooding depth on areas not directly adjacent to the R/W, aerial
photos and USGS quad sheets may be used to make such estimates. As in overtopping, the
estimated time that the area is flooded requires a computation of a design hydrograph and is
not needed unless conditions are similar to that described for a Level 4 or Level 5 analysis
defined in KDOT's "Hydraulic Assessment Checklist."
Computation of flow velocity is required to estimate erosion potential and scour damages.
4. For normal design practice, the allowable water surface elevation or the allowable highwater
(AHW) will be based on peak flow discharge. For purposes of design, antecedent moisture
conditions are assumed to be average and similar to the Soil Conservation Service (SCS)
AMC-II. Water surface elevations (WSE) based on storage-detention design may be used
when special circumstances justify the collection of additional field data required for reliable
assumptions of design or to provide additional information. (See 2.3.5 Detention-Storage)
Acceptable methods of computing flood frequency and peak flow are as follows:
a. Rational Method;
b. "Hydrological Design Utilizing Frequency-Equivalent Hydrographs" (FENL-H) by
Robert L. Smith, University of Kansas, June 1982;
c. USGS Water-Resources Investigations Report 87-4008 and/or 00-4079;
d. USGS Technical Report No. 11, "Magnitude and Frequency of Floods in Kansas," 1975.
e. Watershed modeling methods; HEC-HMS, SCS TR20 and SCS TR55.
It is suggested that the Rational Method be limited to drainage areas 640 acres or less.
FENL-H is limited to drainage areas 400 acres and larger. Watershed modeling methods; 640
acres to 30 sq. miles. USGS Report 87-4008, 00-4079 and USGS Technical Report No. 11;
greater than 30 sq. miles.
Bridge Section
2 - 48
Design Manual
The methods and procedures found in the publication "Guidelines for Determining Flood
Flow Frequency," Bulletin No. 17B of the United States Water Resources Council, shall be
used to evaluate flood frequency at gaged sites. The coefficient of skewness used to predict
design flow shall be the weighted skew (Gw). The weighted skew is a computed combination
of the station skew (Gs) and the generalized skew (Gg). The station skew (Gs) is obtained as
part of the Log-Pearson Analysis of the gaging records as described in Bulletin No. 17B. The
generalized skew (Gg) is computed by equation (2) described in "U.S. Geological Survey
Water-Resources Investigations Report 87-4008," 1987, by Clement. Gaged sites below major
reservoirs are subject to regulated flow and the weighted skew (Gw) may not be applicable.
Consideration should be given to use of the station skew or zero skew (log-normal
distribution) at such locations. Annual published records of stream flow at gaging stations can
be obtained from the Kansas Water Office, Topeka, Kansas.
For basins that have a significant portion of the drainage area affected by a flood control
reservoir(s), the effect of the reservoir(s) may need to be considered in reducing the designfrequency flows. As a general guide, if the spillway is designed for less than a 50 year
frequency or the controlled area represents less than 25 percent of the basin, the effects of a
major federal flood control reservoir(s) may be neglected. To determine the effects of the
reservoir(s), a hydrograph analysis combining the outflow hydrograph(s) from reservoir
routing, stream routing, and the hydrograph(s) from the uncontrolled area should be
investigated to compile the design-frequency flow. The frequency-design hydrograph can be
derived by the methods described in the section on Hydrograph Analysis.
Many bridge sites in Kansas are located within organized Watershed Districts. In some areas,
the watershed reservoirs and conservation practices may significantly affect runoff. For some
locations, published reports of "Project Data and Flood Hazard Information" contain valuable
information of flood flow frequency and water surface profiles. The reports are on file with
the Soil Conservation Service, Salina, Kansas. A list of Watershed Districts and available
reports is available through the Bridge Section.
5. The design frequency will be the frequency recommended by the criteria in Part C, Road
Section Design Manual with consideration given to the minimum desirable overtopping as
noted below. When the design frequency is less than a 100-year recurrence, it will be the
practice of KDOT to review and evaluate the effects of the "100-year" flood, in addition to the
design frequency. The WSE for the "100-year" discharge will be computed for the same size
structure, which was selected on the basis of the design frequency. The Engineer will check
the "100-year" WSE to see if there are additional factors which would negate the
determination of "reasonableness" for the design. In other words, once a solution is found
which is judged reasonable at the design frequency, what are the effects at the "100-year"
frequency that may make it unreasonable?
It should be noted from a standpoint of serviceability, that the true design frequency is the
frequency flow which overtops the roadway and puts it out of service, or it is the frequency
that satisfied the requirements of the allowable water surface elevation (AWS). As noted in
the Road Section Design Manual, Part C, the Allowable Water Surface Elevation for road
design is measured to the top of the subgrade. For design of bridges, the overtopping elevation
Bridge Section
2 - 49
Design Manual
will be considered to be the crown grade on either the bridge or approach roadway, whichever
is lower. For design purposes, once the computed water surface overtops the bridge (or
approach roadway), it is considered out of service. Desirable frequencies to limit overtopping
in relation to the traffic count are listed in the table below and are applicable to primary,
secondary, or off-system roadways.
Table 2.3.3.1-1 Desirable Minimum Overtopping Frequencies
AADT
Recurrent Interval
< 50
10 yr.
< 400
25 yr.
< 1500
50 yr.
< 3000
50 yr.
> 3000
50 yr.
The minimum design of Interstate (and Freeway) bridges requires that the 50-year flood will
not exceed the top of subgrade. The minimum design of non-national highway system is
clarified in Attachment E-4 Bureau of Local Projects Memorandum (93-9) .
For locations where the WSE may be affected by backwater or tailwater from a downstream
confluence with other waterways, the design may be significantly affected by the assumed
frequency of flooding on the downstream basin. An excerpt from the Texas Department of
Highways, Hydraulic Manual, which may be used as a guideline for selection of relative
design frequencies of dependent drainage areas is shown in Section 2.3.12 ( 2.3.6.2
Frequency Mixing ).
Bridge Section
2 - 50
Design Manual
For Detour Bridges: Use the following criteria for hydraulic design of detour pipes and
temporary bridges:
(a)
One Construction Season: Temporary Bridges shall have 2.0 feet of clearance to
top of opening above the Q5 flow. Pipes should have a minimum Q2
overtopping elevation capacity.
(b)
(c)
Document the hydrological and hydraulic study for the temporary structure in the
design notes.
(d)
6. The allowable highwater (AHW) for the highway or property off the R/W will be as defined in
the Road Section Design Manual, Part C. No restrictions or limitations will be imposed on the
amount of backwater or WSE, except that which is required by the AHW or that which the
judgment of the Engineer deems to be reasonable, except for the special requirements noted
elsewhere in the guideline. The AHW will be documented in the design notes.
For open span bridges, it is required that a clearance of 2.0 feet be provided for the passage of
debris between "top of opening" and the water surface elevation at Q100". For interstate design
it is also required that 3.0 ft. debris clearance be provided at "Q50". This clearance may be
reduced, if approved by the State Bridge Office, for slab type bridges with integral bents. The
designer will document any clearance reductions on the HAC.
See Figure 2.3.3.1-1 Crest - Vertical Curve Profile and Figure 2.3.3.1-2 Sag or Level
Profile for schematic of bridge size and clearance vs. different road profiles.
7. Minimum information required on the plans is the frequency, discharge, and WSE (or HW) at
the design frequency and at the 100-year frequency. Where the design is affected by
downstream confluence with other waterways, the frequency and WSE of the downstream
basin is also required. Required plan information for culverts and open span bridges, along
with definitions employed by KDOT.
Bridge Section
2 - 51
Design Manual
Bridge Section
2 - 52
Design Manual
Bridge Section
2 - 53
Design Manual
RISK ASSESSMENT
FOR
ENCROACHMENT DESIGN
BY
BRIDGE SECTION STAFF
BUREAU OF DESIGN
Bridge Section
2 - 54
Design Manual
Level 2
Level 3
Increase Overtopping
Increase Overtopping
Increase Overtopping
Level 4
Level 5
Bridge Section
2 - 55
Level 1
Design Manual
Level 2
Level 3
Bridge Section
2 - 56
Design Manual
Level 5
Bridge Section
2 - 57
Design Manual
Identify measures which might alleviate adverse environmental impacts and identify
other environmental review and consultation requirements which should be
performed concurrently with the EA or EIS.
The appropriate sections of the Data Check Sheet shall be completed. Consideration
shall be given to the items in Level 4 and to the effect of existing floodplain
management studies. If deemed necessary, a floodplain study shall be conducted
which will require inspection of all flood receptors to establish loss values for
inclusion in the analysis.
A partial or full economic analysis shall be conducted with full consideration of capital costs and
risks.
Bridge Section
2 - 58
Design Manual
The proposed drainage structure or immediate backwater thereof is within the city limits,
i.e., an urban area.
Rural areas where the proposed "100-year" WSE plus a 1.0 ft. freeboard would flood a
residence or an insurable building.
Rural areas where the proposed "100-year" WSE plus a 1.0 ft. freeboard would inundate
building sites in a subdivision that is platted and registered with the county authorities.
3. When a proposed structure is located within a flood control project under the direction of the
Corps of Engineers or local public authority, it will be the practice of KDOT to cooperate with
Bridge Section
2 - 59
Design Manual
the flood control agency and furnish a design that will not violate or modify the assumptions
of the design or the operation of the flood control works.
4. Permits: For Corps of Engineers 404 and DWR Permits see Section 1.4 PROJECT PERMITS
Bridge Section
2 - 60
Design Manual
Mr. R. D. Morgan
Associate Administrator for Engineering
and Traffic Operations
Federal Highway Administration
Department of Transportation
Washington, D.C. 20590
Dear Mr. Morgan:
This is in response to your letter of May 3, 1982, seeking our endorsement of the procedure paper
entitled Procedures for Coordinating Highway Encroachments on Floodplains with FEMA.
This paper expands upon my internal policy memorandum of December 29, 1981, concerning the
Federal Emergency Management Agency's (FEMA's) handling of highway encroachments within
regulatory floodways. Your expansion addresses highway agency responsibilities for coordination
with FEMA under various situations in which FEMA has identified flood plains, floodways, and
base flood elevations.
We have reviewed your procedure paper and believe that it provides an excellent guideline for
coordination between highway agencies, communities participating in the National Flood
Insurance Program (NFIP) and FEMA, when flood plain encroachments involving highway
construction are proposed. In accordance with Executive Order 11988, the procedures require
compliance with NFIP standards and regulations, where practicable, but also provide for
responsible actions where no practicable alternative can be identified. These actions include
appropriate compensation to affected property owners, assurance that the NFIP will not incur
additional liability due to increased flood hazards, and the provisions of appropriate technical data
to FEMA so that flood insurance maps and studies can be revised as necessary.
We compliment you on your efforts to establish workable operating procedures which incorporate
coordination with FEMA on site specific projects. We believe that this procedure paper will
facilitate the attainment of our mutual objective of future flood loss reduction. We will provide
copies of the paper, with our endorsement, to our Regional Offices.
Sincerely,
Richard W. Krimm
Assistant Associate Director
Office of Natural and
Technological Hazards Programs
Bridge Section
2 - 61
Design Manual
Bridge Section
2 - 62
Design Manual
2.
A proposed crossing encroaches on a floodplain where a detailed study has been performed
but no floodway designated and the maximum 1 foot increase in the base flood elevation
would be exceeded,
3.
A local community is expected to enter into the regular program within a reasonable period
and detailed floodplain studies are underway,
4.
A local community is participating in the emergency program and base flood elevation in
the vicinity of insurable buildings is increased by more than 1 foot. (Where insurable
buildings are not affected, it is sufficient to notify FEMA of changes to base flood elevations
as a result of highway construction.)
The draft EIS/EA should indicate the NFIP status of affected communities, the encroachments
anticipated and the need for floodway or floodplain ordinance amendments. Coordination means
furnishing to FEMA the draft EIS/EA and, upon selection of an alternative, furnishing to FEMA
through the community a preliminary site plan and water surface elevation information and
technical data in support of a floodway revision request as required. If a determination by FEMA
would influence the selection of an alternative, a commitment from FEMA should be obtained
prior to the FEIS or FONSI. Otherwise this later coordination may be postponed until the design
phase.
For projects that will be processed with a categorical exclusion, coordination may be carried out
during design. However, the outcome of the coordination at this time could change the class of
environmental processing.
Highway Encroachments Which Are Consistent With Regulatory Floodways In Effect
In many situations it is possible to design and construct highways in a cost-effective manner such
that their components are excluded from the floodway. This is the simplest way to be consistent
with the standards and should be the initial alternative evaluated. If a project element encroaches
on the floodway but has a very minor effect on the floodway water surface elevation (such as piers
in the floodway), the project may normally be considered as being consistent with the standards if
hydraulic conditions can be improved so that no water surface elevation increase is reflected in
the computer printout for the new conditions.
Bridge Section
2 - 63
Design Manual
Copy of current regulatory Flood Boundary Floodway Map, showing existing conditions,
proposed highway crossing and revised floodway limits.
2.
Copy of computer printouts (input, computation, and output) for the current 100-year model
and current 100-year floodway model.
3.
Copy of computer printouts (input, computation, and output) for the revised 100-year
floodway model. Fill or development that has occurred in the existing flood fringe area must
be incorporated into the revised 100-year floodway model.
4.
The revised and current computer data required above should extend far enough upstream and
downstream of the floodway revision area in order to tie back into the original floodway and profiles using sound hydraulic engineering practices. This distance will vary depending on the magnitude of the requested floodway revision and the hydraulic characteristics of the stream.
A floodway revision will not be acceptable if development that has occurred in the existing flood
fringe area since the adoption of the community's floodway ordinance will now be located within
Bridge Section
2 - 64
Design Manual
the revised floodway area unless adversely affected adjacent property owners are compensated for
the loss.
If the input data representing the original hydraulic model is unavailable, an approximation
should be developed. A new model should be established using the original cross-section
topographic information, where possible, and the discharges contained in the Flood Insurance
Study which establish the original floodway. The model should then be run confining the effective
flow area to the currently established floodway and calibrate to reproduce within 0.10 foot, the
With Floodway elevations provided in the Floodway Data Table for the current floodway.
Floodway revisions may then be evaluated using the procedures outlined above.
Floodway Encroachment Where Demonstrably Appropriate
When it would be demonstrably inappropriate to design a highway crossing to avoid
encroachment on the floodway and where the floodway cannot be modified such that the structure
could be excluded, FEMA will approve an alternate floodway with backwater in excess of the
1 foot maximum only when the following conditions have been met:
1.
A location hydraulic study has been performed in accordance with Federal-Aid Highway
Program Manual (FHPM) 6-7-3-2 "Location and Hydraulic Design of Encroachments on
Floodplains" (23 CFR 650, Subpart A) and FHWA finds the encroachment is the only
practicable alternative.
2.
The constructing agency has made appropriate arrangements with affected property owners
and the community to obtain flooding easements or otherwise compensate them for future
flood losses due to the effects of the structure.
3.
The constructing agency has made appropriate arrangements so that the National Flood
Insurance Program and Flood Insurance Fund do not incur liability for additional future
flood losses to existing structures which are insured under the Program and grandfathered in
under the risk status existing prior to the construction of the structure.
4.
Prior to initiating construction, the constructing agency provides FEMA with revised flood
profiles, floodway and floodplain mapping, and background technical data necessary for
FEMA to issue revised Flood Insurance Rate Maps and Flood Boundary and Floodway
Maps for the affected area upon completion of the structure.
Bridge Section
2 - 65
Design Manual
2.
To be placed on mailing list to receive all studies and maps as they are completed for a State.
(b)
3.
(2)
All the studies for a particular State. You will receive about 50 percent of the
completed studies to date.
Call NFIP contractor (800) 638-6620, (800) 492-6605 (MD), 897-5900 in D.C., or
(b)
Bridge Section
2 - 66
Design Manual
Bridge Section
2 - 67
(1)
Design Manual
(2)
Bridge Section
2 - 68
Design Manual
Culverts must be designed, sized, and placed correctly. Culverts perched above the grade of the stream
are not allowed. This includes other in-stream structures placed at the inlet with the purpose to reduce
sedimentation within the stream crossing. Culverts must be the shortest length necessary to meet the
project purpose.
New or replacement culverts must be designed to convey the geomorphic bankfull discharge (return
period of 1.01 1.7 years) with a similar average velocity as upstream and downstream sections. A single
culvert is encouraged. The following basic guidelines shall be used when designing the culvert area for
similar average velocity:
Stream Type
Perennial
Intermittent
Ephemeral
Culvert Area
Similar to upstream and downstream preconstruction bankfull
area (approximate minimum area of 85%)
Similar to upstream and downstream preconstruction bankfull
area (approximate minimum area of 50%)
Sized to convey geomorphic bankfull discharge
For permanent crossings, the culvert must be embedded and backfilled below the grade of the stream 1
foot for culverts >48 inches. On culverts 48 inches the bottom of the culvert must be placed at a depth
below or at the natural stream bottom to provide for passage during low flow conditions. Culverts in
streams with non-erodible beds (i.e. bedrock or stable clay) must be constructed flush with the stream
bed, but do not need to be embedded. Culverts in streams with highly erodible beds must be embedded
deeper to lessen the chance of future perching due to downstream degradation and/or may be
accompanied with other grade control measures as needed to prevent erosion.
Low Water Crossings:
The applicant must notify the District Engineer when repairing, rehabilitating or replacing low water
crossings when discharges of dredged or fill material would raise or lower the lowest elevation of the
crossing or when removing the structure.
When replacing or removing low water crossings the applicant must propose and employ measures to
mitigate for and minimize the potential of streambed headcutting where channel incision has occurred
downstream of the structure and the structure is providing grade control that is preventing channel
incision from migrating upstream.
Bridge Section
2 - 69
Design Manual
2.3.4 Documentation
Attachment 2.3.4-1 Hydraulic Assessment Checklist for Drainage Design
The following five (5) pages comprise the:
The current Hydraulic Assessment Checklist for Drainage Design can be downloaded from
KART
Bridge Section
2 - 70
Design Manual
Bridge ID
Designer Name
Date
General Information
County
Highway
Project No.
Project Type
Stream Name
Dist/Area
Location
Legal Description: Section
Township (S)
Range
Setting
Design AADT
%Trucks
Design DHV
Milepost
Serial No.
LOB Piers
Abutment #2
MC Piers
ROB Piers
Proposed Structure
Length (EWS)
Milepost
Serial No.
Structure Type
Spans/Units
Special Environmental Design/Detail (Culverts)
Abutment #1
LOB Piers
Abutment #2
MC Piers
ROB Piers
Year Built
Route Relocation
Structural Deterioration
Inadequate HW Clearance
Other
Inadequate Waterway
Page 1 of 5
Ver. 2011.12
Bridge Section
2 - 71
Design Manual
% Urban
% Cultivated
% Residential
% Timber
% Other
Vertically Unstable
....Countermeasures Proposed
-Degradation/+Aggr. (ft)
Laterally Unstable
Stream Planform
Watershed Development
Development Potential
Upstream Development
Building #1:
Type
Building #2:
Type
Building Location(s)
Discharges
Method of Hydrologic Analysis, Flood Flows
Q 2 (cfs)
Q 10 (cfs)
Q 25 (cfs)
Q 5 (cfs)
Q 50 (cfs)
Q 100 (cfs)
Ver. 2011.12
Bridge Section
2 - 72
Design Manual
Design Information
Existing
Proposed
Proposed
Proposed-Existing
0.0
ft2
0.0
ft2
0.0
fps
0.0
fps
0.0
fps
Proposed: WSE
Clearance
Clearance
ft.
0.00
ft.
ft.
0.00
ft.
@ Q des
0.00
@ Q 100
0.00
@ Historic HW
0.00
ft.
FEMA
FEMA Zone
Backwater
Unobstructed
Water Surface
Elevation
Existing
Backwater
Elevation
Proposed
Backwater
Elevation
Change in
Backwater
Elevation
Q2
0.00
ft.
Q5
0.00
ft.
Q 10
0.00
ft.
Q25
0.00
ft.
Q 50
0.00
ft.
Q 100
0.00
ft.
Qdes
0.00
ft.
Overtopping
Existing
Proposed
Ver. 2011.12
Bridge Section
2 - 73
Design Manual
Exposed Falsework
Headcut Present
Bank Erosion
Streambed Material
LOB D50 (mm)
MC D50 (mm)
Bridge Scour
Method of Scour Analysis
Evidence of Scour (Existing)
Scour Discharge, Qscour
Contraction Scour
(Main Channel)
(Right OB)
Abutment Scour
Setback from Main Channel (ft)
Angle of Attack @ Qscour
Estimated Local Abutment Scour (ft)
Predicted Streambed Degradation (ft)
Foundation
Scour Elevation = Streambed Elevation - (Contraction Scour + Local Scour + Long-Term Degradation)
Existing
Page 4 of 5
Ver. 2011.12
Bridge Section
2 - 74
Design Manual
Describe
Document(s)
NOTE: Send all information in this section related to the hydraulic analysis of the site to the Bridge Section project
leader at the KDOT State Bridge Office with the Hydraulic Assessment Checklist. Also, send a copy to
#BridgeHydraulics@ksdot.org. Reference the Bridge ID with all information. Submit documents in electronic
format when possible.
Ver. 2011.12
Bridge Section
2 - 75
Design Manual
xxx.xx
xx
xx,xxx
xxx.x
x.x
xxx.x
Sq. Mi.
Yr.
cfs
Ft.
Ft.
Ft.
xxx.x
xx,xxx
xx
Ft.
cfs
Yr.
Discharge at Q100
Change in Backwater @ Q100
Backwater Elevation @ Q100
xx,xxx
x.x
xxx.x
cfs
Ft.
Ft.
xxx.x
xxx.x
xxx
xxx
xxx
Ft.
Ft.
Sq. Ft.
Sq. Ft.
cfs
When the proposed bridge replaces an existing bridge, the following additional information
(placed on the CONTOUR MAP sheet) is required: 1) A sketch of the existing waterway
opening; 2) The existing waterway area in Sq. Ft., and 3) The top of opening elevation of
the existing structure. In addition, at sites where existing bridges upstream or downstream will
materially affect the hydraulic operation of the proposed bridge, waterway sketches, areas and
elevation shall be included on the CONTOUR MAP sheet. As a guideline, information from
existing bridges within 1,000 ft. upstream or downstream of the proposed bridge, shall be
included. Existing bridge information beyond 1,000 ft. of the proposed bridge may be
included as needed or as required by the State Bridge Engineer.
Other information that is desirable and may be required on the CONSTRUCTION LAYOUT
sheet, as directed by the State Bridge Engineer, is as follows:
Bridge Section
2 - 76
Design Manual
xxx.x
xxx.x
xx.x
xx.x
Ft.
Ft.
fps
fps
xx
x,xxx
xxx
%
cfs
cfs.
2. Documentation of Historic High Water shall be noted on the CONTOUR MAP sheet.
Documentation shall include year(s) of occurrence and source of information.
Ordinary High Water is required information for the `404' permit. Ordinary High water also aids
in determining the boundary between Class I and Class II
excavation. The boundary between excavation class is located 1.5 ft.
above Ordinary High Water. From instructions and definitions
furnished by the Corps of Engineers for `404' permit applications,
the ordinary high water is the line on the shore established by the
fluctuation of water and indicated by physical characteristics such as
a clear, natural line impressed on the bank, shelving, changes in the
character of soil, destruction of terrestrial vegetation, the presence
of litter and debris, or other appropriate means that consider the
characteristics of the surrounding area. Ordinary high water will
normally be established by a field survey of the site. Where ordinary
high water is not determined by survey of the physical
characteristics, it may be established by use of the Alternate
Proceedure
Excavation Boundary Plane is located 1.5 feet above Ordinary Highwater.
The Design Discharge as computed by the methods noted in this manual. When other methods
are applicable and are used to compute the Design Discharge, it shall be noted on the plans.
Clearance for debris or other purposes shall be measured for the Design Highwater Surface at
the bridge and shall be noted on the plans in the Elevation view of the CONSTRUCTION
LAYOUT sheet as Design HW Clear.=xx.x ft. The location of the top of opening will
normally be assumed at a point in the lowest end span that is one-fourth the interior span
length from the pier. When this location is not appropriate as for long and/or steep bridges, the
location shall be noted on the plans.
The Average Velocity shall be computed from the gross area at the bridge opening below
Design flow depth, i.e., Q/An, where An is the gross waterway area in the constriction at
Bridge Section
2 - 77
Design Manual
Design highwater depth. Design Waterway Provided is the net flow area below the Design
Highwater elevation. Total Waterway Provided is the net flow area below the bridge. Total
Waterway and Design Waterway will be the net flow area (i.e., deduct pier area). When the
stream approach is skewed, all waterway areas shall be measured normal to the stream flow,
i.e., corrected by the bridge length times the Cosine of the skew angle. The projected area of
the piers should likewise be corrected. The plans shall indicate that the waterway areas are
normal to stream flow when corrected for a skewed approach.
Design Backwater Elevation: For convenience, the amount of design backwater will be
measured at Section 1, as shown on the profile section on Figure 2.3.4-1 Longitudinal Section
Along Centerline Roadway, for the design discharge (Qdes). Although Section 1 may not be
the exact location of the maximum highwater, it is accurate enough to provide a reasonable
estimate.
For critical locations where the exact backwater computation might affect the design, i.e.,
where a FEMA floodway exists, the designer should refer to methods given in "Hydraulics of
Bridge Waterways" (HY-1) Chapter IV.
The location of the Overtopping Elevation for the bridge and approaches may be referred by
stationing (Sta. 84+15) or by distance from the bridge (as 375 south of bridge). The location
of the overtopping may occur on the bridge. The overtopping roadway elevation may be either
the centerline elevation or the high shoulder elevation in a superelevated section.
Freeboard as applied to bridge hydraulics is the vertical distance from the top of opening of
the structure to the overtopping elevation. When the overtopping elevation is higher than the
top of opening, there will be no freeboard. This distance is recorded on the Hydraulic
Assessment Checklist.
Additional site-specific information may be required and noted on the plans as determined by
the State Bridge Engineer.
Bridge Section
2 - 78
Design Manual
Bridge Section
2 - 79
Design Manual
Bridge Section
2 - 80
Design Manual
Bridge Section
2 - 81
Design Manual
xx.xx
xx
x,xxx
Sq. Mi.
Yr.
cfs
xxx.x
Ft.
xxx.x
x,xxx
xx
xxx.x
xxx
Ft.
cfs
Yr.
Ft.
cfs
When the proposed structure is a replacement, a description of the existing structure, the total
existing waterway area, and the "top of opening" elevation is required.
The following additional information is desirable and may be required on the CONTOUR MAP
sheet or in the plans as directed by the State Bridge Engineer:
Normal Water Surface Elev. (Qdes)
Q100
Highwater Elevation at Q100
Exit Velocity
FEMA 100 Yr. Floodplain Elev. (Regulatory)
FEMA 100 Yr. Floodway Elev. (Regulatory)
Storage-Detention Volume (Q100)
Water Surface Elev.* @ Q100
xxx.x
x,xxx
xxx.x
xx.x
xxx.x
xxx.x
xxx.xx
xxx.x
Ft.
cfs
Ft.
fps
Ft.
Ft.
Ac-Ft.
Ft.
Bridge Section
2 - 82
Design Manual
Bridge Section
2 - 83
Design Manual
Bridge Section
2 - 84
Design Manual
2.3.5 Detention-Storage
Nearly all highway crossings temporarily impound some flow from flood events. At some
locations, it may be practical and beneficial to take advantage of the natural upstream storage to
design a structure that would be smaller (more economical) than a structure based on peak flow
computations alone.
The feasibility of detention-storage design will be based upon weighing the savings in structure
cost balanced against the cost of additional surveys and additional R/W. The same criteria of
reasonableness used for designs based on peak flow is applicable to detention-storage design.
It is the practice of KDOT that detention-storage design will not be applied to open span bridges
and in general will be limited to culverts with drainage areas small enough to drain the temporary
storage in 24 hours or less at the Q100 level.
Normal field survey data will not provide sufficient information to accurately define the upstream
storage. Additional stream x-sects, parallel x-sects, and ground elevations will be required. A
contour map at 2.0 ft. intervals is required of the storage area.
In order to preserve the storage area assumed for design, it will be the practice of KDOT to
acquire or control use of all the land included in the storage area. It is preferred that the area be
acquired by purchase for R/W; however, in some cases a flowage easement may be appropriate.
(See Section 2.3.8 Easements for Drainage)
Detention-storage areas are not limited to locations immediately adjacent to the R/W. Structures
for temporary impoundments may be constructed at locations remote from the highway project.
In locations where the adjacent landowner desires a permanent impoundment for agriculture or
conservation purposes and such impoundment would qualify for SCS assistance, it will be the
practice of KDOT to cooperate with the SCS and may contribute to the extent that benefits accrue
to KDOT.
Detention-storage methods will not be used to justify the size of drainage structures which are
designed on peak flow discharges. Only those sites where the storage volume can be obtained by
R/W or easement, may the design be designated as a detention-storage design and the hydraulic
data corresponding to detention-storage analysis placed on the plan. However, in areas where the
upstream terrain is not expected to change significantly and very conservative estimates of storage volumes are used, detention-storage methods may be used to provide additional information
to the Engineer to judge the adequacy of the drainage structure. Upstream flow area in the main
channel and immediate overbank area (low terrace) is not considered as contributing to the storage volume (i.e., the incised channel). It is cautioned that in urban, suburban areas, or near suburban areas, the upstream terrain is subject to development and significant alterations may occur
over the life of a drainage structure (75 years for RCB).
Bridge Section
2 - 85
Design Manual
2.3.6 Hydrology
2.3.6.1 Hydrograph Analysis
When a hydrograph is required for an estimate for time of flooding, or for storage-detention
design, the following methods are acceptable:
Modified Rational. It is suggested that the Modified Rational method be limited to rural
drainage areas of 400 acres or less. See the Road Section Design Manual, Part C, for
information and procedure.
FENL-H. Information in the report indicates that the methods and procedures are applicable to
urban or rural drainage basins from 400 acres to 500 sq. miles.
Soil Conservation Service (SCS). SCS methods are appropriate for either rural or urban areas
of any size up to about 20 sq. miles. References for procedures are the SCS National
Engineering Handbook, Section 4; SCS Technical Report No. 55 (TR-55); TR-20, a
watershed modeling computer program. It is suggested that drainage areas larger than 20 sq.
miles may be divided into sub-basins, combined and routed with the TR-20 software. It is
suggested that for small rural basins (1 sq. mile or less) and urban areas, a CN runoff value of
not less than 85 be used for the "100-year" event.
Flood Hydrograph Package, U.S. Army Corps of Engineers, Hydrologic Engineering Center 1 Users Manual, Sept. 1981 (Revised March 1987)
Hydrology, H.E.C. #19, FHWA, 1984, Turner-Fairbank Research Center, McLean, Virginia,
FHWA-IP-84-15, October (Revised August 1985)
The FHWA Drainage Design System (HYDRAIN) also has provisions for generating a
dimensionless hydrograph based on the USGS method or a user defined hydrograph.
It is noted that peak flows associated with hydrograph derivation may not agree with peak flows
computed by regression methods or other methods based on instantaneous peak flow calculations.
For design purposes, it is suggested that more than one method of hydrograph be used to aid the
designer in judging the final results. As an alternative, the peak flow of the hydrograph may be
adjusted to match the peak flow selected for the design discharge. The ordinates may be prorated,
runoff volumes adjusted, or base time modified as deemed appropriate by the Engineer to produce
consistent results.
See the following publications for coefficients of roughness (n):
Roughness Characteristics of Natural Channels
U.S. Geological Survey, Water-Supply Paper 1849
by Harry H. Barnes, Jr.
http://water.usgs.gov/pubs/wsp/wsp_1849/
Bridge Section
2 - 86
Design Manual
Guide for Selecting Mannings Roughness Coefficients for Natural Channels and Flood Plains
U.S. Geological Survey, Water-Supply Paper 2339
by G. J. Arcement, Jr. and V. R. Schneider, USGS
http://www.fhwa.dot.gov/bridge/wsp2339.pdf
Tributary
Tributary
10
1
Main
Stream
2
100
Tributary
100
2
Main
Stream
2
50
2
10
5
10
10
10
10
2
10
5
10
10
10
100
25
100
50
100
100
10
100
25
100
50
5
50
10
50
25
50
50
5
50
10
50
25
10
10
10
10
100
100
100
100
50
50
50
50
50
2
Bridge Section
2 - 87
Design Manual
Bridge Section
2 - 88
Design Manual
When using WSPRO or HEC-RAS, include some cross sections downstream from the bridge to
establish a reasonable water surface profile before the software deals with the bridge constriction.
Predictions of scour depths involve large uncertainties and therefore, conservative assumptions. It
will be the practice of KDOT to assume rigid boundary hydraulics for streams with cohesive
(clay) streambeds (i.e., no increased waterway from scour). Rigid boundary hydraulics will also
be assumed for sand bed streams unless detailed computations of scour depth are performed and
supported by the experienced judgment of the Engineer. It is recommended that not more than 1/5
of the computed depth for main channel scour be used for an increased waterway in the hydraulic
design.
For computations of culvert hydraulics, the following methods are employed by KDOT.
"Hydraulic Design of Highway Culverts," Hydraulic Design Series No. 5 (HDS-5), FHWA,
April 2012.
FHWA culvert analysis program HY-8.
FHWA culvert analysis program HYCLV. HYCLV is contained in the HYDRAIN suite of
hydraulics programs.
"Kansas State University report on model studies for "Hydraulic Entrance Characteristics of
Culverts" by Dr. W. K. Kubitza (Circa 1955).
The KSU report indicates the results were based on the assumption of overbank "ponding,"
which is prevalent in Kansas. Where the approach velocity is direct, as in a relatively deep incised
channel, the study showed the culvert capacity was greater than a "ponded" entrance condition. At
depths greater than the culvert (i.e., submerged), the study showed minimal differences between
the two entrance conditions. It is concluded that the charts are applicable to either condition and
would produce conservative results where little or no overbank ponding occurs. The charts also
include the effects of beveling or rounding the top edge of the culvert entrance. The values in the
chart are applicable where the tailwater is not significantly affected by downstream obstructions
or constrictions (dams, backwater, etc.). The charts are limited to locations where the tailwater
would be (dc + D)/2 or less.
Bridge Section
2 - 89
Design Manual
provide for contingencies and to reflect the relative accuracy of detention-storage design, it is recommended that all land at least 1.0 ft. above the Q100 WSE be included in the purchase or easement. The legal description need not follow the contour location of the WSE but may be
conveniently described in straight line definitions provided it includes all land below the contour
of the WSE noted above. In either method of acquisition it is the intent to prevent fill or change in
the ground contour that would alter the flood storage assumptions made in design and to provide
access to dredge or clear as needed to maintain the storage area. Two examples of restrictions for
flowage easement are included in Attachment 2.3.3.1-1 Risk Assessment for Encroachment
Design
See Road Memorandum No. 03-02 (Corrected) "Labels for Permanent Easements" dated April
18, 2003, for definitions of the various types of permanent easements.
Bridge Section
2 - 90
Design Manual
(Description)
The above estate or easement is taken subject to existing easements for public roads and
highways, public utilities, railroads and pipelines; reserving however, to the landowners, their
heirs and assigns, all such rights and privileges as may be used and enjoyed without interfering
with the use of this easement or abridging the rights hereby acquire
Bridge Section
2 - 91
Design Manual
River Basins. Local sites similar to these areas may be found throughout the state. County SCS
soil maps may aid in judging the resident material.
Estimation of erosion potential for downstream areas depends on many factors other than velocity
and channel material and include channel alignment, vegetation, naturally occurring degradation,
etc. Estimates based on simple approximations of velocity as noted above are considered gross
approximations of velocity. It is the judgment and experience of the designer that will provide the
best estimate of erosion potential of downstream property. The result of an erosion evaluation is
expected to be subjective and described in general terms as "minor," "moderate," "significant," or
substantial." A "substantial " erosion potential would include major loss of channel material for a
considerable reach of stream. The erosion potential should be measured against or compared to
the use of the land. As an example, "moderate" erosion may be intolerable to a downstream flood
control levee or to an embankment of a sewage treatment lagoon, while "substantial" erosion may
be permitted without harm to a rural area of brush and timber. It is noted that erosion of stream
banks occurs as a natural result of flood events regardless of the presence or absence of highway
crossings. It is the local alteration of flow conditions that is a consideration in judging the "reasonableness" of a design.
2.3.9.2 Degradation
Degradation (or aggradation) is the physical response of a stream system in its attempt to attain
equilibrium (stability). The stream will lower its bed level (degradation) by displacing the streambed material to a remote location, in some cases a river delta or other remote reaches where it can
be deposited. In general, degradation (or aggradation) occurs over long reaches of a stream. Major
factors which may cause degradation (or aggradation) are the geological age of the stream, an
imbalance in gradient, the sediment transport capacity, a change in basin discharge. A bridge
crossing generally has little effect on the degradation (or aggradation) of a stream. However, it
may occupy a site in a reach that is actively degrading (or aggrading). Reservoir construction,
sand dredging (mining), or significant channel changes in conjunction with flood control projects
can affect the stream gradient, sediment transport, or basin discharge. It is also noted that the
effects of a single degrading stream may be expected to extend into the stream's tributaries.
It has been KDOT's experience that aggradation has occurred in only a few locations (immediately upstream of reservoirs). Several locations of significantly degrading streams are known and
are described as follows: the lower Kansas River, in particular below Bowersock Dam at Lawrence (see Corps of Engineers Report on Commercial Dredging Activities, January 1988); Local
areas in the Delaware and Wolf River Basins in northeast Kansas; Soldier Creek and Little Soldier
Creek (Flood Control Project in Shawnee County and upstream); Stonehouse Creek US-59 to the
Kansas River (Flood Control Project, Jefferson County and upstream); Locally on the Arkansas
River at Garden City.
It is KDOT's experience that a large number of streams in Kansas exhibit minor to moderate degradation through the state.
For many bridge replacements it is a relative easy task to observe the existing foundation and to
note exposed footings or pilings. It can be assumed that they were not constructed in that manner.
Minimal probing can locate existing footings in relation to present streambeds.
Bridge Section
2 - 92
Design Manual
Typical bridge specifications (Circa 1920 and 1930) indicated that foundations shall be founded a
minimum of 4 feet below streambed and most were.
Bridge Section
2 - 93
Design Manual
3. "Evaluating Scour at Bridges", HEC 18, 4th Edition, FHWA, May 2001
4. "Stream Stability at Highway Structures", HEC 20, 3rd Edition, FHWA, March 2001
Bridge Section
2 - 94
Design Manual
with the Addendum to Highways in the River Environment, HEC 16, July 1980. (These two documents have been updated and combined into one volume by the February 1990 edition, FHWAHI-90-016.)
Bridge Section
2 - 95
Design Manual
as 100 feet. For detailed information on the model studies and field data collected on behavior of
guide banks relating to design considerations, reference is made to Hydraulics of Bridge Waterways, HDS-1 Federal Highway Administration, March 1978. An alternate method for determining the length of guide bank based upon bridge length is shown in Section 2.3.12. See 2.3.10
Guide Banks
Bridge Section
2 - 96
Design Manual
Bridge Section
2 - 97
Q =
Q =
Q100=
b =
An2=
Vn2=
Design Manual
Q
An2
Qf
---------- = Guide bank discharge ratio
Q 100
Ls = Projected length of guide bank, ft.
X2
Y2
+
=1
L2s (0.4 L ) 2
s
Ls =
( X 2 + 6.25Y 2 )
Bridge Section
2 - 98
Design Manual
Bridge Section
2 - 99
Design Manual
Bridge Section
2 - 100
Design Manual
Where unusual problems are anticipated or the adequacy of Shot-Rock is uncertain, the bid item
"Slope Protection (Riprap Stone)" should be used. This item is a graded riprap. The gradation
shall be shown on the plans. When using this bid item, a complete detailed design of the riprap
gradation and filter blanket, if used, is recommended.
The bid item "Riprap (size)" is similar to the bid item "Slope Protection (Riprap)" except the stone
is required by specifications to be placed by hand. Because of the added expense of hand placement, the bid item "Riprap (size)" should only be used in special circumstances.
For more complete guidance in the design of riprap to obtain an adequate safety factor, reference
is made to "Highway in River Environment Hydraulics and Environmental Design Considerations" by U.S. Department of Transportation, FHWA, May 1975, along with the Addendum to
Highways in the Highway Environment, HEC 16, July 1980. (These two documents have been
updated and combined into one volume by the February 1990 edition, FHWA-HI-90-016). Reference is also made to "Design of Riprap Revetment", HEC 11, FHWA, 1989.
2.3.11.3 Miscellaneous
Other methods of bank protection such as articulated concrete mattresses, gabions, concrete filled
bags or other products will be reviewed on a case by case basis.
Bridge Section
2 - 101
Design Manual
Figure 2.3.11.3-1 Typical Slope and Bank Protection, and Channel Lining
Bridge Section
2 - 102
Design Manual
Figure 2.3.11.3-2 Guide for Estimating Stability of Channels and Large Rocks
Bridge Section
2 - 103
Design Manual
Bridge Section
2 - 104
Design Manual
Bridge Section
2 - 105
Design Manual
REFERENCES
Chow, V.T., 1964. Handbook of Applied Hydrology, A Compendium of Water-resources
Technology. McGraw-Hill Book Company. Section 8-I, pp. 22-23.
Procedure developed by C.B. Young (University of Kansas) and B. Rognlie (KDOT)
Example of Alternate Proceedure:
Bridge Section
2 - 106
Design Manual
2.957
200
1.957
= 25 cfs
Background information
For permit compliance, the Kansas Department of Wildlife and Parks Tourism (KDWPT) and
KDOT Construction and Maintenance (C&M) agreed to incorporate several requirement into
temporary crossing designs. As a result of the agreement, the plans will show the ordinary highwater flows as directed on LA852B for temporary erosion control for stream crossings. The main
intention of the requirement is to provide aquatic passage for threatened and endangered species
(T&E) and is justified under the Kansas Nongame and Endangered Species Conservation Act of
1975, KSA 32-957 to 963. The hope is that it increases familiarity of the design concept and
reduces overall impacts to aquatic systems, and therefore issues with other permitting agencies.
KDWPT recognize that it might not be feasible in all scenarios. The intent is to require the design
when impacting T&E waters under KDWPT authority. See KDOT Specifications for Temporary
Erosion Control.
Bridge Section
2 - 107
Design Manual
Plot Contour Map. The contour map should be plotted as soon as practicable after the
notes are received from the field. A scale of 1"=50 is standard; however, use largest scale
that will plot all field data.
A Contour Map is required at field check for all bridge structures including interchanges,
bridge-size boxes and bridge-size box extensions. Include a contour map on 10 to 20
Structures, (Formerly known as '500' Series Structures) for special conditions. The Squad
Leader will decide if the Contour Map is required in the final plans.
2.
Size Structure. If the use of a span bridge is probable at the proposed site, a layout sheet
should be prepared to include as many items as are available at the time of field check.
Plot layout to largest scale that will fit bridge on the sheet (1"=30 Min.). For long bridges
use more than one sheet. As a minimum for field check, the following information should
be included on the contour map and the layout sheet.
a.
Elevation and plan details of proposed structure with span lengths, stations and
profile grade elevations.
b.
c.
d.
The roadway.
e.
f.
g.
h.
Unit stresses.
i.
Design loading.
j.
k.
Streambed elevation, water elevation with date, design high water and historic
high water with date and location, and ordinary highwater elevation and two
Bench Mark elevations.
Bridge Section
2 - 108
Design Manual
l.
m.
n.
For Railroad overpasses, indicate railroad clearances, top of rail, R.R. Stationing,
highway clearance, top of road. (For railroad overpass, see Section 1.2.6 Railroad
Agreement for additional field check data and pre-field check data requirements,
including the Overhead Submittal Checklist).
o.
For channel changes, show plan and elevation view, profile view of ground and
proposed flow-line of channel and typical section.
p.
q.
Show shoulder line, roadbed width, earth slopes and berm information.
r.
Water opening sketch of existing bridge and adjacent bridges. (Include T.O.
Elevation)
s.
t.
If existing structure, show substructure in plan and elevation and check for
conflicts. If the limits of new and existing footings are 5 ft. or less, produce a sheet
showing the existing and proposed substructure elements for Field Check. Note
that in some instances, there are two existing structures that may be of concern.
u.
3.
4.
Prepare questions (on 8 x11 sheets or detail sheets) to be considered during field
check. Typical field check questions to be discussed are as follows:
a.
b.
Bridge Section
2 - 109
Design Manual
5.
c.
Any salvage?
Amount
Where stockpiled
Disposal by contractor
Place as slope protection
d.
_____________
e.
_____________
f.
g.
h.
i.
Condition of channel
Is clearing required?
Is slope protection required?
Are there unusual conditions? List
Is a spur dike required? If so, where.
Ice loads to be considered in design?
j.
Utilities
What utilities are on bridge?
What utilities are near the bridge?
k.
l.
m.
n.
Additional questions for rehabilitation projects (Refer to Bridge Maintenance Packets, see
Section 2.1 GENERAL)
a.
What is the condition of the structure?
Condition of the piers?
Bridge Section
2 - 110
Design Manual
Column damage?
Are footings exposed?
Condition of the deck?
Design Exceptions needed for:
(1) Rail?
(2) Design Loading?
(3) Width?
(4) Clearance?
b.
c.
d.
e.
welded
riveted
bolted
______
______
______
Condition of paint?
Date of last painting
____________
Is paint lead content test (TCLP) required?
What is the condition of abutment?
Clearance?
What is condition of expansion device?
What is condition of bearing devices/bearing pads?
What is condition of concrete deck?
Replacement?
Yes ___ No ___
Overlay?
Yes ___ No ___
Bridge Section
2 - 111
(1)
(2)
f.
6.
Design Manual
For box extension lengths of 15 feet or less, the extension should be tied to
the existing box by either reinforcing dowels or provide lap length with
existing reinforcement.
For extensions greater than 15 feet in length, the extension can generally be
free standing and can butt against the wings and hubguard. Check cover
over hubguard provided by new grade line - should be at least 1-0 to
avoid a hard spot in the traveled way. The hubguard serves as an edge beam
for the slab and when the old hubguard is removed, the slab should be
removed to provide lap length of the reinforcing for the extension. Also,
when butting the slab extension to the existing box, an edge curb should be
constructed.
f.
g.
h.
7.
8.
If channel change is of extended length beyond sheet size for contour map, include
additional sheet showing:
a.
Geometric Layout
b.
Typical Sections
c.
Profile of Channel Change
9.
If the time-table for plan completion is a problem, and project is to have a combined field
check, obtain permission to furnish preliminary plans to Soils and Geology Unit prior to
field check. In the request to Geology, furnish the preliminary plans with the location of
piers and/or type of structure and indicate the plans are subject to change but that an
evaluation is needed to meet the schedule for completion of final plans.
Distribution of Field Check Plans
10.
Bridge Section
2 - 112
a.
b.
c.
Design Manual
**
Send Field Check Plans only on Interstate Projects greater than $1 million (Full
Oversight Management). Include 883, Bridge Inspection Display Sheet, Bridge
Log, Hydraulic Assessment Checklist and Sufficiency Rating if bridge
replacement.
For open span bridges, provide Geology with two field check sets and Soils with
one set. For all consultant Geotech/Geology, refer to Investigation Practices:
Attachment A5-1 Bureau of Design Memorandum (05-15)
For walls, culverts, etc., provide two sets to Soils.
Send Environmental Services the Hydraulic Assessment Report.
Bridge Field check comments should be added to the Road Section plans that go to
District.
For new bridges, certain rehab's and 10 to 20 Structures, (Formerly known as
500 Series RCBs); request a new serial number from the Bridge Special
Assignments Section. Send a one-half size print of the Title Sheet along with the
request.
Bridge Section
2 - 113
Design Manual
Bridge Section
2 - 114
Design Manual
Bridge Section
Bureau of Design
Kansas Department of Transportation
February, 1995
Bridge Section
2 - 115
Design Manual
TABLE OF CONTENTS
Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Existing Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Historical High Water . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Drainage Basin Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Hydrology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Bridge Hydraulics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
a) Existing US-160 Bridge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
b) Proposed 15 m - 6 @ 20 m - 15 m Haunch Slab . . . . . . . . . . . . . . . . . . . . 8
c) Proposed 22 m - 4 @ 27 m - 22 m Steel Rolled Beam. . . . . . . . . . . . . . . . 12
d) Proposed 7 @ 21.5 m Prestressed Beam . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Scour Evaluation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Recommendation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Reference List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Appendix A Hydraulic Assessment Checklist . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
Appendix B Scour Evaluation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-1
Scour Computation Spreadsheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-2
WSPRO Analysis with HP cards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-11
Guide Bank Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .B-23,B-24
Appendix C Hydrology Calcs. with Regression Analysis . . . . . . . . . . . . . . . . . . . . . C-1
Appendix D Rating Curves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D-1
Appendix E WSPRO Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E-1
Appendix F Miscellaneous Data. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F-1
Bridge Section
2 - 116
Design Manual
LIST OF FIGURES
Figure No. 1
Figure No. 2
Figure No. 3
Contour Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Figure No. 4
Figure No. 5
Figure No. 6
Figure No. 7
Aerial Photograph . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Figure No. 8
Figure No. 9
LIST OF TABLES
Table No. 1
Table No. 2
Table No. 3
Table No. 4
Bridge Section
2 - 117
Design Manual
Introduction
The Kansas Department of Transportation plans to replace the bridge on US-160 at the Bluff
Creek crossing 3.62 km West of the Clark-Comanche county line in Comanche County (see
Figure No. 1). The project is scheduled to be let in September, 1996. The project authorization
('883') proposes an 11 m roadway. Design AADT is 1000.
Existing Structure
The existing structure is a 19 @ 9.91 m simple span reinforced concrete deck girder. It was
constructed in 1931 with a 7.315 m roadway. Total waterway provided is 321.4 m2 Low steel
elevation is 556.58 m which is about 2.77 m above the flow line. In 1969, work was done to repair
the existing bridge girder ends and bridge seats at the joints. Today structural deterioration has
prompted a posted load of 23-36-36 T. A comparison of the Existing channel location with the
location in 1931 shows that the channel has migrated about 64 m east. The 1993 Sufficiency
rating is 52.7%.
Historical High Water
The original plans dated 1931 show historical high water at elevation 556.12 m. The original
plans show elevation 263.25 m, and adjusted to current datum, equals elevation 556.12 m.
According to Bob Armstrong, Area One Construction Engineer, water has not been over the
roadway (Crown Grade Elev. 557.57), but it has been reported to be up to the bottom of the deck,
Elevation 557.15 m.
Bridge Section
2 - 118
Design Manual
Bridge Section
2 - 119
Design Manual
Bridge Section
2 - 120
Design Manual
streams in Western Kansas. 5) Log-Pearson III analysis on USGS gage #07157940 on Bluff Creek
adjusted for area. Figure No. 4 shows a log-probability plot for all methods considered.
USGS gage #07157940 was on Bluff Creek at the Cimarron River confluence, and has a
drainage area of 1702 km2 of which 197 km2 is probably noncontributing. There is only 7 years of
gage flow records. The contributing drainage area for the gage is 1505 km2. A Log-Pearson III
analysis was run on the 7 flow values adjusted by the ratio of the areas. (793 m2 /1505 m2) These
flows are not very representative of the flow rates above the Q10 to Q25 range. With such limited
data these flows were not used to determine design flow rates.
For the comparative hydrological study, data from selected gaged sites in western Kansas was
used to create a multiple linear regression model based on the drainage area and the 2-year, 24hour rainfall. There were 26 sites used. Drainage areas ranged from 3 km2 to 14330 km2 with 6
below 25 km2, 9 between 25 km2 and 250 km2, and 10 above 250 km2. There are 2 gage sites with
less than 20 years of record, 7 gage sites between 20 and 25 years of record, and 16 gage sites
with greater than 25 years of record. The maximum years of record is 41 years, and the minimum
years of record is 17 years. The gage data and log-Pearson III frequency-flow data were taken
from the USGS Report 87-4008. The flood frequencies from the comparative hydrological study
were selected for Q2 to Q100. The Q500 frequency flow was taken as 1.7*Q100. Table No. 1
contains the frequency-flow data selected.
Bridge Section
2 - 121
Design Manual
Table No. 1
Flood Frequencies Selected for Design
Q2 = 34.9 m3/s
Q5 = 92.7 m3/s
Q10 = 152 m3/s
Q25 = 255 m3/s
Q50 = 353 m3/s
Q100 = 473 m3/s
Q500 = 804 m3/s
(See Appendix C for computations)
Bridge Section
2 - 122
Design Manual
Bridge Section
2 - 123
Design Manual
Bridge Hydraulics
Stream cross sections as well as cross sections at the existing bridge openings were taken from
the field survey. Additional cross sections were taken from the contour map as required for
analysis. From the USGS Quadrangle map a stream bed profile was plotted (see Figure No. 5). A
slope of 1.72 m/km (0.172%) was chosen to represent downstream tailwater conditions. The
average depth of the channel from the flow line to the Q2 to Q5 bank is about 2 m, and averages
60 m in width. The average depth of the channel that contains the Q100 is about 4 m and is about
600 m to 800 m in width. Average bankfull approximately elevation 555 m to 556 m (see Fig. No.
6). Comparing an aerial photo from July 1993 (Fig. No. 7), and pictures taken during bridge
inspections, Manning's 'n' values of 0.035 to 0.045 for the streambed, 0.10 for overbank timber,
and 0.05 to 0.07 for other overbank areas were estimated. Figure No. 6 shows the cross sections
and 'n' values used for the computer model WSPRO (See Appendix F). Existing overtopping
elevation is approximately 557.5 m. High water has been up to the bottom of the deck (Elev.
557.15 m) but has never been the road.
A WSPRO model was created using the above data. Table No. 2 lists the results obtained from
the WSPRO modeling of the existing and proposed bridges. See Appendix E for the input used in
the WSPRO calculations.
a.) Existing US-160 Bridge Effective low steel elevation is approximately 556.59 m which
is about 2.77 m above streambed. Existing effective waterway opening perpendicular to stream
flow is about 321 m2 Existing high water clearance at Q50 is about -0.32 m. Existing high water
clearance at Q100 is about -0.62 m. The frequency of overtopping is about 80 years. This
resulting frequency is judged to reasonably agree with the highwater information, and the
assumptions for the WSPRO model were deemed satisfactory.
Bridge Section
2 - 124
Design Manual
Bridge Section
2 - 125
Design Manual
b.) 15 m - 6@20 m - 15 m Haunch Slab The haunch slab provides about 368 m2 of effective
waterway opening. Proposed low steel elevation is 557.24 m which is 0.65 m above existing
low steel. High water clearance at Q50 is about 0.35 m. High water clearance at Q100 is about
0.06 m. The proposed bridge is 38.29 m shorter than the existing bridge. Channel grading will be
required to shape the existing channel to take advantage of the proposed bridge opening. A raise
in grade of about 0.28 m will be required. The proposed location for abutments and piers will not
interfere with the existing footings (see Figure No. 8). Overtopping frequency is Q90.
c.) 22 m - 4@27 m - 22 m Steel Rolled Beam The steel rolled beam provides about 410 m2 of
effective waterway opening. Proposed low steel elevation is 557.52 which is 0.93 m higher than
existing low steel. High water clearance at Q50 is about 0.63 m. High water clearance at Q100
is about 0.34 m. The proposed bridge is about 36.29 m shorter than the existing bridge. Channel
grading will be required to shape the existing channel to take advantage of the proposed bridge
opening. A raise in grade of about 1.12 m will be required. The proposed location for abutments
and piers may interfere with the existing footings. An analysis using WSPRO was not made, but
the results would be similar to or better than the haunch slab.
d.) 7@21.5 m Prestressed Beam The prestressed beam provides about the same effective
waterway opening as the steel rolled beam bridge. Proposed low steel elevation is 557.52 which
is 0.93 m higher than existing low steel. High water clearance at Q50 is about 0.63 m. High
water clearance at Q100 is about 0.34 m. The proposed bridge is about 37.79 m shorter than the
existing bridge. Channel grading will be required to shape the existing channel to take advantage
of the proposed bridge opening. A raise in grade of about 1.43 m will be required. The proposed
location for abutments and piers may interfere with the existing footings. An analysis using
WSPRO was not made, but the results would be similar to or better than the haunch slab.
Bridge Section
2 - 126
Design Manual
Table No. 2
Backwater Results from WSPRO Computations
----------------------------------------------------------Existing
Proposed
Normal
19@9.1 15-6@20-15
Frequency
WSEL
Backwater Backwater
----------------------------------------------------------Overtopping 557.50
Q80
Q90
Contact L.S.
Q25
Q115
Q2
555.57
0.00
0.00
Q5
556.23
0.00
0.00
Q10
556.60
0.02
0.02
Q25
556.94
0.05
0.11
Q50
557.17
0.17
0.18
Q100
557.44
0.30
0.26
-----------------------------------------------------------
Discussion
The steel rolled beam alternate and the prestressed concrete beam alternate would require that
highwater clearance at the Q100 be at least 0.3 m but preferably not less than 0.6 m. This would
require a raise in the road grade in the vicinity of the bridge on the order of 1.1 m to 1.4 m for the
steel rolled beam and on the order of 1.4 m to 2.0 m for the prestressed concrete beam. Because of
the existing steep grade on the approach to the bridge from the west, a considerable expense
would be needed to raise the grade more than 0.3 m at the bridge site. The requirement for the
highwater clearance at the Q100 to be at least 0.3 m has been waived before on reinforced
concrete haunched slabs due to their weight and inability to trap air and debris between girders.
Bridge Section
2 - 127
Design Manual
The shorter proposed bridge will cause an increase in the velocity of the flow through the bridge
at flow rates below Q70. The largest increase in velocity is at Q25 which is 25% greater than the
existing bridge. (See Appendix D-5) The overall performance of the shorter proposed bridge will
be improved above the Q70 flow rates due to the increased highwater clearance. The estimated
cost for the haunch slab alternate is listed in Table No. 3.
Table No. 3
(15 m - 6@20 m - 15 m Reinf. Conc. Haunch Slab Alternate)
Bid Item
Quantity
Units
Unit Cost
Total
70
m3
$45.00
$3,150.00
m3
$365.00
$0.00
1103.7
m3
$390.00
$430,443.00
150000
kg
$1.35
$202,500.00
kg
$1.20
$0.00
HP250x62 Piles
60
$85.00
$5,100.00
126
$1050.00
$132,300.00
36
m2
$22.00
$792.00
30.2
m2
$50.00
$1,510.00
Total =
$775,795.00
= $470/m2
Bridge Section
2 - 128
Design Manual
Scour Evaluation
Based on the original plans dated 1931, redbeds were estimated at elevation 551.2 m or about
2.6 m below the existing streambed. The redbeds consist mainly of shale, siltstone and sandstone
interbedded with gypsum, salt and dolomite. The banks of the stream are composed of sandy
loam. Between the redbeds and the stream bed there is sand. A scour analysis for the proposed 15
m - 6 @ 20 m - 15 m RCSH bridge was completed using the procedure outlined in Bridge Scour
Analysis Using WSPRO by Parr. The Q100 was used for the worse case for bridge scour. See
Table No. 4 for a summary of the results. Appendix B contains the data and calculations used for
the scour analysis.
Table No. 4
Scour Type
Left Overbank
Main Channel
Right Overbank
Degradation
0.0 m
0.0 m
0.0 m
Contraction
1.1 m
1.7 m
1.4 m
Pier
3.5 m
3.0 m
2.9 m
Abutment
5.2 m
--
5.2 m
Total at Pier
4.6 m
4.7 m
4.8 m
Total at Abutment
6.3 m
--
6.6 m
Bridge Section
2 - 129
Design Manual
A review of the maintenance folder for the US-160 bridge revealed no record of repairs due to
stream erosion, although the contour map suggests that stream erosion has occurred at the bridge
site. Also, the stream bed is sandy and there is evidence that the main channel has moved laterally.
Figure No. 9 shows the plot of the computed scour at the bridge site. There is a large amount
of calculated abutment scour. Using the guidelines from HEC #20, the length of guide bank
suggested is 25 m. Guide banks should be used on both abutments. The piling or the drilled shafts
for the piers will be driven to bearing or will socket into the redbeds respectively, so scour will not
be critical for this bridge.
Recommendation
Based on the above information it is recommended that the proposed 15m-6@20m-15m
reinforced concrete haunch slab replace the existing structure.
Bridge Section
2 - 130
Design Manual
Bridge Section
2 - 131
Design Manual
Reference List
1.
2.
3.
4.
5.
6.
Floods In Kansas and Techniques for Estimating Their Magnitude and Frequency on
Unregulated Streams, U.S.G.S. Regression Method, R.W. Clement, U.S.G.S. Lawrence,
Kansas, 1987.
7.
Technical Report No. 11, Magnitude and Frequency of Floods in Kansas, Kansas Water
Resources Board. February, 1975.
8.
9.
Evaluating Scour at Bridges Second Edition, Hydraulic Engg. Circular #18, Federal
Highway Adm., Report No. FHWA-IP-90-017. Revised April, 1993.
10.
Stream Stability at Highway Structures, Hydraulic Engg. Circular #20, Federal Highway
Adm., Report No. FHWA-IP-90-014. February, 1991.
11.
Bridge Scour Analysis Using WSPRO, David E. Parr & Shimin Zou Department of Civil
Engg., University of Kansas, Lawrence. November, 1992.
12.
Soil Survey of Clark County, Kansas, United States Department of Agriculture, Soil
Conservation Service, US Government Printing Office: 1982-376-600/2032, Issued
December 1982.
13.
Soil Survey of Comanche County, Kansas, United States Department of Agriculture, Soil
Conservation Service, US Government Printing Office: 1989 0-242-994:QL3.
Issued June 1989.
Bridge Section
2 - 132
14.
Design Manual
Kansas Landscapes: a geologic diary, Frank W. Wilson, Kansas Geological Survey, The
University of Kansas, Lawrence, Kansas. 1978.
15.Kansas Rocks and Minerals, Laura Lu Tolsted and Ada Swineford, Kansas Geological Survey,
The University of Kansas, Lawrence, Kansas. 1997
Bridge Section
2 - 133
Design Manual
Bridge Section
2 - 134
Design Manual
Bridge Section
2 - 135
Design Manual
Bridge Section
2 - 136
Design Manual
Bridge Section
2 - 137
Design Manual
Bridge Section
2 - 138
Design Manual
List of Figures
Figure 3.4.2-1 Military Heavy Equipment Transport .....................................................................7
Figure 3.4.2-2 Map showing area of Ft. Riley military influence for Seismic Detailing ..............8
Figure 3.4.7-1 Railroad Grade Separation Crash Wall Details .....................................................13
Figure 3.4.8-1 FLOW CHART FOR SEISMIC LOADS .............................................................16
List of Tables
Table 3.3 -1 Standard KDOT Load Modifiers ................................................................................3
Appendix
Appendix A ...................................................................................................................................20
Reference
References .....................................................................................................................................19
Bridge Section
3-i
Design Manual
Bridge Section
3- 1
Design Manual
ate strength reduction factor (0.75 for both tied and spiral columns See Article 5.5.4.2) to
account for variations in material strengths and workmanship.
Even in the absence of external loading, concrete experiences deformations and volume changes
due to shrinkage and the effects of temperature changes. Reinforcement for shrinkage and temperature stresses must be provided near exposed surfaces of walls and slabs not otherwise reinforced. The total area of reinforcement provided shall be at least that specified in Article 5.10.8 in
each directions. Shrinkage is a special consideration in the design of prestressed concrete.
Bridge Section
3- 2
Design Manual
Redundancy ( R)
Importance ( I)
Value
Condition
1.00
1.05
1.00
Redundant
1.05
Non Redundant
0.95
1.00
1.05
3.4 Loads
3.4.1 Permanent Loads
The dead load consists of the structure complete, including roadways, curbs, sidewalks and railing. In addition to the structure dead loads, superimposed dead loads such as pipes, conduits,
cables, stay-in-place forms and any other immovable appurtenances should be included in the
design.
Consider the weight of the overlay on a two-course deck to be a 'DC' load. Future
wearing surface (FWS) loads will be considered 'DW' loads. Design dead loads for future wearing surfaces are closely related to KDOT's policy for Bridge Deck Protection (see Section 9.2.1).
For one-course decks with 2 in. clear to top of reinforcing, 25 psf will be used. For two course
decks and one course decks with 3 in. clear to top of reinforcing, 15 psf will be included in the
design. This loading assumes that when the future overlay is in place, in. of concrete will be
milled off the decks that have 2 in. clear and 1 in. will be milled off the decks with 3 in. clear to
top of reinforcing.
The future wearing surface load is not included in the dead load deflections.
Bridge Section
3- 3
Design Manual
Bridge Section
3- 4
Design Manual
loads is a change in KDOTs policy. In the past, only the areas surrounding Fort Riley were subject to the HET loadings. However, the recent trend of routing these military vehicles throughout
the entire state has warranted a change in KDOTs policy.
Use the following HET application and rating guidelines:
HET: Use a minimum Operating Stress Level Rating Factor of 1.0 with full impact and modified
distribution described below. This should result in the HET loading equaling 170-175% of a
HS20 truck and resulting stress levels.
1) For Girder Bridges use full impact and a single lane distribution factor (S/7.0) at the Operating Stress Level.
2) Slab Bridges have a single lane distribution equal to the multi-lane distribution, use full
impact and a 15% increase in the distribution (i.e. 1/E will become 1/(E*1.15)).
NOTE: The single lane distribution factor in girder structures and the15% increase in distribution in slabs is an approximate adjustment for the twelve-foot width trunnion
axles on the trailer.
3) Fatigue and crack control criteria, which is used for normal load rating trucks, are not used
for the HET vehicle or other permitted vehicles due to the smaller number of loading occurrences. See section 4.10.2 LFD Load Rating
4) All new bridge design plans, for projects on state routes, will include the following LFD &
LRFR Rating Factors Chart, on the General Notes and Summary Sheet.
Bridge Section
3- 5
Design Manual
Bridge Section
3- 6
Design Manual
Bridge Section
3- 7
Design Manual
Figure 3.4.2-2 Map showing area of Ft. Riley military influence for Seismic Detailing
Note:
Only A, B & C route bridges within the above are considered relative to the enclosed area.
Bridge Section
3- 8
Design Manual
Bridge Section
3- 9
Design Manual
Bridge Section
3 - 10
Design Manual
2) If it is required that the face of the pier be located inside the clear zone, the design of the pier
must include the 600 kip collision force.
3) If the pier is located inside of the clear zone, use one of the following barriers to protect the
pier:
a) If the barrier is located greater than 10-0 from the face of the pier, use a 42 (TL5) Barrier
Rail.
b) If the barrier is located 10-0 or less from the face of the pier, use 54 high (TL5) Barrier
Rail.
Bridge Section
3- 11
Design Manual
For a bridge over a railroad, KDOT will retain design criteria, but allow exemptions consistent
with Table C.3.6.5.1-1; use the road over as determination of route traffic count and railroad as
curved or tangent determination. The above criteria is related to the existing railroad conditions.
1) If the face of a pier is located greater than 50-0 from the centerline of the tracks, the collision force on the pier will not be required.
2) If the face of a pier is located less than 50-0 and greater than 25-0 from the centerline of
the tracks, the design of the pier must include the 600 kip collision force.
3) If the face of a pier is located less than or equal to 25-0 (H) from the centerline of the tracks,
the design of the pier must include a crash wall in addition to the 600 kip collision force. See
Figure 3.4.7-1 Railroad Grade Separation Crash Wall Details for design and geometry
requirements of the crash wall.
Bridge Section
3 - 12
Design Manual
Bridge Section
3- 13
Design Manual
As is greater than 0.05 then use 0.25 times the dead load plus EQ = 0.25
*As is greater than 0.05 then use 0.25 times the dead load plus EQ = 0.50
* See Figure 3.4.2-2 Map showing area of Ft. Riley military influence for Seismic Detailing for
Fort Riley military influence area.
These horizontal forces are transferred through the connector into the substructure. The substructure elements are then designed and reinforced to resist these applied static loads. The forces
transferred to the substructure elements have response modification factors as shown below.
Structures within the Ft. Riley influence are either Critical or Essential, structures outside this
region are defined as Other. There maybe exceptions, a structure maybe upgraded from
Essential to Critical if an exceeding long detour, if no other crossings are within that reach of
the river system or as directed by the State Bridge Office. A structure is Critical if the location
is at a multilevel interchange where collapse would compromise other important routes below.
Bridge Section
3 - 14
Design Manual
The response modification factors for the transfer of loads to the connection from the superstructure are shown above, these factors are self-explanatory.
Article 3.10.9.5 does not allow friction to be used to resist the longitudinal forces.
Use Site definitions in Table 3.10.3.1-1 with Acceleration Coefficients in Figure 3.10.2.1-3 to
determine As.
For retrofit design, See the FHWA Report (1987), this can assist designers in evaluating existing
bridges for seismic resistance.
Bridge Section
3- 15
Design Manual
3 - 16
Bridge Section
Design Manual
Bridge Section
3- 17
Design Manual
need to be considered in the design of the substructure. The bridge should be fully functional
while in a scoured condition under the strength and service limit states when subjected to a 100
year flood or less. Check the 100-year flood, the overtopping flood (if less than the 100-year
flood) and other events if there is evidence that such events would create deeper scour than the
100-year or overtopping floods.
Stream forces shall be applied to a depth based on the scour evaluation. When checking the lateral resistance of the piling or drilled shafts, no lateral support from the soil above the estimated
scour line shall be assumed.
See 2.3.9.3 Scour Analysis for further discussion on scour.
Bridge Section
3 - 18
Design Manual
References
AASHTO, (2004). A Policy on Geometric Design of Highway and Streets, 5th Edition.
FHWA Report, (1987). Seismic Design and Retrofit Manual for Highway Bridges, Report Number FHWA-1P-87-6.
Portland Cement Association, (1983). Continuous Concrete Bridges, Second Edition, p.34.
Bridge Section
3- 19
Design Manual
Appendix A
Definitions:
ADTTSL is the single-lane average daily truck traffic in one direction.
This is for the traffic lane in which the majority of the truck traffic crosses the bridge. On a typical bridge
with no nearby entrance/exit ramps, the shoulder lane carries most of the truck traffic. The frequency of
the fatigue load for a single lane is assumed to apply to all lanes since future traffic patterns on the
bridge are uncertain.
D
If only bidirectional ADTT is available, one direction truck traffic may be estimated as 55 percent of the
biderectional truck traffic.
rate
If the design ADTT is not given for a 75 yr design life, the data my be estimated by extrapolating the
current growth rate given.
AADT
average annual daily traffic. (Limit of 20,000 vehicles per day per lane)
Inputs:
AADTcurrent 3450
Yearcurrent 2011
AADTdesign 4325
Yeardesign 2031
p 0.85
Bidirectional "no"
D 55%
Theavy 24.9%
Tmed 5.1%
Calculations:
rate
AADTdesign AADTcurrent
rate
Yeardesign Yearcurrent
AADT75
AADTProjected
AADTcurrent AADTProjected
AADT75
2
ADTTSL
6731
5091
if Bidirectional = "yes"
otherwise
Results:
ADTTSL
1298
Bridge Section
3 - 20
Design Manual
4 ANALYSIS
Table of Contents
4.1 General .....................................................................................................................1
4.2 Methods of Analysis .................................................................................................1
4.2.1 Hand Analysis Methods ...............................................................................................1
4.2.2 Line Girder Analysis Methods .....................................................................................1
4.2.3 Grid Analysis Methods .................................................................................................1
4.2.4 Plate and Eccentric Beam Grid Analysis Methods ......................................................2
4.2.5 3D Grid Analysis Methods ...........................................................................................2
4.2.6 3D Analysis Methods ...................................................................................................2
Bridge Section
4-i
Design Manual
4 ANALYSIS
4.1 General
In general all analysis will fall into two categories, elastic and inelastic, that is, behaving in a linear or non-linear fashion. Of these, there are two parameter types to consider, geometric and material behaviors. With the exception of P-delta analysis for long columns in substructure design, all
KDOT designs will be designed as linear elastic using first order analysis. Allowing inelastic
material resistance without doing a second order analysis is considered a lack of compatibility.
Bridge Section
4- 1
Design Manual
4.3 Discretization
Prior to the advent of desktop computers, structures were mathematically disassembled to simplify the analysis. Traditionally, the reaction of individual components were used in loading adjacent members, thus limiting the degree of external indeterminacy and simplifying the work of the
analyst. For planer (1-D) analysis, this method still has considerable merit in that conservative
boundary conditions can be applied to each member thus maximizing the force effects in each.
Also, these methods lend themselves to closed form solutions. Modern methods do not need this
level of simplification, however the principles used still apply. All modern structural analysis programs use stiffness methods to model the structures behavior. This involves mapping a members
degrees-of-freedom, through the member stiffness matrix, to the structure degrees-of- freedom
creating a global structure stiffness matrix with boundary conditions consistent with the actual
structure. Inverting the structure stiffness matrix and multiplying by the load vector yields the
structures displacement vector. From this, all member end forces are obtained. The general form
is:
1
{ }= [ K] {P }
Where:
{ } = Displacement
1
Bridge Section
4- 2
Design Manual
The structure being analyzed shall be reduced to members or elements connected with the same
number of degrees-of-freedom which represents the attributes of the physical structures. Members
which have only slight cross-sectional changes can be modeled as prismatic members with nodes
at convenient locations such as tenth points. Non-prismatic components may be modeled by discretization of the components into a number of frame elements with stiffness properties representative of the actual structure at the locations of each element. The use of beam elements with
nodes having six degrees-of-freedom will accomplish the desired goal. When using finite elements, plates or shells, limit the aspect ratio to 5:1 to reduce errors. Solids should only be used as
load transferring devices or to prove structural continuity. It is important to remember that rods,
beams, plate and shells derive their stiffness from constants multiplied outside of the stiffness
matrix, whereas solids derive their stiffness as geometry from nodal locations. Solids are therefore
more sensitive to geometrically induced errors.
The degree of continuity and the location within the cross-section where load transfer occurs
could conceivably effect the analysis results for members that are not considered axially rigid. If
the member stiffness matrix considers an axial degree-of-freedom, then the load path will follow
the centroid of the member and supports resisting these forces will form a couple, resulting in
internal moments. These considerations must be well understood by the analyst. Using a member
offset creates a rigid link which will pick up these internally coupled effects.
Boundary conditions for the model vary with assumed structural responses of the supports. They
can be idealized as pinned or fixed for both translation and rotation in either a yielding or nonyielding condition. This can be refined where the rotational or translational stiffness is represented by springs with the same stiffness as the members framing into that location. One common
example of this, in bridge design, is the modeling of the substructure elements. For example, the
analyst may represent pile as short lengths assumed by fixed at a point below the ground corresponding to where the maximum moment in the pile would occur. This can be determined by a PY analysis performed with programs like L-Pile or COM624. Without such information it is recommended that this point of fixity be considered at 8 feet below the ground line for cohesive
materials and 10 feet for cohesionless materials. If the boundary conditions can change during the
life of the structure, as in the case of scour, then both limits will be investigated.
Bridge Section
4- 3
Design Manual
Bridge Section
4- 4
Design Manual
Bridge Section
4- 5
Design Manual
4.6 Superstructure
This section looks at how the force effects for each design element are obtained.
4.7 Substructure
4.7.1 Bearing
To maximize the force effects use the controlling (obtuse corner) skew correction with the maximum load factor for all supports. Check uplift by using the lower skew correction factor (acute
corner) with the minimum load factor.
Bridge Section
4- 6
Design Manual
4.7.3 Column
All loads must pass through the columns into the foundation. For vehicular collision design,
frame action can be considered if a crash worthy wall is cast between the columns. Columns will
be analyzed for moments caused by biaxial loads at the top and bottom of the column.
4.7.4 Footing/Foundations
This section is to be completed later.
4.8 Fixity
The overall fixity of the bridge should be examined in detail for bridges on steep grades, moderate
to severe curvature, or when the columns are tall and/or slender. Use the following guidelines for
providing fixity at bearings.
For short bridges on steep grades, the down hill abutment should be fixed. For longer bridges
the flexibility of each pier and its bearings need to be considered to determine the appropriate
substructure units to fix. If pier flexibility and geometry permit, a minimum of two fixed
piers per expansion unit should be used.
For very flexible piers, such as pile bents or slender columns, the expansion bearings may be
redundant in that the pier may move before the bearings begin to slide.
For typical prestressed I-beam bridges with two sets of bearings surfaces on each pier (per
beam line), sufficient anchorage to the pier is provided by using strands that to extend into the
cast-in-past diaphragm that is anchored to the pier beam though doweled reinforcement.
For river piers and for spans over 145, feet designers will provide bearings that are guided
externally.
(1) NCHRP Report #592 (Project 12-62) Simplified Live Load Distribution Factor Equations
(2) Non-Standard Gage Finite Element Analysis using AASHTOWare Bridge Rating/AASHTOWare
Bridge Design
Bridge Section
4- 7
Design Manual
5 CONCRETE
Table of Contents
5.1 Cast in Place Concrete ............................................................................................................1
Bridge Section
5-1
Design Manual
List of Tables
Table 5.3.2.1-1 Temperature Effects. .............................................................................................2
Table 5.1.4-1 Nominal Fatigue Resistance of Splices ..................................................................16
Table 5.1.5-1 Cover for Unprotected main Reinforcing Steel (in.) ..............................................20
Table 5.2.1-1 Prestressed Beam Length Harp Criteria ..............................................................107
List of Figures
Figure 5.1.3.3-1 ...............................................................................................................................6
Figure 5.1.3.5-1 Phased Construction Splice Types .......................................................................8
Figure 5.1.3.5-2 Splice/ Coupler Reinforcing .................................................................................9
Figure 5.1.4-1 Hook Details ..........................................................................................................12
Figure 5.1.4-2 Stirrups Details ......................................................................................................12
Figure 5.1.4-3 Prestressing Strands Development Length ...........................................................13
Figure 5.1.5-1 Armoring for Expansion Joints .............................................................................18
Figure 5.1.5-2 Elastomeric Concrete ............................................................................................18
Figure 5.1.6.2-1 Area of Steel Required .......................................................................................26
Figure 5.1.6.3-1 Column Design ................................................................................................27
Figure 5.1.6.3-2 Minimum Reinforcement Ratio ........................................................................28
Figure 5.1.6.3-3 Column Expert Software Limits For Redundancies ..........................................30
Figure 5.1.6.3-4 Column Expert Software Limits For 75% Rule .................................................30
Figure 5.1.6.3-5 Seismic Concrete Detailing ................................................................................31
Figure 5.1.6.3-6 Seismic Concrete Detailing ................................................................................32
Figure 5.1.6.3-7 Seismic Concrete Detailing ................................................................................33
Figure 5.1.7.1-1 Standard R.C. Haunched Slabs ..........................................................................40
Figure 5.1.7.1-2 Transverse Spacer Frames ..................................................................................41
Figure 5.1.7.1-3 Continuous Slab Edge Beam ..............................................................................42
Figure 5.1.7.1-4 Suggested Standard Abutment Design ...............................................................43
Figure 5.1.7.1-5 Standard Haunched Slab Abutment Details .......................................................44
Figure 5.1.7.1-6 Pier Beam Design - RCHS .................................................................................45
Figure 5.1.7.1-7 General notes and Quantities (BR 200) .............................................................46
Figure 5.1.7.1-7a Slab Elevations (BR 203) .................................................................................47
Figure 5.1.7.1-8 Abutment Details ...............................................................................................48
Figure 5.1.7.1-9 Pier Details (BR540) ..........................................................................................49
Figure 5.1.7.1-10 Superstructure Details - Concrete Placing Sequence .......................................50
Figure 5.1.7.1-11 Superstructure Details ......................................................................................51
Figure 5.1.7.1-12 Corral Rail ........................................................................................................52
Figure 5.1.7.1-13 Bill of Reinforcing and Bending Diagram ......................................................53
Figure 5.1.7.2-1 General Notes (A28GNot) .................................................................................56
Figure 5.1.7.2-2 Abutment Details ...............................................................................................57
Figure 5.1.7.2-3 Superstructure Details ........................................................................................58
Figure 5.1.7.2-4 Slab Details ........................................................................................................59
Figure 5.1.7.2-5 Post Tension Details ...........................................................................................60
Bridge Section
5-2
Design Manual
Appendixs
Appendix A Reinforced Concrete Design Equations ...................................................................63
Appendix B Reinforced Development Lengths Table................................................................. 66
Appendix C Post- Tensioned Haunched Slab Bridge Users Manual ..........................................70
Appendix A Prestress Beam Guidelines ....................................................................................155
Appendix B PreStress Harp Strand Force Calculator ................................................................157
Appendix C Prestressed Girder (Transportation Stress Check) ..................................................159
References
References ...................................................................................................................................62
Bridge Section
5-3
Design Manual
5 CONCRETE
5.1 Cast in Place Concrete
5.1.1 General
Cast in place reinforced concrete is used extensively in bridge projects. The design of bridge
decks, which are supported by beams or girders, are referred to as deck slabs or thin slabs and is
discussed in 9 DECK SLAB. Slab bridges, in which the deck is the only support for the loads can
be either normally reinforced or post-tensioned. When possible KDOT uses predesigned superstructures called design standards. Currently the available standard span bridge types are Reinforced Concrete Haunched Slabs with and without post tensioning. These come in finite span
combinations and have been found by KDOT to be an economical and robust structure type. Likewise, it is KDOTs policy to use predesigned box culvert standards for crossings which have been
hydraulically sized within the limits of this structure type. Walls, pier beams, abutment beams,
footing and columns represent the majority of the design challenges not currently supported by
predesigned standards.
Concrete Designations:
Current English
Grade 2.5
Grade 2.5(AE)
Grade 3.0
Grade 3.0(AE)
Grade 3.5
Grade 3.5(AE)
Grade 4.0
Grade 4.0(AE)
Grade 4.5
Grade 4.5(AE)
Grade 5.0
Grade 5.0(AE)
Old English
Grade 2.9
Grade 2.9(AE)
Grade 3.6
Grade 3.6(AE)
Grade 4.0
Grade 4.0(AE)
Grade 4.4
Grade 4.4(AE)
Grade 5.0
Grade 5.0(AE)
Current Metric
Grade 17
Grade 17(AE)
Grade 21
Grade 21(AE)
Grade 24
Grade 24(AE)
Grade 28
Grade 28(AE)
Grade 31
Grade 31(AE)
Grade 35
Grade 35(AE)
Old Metric
Original
Grade 20
Grade 20(AE)
Grade 25
Grade 25(AE)
Class B
Class B(AE)
Class A
Class A(AE)
Grade 28
Grade 28(AE)
Grade 30
Grade 30(AE)
Grade 35
Grade 35(AE)
Class AAA
Class AAA(AE)
Class AAAA
Class AAAA(AE)
tions along with the current equivalent. When designing new structures or repairing existing
structures, use the current material designations. For repairs match the existing plans original
materials to current materials. For a listing of aggregate types, concrete mix proportions, air
entrainment amounts, maximum slump and cement blend types refer to Section 401 of the Standard Specifications for State Road and Bridge Construction
Currently KDOT does not use lightweight concrete applications. There is active research in this
area looking into the benefits of the internal curing capacity of porous aggregates.
Bridge Section
5-1
Design Manual
At the time of this printing the use of self consolidating concrete is limited to repairs where access
is limited and the designer should consult the Bridge Maintenance Plans Engineer prior to use.
Equation C5.4.2.4-1
fr
0.24 f c'
0.37 f c'
0.20 f c'
The coefficient of thermal expansion is a function of the aggregate material used; aggregate types
ranging from 3.0 - 9.0 x 10 -6/oF, with calcium carbonate aggregates on the low end and silica
aggregates on the high end. KDOT will use:
Normal Weight Concrete = 6.0 x 10 -6/oF
KDOT will use procedure A and cold climate for calculating the temperature ranges in Article
3.12.2.3. For calculating the thermal force effects and displacements for design use the following:
Table 5.3.2.1-1 Temperature Effects.
Effect
TU
TU
0.33
1.2
45F
80 F **
**Total joint movement from the minimum temperature to the maximum temperature. Unless a
more refined analysis is performed, the total displacement may be split for setting joints in the
field.
This chart uses load factors based on experience and differs from the 0.5/1.2 given in the current
specfication. The long term effect of concrete creep for temperature forces is given as a reason to
reduce the effects of thermal forces transferred to the substructure. The more stringent temperature range for displacement is based on the experience that concrete grows with time, KDOT uses
this to allow for the designing for large thermal movements.
Bridge Section
5- 2
Design Manual
Bridge Section
5-3
Design Manual
much more expensive than epoxy rebar. If such material are to be considered on a project, prior
KDOT authorization is required.
ASTM A 615 Properties:
fy = 60 ksi yield strength
USC NOMINAL DIMENSIONS
Es = 29,000 ksi
SI NOMINAL DIMENSIONS
BAR SIZE
DESIGNATION
AREA
(sq. in.)
DIA.
(in.)
CI.
(in.)
WEIGH
T
(lb./ft.)
BAR SIZE
DESIGNATION
AREA
(sq.
mm)
DIA.
(mm)
CI.
(mm)
MASS
(kg/m)
#3
0.11
0.375
7 16
0.376
#10
71
9.5
11
0.560
#4
0.20
0.500
9 16
0.668
#13
129
12.7
14
0.994
#5
0.31
0.625
11 16
1.043
#16
199
15.9
17
1.552
#6
044
0.750
78
1.502
#19
284
19.1
22
2.235
#7
0.60
0.875
2.044
#22
387
22.2
25
3.042
#8
0.79
1.000
1 18
2.670
#25
510
25.4
29
3.973
#9
1.00
1.128
1 14
3.400
#29
645
28.7
32
5.060
#10
1.27
1.270
1 7 16
4.303
#32
819
32.3
37
6.404
#11
1.56
1.410
1 58
5.313
#36
1006
35.8
41
7.907
#14
2.25
1.693
1 78
7.650
#43
1452
43
48
11.380
#18
4.00
2.257
2 12
13.600
#57
2581
57.3
64
20.240
0.153 in2
0.217 in2
Bridge Section
5- 4
Design Manual
=
=
=
no markings
two longitudinal marks on bar or 60
four longitudinal marks on bar or 75
Reinforcement Bar Length: Limit the length of Grade 40 bars to 40 ft. and Grade 60 bars to 60
ft. for shipping and handling purposes.
Bridge Section
5-5
Design Manual
#4
2.00
#5
2.50
#6
4.50
#7
5.25
#8
6.00
#6
4.50
#7
5.25
#8
6.00
#4
3.00
#5
3.75
Shipping Limitations:
Shipping width or loading limitations for a single bent bar and L-shaped bar are shown in the figure below taken from, Manual of Standard Practice, Concrete Reinforcing Steel Institute,
(CRSI). The length limit is based on an assumed stock limit. For additional information see the
current CRSI booklet.
Figure 5.1.3.3-1
Bridge Section
5- 6
Design Manual
The bars are further grouped by bar size and then bar mark.
Bridge Section
5-7
Design Manual
5.1.3.5 Constructability
For drilled shaft to column connections use a splice cage that can be inserted in the top of the
drilled shaft concrete immediately after placement while the concrete is in a plastic or fluid like
state. This allows the contractor to access the center of the shaft for tremie operations.
For phased construction, if mechanical splices are not used and there is enough room for a lap
splice, the use of a splice bar allows the contractor to build cages then tie them together easily through a header. (An example of this is shown in the picture below on the left). As in the case
of phased construction using mechanical splices for locations where there is not room for a lap
bar sticking out past the form, (ie adjacent to shoring) mechanical splices with lap bars simplifies forming the header for the construction joint and eliminates the need for the contractor to
thread long bars through holes in headers. (An example of this is shown in the picture below on
the right). The designer should consider the physical limitation for phased construction.
Figure 5.1.3.5-1 Phased Construction Splice Types
Bridge Section
5- 8
Design Manual
Bridge Section
5-9
Design Manual
Bridge Section
5 - 10
Design Manual
Bridge Section
5 - 11
Design Manual
Bridge Section
5 - 12
Design Manual
3
Where:
d b = nominal strand diameter (in.)
f ps = average stress in prestressing steel at the time for which the nominal resistance of the
member is required (ksi)
f pe = effective stress in the prestressing steel after losses (ksi)
= 1.0 for pretensioned panels, piling, and other pretensioned members with a depth less
than 24
= 1.6 for pretensioned members with a depth greater than 24 in.
Bridge Section
5 - 13
Design Manual
Bridge Section
5 - 14
Design Manual
Bridge Section
5 - 15
Design Manual
= load factor specified in Table 3.4.1-1 for the Fatigue I load combination
= force effect, live load stress range due to the passage of the fatigue load as specified in Article 3.6.1.4, (ksi)
( F ) TH = constant-amplitude fatigue threshold, (ksi)
The section properties for fatigue investigations shall be based on cracked sections where the sum
of stresses, due to unfactored permanent loads and prestress, and the Fatigue I load combination is
tensile and exceeds 0.095 f c' .
Mechanical Splice: Article (5.11.5.3.2)
It is KDOTs policy not to use welded splices
Stagger splices at least 24 in.
The design stress in the mechanical splice is limited to half the yield strength
Headed Reinforcement has not been used by KDOT as anchorage for development, but is
allowed by Specification. If confined, the headed rebar is considered fully developed within
its length.
Use mechanical Couplers that appear on KDOT prequalified list (PQL-32)
The default couplers used (in KDOTs Standard Cell Library Notes) are Fatigue Resistant,
that is, they have been tested for 12 ksi cyclic stress.
Table 5.1.4-1 Nominal Fatigue Resistance of Splices
( F ) TH
Type of Splice
for greater
than
1,000,000
cycles
18 ksi
12 ksi
4 ksi
Bridge Section
5 - 16
Design Manual
Spiral Ties:
Spirals ties are not lapped for development, but are considered anchored with 1 1/2 turns on the
top and bottom of the spiral cage. For seismic detailing of the top and bottom of columns within
zone 1C, use one continuous spiral within the plastic zone or group with hoops ties for construction purposes.
Effects of Vibrations from phasing :
The University of Kansas, through KDOTs research effort (KTRAN), has shown that vibrations
due to adjacent traffic loading on freshly placed concrete results in minimal increases in the
required development or bond length. Therefore modification of the lap splice length for phased
construction due to the effects of traffic vibrations is not required. Darwin (1983)
Bridge Section
5 - 17
Design Manual
Include the note above when using armored joints in prevent voids from remaining after construction.
Figure 5.1.5-2 Elastomeric Concrete
Bridge Section
5 - 18
Design Manual
W/C
>0.50
0.46
0.44
0.40
<0.40
Factor
1.2
1.1
1.0
0.8
0.8
KDOTs Grade 4.0 AE concrete has a W/C of 0.44. Use a W/C factor of 1.0 for cover detailing
purposes. Grade 4.5 AE concrete has a W/C of 0.40. Use a W/C factor of 0.8 for detailing purposes.
The required cover to protected coated reinforcement (epoxy) uses the interior portion of Table 1
Bridge Section
5 - 19
Design Manual
Cover (in.)
4.0
3.0
3.0
2.5
2.5
2.0
1.5
2.0
1.0**
2.0
0.8
2.0
3.0
2.0
2.0
3.0
3.0
2.0
3.0
4.0
Bridge Section
5 - 20
Design Manual
Finished edges:
Round (radius), chamfer, or armor all exposed edges and corners to guard against spalling. It is
KDOTs practice to detail 3/4 in. triangular molding for this purpose. Likewise, use fillets on
inside (re-entrant) corners. Where two surfaces are to slide past each other, as in the case of semiintegral abutments, special care should be given to the detailing so the joint is free to move.
Boundaries:
When two concrete members are placed adjacent to each other, Type B expansion joint filler
material will be used (Division 1500) to prevent spalling and to allow for the concretes to be properly consolidated while allowing room to expand at different rates after hardening. If two members are placed, one on top of the other and are not connected then a bond breaker such as tar
paper should be called out to allow contractions due to curing one member relative to the other
without binding. In the case where a steel plate (plate in rail or in sidewalk), in an expansion joint
will be in contact with concrete it is common to call out a steel trowel finish and a greased surfaced to facilitate movements.
0.90
1.00
0.90
0.70
0.75
0.70
0.70
Bridge Section
5 - 21
Design Manual
Bridge Section
5 - 22
Design Manual
(Article 5.8.2.5)
bv s
A v > 0.0316 f c ------- (Equation 5.8.2.5-1)
fy
Where:
A v = area of transverse reinforcement within distance, s (in.2)
b v = width of the web (in.)
s = spacing of transverse reinforcement (in.)
f y = yield strength of transverse reinforcement (ksi)
f' c = specified compressive strength of concrete at 28 days (ksi)
Maximum Transverse Reinforcement spacing required is a function of shear stress per (Article
5.8.2.7):
v u < 0.125 f c' then:
Where:
v u = shear stress in concrete per (Article 5.8.2.9)
Vu
v u = ------------b v d v
d v = 0.72h
or 0.9d e
(in.)
Bridge Section
5 - 23
Design Manual
When (Article 5.8.4.1) is satisfied then = 2.0 and = 45 , otherwise as previously discussed, use the General Procedure for calculating and
The factored shear resistance is required to be greater than the factored loads:
Vr Vu
Where:
V u = factored shear demand at the controlling limit state
V r = V n = the factored resistance
a = 1 c
As fs
c = -----------------------0.85f c' 1 b
For flanged sections the stress block will be limited to the flange to be considered a rectangular
section, otherwise the section is consider a T-section.
Where:
M n = Nominal flextural resistance, (kip-in)
A s = Area of mild tension reinforcement, (in2)
f s = Stress in mild tension reinforcement, (ksi)
f' c = Specified compressive strength of concrete at 28 days, (ksi)
d s = Distance from the compression fiber to mild tension reinforcement, (in)
c = Distance from the compression fiber to the neutral axis, (in)
Bridge Section
5 - 24
Design Manual
The factored flexural resistance is required to be greater than the factored loads:
Mr Mu
Where:
M u = factored flexure demand (load) at the controlling limit state
M r = M n = the factored resistance
Maximum Reinforcement (Article 5.7.3.3.1)
The old c d > 0.42 relationship as the upper limit for reinforcement is not used in the current
specification. Tension controlled regions are defined as locations where the strain in the reinforcement is greater than 0.005. This minimum strain promotes ductiliy of the member at a failure
condition. The design procedure outlined for flexural design assumes a tension controlled region.
For a complete list of design assumptions for Strength and Extreme Event Limit States see (Article 5.7.2).
Minimum Reinforcement (Article 5.7.3.3.2)
The minimum amount of reinforcement to develop Mr is the lesser of:
1.2 Mcr or 1.33 Mu
Conservatively Mcr can be taken as:
M cr = S c f r with fr taken as 0.37 f 'c
Bridge Section
5 - 25
Design Manual
Bridge Section
5 - 26
Design Manual
To reduce cracking in a member, which is 3 ft. in depth or greater, the reinforcement on the longitudinal skin reinforcement along the sides of the member will be limited to:
Ae
A sk 0.012 ( d e 30 ) ----4
d
6
-----e or 12 in.
For flexure members 3 ft. in depth or less it is good design to place, as a minimum, place #4 bars
at a maximum of 12 in. spacing along the sides of the member.
Reinforcement:
In the past, the Specification indicated that the minimum reinforcement be equal to 0.01Ag. Now
fc
As
according to Equation 5.7.4.2-3 the minimum reinforcement ratio, ------, is 0.135 ----- with a
Ag
fy
minimum size of #5 and minimum of six reinforcing bars. At no time should the column be reinforced greater than 0.08Ag. KDOTs experience dictates that a column should be designed with
between 1% and 2% reinforcement, columns outside this range are candidates for resizing. A
normal 6 bar spacing should be used (2.5 db min and 8 max).
Bridge Section
5 - 27
Design Manual
fy
3.50%
Min.U = 13.5%(f'c/fy)
40
3.00%
50
2.50%
60
2.00%
75
1.50%
100
1.00%
0.50%
0.00%
3
10
f'c
For structures not falling in the Seismic Concrete Detailing Zone detail the confinement reinforcement as ties per Article 5.10.6.3. For strucutures fall within the Seismic Concrete Detailing
Zone transverse reinforcment will be detailed according to Article 5.10.11.4.1d.
The KDOT preferred lateral reinforcement in round columns is the spiral tie with a 6 in. pitch.
This spacing may not meet the requirements of the spiral definition in Article 5.7.4.6, for largerdiameter columns. Currently, the maximum diameter of spiral tie reinforcing is 72 in. For square,
rectangular or large diameter columns (> 6 ft.) use individual hoop ties with a maximum spacing
of 1 ft. A closer spacing will be used near the junction of the column with the beam, footing or
near hings. Drilled shaft confinment reinforcement usually consists of #5 spiral or hoops at 12
spacing, the region shown at the shocket interface for seimic detailing will be closer as described
below.
Reinforcing dowels projecting from a spread footing are normally provided with additional
length. This is to provide adequate splice length in the event the footing has to be lowered slightly
in the field due to adverse foundation conditions.
Columns on bridges that come in contact with salt water drainage or spray are required to have
some form of protection. Protection may be in the form of extra concrete cover over the reinforcing steel, use of a concrete sealer or, in some cases, epoxy coated bars. Typically a 3 clearance is
used for the 3db requirement.
Bridge Section
5 - 28
Design Manual
Column Analysis:
kl u
For members not braced against sidesway, slenderness effects may be neglected if ------- < 22 .
r
For member braced against sidesway slenderness effects may be neglected if
kl u
------- < 34 12 ( M 1 M 2 ) .
r
kl u
For members where ------- < 100 use the approximate method per Article 5.7.4.3.
r
kl u
For members where ------- > 100 use second order analysis to determine slenderness effects.
r
A P-delta second order analysis can be used in lieu of the approximate method.
Bridge Section
5 - 29
Design Manual
C
balanced
A
Bridge Section
5 - 30
Design Manual
Seismic Detailing:
Column:
Figure 5.1.6.3-5 Seismic Concrete Detailing shows the more stringent detailing practices as a
result of changes in the current LRFD specification for seismic detailing. The main differences
revolve around the change in return period for the event (from 500 yr. to 1000 yr.) and thus seismic detailing criteria for concrete in Zone 1B and IC per Article 5.10.11.4.1d, requires top and
bottom hinge connections. See Figure 3.4.8-1 FLOW CHART FOR SEISMIC LOADS for the
KDOT flow chart to determine which criteria to follow. At connection locations between the column and footing or column and pier beam, the confinement reinforcement must extend into the
connected member.
Footing:
Where piling penetrate the pile cap, abutment beam or pier beam, use details for confinement
reinforcement shown in the Figure 5.1.6.3-6 Seismic Concrete Detailingto meet the intent of Article 5.10.11e for seismic detailing. Use headed shear studs welded to the top of piling to provide
positive connections to the concrete. Use stirrups to provide overall confinement of the pile cap as
shown in detail below.
Bridge Section
5 - 31
Design Manual
Bridge Section
5 - 32
Design Manual
Drilled Shaft:
The nominal confinement reinforcement for drilled shafts in the past has been #5 bars at 12 spacing, for the regions shown in Figure 5.1.6.3-7 the confinement spacing will decrease. These
potential plastic hinge zones occur at the shaft/column interface. There can be a significant
changes in stiffness at this interface. The zone above and below the shaft /top of rock socket interface is the location where the lateral force are resolved. For 6-0 diameter and less drilled shafts
within this region, the shaft will be detailed as #5 bars spaced at 6 as a minimum. For 6-0
diameters and greater drilled shafts use 50% of the requirement from Article 5.10.11.4.1d. At the
column shaft interface, the tie-cage shown with spiral reinforcement should be extended to the
limits shown in Figure 5.1.6.3-7.
Figure 5.1.6.3-7 Seismic Concrete Detailing
Bridge Section
5 - 33
Design Manual
Bridge Section
5 - 34
Design Manual
The abutment wings are usually an extension of the abutment beam with a minimum extension of
5 ft. The extension should slope to match the shoulder slope for the guard fence backup. The top
elevation of the wing should match the bridge gutter line or approach gutter. Install strip drains on
the backside of the Abutment Backwall for drainage purposes. If abutment drainage is not needed,
it will be removed at field check.
For skewed slab bridges, the main reinforcing steel is placed longitudinally and the transverse
reinforcing steel is placed along the skew since spacer frames placed perpendicular to the centerline on a skewed bridge results in complications. Longitudinal spacer frames have been used but
are not recommended except for widenings. For skews greater than 20, the reinforcing steel
should be placed perpendicular to the centerline (uniform depth slab).
The uniform dead load deflection for skewed bridges is computed for the span length and that
value decreased by the percentage equal to the skew angle in degrees.
A design procedure for concrete haunched slab bridges is included on the following pages. Example details of a Reinforced Concrete Haunched Slab bridge begins at Figure 5.1.7.1-7 General
notes and Quantities (BR 200).
Standard Haunched Slab Design Criteria:
A. Loading Specifications and Unit Stresses
1. Load and Resistance Factor Design
2. For Live Load distribution, E, (Article 4.6.3.3) the span length, L1, shall be based upon
the end span.
3. Check fatigue and crack control serviceability requirements as they may govern the
design.
4. Reinforcing Steel: Grade 60 (epoxy coated) fy = 60 ksi
Usage
AADT
< 3000
Superstructures:
Slab Span
3000-5000
>5000
Gr 4.0 (AE)(SW)
(2" clear.)
Gr 4.0 (AE)(SA)
(2" clear.)
Gr 4.0 (AE)(SA)
(3" clear.)
Gr 4.0 (AE)(SW)
(2" clear.)
Gr 4.0 (AE)(SA)
(2" clear.)
Gr 4.0 (AE)(SA)
(3" clear.)
Post-Tensioned
Slabs
C.I.P.Conc.
Beams
Bridge Section
5 - 35
Design Manual
c
s := 1 + -----------------------------0.7 ( h d c )
e = 0.75
Bridge Section
5 - 36
Design Manual
From conventional concrete design practices; calculate the stress in the reinforcement and determine the maximum spacing, s for the reinforcement:
A
s
= --------bd
k=
( n) + 2 n n
j = 1 --k3
M
f s = ------------------As j d
3. When computing the design "dc," neglect the top 1 in. of the deck.
4. Minimum reinforcement in the top of the slab at the abutment shall be in the range of 1.2
to 1.6 in.2/foot of roadway width.
C. Positive Moment Design:
1. Use a four-bar repeating pattern (5 in. spacing)
2. The crack control Z" factor has been replaced with the below equation which uses the
actual depth of reinforcement cover and actual stress at service limit state.
See Negative Moment above for crack control parameters
D. Design of Transverse Steel:
1. Distribution Reinforcement, per Article 5.14.4:
The amount shall be a percentage of the main reinforcement steel required for (maximum)
positive moment, as given by:
Percentage = 100/ L < 50 percent (L in feet)
Do not design distribution reinforcement for a percentage of steel required for serviceability
requirements (i.e., crack control or fatigue) use the Strength I Limit State.
The area of steel required by maximum positive moment in Span No. 1 and the percentage
requirement for distribution steel based upon Span No. 1 length, L, will control the design.
Use load factor design in computing area of steel required for maximum positive moment.
Bridge Section
5 - 37
Design Manual
Bridge Section
5 - 38
Design Manual
Bridge Section
5 - 39
Design Manual
Bridge Section
5 - 40
Design Manual
Bridge Section
5 - 41
Design Manual
Bridge Section
5 - 42
Design Manual
Bridge Section
5 - 43
Design Manual
Bridge Section
5 - 44
Design Manual
Bridge Section
5 - 45
Design Manual
5 - 46
Bridge Section
Design Manual
Bridge Section
5 - 47
Design Manual
Bridge Section
5 - 48
Design Manual
Bridge Section
5 - 49
Design Manual
Bridge Section
5 - 50
Design Manual
Bridge Section
5 - 51
Design Manual
Bridge Section
5 - 52
Design Manual
Bridge Section
5 - 53
Design Manual
(32 ft.)
(36 ft.)
(40 ft.)
40 ft. OS
(44 ft.)
Design Loads:
Dead Loads:
Concrete Dead Load = 145 pcf
Traffic Barrier Load = 275 plf per rail
Future Wearing Surface = 25 psf
Live Loads:
Live load design is accompanied by a corresponding allowable concrete tensile stress limitation.
"No" tension in concrete for HS-20 Loads.
3 * f'c^0.5 maximum tension for HS-20 + Kansas Overload Provisions.
3 * f'c^0.5 maximum tension for HL-93 Loads (LRFD).
The superstructure is designed to satisfy the older AASHTO LFD (Load Factor Design) and the
current AASHTO LRFD (Load Resistance Factor Design) design specifications.
Load Rating:
The goal of design load rating for the given span ranges, governed by the standard HS-20 Truck
among all seven (7) Kansas load rating trucks, is 1.10.
The design of larger span groups C and D spans results in a minimum 1.10 rating for the HS-20
truck.
The design of smaller span groups A and B spans results in a minimum 1.10 rating for the HS20 Truck for maximum positive and negative moments, and a minimum 1.05 rating for negative
moment near mid-span of the exterior spans.
Skews:
An example of a 30 degrees skewed structure is available for download as reference material.
Below is a partial list of considerations for skewed post-tensioned haunched slab bridges.
Longitudinal post-tensioning details are expected to be substantially unchanged.
Transverse post-tensioning details will require modifications to accommodate skew and potential
conflict with rail post reinforcement.
Anchor end recess will also require special details to accommodate the skew.
Bridge Section
5 - 54
Design Manual
Multi-span Applications:
The current standards for post-tensioned concrete haunched slabs are limited to three (3) continuous span arrangement. Unlike the standards for the conventional reinforced concrete haunched
slabs, post-tensioned concrete slab design cannot be extended to multi-span application in a
straightforward manner. The additional length of tendons results in increased loss of prestress,
which may require additional prestress. KDOT may, in the future, develop standards for multispan applications. The maximum total length of post-tensioned concrete slab bridges, without
introducing a strand splice or interior span joints, is expected to be about 600ft.
Availability:
The standards are available in three components:
1. The user's Manual: Appendix C Post- Tensioned Haunched Slab Bridge Users Manualt
2. Plan standards Microstation ".dgn" drawing file format
3. Standard Specifications for State Road and Bridge Construction Section 716 of the Standard Specifications, (Construction specifications for post-tensioned concrete haunched slab
bridges).
Bridge Section
5 - 55
Design Manual
Bridge Section
5 - 56
Design Manual
Bridge Section
5 - 57
Design Manual
Bridge Section
5 - 58
Design Manual
Bridge Section
5 - 59
Design Manual
Bridge Section
5 - 60
Design Manual
Bridge Section
5 - 61
Design Manual
References
Darwin D., (1983). Effects of Traffic Induced Vibrations on Bridge Deck Repairs, p. 9.
Mander, J.B., Priestley, M.J.N., and Park, R. (1998). Theoretical Stress-Strain Model for
Confined Concrete Journal of Structural Engineering, ASCE, V.114, No. 8, p. 1804-1849,
August 1988.
Mander, J.B., Priestley, M.J.N., and Park, R. (1998).Observed Stress-Strain behavior of
Confined Concrete Journal of Structural Engineering, ASCE, V.114, No. 8, p. 1804-1825,
August 1988.
Rasheed H,.(2009). Interactive Software for Design, Actual Ultimate Capacity and Health
Monitoring of Confined Circular Columns.
Bridge Section
5 - 62
Design Manual
strength design, knowing the maximum strain value of the concrete c = 0.003 and the linear distribution.
Tension equal to Compression A s f y = 0.85f c ab and solving for the depth of the assumed
Asf y
stress block yields a = ----------------- from Hookes Law determine the yield strain
0.85f c b
60 y = -----y = -------------E
29000
s
a- and using similar triangles ---------- = 0.003
------------- deter The depth to the neutral axis is x = ---dx
x
1
mine the strain in the steel
0.003
s = ------------- ( d x ) if the strain is greater than yield then use
x
yield s y
Check the reinforcement ratio, the balanced point occurs when the steel yield and the concrete
0.85 1 f c
87
crushes at the same time b = -------------------- ---------------fy
87 + f y
min = 200
--------- max = 0.75 b
fy
Bridge Section
5 - 63
Design Manual
The reinforcement ratio ia required to be between the minimum (under reinforced) and maximum
(over reinforced)
A
= -----s max < < max
bd
Moment Capacity Equations
Af
f cb
f c
0.9
s y
Mn = ------- A s f y d 0.59 --------
12
0.9
2
Mn = ------- f y bd 1 0.59 ----y-
12
0.9
Mn = ------- A s f y d a---
12
Double Reinforced Beam
------------
1 = 0.85 0.05 f c 4000
1000
To analyze a doubly reinforced member, the determination of the stress in the compression reinforcement is required. If the following is true
f c d 87
s A s
A
------------------ 0.85 1 ------------------------ bd
f y d 87 + f y
Then the moment capacity can be solved for directly
0.9
Mn = ------- ( A s A s )f y d a--- + A s f y ( d d )
12
2
That is, the compression steel and the tension steel has yielded
f s = f y and s' y
Bridge Section
5 - 64
Design Manual
If it has not reached yield then find the stress in the compression steel:
Need to find
f s = E s'
s'
( x d -)
------------ = 0.003
------------- = s' = 0.003
------------------------------x d
x
x
aDetermine the location of the neutral axis
x = ---1
Using similar triangles
a- d
---
1
Determine the strain in both tension and compression steel s' = 0.003 -------------------a---1
s
---------- = 0.003
------------dx
x
Cs + Cc = T = fy As
a
Moment Capacity is M n = ------- C s ( d d ) + C c d --- and check ratio
12
2
f sb
A
- compare to min = 200
max = 0.75 b + ------------- and = -----sfy
bd
fy
A
= -----sbd
Bridge Section
5 - 65
Design Manual
DEVELOPMENT LENGTH
TOP BARS
BAR
SIZE
0.8
EPOXY
1.20
0.8
13.
17.
21.
26.
32.
42.
53.
67.
82.
114.
147.
12.
14.
17.
21.
26.
34.
42.
54.
66.
91.
118.
16.
21.
26.
31.
38.
50.
63.
80.
99.
137.
177.
13.
17.
21.
25.
31.
40.
51.
64.
79.
109.
142.
3
4
5
6
7
8
9
10
11
14
18
LD
12.
12.
15.
18.
23.
30.
38.
48.
59.
81.
105.
12.
12.
12.
15.
18.
24.
30.
39.
47.
65.
84.
12.
15.
18.
22.
27.
36.
45.
58.
71.
98.
126.
>
>
>
>
>
>
>
>
>
>
>
0.8
12.
12.
15.
18.
22.
29.
36.
46.
57.
78.
101.
>
>
>
>
>
>
>
>
>
>
>
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
5.1
6.8
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
11.9
15.8
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
5.1
6.8
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
11.9
15.8
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
<
<
16.
21.
26.
31.
39.
51.
64.
81.
100.
138.
179.
13.
17.
21.
25.
31.
41.
51.
65.
80.
111.
143.
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
<
<
14.
18.
23.
27.
34.
45.
57.
72.
88.
122.
158.
12.
15.
18.
22.
27.
36.
45.
58.
71.
98.
126.
COMPRESSION BARS
BAR SIZE
LD
3
4
5
6
7
8
9
10
11
14
18
8.
10.
12.
15.
17.
19.
22.
24.
27.
32.
43.
Bridge Section
5 - 66
Design Manual
CLASS A SPLICES
BAR
SIZE
3
4
5
6
7
8
9
10
11
BAR
SIZE
3
4
5
6
7
8
9
10
11
TOP BARS
LD
13.
17.
21.
26.
32.
42.
53.
67.
82.
0.8
12.
14.
17.
21.
26.
34.
42.
54.
66.
EPOXY
1.20
16.
21.
26.
31.
38.
50.
63.
80.
99.
0.8
13.
17.
21.
25.
31.
40.
51.
64.
79.
>
>
>
>
>
>
>
>
>
12.
12.
12.
15.
18.
24.
30.
39.
47.
12.
15.
18.
22.
27.
36.
45.
58.
71.
12.
12.
15.
18.
22.
29.
36.
46.
57.
>
>
>
>
>
>
>
>
>
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
16.
21.
26.
31.
39.
51.
64.
81.
100.
13.
17.
21.
25.
31.
41.
51.
65.
80.
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
14.
18.
23.
27.
34.
45.
57.
72.
88.
12.
15.
18.
22.
27.
36.
45.
58.
71.
COMPRESSION BARS
BAR
SIZE
STD
TIED
3
4
5
6
7
8
9
10
11
12.
15.
19.
23.
27.
30.
34.
39.
43.
12.
13.
16.
19.
22.
25.
29.
32.
36.
Bridge Section
5 - 67
Design Manual
CLASS B SPLICES
BAR
SIZE
3
4
5
6
7
8
9
10
11
BAR
SIZE
3
4
5
6
7
8
9
10
11
TOP BARS
LD
17.
22.
28.
33.
41.
54.
69.
87.
107.
0.8
14.
18.
22.
27.
33.
44.
55.
70.
86.
EPOXY
1.20
0.8
20.
27.
33.
40.
50.
65.
82.
104.
128.
16.
21.
27.
32.
40.
52.
66.
84.
103.
>
>
>
>
>
>
>
>
>
12.
13.
16.
19.
24.
31.
39.
50.
61.
14.
19.
24.
29.
36.
47.
59.
75.
92.
12.
15.
19.
23.
29.
37.
47.
60.
73.
>
>
>
>
>
>
>
>
>
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
20.
27.
34.
40.
50.
66.
83.
106.
130.
16.
22.
27.
32.
40.
53.
67.
85.
104.
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
18.
24.
30.
36.
44.
58.
74.
93.
115.
14.
19.
24.
29.
36.
47.
59.
75.
92.
COMPRESSION BARS
BAR
SIZE
STD
TIED
3
4
5
6
7
8
9
10
11
12.
15.
19.
23.
27.
30.
34.
39.
43.
12.
13.
16.
19.
22.
25.
29.
32.
36.
Bridge Section
5 - 68
Design Manual
CLASS C SPLICES
BAR
SIZE
3
4
5
6
7
8
9
10
11
BAR
SIZE
3
4
5
6
7
8
9
10
11
TOP BARS
LD
0.8
EPOXY
1.20
0.8
22.
29.
36.
43.
54.
71.
90.
114.
140.
18.
23.
29.
35.
43.
57.
72.
91.
112.
26.
35.
43.
52.
65.
85.
108.
136.
168.
21.
28.
35.
42.
52.
68.
86.
109.
134.
>
>
>
>
>
>
>
>
>
13.
17.
21.
25.
31.
41.
51.
65.
80.
19.
25.
31.
37.
46.
61.
77.
98.
120.
15.
20.
25.
30.
37.
49.
62.
78.
96.
>
>
>
>
>
>
>
>
>
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
CL.
3 Db
SPA.
6 Db
1.1
1.5
1.9
2.2
2.6
3.0
3.4
3.8
4.2
2.6
3.5
4.4
5.2
6.1
7.0
7.9
8.9
9.9
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
26.
35.
44.
52.
65.
86.
109.
138.
170.
21.
28.
35.
42.
52.
69.
87.
111.
136.
EPOXY
1.5
0.8
<
<
<
<
<
<
<
<
<
23.
31.
39.
46.
58.
76.
96.
122.
150.
19.
25.
31.
37.
46.
61.
77.
98.
120.
COMPRESSION BARS
BAR
SIZE
STD
TIED
3
4
5
6
7
8
9
10
11
12.
15.
19.
23.
27.
30.
34.
39.
43.
12.
13.
16.
19.
22.
25.
29.
32.
36.
Bridge Section
5 - 69
Design Manual
USERS MANUAL
February, 2013
K
Volume III US (LRFD)
Version 1/14
t fT
t ti
Bridge Section
5 - 70
Design Manual
Table of Contents
I. INTRODUCTION............................................................................................................... 3
II. DESIGN ........................................................................................................................... 6
III. PLAN PREPARATION ...................................................................................................12
IV. SPECIFICATIONS .........................................................................................................17
V. COST ESTIMATE ...........................................................................................................18
VI. CONSTRUCTION INSPECTION REQUIREMENTS ......................................................19
VII. LESSONS LEARNED ...................................................................................................25
APPENDIX..........................................................................................................................28
Bridge Section
5 - 71
Design Manual
I. INTRODUCTION
I.1 Description
Post-tensioned concrete haunched slab (XCSH) design and details included in this manual
are intended for the use of bridge details that can be obtained from KDOT Bridge Section for
the preparation of bridge plans. The format is similar to the existing standards available for
reinforced concrete haunched slab bridges (RCSH). This manual consists of eight (8) major
sections: Introduction, Design, Plan Preparation, Specifications, Cost Estimate, Construction
Inspection Requirements, Lessons Learned, and Appendix.
I.2 Scope
The project scope consists of design and plan preparation for a 3-span, post-tensioned
concrete haunched slab bridge, referred to by the KDOT bridge superstructure log code as
XCSH in this manual. There are four (4) span arrangements and five (5) roadways plus one
2 offset crown roadway for each span arrangement included in the manual. No skews are
included in the preparation of the standard plans at the present time. However, a sample
set of a skewed bridge is made available.
The four span arrangements are:
A.
B.
C.
D.
50 ft 65 ft 50 ft
55 ft 72 ft 55 ft
62 ft 82 ft 62 ft
71 ft 92 ft 71 ft
28 ft
32 ft
36 ft
40 ft (plus a 40 ft roadway width with 2 offset crown)
44 ft
Bridge Section
5 - 72
Design Manual
2. The need for improved safety under overpass structures by minimizing the number of
piers and maximizing horizontal clearance (in comparison to RCSH).
3. The need to minimize the number of piers in the stream channel in relation to scour, drift
accumulation, minimizing obstruction to flow, etc. (in comparison to RCSH).
4. The need for a high-performance type bridge superstructure. The bi-directional, precompression in the slab reduces the cracking of the concrete slab, rendering the slab
more impervious to moisture penetration and thus, chlorides. The entire superstructure
is in a state of pre-compression.
5. The need for competitive cost alternatives to shorter span prestressed girder bridges.
6. The need for a low-maintenance type bridge with least life-cycle cost potential.
Limitations
Constructability: XCSH application should be considered carefully where very deep
channels are encountered which may preclude the use of a cast-in-place type structure
requiring formwork. However, many contractors have innovative ways of forming the
concrete superstructure using steel beams or trusses, so the designer should check the
availability of such construction technology before ruling out the post-tension (P/T) option for
bridges over deep channels. The same concern should be checked for overpasses over
railroads or existing highways to allow traffic through construction.
Skews: Even though skewed XCSH bridges are entirely possible and have been built in the
past up to 30 degrees, the current standards do not include standard XCSH details for
skews. However, an example set of plans is available for reference. See Section II.7 for
additional information.
Horizontally Curved Bridges: The current standards do not include horizontally curved XCSH
applications. See section II.8 for additional details.
Multi-Span Applications: The current standards are limited to a three (3) span configuration
of XCSH. The concepts and details needed to add additional interior spans require further
investigation regarding prestress losses, movement at the abutments, etc. More than threespan XCSH applications are beyond the scope of these standards at this time.
Minimizing the number of piers for a given bridge length, compared to RCSH
Substantial savings in mild steel reinforcement placement in the slab
Savings in cost due to eliminating the need to raise the approach grade profile,
compared to girder type superstructures
KDOT B id
20
Bridge Section
5 - 73
Design Manual
This users manual is not intended to endorse the choice of XCSH as the most
effective bridge solution for a given project location. The designer of the project is
solely responsible for the choice of the XCSH application as well as all structural
design and calculations required by the codes of professional practice. The standard
design and details presented in this manual and the available developed standard
sheets require checking by the designer for the required and applicable loading
conditions specific to each project location.
Bridge Section
5 - 74
Design Manual
II. DESIGN
II.1 Designers Responsibility
The integral pile bent type abutment and the superstructure slab have been pre-designed in
the preparation of the plan standards, available as a part of this project. A wall type pier has
been included in the plans as an example. The designer is solely responsible for the
complete design of all foundation elements (both piers and abutments), the piers and any
non-standard abutments in accordance with the requirements of this manual and applicable
AASHTO and other design specifications. The designer is also responsible to check the
standard abutment and superstructure design for all loading and functional conditions
specific to each project site.
150 lb / ft3
376 plf per rail (2-8 Kansas Corral rail with curb)
25 psf
2. Live Loads
The XCSH Bridge standards have been designed to meet KDOT requirements for three live
loads:
HL-93
HS-20
HET
The designer is responsible for checking the design of the superstructure and the standard
abutment for the specific loads applicable to each project location.
3. Design Methodologies
The superstructure and substructure was designed using the AASHTO 2004 edition of the
LRFD Specifications, and then rated using the AASHTO 17th Edition of the LFD
Specifications. The Designer is responsible to use Engineering judgment to verify no code
changes since 2004 will affect the superstructure design. Allowable concrete stresses used
for the service conditions are:
Tension in concrete (psi):
3
93
& ; 6
93
Bridge Section
5 - 75
Design Manual
Bridge Section
5 - 76
Design Manual
Bridge Section
5 - 77
Design Manual
XCSH pre-drilled pile holes with backfill material is to move the equivalent point of fixity of
the pile down, so that the moments generated at the point of fixity in the pile from the
displacement happening above at the abutment, are reduced. Example A.1, provided in the
Appendix at the back of this report, provides a detailed analysis of such a check. For the
example (a D span configuration with a 44 roadway), in effect, a 16 depth to fixity is
needed below the abutment beam. If the project site geology will not allow the pile that
depth of fixity, then pre-drilled pile holes should be employed as appropriate.
Drilled shafts can be used at the abutments; however they must be designed to allow
shortening of the slab to occur without significant restraint. In cases where the subsurface
rock/shale is very near the bottom of the abutment beam, integral abutment design on pile
foundations, even with pre-drilled holes, is not a practical solution. The superstructure slab,
in such instances, must be independently supported on the abutment beam using
expansion bearing devices and a backwall at the abutment (Fig. A.1 - Appendix).
Alternatively, a semi-integral abutment could be employed. Either design is beyond the
scope of this manual and should be performed entirely by the designer.
2. Pier Design
The design of the pier is similar to the substructure design of the abutment. However, the
requirement of shortening of the superstructure at the pier is much lower than that at the
abutment (about 60 percent less), due to the piers close proximity to the point of no
movement.
The connection between the superstructure slab and the top of the pier must be designed to
not transfer any moment between the superstructure and the pier in the longitudinal
direction, providing essentially a pinned connection, in order to allow the free movement of
the superstructure. The standards provide a plan detail for a sample wall type pier showing
a typical connection detail between the slab and the pier beam. This consists of the single
row of piling stopping short of the top of wall, and an X bar reinforcing connection from the
top of wall to bottom of superstructure. Such a connection succeeds in providing a pinned
connection between the superstructure and substructure.
However, when a single row of columns are used, the primary column reinforcement can be
extended into the slab for the minimum embedment length required as per the code. Stop
the web walls between the columns, 1 ft below the bottom of the slab. For moderate to
large column spacing, many XCSH bridges have been constructed with a separate pier cap,
sitting immediately below the superstructure. This separate pier cap is conservatively
designed to accommodate all the flexural and shear loadings (neglecting the superstructure
above). More importantly, the connection between the separate pier cap and the
superstructure again consists of X bar reinforcing, to achieve a pinned connection.
Pre-drilled pile holes may be required when hard subsurface soil conditions are encountered
very close to the bottom of the pier wall or the footing (within 7 ft) as per the discussion
above in the case of the abutment design.
Drilled shafts can be used at the piers; however, they must be designed to take into
consideration the forces due to deformations of the slab.
Bridge Section
5 - 78
Design Manual
In summary, the procedure for the design of the substructure in the XCSH is not greatly
different than that for RCSH, except for considering the magnitude of deformations that
occur in the slab as a result of post-tensioning. This is usually more of a concern at the
abutment than at the pier.
Bridge Section
5 - 79
Design Manual
Extreme caution is
Bridge Section
5 - 80
Design Manual
Sheet Title
Abutment Details I
Abutment Details II
Slab Details I
Slab Details II
Post-tensioning Details I
Post-tensioning Details II
Grouting Sequence & Post-tensioning Notes
Post-tensioning Data & Construction Sequence
Spacer Frame Details
II
III
Pier Details
Bridge Section
5 - 81
Design Manual
All sheets from Groups I, II & III are required in the plans for XCSH application without any
exception. In addition, the following sheets are required in the plans for any XCSH bridge
design:
Slab Elevations
Contour Map
Construction Layout
Engineering Geology
Abutment Strip Drain
Corral Rail Details
Bridge Excavation
Supports & Spacers for Reinforcing Steel
Standard Pile Details
The rail detail sheet, which is an existing KDOT base sheet, will require a special detail
inclusion as shown on the Post-tensioning Details II sheet. The designer should reference
both the Post-tensioning Details sheets and the Post-tensioning Data & Construction
Sequence sheet for proper post spacing and reinforcing.
The designer must thoroughly familiarize oneself regarding the details on the standards in
Group I so all other sheets will have information and details consistent with and as required
by the sheets in Group I.
III.3 Sheet Indexing System
The sheets are indexed by span arrangement and roadway width. The following system is
used to designate the span arrangement:
Spans
Designation
50 ft 65 ft 50 ft
55 ft 72 ft 55 ft
62 ft 82 ft 62 ft
71 ft 92 ft 71 ft
A
B
C
D
The sheets are indexed with span designation followed by the roadway width and an
abbreviated title of the sheet. Thus,
D44SS2.dgn refers to Slab Details II for 44 ft roadway in a 71 ft 92 ft 71 ft span (D)
arrangement. A list of abbreviated titles for the standards is shown below:
Sheet Title
Sheet Designation
KDOT B id
*GNOT.dgn
*ABT1.dgn
*ABT2.dgn
*PIER.dgn
*SS1.dgn
13
20
Bridge Section
5 - 82
Design Manual
Slab Details II
Post-tensioning Details I
Post-tensioning Details II
Grouting Sequence & Post-tensioning Notes
Post-tensioning Data & Const. Sequence
Bill of Reinf. Steel & Bending Diagram
Spacer Frame Details
*SS2.dgn
*PTD1.dgn
*PTD2.dgn
*PTN1.dgn
*PTN2.dgn
*BAR1.dgn
*BAR2.dgn
Note: KDOT may have revised the sheet designations to match their latest CADD standards
and naming conventions. Use KDOT latest naming conventions for sheet labeling.
III.4 Step-by-step Plan Preparation Procedure
Step 1: Determination of Sheet Designation
Determine the span arrangement (A through D) and roadway width (28 ft through 44 ft). For
example, the designation for 62 ft 82 ft 62 ft spans with 40 ft roadway would be C40.
Step 2: Obtain Standards for Groups I, II and III.
Obtain all CADD plan standards for the designation determined in step 1 (ex. C40) for
Groups I, II and III as outlined in Section III.3.
Step 3: Abutment Design and Details (Group I)
Based on subsurface soil conditions as noted in Sections II.4, check if the standard pile bent
type abutment design and plan standards can be used. If not, perform the abutment design
as per the procedure outlined in Section II.4 for the loads specified on the standard
abutment sheets as well as AASHTO specifications. Use the example in the Appendix as a
guide, if necessary. If non-standard abutment design is performed, use the format of the
standard abutment plans to prepare the plans for the non-standard abutment design. In
most circumstances, the standard abutment design should be satisfactory. However, note
the standard abutment design and details are for Steel H Piles only. The designer should
use appropriate pile type, size and number as needed by the site geology and check the
design as required.
x
Check to see if pre-drilled pile holes are necessary as per Section II.4.
Bridge Section
5 - 83
Design Manual
Single row of columns on drilled shafts or spread footings (founded either on rock/shale or
pile group) need to be designed following the procedures outlined in Section II.4.
Use the format of the sample plan detail sheet to prepare the actual pier detail sheet.
x
Check to see if pre-drilled pile holes are necessary as per Section II.4.
Make sure the connection between the superstructure slab and the pier beam is a
pinned type connection as shown on the sample pier detail sheet for a wall type pier.
KDOT B id
15
20
Bridge Section
5 - 84
Design Manual
Bridge Section
5 - 85
Design Manual
IV. SPECIFICATIONS
IV.1 General
The Contract Documents for the post-tensioning work shall be as stated on the plans and
any Project Specifications. There should be consistency between the information shown on
the plans and any Project Specifications that may be used by the designer.
See KDOT Specifications, Post-tensioning (Haunched Slab Bridges), Section 716, and
subsequent Special Provisions. Note that the Sika Grout 300PT will not be allowed due to
recent discovery of chloride presence.
Bridge Section
5 - 86
Design Manual
V. COST ESTIMATE
V.1 Unit Price
The Contract Unit Price for all post-tensioning work is set as Lbs of strand weight, including
longitudinal and transverse strands. Limits and method for calculating strand weights, as
well as a breakdown of the transverse and longitudinal weights, is shown for information
only on the General Notes sheet. The Unit Prices for other work in the bridge project shall
be as per the Specifications, and is similar to what is done for RCSH.
V.2 Estimating Unit Prices
The plan shows approximate quantity of the TOTAL prestressing strand weight. Based on
XCSH bridges built in Kansas since 1989, the following information is presented for certain
items that are affected by post-tensioning:
Item
Unit
Cu. Yds.
Lbs.
* See Bridge Manual for aggregate type. Note: PB aggregate is intended for prestressed
girder bridges and not for XCSH.
Unit prices for bridge items should be estimated using similar assumptions as for any other
similar type of bridge and location.
Bridge Section
5 - 87
Design Manual
Pre-drilled pile holes may be required more often at the abutments for XCSH than for
conventional RCSH.
The top of wall type pier is not monolithic with the superstructure slab in a XCSH. The
reinforcement, projecting above the top of the pier beam, is crossed into the
superstructure slab to provide a pinned connection. Additionally, a Type B expansion
joint material is placed on top of the pier beam along the edges to allow rotation of the
superstructure slab.
The placement of P/T tendons and the varying slab depth will require significant control,
precision, and care. The longitudinal duct profile and the slab depth are critical. The
ducts must be sealed properly to prevent the entrance of concrete.
The conflict between P/T tendons and mild steel reinforcement in the slab, even though
checked carefully in the plan preparation, may require some trouble shooting in the
field. Post-tensioning ducts always have precedence over mild steel reinforcement, and
longitudinal P/T has precedence over transverse P/T. As per the plans, adjust the
location of the transverse P/T up or down to avoid conflicts with the longitudinal P/T, but
this adjustment should be minimized to make sure eccentricity from the transverse P/T
does not introduce tension into the slab.
The slab concrete requires higher concrete strength than conventional RCSH. Additives
such as a superplasticizer may be required to increase workability. Note, it is desirable
to minimize shrinkage, and superplasticizers sometimes increase the rate of shrinkage.
Extra care is required to make sure the ducts are not dislocated during concrete
placement. Concrete consolidation is critical, especially in congested areas, such as at
the abutments near the end anchorage.
The timeliness and the manner required for concrete testing are critical due to the
requirements of stressing operations.
Extreme caution and complete compliance with safety procedures are required during
stressing operations.
Bridge Section
5 - 88
Design Manual
The grouting process is a unique component of post-tensioning and has received the
most attention in recent times due to issues related to grouting of other P/T structure
types. The grout material used is critical and must meet KDOT Specifications. As per
the Contract documents, an ASBI Certified Grouting Technician is required to supervise
all grouting operations on the bridge. It is important for the Contractor and Inspector to
realize that the intent of the grouting operation is to fully encapsulate the P/T tendons,
both for the protection of the tendons from chloride attack, and for the continuous
bonding of the tendons to the slab. The grouting process should result in zero non-grout
voids (i.e., no pockets of air or water should remain in the ducts after the grouting
operation).
Slab forms must be left in place as stated on the plans, at least until after all stressing
and grouting operations are complete.
Protecting all exposed end anchorages and filling the anchor recesses, after grouting,
are important finish items.
In general, the construction of XCSH, though not more complex than any other type of
bridge, does require more care than most conventional concrete bridges in terms of
sequence, precision and safety.
The information presented in this section is intended to assist the Owners representative to
conduct a proper inspection of XCSH construction. It is not intended to release the
Contractor or the Inspectors from the responsibilities of carrying out the project as per Plans
and Specifications, nor does this information represent all procedures required in the
construction of the project.
Bridge Section
5 - 89
Design Manual
B. Check shop drawing for Spacer Frames; the plan dimensions are based on the design
profile and the assumed duct size. If duct sizes are different from plan dimensions and if
approved by the Engineer, have the Contractor revise and re-submit Spacer Frame
dimensions to match the approved duct size and profile.
C. Review the slab concrete mix and placement procedure submitted by the Contractor.
D. Review the slab curing procedure submitted by the Contractor.
E. Review all concrete testing procedures submitted by the Contractor.
F. Review grout mix and placement procedure submitted by the Contractor.
2. Piles
A. Check the requirements for pre-drilled pile holes.
B. Check the orientation of the piles.
3. Piers
A. For wall type pier, check the rebar connecting the pier beam to the slab; it must cross at
the top of pier beam and the exposed portion must be protected until the slab concrete is
placed.
B. For wall type pier, Type B expansion joint material must be placed on the top of the pier
beam as shown on the plans.
4. Slab Form
A. Check the slab depths at spacer frame locations and at the faces of abutments and piers
along the center line and the edges of the roadway. Check the tolerance for slab depth
as per the plans.
B. Check the form soffit for camber, especially for negative camber as per the plans.
Adjust plan camber if long span beams are used to support the forms.
C. Check the dimensions of the recesses in the forms for the P/T anchors.
D. Record elevations on the Slab Elevations sheet.
5. P/T Ducts
A. Check longitudinal duct size, spacing, duct profiles at spacer frame locations and at the
center line of abutments and piers. Check the tolerance for duct placement in the
horizontal and vertical directions. Make sure that the longitudinal ducts are laid out in a
straight line and follow a smooth parabolic profile. Snaking of the profile should not be
allowed.
KDOT B id
21
20
Bridge Section
5 - 90
Design Manual
B. Check transverse duct size, spacing and profile at the edges of the slab and at the
center line of the roadway. The transverse duct spacing is critical to avoid interference
with rail posts.
C. Check the splices and connections in the ducts to make certain they are sealed to
prevent the entrance of concrete during placement.
D. Check to make sure that the minimum clearances to concrete surfaces from the ducts
are provided near mid-spans and piers as shown on the plans.
E. Check to make sure that the P/T Ducts and mild steel reinforcement are tied securely to
prevent displacement during concrete placement. It is critical that the longitudinal ducts
do not shift during concrete placement.
F. Check to make sure that all parts of the ducts are corrosion protected as per the plans.
6. P/T End Anchorage
A. Check the type of anchor device installed and special reinforcing such as spirals and
grids in the local zone of the end zone. Make sure that spiral and local zone
reinforcement is securely tied in place prior to concrete placement.
B. Check to make sure parts of anchor devices are corrosion protected, as per the plans.
7. General End Zone Reinforcing
A. Check the proper installation of the general end-zone reinforcing in the abutment
consisting of closely spaced stirrups, O bars and L bars as per the plans.
8. Inspection by P/T Manufacturer
A. Prior to the placement of concrete in the slab, check to verify for the inspection and the
approval of all P/T hardware and end-zone reinforcing installation by a qualified
representative of the P/T Manufacturer. Such inspection must be done in the company
of the KDOT inspector and the Contractor.
9. Slab Concrete Placement
A. Verify appropriate strength (5 ksi) concrete (with superplasticizer, as applicable) is
delivered for the slab, capable of attaining specified release strengths.
B. Verify the slab concrete is thoroughly vibrated around the ducts.
C. Verify the test samples are taken and kept on site to accurately represent the strength of
concrete at site conditions.
D. Alert the Contractor to place concrete in a manner to avoid direct impact to the ducts or
displacement of the ducts during all concrete placement, vibration, and screeding
operations.
KDOT B id
22
20
Bridge Section
5 - 91
Design Manual
Bridge Section
5 - 92
Design Manual
D. Check the grout material and type that will be used for the recess pockets. It is critical to
use an approved material as specified on the plans.
14. Form Work Removal
A. Removal of slab forms shall be in accordance with the plans. In any event, check to
make sure the slab forms are not removed until after all stressing and grouting
operations are complete.
15. Finishing
A. Check to make sure exposed anchor devices and recess pockets are cleaned of all
debris, grout and other material.
B. Check the corrosion protection applied to all exposed anchor devices after grouting is
complete.
C. Check to ensure that the exposed surfaces of the recess pockets are appropriately
prepared for filling with material as per the plans and specifications.
D. Check to ensure all recess pockets (transverse and longitudinal) are filled with an
approved material per the post-tensioning specifications, and the appropriate surface
treatment waterproofing membrane is applied on required surfaces (see plans and
specifications). Recess pockets should be filled thoroughly and finished smooth and
flush with the adjacent concrete surface.
E. Check to verify all stressing record documents are properly completed and signed by the
P/T Manufacturers Engineer.
Bridge Section
5 - 93
Design Manual
The pockets on the edge of the slab for transverse post-tensioning are exposed and visible
elements. The primary importance for these pockets is that they must be filled with a
material that is capable of providing protection for the end anchorage of the post-tensioning
assembly. Such a material serves as a line of defense in preventing chloride access to the
assembly and reducing corrosion potential. Of secondary importance, these pockets should
blend in with the adjacent concrete for aesthetic purposes. Although perhaps not an issue in
rural environments, and at many stream crossings, these pockets should not be unsightly in
urban environments. Currently KDOTs Specifications for Recess Pocket Filling read: Fill all
longitudinal and transverse end anchorage recess pockets as shown in the Contract
Documents. Apply an approved epoxy resin bonding agent according to the manufacturer
prior to placing an approved non-shrink, non-metallic grout. Apply grout according to the
grout manufacturers instructions. Finish the outside exposed surfaces of the recess pockets
smooth and flush with the surrounding concrete surface. Select grout to match the color of
the surrounding concrete slab.
KDOT B id
25
20
Bridge Section
5 - 94
Design Manual
It is believed that the current specifications succeed in achieving their primary objective:
protecting the transverse anchorage assemblies. Potential ways to improve the secondary,
aesthetic issue include:
1. The use of an approved epoxy system that will not break or deteriorate when in contact
with salt and water.
2. The use of an approved material such as Magnesium Ammonium Phosphate Concrete.
This material is widely used in Florida.
3. Applying a waterproofing membrane to serve as another layer of protection to the sides
of the slab.
4. Avoid drainage through the corral opening by applying a continuous curb with scuppers
to prevent drainage over the side. Drainage over the side is probably the primary attack
mechanism on the transverse anchorage. If needed, scuppers would have to be placed
carefully to avoid post-tensioning hardware.
VII.2 Longitudinal Shrinkage Cracks
Many post-tensioned haunched slabs bridges have shown hairline longitudinal cracks that
start over the pier and propagate longitudinally along the bridge. These hairline cracks
develop at the top of the slab only. It is believed that these cracks occur due to shrinkage
(specifically, drying shrinkage) of the concrete in the transverse direction.
Conventionally reinforced concrete slab bridges have shrinkage cracks in transverse and
longitudinal directions. It is believed that in the XCSH bridges the magnitude of the
longitudinal post-tensioning forces eliminates the shrinkage cracks in the transverse
direction. But not enough transverse post-tensioning is being applied to eliminate shrinkage
cracks in the longitudinal direction.
Bridge Section
5 - 95
Design Manual
Another suspected reason for these hairline longitudinal cracks is the lack of a mild steel
reinforcement mat over the longitudinal duct over the pier. It is believed that the hairline
crack starts over the pier before it grows through the slab. The longitudinal duct is located
very close to the top of the slab with the 3 minimum cover. This in turns prevents adding
mild steel over the duct near the pier.
Although the top slab shrinkage cracks in the longitudinal direction should be taken
seriously, it is not believed they are a critical danger to the structural integrity of the XCSH
Bridge. That being established, following are possible approaches to this problem:
1. Provide wire mesh reinforcement over the duct near the pier so that the longitudinal duct
is completely confined. Adding the wire mesh will not encroach much on the 3 minimum
cover. The use of #3 bars in the mesh should be adequate.
2. Increase amount of top mat transverse mild steel in order to minimize shrinkage cracks
in the longitudinal direction. Increasing the amount of mild steel may aid in reducing the
amount of shrinkage. Currently the standards call for #4 at 12 centers, except at the
piers, where #4 @ 6 centers is called for. #5 at 6 centers could be used everywhere,
also aiding as a work platform prior to concrete pour. It should be noted that ACI SP227-1 may indicate a stiffer mild steel top mat compared to the bottom mat may actually
be counter-effective.
3. Increase amount of transverse post-tensioning. Increasing the transverse posttensioning would not reduce shrinkage, but could eliminate shrinkage cracks. Currently,
the compressive stress due to the transverse tendons is about 100 psi. Doubling up on
this stress value will be beneficial and will control any potential cracks that may develop.
4. Apply an overlay to seal the cracks after they develop. Because the shrinkage cracks do
not pose a critical threat to the structural performance of a XCSH bridges and because
shrinkage cracks are tolerated on a RCSH bridge where they are more extensive in
nature, a viable alternative is to live with the problem. Additionally, the cracks in the slab
could be sealed after they develop. This would involve waiting many years for full crack
development and then sealing them with KDOTs multi-layer polymer overlay, or
something similar.
Bridge Section
5 - 96
Design Manual
APPENDIX
Bridge Section
5 - 97
Design Manual
Example A.1
Check capacity of the steel H-piles in the abutment for a 71 ft 92 ft 71 ft Post-tensioned
Concrete Haunched Slab span bridge, 44 ft roadway subject to HL-93 Live Loading and 25
psf future wearing surface load. Pile orientation is such that the weak axis resists
longitudinal forces.
466
DW: FWS
27
PS: Secondary
40
-6
528
44<
6 12
<
> = 1,760,
2
2
2
2
Bridge Section
5 - 98
Design Manual
A
#CDEFG
HICDEF
J (ICDEF L )
(NSOPQ(RV#')(WN#')
NOP Q(R
+
S R(T"U
NXSW#' L
= 50 ,
3. Lateral Loads:
During the analysis, a relative stiffness comparison was conducted. It was found that the
longitudinal and lateral stiffness of the abutments versus piers equaled 1:9, therefore the
following ratio will be used to determine lateral load sharing between abutments and piers:
YZ7 / = /
YZ
1
=/
= 5% /
[! + [YZ
92+12
]^(_`_'de_U = 50
fTb_c = 5% (71 2 + 92) 5 0.012,
= 0.7 ,
Bridge Section
5 - 99
Design Manual
f'de_U = fTb_c
50
= 2.9 ,
12
100
= 1.2 ,
40
#R(T"U
[ (R(T" W )
23, (263,
) 21
=
7
1372 W
=S.XQ(R ('"_U(b_)
kP.jQ(R ($bgRd"UU(b_)
KDOT B id
31
20
Bridge Section
5 - 100
Design Manual
NW(_
N#'
= 0.97
12
> = 0.31
1
12
> = 0.38
1
Use factored load combinations to determine pile demand (Article 3.4.1-Load Factors
and Load Combinations).
Magnify moments as appropriate due to lateral
displacements.
Calculate pile capacities for axial, weak axis bending, and strong axis bending
(Articles 6.9.4.2, 6.12.2.2, and 6.10.8.2, respectively). Also see Article 10.7.3.13 for
fully embedded piles.
Nominal
Capacity
Resistance Factored
Factor
Resistance
Axial (k)
767
0.7
537
114
1.0
114
222
1.0
222
-i_Tb_c -i_'de_U
!i
!i
!i 8 -i_Tb_c
-i_'de_U
< 0.2, \
+
+
1.0,
+
+
1.0
!d
2!d -d_^"eQ -d_U'db_c
!d 9 -d_^"eQ -d_U'db_c
Bridge Section
5 - 101
Design Manual
abutment, magnified moments have simply been taken as the longitudinal displacement
multiplied by the factored axial force.
Pile Demand and
Interaction Table
Str I
Str I
(min) (max)
Str III
(min)
Pu (k)
-152
-181
-66
-96
-132
-161
2.50
2.33
2.34
2.16
2.51
2.33
-52
-47
-59
-55
-55
-50
Mu trans (k-ft)
-32
-35
-13
-17
-28
-31
-83
-82
-72
-72
-82
-81
Interaction Value
0.93
0.98
0.73
0.76
0.91
0.96
The axial capacity of the pile, without bending is also checked per AASHTO LRFD Article
6.15.2, for pile damage and other unknowns occurring due to driving.
!d_ge = $_`egec"` !_ = 0.50 767, = 383,
The maximum factored axial load on the pile is 181kips, therefore this is satisfied. Pile
drivability shall also be checked according to Article 10.7.8 - Drivability Analysis.
Summary
The procedure presented in this example is an approximate, simplified and practical
approach for most commonly encountered soil conditions consisting of well drained and
predominantly granular type soil. In the event complex soil conditions are encountered,
such as highly plastic clay, etc., a detailed geotechnical investigation and analysis of piles
for lateral loads by an experienced geotechnical professional might be warranted. The
choice of the approximate method or a detailed geotechnical analysis using more advanced
methods of analysis should be made by the professional engineer in charge of the design of
the bridge based on site conditions and choice of substructure design. The above example
is presented to illustrate the concept for checking substructure capacity when posttensioning of the superstructure is involved.
Bridge Section
5 - 102
Design Manual
Table A.1
Movement of the Slab at Abutments
XCSH Information
Span
Depth
(min)
(in)
Depth
(max)
(in)
Total
Length
(ft)
CR+SH
(in)
PS
(in)
TU
(in)
Total
(in)
17
29
165
0.66
0.18
0.27
1.11
18
31
182
0.71
0.19
0.29
1.19
20
35
206
0.91
0.26
0.33
1.51
22
38
234
0.97
0.31
0.38
1.66
Figure A.1
Bridge Section
5 - 103
5 - 104
-40
6
0
-50
0
0
0
0
0
-1
PS
CR+SH
TU
*HL-93
BR
WS Long
WS Trans
WL Long
WL Trans
*WS Overturn
-8
-11
-37
-66
-226
-168
70
Long
Mom
(k-ft)
19
47
Trans
Mom
(k-ft)
-27
-466
Axial
(k)
0.04
0.05
0.17
-0.04
0.38
1.29
0.96
-0.03
-0.40
'x
(inch)
-0.0005
0.0000
0.0045
0.0090
-0.0004
-0.0056
Phi
(slab)
(rads)
DW
DC
LRFD Loads \
Force, Disp.
0.0
0.0
0.0
0.0
0.0
1.75
1.75
1.0
1.0
1.0
0.0
0.9
Str I
(min)
0.0
0.0
0.0
0.0
0.0
1.75
1.75
1.0
1.0
1.0
1.5
1.25
Str I
(max)
1.4
0.0
0.0
1.4
1.4
0.0
0.0
1.0
1.0
1.0
0.0
0.9
Str III
(min)
1.4
0.0
0.0
1.4
1.4
0.0
0.0
1.0
1.0
1.0
1.5
1.25
Str III
(max)
0.0
1.0
1.0
0.4
0.4
1.35
1.35
1.0
1.0
1.0
0.0
0.9
Str V
(min)
0.0
1.0
1.0
0.4
0.4
1.35
1.35
1.0
1.0
1.0
1.5
1.25
Str V
(max)
Table of Results from Analysis and Load Combinations for Abutment Piles (Results are summation of all piles in abutment)
Bridge Section
Design Manual
0.60 f'ci
0.24 f c
0.60 f'c
Final Compression
Final Tension
Final Allowable Compression
with LL+1/2(Peff+DL)
0.0948 f c
0.40 f'c
5.9.4.1.1
5.9.4.1.2
5.9.4.2.1
5.9.4.2.2
5.9.4.2.1
0.45 f'c
5.9.4.2.1
5.9.4.2.1
Final DL Compression
5.9.4.1.2
Properties
The coefficient of thermal expansion is a function of the aggregate material used; aggregate types
ranging from 3.0 - 9.0 x 10 -6/oF, with calcium carbonate aggregates on the low end and silica
aggregates on the high end. KDOT will use: Normal Weight Concrete = 6.0 x 10 -6/oF
Concrete Strength and Strand Usage
Use 0.5 in. 270 ksi strands for K2 and K3 with f'ci = 4 ksi and f'c= 5 ksi
Use 0.5 or 0.6 in. 270 ksi strands for K4 with up to f'ci = 5 ksi and f'c= 6 ksi
Use 0.6 in. 270 ksi strand for K6 with f'ci = 5 ksi and f'c= 6 ksi
Do not exceed f'c= 6 ksi
Note: Adjust f'ci in 0.10 ksi increments per span as needed, limit f'ci to 0.80 - 0.85 f'c
Calculation of Losses
Include elastic shortening per Article 5.9.5.2.3
Bridge Section
5 - 105
Design Manual
Use the Approximate Method for time dependant losses, Article 5.9.5.3; this calculated
value can be used as a lump sum for software which does not have the Approximate
Method available.
Diaphragms
Use temporary intermediate diaphragms for the following conditions
Up to 40 ft. spans: none are required
40-80 ft. spans: use at first and third quarter points
80 -120 ft. spans: use at first three quarter points
Greater than 120 ft. spans: use a special design
Temporary diaphragms are property of the contractor, to be removed from site
Use CIP diaphragms at all supports (detail per Bridge Design Manual)
Use CIP intermediate diaphragms when the structure is heavily skewed or splayed
Time to Continuity (Article 5.14.1.4.4)
KDOT assumes continuity is made at approximately 50 days; use this to calculate camber
The minimum beam age will be 28 days at the time of continuity
Restraint moments are not used in determining beam design moments
The CIP continuity diaphragm is considered partially effective per Article 5.14.1.4.5
Full continuity is assumed at interior supports for determining the required slab reinforcement at the Strength Limit State
Analysis (+M) regions
Beam self weight will be resisted by considering simply supported member conditions for
Service and Strength Combinations
Non-Composite DL will be resisted by considering simply supported member conditions for
Service and Strength Combinations
Composite DL will be resisted by considering simply supported member conditions for Service and Strength Combinations
Live Load and Dynamic Load will be resisted by considering simply supported member conditions for Service and Strength Limits States.
Analysis (-M) regions
Composite DL will be resisted by considering the members as continuous
Live Load and Dynamic Load (LL/IM) will be resisted by considering the members as continuous
As a minimum, reinforce the slab per Article(s) 5.7.3.2, 5.7.3.3 and 5.7.3.4
As a minimum, develop the slab reinforcing steel past the quarter point of the longest span,
in-lieu of Article 5.14.1.4.8, and then begin to stagger the bars to be cut-off
Strand Extension (Article 5.14.1.4.9a)
Provide positive restraint moment capacity at piers and abutments by extending strands a
minimum of 36 in. to resist 0.6*Mcr
As a minimum extend six strands; four on the bottom and two on the top
Confinement /Splitting (Article 5.10.10)
Do not exceed 3 in. spacing within the splitting zone defined as a region h/4 from the beam
end
Do not exceed 6 in. spacing within the distance of 1.5d for the confinement reinforcing steel
Bridge Section
5 - 106
Design Manual
Economic Range
40-60 ft.
50-70 ft.
60-100 ft.
90-120 ft.
As shown in Table 1, consideration should be given to using only straight parallel strands on short
prestressed beams due to the high hold-down force required. Table 1 is based on using the minimum strand eccentricity from the geometry shown in Figures 1a-1d, adjusting strand eccentricities at beam ends can increase these controlling hold down forces. Use Appendix B PreStress
Harp Strand Force Calculator to verify hold down forces. Additional strands may be needed in
the top of the beam to limit tensile stresses in the top of the beam at transfer. Local prestressed
Bridge Section
5 - 107
Design Manual
manufactures have indicated that up to 8 strands can be added, in-lieu of harping, for a more economical beam. This is due to the costs associated to the hold down hardware and labor.
The harped strand hold-down points on prestressed beams shall normally be located at the 0.4 and
0.6 points. The vertical force required to deflect the strands downward in the beam shall be limited to 4 or 5 kip per strand and 38 or 45 kip per hold-down device for 0.5 and 0.6 in. strand
respectively. In certain instances, these values could be increased depending upon the type of
hold-down device used. The designer will verify the manufactures prestressed hardware information during shop plan review. Show the vertical uplift force per strand and the total uplift force
per hold down device Figure 5.2.15-4 K4 Beam Details (BR302a) within the design plans. For
beams with a single harp point, at the 0.5 point, the hold down force will be taken as having two
vertical components unlike the single vertical component from two harp points.
Debonding of strands in the end region of beams may be used to control excessive compressive
stresses due to the prestressing force. Strands may be debonded by encasing the strand in a plastic
sheath along a certain portion of the length; typically strands are debonded in 5ft increments. PCI
Journal (1981).
Do not debond strands which will be extended per Article 5.14.1.4.4.9a. In addition, the following
shall be incorporated in members where debonding is included:
Article 5.11.4.3 Partially Debonded Strands
Not more than 40% of the strands at one horizontal row will be debonded
Not more than 25% of the total strands can be debonded
The exterior strands of each horizontal row shall be fully bonded
Symmetric debonding about member centerline is required
Not more than 40% of the debonded strands, or four strands - which ever is greater - shall
have the debonding terminated at a section
Shear investigation shall be made in the regard to the reduced horizontal force
Bridge Section
5 - 108
Design Manual
Consideration may also be given to using 0.6 inch strand on long K4 Beams to alleviate congestion. If 0.6 inch strand is used on one span of a bridge, then use 0.6 inch for all spans of that
bridge.
The fabricator will use 0.6 in hold down hardware whenever 0.6 strand is used.
design steel area (0.5 in. seven-wire strand) = 0.153 in2
design steel area (0.6 in. seven-wire strand) = 0.217 in2
Allowable strand stress is as follows:
fpu = 270 ksi tensile strength
fpy = 243 ksi yield strength
The modulus of elasticity for the strand is Es = 28,500 ksi
Jacking Load (0.5 in low-relaxation) = 0.75 fpu = 202.5 ksi (per Table 5.9.3-1)
= 31.0 kip/strand
Jacking Load (0.6 low-relaxation) = 0.75 fpu = 43.9 kip/strand
Initial Stress (fpt) = Jacking stress (fpj) - Initial losses
fpj = Jacking stress, ksi
pt = Stress in prestressing steel immediately after transfer, ksi
Initial losses = Elastic Shortening f pES
Note: Steel relaxation at transfer has been removed from the specification for the Approximate
Method, which KDOT uses to determine time dependent losses.
KDOT assumes strand release to be 18 hours. If a higher strength concrete is used, resulting in a
higher required initial strength, then the time to strand release may be increased. This would result
in higher initial steel relaxation losses, not accounted for by the current method used.
fpe
Bridge Section
5 - 109
Design Manual
fy
fs
Cast-In-Place Concrete:
fc
Bridge Section
5 - 110
Design Manual
Final maximum compression is checked under Service I limit state and final maximum tension is
checked under Service III limit state. The difference between Service I and Service III limit states
is that Service I has a load factor of 1.0 for live load while Service III has a load factor of 0.80.
Stress Limits in prestressed beams due to the prestressing force, service loads and prestress losses
shall be limited per Table 5.9.4.2.1-1 Which is summarized below:
LRFD Design Stress Limit, (ksi) at Service Limit States
Concrete Stresses
LRFD Design Stress Limit, (ksi) at Service Limit States
Stage
Stresses, (ksi)
Article (s)
0.60 f'ci
5.9.4.1.1
5.9.4.1.2
Initial Compression
* Initial Tension
0.24 f c
0.60 f'c
Final Compression
Final Tension
Final Allowable Compression
with LL+1/2(Peff+DL)
0.0948 f c
0.40 f'c
5.9.4.2.1
5.9.4.2.2
5.9.4.2.1
Final DL Compression
0.45 f'c
5.9.4.2.1
0.60 f'c
5.9.4.2.1
0.24 f c
5.9.4.1.2
Bridge Section
5 - 111
Design Manual
All losses of the prestressing force on a member are interrelated. Prestress losses may be categorized as either instantaneous or time-dependent.
fpES = Instantaneous losses are due to anchorage set, friction and elastic shortening of the concrete however; only elastic shortening is considered for this method.
fpLT = Long-term time-dependent losses are those due to creep, shrinkage and relaxation of the
steel.
General losses follows Article 5.9.5
fpT = The sum of all losses = fpES + fpLT
Losses before the slab is cast (instantaneous):
Elastic shortening is computed as follows:
fpES
Ep
28,500 ksi
Eci
=
=
fcgp
(33,000W3/2
f c ksi.)
Pi ec2 Mg ec
P
f cgp = ------i + ----------- -----------Ig
Ag
Ig
In computing fcgp, the prestressing steel stress may be assumed to be 0.70 fpu for low relaxation
strand. This assumption is checked after the calculation of the loss, iterations may be necessary.
The alternative equation may also be used which gives a direct solution for fpES (Equation
C5.9.5.2.3a-1).
Bridge Section
5 - 112
Design Manual
( I + e2 A ) e M A
A g I g E ci
2
A ps ( I g + e m A g ) + ----------------Ep
A f
ps pbt g
m g
m g g
f pES = -----------------------------------------------------------------------
where:
A ps
Ag
E ci
Ep
em
f pbt
Ig
Mg
h = 1.7 0.01 H
(Equation 5.9.5.3-1)
5 st = --------------------( 1 + f ci )
where:
fci
fpi
Bridge Section
5 - 113
Design Manual
st
f pR
Note: The summation of losses fpLT may be entered as a lump sum, if the software being used
does not have the refined method available.
T.Y. Lin (1975) wrote that, An error in computing losses can affect service conditions such as
camber, deflection, and cracking. However, it has no effect on the ultimate strength of a flexural
member unless the tendons are unbonded or the final stress after loss is less than 0.5 fpu(p.88).
Bridge Section
5 - 114
Design Manual
As in the past non-composite dead loads are resisted by simple span conditions.
Composite dead load (rail and future wearing surface) are resisted by simple span conditions.
Live load beam design for positive moments are resisted by simple span conditions.
Slab design, in the negative moments regions, are designed to resist negative moments
assuming 100% continuity.
Anchor the slab reinforcement by extending to the 0.25 point + development length before
beginning the staggered cut-off (not more than 50%) of the longitudinal deck slab reinforcement. Using this anchor location is slightly different than described by Article 5.14.1.4.8.
Positive moment continuity steel (strands extended into the pier diaphragm) will be provided.
It is assumed that by following the above criteria, the potential positive restraint moments are balanced with the less-than-fully-effective continuity at the diaphragms. Thus, the additional
demand in the positive moment region due to restraint moments are already accounted for and
should not be included elsewhere. See Commentary C5.14.1.4.2.
M nd M cd + M cl
fcb = F
--- Fe
------ + --------+ ------------------------
Sb
A Sb
Sb
where:
fct
fcb
Bridge Section
5 - 115
Design Manual
Sb
Sb'
St
St'
Mnd
Mcd
Mcl
Temporary Stresses:
After the total design loads are satisfied by the design equations, initial stresses at strand release
from the application of prestress forces should be investigated. Temporary stresses are computed
as follows:
fct
F F i e c M nd
- -------- -----i + --------A
St
St
fcb
F F i e c M nd
-----i --------- + --------A
Sb
Sb
fct
F Fi ec
-----i + --------A
St
f cb
F Fi ec
-----i --------A
Sb
At midspan of beam
At end of beam
Where:
fct or cb
Fi
ec
Bridge Section
5 - 116
Design Manual
Si
Mnd
Mn
2
(assuming a rectangular section with only prestressing steel present)
where:
c
fps = fpu ( 1 k ----- (Equation 5.7.3.1.1-1)
dp
f py
where; k = 2 1.04 -------
f pu
The above equation provides an approximate value of fps. AASHTO allows the use of this equation provided requirements of Article 5.7.3.1.1 are met.
The procedure for computing the nominal moment capacity of a composite prestressed concrete Ibeam depends on the distance from the neutral axis to the compression face of the member. T-sec-
Bridge Section
5 - 117
Design Manual
tions where the neutral axis lies in the flange, i.e. c is less then the slab thickness, are considered
rectangular sections.
The distance from the neutral axis to the compression face of the member is computed as follows
(assuming no mild steel or compression reinforcement is present):
A ps f pu
c = -------------------------------------------------------- (Based on Equation, 5.7.3.1.1-4)
f pu
0.85f c 1 b + kA ps --------dp
Where:
b
dp
Aps
fps
fpu
fc
distance between the neutral axis and the compressive face (in.)
For most KDOT designs of prestressed concrete composite members, the rectangular compression stress block falls within the cast-in-place deck slab. When the neutral axis falls outside the
flange (i.e., flange thickness is less than c), the designer should use the Article 5.7.3.1.1-3 to
compute the nominal capacity of the composite member.3
Maximum steel percentage:
In the Standard Specifications the maximum percentage of steel was limited by the requirement
stating that the steel yields before the beam reaches ultimate capacity. The depth of the flexural
compressive block was compared to the depth of the steel centroid to verify adequate ductility.
Article 5.7.2 considers a section with the steel strain near the extreme fiber greater than 0.005 to
be a tension controlled region. Prestressed Beams are tension controlled. Unless unusually high
amounts of ductility are required, the 0.005 limit will provide ductile behavior for most designs.
Bridge Section
5 - 118
Design Manual
High ductility is required for redistribution of negative moments for continuos members according to Article 5.7.3.5 at strength limit states.
Minimum steel percentage:
The minimum prestressing steel, from Article 5.7.3.3.2, shall be that required to develop an ultimate flexural capacity at the critical section at least equal to the lesser of:
1.2 times the cracking capacity or
1.33 times the factored moment required by the applicable Strength I Load Combination.
The cracking capacity of the section shall be based upon a modulus of rupture of 0.37 f ' c ksi in
accordance with Article 5.4.2.6. Contrary to the Standard Specifications, the LRFD Specifications state that this requirement will be met at every section.
The combined moment to cause cracking is the sum of the total dead load moments plus an additional superimposed moment to reach a bottom fiber stress of 0.37
Sc
Where:
Mcr
fr
fcpe
Mdnc
Snc
Sc
Bridge Section
5 - 119
Design Manual
Mn
2
(assuming a rectangular section with non-prestressed tension reinforcement)
The distance from the neutral axis to the compression face of the member is computed as follows
(assuming no prestressing steel or compression reinforcement is present):
As fs
c = ------------------------- (Based on Equation 5.7.3.1.1-4)
0.85f c 1 b
Bridge Section
5 - 120
Design Manual
where:
b
ds
=
=
As
fs
fc'
c
a
=
=
Bridge Section
5 - 121
Design Manual
response of diagonally cracked concrete subject to in-plane shear and normal stresses. Prior to the
2008 interim revisions, the General Procedure for shear design was iterative and required the use
of tables for the evaluation of and (see Appendix B5)*. With the 2008 revisions, this design
procedure was modified to be non-iterative and algebraic equations were introduced for the evalAppendix
B5 are functionally equivalent to those used in the Canadian
uation of and . These
equations
design code (A23.2-M04, 2004), were also derived from the MCFT (Bentz et al. 2006), and were
evaluated as appropriate for use in the AASHTO LRFD Bridge Design Specifications (Hawkins et
al., 2006,2007)
Article 5.8.3.4.3 - Simplified Procedure for Prestressed and Nonprestressed Sections
This design procedure is based on the recommendations of NCHRP Report 549 (Hawkins et al.,
2005). The concepts of this Article are compatible with the concepts of ACI Code 318-05 and
AASHTO Standard Specifications for Highway Bridges (2002) for evaluations of the shear resistance of prestressed concrete members. However, those concepts are modified so that this Article
applies to both prestressed and nonprestressed sections.
The longitudinal reinforcement resists the additional force due to shear, i.e., the horizontal component of the diagonal compression field. The tensile capacity of the reinforcement on the flexural tension side of the member, taking into account the lack of full development of that
reinforcement, is checked using Equation 5.8.3.5-1.
When computing strains for sections in the negative moment region, be aware that only reinforcing on the tension side of the beam may be used. Therefore, near a pier, the only prestressing steel
that can be used in the strain equation are the harped strands located on the tension side of the
beam.
Detailing for Shear
At beam ends, use #5 stirrups spaced at 3 in for a distance of h/4 from the end of the beam for
the splitting zone defined in Article 5.10.10.
For transportation considerations, continue use of #5 stirrups to a distance of one-tenth of the
beam span.
According to Article 5.10.10.2 at no instance will the confinement reinforcement from the
end of the beam to 1.5d be spaced greater than 6 in. See Section 3.2.9.12 Transportation for
additional requirements.
Additionally, do not exceed 18 in. stirrup spacing within the beam. Do not exceed a 6 in.
change in spacing when changing spacing along the length of the beam will result in a
reduced shear capacity by more the 50% along the member
Use #5 stirrups throughout the beam.
*Note: AASHTOWare Bridge Design, design software uses the iterative general method described
in Appendix B5.
Bridge Section
5 - 122
Design Manual
5.2.10 Diaphragms
For typical Abutment Diaphragm Details, see Figure 5.2.15-5 K2 Beam Details (BR302c).
For typical Pier Diaphragm Details, see Figure 5.2.15-7 Typical Pier Diaphragm and Figure
5.2.15-7a Optional Abutment Diaphragm.
For typical Concrete Intermediate Diaphragm Details, See Figure 5.2.15-8 Typical Concrete
Intermediate Diaphragm.
For Temporary Diaphragm Details, see Figure 5.2.15-9 Temporary Diaphragm Details (BR
305)
Permanent diaphragms:
Cast-in-Place (CIP) permanent diaphragms are required at all supports; see Figure 5.2.15-5 K2
Beam Details (BR302c) for details. In general, CIP permanent intermediate diaphragms are not
preferred or required. Intermediate diaphragms are most beneficial in stabilizing the beam during erection and offer little distribution of live load and therefore, they can be removed after the
structure has been made continuous and composite. LTRC, (2008)
Temporary diaphragms: **
Temporary diaphragms are required to stabilize beams during the construction of the deck. Plans
shall show the location of the temporary diaphragms. Generally, locate the diaphragms approximately 12 ft. from the beam ends or at quarter points - whichever is closest to the pier. As strand
geometry allows. Temporary diaphragms are required in all bays or as noted below. They are
attached by either coil inserts cast into the beam or by bolting with an open hole cast into the
beam. Open hole type connections are preferred (and shown in Base Sheet BR305) by KDOT
because this detail provides for a more modular construction (interior and exterior beams are the
same). For bridges with an even number of beam lines every other bay may be sufficient to connect two beams, and thus creating frame action see Figure 5.2.15-9 Temporary Diaphragm Details
(BR 305) Steel temporary diaphragms shall remain in place until the concrete diaphragms (if
required) and the deck have cured. The Contractor will remove the diaphragms and erection
angles and fill the open holes of the exterior face of the exterior beam an prequalified epoxy grout.
The plans note states that all temporary diaphragms are subsidiary to other bid items.
For conventional overhang formwork supported by the exterior beams only, the plans will show
either of the following options:
a. For spans less the 40 ft long, no temporary steel diaphragms are required.
b. For spans 40-80 ft long, use two temporary steel diaphragms at locations at the first and
third quarter points.
c. For spans greater than 80 ft but less than 120 ft, use three temporary steel diaphragms
located at all three quarter points.
d. For spans > 120 ft, a special design is required.
Needle beams may be used in lieu of temporary steel diaphragms to support formwork and stabilize beams during construction, as accepted by the Engineer. Needle beam support and framing is
Volume III US (LRFD)
Version 1/14
Bridge Section
5 - 123
Design Manual
considered to be falsework and is subject to the falsework review requirements as per the KDOT
specifications. (See Section 5 of the Bridge Manual).
** Note: This does not replace the requirements for erection controls on structures over traffic.
5.2.13 Transportation
During transportation, prestressed beams may be subjected to dynamic forces. This bouncing
of the beam can reduce the dead load on the member which could result in critical tension stresses
in the top of the beam. The designer should check these stresses by assuming support points for
beam transportation at 5.0 ft. from the end of the beam or to the first tenth point of the span,
whichever is greater. If the controling support distance is somewhere between 5 ft. and the first
tenth point, be sure to enter this maximum support length on the beam Details Sheet. Verify that
the maximum support length dimension is shown on the shop drawings. Check tension in the top
Bridge Section
5 - 124
Design Manual
of the beam over the temporary support due to the cantilevered moment. To approximate the
dynamic load effects, assume a beam dead load of 3g on the cantilevered portion (PCI Design
Handbook, 1985, p. 5-17).
Also check the tension in the top of the beam at the harp point of the strands using the reduced
span length due to the temporary supports. Again, use 3g for the overhang force, but use the
normal beam dead load (g) when computing forces between the supports. Allow a maximum
temporary tension stress of 0.24 f c avg ksi or7.5 f c avg psi. This upper limit is allowed only if
the stress in the mild reinforcement at the top of the member meet the requirements of the commentary for Article C5.9.4.1.2.
For additional information on the handling of beams, see: (PCI JOURNAL, 1987, p.87-101).
See Appendix C Prestressed Girder (Transportation Stress Check) for Example calculations for
transportation stress check
Factor of safety
45 degree lifting angle
Strand
K4 beam mass
= 100 x 671 lb./ft./1000
= P
= 0.75 fs(As)
No. of strands
=4
= diameter low-lax (fs = 270
ksi)
= 671 lb./ft.
= 67.1 kip
= 33.55 kip
= 0.75(270 ksi)(0.153 in2)
= 31 kip/strand
= P (1/Sin 45)(F.S.) / Allow. kips/
strand
= 33.55 kip (1.4)(4) / 31 kip/strand
= 6.1 strands required
= 3.05 loops required
Bridge Section
5 - 125
Design Manual
Embedment Length
Le
=
=
5.6 kip/strand
36.55 ksi
32.6"
Assume a factor of
safety of 2.0
fs
Le
Conclusion:
Use 33" embedment
Bridge Section
5 - 126
Design Manual
Bridge Section
5 - 127
Design Manual
Bridge Section
5 - 128
Design Manual
Bridge Section
5 - 129
Design Manual
Bridge Section
5 - 130
Design Manual
Bridge Section
5 - 131
Design Manual
Bridge Section
5 - 132
Design Manual
Bridge Section
5 - 133
Design Manual
Bridge Section
5 - 134
Design Manual
Bridge Section
5 - 135
Design Manual
Bridge Section
5 - 136
Design Manual
Bridge Section
5 - 137
Design Manual
Bridge Section
5 - 138
Design Manual
Bridge Section
5 - 139
Design Manual
Bridge Section
5 - 140
Design Manual
Bridge Section
5 - 141
Design Manual
Bridge Section
5 - 142
Design Manual
Bridge Section
5 - 143
Design Manual
Bridge Section
5 - 144
Design Manual
Bridge Section
5 - 145
Design Manual
Bridge Section
5 - 146
Design Manual
Bridge Section
5 - 147
Design Manual
Bridge Section
5 - 148
Design Manual
Bridge Section
5 - 149
Design Manual
Bridge Section
5 - 150
Design Manual
Bridge Section
5 - 151
Design Manual
Bridge Section
5 - 152
Design Manual
Bridge Section
5 - 153
Design Manual
Bridge Section
5 - 154
Design Manual
LFDandLRFDPrestressedBeams
AASHTO Requirement
Code AASHTO KDOT
StrandType&Properties
SevenWireLowRelaxationStrands(Dia)
TensileStrength(Fpu)(ksi)
YieldStrength(Fpy)(ksi)
ModulusofElasticity(ksi)
2
StrandArea(in )
Mass/Wtperunitlength(lbs/ft)
TransferLength(in)
1/2"
270ksi
0.90fpu =243ksi
28,500ksi
2
0.153in
0.521lbs/ft
60ds =30"
StrandType&Properties
SevenWireLowRelaxationStrands(Dia)K4orK6Only
Mass/Wtperunitlength(lbs/ft)
StrandArea(in2)
TransferLength(in)
0.6"
0.732lbs/ft
2
0.215in
60ds =36"
5.4.4.11
5.4.4.11
5.4.4.2
5.11.4.1
X
X
(ksi)
0.24*SQRT(f'ci)
7.5*SQRT(f'ci)
0.60*f'c
0.0948*SQRT(f'c)
0.45*f'c
0.40*f'c
P/SProperties
InitialLossElasticShortening
LongTermLossMethod(AASHTO,LumpSumorPCI)
JackingStressRatio(lowrelaxation)
P/STransferStressRatio(lowrelaxation)
TransferTime(18hrs=0.75days)
(
y)
AgeatDeckPlacement(days)
FinalAge(days)
LossDataAASHTOPercentDL
AASHTOApproximateMethod
0.75
LeaveitBlank
18
50
27375
0%
LossData,"LumpSum"(ksi)
FinalLoss
CompositeLoss
ContinuousLoss
Notused
Notused
Notused
5.11.4.1
9.15.1
9.15.1
9.15.2
9.15.2
9.15.2
9.15.2
9.15.2
X
X
X
X
X
X
X
X
X
<======
(psi)
0.60*f'ci
IntentionallyRoughened
TopFlangeWidth
0.28ksi
1
0.3
1.8ksi
Shrinkage/Time
BeamCuringMethod,MoistorSteam
SlabCuringMethod,MoistorSteam
DeckDryingTime
SlabInterface
InterfaceType
InterfaceWidth
Cohesion(ksi)
FrictionFactor
K1
K2
LossData"PCI"(ksi)
UltimateCreepLoss
MaturityCoefficent
UltimateShrinkageLoss
LFDRatingStressLimits
(ksi)
(psi)
0.60*f'ci
InitialAllowableCompression
0.0948*SQRT(f'ci)<=0.20ksi
3*SQRT(f'ci)<=200psi
InitialAllowableTension
0.60*f'c
FinalAllowableCompression
FinalAllowableTension(NoteBelow)
Zero Inv or 0.19*SQRT(f'
ZeroInvor0.19
SQRT(f c)Oper
) Oper ZeroInvor6
Zero Inv or 6*SQRT(f'
SQRT(f c)Oper
) Oper
0.40*f'c
FinalAllowableDLCompression
0.60*f'c
FinalAllowableSlabCompression
0.40*f'c
FinalAllowableCompression
(LL+1/2(Pe+DL))
IfratinganLRFDdesignedbridgeverifytheInventoryratingfactorfortheHSdesigntruckis1.10orgreater
=====> VisittheFactorsTaboftheMemberAlt.foreachmemberandsettheASDFactorforP/SConcreteTensionforInventorytoZERO
TheOperatingratingfactorshouldbegreaterthan1.0fortheHETloadratingtruckusingasinglelane(S/7)andfullimpact.
LRFDDesignStressLimits
InitialAllowableCompression
I iti l All
InitialAllowableTension(WithAsproportionedasperFig.
bl T i
(With A
ti
d
Fi
C5.9.4.1.21)
FinalAllowableCompression
FinalAllowableTension
FinalAllowableDLCompression
FinalAllowableCompression
(LL+1/2(Pe+DL))
X
X
X
X
3*SQRT(f'ci)
5.9.4.1.1
5.9.4.1.2
5.9.4.2.1
5.9.4.2.2
5.9.4.2.1
5.9.4.2.1
X
X
X
X
5.8.4.1
5.8.4.3
5.8.4.3
5.8.4.3
5.8.4.3
X
X
X
X
X
5.9.5.2.3
5.9.5.3
5.9.3
X
X
X
X
X
X
X
X
X
X
X
X
X
ModifiedPCI
Setonplans
X
X
X
X
0.75
X
X
X
Steam(assumed)
Moist
14Days
X
X
X
0.75
28
50
75
75
X
X
X
seeBridgeDesignManual
Use28days,0.75
seeBridgeDesignManual
Time
CuringTime(18hrs=0.75Days)
Time Continous (Days)
TimeContinous(Days)
TimeComposite(Days)
ServiceLife(years)
TimeofAnalysis(years)
LRFDShearComputationMethod
GeneralorSimplified
Miscellaneous
Humidity
SustainedModularRatio
CamberCalcs
X
X
General
MaybeSimplified
5.8.3.4.2
5.8.3.4.3
X
X
65%
2
5.7.1
Bridge Section
5 - 155
Design Manual
Bridge Section
5 - 156
Design Manual
Input
Strand Eccentricity (in)...............................................................
e 45
Beam Length(ft)......................................................................
Lb 60
0.6
(in 2 )............................................................
Area 0.217
(Note: Use 0.153 in2 for 0.5" strand and 0.217 in 2 for 0.6")
Number of Strands being harped (each)...........................
Ns 6
fu 270
Maximum Prestressing Force per strand (80% max for guts) (kip) ....
Pu 45
PS_Force_Max Area fu .80
Harp Location (tenth point less than or equal to 0.5) ...................... Harp 0.4
(must be symmetric)
Harpn 2
Number of Harp Locaions(each)..............................................
(typically two are used)
Calculations
90
strandper
e
atan
360
L Harp 12 2
2
Harpn
81.119
360
Pu cos
Planper_stand strandper
Total strandper Ns
Total device Total
Bridge Section
5 - 157
Design Manual
Results
PS_Force
Pu if Pu d PS_Force_Max
Total
Total if Total d 38
"Check Manufacture" otherwise
otherwise
Checks
Prestressing force per strand (80% GUTS max.) (kip) ......
PS_Force
45
Hold down force per strand (kip) (4 for 0.5" and 5 for 0.6" strand)..
strandper
"Check Manufacture"
Planper_stand
Total hold down force per device (kip) (38 kip max).............
Total
"Check Manufacture"
Total device
6.947
41.682
Bridge Section
5 - 158
Design Manual
From the shear & moment diagrams, it can be shown that by moving the supports inward, the
dead load moment between the support is reduced by a constant value. As can be seen the shape
of the moment diagrams are the same from support to support of the transported beam. Therefore
the value of the reduction is equal to the cantilever moment plus the value of the moment, for the
beam supported at the ends, at the location of the transportation support.
Bridge Section
5 - 159
Design Manual
Worked Example:
At Beam End
P
1,018.7 kip
31.8 kip
St
9, 754in
= 9,080 k-in = Pe
Sb
9, 815in
692in
A. Stress at Support
2
3W ( 7.0 ) - =
M + 7.0 V + -----------------------2
Moment = 9, 080 k in + 2, 671k in + 635 k in = 12, 386 k in
Moment=
, 018.7 -k 12
, 386 k in- = 202 psi
f c Top = P
--- Moment
--------------------- = 1--------------------------------------------------2
3
A
St
692in
9, 754in
compression OK
Bridge Section
5 - 160
Design Manual
1, 018.7 k
P
, 386 k in- = 2, 734psi compression OK
f c Bot = --- + Moment
--------------------- = ---------------------- + 12
------------------------------2
3
A
Sb
692in
9, 815in
Allowable Stresses:
Allow Comp. = 0.6 f c
Allow Comp.
, 931psi + 5, 947psi- = 5, 440psi
f c = 4---------------------------------------------------2
= 3, 260psi
Allow Ten. = 5 f c = 5 5, 440 = 370psi
B. Stresses at Hold Down
2
W ( 29.5 ) - R ( 29.5 )
Moment = M + 36.5 V + 3W 33.0 7.0 + ---------------------y
2
= 9, 080k in + 13, 928k in + 5, 988k in + 3, 759k in 15, 165k in = 17, 590k in
, 018.7 k- 17
, 590 k in- = 331psi Tension OK
f c Top = P
--- Moment
--------------------- = 1--------------------------------------------------2
3
A
St
692in
9, 754in
, 018.7 k- + 17
, 590 k in- = 3, 264psi Comp. OK
--- + Moment
f c Bot = P
--------------------- = 1--------------------------------------------------2
3
A
Sb
692in
9, 815in
Bridge Section
5 - 161
Design Manual
MathCadd Example:
Transportation Stress Calculations:
Beam Data:
K4+2
D 56in
L 82ft
HarpPt 33ft
0.4*L
Use_As.top 1
1=yes, 0=no
b top 24in
A 692in
Vps 30.9kip
St 9754in
M ps 8850kip in
Sb 9815in
As.top 0.78in
fpc 5290psi
fy 60ksi
Calculations
W A 150 pcf
fc_ten_allow
fc_comp_allow
fc_ten_allow
0.721
kip
ft
3.174 ksi
0.552 ksi
otherwise
Bridge Section
5 - 162
Design Manual
6 STEEL
Table of Contents
6.1 General .....................................................................................................................1
6.2 Materials ...................................................................................................................3
6.3 Layout .......................................................................................................................8
6.3.1 Cross Frame Layout ...................................................................................................14
List of Figures
Figure 6.2-1 Fracture Critical Member Designation. .....................................................................6
Figure 6.3-1 Alignment of Bearing Devices .................................................................................11
Figure 6.3-2 Curved Bridge Geometry .........................................................................................12
Figure 6.3.1-1 Cross Frame for Skewed Bridges ..........................................................................15
Figure 6.3.1-2 Transverse Stiffener Placement .............................................................................16
Figure 6.4-1 Fillet Depth Computation for Steel Girder ..............................................................19
Figure 6.4-2 Fillet Reinforcement ................................................................................................20
Bridge Section
6-1
Design Manual
List of Tables
Table 6.4.7-1 KDOT Plate Grip Table for Structural Bolts ..........................................................38
Appendixs
Appendix A Steel Beam Circular Haunch ....................................................................................71
References
References: ....................................................................................................................................70
Bridge Section
6- 2
Design Manual
6 Steel
6.1 General
General:
Structural steel, in the form of rolled steel beams, welded plate girders or steel box girders are
used for bridge superstructures. In rare instances integral pier caps will be designed using steel.
This section is intended to provide general design guidance and information on detailing practices. Generally, the shop connections are welded and field connections are made by mechanical
fasteners. Welded field splices, while used in the past, are not allowed under normal circumstances.
It is KDOT policy to use shear connectors in both positive and negative moment areas.
Rolled Beam:
For spans up to 120 feet rolled beams should be considered. To effect economy in the use of rolled
beams, rolled beam sections of different sizes may be field bolted together. Use the longest pieces
possible, it is common to go from the abutment to the next field splice over the pier with one piece
on shorter spans. Do not use welded shop splices, but continue pieces from bolted splice to bolted
splice. When changing sections on rolled beams stay within a beam series, with the lighter sections used in the positive and the heavier within the negative moment regions. Use fill plates when
thickness changes between the adjacent sections are greater than 1/4 in. Because of load induced,
the use of cover plates should be avoided unless the cover plate termination is within the bolted
field splice.
Plate Girder: An advantage of plate girders is they can be tailored to fit shear and moment
requirements more closely than rolled beams. Plate girders become advantageous and are used for
spans up to 275 feet. Plate girders are ideally suited for geometric changes and can be made to
conform to horizontal and vertically curved highway segments. Camber can be cut into the webs
to account for dead load deflection. Because of the tailored nature of plate girders fillets and overhangs can be designed to be uniform, thus reducing construction complexities.
Steel Box Girders:
Steel Box Girders or Tubs are closed sections after the deck is constructed creating a torsionally
efficient member. The only preferred use of this type of girder for bridges is with small radii on
horizontally curved bridge superstructures. This superstructure type is ideally suited for ramps
and fly-over locations.
Member Origin:
Mill Lengths for Plate and Rolled Shapes:
Steel bridges are fabricated and constructed with steel elements that are produced at two different
types of steel mills; shape mills and plate mills. In addition to different products, the grades of
steel available from each type of mill differ slightly.
Shape mills produce bars, angles, tubes, pipes, channels, W sections (wide flange), S sections
(American Standard), and HP, and PZ piling that satisfy a variety of material specifications.
Standard mill lengths available for these sections range from 30 to 60 ft. With sufficient quanti-
Bridge Section
6- 1
Design Manual
ties and sufficient lead time, longer lengths may be available. AISC's "Modern Steel Construction" yearly January issue provides information on different shapes available domestically from
various mills. The designer will check the availability of shapes before specifying their use in a
structure. Go to http://www.nucoryamato.com/staticdata/RollCastSchedule.pdf for casting schedule.
Plate mills produce flat sections that are used to fabricate plate girders, connector plates, gusset
plates, etc. Plate steel is also produced in a number of different material specifications. Larger
plate mills have a width limitation of 150 in. The maximum available plate length varies by mill
and cross-sectional dimensions of the plate. The Burns Harbor Plate Mill capacity limitations
should be used for this purpose. See Burns Harbor Plate Length Availability
The designer should verify that the plate length requested between the shop splices are available.
Provide alternate shop splice locations by using the following guidelines for considering plate
lengths.
Structural Steel Members: Guidelines for plate girder shop splices
Flange plates < 80 ft. should be one piece field splice to field splice
See the Bridge Design Manual (BDM) Section 6.4 for minimum flange thickness & width
requirements vs. span length
Flange plates > 80 ft. should show two optional shop splices
Minimum length of plate is 60 ft. in positive moment, 40 ft. in negative moment area
Center about pier or maximum positive moment unless directed otherwise
Flange splice and web splice shall be offset > 6 in.; more if any thickness > 2 in.
Flange or web splice shall both be offset from any stiffener by > 6 in.; more if any thickness
> 2 in.
Flange plates > 100 ft. should show two shop splices
Minimum length of plate is 60 ft. in positive moment, 40 ft. in negative moment area
Center about pier or maximum positive moment unless directed otherwise
If thicker plate extends to the field splice - redesign of the splice may be required
A splice thickness ratio of 2:1 or less is preferred. Additional length may be required.
Flange splice and Web splice shall be offset > 12 in.; more if any thickness > 3 in.
Flange or Web splice shall both be offset from any stiffener by > 12 in.; more if any thickness
> 3 in.
Flange plates > 120 ft. should show two or more shop splices
Typically a minimum of 20 ft. of flange length or 1000 lbs. of flange weight savings is equal
to an optional shop splice
Note: All shop and field splices shall be made where shown on the Contract Plans as a splice or
as an optional splice. Elimination of any splice may be requested.
Bridge Section
6- 2
Design Manual
Note: If the above guidelines are followed and the fabricator requests a change in location or the
addition of a shop splice, it has been KDOTs policy to limit the stress at the proposed location to
50% of the yield stress. As such it is KDOTs Bridge Office that will accept or reject the proposed location.
* The shaded area above is the approximate tenth point limits for balanced spans
Jointless Bridge Types:
It is KDOTs policy to use integral and semi-integral bridge abutments when possible. Placing the
expansion joint on the approach pavement has numerous advantages, a failed joint will not compromise bridge elements and repairs of the approach are often less costly. For steel structures
adjacent to MSE walls isolate bridge superstructure movements from MSE wall. The substructure
must be prevented from movements that could damage the MSE wall.
6.2 Materials
Structural Steel and Properties: (Section 1600 of KDOT Standard Specifications)
Shape sections, other than pipe and tubing, are typically available in M270 or A709 36, 50, or
50W grades. Steel plate is available in M270 Grade 36, 50, and 50W. High Performance Steel
(HPS) is available in M270 Grade HPS50W and HPS70W. The LRFD Specifications identify a
number of steels that can be incorporated into bridge structures, they are identified in Tables
6.4.1-1 and 6.4.2-1 with both AASHTO and ASTM designations. Weathering steels have a "W"
appended to the grade designation (e.g. 50W, HPS70W, HPS100W). Designers should note that
the AASHTO and ASTM designations are not identical. All Flanges will be AASHTO M270 and
webs will be ASTM A709.
Bridge Section
6- 3
Design Manual
The typical steels for KDOT bridge designs are Grade 50W and HPS70W. The use of hybrid sections can be cost effective. The bottom flange in positive moment regions and both flanges near
piers would utilize HPS70W, all other steel would be 50W.
Secondary members such as stiffeners, cross frames and diaphragms should be made of Grade 36
Steel unless design indicates a need for a higher strength steel. This is valid regardless of the base
metal used for flanges and webs.
For miscellaneous structural steel items, specify A709 Gr. 36, but place a note on the plans stating
A36 may be substituted. Although they are basically the same steel, A36 is more readily available
in small quantities. Requiring A709 Gr. 36 may require retesting and re-certification of A36 material, which can be expensive and time consuming.
Fatigue and Fracture:
The AASHTO Specifications require additional tests (Charpy testing) to verify the toughness of
the material. All Fracture Critical Members (FCM) must be designated according to AASHTO M
270 inclusive of requirements S84. In accordance with AASHTO Specifications, the material for
all main load-carrying members of steel bridges (rolled beam and welded plate) subject to tensile
stresses shall meet (as a minimum) the Charpy V-notch test for notch toughness (Zone 2).
Because of the increased availability and reduced costs, it is KDOTs policy to specify T3 material accordingly:
Use T3 materials for all plate girders calling out Gr.36 or Gr. 50 materials.
Use HPS material for all plate girders calling out Gr. 70 materials.
Use T3 for all rolled beams calling out Gr. 36 or Gr. 50 materials.
Use T2 for rolled shapes for all materials.
Use T3 for finger plates.
If failure of fracture critical tension members could cause collapse of the bridge, special consideration is required in accordance with a Fracture Control Plan. Fracture critical members shall be
clearly delineated on the bridge details. See Figure 6.2-1 Fracture Critical Member Designation.
for detailing example. For guidance on this particular problem, reference is made to Guide Specification for Fracture Critical Non Redundant Steel Bridge Members, AASHTO, 1978.
Bridge Section
6- 4
Design Manual
Fracture-Critical Members:
* Material for fracture critical members (FCM) requiring Charpy V-Notch
testing will be noted as M270 Gr.___F3 (FCM) on the plans.
* The following FCMs require Charpy V-Notch testing:
All Flanges, Splice Plates, Cross-frames, Webs, Bearings, Floor Beams,
Fill Plates > 0.375 in., Stiffeners
Fracture Critical Members must be called out on the plans.
Governing Welding Specification: D1.5 and Fracture Control Plan
2.
Note: T3 is available in thickness greater than in most mills. Use T3 when ever possible, but
consider substitutions with material of lesser toughness for non-critical secondary members.
3.
Non-Fracture-Critical members not needing Charpy tests:
* Material for non-FCMs not requiring Charpy V-Notch testing will be
noted as A709 Gr.___on the plans.
Main Members:
Webs < 0.5in., Fill Plates < 0.5 in., Stiffeners < 0.5 in.,
Splice Plates < 0.5"
Governing Welding Specification: D1.5
Non-main Members:
Drainage, Bearings (Rockers), Bearings (plates), Diaphragms, Cross Frames,
Fill Plates (not developed), Finger Joints (< 6 in.), Expansion Device
Armoring, misc. hardware.
Bridge Section
6- 5
Design Manual
Bridge Section
6- 6
Design Manual
higher cost, A490 bolts should not be used without first consulting the Senior Squad Leader
assigned to the project. A490 bolts cannot be sold with plating, galvanizing, or mechanical zinc
coating, so their use as field bolts could be problematic. Lengths are limited to 6 in. for these bolts
and availability for lengths over 4 in. for A490 should be verified before letting. A325 or A490
cannot be welded or tack welded due to the high carbon content. Lengths for all structural fasteners will conform to grip tables in Table 6.4.7-1 KDOT Plate Grip Table for Structural Bolts
For applications where strength is not the primary design consideration, ASTM A307 bolts may
be used. ASTM A307 bolts are used where welding of the bolt head is required (as in anchorages
for expansion joints or brackets).
Additional fastener information may be found in "Mechanical Fasteners for Steel Bridges", Vol. I,
Chapter 4A, Highway Structures Design Handbook, April 1996.
A Type 1 bolt designation is used for steels other than weathering steel. Type 3 is used for weathering steel. Both ASTM A325 and A490 may be Type 3. Type 1 bolts may be either hot dipped
(ASTM A153) or mechanically galvanized (ASTM B695). Galvanized bolts must be retested
after the coating is applied and are shipped with a visible dye (blue) wax coating.
Anchor bolts must conform to AASHTO M314 Grade 36, 55 or 105 galvanized. Swedged anchor
bolts according to KDOT Standard Specification 1615.
Nuts:
All nuts must conform to ASTM A563 for the Property Class and design style of the nut. Use
Grades DH, DH3, C, C3 and D for ASTM A325. Nuts for ASTM A490 Type 3 shall be Grade
DH3.
Washers:
Washers must conform to ASTM F436 except Direct Tension Indicators (DTI) which conform to
ASTM F959 Type 1 uncoated or Type 3 weathering. NOTE: KDOT does not use indicator
type DTIs (squirters or bleeders), but uses a feeler gauge to measure the gap or lack of gap in the
DTI which indicates the tension in the bolt shank.
Beveled washers are used when the angle formed between the nut or bolt head contact surface and
the member is 20:1 or greater.
Plate washers are used for round holes larger than oversized or elongated/slotted holes. Plate
washers have a minimum thickness of 5/16 in.
For all standard bolting operations of primary and secondary members KDOT uses a hardened
washer under the turned element and a DTI under the static element.
Shear Studs:
Welded shear stud connectors can be either field or shop applied based on the Contractors choice,
but in either case shall conform to ASTM A108 Grades 1010 through 1020.
Bridge Section
6- 7
Design Manual
Weld Materials:
Shop welding materials (filler materials, electrodes and consumables) are governed by AWS
D1.5. For calculations involving the capacity of welds the designer shall assume materials consistent with E 70XX type electrodes for all structural steel materials, unless known otherwise.
The designer will verify the shop details weld procedures are on the approved list for that fabricator.
Coating Types: (Section 700 of KDOT Standard Specifications)
Paint all structural steel, which require a coating system, in compliance with the Structural Steel
Protective Coatings Council (SSPCC) requirements. New steel bridges may be either comprised
of weathering or non-weathering steel. Both require protective coatings to be applied and both
have limitations for use. Currently new steel is blasted to a SP-10 and prime coated with inorganic zinc and existing steel is blasted to a SP-6 and prime coated with organic zinc. Both new
and existing are top coated with water borne acrylic.
Bearings:
Steel plate used for bearings shall be ASTM A709 Grade 36 or 50 or ASTM A514. Pins for steel
bearings shall be ASTM A668. Castings for bearings shall satisfy ASTM A148, Grade 40 - 80.
Do not use weathering steel for any bearing device application other than for elastomeric without
PTFE.
Bridge Section
6- 8
Design Manual
6.3 Layout
Tangent Layout:
This is most common and least complicated bridge layout. The designer is reminded to look for a
PT (point of tangent) or PC (point of curvature) on the roadway near the ends of the structure indicating a possible transition zone for the roadway cross-slope. The design will use a Type B shop
laydown unless long/deep spans are used and the fabricator limitations require a Type C. The
designer will get prior approval, from the State Bridge Office, to use Type C shop laydown.
Horizontally Curved Layout:
The designer will verify that the structure does not have a superelevation transition on the bridge.
Sections in transition will have warped deck sections and a unique cross-frame layout. Extra care
will be given to these areas to prevent cuts in the slab from negative fillets.
In order of progressing difficulty the designer should consider the following possibilities for laying out a curved steel bridge:
For a structure on a horizontal curve having a large radius, when compared to the length of
the bridge, a rectangular framing system can be used rather than a curved framing system. A
rectangular deck can be cast with the striped following the curve. This will create variable
shoulder widths and equal overhang widths. Verify that the shoulder width will not be less
than required by the road design cross-section. After consulting the road designer, the bridge
designer can move the centerline of the structure half the mid-ordinate distance. Use a Type
B shop laydown for this bridge layout type.
Note:
The rule-of-thumb for detailing a rectangular deck and girder system for a road section
with a large radius is; if the mid-ordinate of a chord taken from centerline of abutment to
centerline of abutment is less than 12 in. then the previous method can be effective.
Another method for a curved roadway is for rolled beams to be used as short chords from
field splice to field splice with a kink in the beams. This kink in plan view, is located at
the field splice. For this system a curved deck is cast. The variations in the overhang width
should be minimized and the shoulder width must not be less than that required by the road
design cross-section. Use Type B shop laydown.
Both rolled beams and plate girders can be horizontally curved when the radius/ bridge length
combination is too great to apply the previously mentioned methods. For large radius bridges
the designer will use Type B shop laydown. When the bridge has a smaller radius or if the
structure has a transition to superelevation on the structure the designer will use a Type A
shop laydown.
When the roadway curvature dictates curved members are required the designer is to consider
the use of parallel bents to simplify the layout, fabrication and construction. This approach
maintains a constant span length and skew angle relative to a local tangent (if the structure is
skewed).
Bridge Section
6- 9
Design Manual
Bridge Section
6 - 10
Design Manual
Bridge Section
6 - 11
Design Manual
Girder Spacing:
Although girder spacing can have many variations depending on the bridge site conditions,
KDOT uses 8 ft. girder spacing for all standard roadway widths. Wider spacing requires deeper
sections, and heavily reinforced deck slabs. Wider girder spacing does allow the use of less girder
lines however, disadvantages to this philosophy include taller piers for the deeper girders, roadway clearance issues and difficulty in bridge deck replacement when phase construction is
required.
Phasing:
In developed urban areas the designer will consider the effects of future repairs and rehabilitation
on the traveling public. In instances where an existing structure is to be replaced and phasing is
required the designer will make every effort to phase on three girder lines as a minimum. It was
common practice in the past that bracing was not used in all bays. The existing structure, to be
used for carrying traffic during construction, must have cross-frames in all bays.
Bridge Section
6 - 12
Design Manual
Where there is 2 in. or more of differential deflection due to concrete placement between the
phases use a closure pour if the roadway width is sufficient. Regardless of deflection amounts
disconnect the lateral bracing in the bay between the phases, field drilling may be required to
avoid overstressing the members.
Unit Changes:
Unit changes are points of discontinuit. Unit changes may occur for various reasons, more commonly its because of the overall bridge length. Section changes, material changes or superstructure type changes all result in unit change. In a long structure, where a unit change is required for
thermal expansion limits, the unit change may be at the pier or at a hinge location. In most cases a
common pier is recommended. With a common pier the structure is discontinuous, basically
creating long end spans within the structure, the structural members will be less efficient. If a
hinge is used in a span, it will be the shelf type instead of the older style pin and hanger type.
Locating the shelf type hinge at the dead load inflection point is recommended. An elastomeric /
PTFE bearing device is preferred for this application.
Expansion Joint Location:
Use integral or semi-integral abutments whenever possible. Joints in the approach is preferred
over joints in the bridge structure. The designer will consider the grade on the bridge if joints are
required. Consider fixing the lowest elevation on the structure to prevent the joint from closing
due to creep downhill of bearings and pier columns.
Expansion Joint Types:
Expansion joints are a source of regular maintenance. KDOT has had success by placing Membrane Sealant type expansion joints on the approach slabs. See RD712 for details. For joints on
the bridge structure, the use of armored strip seals on non-skewed bridges works fairly well for
intermediate length expansion. Use finger or sliding plate expansion joints with sealing troughs
for larger length expansion. Modular joints are problems in operation and in repair, do not use
without prior approval from the State Bridge Office. See 14 EXPANSION JOINTS AND
BRIDGE BEARINGS for further information on expansion joints.
Bearing Layout and Types:
Bearing type selection is a function of the type of structure and layout of the structure. For smaller
structures, with spans less than 200 ft., use elastomeric or elastomeric/TFE devices. For spans
greater than 200 ft. use steel bearings. For horizontally curved bridges where the curve is greater
than 2.5 degrees use pot bearings. Layout the bearings along the chord for curved structures. See
14 EXPANSION JOINTS AND BRIDGE BEARINGS for further information on bearing device
type and layout.
Shear Stud Layout:
KDOT uses shear studs in both the negative and positive moment regions to effect composite
action. Avoid placing studs at centerline of bearing, offset the stud a minimum of 18 in. to avoid
maximum stress regions. Avoid bolted field splice locations by offsetting the stud from the end of
the splice plate by not less than 6 in. to avoid fit-up conflict. The Contractor will decide to either
6 - 13
Bridge Section
Design Manual
Bridge Section
6 - 14
Design Manual
Bridge Section
6 - 15
Design Manual
Bridge Section
6 - 16
Design Manual
Type
Simple
Span
Continuous
Span
0.040L
0.032L
0.033L
0.027L
Trusses
0.100L
0.100L
Size
Length
PL " x 10"
< 80 ft.
PL 1" x 12"
PL 1" x 15"
To effect economy in steel bridges, the requirements for stress should correspond to the change in
moments. Improved and efficient welding procedures make flange splices more economical.
However, least weight designs mixes a wide variety of sizes and shapes, which is not practical.
The increased labor costs incurred by splicing often more than offsets the material cost savings.
Generally, to simplify fabrication, flange plates should be the same size from field splice to field
splice for spans up to approximately 100 ft. For spans greater than this, a general guide would be
to limit plate lengths to a minimum of approximately 20 ft. In addition, an average of about 1,100
lbs. of flange material should be saved to justify the introduction of a flange shop splice.
If a fabricator requests and receives permission to continue a larger plate rather than use splices
as detailed, or any change effecting geometry or capacity, revise the girder plan details, shop
details and resubmit the required computer model to KDOTs load rating section with an explanation of the changes.
Bridge Section
6 - 17
Design Manual
Field splices should be located close enough to each other so individual pieces will be stable without buckling during lifting and when set in place. As a general rule, the unsupported length of the
field piece divided by the minimum width of compression flange should be less than 85. Girder
segment length and depth should be limited to 120 ft. and 10 ft. respectively with a maximum
mass of approximately 90 tons. Shop capacities of several companies which commonly fabricate
girders for KDOT can be found at the following Internet website: http://www.ksdot.org/burdesign/bridge/fabricator.asp
Proportioning Webs and Flanges:
Reference is made to "Design of Welded Structures" by Omer Blodget, published by Lincoln Arc
Welding Foundation for methods of computing the optimum girder depth. According to the criteria presented, the optimum girder depth would be one-half the weight of steel in the web and
one-half in the flanges. Clearance restrictions in many cases prevent the use of the optimum
depth. Since the composite action of the girder applies only to the live loads, Blodget's procedure
may be used as a guide. Maintain constant flange widths when possible, this reduces the amount
of run-off tabs during fabrication and allows gang cutting.
Web Plates:
Efficient web design requires designers to estimate the cost of using transverse web stiffeners versus the cost of specifying a thicker web plate to reduce the number of stiffeners. One rule of
thumb is to use the 1-2-4 estimating guide. That is, if the girder steel is $1 per pound, then the
cross-frame and diaphragm steel is $2 per pound and the stiffener and intermediate stiffener steel
is $4 per pound.
Note: A trial solution for longer spans use a web thickness 1/16 in. less than required for an unstiffened web. For spans less than 100 ft. in length, use a constant web thickness between field
splices.
Note: Unless unusual conditions exist, use a constant depth web for spans less than 200 ft.
Rolled Beam Member Sizes:
Rolled Beams, unlike plate girders, cannot be tailored to match the stress profile. The designer
will find a series within the AISC beam tables for W sections that match the demand. Beams
within a series have the same overall height so fill plates will be needed only on the interior of
the flange and possibly the web. It is quite common to have the lighter section in the series for the
positive moment region and then step up one or two sizes within the same series for the negative
moment regions. Common beam sizes are W 24 thru W 40, recently a W 44 section has been
made available for use, the designer should call for availability as these shapes are not rolled as
frequently.
Grading for Vertical Curvature and Camber:
The designer will change girder or beam profile by inserting a point of inflection (PI) or kink at
the bolted field splice rather than at a shop splice location. If the kink was allowed at a shop
splice and the fabricator wants to carry the heavier section from field splice to field splice, all the
elevations would have to be recalculated.
Bridge Section
6 - 18
Design Manual
The minimum fillet f for rolled beams or plate girders will be 1 in. to allow for field variations.
Figure 6.4-1 Fillet Depth Computation for Steel Girder
-T
(Slab Thickness)
Bridge Section
6 - 19
Design Manual
6.4.1 Welding
The most common welds for plate girder fabrication are groove and fillet welds. Groove welds for
connecting plates of different thickness are to develop the full strength of the thinner part joined.
The strength of fillet welds is developed in shear and is determined by the effective throat dimension and the weld length. The size of a fillet weld is designated by leg size and the minimum size
shall be 1/4 in.
Fillet welds greater than 5/16 in. require two passes by the automatic welder, which is time consuming and expensive. Most web to flange fillet welds do not need to be greater than 5/16 in. Web
to flange fillet welds greater than 5/16 in. should be verified by design. Depending on the thickness of material, the table below should serve as a guide to determine the size of fillet weld to be
used.
Bridge Section
6 - 20
Design Manual
*MIN. FILLET
WELD SIZE
1/4 in.
5/16 in.
Call out the type of weld on the bridge plans. Do not call out a D1.5 weld procedure. The Fabricator will specify the weld procedure on the shop drawings. This procedure is indicated on the tail of
the weld symbol. Weld procedures are reviewed for acceptance by the KDOT Materials Section.
A compilation of prequalified welds from fabricators is available on the State Bridge Office
Intranet webpage. It is the responsibility of the Bridge Section personnel or its Consultant checking shop details to ascertain if the weld procedures called out are current and match the application. Exceptions to the pre-qualified weld procedures are proprietary items and other items with
Type "D" certification.
KDOT has shown a double bevel weld detail on plates with thickness > in. See Figure 6.4.1-2
Flange and Web Welded Splice Configurations. Modern fabricators can accomplish this weld
using a single bevel weld. KDOT allows the single bevel detail as long as the final product is
acceptable to the KDOT Materials Engineer.
On the weld symbol used for welded girder shop splices, the "G" for grind above the "flush"
contour symbol is not required. The required finish may be obtainable without grinding. Omitting
the "G" does not prohibit the Fabricator from grinding, if grinding is needed to obtain the required
finish.
Material and construction shall conform to the KDOT Specifications and the AASHTO/AWS
D1.5 Bridge Welding Code. Material not covered by the Bridge Welding Code will be covered by
AWS D1.1. This includes structural tubes and other ancillary material used in signing and lighting
structures.
Bridge Section
6 - 21
Design Manual
Bridge Section
6 - 22
Design Manual
Bridge Section
6 - 23
Design Manual
6.4.2Transverse Stiffeners
Intermediate Stiffeners:
Intermediate transverse stiffeners shall be 3/8 in. minimum thickness and welded to the web with
a 1/4 in. minimum continuous fillet weld. The stiffeners will normally be placed on one side of
the web (inside face) and shall be welded to the compression flange and tight fit at the tension
flange. The vertical distance between the end of the stiffener weld and the near edge of the
web-to-tension flange fillet weld shall be no more than six times nor less than four times the web
thickness. Stiffener plates shall be clipped 1 inch horizontally to clear the fillet weld. The welds
shall end 1/2 in. from the clip. If the intermediate stiffeners are used as connecting plates for cross
frames, the stiffeners shall be welded (preferred) or bolted to both flanges and the flange stress at
the stiffener shall be investigated for, See Figure 6.4.2-1 Transverse Stiffener Details.
On welded plate girders, if diaphragms are offset (e.g. a skewed bridge), place the stiffeners in
pairs and attach them to the flanges (interior girders only). This will stiffen the web-stiffener area
and reduce-out-of-plane bending. See Figure 6.4.2-2 Connection Stiffener Details
Bearing Stiffeners:
For all bearing devices provide bearing stiffeners in accordance with Article 6.10.11.2. Without
exception, use bearing stiffeners on both sides of the web on all girders and as close as practical to
the outer edges of the flanges.
The bearing stiffeners shall be tight fit at the top flange and milled (or ground) to bear at the bottom flange meeting the requirements of the ANSI/AASHTO/AWS D1.5 Bridge Welding Code, This
means 75% of the end area of the stiffener shall be "in contact" with the flange. "In contact" is
defined as fitting within 0.010 in. for 75 percent of the projected area with no gap more than 1/32
in. for the remaining 25 percent of the projected area. Bearing stiffeners shall be fillet welded to
the web and to both the top and bottom flange. Welding is required to satisfy the requirement for a
positive connection for stiffeners connected to cross-frames or diaphragms. At the fabricator's
option, the bottom of the bearing stiffener may be welded with a complete penetration weld. This
is typically done for bridges with skew angles greater than 35 degrees.
As an option, the Bearing Stiffener may be bolted to the top flange. This option should only be
used in cases where there is a problem. Bearing stiffeners shall be clipped as described above for
intermediate stiffeners. The total end reaction transmitted to the bearings from maximum factored
design load will not exceed the maximum strength of the bearing stiffener acting as a column and
the fillet weld connecting the web to the stiffener per Article 6.10.11.2.
Bridge Section
6 - 24
Design Manual
Bridge Section
6 - 25
Design Manual
Bridge Section
6 - 26
Design Manual
Bridge Section
6 - 27
Design Manual
Bridge Section
6 - 28
Design Manual
Bridge Section
6 - 29
Design Manual
Bridge Section
6 - 30
Design Manual
Bridge Section
6 - 31
Design Manual
Bridge Section
6 - 32
Design Manual
Bridge Section
6 - 33
Design Manual
Bridge Section
6 - 34
Design Manual
Bridge Section
6 - 35
Design Manual
Bridge Section
6 - 36
Design Manual
Filler Plates:
Bolted flange splices with unequal flange thicknesses require filler plates. Filler plates need not be
extended or developed for friction connections in accordance with Article 6.13.6.1.5. For girder
splices where the thicker flange is equal to or greater than twice the thickness of the thinner flange
an eccentricity of forces exist. This produces a moment couple which may reduce the clamping
force and thus reduce the allowable slip load per bolt as per Article 6.13.2.2. See filler plate sketch
on Figure 6.4.7-2 Fill Plate Extension.
Refer to the following guidelines concerning filler plates:
1. The thickness of fill plate should not exceed the thickness of the thinner flange plate.
2. Fill plates should not be less than 1/8 in. and not more than 1" in thickness.
3. Fill plates on high strength girders need not be high strength steel unless the fill plate needs
to be developed.
4. Fill plates less than 1/2 in. need not meet fatigue requirements.
5. Fill plates less than 1/2 in. used on unpainted weathering (Grade __W) steel girders
shall be painted (prime coat) and need not be weathering steel. Fill plates equal to or
greater than 1/2 in. used on weathering steel girders shall also be weathering steel.
When specifying filler plate material, the following stipulations apply:
1.The minimum thickness of A36 (ASTM A709 Gr. 36 or AASHTO M270 Gr. 36) plate
available is 3/16 in. Thicker plates come in 1/16 in. increments.
2. Sheets less than 3/16 in. are measured using gauge. (11 ga. = 0.1233 in. approximately =
1/8 in.). The sheets are made of ASTM A570 (hot rolled) or ASTM A611 (cold-rolled) steel or
ASTM A1011 (hot rolled).
Bridge Section
6 - 37
Design Manual
BoltDiameter,in.
1
1&1
RangeofGripLengths,in.
1
3/163/8
1
7/165/8
3/163/8
1
11/167/8
7/165/8
5/161/2
2
15/1611/8
11/167/8
9/163/4
7/165/8
2
13/1613/8
15/1611/8
13/161
11/167/8
7/165/8
2
17/1615/8
13/1613/8
11/1611/4
15/1611/8
11/167/8
7/165/8
2
111/1617/8
17/1615/8
15/1611/2
13/1613/8
15/1611/8
11/167/8
3
115/1621/8
111/1617/8
19/1613/4
17/1615/8
13/1613/8
15/1611/8
3
23/1623/8
27/1625/8
115/1621/8
23/1623/8
113/162
21/1621/4
111/1617/8
115/1621/8
17/1615/8
111/1617/8
13/1613/8
17/1615/8
3
3
211/1627/8
27/1625/8
25/1621/2
23/1623/8
115/1621/8
111/1617/8
4
215/1631/8
211/1627/8
29/1623/4
27/1625/8
23/1623/8
115/1621/8
4
33/1633/8
215/1631/8
213/163
211/1627/8
27/1625/8
23/1623/8
4
37/1635/8
33/1633/8
31/1631/4
215/1631/8
211/1627/8
27/1625/8
4
311/1637/8
37/1635/8
35/1631/2
33/1633/8
215/1633/8
211/1627/8
5
315/1641/8
311/1637/8
39/1633/4
37/1635/8
33/1633/8
215/1631/8
5
43/1643/8
315/1641/8
313/164
311/1637/8
37/1635/8
33/1633/8
5
47/1645/8
43/1643/8
41/1641/4
315/1641/8
311/1637/8
37/1635/8
5
411/1647/8
47/1645/8
45/1641/2
43/1643/8
315/1641/8
311/1637/8
6
415/1651/8
411/1647/8
49/1643/4
47/1645/8
43/1643/8
315/1641/8
6
53/1653/8
415/1651/8
413/165
411/1647/8
47/1645/8
43/1643/8
6
57/1655/8
53/1653/8
51/1651/4
415/1651/8
411/1647/8
47/1645/8
6
511/1657/8
57/1655/8
55/1651/2
53/1653/8
415/1651/8
411/1647/8
7
515/1661/8
511/1657/8
59/1653/4
57/1655/8
53/1653/8
415/1651/8
7
63/1663/8
515/1661/8
513/166
511/1657/8
57/1655/8
53/1653/8
7
67/1665/8
63/1663/8
61/1661/4
515/1661/8
511/1657/8
57/1655/8
7
611/1667/8
67/1665/8
65/1661/2
63/1663/8
515/1661/8
511/1657/8
8
615/1671/8
611/1667/8
69/1663/4
67/1665/8
63/1663/8
515/1661/8
8
73/1673/8
615/1671/8
613/167
611/1667/8
67/1665/8
63/1663/8
8
77/1675/8
73/1673/8
71/1671/4
615/1671/8
611/1667/8
67/1665/8
8
711/1677/8
77/1675/8
75/1671/2
73/1673/8
615/1671/8
611/1667/8
9
715/1681/8
711/1677/8
79/1673/4
77/1675/8
73/1673/8
615/1671/8
Note:UseLoadIndicatorWashersforallhighstrengthboltsconnectingmainandsecondarygirdermembersNormally,Thiswould
onlyinclude3/4"&7/8"diameterH.S.bolts.
Bridge Section
6 - 38
Design Manual
Bridge Section
6 - 39
Design Manual
Bridge Section
6 - 40
Design Manual
Bridge Section
6 - 41
Design Manual
Bridge Section
6 - 42
Design Manual
6.4.9 Fatigue
Fatigue cracks are generally classified as either load induced or displacement induced. Load and
stress limits are placed on members to minimize load induced cracks from forming. Proper
detailing practices are used to prevent displacement induced cracks. Designers should check
connections for resistance. Material considerations for member and element will be consistent
with Section 6.2 Materials.
It is KDOTs policy, for all non redundant highway bridges or members which cannot be
inspected after erection, to be detailed for the Fatigue I Limit State, infinite life, regardless
of ADT level. For other structures, where importance and loss of service is deemed critical,
design for infinite life. The designer will discuss the impact of service loss, with the State
Bridge Design Engineer for these application(s).
Detailing practices that prevent displacement induced cracks from forming include:
Positively connecting connection stiffeners to the top and bottom flanges.
Coping longitudinal stiffeners and terminating welds before reaching the end of an element.
Top and bottom transverse stiffeners are typically coped from face of web and from face of
flange. See Figure 6.4.2-1 Transverse Stiffener Details.
When the bridge is skewed greater than 40 degrees, the use of back-up stiffeners on skewed
bridges with non-skewed cross frames can reduce this effect.
Not framing into a hard spot with a cross frame, that is, on skewed bridges with non skewed
cross frames, not having connection at a pier on one end of the cross frame and in the span on
the other end of the cross frame. See Figure 6.3.1-1 Cross Frame for Skewed Bridges for
details.
Detailing practices that help prevent load induced cracks from forming include:
Do not exceed the stress range applicable for a given detail category.
Do not place a shear stud at centerline of bearing but offset by 6 in. to eliminated potential
maximum stress range location.
Where known prone details cannot be eliminated, require Ultra-Sonic Impact Treatment
(UIT) at critical locations. This treatment is done in the field after the full dead load stresses
are imposed.
Provide bolted connections instead of welded connections for critical details within critical
locations.
Do not detail intersecting welds and/or eliminate locations where excessive restraint could
create a bi-axial or tri-axial stress state.
Do not detail intermittent fillet welds in areas of cyclic stress.
Do not terminate welds at the end of connection plates, but hold back 4 to 6 times the thickness of the materials.
Do not wrap welds around plates, the weld will have insufficient throat as it goes around the
corner and will be weakened.
Avoid welding connection plates (stiffeners, gussets or connections) to primary member webs
or flanges without large radius intersections.
Bridge Section
6 - 43
Design Manual
Avoid details where a longitudinal fillet (parallel to the primary direction of stress) is interrupted or terminated.
Figure 6.4.9-1 Stiffener Detail from AASHTO for wind bracing
4 - 6 tw
Bridge Section
6 - 44
Design Manual
Horizontally curved I-shaped girders are suitable for spans of lengths similar to straight plate
girders and are preferred in lieu of tub-shaped girders. The curvature may be achieved either by
cutting the flanges on a curve or by fabricating a straight girder then heat curving. The radius of
curvature should not be less than the requirements of Article 6.7.7.2. A common heat curving
method is a system referred to as "V" heats. When applying this system, the girder must be investigated for overstress and camber loss. Article 6.7.7.3 requires camber loss to be added to a heat
curved girder to compensate for loss of deflection after heat curving due to construction loads and
time, which is usually the first few months of service load. The loss is thought to be due to the dissipation of residual stresses imposed by heat curving. For girders with a radius in excess of 1000
ft., the extra camber may not be required. For radii less than 1000 ft. use the camber formula as
presented in Article 6.7.7.3. In all cases, the fabricator must show his procedure and make the necessary camber correction calculations.
For further guidance on design of curved girders, reference is made to "Highway Structures
Design Handbook" Vol II, U.S. Steel; "Fabrication Aids for Girder Curved with V-Heats" by U.S.
Steel; "Deflection and Camber Loss in Heat-Curved Girders," Transportation Research Board
950.
Bridge Section
6 - 45
Design Manual
Bridge Section
6 - 46
Design Manual
Bridge Section
6 - 47
Design Manual
6.4.12 Paint
New Steel:
Bridge paint systems are limited to three colors. The standard green is the default color for nonweathering steels. Weathering steels default to a brown color. Urban, highly visible or other special bridges may use the blue alternate.
When ever possible use weathering steel for all new structures where appropriate see 6.2 Materials for material call out. Inappropriate locations include salt spray areas within urban regions and
areas where there is less than 2 ft. of freeboard. See 6.4.13 Weathering Steel Guidelines for appropriate usages.
Paint weathering steel as follows: (Painting includes blast cleaning, prime coat, and top coat
unless otherwise noted.)
1) Where girder ends are embedded in the abutment, blast clean and prime coat the entire
embedded portion of the girder, including diaphragms, plus an additional distance of 2 in.
2) Blast clean and prime coat both sides of fill plates less than in. thick. Note: Fill plates
less than in. thick need not be weathering steel.
3) Paint all structural steel surfaces (not included above) within a distance of two times the
depth of the girder (2D) on either side of an expansion joint. A nearby stiffener would be a
convenient location to stop painting.
4) When drainage is allowed over the side of the deck on a plate girder bridge, and the
exterior girder is to be painted: blast clean all surfaces of the exterior girder; prime and
top coat the exterior surfaces, including the bottom of bottom flange, of the exterior
girder only.
5) When drainage is allowed over the side of the deck on a rolled beam bridge, painting the
exterior beam is not required. If a uniform appearance is desired, blast clean the entire
exterior facia of unpainted exterior girders after erection.
Bridge Section
6 - 48
Design Manual
Existing Steel:
Report paint history and toxicity characteristic leaching, and procedure (TCLP) results.
**Contact KDOT Environmental Services shortly after field check to request field
reconnaissance and TCLP sample.
All existing structures which are to be repainted require investigation into the physical paint
characteristics.
KDOT will conduct Toxicity Characteristic Leaching Procedure (TCPL) tests on all existing
bridge repaint and steel bridge removal jobs which have non-lead paint systems currently on the
structure. Note a TCPL test request is required on the Field Check letter. Also note, a TCPL test is
required on the sheet attached to the Field Check letter. Put "TCPL Required" in the "Feature"
field at the bottom of the sheet and then add any Comment in the field to the right.
Definition:
Paint with a lead content less than 0.135 oz/cy (5 mg/l) is not considered lead based paint.
If the results of the toxicity investigation are positive, then include the bid item Environmental
Protection in the plans, otherwise do not include this bid item.
Bridge Section
6 - 49
Design Manual
Bridge Section
6 - 50
Design Manual
Bridge Section
6 - 51
Design Manual
Avoid details serving as water and debris traps. Use drip plates attached to the bottom flange of
a girder to divert water off the structure before it runs onto another bridge component (check ).
See Figure 6.4.13-1 Drip Plate Detail .
Do not use weathering steel in rocker bearing devices (or components with finished surfaces),
expansion devices, or expansion device armoring. Sole plates may be weathering steel when used
with elastomeric expansion devices.
Aesthetically, exposed weathering steel can cause unsightly staining of the substructure concrete.
A majority of the staining occurs during construction after the weathering steel is first erected and
exposed to the weather, and up until the deck concrete has been placed. Therefore, on structures
highly visible (i.e. grade separations), all substructure concrete must be protected during construction. See the Specifications for method of protecting and cleaning substructure concrete.
On structures with less visible substructures, i.e. rural stream crossings, provide grooves in the
bearing seats to direct rust-laden water down the side of the pier/abutment beam in a controlled
manner. Additional reinforcing steel cover will be required to keep proper clearance from
grooves.
Bridge Section
6 - 52
Design Manual
Bridge Section
6 - 53
Design Manual
Bridge Section
6 - 54
Design Manual
Y
> 8 Clear
from still
water
Y
Unpainted
Over water ?
Vertical
clearance
16
Paint
N
Length
> 100
VC
< 18
Y
N
Y
N
Spill thru Abuts
4 Lanes
N
Y
Y
Length
> 100
N
N
Y
Length
> 300
N
> 4 Lanes
= 6 Lanes
> 6 Lanes
8 Lanes
N
Length
> 400
> 8 Lanes
Bridge Section
6 - 55
Design Manual
Bridge Section
6 - 56
Design Manual
6.5 Design
6.5.1 Design: General
All steel bridges will be designed and detailed as fully composite members in both the negative
and positive moment areas for the final conditions. Except where the bridge changes units, steel
bridges will be made continuous for both dead load and live load.
The primary load combinations for steel bridge design are Strength I, Service II, Fatigue I and II.
Strength I for steel is used for flexure, shear, and composite shear stud design.
Service II for steel is used for 1% cut-off, controlling yield and for slip critical connections.
Fatigue I is for infinite life and fatigue II is for finite life .
Steel sections are classified as compact, non-compact. Compact sections may be able to develop
the inelastic resistances without global or local instabilities. Non-compact sections are limited to
elastic capacities equal to or less than the yield fy. The LRFD Specification references inelastic
capacities by moment resistances Mn and elastic capacities by stresses fn.
For composite steel design, when determining stiffness for elastic properties for strength and service limit states, utilize the concrete deck in the positive moment areas by transforming the concrete to an equivalent area of steel using the modular ratio ("n"short-term). In the negative
moment areas use one-third the concrete deck (3nlong-term) or the effective slab reinforcing
steel whichever is larger.
Bridge Section
6 - 57
Design Manual
Bridge Section
6 - 58
Design Manual
I yc
D
b f ---- t f 1.1t w and 0.1 ------ 10
6
I yt
where:
I yc, I yt = moment of inertia of compress or tension flange about the vertical axis in the plane of
the web.
b f, t f = width and thickness of the flange.
Bridge Section
6 - 59
Design Manual
6.5.2.1 Axial
Axial superstructure forces are generally ignored because bearing devices are detailed to translate
freely or, in the case of adjacent bolstered piers, the columns will creep off the superstructure
axial loads by deflecting. Because there is a need to eliminate joints in favor of abutments with
integral or semi-integral connections, there is the possibility that at some point the flexibility at
the abutment could increase. Mud jacking or changes in geotechnical properties may cause unintended axial forces. Rolled beams are more robust and better equipped to absorb this force when
compared to plate girders. For plate girders the designer will investigate the need to add lateral
bracing and/or stiffeners near the abutments to overcome the passive resistance at the abutment.
V n = V cr = CV p
V p = 0.58F yw Dt w
C = ratio of shear buckling to capacity per Equations 6.10.9.3.2-4, 5 and 6
Bridge Section
6 - 60
Design Manual
Interior Panels:
The nominal resistance is
(1 C)
V n = V p C + 0.87
---------------------------do 2
1 + -----
D
when the post-buckling is satisfied by
2Dt w
---------------------------------- 2.5
( b fc t fc + b ft t ft )
otherwise use
0.87 ( 1 C )
V n = V p C + -------------------------------------------d o 2 d o
1 + ----- + ---- D
D
Where:
do= transverse stiffener spacing
tw = web thickness
bft or fc= flange width (tension or compression)
tft or fc= flange thickness (tension or compression)
Transverse Connection and Shear Stiffeners: Article 6.10.11
The stiffener width will satisfy Article 6.10.1.2. The minimum plate thickness shall be 5/16 in. for
all stiffeners except bearing stiffeners.
Design the sections so that V u is not greater than V cr at either panel support then:
The moment of inertia shear stiffeners will be the lesser of:
It =
3
bt w J
4 1.3
D t F yw 1.5
or I t = ---------------- ---------
40
E
Bridge Section
6 - 61
Design Manual
Where:
b = smaller of d0 or D
t = smaller of Fyw/Fcrs or 1.0
2.5 - 2.0 0.5 and F = 0.31E
-------------- F ys
J = -------------------cr
2
2
b----t
( do D )
t
Longitudinal Stiffeners:
2D c
Longitudinal stiffeners should be located --------- away from the compression flange as a first trial,
5
and be designed per Article 6.10.11.3
Bearing Stiffeners:
Bearing stiffeners shall transfer load to the flanges of rolled beams or plate girders using either
mill to bear and fillet welding to the flanges or full penetration flange welding.
Bearing stiffeners will be designed per Article 6.10.11.2.
Bridge Section
6 - 62
Design Manual
by using frames placed along the skew, for bridges up to 40 degrees, and making the frames continuous in all bays.
6.5.5 Fatigue/Fracture
Fracture:
Fracture toughness or notch toughness is the ability of a material with a flaw to absorb energy
without uncontrolled or unstable crack growth at a given temperature. Material toughness does
not prevent cracking, good detailing combined with appropriate live load stress range prevents
cracking.
All primary members with tensile stress due to Strength I Limit State shall comply with Section
6.2 Materials for fracture toughness requirements. Refer to Table 6.6.2-2 for additional criteria
for non-redundant members.
Intersecting welds will be eliminated from use on KDOT structures. Weld intersections create biaxial or tri-axial restraint conditions (ref: Hoan Bridge Failure) which do not allow the material to
yield. Brittle conditions can be created in ductile materials due to poor detailing or construction.
Stress Induced
There are two limit states within the LRFD specifications, I and II. I is intended for infinite life
and II is for finite life.
It is KDOTs policy to design for the I Limit State for all non redundant highway bridges or for
structures with members that cannot be inspected after erection, regardless of ADT level.
Avoid details E or E as shown in Table 6.6.1.2.3-1 or move detail to areas on the structure where
the net effect of stress is in compression. If this cannot be done the designer will consider using
Ultra Sonic Impact Treatment (UIT) in the field after the full dead load is on the structure to
improve the detail. UIT treatment improves the weld detail by imposing a residual compressive
force on the surface, and smoothing the transition from weld to base metal, extending the time to
crack initiation.
Distortion Induced
Members which intentionally or unintentionally provide load transfer must be positively connected. In the past, lack of connectivity for members which transfer load by moving relative to
one another caused cracks to form in the web of many structures. Traditional 1-D girder analysis
will not check for these conditions. It is the designers responsibility to check relative movements
and determine the stresses which are limited to Article 6.6.1.3. In-lieu of doing a 2-D analysis the
designer will detail the connection to resist a 20 kip force per Article 6.6.1.3.1.
Bridge Section
6 - 63
Design Manual
Bridge Section
6 - 64
Design Manual
Bridge Section
6 - 65
Design Manual
Steel box girders are an alternative type of welded steel-plate girders. The steel box girders are
advantageous because they provide improved structural strength and appearance. From a structural viewpoint, box girders offer the advantage of a more efficient cross section for resisting torsion over plate girders. The improved torsional rigidity allows distribution of the live loads more
uniformly to all girders supporting the deck and also makes the box section particularly advantageous for curved bridges. The wide bottom flange makes a shallow construction depth economically feasible.
Steel box girders are shop welded. If aesthetics are important, the field connections of the girders
should be welded. The secondary members may be welded or bolted. Top lateral bracing near the
piers may require bolted connections to satisfy fatigue behavior. For curved girders, some of the
holes may need to be slotted to aid in fit-up. Diagonal and cross bracing should be installed in the
shop to protect the girder during shipping and erection.
It is KDOT Bridge policy to avoid the use of unpainted weathering steel for this application. If a
rustic tone is desired to blend with the surroundings, the bridge should be painted with an inorganic zinc coat and a field acrylic or polyurethane finish coat to match the desired color.
Composite box girders are designed with two web plates, both of which are either vertical or
inclined, or sometimes vertical and inclined combined. A 3/8" plate should be the minimum plate
thickness for this application. Inclined webs, besides offering pleasing aesthetics, allow the bottom flange plate to be narrower and thicker, thus providing more efficient bottom flanges. In continuous box girders, to prevent buckling of the bottom flange, longitudinal stiffeners may be
added in the negative moment region. Webs of box girders are similar to plate girders, the girder
webs may be stiffened transversely or both transversely and longitudinally. Theoretically, the steel
top flanges for the composite girders need not be wider than required to provide adequate bearing
for the concrete deck and to allow sufficient width for welding shear connectors to the flanges.
However, loads during fabrication, shipping and erection must be considered. Generally, the minimum top flange plate should be 12" x 3/4".
Box girders differ from plate girders, the cross bracing between webs is concealed within the box
section. Internal diaphragms or cross frames are required within the box girder at each support to
resist rotation, displacement and distortion of the cross section. Also, diaphragms or cross frames
may be designed at other locations to stabilize the box girder for handling and erection. For continuous spans, cross frames are usually provided on each side of a field splice. A length of approximately 120 feet and a weight of about 90 tons are two maximums for sections, this can usually be
handled efficiently either in the shop or in the field. Other circumstances may place further
restrictions on the maximum size and weights of sections for a particular project.
Although the box girders are designed using three steel sides with the composite concrete deck to
complete the enclosure, the girder should not be considered impervious to moisture and the inside
surfaces should be protected. The inside surfaces of the box girder should be painted with a 6-mil
(two coats) zinc coating. The contract plans should show the option of providing either two coats
of inorganic paint with the second coat applied more than 3 hours and less than 24 hours after the
first coat or one shop coat of inorganic zinc and a field coat of organic zinc paint. The final coat
Bridge Section
6 - 66
Design Manual
should provide a light surface to aid visibility for periodic field inspection. Also, provision for
inspection of the interior is a requirement.
In designing a composite box girder with a vertical axis of symmetry, each half of the cross section may be considered equivalent to a plate girder section. Therefore, the principles of composite
design for I-beams and plate girders may be applied to the box girder. For the composite box
girder, the deck slab spans from web to web of each girder and between the webs of adjacent girders. Stay-in-place forms should be specified to span the open top of the steel box girders. This has
an advantage of providing temporary lateral support against buckling of the compression flange
during concrete placement. Also, when unremovable timber forms are used, clutter exists and creates a nuisance during future inspections. Welding to the structure of supports for the
stay-in-place forms should not be permitted. A system of angles with straps across the flange
should be used to provide support to the stay-in-place forms. When using forms with corrugations, the transverse reinforcing steel should be located and spaced so the bars lie directly over the
valleys in the form. Usually the forms are placed perpendicular to the girder flanges. On curved
and skewed bridges the bar spacing and corrugation spacing may not coincide. For these cases
and particularly when additional concrete weight is unacceptable, forms with a flat soffit to cover
the corrugations should be considered. The deck slab usually cantilevers beyond the outer webs of
the exterior girders. Therefore, the slab may be designed in the same manner as for a series of
plate girders with composite construction throughout the length of the girders. Spherical or pot
bearings should be considered for bearing devices to support the box girders. For box girder
bridges up to 300 feet in total length, the bridges may be designed with monolithic abutments.
However for bridges curved or with an extreme skew, lengths of less than 300 feet may preclude
the use of monolithic abutments.
Bridge Section
6 - 67
Design Manual
shown on the erection plans. Points of counterflexure are not considered braced points for the calculation of unbraced lengths. Only bracing locations where Kl/r for the bracing member does not
exceed 22 is considered as braced.
Stock piling construction equipment, materials or debris on partially completed structures will not
be allowed without having a previous evaluation and being shown on the erection plans.
Torsional analysis of the exterior girder is required when overhang brackets are used.
During plan development the designer should estimate the screed load using typical screed information (see attached) and run KDOTs TEAG. If the analysis shows more than two temporary
supports are required, See "B" below. If the analysis shows that two or less additional transverse
supports are required, See "A" below. If the analysis shows no temporary supports are required,
show estimated screed load.
A. Add a note below the Loading Diagram:
"Provide temporary bracing at the top and bottom flanges of the exterior beams during concrete
placement of the deck. The temporary bracing and labor for installation is subsidiary to the bid
item, "Concrete (Grade 4.0)(AE)(XX)". Details for proposed temporary bracing shall be submitted with the falsework plans."
The Contractors Engineer should run TEAG to determine if additional supports are required.
B. Reduce the diaphragm spacing or add additional diaphragms in the exterior girder bays. If the
structure is wide, adding additional diaphragms in the exterior bays may be the most cost effective.
If bolt slip is the issue, provide 7/8" dia. Bolts instead of " dia. and a Class B splice instead of a
Class A splice. If the bolts do not slip into bearing; the bridge would have some rebound of the
girder rotation after the passing of the screed.
For rolled beams, the permanent bent plate diaphragms could be greater than the depth of the
beam, but remember to allow sufficient room for formwork to be placed and to keep their spacing
less than 25 ft..
Check the stability and stresses on the incompleted framed structure without the deck or other
missing members per the erection plan to determine if temporary lateral bracing is required; per
Article 6.10.1.6 and/or Article 4.6.2.7 and check Strength III with the 1.25 factor on the wind per
Article 3.4.2.1.
Falsework:
See Chapter 5 in the LFD KDOT Bridge Design Manual.
Pouring Sequence:
KDOT has decided to use single course deck slabs instead of our past practice of using overlaid or
two course deck slabs. The pouring sequence must be known at the time of shop plan review,
Bridge Section
6 - 68
Design Manual
prior to fabrication. If the designer had intended all the positive moment concrete would be placed
followed by the pier placements and the contractor decided to use a different placement the grading (fillet heights) would be incorrect. The contractor must submit and/or coordinate with the fabricator if the plan pouring sequence will not be used.
For a continuous structure the pouring sequence on a steel bridge must either place concrete in the
positive moment areas first and follow with the negative or place concrete continuously over a
number of supports and stop at the inflection point before the pier to prevent cracking the newly
placed concrete. To resume a pour on a continuously placed pour an analysis must be done to
determine the stresses over the piers on the previously placed sections.
A concrete placement or removal sequence will verify a positive reaction at the supports. At all
stages of construction the designer will consider the effects of uplift. Uplift is considered an
uncontrolled or destabilizing effect and should be eliminated. Temporary restraints may be used
to control uplift.
Slip Condition:
The designer will check all conditions of field erection that may cause joints to slip and go into
bearing. The erection plan will clearly illustrate the number of drift pins and fully tightened bolts
at each connection location. Snug tight bolts will not be used when calculating incept slip conditions.
Bridge Section
6 - 69
Design Manual
References:
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
Bridge Section
6 - 70
Design Manual
Bridge Section
6 - 71
Design Manual
Bridge Section
6 - 72
Design Manual
Bridge Section
6 - 73
Design Manual
List of Figures
Figure 8.1-1 Prestress Beam Protection. ........................................................................................2
Figure 8.3-1 Kinematic wave formulation Chart #1 .......................................................................9
Figure 8.3-2 Scupper Requirement Nomograph ...........................................................................10
Figure 8.3-3 Bridge Deck Drainage (8" x 6" Scuppers) ...............................................................15
Figure 8.4-1 Chart #2 - Velocity in triangular gutter sections ......................................................19
Figure 8.4-2 Chart #7 - Grate inlet frontal flow interception efficiency ......................................20
Figure 8.4-3 Chart #8 - Grate inlet side flow interception efficiency ...........................................21
Figure 8.4-3 P-1-7/8 and P-1-7/8-4 grates ....................................................................................22
Figure 8.4-4 Example #2 - Grate Inlet Capacity ...........................................................................24
Figure 8.4-5 Bridge Deck Drainage (1x 3 Grates) .....................................................................25
Figure 8.5-1 Inlet detail showing formed blockout under inlet box .............................................27
Figure 8.5-2 Example: Grate Inlet on Steel Girder Bridge ...........................................................28
Figure 8.5-3 Example: Grate Inlet on Steel Girder Bridge ...........................................................29
Figure 8.5-4 Example: Grate Inlet on Steel Girder Bridge ...........................................................30
Figure 8.5-5 Example: Grate Inlet on Prestressed Girder Bridge .................................................31
Figure 8.5-6 Example: Scupper on Steel Box Girder Bridge .......................................................32
Figure 8.5-7 Example: Scupper on Prestressed Bridge ................................................................33
Figure 8.5-8 Example: Scupper on Steel Girder Bridge ...............................................................34
Figure 8.5-9 Example: Scupper on T-Girder Bridge ....................................................................35
Figure 8.5-10 Typical Drainage System Details ...........................................................................36
Bridge Section
8-i
Design Manual
Bridge-deck drainage systems are a continual maintenance problem; therefore, the designer
should eliminate drains on bridges when they are unnecessary. A drain-free bridge may be
achieved by using open bridge rails. Where curbs are required, the designer can take advantage of
the shoulder section provided on most of todays bridges by using it as a gutter. If the runoff coming to the bridge is removed before it runs onto the bridge, the hydraulic capacity of the shoulder
may be great enough to eliminate the need for bridge drains on short bridges.
Inlet structures located immediately off the end of the bridge should be designed in collaboration
with the road section to determine when and where they are needed. This coordination also helps
to avoid conflicts with other bridge or roadway structures such as guard fence posts which could
interfere with the drainage flow.
Short continuous span bridges, particularly overpasses, may be built without inlets on the bridge
and the water carried downslope by a flume or inlet structure near the end of the bridge. An open
flume down the sideslope or foreslope is preferred because the concrete flume is more accessible
for maintenance and repair.
On long bridges, drainage should be provided by scuppers or grates of sufficient size and number
to adequately drain the gutters and limit the encroachment of water in the driving lanes.
On bridges containing open-type expansion devices, drains should be located to pick up as much
drainage as possible before it crosses the device. Glands shall be placed in finger devices to carry
drainage; however maintenance cleaning of these troughs and other inlets and grates may be
limited. Drainage design and details should provide the necessary hydraulic capacity with a
minimum of required maintenance. Conservative assumptions of hydraulic capacity is encouraged to provide drainage operation based on limited maintenance. (50% inlet efficiency is a good
rule.)
Coat the top of Prestressed Beams with Substructure Waterproofing Membrane where the deck
drains are located to prevent leaks from compromising the member.
Bridge Section
8- 1
Design Manual
Bridge Section
8- 2
Design Manual
8.2 Design/Procedures
8.2.1 Design Spread and Rainfall Frequency
The purpose of the bridge-deck drainage system is to remove rainfall-generated runoff from the
bridge deck before it encroaches onto the traveled roadway to the limit of the design spread, (T).
For Kansas Interstates and Freeways (A and B routes) with two or more lanes in one direction,
drains may be spaced so the top width of flooding (T) is preferably not more than 10 feet but in no
case shall encroach more than one half of a thru lane. For urban areas where high volume rush
hour traffic must be considered, the designer should consider a design spread (T) which will
exclude all lanes from flooding. For two lane B, C, D and E routes, the traffic lanes in each
direction should not be restricted to less than 10 feet. On superelevated bridges, the depth of flow
in the gutter should be restricted to 9 inches.
The design of A and B routes should be based on a 10 year frequency storm. ForC, D
andE routes, a 5 year frequency storm is adequate.
Use a 50-year frequency storm for all bridges located in the sag vertical curve where ponded
water can be removed only through the storm-drain system.
cia
Q
c
i
a
=
=
=
=
The rainfall intensity used in the Rational Equation is selected for a duration equal to the time of
concentration for a particular drain. The time of concentration ( t c ) is the time required for the
runoff to reach the drain from the furthest point of the drainage area.
To estimate t c , apply the Kinematic Wave equation:
0.6 n 0.6
t c = 56L
-------------------------i 0.4 S 0.3
Bridge Section
8- 3
Design Manual
Where:
tc
L
n
i
S
=
=
=
=
=
The solution is one of trial and error. Estimate the location of a drain to get L and select i for an
assumed 5 minute storm from the Rainfall Intensity Tables for Kansas. (If Kansas Rainfall Intensity Tables are not available, refer to Appendix A of HEC 12 (1984) for development of intensityduration-frequency curves using NWS HYDRO-35 maps.) Reiterate until the assumed storm
duration equals the computed t c . If t c is less than 5 minutes it is KDOT policy to use the 5 minute storm for the design of bridge drains. The maximum intensity need not exceed 6 inches per
hour. (Experience has shown when the intensity of rainfall exceeds 6 inches per hour, a drivers
vision becomes substantially obscured because the capacity of the windshield wipers is exceeded.
Operational speed is therefore voluntarily reduced and the probability of hydroplaning is
less.)(Ref.1)
Bridge Section
8- 4
Design Manual
1/2
8/3
K Sx S T
Q = ----------------------------------------n
Where
K
Sx
S
T
n
Q
=
=
=
=
=
=
a constant (0.56)
cross slope (road crown slope), ft./ft.
road grade, ft./ft.
top width of flow, feet
0.016
flow rate, cubic feet/second
and
nQ
T = -------------------------------5/3 1/2
K Sx
S
3/8
References:
For additional information on pavement drainage refer to:
1)
2)
3)
4)
Bridge Section
8- 5
Design Manual
2)
Problem:
Design scuppers in Area I for a 500-foot interstate bridge located in Johnson County, Kansas, based upon the following information:
Bridge Section
8- 6
1.
Design Manual
Find the distance from the PC to the high point of the curve.
a)
b)
k (a constant) =
A- = ------------1.5 - = 0.075
-----2L
2 ( 10 )
(L in stations)
c)
d)
A
---- = 1.5
------- = 0.150
L
10
g
+ 1.00 - = 6.667 Sta.
Location of high point: xt = -----1- = -------------------2k
2 ( 0.075 )
P.C. Sta. =
95 + 00
+ 6 + 66.7
101 + 66.7 = Sta. of high point
Allowable spread:
= + 10 - (0.150)(97.50 - 95.0)
= 0.625% = .00625 ft./ft.
Bridge Section
8- 7
2.
Design Manual
Need to determine Rainfall Intensity (i) which depends on the storm duration
(which is equal to the time of concentration) and to the recurrence interval.
The time of concentration may be estimated from Chart 1, Figure 8.3-1 Kinematic wave
formulation Chart #1or from the Kinematic Wave Equation:
0.6 n 0.6
t c = 56L
-----------------------i 0.4 s 0.3
Assume tc = 5 min., then for Johnson Co. and a 10-year storm, i = 9.11 in/hr. (from Kansas
Rainfall Intensity tables. 1981)
@EWS:
0.6
0.6
L=
=
=
24393.6
------------------Cn
Sx S T
--------------------------------iw
1.67
0.5
2.67
( 0.0156 ) ( 0.00625 ) ( 10 )
------------------------------------------------------------------------------6(35.33)
Bridge Section
8- 8
Design Manual
Bridge Section
8- 9
Design Manual
Bridge Section
8 - 10
3.
Design Manual
2.67
2.67
Find distance to first scupper from high point (where spread reaches 10-0).
Since S is variable;
L = (16.94 x
105 )
1.67
2.67
(------------------------------------------------0.0156 )
( 10 ) - 0.5
S
212
L = 3,590 S0.5
Use trial and error to get distance from high point equal toL from formula.
Station
100+66.7
100+16.7
99+66.7
Distance from
High Point
100
150
200
Computed L
0.0015
0.00225
0.0030
139
170
197
0.0028
190
(Close enough)
187
Bridge Section
8 - 11
Where:
c=
i=
a=
Design Manual
0.9
6.0 in./hr.
WL----------------= drainage area in acres
43, 560
35.33 (L + l 1 )
0.9 (6.0) x ---------------------------------- - 0.14 cfs
43, 560
0.56
also, QR2 = ---------- Sx 1.67 S2 0.5 t2.67
n
=
0.56
------------- (0.0156)1.67 S2 0.5 t2.67
0.016
29.745Q R2
solving for t = -------------------------0.5
S2
0.375
0.375
Bridge Section
8 - 12
Design Manual
0.375
0.375
The number of scuppers required by the above procedure should be considered a minimum. The final scupper spacing still requires some engineering judgement.
Allowance should be made for the inevitable clogging of scuppers with debris. A factor of
safety of two has been suggested. Scuppers should also be spaced to clear piers and facilitate construction.
Bridge Section
8 - 13
Design Manual
Drainage from scuppers in the end span would fall on the berm so the berm are to be
protected by slope paving, dumped rock or drain troughs.
If drainage cannot be discharged thru vertical downspouts, and a drainage system is
required, it may be more economical to use grates located near piers supporting the downspouts.
Drainage off the end of the bridge needs to be picked up by a grate inlet or by a concrete
flume directing the flow down the side slope.
See Bridge Deck Drainage (8" x 6" Scuppers) sheet, Figure 8.3-3 Bridge Deck Drainage
(8" x 6" Scuppers) for final scupper spacing.
Bridge Section
8 - 14
Design Manual
Bridge Section
8 - 15
Design Manual
Compute Eo:
Eo
Eo
Qw
Q
W
T
=
=
=
=
=
=
for
b)
Qw / Q = 1 - (1 - W/T) 2.67
ratio of frontal flow (flow passing over the grate) to total gutter flow.
flow in width W, cfs
total gutter flow, cfs
width of depressed gutter or grate, ft.
total spread of water in gutter, ft. (max. 10)
W = 2,
W = 3,
W = 4,
Eo = 0.449
Eo = 0.614
Eo = 0.744
Find Rf factor, which is the ratio of frontal flow intercepted to total frontal flow.
Rf = 1 - 0.09 (V - Vo)
V = Velocity of flow in gutter
Bridge Section
8 - 16
Design Manual
Vo = 3.0
Vo = 3.8
Vo = 4.7
Find Rs factor, which is the ratio of side flow intercepted to the total side flow.
Rs =
1
1 + 0.15 V1.8
Sx L2.3
L = 1,
L = 1.5,
L = 2.0,
Rs = 0.043
Rs = 0.102
Rs = 0.180
Bridge Section
8 - 17
Design Manual
Compute efficiencies for the various grate sizes listed below: E = Rf Eo + Rs (1 - Eo)
L
1
1
1.5
1.5
2
2
x
x
x
x
x
x
Rf
2
3
2
3
2
3
1
1
1
1
1
1
Eo
Rs
0.449
0.614
0.449
0.614
0.449
0.614
0.043
0.043
0.102
0.102
0.180
0.180
0.473
0.631
0.505
0.653
0.548
0.684
Due to the rather flat grades with resulting low gutter velocities, the more efficient grates
are wider, narrow ones. Even though the chart shows the 2 x 3 grate to be the most efficient for this particular example, the 1 x 3 grate appears to be the most cost effective since
reducing the inlet size by 200 percent, only decreases the grate efficiency by 8 percent.
Bridge Section
8 - 18
Design Manual
Bridge Section
8 - 19
Design Manual
Bridge Section
8 - 20
Design Manual
Bridge Section
8 - 21
Design Manual
Bridge Section
8 - 22
2.
Design Manual
Bridge Section
8 - 23
Design Manual
Bridge Section
8 - 24
Design Manual
Bridge Section
8 - 25
Design Manual
Bridge Section
8 - 26
Design Manual
Figure 8.5-1 Inlet detail showing formed blockout under inlet box
Bridge Section
8 - 27
Design Manual
Bridge Section
8 - 28
Design Manual
Bridge Section
8 - 29
Design Manual
Bridge Section
8 - 30
Design Manual
Bridge Section
8 - 31
Design Manual
Bridge Section
8 - 32
Design Manual
Bridge Section
8 - 33
Design Manual
Bridge Section
8 - 34
Design Manual
Bridge Section
8 - 35
Design Manual
Bridge Section
8 - 36
Design Manual
9 DECK SLAB
Table of Contents
9.1 General .....................................................................................................................1
9.2 Protection for Bridge Decks .....................................................................................2
9.3 Use of Epoxy-Coated Reinforcing Steel ..................................................................3
9.4 Design Considerations: ............................................................................................4
9.5 Design Information for Concrete Deck ....................................................................5
9.6 Design Procedure and Practice (Main Reinforcement Perpendicular to Traffic) ....6
9.7 Details of Reinforcement for Deck Slabs ...............................................................11
9.7.1 Reinforcement for Deck Slabs ...................................................................................13
List of Tables
Table 9.2-1 Deck Protection ...........................................................................................................2
Table 9.5-1 Deck Criteria ...............................................................................................................5
List of Charts
Chart 9.13-1 One Course 8.5 in. Deck Slab ..................................................................................20
Chart 9.13-2 One Course 8 in. Deck Slab .....................................................................................21
Chart 9.13-3 One Course 8.5 in. Deck Slab ..................................................................................22
Chart 9.13-4 Two Course 8.5 in. Deck Slab .................................................................................23
List of Figures
Figure 9.7-1 Transverse Reinforced Slab .....................................................................................12
Figure 9.7-2 Corral Rail Post Detail ............................................................................................12
Figure 9.8-1 Thermal Effect at Abutments ...................................................................................13
Figure 9.13-1 Slab Reinforcement for Bridges w/Standard Roadways ........................................18
Figure 9.13-2 Standard Deck Slab Prestress Girder Bridges ........................................................19
Figure 9.14.1-1 Fillet Detail (Steel Beam) ...................................................................................24
Figure 9.14.1-2 Fillet Detail (Prestressed Girder) ........................................................................25
Figure 9.14.1-3 Fillet Reinforcement ...........................................................................................26
Figure 9.15-1 AASHTO Table A4-1 ............................................................................................30
Figure 9.15-1 Maximum Reinforcement ......................................................................................33
Bridge Section
9-i
Design Manual
List of Appendixes
Appendix A Overhang Design: Corral Rail ..................................................................................40
Appendix B Overhang Design: Barrier Rail .................................................................................46
Appendix C MathCadd Document for Deck Slab Design ............................................................51
Appendix D MathCadd Document for Deck Panel Design ..........................................................57
Bridge Section
9 - ii
Design Manual
9 DECK SLAB
9.1 General
The information in this section pertains to concrete bridge deck structures which have the primary
direction of reinforcement perpendicular to the direction of traffic. All concrete bridge decks supported by girders, beams, and stringers will have the primary direction perpendicular to the direction of traffic. This section is based on the fourth edition LRFD bridge design specifications.
Unlike the LFD Standard Specifications equations for determining live load force effects, the
LRFD design live load moments can be obtained directly from Figure 9.15-1 AASHTO Table A41 within the AASHTO-LRFD specifications. When using Table A4-1 for positive and negative
moments the actual girder spacing is used. This is a change from traditional LFD designs, for positive moments, which used the effective slab span with assumptions of simply supported members
and a continuity reduction. Likewise, a reduced negative moment at the design section, replaces
the effective slab span length previously used. An example design for a concrete bridge deck
design is included within this section. Also, design guides with the Area of Steel vs. Actual Girder
Spacing have been developed for HL-93 loading for both positive and negative moment reinforcement; these charts will aid in the understanding of the loading conditions. KDOT will continue to use the effective span length for both positive and negative dead load moment force
effects for deck slab design. Following the deck slab example a Mathcadd document has been
developed for both deck slab design and prestressed panel design.
The crack control equations have changed from the "Z" checks used in the past, which was used
in conjugation with an assumed 2 in. maximum cover. The current equation, in the fourth edition,
use an exposure factor and the actual stress in the rebar. Unfortunately, there are similar limitations for thin members like deck slabs. Therefore, until corrections are made to the specifications
it will be KDOTs policy to use a 2 in. maximum cover + bar diameter for dc in the equations
found in Article 5.7.3.4
In addition to designing the bridge deck for the dead and live loads at the strength limit state and
service limit states, the AASHTO-LRFD specifications require designing for extreme limit states
considering vehicular collision with the railing system. The resistance factor at the extreme limit
state is taken as 1.0. This signifies that, at this level of loading, damage to the structural components is allowed and the goal is to prevent the collapse or, in this case, failure of the deck overhang.
Traditionally, the deck overhang and the interior sections of the deck are designed separately. The
negative moment reinforcing steel in the overhang is checked against the negative moment
requirements over the girder and the controlling location is used for the entire deck width. The
general analysis for the overhang, as presented in Section A13.4 of the AASHTO-LRFD Specifications, is summarized in Appendix A-1 and A-2. These appendices show the modeling of the
girder\deck\rail components as a system using finite elements. General design guidelines for cases
adhering to the limits of the modeling are presented and can be used without additional modeling.
Bridge Section
9- 1
Design Manual
Maintenance
*
Standard: Non
Metro Areas
Metro Areas
***
Minimum total
deck thickness
8 in.
8 in.
8 in.
Decks: One
Course
----
Gr 4.0 (AE)(SA)
(3 in. clear)
Gr 4.0 (AE)(SA)
(3 in. clear)
Surface Preparations
N/A
Overlay
N/A
N/A
Gr 4.0 (AE)(SA)
(3 in. clear)
Gr 4.0(AE)(SA)
(3 in. clear)
Gr 5.0 (AE)(PB)
Gr 5.0 (AE)(PB)
Gr 5.0 (AE)(PB)
***Note: To be decided at field check. In general, if the structure will have limited access after
construction or cause significant delays or is requested by District Staff, then overlay as new
structure, otherwise, it will be applied as a maintenance operation later.
** Prestressed panels will not be used without prior approval by the State Bridge Office
* Maintenance work can have variations, dimensions may change based on conditions.
(AE) = Air Entrained
(SA) = Structural concrete with select course aggregate for Wear and Absorption.
(OL) = 1 in. Portland Cement Concrete Overlay
(PB) = Structural concrete with select aggregate for use in Prestressed Panels.
Bridge Section
9- 2
Design Manual
Use special aggregate for all concrete placed with the superstructure concrete and/or concrete
above the bridge seats.
As mentioned, the use of silica fume overlays has been eliminated in favor single course decks.
Two course deck construction has been shown, by research, to have significantly higher crack
density and overall lower long-term performance. A one course deck with 3 in. of cover, properly
placed and cured has been shown to have fewer settlement and shrinkage cracks. Improvements in
the type, length and timing of the deck cure, after placement have been thoroughly researched and
are key factors in the long-term deck performance. This is further enhanced by the use of multilayer polymer concrete overlay, the polymer effectivly waterproofs the deck reducing the effects
of chloride intrusion and freeze-thaw. Durable seeding (flint rock from Oklahoma) within the
overlay adds significant friction eliminating the need for tining. It is estimated that the polymer
overlay will last 10 years at which time a additional overlay and seeding material will be installed
without the need for milling the surface. This overlay can be completed within a few days having
the structure back in service quickly.
Additionally, plastic tining and/or excessive finishing are being replaced by minimal finishing followed by rapid cover with wet burlap (max 15 min.) and diamond tining the groves after the cure.
The bid item Bridge Deck Grooving , measured by the square yard, has been created for single
course decks without multi-layer polymer overlays. This bid item is not included for bridge decks
with polymer overlays or for single course decks on gravel roads, such as on local projects structures. Where the bid item Bridge Deck Grooving or Polymer Overlay is not included the
Contractor will use a coarse burlap drag to roughen the deck.
The multi-layer polymer concrete overlay is considerd to have a nominal thickness and a nominal mass and will not be considered for the design or grading of deck slabs.
Bridge Section
9- 3
Design Manual
Bridge Section
9- 4
Design Manual
can be used directly if the assumptions and limitations listed at the beginning of the appendix are
fully met. Dynamic allowance and multiple presence factors are already included in this table.
Distribution steel, which provides for the proper distribution of load in the secondary direction, is
taken as a percentage of the primary direction reinforcement in the positive moment region
between the girders. The design of the distribution steel for the entire bridge shall be based on the
widest girder spacing found on the structure.
Skew effects are to be considered per Article 9.7.1.3. The effectiveness of the reinforcement is
reduced as the skew increases to the maximum allowed by KDOT for rebar placed parallel to the
skew. For structures skewed less than 25 the primary reinforcement should be parallel to the
skew. For skews greater than 25 the reinforcement should be investigated for the reduced effectiveness. For construction purposes KDOT allows reinforcement to be placed in the skew up to
35.
The minimum reinforcing bar clearance for top bars must meet the requirements for bridge deck
protection (9.2 Protection for Bridge Decks). For the bottom reinforcement, the bar clearance
shall be 1 in. This is a change from the past KDOT policy because the maximum aggregate size
in the future will be 1 in.
The structural depth of concrete slabs, for Strength Limits States, shall be reduced by in. for all
decks to account for long-term wear and deterioration under service conditions. This is a change
in KDOT design practice; see Chapter 4 for load rating information. The above information is
summarized in the Table 9.5-1 Deck Criteria.
On bridge decks that are built by two-stage construction (sub-deck and wearing surface), the
designer should evaluate the load carrying capacity of the subdeck to determine whether or not it
will support the legal loads, construction equipment loads, material stockpiles or any other applicable load. Stresses in the concrete and reinforcing steel resulting from these loads should be limited to fc = 1,600 psi and fs = 24,000 psi, respectively. Legal loads will not be permitted on the
subdeck until a minimum of 14 days has elapsed from placing the final pour. The design should
be analyzed by comparing the capacities to the force effects in Article Table A4-1 multiplied by
10/16 to prorate the values to the 10 kip legal load.
Bridge Section
9- 5
Design Manual
For negative moments and shear forces, location of the design section from the centerline of the
girder shall be per Article 4.6.2.1.6.:
For steel I-beams and steel tub girders use one-quarter the flange width from the centerline of
the support.
For precast I-shaped concrete girders and concrete boxes use one-third the flange width but
not exceeding 15 in.
Material Properties and Loading:
Method = Traditional Design Method in Article 9.7.3
Grade 4.0 Concrete: fc = 4,000 psi
Grade 60 Reinforcement: fy = 60,000 psi
Transformation n = Es/Ec = 8
Future Wearing Surface (DW): 15 psf for one course deck / 15 psf for two course
Normal Weight Concrete (DC): 150 pcf
Live Load (LL): HL-93 Table A4-1
Extreme Event Loading: Article TL-4
Overhang Design: Article 13.4.1 Design Cases
Overhang Thickness: Deck Thickness (uniform) + 1
Deck Type: One course
Wear: 1/2
Aggregate: SA
wS
Dead Load Moments will be calculated using --------- for both positive and negative movement
10
regions, where S is the effective deck slab span.
Live Load Moments are from Table A4-1. This table is used with the limitations described in
the appendix in Chapter 4. This table is used with the center to center girder spacing for positive momements and the design location from the centerline of the girder for negative
moment.
The overhang design is calculated separately based on extreme event loading which KDOT
has modeled. The required capacity is based on this analysis.
Article. 9.7.1.1 Minimum Slab Thickness Shall be 7.0 in.
Table 5.12.3-1 Minimum Cover of decks exposed to de-icing salts shall be 2 in.
KDOT uses 8 in. for one-course and 8 in. for two-course decks with 1 in. additional thickness
for the overhang. This additional thickness helps distribute load for the rail hit and provides clearance for the rail bars which are bent into the deck.
KDOT uses a minimum of 8 in. deck + 3 in. cover for this application according to Table 9.2-1
Bridge Section
9- 6
Design Manual
w dl S
M dl : = ----------------10
w fws = future wearing surface (see Table 9.4-1)
w deck = uniform distribution deck self weight
Volume III US (LRFD)
Version 1/14
Bridge Section
9- 7
Design Manual
Where: S = effective slab span (taken as 1/4 pts. on flanges for steel beams/ girders or the lesser
or 1/3 pts. or 15 for concrete beams).
w dl : = w deck + w fws
Live Load Force Effects:
AASTO LRFD Deck slab moments have been calculated for various girder spacings and are presented in Table A4-1 with the following limitations and assumptions:
Parallel girders.
Multiple Presence factor and dynamic allowance is included in table.
Article 4.6.2.1.6 distance between girders and design section (values are to be interpolated).
Supported on at least three girders and spaced not greater than 14-0.
Minimum Overhang of 21.0 and Maximum Overhang of the smaller of 0.625 times the
girder spacing or 6-0.
Moments are for interior girders and do not apply to overhang design.
Flexure Design:
Strength Limit State Loads: U = 1.25 (DC)+1.5(DW)+ 1.75 (LL)
Service Limit State Loads: U = 1.00 (DC) + 1.00(DW)+1.00 (LL)
Section Properties
b d deck 2
S deck : = --------------------6
Where:
this is
this is
Bridge Section
9- 8
Design Manual
M n : = A s f y d s a---
2
Where:
M n = nominal resistance
The factored resistance M r is taken as:
Mr : = Mn
Satisfy that:
Mr Mu
For the transverse reinforcement it is convenient to use 6 spacing for ease of field layout. After
satisfying the above Strength I requirement; the following conditions should be met:
Article 5.10.3.1 and 2 Maximum and Minimum spacing of Reinforcement
Minimum Spacing - 1.5 * Bar Diameter, 1.5 * Max. Aggregate or 1.5
Maximum Spacing - 1.5 * Member Thickness or 18
KDOT traditionally has limited the spacing for the slab reinforcement to the thickness of the
member.
Article 5.7.2.1 In bending assume tension controlled section
Bridge Section
9- 9
Design Manual
Unless otherwise specified, at any section of a flexural component, the amount of tensile reinforcement shall be adequate to develop a factored flexural resistance, M r , at least equal to the
lesser of:
1.2 * M cr
where
S
M cr = S c f r M dnc ------c- 1 S c f r
S
nc
700 e
s ------------------ 2 d c
s f ss
d
c
s := 1 + -----------------------------0.7 ( h d c )
f ss =
h =
dc =
e = 0.75
From conventional concrete design practices; calculate the stress in the reinforcement and determine the maximum spacing, s for the reinforcement:
Bridge Section
9 - 10
Design Manual
s
= --------bd
k=
( n) + 2 n n
j = 1 --k3
..stress in reinforcement
M
f s = ------------------As j d
Bridge Section
9- 11
Design Manual
At each corral rail post location center the #5 SP1 bars as shown in. These bars increase the torsional capacity of the slab in the critical section directly in front of the post allowing the slab and
rail to redistribute the force effects from the TL-4 extreme event loading requirements.
Figure 9.7-2 Corral Rail Post Detail
At the discontinuous ends of the deck slab, at joint locations and unit changes, the slab must be
supported by a structural element such as a diaphragm or cross frame and the slab reinforcement
should be increased to account for the edge beam effect.
Bridge Section
9 - 12
Design Manual
LStrain: = -----L
Stress: = E
Thermal expansion: L = T L
Bridge Section
9- 13
Design Manual
Substitution yields
L
= E ------L
= T E
And knowing that
P
A girder
girder
girder = --------------- = T E
yield rebar
= 6.5 10
W30 x 99
girder = T E
girder = 6.5 10
40F 29 10 psi
k
P = 219.4 ---------------girder
Factored thermal expansion force = P u = 1.3 219.4
k
P u = 285 ---------------girder
Bridge Section
9 - 14
Design Manual
in
ft
in
in
0.80 ------- > 0.5973 ------ft
ft
Ok
Bridge Section
9- 15
Design Manual
flared deck bridges is difficult and a smooth soffit is beneficial. The form capacity must be evaluated for locations where the slab is thickened, for instance at a finger joint expansion device.
Due to the possibility of falling debris from "rust out," steel stay-in-place forms should not be
used over state highways. However, in recent construction projects the railroad requested the use
of stay-in place forms to eliminate form removal. Maximum dead load deflections of stay-inplace forms shall be: Span/180 with a maximum of 0.5 inch. The use of stay-in-place forms
should be determined at field check. See 6.5.8 Steel Box Girders (Composite) for comments on
erection and bar placement when using steel stay-in-place forms. The designer should add notes
cautioning the contractor against welding metal stay-in-place forms to girder flanges.
Bridge Section
9 - 16
Design Manual
convenient to use a three-bar, 18 in. pattern. This permits the cutoff of two of the bars when not
required for stress, with the third bar extended the full length of the bridge. In the past the dead
load counterflexure was used to terminate a portion of the negative moment slab steel. The current LRFD requirement in Article 6.10.1.7 states that 1% of total cross-sectional area is the
amount of reinforcement which must extend to a point where either (1) the factored construction
loads or (2) load combination service II in Table 3.4.1-1 does not exceed fr , where = 0.9 for
flexure & f r = 0.24 f c taken from Article 5.4.2.6. These stresses are calculated according to
Article 6.10.1.1.1d. This reinforcement will have a yield strength not less than 60 ksi and a bar
size not exceeding #6 with bar spacing not greater than 12 in. The reinforcement is to be placed in
two layers uniformly distributed across the deck width and 67% placed in the top layer.
Bridge Section
9- 17
Design Manual
Bridge Section
9 - 18
Design Manual
Bridge Section
9- 19
Design Manual
Bridge Section
9 - 20
Design Manual
Bridge Section
9- 21
Design Manual
Bridge Section
9 - 22
Design Manual
Bridge Section
9- 23
Design Manual
Bridge Section
9 - 24
Design Manual
Note: Reinforce fillets if height is greater than 4 for horizontally curved bridges, or greater
than 6 for bridges built on tangents.
Procedure to determine fillet depth f for proper placement of deck forms:
+ T.D.(Top of Deck elevation at final grade)
- T (Slab Thickness)
+ Concrete Dead Load Deflection: downward deflection is added, upward
deflection is subtracted.
- T.F (Field Shot at Top of Flange after all Structural Steel has been erected)*
= f (Fillet height required)
Bridge Section
9- 25
Design Manual
T (Slab Thickness)
Bridge Section
9 - 26
Design Manual
Dead Load Moments will be calculated using the wl /10 for both positive and negative
regions.
Live Load Moments are from Figure 9.15-1 AASHTO Table A4-1; This table is used with the
limitations described in the appendix in chapter #4.
The Overhang Design is calculated separately based on extreme event loading.
KDOT has modeled the overhang using finite elements which show the distribution of load
based on the elastic analysis, the required capacity is based on this analysis in Appendix A
Overhang Design: Corral Rail.
Example Design Information:
Traffic Count: AADT = 3200 Span Layout: 75' - 100' - 75'
Structure Type: Rolled Beam, 3 Span, Composite, Continuous W40x249
Deck Information: * 8 in. Deck Slab w/o Overlay 3 in. clear Gr. 4.0 (AE)(SA)
Beam Spacing = 5 Spaces @ 8'- 0" = 40'-0"
Overhang Information = 3'-0"
Roadway = 44'-0"; Skew = 10 degrees Rt.; Rail = 32 in. Corral Rail; Drainage Over side
Out to Out Deck = 46'-0"
Thermal Expansion = Intergal Abutments
*KDOT adds 1 in. to the normal deck thickness for the overhang.
Unit Weight of Concrete = Normal Weight = 150 pcf
Modular Ratio
, 000ksiEs- = 29
-----------------------n = ----8
3, 605ksi
Ec
Bridge Section
9- 27
Design Manual
Article 9.7.1.2 Composite action, shear connectors are to be designed according to section 5, 6
and 7 o f the LRFD specification.
Article 9.7.1.3 If a skewed deck exceeds 25 then direction of primary reinforcement is
perpendicular to centerline of bridge.
KDOT allows up to 35 but requires investigation into the reduced effectiveness when placing the
primary reinforcement parallel to the skew.
A s provided * cos 10
A s provided * 0.9848 Reduce Capacity by 1.5%
The plane which is to the design section is not to the direction traffic and therefore, is
adjusted to account for the lack of effectiveness.
Article 9.7.1.4 Edge Support
KDOT considers and includes the concrete parapet to fully support the edge of the slab, and the
structure is integral at the abutments, this condition is satisfied. However, at unit breaks and free
standing abutments this must be addressed and edge beam design must be considered.
Dead Loads:
Article 4.6.2.1.6 Based on a 1-foot wide strip.
Effective Slab Span is:
one-quarter from center - center support for steel I-shapes
one third from center - center support for prestressed I-shapes for a max. of 10 in. from center
of support for prestressed I-shape.
For this example c-c = 8'-0" using W40x249
b f = 15.75 in
in-
15.75
------------------2
12
Effective Slab Span = 8.0 ft --------------------------------- = 7.34 ft Effective Slab Span is used for DL only
4
Dead Loads are calculated based on a 1-foot strip. Dead Load Moments for both the positive and
negative regions are based on:
2
M DL
w DL L
= ------------------10
Bridge Section
9 - 28
Design Manual
lb 8.5
lb
DC = Deck = 150 -----3- ------- 1 ft = 106.3 ----12
ft
ft
lb
lb
DW = Future Wearing Surface = 15 -----2- 1 ft = 15 ----ft
ft
Dead Load Moments
lb
lb
2
2
106.3 ----- 7.34ft
15 ----- 7.34ft
ft
ft
M DC = ------------------------------------------- = 572.7 lb ft M DW = ----------------------------------- = 80.8 lb ft
10
10
Live Load Moments:
Positive Moment
Slab Span = 8.00 ft.
Value from table
8.00 ft = 5.69k ft
Negative Moment:
in- = 3.94 in
Negative Moment Taken at Flange Width 15.75
------------------4
Values from table
Girder Spacing
8.00ft
Design Section
Design section
3 in
6 in
5.65k ft
4.81k ft
Bridge Section
9- 29
Design Manual
4
4
4
4
5
5
5
5
6
6
6
6
7
7
7
7
8
8
8
8
9
9
9
9
10
10
10
10
11
11
11
11
12
12
12
12
13
13
13
13
14
14
14
14
15
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
-3
-6
-9
-0
Positive
Moment
4.68
4.66
4.63
4.64
4.65
4.67
4.71
4.77
4.83
4.91
5.00
5.10
5.21
5.32
5.44
5.56
5.69
5.83
5.99
6.14
6.29
6.44
6.59
6.74
6.89
7.03
7.17
7.32
7.46
7.60
7.74
7.88
8.01
8.15
8.28
8.41
8.54
8.66
8.78
8.90
9.02
9.14
9.25
9.36
9.47
NEGATIVE MOMENT
Distance from CL of Girder to Design Section for Negative Moment
0.0 in.
3 in.
6 in.
9 in.
12 in.
18 in. 24 in.
2.68
2.07
1.74
1.60
1.50
1.34
1.25
2.73
2.25
1.95
1.74
1.57
1.33
1.20
3.00
2.58
2.19
1.90
1.65
1.32
1.18
3.38
2.90
2.43
2.07
1.74
1.29
1.20
3.74
3.20
2.66
2.24
1.83
1.26
1.12
4.06
3.47
2.89
2.41
1.95
1.28
0.98
4.36
3.73
3.11
2.58
2.07
1.30
0.99
4.63
3.97
3.31
2.73
2.19
1.32
1.02
4.88
4.19
3.50
2.88
2.31
1.39
1.07
5.10
4.39
3.68
3.02
2.42
1.45
1.13
5.31
4.57
3.84
3.15
2.53
1.50
1.20
5.50
4.74
3.99
3.27
2.64
1.58
1.28
5.98
5.17
4.36
3.56
2.84
1.63
1.37
6.13
5.31
4.49
3.68
2.96
1.65
1.51
6.26
5.43
4.61
3.78
3.15
1.88
1.72
6.38
5.54
4.71
3.88
3.30
2.21
1.94
6.48
5.65
4.81
3.98
3.43
2.49
2.16
6.58
5.74
4.90
4.06
3.53
2.74
2.37
6.66
5.82
4.98
4.14
3.61
2.96
2.58
6.74
5.90
5.06
4.22
3.67
3.15
2.79
6.81
5.97
5.13
4.28
3.71
3.31
3.00
6.87
6.03
5.19
4.40
3.82
3.47
3.20
7.15
6.31
5.46
4.66
4.04
3.68
3.39
7.51
6.65
5.80
4.94
4.21
3.89
3.58
7.85
6.99
6.13
5.26
4.41
4.09
3.77
8.19
7.32
6.45
5.58
4.71
4.29
3.96
8.52
7.64
6.77
5.89
5.02
4.48
4.15
8.83
7.95
7.08
6.20
5.32
4.68
4.34
9.14
8.26
7.38
6.50
5.62
4.86
4.52
9.44
8.55
7.67
6.79
5.91
5.04
4.70
9.72
8.84
7.96
7.07
6.19
5.22
4.87
10.01
9.12
8.24
7.36
6.47
5.40
5.05
10.28
9.40
8.51
7.63
6.74
5.56
5.21
10.55
9.67
8.78
7.90
7.02
5.75
5.38
10.81
9.93
9.04
8.16
7.28
5.97
5.54
11.06
10.18
9.30
8.42
7.54
6.18
5.70
11.31
10.43
9.55
8.67
7.79
6.38
5.86
11.55
10.67
9.80
8.92
8.04
6.59
6.01
11.79
10.91
10.03
9.16
8.28
6.79
6.16
12.02
11.14
10.27
9.40
8.52
6.99
6.30
12.24
11.37
10.50
9.63
8.76
7.18
6.45
12.46
11.59
10.72
9.85
8.99
7.38
6.58
12.67
11.81
10.94
10.08
9.21
7.57
6.72
12.88
12.02
11.16
10.30
9.44
7.76
6.86
13.09
12.23
11.37
10.51
9.65
7.94
7.02
Bridge Section
9 - 30
M DC = 0.573k ft M DW = 0.081k ft
Design Manual
Span = 8.00ft
M LL = 5.69k ft
From 9.15-1 AASHTO Table A4-1
Span = 8.00ft
M LL = 5.39k ft
Distance = 3.94 in
(Single Interpolation)
= M
NOTE:
Live Load Tables have dynamic allowance, plus a multiple presence factor included.
Check Overhang limits for table:
Max. Overhang = 0.625 x 8.0' = 5'-0"
Overhang = 3'-0" < 5'-0" OK
Flexural Design
Strength I Limit State Loads:
U = 1.25 ( DC ) + 1.50 ( DW ) + ( 1.75 ) ( LL )
Positive Moment for Design:
M U+ = 1.25 ( M DC ) + 1.50 ( M DW ) + 1.75 ( M LL+ )
k ft
= 1.25 ( 0.573 ) + 1.5 ( 0.081 ) + 1.75 ( 5.69 ) = 10.80 ---------ft
Negative Moment for Design:
_
k ft
= 1.25 ( 0.573 ) + 1.5 ( 0.081 ) + 1.75 ( 5.39 ) = 10.27 ---------ft
Service I Limit State Loads:
U = 1.0 ( DC ) + 1.0 ( DW ) + 1.0 ( LL )
Positive Moment for Design:
+
Bridge Section
9- 31
Design Manual
Section Properties:
One Course Deck - Structural Thickness =
2
b ( d Deck )
12in 8in
3
S Deck = ---------------------------- = -------------------------- = 128in
6
6
--#5
8
d s Top = d Deck 3 in clr ------- = 8.5in 3in --- = 5.188 in
2
2
2
2
As fy
60ksi- = 0.5203in
----------------------------------------a = c 1 = -----------------------= 0.7386in
0.85
4ksi
12in
0.85 fc b
1
k ft
------------- ------ = 12.10 ---------M n = ( A s cos 10 ) f y d s a--- = ( 0.51 ( cos 10 ) )60ksi 5.188 0.739
ft
2
2 12
k ft
k ft
M r = M n = ( 0.9 12.10k ft ) = 10.9 ---------- > 10.3 ---------ft
ft
Mr > Mu
OK
Bridge Section
9 - 32
Design Manual
58
d s bot = d deck 1.5in clr 0.5in Wear ---------- = 6.188in
2
2
M r > M u OK
Slab Thickness
Bridge Section
9- 33
Design Manual
5 8in
d Top = 8.5 in 3in --------------- = 5.188in
2
cl
8in- = 6.188in
d Bottom = 8.5in 0.5in 1 in = 5-------------2
wear
a max = 1 c max
cl
Used for 4ksi concrete
= 0.85 c max = 0.85 0.375d = 0.85 0.375 5.188in = 1.654in
c = 0.7386in
--------------------- = 0.8689in
0.85
M a Top = 0.7386in
< 1.654in
+M a Bottom = 0.7386in
Article 5.7.3.3.2 Minimum Reinforcement
At any section of a flexural component, the amount of prestressed and non-prestressed tensile
reinforcement shall be adequate to develop a factored flexural resistance, M r , at least equal to the
lesser of:
1.2 M cr
S
M cr = S c ( f r + f cpe ) M dnc ------c- 1 S c f r
S
nc
where f r = 0.37 f c
(or)
1.33 M u Strength I
Strength I
+
Bridge Section
9 - 34
Design Manual
( 128in 0.74ksi )
1.2 M cr = S c f r = ( 1.2 ) --------------------------------------------- = 9.47k ft
12
_
Mu = 6.05k ft
S c = 128in
M
ft ( 12 )- = 0.567 ksi > 0.80 f
f ss = -----------u = 6.05k
-----------------------------------r
3
Sc
128in
Limit the spacing S, in the mild reinforcement for Positive and Negitive Moments (layer
closest to the tension face)
Where d c = depth of cover to CG of Rebar
(limit d c to 2 in. + bar dia.) (KDOT policy)
fs
for #4s & #5s alternate @ 6 in. spa. top & bottom
A s = 0.51in 2
Bridge Section
9- 35
Design Manual
k=
n + 2n n
k=
2
( 0.0081 8 ) + 2 ( 0.0081 8 ) ( 0.0081 8 ) = 0.301
j = 1 --k- = 1 0.301
------------- = 0.900
3
3
M
( 6.05k ft ) 12
f s = ------------------- = ----------------------------------------------------------------------------- = 31.0 ksi
A s j d 0.51 ( cos 10 ) 0.900 5.188in
Using the stress in the reinforcement to determine the maximum allowable bar spacing,
700 e
S -------------- 2d c
s f ss
d
c s = 1 + --------------------------
0.7 ( h d c )
2.3125in - = 1.58
s = 1 + ------------------------------------0.7 ( 8 2.3125 )
700
0.75
S ----------------------------------- 2 ( 2.3125 )
1.58 31.0ksi
S 6.1in > 6in
bar spacing OK
Positive Moment,+M:
d c = 1.5in + #5
------ = 1.8175in
2
Bridge Section
9 - 36
Design Manual
f s = 25.2ksi
700 e
S -------------- 2d c
s f ss
d
c s = 1 + --------------------------
0.7 ( h d c )
1.8125in - = 1.42
s = 1 + ------------------------------------0.7 ( 8 1.8125 )
bar spacing ok
Bridge Section
9- 37
Design Manual
in 2
A s = 0.51 ( cos 10 ) ------ft
Therefore the minimum amount of longitudinal reinforcement for distribution of load is:
use
in 2
in 2
A sLONG = 0.67 0.51 (cos 10 ) ------- = 0.34 ------ft
ft
in
#4 Bars @ 6 Spa. = 0.40 ----ft
in
1% A s = 0.01 8.5in 12in = 1.02 -------------------ft width
In the past LFD designs have reduced the total cross-sectional depth by the wear and calculated
the 1% based on the structural thickness rather than the total thickness, this has changed for LRFD
designs.
This reinforcement is not to be greater than #6 bars with spacing not exceeding 12 in. uniformly
2
distributed in two layers. --- of this reinforcement shall be placed in the top layer
3
0.75
in - = 0.65
------------------2
1.15 in
Bridge Section
9 - 38
Design Manual
in 2
As = area of reinforcement in each direction & each face ------ft
b = least width of component section (in)
in 2
#4 @ 12 in = 0.20 ------- will satisfy
ft
Distribution & reinforcement controls in the longitudinal direction at the top of the slab are
satisfied with #4s @ 12 in spacing.
Bridge Section
9- 39
Design Manual
Different widths of overhangs were modeled. The shortest overhangs showed the highest
stresses, as expected. Several girder types were modeled; the type of girder (welded plate, rolled
beam or concrete) did not significantly affect stresses in the overhang.
A force of 54 kips was applied perpendicular to the rail. The resulting stress contours in the slab
are displayed above.
From the STAAD Model, compute the average moment at the base of the Post. Distribute the
moment over a distance of the post width plus (2 x post depth): 36 in. + 2(10 in.) = 4.66 ft. Since
the STAAD Model consist of one-foot segments, conservatively round down to the nearest 0.5
foot. Therefore, the moment will be distributed over a width of 4.5 feet. (Note: The attached
STAAD Model moment contour is for a force of 54 kip):
A1 W 40X249, 2'-0' to 3'-0" Overhang with 32 in. Kansas Corral Rail
1) - Compute the average moment at post base.
Bridge Section
9 - 40
Design Manual
Distribute moment over a distance of post width + (2 x Post Depth) = 3ft + 2 x 10 in = 4.66 ft
Moment
Length
k ft
16.95 ---------- 0.4 ft = 6.78
ft
k ft
15.85 ---------- 0.6 ft = 9.51
ft
k ft
13.60 ---------- 1.5ft = 20.40
ft
k ft
10.75 ---------- 1.5ft = 21.50
ft
k ft
7.96 ---------- 0.5ft = 3.98
ft
k ft
Total = 62.17 ---------ft
k ft
62.17 ---------2
ft
k ft
-----------------------= 13.82 ---------- Average Moment @ base of post due to vehicular impact of TL-4.
ft
4.5 ft
2) - Addition DL due to Rail & Slab
lb
5
lb 6
k ft
9in 10in 12in300 ----- ------ + -------------------------------------- 150 ----- ------ = 0.189 ---------3
ft 12
ft
ft 12
12
rail
slab
Bridge Section
9- 41
Design Manual
k ft
M u = M cr = 13.82 + 1.25 ( 0.189 ) = 14.05 ---------ft
3) - From Slab Design w/ #4, 5 @ 6 in. Top
#4, 5 @ 6 in. Bottom
2
a
M n = M r = 1.0 A s f y d --- = -------------------------------------------------------------------------- = 22.9k ft
2
12
Extreme Event
Bridge Section
9 - 42
Design Manual
Mu
Pu
Pu
-------- + ----------- 1.0 M u M R 1 ---------
P n
P n M n
A stotal = A stop + A sbottom
= 0.818 + 0.818 = 1.64in
P u = T ct = 10.8k ft
P r = A s f y
= 1.0 1.64 60
= 98.4k/ ft
ftft- = 20.4 k---------M u ( 1.0 22.9k/ ft ) 1 10.8k/
-------------------
ft
98.4k/ ft
6) - Compare Load to Resistance
Mr Mu
k ft
k ft
20.4 ----------- 14.08 ----------- OK
ft
ft
0.31in
60ksi = 11.62in
Basic Development ------------------------------ = --------------------------------------------------
4ksi
fc
Bridge Section
9- 43
Design Manual
in
A sTop = 0.51 ------- #4 & #5 @ 6in
ft
2
in
A sBot = 0.51 ------- #4 & #5 @ 6in
ft
d = 6.187 in
As fy
a = --------------------- = 0.75in
0.85 f c B
2
in
1.0 60 0.51 ------- ( 6.187in 0.75 )
k ft
ft
M r = M n = 1.0 A s f y d --a- = -------------------------------------------------------------------------------------- = 13.87 ----------
ft
2
in
12 ----ft
k54k = 7.36 --P u = T ct = -------------ft
7.33ft
in
k
P n = A sr f y = 1.02 ------- 60ksi 1.0 = 61.2 ---ft
ft
k-
7.36 --Pu
k--------- ftk ft
ft
ft
6B) - M r M u 12.2
k ft / ft
9.76
k ft / ft
OK
Summary of Analysis
Bridge Section
9 - 44
Design Manual
In summary, the analysis indicates that for various combinations of overhang length, diaphragm
spacing & girder spacing; the negative moment reinforcement requirement due to the HL-93 slab
loading over a girder controls the amount of reinforcement in the top of the slab.
If an overhang greater than 3'-0" is used the negative moment maybe controlled by AASHTO
A.13.4 Design Case 2 or 3.
Bridge Section
9- 45
Design Manual
Different widths of overhangs were modeled. The shortest overhangs gave the highest stresses, as
expected. Several girder types were modeled; the type of girder (welded plate, rolled beam or
concrete) did not significantly affect stresses in the overhang.
A force of 54 kip was applied perpendicular to the rail. The resulting stress contours in the slab
are displayed on above.
From the STAAD Model, compute the average moment at the base of the barrier, and distributed.
Bridge Section
9 - 46
Design Manual
W/ Overhangs ranging from 2.3 ft - 3.6 ft Overhang with 32 in F Type Barrier Rail
1) Use Hot Spot moment from STAAD model in design since the model redistributes the forces
linear in a elastic fashion.
2) Reduce reinforcement capacity based on tension in slab caused by rail hit. Distribute this over
the following area.
Distribute moment over a distance of 3.6 ft + (2 x Rail Width + 2(distance to "hot spot")) = 3.6 ft
+ 2(15 in)+2(6 in) = 7.0 ft.
ft 2 ( 12 )
ft
ft
12
Total Movement at Face of Rail
k ft
M u = M cr = 8.21 + 1.25 ( 0.365 ) = 8.66 ---------ft
3) - From Slab Design w/ #4, 5 @ 6 in Top & Bottom
Bridge Section
9- 47
Design Manual
A sTop
in
in
= #4 & #5 @ 6 ----- = 0.51 ------ft
ft
in
A sTop cos 10 = 0.5023 ------ft
As fy
0.5023 60ksi- = 0.739in
a = ------------------------ = ------------------------------------0.85 ( 4ksi )12in
0.85 ( f c )b
-------------
1.0 0.502 60 6.19in 0.739
2
k ft
M r = M n = 1.0 A s f y d d--- = ----------------------------------------------------------------------------- = 14.61 ---------
ft
2
12
Extreme Event
5) - Reduce by tension in slab caused by rail hit.
k
T ct = 54kip
-------------- = 12 --ft
4.5ft
Bridge Section
9 - 48
Design Manual
Assume the interaction between moment and axial force is a straight line:
Mu
Pu
Pu
-------- + ---------- 1.0 M u M n 1 ---------
Pn
Pn Mn
k
P r = T ct = 12 --ft
2
12 --
ft
1 -------------
k
54.6 --
ft
k ft
= 11.40 ---------ft
k ft
k ft
11.40 ---------- 8.58 ---------- OK
ft
ft
Bridge Section
9- 49
Design Manual
Epoxy 1.2 ld
A s required 8.58
---------------------- ------------- 1.2 0.8 11.625in = 8.40in < 13in OK
A s provided 11.40
Summary of Analysis
In summary, the analysis indicates that for various combinations of overhang length, diaphragm
spacing & girder spacing; the negative moment reinforcement requirement due to the HL-93 slab
loading over a girder controls the amount of reinforcement in the top of the slab.
If an overhang greater than 3'-6" is used the negative moment maybe controlled by Article A.13.4
Design Case 2 or 3.
Bridge Section
9 - 50
Design Manual
AADT = 3000
75'-100'-75' Rolled Beam, Composite, Continuous
8.5 in. One Course Deck Slab
3.0 in. Clr.
Gr. 4.0 (AE)(SA)
44'-0" Rdwy, Skew = 10 Rt.
6 - Beams Spaced at 8'-0"
W40x249
Overhangs = 3'-0" for total Out to Out of deck = 46'-0"
32 in. Corral Rail
Drainage over the sides
Integral Abutments
Methodology:
w l
Dead Load Moments will be calculated using
10
Live Load Moments are from Table A4-1; this table is used with the limitations described in the appendix in
Chapter 4.
The overhang design is calculated separately based on Extreme Event loading. KDOT has based the required
capacity on a model of the overhang using finite elements for the distribution of load based on elastic analysis.
Article 9.7.1.1
Minimum slab thickness is 7.0 in. KDOT uses an 8.5 in. thick deck for interior sections of the
bridge deck and an extra 1 in. of thickness for the overhang.
Table 5.12.3-1
Minimum cover for decks exposed to de-icing salts shall be 2.5 in. KDOT uses 3.0 in. of cover for all deck
slabs.
Article 9.7.1.2
Under most circumstances, KDOT uses a composite slab design procedure. Refer to the respective sections
in the LRFD Specification in Chapters 5,6 and 7.
Article 9.7.1.3
If skewed deck exceeds 25 then primary reinforcement for decks is placed perpendicular to the centerline of
the bridge. KDOT allows up to 35, but requires investigation into the reduced effectiveness:
As provided * cos(10) = 0.9848*A s provided
Or a reduced capacity of about 2%.
Article 9.7.1.4
Because KDOT consideres the concrete parapet to fully support the edge of the slab and because the main
deck reinforcement is transverse, no additional edge beam need be provided.
1-6
Bridge Section
9- 51
Design Manual
Deck Loads
Use a 1 foot wide strip of deck for design purposes.
Article 4.6.2.1.6
Effective Slab Span is taken at one-quarter the flange width from the centerline of support for steel beams
and one-third the flange width from the centerline of support for prestressed beams at no more than 15 in.
from the center of the support. This is used for calculating the Dead Load Moments.
S 8.0
b f 15.75 in.
ft.
bf
2
12
Seff S
4
ts 8.5
in.
7.344 ft.
Seff
Deck Concrete Unit Wt for dead load purposes is 150 lb/ft^3, so deck load per foot is:
ts
lb
wDC 150 1
ft
12
wFWS 15 1
wDC Seff
M DC
ft
10000
wFWS Seff
M DW
lb
M DC
0.573 kip ft
M DW
0.081 kip ft
10000
To use Table A4-1, the Overhang has to be less than 0.625*GirderSpacing or 6 feet, whichever is less.
21
OHmax 0.625 Seff
OHmin
12
OHmax
4.59 ft.
OHmin
OH 3.0
1.75 ft.
ft.
<== OK
kip ft
M LLneg 5.39
kip ft
M Upos
10.80
kip ft
M Uneg
10.27
kip ft
M Spos
6.34
kip ft
M Sneg
6.04
kip ft
2-6
Bridge Section
9 - 52
Design Manual
12 tseff
tseff ts wear
sdeck
128
Skew 10 degerees
in
0.9
cleartop 3.0 in
clearbot 1.5 in
BARdia_top
BARdia_bot
in
5
8
in
fy 60 ksi
Try Alternating #4 and #5 bars at 6 in. spacing in bottom of slab for Positive Moment
2
in
ASprovidedBot 0.51
d bot t s clearbot
d bot
BARdia_bot
2
b 12
ft
wear
Skew
f
180 y
a
0.85 fpc b
a
Skew
f d
180 y bot
M Rpos
13.15 kip ft
a 1
2 12
0.739
M Rpos M Npos
10.80 kip ft
M Upos
>
(1 foot strip)
ASprovidedBot cos
6.188
in
<== Check!
Try Alternating #4 and #5 bars at 6 in. spacing in top of slab for Negative Moment
2
ASprovidedTop 0.51
d top t s cleartop
d top
in
ft
BARdia_top
a
5.188
Skew
f
180 y
ASprovidedTop cos
0.85 fpc b
a
Skew
f d
180 y top
M Rneg
10.89 kip ft
>
a 1
2 12
M Uneg
0.739
M Rneg M Nneg
10.27 kip ft
<== Check!
3-6
Bridge Section
9- 53
Design Manual
MIN
0.938 in
MIN
0.938 in
MAX
12.75in
<
6 in.
KDOTmax
8.5in
<== Check!
>
Article 5.7.3.3.2
fr 0.37 fpc
sdeck fr
M cr
1.2 M cr
12
kip ft
9.472
9.472 kip ft
<
M Rpos
13.15 kip ft
<
M Rneg
10.89 kip ft
<== Check!
9.472 kip ft
M minNeg
Article 5.7.3.4
<== Check!
Crack Control
Top Steel
Will calculate the actual stress in the tensile reinforcement by using the working strength
method for a crack concrete section. Will solve the quadratic equation below, which was
developed by summing the moments about the neutral axis.
d c min 2 cleartop
Guess
n 8
BARdia_top
dc
2.313
k 0.21
Skew
180
As ASprovidedTop cos
Given
b k d top
2
k Find( k )
fs
n As d top k d top = 0
12M Sneg
k
As d top 1
3
0.301
fs
30.936
ksi
As
b d top
8.068 u 10
k
3
( n ) 2 n n
4-6
Bridge Section
9 - 54
Design Manual
dc
s 1
0.7 t s d c
700 e
f 2 dc
s s
smax
smax
1.534
6.439
>
6 in.
<== Check!
Bottom Steel
Will calculate the actual stress in the tensile reinforcement by using the working strength
method for a crack concrete section. Will solve the quadratic equation below, which was
developed by summing the moments about the neutral axis.
BARdia_bot
d c clearbot
dc
1.813
Guess
Skew
180
As ASprovidedBot cos
k 0.2
Given
b k d bot
2
k Find( k )
fs
n As d bot k d bot = 0
k
0.279
12M Spos
fs
k
As d bot 1
3
27.011
ksi
dc
s 1
0.7 ts d c
smax
700 e
f 2 dc
s s
smax
1.387
15.057
>
6 in.
<== Check!
5-6
Bridge Section
9- 55
Design Manual
Article 9.7.3.2
Distribution Reinforcement
81.183 %
Seff
min
220
Seff
AsLongBot
67
100
67 %
Skew
180
SprovidedBot cos
AsLongBot
0.337
in
ft
in
ft
Article 5.10.8
For bars, the area of reinforcement per foot, on each face and in each direction should be:
b deck 44 12
b deck
528 in
AsShrinkTemp
2
AsShrinkTemp
0.091
1.3 b deck ts
2 b deck ts fy
2
in
ft
0.40
in
<== Check!
ft
AsNegMoment
1.02 in
ft
No greater than #6 bars for this reinforcement spaced no greater than 12 in. uniformly distributed in two
layers with 2/3 placed in the top layer.
Try Alternating #6 & #5 bars spaced at 6 in. for the top layer.
2
AsLongTop 0.75
in
From above:
ft
in
AsLongBot 0.40
ft
AsLong
AsLongTop
AsLong
1.15
in
ft
0.652
>
AsNegMoment
0.67
1.02
in
ft
<== Check!
<== Check!
6-6
Bridge Section
9 - 56
Design Manual
ksi 1000psi
kip 1000lbf
Input
Total finished Deck Slab Thickness .........................................................................
ttotal 8in
tpanel 3in
S
Pi 16.1 kip
fpc_slab 4ksi
fpc_panel 5ksi
fpci_panel 4ksi
lbf
Wc 150
3
ft
fy 60ksi
fpy 243ksi
fpu 270ksi
Aps 0.085 in
d ps
8 0 ft
12
3
8
in
Ep 28500 ksi
wtopFlange 24in
Spanel
6.833 ft
57
psi
Eps
fpc_panel ksi
4030.5 ksi
Ec
57
psi
Ec
fpc_slab ksi
3605 ksi
Ect
57
psi
fpci_panel ksi
Ect
3605 ksi
1-5
Bridge Section
9- 57
Design Manual
fpi
fpi
Aps
189.4 ksi
<
0.75 fpu
202.5 ksi
<== Check
'fpES
Ect
Pi
fcgp
fcgp
'fpES
t panel b
7.1 ksi
J st
5 ksi
'fpR 2.4ksi
1 ksi fpci_panel
'fpLT 10.0
fpi Aps
Ag
Ag b t panel
'fpLT
24.4 ksi
'fpT
'fpT
31.5 ksi
fpi
16.6 %
V ps
V ps
Ag
745.9 psi
0.45 fpc_panel
>
2250 psi
<== Check
b eff
b eff
Ec
Eps
tpanel
b tpanel
2
y bar
t slab_struct
tpanel
beff tslab_struct
2
5.367 in
y bar
3.404 in
2
2
t panel
t slab_struct
Itotal
t
t
b t panel y bar
b eff tslab_struct tpanel
y bar
12 panel
12 slab_struct
2
2
b eff
scomp
Ipanel
1
12
b t panel
spanel
Itotal
y bar
Ipanel
tpanel
scomp
47.6 in
spanel
9 in
2-5
Bridge Section
9 - 58
Design Manual
Applied Loads
Seff_Panel
Seff_Slab
Spanel 2 5 in 2 1 in
S 2
Seff_Panel
wtopFlange
Seff_Slab
3
Wc b
M DL_SelfWeight
t panel Seff_Panel
Wc b
M DL_Slab
M LL_Construction
50
M DL_FWS
25
t slab Seff_Panel
80 in
lbf
IMP
Seff_Slab 2ft
32
16000 lbf
118.8 ft lbf
M LL_Construction
Seff_Slab
148.5 ft lbf
M DL_Slab
2 10
89.1 ft lbf
M DL_SelfWeight
lbf b
2
S
2 8 eff_Panel
ft
ft
M LL_old
74 in
55.6 ft lbf
M DL_FWS
1.3
0.80
12in
b IMP
M LL_old
2253.3 ft lbf
From Appendix 4A the Positive Live Load Moment for the given Girder Spacing S is:
M A4_1
M LL
M A4_1
12in
M LL
5.69kip ft
M LL
2845 ft lbf
M LL_old
1.263
J LL
1.0
0.8
MDL_SelfWeight
V DL_Construction
J DL
V LL_Construction
J LL
V Construction
spanel
M DL_Slab
spanel
MLL_Construction
spanel
V DL_Construction V LL_Construction V ps
V Construction
302.2 psi
<
0.0948 fpci_panel
ksi
189.6 psi
<=== Check
ksi
3-5
Bridge Section
9- 59
Design Manual
V DL_FWS J DL
M DL_FWS
scomp
V Final
<
158.7 psi
ksi
0.19 fpc_panel
<=== Check
424.9 psi
ksi
J DW 1.5
J LL 1.75
Mu
5359.2 lbf ft
Ltransfer
E 1 0.85
k 2 1.04
fpy
fpu
tpanel
d p tslab_struct
0.28
fpe
fpu
0.585
>
0.5
<=== Check
Aps fpu
c
1.87 ft
fpu
d ps
dp
c
fps fpu 1 k
dp
1.237 in
5.313 in
fps
252.4 ksi
Ld
12.3 ft
dp
fpe
fp ( x )
N in
Ld
157.9 ksi
fpe x
Ltransfer
fps
ksi
f
3 pe
2
if x Ltransfer
x Ltransfer
fpe
f fpe
Ld Ltransfer ps
otherwise
c
Spanel
Aps fps
0.85 fpc_slab E 1 b
fps fp Ld_max
fps
172 ksi
a E 1 c
0.843 in
0.717 in
4-5
Bridge Section
9 - 60
Design Manual
Mn
M r I M n
Mr
6034.9 lbf ft
6034.9 lbf ft
>
Mu
5359.2 lbf ft
<== Check
fr
0.37
ksi
fpc_panel ksi
fr
fcpe V ps
827.3 psi
scomp
Mr
6034.9 lbf ft
>
3939.1 lbf ft
<=== Check
1.33 M u otherwise
5-5
Bridge Section
9- 61
Design Manual
10 FOUNDATION
Table of Contents
10 Foundations ...............................................................................................................1
10.1 General ...................................................................................................................1
10.2 Footings ..................................................................................................................2
10.2.1 Spread Footings ...................................................................................................3
10.2.2 Pile Footing .........................................................................................................4
10.3 Bending Moment ....................................................................................................5
10.4 Shear Design ..........................................................................................................5
10.5 Reinforcement ........................................................................................................9
10.6 Piling ....................................................................................................................12
10.6.1 Timber Piles ......................................................................................................13
10.6.2 Steel Piles ..........................................................................................................13
10.6.3 Cast-in-Place Pipe Pile ......................................................................................13
10.6.4 Prestressed Concrete Piles .................................................................................14
10.6.5 Cast-in-Place Pressure Grouted Piling ..............................................................14
10.6.6 Composite Pile ..................................................................................................14
10.6.7 Pile Points ..........................................................................................................14
10.6.8 Negative Skin Friction ......................................................................................15
10.6.9 Estimating Pile Capacity ...................................................................................15
10.6.10 Pile Driving Analyzer ......................................................................................16
10.6.11 Using the Geology Report for Pile Capacity ...................................................18
10.7 Drilled Shafts ........................................................................................................22
10.7.1 Design ................................................................................................................23
10.7.2 Details ................................................................................................................24
10.7.3 Cross Hole Sonic Logging Tests .......................................................................27
Figures
Figure 10.4-1 Spread Footing Critical Shear .................................................................................7
Figure 10.4-2 Pile Cap Footing Critical Shear ...............................................................................8
Figure 10.5-1 Recommended Placement of Footing Steel (Square) ............................................10
Figure 10.5-2 Recommended Placement of Footing Steel (rectangular) ......................................11
Figure 10.6.11-1 Standard Pile Details .........................................................................................21
Figure 10.7.3-1 Plan of Drilled Shaft ...........................................................................................28
Figure 10.7.3-2 Drilled Shaft Dowel Bars ....................................................................................29
Figure 10.7.3-3 Uncased Drilled Shaft - Dry Pour Method Only .................................................30
Figure 10.7.3-4 Drilled Shaft Construction Using Temporary and Permanent Casing ................31
Figure 10.7.3-5 Example: Permanent Casing Drilled Shaft Design ............................................32
Figure 10.7.3-6 Example: Permanent Casing Drilled Shaft Design .............................................33
Bridge Section
10 - i
Design Manual
Appendix
Appendix A EXAMPLE: Spread Footing Design ........................................................................34
Appendix B EXAMPLE: Pile Cap Footing Design ......................................................................43
Appendix C Footing Orientation .................................................................................................51
Bridge Section
10 - ii
Design Manual
10 FOUNDATIONS
Since the safety and stability of a bridge structure is of paramount importance, the design engineer
should avail himself of pertinent data concerning the foundation material for proper performance
of the foundation. This would include topographic maps, geological maps, boring logs and laboratory reports of tests on the foundation materials. KDOTs Geotechnical Manual should serve as a
guide for this purpose. The structural engineer is to work closely with the Geology Section to
determine the following: (1) distribution, classification and physical properties of the soil and
rock, (2) bearing capacity of foundation material, (3) the predicted settlement of foundation material, (4) possible influence of adjacent structures, and (5) the effects of groundwater. KDOTs
Geology Section will determine the factor resistances for all foundation elements.
10.1 General
Similar to many other Department of Transportations (DOTs), historically KDOT has used
Working Stress Design (WSD) methods in the foundation design of bridge structures. For the purposes of KDOTs Bridge Foundation Design, Chapter 10 of the LRFD AASHTO Bridge Design
Manual has changed little from the methodologies used in the Standard Specifications. Some of
the material presented within this section has not changed as the methods, details and comments
are still valid.
During preliminary design a number of activities take place to determine the types of foundations
to be used and the permitted capacities for foundation components.
Prior to beginning final design on highway projects, designers should review the Foundation
Engineer's Report and if it is a bridge replacement, review the existing bridge plans.
If a scour analysis is needed, the designer should request the sampling as soon as this is determined.
Bridge foundation studies and geology reports on state projects are compiled by the Geology
Section of the Bureau of Structures and Geotechnical Services. The request for geology is
normally made shortly after field check. The designer typically does not supply the Geologist
with design loads unless drilled shafts are to be used. For drilled shaft foundation supply the
appropriate strength limit loads at the top of the shaft to the Geologist.
The geology report gives recommendations as to the type of foundation to be used at the site (i.e.
spread footing, piling, or drilled shaft). Other recommendations and information in the geology
report may include: minimum footing elevations, pile tip elevations, pile type, bearing capacities,
subsurface soil profile, soil parameters for lateral loads, water table elevation and discussion of
conditions which may be encountered during construction.
In many cases pile supported footings will be recommended. The piling may be precast concrete,
steel H-pile, or steel pipe pile using cast-in-place concrete. Where scour is not a concern and
rock with adequate bearing capacity is found near the surface, spread footings may be recommended. When rock is not near the surface, a footing supported on drilled shafts may be recom-
Bridge Section
10 - 1
Design Manual
mended. When drilled shafts are used, the designer will supply the Geology Section with the top
of shaft factored dead loads and lives loads so the shaft may be sized.
The bearing resistance for the material below spread footings or the axial load capacity for piles
or shafts will be provided in the foundation recommendations.
Recommendations may specify that a waiting period be provided after the placement of an
embankment in order to allow settlement to occur before starting construction of a substructure.
In some cases, a surcharge embankment, to be removed after the waiting period, may also be recommended as a means of accelerating the rate of consolidation.
If long term settlement is expected, pile downdrag will be considered. Unless piles are isolated
from the settling material settlement will introduce downdrag in the piling due to side friction.
The amount of downdrag to consider will be specified in the Foundation Recommendations.
To ensure that foundations will have the capacities anticipated during design, testing or observations are made before and during construction. These construction controls consist of bore hole
testing for spread footings, KDOTs pile driving formula, Pile Driving Analyzer (PDA) testing, or
Investigative Core Holes and Cross-hole Sonic Logging (CSL) for drilled shafts. The foundation
recommendations will identify the construction controls to be used for the project. The designer
will identify on the Geology Sheet and include the bid items required for the investigations and
construction controls.
For bridges on the local road system, the local agency or their consultant will retain a private geotechnical engineering firm to prepare a foundation recommendations report. The report will summarize the geotechnical conditions, the proposed bridge structure, and recommend a foundation
type.
10.2 Footings
In accordance with KDOT policy, footings will not be founded on soils, but be set on a solid
foundation (rock), or on piles driven to solid foundation, on piles driven to a friction bearing
below the maximum anticipated scour or drilled shafts with rock sockets.
The depth of footings below ground line shall be determined by considering the depth of the frost
line, the character of the foundation material and the possibility of undermining. Maximum depth
of frost in Kansas is 2-6 to 3-0.
Footings for streams exposed to erosive action should have the bottom of footings or the top of
piles founded a minimum of 6-0 below stream bed. This depth should consider the location of
the footing relative to the channel, if placed away from the main channel and there is no signs of
degradation this recommendation may be considered overly conservative. Determining the
elevation of the bottom of footings located in channel changes which interrupt the normal stream
gradient, or meandering streams and sand bottom streams requires special consideration. The
geology report will recommend a location of the footing on formation to support the imposed
load. However the designer must place the footing at a location he determines will support the
Bridge Section
10 - 2
Design Manual
Bridge Section
10 - 3
Design Manual
Bridge Section
10 - 4
Design Manual
achieve proper top-of-pile elevation without have to splice a small segment to embed the piling
the required amount. The designer should include this cut-off amount in the quantities for piling.
1
2
M cr = --- b h f r
6
where f r = 0.37 fc
Bridge Section
10 - 5
Design Manual
to Articles 5.13.3.6, for the location of critical sections for shear and for the load for pile location.
For beam action (one-way) shear the resistance can be calculated by method of sections.
Because there will be no prestressing or shear reinforcement the controlling nominal shear resistance as given in Article 5.8.3 as:
V n = 0.0316 f' c b v d v
For footings where the distance from zero shear to the face of the column is less than 3 d v or there
is no transverse reinforcement = 2.0 .
The factored shear resistance is V r = V n = 0.90V n
For punching (two-way ) shear the factored shear for two-way action must be adjusted in
accordance with Article 5.13.3.6.3 This adjustment is by the ratio of the lengths of the long and
short sides of a rectangular column and a reduced allowable punching shear stress must be used.
When individual loads overlap or project beyond the edge of the member the critical portion is
that is the smallest envelope that will actually resist the shear and is given by:
V n = 0.063 + 0.126
------------- f'c b o d v 0.126 f'c b o d v
Where:
c = ratio of the long side to short side of the rectangle through which the
concentrated load or reaction force is transmitted
b o = perimeter of the critical section
d v = effective shear depth
b v = effective shear width
One-way and two-way shear in footings is illustrated graphically in the following pages.
A design example for a spread footing can be found at Appendix A EXAMPLE: Spread Footing Design
A design example for a pile cap footing can be found at Appendix B EXAMPLE: Pile Cap
Footing Design
Bridge Section
10 - 6
Design Manual
Bridge Section
10 - 7
Design Manual
Bridge Section
10 - 8
Design Manual
10.5 Reinforcement
(a)
(b)
For ease of construction and detailing it is recommended where possible a 6" bar
spacing be used in all reinforced concrete footings.
(c)
The reinforcement in the long side as mentioned above and as specified should be
determined per Article 5.13.3.5 as follows:
1.
Compute total steel required (Ast) for short bars (long side).
2.
Compute As-BW = (2 Ast / (B + 1))B where As-BW is the total average steel
in the column band with in the short direction.
3.
Determine bar size for steel at 6" centers and equally space across footing.
The above recommendation will place an excess of reinforcing steel in the area
outside the column strip. However, for a majority of footings of the size generally
found on KDOT bridge footings, the ease of construction of all bars the same
spacing outweighs the savings in cost of the steel. At locations where a long span
bridge results in a large footing, the costs can be evaluated to determine if varying
the spacing would be beneficial.
(d)
When footings greater than 4-0 in thickness are used, the designer should
consider placing reinforcing steel (temperature distribution steel minimum) in the
top of the footing. Reinforcing should also be placed in the top of the footing when
the footing is in an uplift condition.
(e)
In pile foundations, minimum rebar clearance over the top of pile shall be 3".
Bridge Section
10 - 9
Design Manual
Bridge Section
10 - 10
Design Manual
Bridge Section
10 - 11
Design Manual
10.6 Piling
Piling is considered when the subsurface conditions are not suitable for spread footings to be
used. Since it is KDOT's policy to construct spread footings only on a rock foundation, the use of
piling is quite prevalent. Piles are also used as a protection against scour.
For a pile foundation to perform satisfactorily, the designer must study and evaluate carefully the
properties of the pile materials and the foundation materials around and beneath the piles to
determine the proper pile type and length. The geology report makes recommendations as to the
type and size of pile, pile tip elevation and factored resistances; however, this does not relieve the
designer of the responsibility to be aware of special conditions which might require further
investigation or a change in scope.
Piles may be classified in two main types, point bearing or friction. Realistically, there is usually
friction on pile and some point bearing at the pile tip. However, a pile which receives the majority
of its support from soil near its tip is a point bearing (end bearing) pile, and a pile which receives
the majority of its support by friction from the soil along its shaft is referred to as a friction pile.
When friction piles are used in a structure, at least one Test Pile Special shall be specified on the
plans. Depending upon the size of the structure, a test pile may be located at the abutment and
possibly one or more piers.
In the use of piling for a particular job, the selection of the pile type is dependent upon the
following factors: (1) the magnitude of the loads, (2) the properties of the foundation material, (3)
exposure conditions, and (4) economic consideration. Other considerations in determining the
choice of type of pile may include:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
Length required.
Bearing value desired per pile.
Experience with similar structures and conditions.
Value of a pile as a column if end bearing.
Resistance of piling to hard driving.
Minimum disturbance or maximum displacement of soil, if a factor.
Ease of driving at an angle if batter piles are required.
Presence of elements in foundation material which would be injurious to certain types of
piles.
Need to splice pile in field.
The capacity of single piles may be evaluated by the structural strength of the pile and by the
supporting strength of the soil. From past experience with driven piles, the designer can be
confident for end bearing piles driven below ground, there is little danger of buckling. Even soft
soils can provide the small amount of lateral support necessary to prevent lateral buckling.
Bridge Section
10 - 12
Design Manual
When different size piling are used on a bridge, show separate bid items for each pile size in the
Summary of Quantities on the details.
Piles can be further classified by the material of which they are made, i.e., timber, steel, concrete
and composite piles.
Bridge Section
10 - 13
Design Manual
recommended. Pipe pile are considered concrete pile for bidding and on the Standard Pile sheet.
Open ended piling are okay to use in dense fine grained sands. Fill the area from the top of the
earth plug to the top of the pipe with concrete.
Bridge Section
10 - 14
Design Manual
manufactured with the use of welded plates. The KDOT Specifications adequately cover the
requirements for pile points.
Pile-Driving Formulas
Numerous dynamic pile-driving formulas have been developed based on the amount of
energy delivered to the pile by the hammer and the resulting penetration of the pile. See
Section 704 of KDOT Standard Specifications for Modified ENR formulas used by
KDOT. The basic assumption of these formulas is as follows:
Energy input = energy used + energy lost
WH = RS + Z
where W = weight of the falling hammer (or ram)
H = height of drop of W
R = ultimate resistance of the soil to penetration by pile
S = penetration of pile into soil per blow (set)
Z = sum of all energy losses due to any cause whatever
Therefore, by knowing the energy input (WH) and estimating the energy losses (Z), the
driving resistance (R) can be calculated from pile movement observations (S).
Because of the difficulty in estimating the many energy losses during pile driving, these
dynamic formulas can only approximate pile driving resistance. However, they are used
to determine when to stop driving a pile so the bearing capacity of the pile will be the
same as the other piles driven in the same subsoil.
Bridge Section
10 - 15
Design Manual
The ENR formulas already incorporate a safety factor, therefore, applying a safety factor
to the load is not necessary.
It should be noted for heavy piling (i.e. larger than HP14x102), the pile driving formulas
found in the KDOT Specifications may not be valid and the PDA should be used to verify
the pile loads. Specifications also require the gross energy to be 2.5 times the weight of
the pile in pounds (Section 704). In these cases, the designer must specify the required
minimum hammer energy on the plans.
(b)
Bridge Section
10 - 16
Design Manual
The Analyzer measures force and acceleration of the pile by attaching strain transducers and
accelerometers directly on the pile. For each hammer blow, data is fed into a small field computer
and calculations made based upon one-dimensional wave mechanics.
The PDA was developed to perform in a manner which can easily be used on a routine basis in the
field. The PDA can perform the following:
(a)
Calculate and display the Case Method Capacity.
(b)
Calculate and display driving energy delivered to the pile top.
(c)
Sensing and display the maximum force at the location of the measurement transducers.
(d)
Sensing and display the maximum velocity at the location of the measurement
transducers.
(e)
Scaling of the measured records and deliver the records to an analog tape recorder.
(f)
Display of measured force and velocity record in a form which can easily be evaluated.
(g)
Display of measured force and velocity records on a plotter for examination and
evaluation in the field.
A line printer on top of the PDA prints a line of digital output for each hammer blow. Specific
quantities include the following:
(a)
Maximum force, velocity, acceleration and displacement at the transducer.
(b)
Force resisting penetration.
(c)
Predicted static pile capacity.
Stress wave travel time.
(d)
(e)
Maximum energy transmitted to the pile.
(f)
Maximum computed tension in the pile.
(g)
Pile integrity check.
(h)
Hammer operating rate in blows per minute.
The primary use of the PDA is in driving friction pile. It has limited application for point bearing
pile unless a drive history in a particular material is desired or if cracked or damaged pile is
suspected.
The pile is driven to a blow count required at a specific site which yields a capacity of
strength I / Phi value to ensure that the pile has sufficient capacity.
Provides minimum pile length and penetration required.
(c)
Indicates if the contractors hammer is adequate to drive the pile and obtain desired
capacity.
(d)
Bridge Section
10 - 17
(e)
Design Manual
The PDA can be used in conjunction with a CAPWAP (Case Pile Wave Analysis Program)
program to develop a data base of soil and pile properties applicable to future WEAP foundation
solutions.
As mentioned earlier, the Geology Report gives recommendations for pile type, size, tip elevation
and allowable load. Normally, the Geology Section runs the WEAP Program, if necessary, to help
determine foundation recommendation.
The designer should refer to KDOT Specifications Section 704 for information on Test Pile
(Special) for requirements when the Pile Driving Analyzer is to be used.
References:
Recommended Practice for Design, Manufacture and Installation of Prestressed Concrete
Piling - PCI Journal, March-April 1977 Vol.22, No. 2, Page 20.
Steel H-Piles - U.S. Steel Corporation
Wave Equation Analysis of Pile Foundations, Weap86 Program, Volume I, II, III, IV; FHWA,
March 1986.
Bridge Section
10 - 18
Design Manual
118 Tons
___ Tons
Designer notes below are included in the plan notes, but not placed on the plans
*** The Designer will fill in the above ________ with the formation or elevation as provided in
the geology report.
Bridge Section
10 - 19
Design Manual
***When the PDA is used, the piles are driven to a strength/Phi resistance value.
*** The Pile Driving Formula Load is the value calculated from the pile formulas in the Specifications.
NOTE:
The Controlling Strength Limit is used because the Modified ENR Pile Driving Formulas used by
KDOT have a Factor of Safety between 5.0 8.0 built into them, and have not been calibrated to
the Nominal Resistance from the PDA driving RPDA. When the PDA is used in the field and the
blow count is established for a particular hammer the Nominal Resistance, Rn = Strength/Phi
resistance value is used because the PDA has no built in Factors of Safety but, measures the actual
forces and stresses. When the PDA is used the minimum driving resistance is RPDA, and the maximum driving force is 110% RPDA.
NOT9301 shown incomplete for example purposes
LRFD DESIGN PILE LOAD:
Design Loading (Tons/Pile) Strength I Service I
Phi
Abutment 1
118 tons
69 tons
0.65
Piers
_________ _________ ________
*** The designer will fill in the ____ above for the controlling limit state. The value of Phi is in
the Geology Report.
NOTE:
The information above clarifies the service conditions and reports the Strength Limit State, when
the PDA is used the Nominal Resistance can be calculated by the Geologist.
The PDA requested on the Geology Report accompanies the bid item, "Test Pile Special", and
designer will add an additional 10'-0" to the pile length to allow for the gages to be installed.
Bridge Section
10 - 20
Design Manual
10 - 21
Bridge Section
Design Manual
The footing would have short piles (10 foot or less) and it is unlikely penetration of
the piles could be obtained to anchor the ends of the pile without pre-drilling.
(b)
The water table is relatively high and thus, to construct a footing on formation, a
deep cofferdam would be needed. Previous experience may also indicate a
cofferdam would be difficult to seal.
(c)
A spread footing foundation would be uneconomical because the depth of the rock
formation would require an excessive amount of shoring and excavation.
(d)
There are concerns about pile driving vibrations, noise or overhead clearance.
For bridge construction KDOT utilizes four bid items for drilled shaft construction:
Drilled Shaft (size)(cased) or Drilled Shaft (size) ,
Permanent Casing (size)(Set Price),
Sonic Test (Drilled Shaft)(Set Price)
Core Hole (Investigative).
A cased Drilled Shaft may be constructed with a heavy walled temporary casing and with a thin
walled CMP permanent casing depending upon the site conditions. In many instances the
Contractor will elect to use a heavy walled permanent casing to speed the construction of the
shafts. The geology report may indicate the use of only a heavy walled permanent casing for
special site conditions. The designer will add this information to the plans if directed to do so.
KDOT does not allow the construction of drilled shafts using temporary casing.
Uncased construction of drilled shafts are used only when bedrock is at the surface and the excavated shaft is expected to be stable and no caving soil or excess water flow is anticipated. This
method of construction is mainly used on smaller drilled shafts such as those used for sign support
foundations.
For High Mast Light Towers and Overhead Sign Structures construction the drilled shaft may be
cased or uncased. There is not a bid item and the drilled shaft is not paid for or measured in the
field.
The geology report will indicate which of the drilled shafts will have the bid item Core Hole
(Investigative) used. A core hole is drilled with NX sized drilled and retained in the field to
compare the material at the rock socket tip elevation. If the site is geologically uniform in nature
then the geologist may require only one core hole on the site. However, if the site is non-uniform
Bridge Section
10 - 22
Design Manual
or is varied, the geologist may have one or two core holes per bent. Based on the directions from
the geology report, it is the designer responsibility to place Core Hole (Investigative)on the
Geology Sheet.
The bid item Sonic Test (Drilled Shaft)(Set Price) is added by the designer and is used for
Cross-Hole Sonic Logging (CSL). In general, the rules the field follow for which shafts to test
are: All wet pour drilled shafts get CSL tested and the first pour of any different pouring method
gets CSL tested. The designer will detail the number of CSL tubes to be included in each shaft.
Usually the shafts are drilled to rock and then socketed a minimum of 1 times the diameter into
the rock. 1 times the diameter is a minimum embedment for the shaft to be considered a fixed
support for structural analysis. When the shaft cannot be located or is not located 1 diameters
into a sound un-weathered formation, the condition of the support can be assumed as pinned for
structural analysis. In most cases, locate the tops of the drilled shafts casings above the ground
line or above the Ordinary High Water line to eliminate the need for cofferdams, seal course or
structure excavation and to facilitate the placement of concrete.
On wet pours (concrete placed underwater), debris and water from the bottom of the shaft rises to
the top as the shaft is filled with concrete. The Contractor removes this debris, excess water and
unsound concrete from the top of the shaft by overfilling the casing until clean, sound concrete is
apparent. Locating the top of the casing above the ground line allows the Contractor to more
easily accomplish this task.
In streams, locate the top of the casing above the Ordinary High Water so the Contractor does not
have to provide cofferdams to construct the drilled shafts. The bottoms of web walls are normally
located 1 foot above Ordinary High Water. When the channel could migrate laterally, the bottom
of the web wall will be located below the existing ground line. In this instance, the top of the
drilled shaft casing cannot extend above ground line because it is preferred to have the top of the
shaft located below the web wall. In this case, additional excavation beyond the minimum may be
required to provide the contractor sufficient room to construct the columns and web wall. Place a
note on the plans alerting the Contractor to the fact additional excavation beyond the minimum
may be required. Additional work necessary to complete the task is subsidiary to the Pay
Quantity.
10.7.1 Design
Drilled shafts are designed to transmit axial loads to a rock foundation material and to resist
bending due to lateral loads.
The design of drilled shaft foundations is somewhat empirical as far as soil-shaft or rock-shaft
interaction is concerned. With many foundation materials, it is difficult to simulate in the
laboratory the in-situ environment due primarily to the problem of obtaining undisturbed
samples of the material. Transfer of axial load from the shaft to the supporting material is
Volume III US (LRFD)
Version 1/14
Bridge Section
10 - 23
Design Manual
dependent upon interrelated factors such as subsurface conditions, the geometry and structural
features of the shaft, method of construction, and elapsed time after construction.
The skin friction along the length of the shaft in soil is relatively small since the drilled shaft is
unlike a driven pile where the surrounding soil is compacted. For this reason the skin friction of
the shaft in soil is neglected. A drilled shaft is usually designed as a compression member with the
load carried by side friction on the rock plus the rock end bearing capacity. Side friction values
and end bearing values are recommended in the geology report.
The behavior of a drilled shaft under lateral load is largely controlled by the flexural stiffness of
the pier relative to the stiffness of the material surrounding the upper portion of the shaft and also
upon the degree of shaft head fixity. The geology report will give p-y curve data for each of the
layers that the shaft is passing through. The designer can use this data to determine what spring
constants to be used in the structural modeling of the shaft. In modeling the shaft this way the
resistance of the shaft is not focused on a fixed point, as when one assumes a point of fixity a
certain distance in the founding rock socket, but spreads the lateral load over a greater length of
the shaft. This can be more beneficial when the shaft is passing though shale layers that would
normally not be considered a point of fixity, but do offer some lateral resistance.
Example information from Geology Report: Heebner Shale Member based on 4.0 foot drilled
shaft:
YP (I,J)
0.0000
0.0016
0.0096
PP (I,J)
0.0000
873.600 k/ft
1092.000 k/ft
K spring
k
1092 ---ft
k
k
= -------------------- 1.0ft = 113, 750 ---- = 9, 479 ----0.0096ft
ft
in
The above spring constant can used in the structural model per foot length of drilled shaft within
that geologic zone, this can be done for each geologic zone for a drilled shaft.
10.7.2 Details
Drilled shafts used on KDOT bridges will normally be a minimum of 3 in diameter since this is
about the minimum size which can be properly inspected.
As a minimum, the drilled shaft diameter will be at least 6" larger than the column it supports.
Likewise, the pier cap will be 6" larger than the column which supports it. This is for contractor
convenience and is considered sound detailing practice for constructability.
Bridge Section
10 - 24
Design Manual
The clear spacing between vertical bars of the reinforcing bar cage should be three to five times
the size of the maximum coarse aggregate. (Use 3" minimum clearance.)
The outside diameter of the assembled rebar cage will have a minimum clearance Figure 10.7.32 Drilled Shaft Dowel Bars smaller than the casing diameter to permit the free flow of concrete
between the rebar cage and the hole and to provide adequate concrete cover.
Controlled free-fall concrete will be allowed in drilled shafts less than or equal to 4-0" in
diameter. Larger diameter shafts typically have cross-ties in the reinforcing cage. These cross-ties
will cause a problem with concrete segregation in a free-fall situation.
Use spiral reinforcing, with a pitch of 1-0, in the drilled shafts. Use hoops only when spiral
reinforcing is unavailable. Current maximum diameter of spiral reinforcing is 8 feet. See Figure
10.7.3-1 Plan of Drilled Shaft for additional reinforcing details.
Smooth steel casings used in the construction of drilled shafts shall be designated by specifying
the inside diameter. Casing is commonly available in 6" increments of diameter.
Standard diameters with available wall thicknesses are listed below.
Standard Tool Casings
Outside Diameter
Standard Available
Wall Thickness Range
18" thru 24
Corrugated metal pipe casings are designated by specifying the inside diameter.
The following is pertinent plan information relating to the different methods of drilled shaft
construction:
Uncased Drilled Shaft: (See Figure 10.7.3-3 Uncased Drilled Shaft - Dry Pour Method
Only)
The Geology report will indicate where this method can be used. It will typically be at
a site where the bedrock is very near the surface and no excessive water flow into the
shaft. Show a note on the plans: CONSTRUCT THE DRILLED SHAFTS USING
THE UNCASED METHOD. (See Standard Note 1100 DRILLED SHAFTS).
Bridge Section
10 - 25
Design Manual
Show the rock socket minimum length of 1 times the shaft diameter.
Cased Drilled Shaft: (See Figure 10.7.3-4 Drilled Shaft Construction Using Temporary
and Permanent Casing)
Show a note on the plans: CONSTRUCT THE DRILLED SHAFT USING THE
CASED METHOD. (See Standard Note 1100 DRILLED SHAFTS).
Show rock socket diameter and minimum uncased length of rock socket.
Do not show bid item: PERMANENT CASING. (The casing is subsidiary to the bid
item DRILLED SHAFTS and should be noted as such.)
Figure 10.7.3-5 Example: Permanent Casing Drilled Shaft Design is an example of a cased drilled
shaft design.
There has been some confusion concerning the bid items Drilled Shaft and Permanent
Casing. The following explanation clarifies our intentions:
When permanent casing is called for in the contract plans, the bid item Permanent
Casing is not shown on the plans. The casing is subsidiary to the bid item Drilled
Shafts and should be noted as such.
All other projects with drilled shafts require the bid item Permanent Casing. The price
will be set by the Construction Department in the proposal. If in the Engineers judgment,
actual construction conditions require a permanent casing be used, the Contractor will be
paid for the casing at the contract price.
In some cases, a Contractor may decide a permanent casing method is in his best interest
even though a permanent casing is not required by plan or, in the judgment of the
Bridge Section
10 - 26
Design Manual
Number of Pipes
4
5
6
7
8
Inspect the first wet hole on a project using Sonic Testing. Inspect dry holes if a problem is
suspected.
Woodland, R.J.; Gardner, W.S.; Greer, D.M., Drilled Pier Foundations, McGrawHill Book Co., Inc., New York, 1972.
2)
Reese, Lymon C., Handbook on Design of Piles and Drilled Shafts Under Lateral
Load, Federal Highway Administration, FHWA-IP-84-11, July, 1984.
3)
Bridge Section
10 - 27
Design Manual
Bridge Section
10 - 28
Design Manual
Bridge Section
10 - 29
Design Manual
Bridge Section
10 - 30
Design Manual
Figure 10.7.3-4 Drilled Shaft Construction Using Temporary and Permanent Casing
Bridge Section
10 - 31
Design Manual
Bridge Section
10 - 32
Design Manual
Bridge Section
10 - 33
Design Manual
1.25
1.75
1.75
1.00
P
1150
240
0
0
MT
0
1500
0
150
ML
30
250
65
0
Strength I Combination
Axial
Pu = 1.25(1150) + 1.75(240) = 1858 k
Moment about the transverse footing axis
MuT = 1.75(1500) + 1.00(150) = 2775 k-ft
Moment about the longitudinal footing axis
MuL = 1.25(30) + 1.75(45) + 0.33(450) = 551 k-ft
Try a 16 ft x 8 ft footing
Bridge Section
10 - 34
Design Manual
Bridge Section
10 - 35
Design Manual
square =
7.06ft = 2.66ft
Longitudinal Axis
Because only a small portion of the footing is outside the critical section, at dv away from the support, there is no need to check it.
Bridge Section
10 - 36
Design Manual
dv
The critical section for two-way shear is located at ----- away for the face of the support
2
dv
----- = 2.21ft
-------------- = 1.105ft
2
2
Load
Calculate the shear demand by using the bearing pressure times the net area
Pu
1858k
V u = ------------- A net = ------------------------ ( ( 8ft 16ft ) ( 10.87ft 5.21ft ) ) = 1036k
A total
8ft 16ft
Resistance
Calculate concrete shear strength Article 5.13.3.6.3
V n = V c = 0.063 + 0.126
------------- f' c b o d v 0.126 f' c b o d v
longside- = 8.66ft
c = ------------------------------------ = 2.89
shortside
3.0ft
2.89
k
Bridge Section
10 - 37
Design Manual
Pressure
P M uT c T
k
1858 2775 ( 8 )
k
q u ( trans ) = -----u ---------------- = ------------ -------------------- = 14.5 8.13 max = 22.6 -----2- min = 6.4 -----2128
2731
I
A
T
ft
ft
Load
Calculate the resultant forces
k
k
k
1
k
R1 = 18.9 -----2- 3.67ft = 69.3 ---R2 = --- ( 22.6 18.9 ) -----2- 3.67ft = 6.78 ---ft
2
ft
ft
ft
Calculate the moment
k----------- ft-
k
k
ft
M u = 69.3 ---- 1.84ft + 6.78 ---- 2.45ft = 144.1
ft
ft
Resistance
2
As fy
in
1.58 60 - = 2.32in
M n = A s f y d --a- a = ------------------ Try #8 @ 6 = 1.58 ------- a = --------------------------ft
2
0.85 12 4
0.85bf' c
1
2.32
M n = ------ 1.58 60 ( 2.21 12 ) ---------- = 200.3
12
2
k----------- ftft
k
ft-----------ft
k----------- ftft
= 186.2
k
ft-----------ft
1
2
1.2M cr = 1.2S c f r = 1.2 --- bh 0.37 f' c
6
1.2M cr
1
1
2
= ------ ( 1.2 ) --- 12 ( 2.5 12 ) 0.37 4 = 133
12
6
M r > 1.33 M u
k----------- ftft
OK Use #8 @ 6 spacing
Bridge Section
10 - 38
Design Manual
Pressure
P M uL c L
1858 551 ( 4 )
k
k
q u ( long ) = -----u ---------------- = ------------ ----------------- = 14.5 3.23 max = 17.7 -----2- min = 11.3 -----2128
683
IL
A
ft
ft
Load
Calculate the resultant forces
k
1
k
k
k
R1 = 15.7 -----2- 2.5ft = 39.2 ---R2 = --- 2.0 -----2- 2.5ft = 2.5 ---2
ft
ft
ft
ft
Calculate the moment
k
k
M u = 39.2 ---- 1.25ft + 2.5 ---- 1.67ft = 53.2
ft
ft
Resistance
k----------- ftft
in
Try #8 @ 6 = 0.88 ------- d v = 30 3 1 0.44
---------- = 25.78 = 2.15
ft
2
As fy
a
0.88 60
M n = A s f y d --- a = ------------------ a = ---------------------------- = 1.29in
2
0.85bf' c
0.85 12 4
1
M n = ------ 0.88 60 ( 2.15 12 ) 1.29
---------- = 110.6
12
2
k----------- ftft
k
ft-----------ft
k----------- ftft
= 70.8
k----------- ftft
1
2
1.2M cr = 1.2S c f r = 1.2 --- bh 0.37 f' c
6
1.2M cr
1
1
2
= ------ ( 1.2 ) --- 12 ( 2.5 12 ) 0.37 4 = 133
12
6
M r > 1.33 M u
k----------- ftft
Bridge Section
10 - 39
Design Manual
in
A s BW
in -
2 0.88 -----2
2A
ft
in
st
= ------------ = --------------------------- = 1.17 ------ + 1
ft
2+1
longside- = 16
= ---------------------------- = 2
shortside
8
in
Use #7 bars at 6 spacing A s = 1.20 ------- for the short bars in the longitudinal direction
ft
Use the required bandwidth steel for the entire length of the footing.
Crack Control
Service I Combination
Pu = 1.0(1150) + 1.3(240) = 1462 k
MuT = 1.3(1500) + 1.0(150) = 2100 k-ft
MuL = 1.3(250) + 1.0(65) = 390 k-ft
Service I Footing Pressure Loads
M uT c T
P
k
k
1462 2100 ( 8 )
q u ( trans ) = -----u ---------------- = ------------ -------------------- = 11.4 6.15 max = 17.6 -----2- min = 5.27 -----2I
128
2731
A
T
ft
ft
P M uL c L
1462 390 ( 4 )
k
k
q u ( long ) = -----u ---------------- = ------------ ----------------- = 11.4 2.28 max = 13.7 -----2- min = 9.13 -----2IL
128
683
A
ft
ft
Bridge Section
10 - 40
Design Manual
Load
Calculate the resultant forces
k
k
R1 = 14.8 -----2- 3.67ft = 54.2 ---ft
ft
Calculate the moment
k
1
k
R2 = --- 2.8 -----2- 3.67ft = 5.14 ---2
ft
ft
k
k
M uT = 54.2 ---- 1.84ft + 5.14 ---- 2.45ft = 112.3
ft
ft
Flexure longitudinal axis (short bars)
Load
Calculate the resultant forces
k
k
R1 = 12.3 -----2- 2.5ft = 30.7 ---ft
ft
Calculate the moment
M uT
1
k
k
R2 = --- 1.4 -----2- 2.5ft = 1.75 ---ft
2
ft
k
k
= 30.7 ---- 1.25ft + 1.75 ---- 1.67ft = 41.3
ft
ft
k----------- ftft
k----------- ftft
Bridge Section
10 - 41
Design Manual
Section Modulus
1
1
2
2
3
S c = --- bh = --- 12in 30in = 1800in
6
6
Depth of cover from tension face to reinforcing center
7
--8
d cL = 3 + 1 + --- = 4.44 for second layer #7 bars
2
8--d cT = 3 + --8- = 3.50 for first layer #8 bars
2
Reinforcing Stress
A
1.20 - = 0.0033
= ------s L = ---------------bd
12 ( 30 )
1.58 - = 0.0044
T = ---------------12 ( 30 )
E
n = -----s = 8
Ec
kL =
n + 2n n =
kT =
n + 2n n =
2
2
k
k
j L = 1 -----L = 1 0.4874
---------------- = 0.8375
j T = 1 -----T = 1 0.5581
---------------- = 0.8140
3
3
3
3
M uL
ksi
41.3 k ft ( 12 )
f ssL = ------------------- = -------------------------------------------------------- = 19.1
A sL j L d L
1.2 ( 0.8375 ) ( 2.15 12 )
M uT
ksi
112.3 k ft ( 12 )
f ssT = ------------------- = ----------------------------------------------------------- = 39.5
A sT j T d T
1.58 ( 0.8140 ) ( 2.21 12 )
Spacing
700
S --------------e- 2d c
s f ss
dc
s = 1 + -------------------------0.7 ( h dc )
4.44
sL = 1 + ---------------------------------- = 1.25
0.7 ( 30 4.44 )
3.50
sT = 1 + ---------------------------------- = 1.13
0.7 ( 30 3.50 )
Bridge Section
10 - 42
Design Manual
1.25
1.75
1.75
1.00
0.33*
DC/EV
LL
BR
WA
TU
P
700/50
250
0
20
0
MT
0
55
0
75
0
ML
30
0
45
0
450
Strength I Combination
Pu = 1.25(750) + 1.75(250) + 1.00(20) = 1395 k
MuT = 1.75(55) + 1.00(75) = 171 k-ft
MuL = 1.25(30) + 1.75(45) + 0.33(450) = 264 k-ft
Pile Cap Inertia
2
Rr
10x42
265k
0.65
172k
12x53
375k
0.65
243k
Bridge Section
10 - 43
Design Manual
Pile Loads
Max./Min. Pile Load: P/A + MC/I
k
4.91ft = 2.22ft
Bridge Section
10 - 44
Design Manual
1
Effective Shear Depth = d v = 42 12 3 --- = 22.5 assume a #9 bar will be used
2
One-Way Shear (Beam Shear)
2.22
Critical section at dv away from center of the equivalent column= ------------ 12 + 22.5 = 35.82
2
The piles are slightly outside the critical section, piles inside the critical section do not contribute
Calculate the contributing portion
35.82- = 1.5 %
% of pile outside = 36
-----------------------------12pile
Pile Loads
k
k
k
1395
k
k
( 2.5ft )
192
--------------- + 264
---------------------------- = ----------- V u = 192 3pile 0.015 = 8.6
8 pile
37.5
pile
Resistance
Bridge Section
10 - 45
Design Manual
d
Distance to Critical Section ----v- = 11.25
2
2.22
Distance from column centerline ------------ 12 + 11.25 = 35.82
2
Perimeter of critical section b o = 24.6 8 = 197
The piles are slightly inside the critical section, piles outside the critical section do not contribute
24 - = 97 %
Calculate the contributing portion -----------24.6
Load
k
Resistance
V n = V c = 0.063 + 0.126
------------- f' c b o d v 0.126 f' c b o d v
longside- = 1.0
= ----------------------shortside
k
0.126 f'c b o d v = 0.126 4 197 22.5 = 1122 Vn<Vu NG Try 4-0 footing thickness
Bridge Section
10 - 46
Design Manual
1
New Effective Shear Depth = d v = 48 12 3 --- = 32.5
2
d
Distance to Critical Section ----v- = 16.25
2
2.22
Distance from column centerline ------------ 12 + 16.25 = 29.57
2
Perimeter of critical section b o = 29.6 8 = 237
Piles outside the critical section do not contribute
24 - = 81 %
Calculate the contributing portion -----------29.6
Load
k
Resistance
V n = V c = 0.063 + 0.126
------------- f' c b o d v 0.126 f' c b o d v
longside- = 1.0
= ----------------------shortside
0.126 f'c b o d v = 0.126 4 237 29.6 = 1763
k
Bridge Section
10 - 47
Design Manual
1
Effective Shear Depth = d v = 48 12 3 --- = 32.5
2
d
Distance to Critical Section ----v- = 16.25
2
Perimeter of critical section length = ( 1.25 + 2.5 )12 + 12
-------- + 16.25 = 67.25
2
width = ( 1.25 )12 + 12
-------- + 16.25 = 37.25
2
b o = 67.25 + 37.25 = 104.5
Loads
Vu = 2 piles @ 203.4k= 406.8k
Resistance
0.126
V n = V c = 0.063 + ------------- f' c b o d v 0.126 f' c b o d v
= 67.25
---------------- = 1.81
37.25
k
V n = V c = 0.063 + 0.126
------------- 4 104.5 32.5 = 900.8
1.81
k
Bridge Section
10 - 48
Design Manual
Flexure Design
Pile Loads
k
k
1395 - 264 k ( 2.5ft )
-------------+ ---------------------------- = 192
----------8 pile
37.5
pile
k----------- ftft
k ft
-------------
ft
M u = 192 3piles 1.39 = 800.6
----------------------- = 106
7.5ft
2
As fy
in
1.20 60 - = 1.76
M n = A s f y d --a- a = ------------------ Try #7 @ 6 = 1.20 ------- a = --------------------------
ft
2
0.85bf' c
0.85 12 4
k
1
1.76
M n = ------ 1.20 60 32.5 ---------- = 189.7
12
2
k----------- ftft
k----------- ftft
k----------- ftft
= 140.9
k----------- ftft
1
1
2
2
= 1.2S c f r = 1.2 --- bh 0.37 f' c = 1.2 --- 12 ( 32.5 + 3 ) 0.37 4 = 186.5
6
6
M r > 1.33 M u
k----------- ftft
Bridge Section
10 - 49
Design Manual
Crack Control
Service I Combination
Pu = 1.0(750) + 1.3(250) + 1.00(20) = 1095 k
MuT = 1.3(55) + 1.0(75) = 157.5 k-ft
MuL = 1.0(30) + 1.3(45) + 1.0(450) = 118.5 k-ft
Service I Pile Loads
k
k
614 - = 81.9 k ft
M u = 147.4 3pile 1.39ft = -----------------7.5ft
Section Modulus
1
1
3
2
3
S = --- b h = --- ( 12in ) ( 32.5 + 3in ) = 2520in
6
6
7--d c = 3 + --8- = 3.4375
2
Stress
A
1.20 - = 0.0031 n= 8
= ------s = -------------------bd
12 ( 37.5 )
k =
n + 2n n =
j = 1 k--- = 1 0.4713
---------------- = 0.8429
3
3
Mu
ksi
81.9 k ft ( 12 )
f ss = ---------= 29.9
- = -------------------------------------------1.2 ( 0.8429 ) ( 32.5 )
A s jd
Spacing
700
dc
3.4375
S --------------e- 2d c s = 1 + -------------------------= 1 + -------------------------------------------------------------- = 1.1325
s f ss
0.7 ( h dc )
0.7 ( 37.5 + 3clr 3.4375 )
700 ( 1.0 ) - 2 ( 3.4375 ) = 13.79 > 6 OK
S ------------------------------1.1325 ( 29.9 )
Bridge Section
10 - 50
Design Manual
Bridge Section
10 - 51
Design Manual
Bridge Section
10 - 52
Design Manual
Bridge Section
10 - 53
Design Manual
List of Figures
Figure 11.2-1 Typical Abutment Connection to the Approach Slab ..............................................5
Figure 11.2-2 Abutment Aggregate Drainage System ....................................................................6
Figure 11.2-3 Abutment Strip Drain ...............................................................................................7
Figure 11.2-4 Integral Stub Type Abutment (Seismic Pile Connection) ........................................8
Figure 11.2-5 Free Standing Abutment with Counterfort ...............................................................9
Bridge Section
11 - 1
Design Manual
Appendix
Appendix A Structure Protection Guidelines .............................................................................106
Appendix B Example Calculations .............................................................................................117
Appendix C Sheet Pile Retaining Wall Example MathCadd .....................................................125
Appendix D Noise Abatement Policy .........................................................................................131
Appendix E Landscape Retaining Wall Policy Revision 1 ........................................................138
Bridge Section
11 - 2
Design Manual
11.2 Abutments
Types and Usage:
Abutments are used at the ends of bridges to retain the embankment and carry the vertical and
horizontal loads from the superstructure into the substructure.
Abutments fall into two general categories: the spill-through abutment and the retaining-wall
(vault) type abutment. A bridge with a spill-through abutment may require additional length to
cover the embankment slopes. However, spill-through abutments are considerably more economical, the comparative cost between a longer bridge with a spill-through abutment versus a shorter
bridge with a large wall-type abutment could be about the same. Spill-through type abutments
have proven to be relatively maintenance free elements and are preferred.
Abutments may be further categorized as either free-standing, with an expansion joint in the deck
slab, integral or semi-integral, with an expansion joint only in the approach slab. To eliminate
joints and reduce initial cost as well as ongoing maintenance costs, KDOT prefers abutments to
be integral or semi-integral with the superstructure wherever practical. In general, it is KDOT policy to use integral abutments on steel bridges up to 300 ft. in length and on prestressed bridges and
concrete haunched slabs up to 500 ft.. Semi-integral type abutments can be used up to the limits of
the expansion joints on the approach slabs.
Bridge Section
11- 1
Design Manual
Within the categories mentioned above the type of abutment to use for a particular structure is
normally governed by economics. Other factors that may be involved in selecting an abutment
type are the required channel area and section, minimum horizontal clearances, environmental,
length of bridge, type of geology, safety and aesthetics.
The basic types of abutments are:
Stub Type Cap on piling, drilled shafts or keyed into rock
U Type on piles or drilled shafts
Column Bent with or without web wall utilizing a pile cap or drilled shafts
Pile Bent with a web wall
If the length, along the centerline of the abutment, is greater than 90 ft., a 1 in. expansion relief
joint should be located between bearings near mid-length. On stage constructed abutments, a total
length of 120 ft. or less may be permitted without requiring a 1 in. expansion joint. For abutments
located on superelevation or transition elevation, the base of an abutment shall be constructed
level using reinforced pedestal bearing seats, if the difference between the low and high elevation
of the bridge seat is 10 in. or less. For a difference in elevation less than 20 in., the base of the
abutment cap shall be stepped with the reinforcement continuous through the transitions. For differences greater than 20 in., the base should be sloped to match the roadway cross-slope.
Provide a separation/ isolation from the thermal movements of the abutment and any adjacent
wall elements. Flexible elements (MSE Walls) and inflexible elements (Bridge Abutments) must
be allowed to move independently- KDOT has experienced instances when this idea was not followed, the results are repairs and/or constant maintenance issues. See section 11.6.1 MSE Design
Considerations for guidance. The designer will consider both longitudinal and transverse movements of the abutment and wall system.
Abutments under expansion joints (free-standing) shall have a multiple layers of protection
against the potential for leaking expansion joints sometime in the future. Use epoxy coated reinforcement in the abutment backwall and abutment beam. Slope the beam seat to drain and use
bearing risers to keep debris and water from ponding. All exposed surfaces of backwalls, bridge
seats, and front faces of pile caps will be coated with Substructure Waterproofing Membrane. For
cases involving both existing and new concrete, such as structure widening, apply this protection
to both new and old concrete.
Pile Orientation:
For integral abutments maintain a weak axis pile orientation that is perpendicular to the centerline of the bridge for bridge skew angles of 30 degrees or less.
Bridge Section
11- 2
Design Manual
For integral abutments with bridge skew angles greater than 30 degrees, maintain a weak axis
pile orientation that is parallel to the center line of the abutment.
For free-standing and semi-integral abutments, the strong axis of the pile will be placed parallel to the center line of the abutment.
Free-standing or semi-integral abutments can have up to half of the piles in any row battered and
oriented to resist horizontal earth pressures. Pile batter should be less than 3 to 12, horizontal to
vertical. The designer should check the placement of battered piles at the bottom of the abutment
beam so the edge clearance is not reduced below requirements.
Stub Type Cap abutments are the most commonly used type. They may be integral, semi-integral
or free-standing. Normally, only steel H-piles are allowed to be used in integral abutments
because of flexibility. Steel piles in integral abutments shall be placed with the weak axis
according to the pile orientation mentioned above.
U-Type abutments have wing walls which are parallel to the roadway, the wing walls should be
supported on piling or spread footings. This abutment type is used when grading around the
bridge is restricted and/or there are other geometric restrictions.
Column Bent abutments are used rarely and only where geology requires a spread footing or
when other special conditions exist.
Pile Bent abutments with a web wall are becoming more common on single span bridges. When
used with slab bridges that are designed and constructed to be integral, the moment resisting wall
can increase the efficiency of the structure.
Free-standing (expansion) abutments shall have a minimum backwall thickness of 1ft.. Freestanding abutments approximately 50 ft. and greater in length (measured along centerline
abutment) shall have a concrete lug or counterfort and pile at the mid-point of the abutment for
stability purposes. To resist lateral loads all free-standing abutments have some battered piles in
the row of piles closest to the bridge. Do not batter all the piles in a single row of piling, this can
cause significant bending stresses if the fill material settles.
Drainage:
Drainage often collects behind backwalls due to opening of the joint between the approach slab
and the slab rest or when the joint at the end of the approach slab leaks. Current practice is to
specify an abutment aggregate drainage system for structures with integral and semi-integral
abutments. The use of a traditional strip drain for Standard Haunched Slabs (RCSH) and other
abutment types is recommended.
Bridge Section
11- 3
Design Manual
Approach Slab:
All structures will be designed with an approach slab rest parallel to the abutment backwall.
Detail the approach slab to be attached to the abutment with reinforcement of suitable capacity
and spacing. See Figure 11.2-1 Typical Abutment Connection to the Approach Slab for details.
Allow the approach slab to float between the wings for U-Type abutment without a slab rest or
attachment to the wings. Approach Slab details can be found through KDOT Authentication and
Resource Tracking (KART) found at http://kart.ksdot.org/ and are labeled RD711 to RD715. For
joint openings greater than 4 in. a special design will be required. See Section 14 for details.
Bridge Section
11- 4
Design Manual
Bridge Section
11- 5
Design Manual
Bridge Section
11- 6
Design Manual
Bridge Section
11- 7
Design Manual
Bridge Section
11- 8
Design Manual
Bridge Section
11- 9
Design Manual
11.3 Design
Normal wings used on a stub type abutment (wings 90 to centerline roadway or that follow the
skew) are required on all bridges with integral abutments. Both semi-integral and free standing
abutments may be used with u-type or stub abutments, with the later being preferred.
Earth Pressures:
Abutments are typically supported on piles, drilled shafts, or spread footings in rock. Abutments
designed with a strip drain drainage system cannot provide the movement required to achieve
active soil pressure conditions. Therefore, the design backfill pressure for abutments should be
based on at-rest conditions. Abutments designed using an abutment aggregate drainage system
with geofoam wil provide enough movement to achieve active soil pressure conditions. If
geofoam is provide abutment wing walls will behave similarly to abutment backwalls, the
designer can assume active conditions, if not use at-rest conditions.
Active conditions are not appropriate for backfills containing cohesive materials. The remolding
properties of cohesive soil specifically, a clay backfill will exert at-rest pressures, the structure
will yield resulting in the earth pressure exerted by the clay reducing to active conditions, the
reconsolidation process will occur and earth pressures will increase to the at-rest condition and
the process with start over. It should be noted the use of a sand backfill is not recommended in any
condition due to its proclivity to not be free-draining because it accumulates fines and its
tendency to only achieve a densely compacted state under repeated dynamic loading, i.e., in
service under traffic loading.
The design pressures should include residual stresses caused by compactive efforts or stresses
from swelling pressures or excess hydrostatic pressures. Hydrostatic pressures should be included
used when the backfill material is not free-draining.
Live Load Surcharge:
Live load surcharges are minimized for abutment backwalls because of the inclusion of the
approach slab rest for straight type abutments, but because the approach slab floats between the
wings it should be included in wing walls which are parallel to the roadway.
Thermal Pressures and Force Effects:
Due to the length limitation imposed on integral abutment type bridges, abutment pile stresses are
normally not considered. KDOT has not observed excessive distress in the piling. However some
distress in the concrete has been observed in the wings of straight type abutments outside the
influence of the girders thrust; include additional shear reinforcement in these regions or extend
the geofoam over the abutment wings to eliminate this force effect.
The abutment piles can assumed to be fixed at about 15 ft. below the bottom of the abutment
beam for piles driven into sand and 10 ft. for piles driven into clay. Use these values when
building the abutment substructure models to determine the force effects from temperature
changes. For abutments on drilled shafts the point of fixity can be determined from using the
program SHAFT 6.0.
Live Loads:
Bridge Section
11- 10
Design Manual
11.4 Details
It is KDOTs preference not to pass utilities through the abutment backwall, but where conduit
extends through an abutment, provide horizontal dimensions from a working point to the location
where the conduit penetrates the front face of the abutment or the outside face of the wingwall.
The elevation at mid-height of the conduit should also be provided. Contact KDOT Bridge Management whenever a utility is placed in a bridge substructure.
Use preformed anchor bolt holes for bearing devices to prevent drilling or cutting into the reinforcement.
For presentation clarity, detail abutments with complicated layouts on separate sheets. Identical
abutments (except for minor elevation differences) may be detailed on common sheets.
For semi-integral abutments provide shear keys to guide the bridge movement and to restrain the
bridge laterally. The keys will be shaped to prevent the bridge from binding. Do not rely on the
bridge wings wall as the sole means of lateral support. See Figure 11.4-7 Semi-Integral with Shear
Key Guides for an example.
All reinforcement, except those completely in the footing, shall be epoxy coated. The minimum
size of longitudinal reinforcement in abutment and wingwall footings is No. 6 bars.
Provide shrinkage and temperature reinforcement per Article 5.2.6. For sections over 48 in. thick
provide a minimum of No. 5 bars at 1 ft.. Temporary construction loads may require additional
reinforcement.
For bearing pedestals over 2 in. tall provide both directions under the bearings. For pedestals with
a height of 2 in., only the transverse reinforcement is required. Horizontal steel in pedestals
should have 2 in. of clear cover to bridge seat. Provide a minimum of 2 in. of clear distance
between anchor rods and reinforcing tie bars.
See Section 9.8 for negative moment reinforcing steel requirements when using integral
Volume III US (LRFD)
Version 1/14
Bridge Section
11- 11
Design Manual
Bridge Section
11- 12
Design Manual
For all steel bridge integral abutments use the abutment beam rest shown in Figure 11.4-1 Pintel
Integral Abutment Beam Rest. If the structure is on a inclined grade greater than 2.0% then pintel
the beam rest and detail slotted holes in the bottom of the steel beams that capture the pintel bolt
and stabilize the beam from movements. This is described in Section 6.4.6 Integral Abutment
Beam Supports.
Limit the length of the wing wall cantilever to 8 ft.. Use piling to support longer the wings. For
detailing purposes provide a horizontal construction joint at the elevation of the concrete pile cap
because usually the upper portion of the wingwall is cast with the diaphragm and deck.
For free-standing abutments if the backwall is greater than 6 ft. tall or if the abutment is 40 foot or
greater in length then counterfort the backwall. Counterfort abutments will have at least one vertical pile or shaft for support.
For seismic requirements detail the connection between the piling and the abutment beam using
spiral reinforcement as shown in Figure 11.4-1 Pintel Integral Abutment Beam Rest. Tie the piles
to the abutment beam by detailing shear stud anchors or drilled holes with reinforcement to provide a positive connection.
For free standing abutments, include pedestals (bearing risers) under bearings and slope the
bridge seat between pedestals to provide drainage away from the parapet wall and bearings. A
standard seat slope provides one inch of fall from the back of the seat to the front of the seat. In
no case should the slope be less than 2 percent. Protect the bridge side of the back wall and the
bearing seat with a epoxy substructure waterproofing membrane.
Limit the maximum pedestal height to about 9 in.. The minimum pedestal height is 2 in. (at the
front of the pedestal). Set back pedestals a minimum of 1 in. from the front face of the abutment.
Curtain Walls:
Curtain walls extend perpendicular to the bridge side of the back wall to prevent soil from coming
in contact with the bearing devices on free standing abutments. If they are needed, curtain walls
should be considered as a viable means of protecting the bearings, bearing seats and shortening
the length of the wing walls. This is most appropriate for deeper girder bridges where the wings
can become excessively long or where the geometry would prevent proper grading of the berm
slopes. See Figure 11.4-5 Curtain Wall for details.
Bridge Section
11- 13
Design Manual
Bridge Section
11- 14
Design Manual
Bridge Section
11- 15
Design Manual
Bridge Section
11- 16
Design Manual
Bridge Section
11- 17
Design Manual
Bridge Section
11- 18
Design Manual
Figure 11.4-6 Counterfort Abutment With Curtain Wall and Battered Piles
Bridge Section
11- 19
Design Manual
Bridge Section
11- 20
Design Manual
11.5 Pier
11.5.1 General
A wide variety of pier types are used in bridge construction. The simplest may be pile bent piers
where a reinforced concrete cap is placed on piling. A more typical pier type is a cap and column
pier with columns supported on individual footings supporting a common cap. It is typical for cap
and column type piers with standard roadway widths have from three to five columns. Do not use
two columns to support a pier beam. The spacing of columns depends on the superstructure type,
the superstructure beam spacing, and the size of the columns. At ti wall piers may be used to support superstructures. Where extremely tall piers are required, columns may have a strut connection and between the columns near the lower one third of the columns to create frame action and
bracing. It is preferred for stream crossings not to place a pier in the main part of the channel, but
rather to span the channel with piers on the lower over-bank adjacent to the main channel.
Piers under deck joints (at unit breaks) shall have a multiple layers of protection against the potential for leaking expansion joints sometime in the future. Use epoxy coated reinforcement in the
pier cap. Slope the top of the beam to drain and use bearing risers to keep debris and water from
ponding. All exposed surfaces of the top of the pier beam will be coated with Substructure
Waterproofing Membrane. Coat the sides of the pier beam for a distance of 12 in. from the top to
promote a vertical flow. For cases involving both existing and new concrete, such as structure
widening, apply to both new and old concrete.
Protect columns in areas near vehicular splash zones. Columns located near the traveled way or in
urban areas where tunnel like effects are created by wider multilane overpasses the constant
spray or mist contacting the column surfaces create the potential for corrosion. For columns in
splash or spray zones use a minimum of 3 in. of cover and epoxy coated reinforcement for the longitudinal and spiral reinforcement.
Bridge Section
11- 21
Design Manual
Pile bents may be constructed of prestressed concrete pile or steel H-piles. Piles for pile bents
shall penetrate not less than 1/3 the unsupported length of the pile (unless refusal is encountered)
nor less than 10-0 into hard cohesive or dense granular material. For pile bent piers the
unsupported length shall be defined as the portion of the pile from ground line ( or scour line) to
the bottom of the pier cap or wall.
Piling exposed to a corrosive environment should be protected .
In the structural analysis of pile bents, a determination needs to be made as to the depth below the
ground surface at which the piles may be considered fixed. Refer to Vol. I, Chapter 10 of the USS
Highway Structures Design Handbook for a method to estimate the depth of fixity. See Vol. II,
Chapter 11 in the above reference for a design example. Another method to estimate the depth of
pile fixity was presented in the December 1976 issue of the ASCE Civil Engineering Magazine
The Equivalent Length of a Pile or Cassion in Soil by Peter Kocsis.
The reinforced concrete caps for pile bents shall have a minimum width of 2-6. For the design
of pile bent piers which are based on the assumption of a rigid connection (100% fixity) between
the piling and pier beam, a minimum pile embedment of 1 D is recommended (D = nominal
diameter). Punching shear in the pier beam shall be checked at the pile location.
The pile embedment of 1 D is the result of research done by the U.S. Army Corps of
Engineers**. Note, the referenced report was conducted using computer modeling and not
physical testing. The report assumed a side cover of 1D and analyzed pile spacings up to 5D. The
report noted a 1ft. embedment produced a fixity ranging from 61 to 83%. The conclusion of the
report indicated an embedment of 2D would provide full fixity. A minimum of 1 D is
recommended at this time. Provide a side cover minimum of 6 in. to approximate the behavior of
the test model.
**
Fixity
A pile encasement wall shall provide a concrete cover of at least 6 in. to the pile with an overall
minimum thickness of 2 ft.. KDOT specifications allow a variation of 2 in. in the head of the pile
after driving. This should be considered in setting wall width. The encasement wall is not
considered structural, however, a nominal amount of reinforcing steel should be provided so the
wall stays in place. The recommended minimum reinforcement is #4 bars horizontal and vertical
at 1-6 centers with #3 cross ties at 4-6 center to center both vertical and horizontal. The cross
ties should have a 180 hook on one end and a 90 hook on the other end. See Figure 11.5.7-12
Pile Bent with Web Wall
Bridge Section
11- 22
Design Manual
Bridge Section
11- 23
Design Manual
Pier beams should normally be 6 in. wider than the column (3 in. overhang on each side of the
column).
For bridges where the skew angle does not exceed one degree, the designer should consider a
right angle bridge with skewed columns. To keep equal span lengths, the pier cap is constructed
square and widened to accommodate the skewed columns. Where bearing pads or plates are used,
the beam edge clearance should not be less than 6 in.. For skews greater than one degree but less
then five degrees, with approval, this type of layout may be considered but the pier cap should not
exceed the column dimension by more than 18 in.. The eccentricity of the column load must be
considered as well as the economy of the extra material used. Where horizontal clearance is a
factor, the designer must also check the clearance to the pier cap to see if it falls below the
required vertical clearance.
Pier beams on free standing piers with bridge seats exposed to deck or joint drainage should have
epoxy coated steel. The top surface should be coated with a waterproofing material such as
Substructure Waterproofing Membrane.
Preferably, elastomeric pads should be placed on a raised concrete step. The reinforced step shall
be a minimum of 3ft. and a maximum of 8 ft. high.
11.5.7 Details
To facilitate the use of standard forms, detail round and rectangular pier columns and pier caps
with outside dimensions that are multiples of 2 in..
In general, the column should be reinforced to between 1% and 2% reinforcing steel. Size the
column to accommodate these percentages.
When laying out piers, consider the economy to be gained from reusing forms (both standard and
non-standard) on different piers constructed as part of a single contract.
Dimension piles, footing dimensions, and center of columns to working points.
For pier caps (with cantilevers) supported on multiple columns, space the columns to balance the
dead load moments in the cap.
Label the ends of piers (South end, North end, etc.). Add a separate sheet with only substructure
layout information for bridges with complex geometrics.
The minimum column diameter or side of rectangular column is 2'-6"
Slope pier caps in a straight line and utilize concrete pedestal beam seats when possible. Pedestals shall be set back at least 1 in. from the edge of cap and be no taller than 9 in.. Consider
omitting pedestals if their height is less than 1 in..
Bridge Section
11- 24
Design Manual
Choose a pier cap width and length that is sufficient to support bearings and provide adequate
edge distances. As a guide, choose a pier cap depth equal to 1.4 to 1.5 times the width.
The bottom of the pier cap should be approximately parallel to the top. Taper cantilever ends
about 1/3 of the depth of the cap. When round pier columns are required, use rounded pier cap
ends as well. The ends of pier caps for other types of pier columns should be flat. Detail solid
shaft (wall) piers with rounded ends for both the cap and shaft.
Integral Steel Box Beam Pier Caps:
Avoid the use of steel box beam pier caps whenever possible. Conventional concrete pier caps or
prestressed / post-tensioned caps are preferred.
To ensure that components are constructible, review the design details of box beam pier caps with
the fabrication inspector early in the plan development process. Plan to create a Project Special
Provision that requires full shop assembly and a procedure created from the full assembly. As a
minimum require 25% pinned and 50% fully tightened bolts for the assembly.
The minimum dimensions of a box pier cap are 3ft. wide by 4'-6" high. Make access openings
within the box as large as possible and located to facilitate use by inspection personnel. The minimum size of access openings in a box pier cap is 18" x 30" (with radius corners.).
Provide access doors near each end. If possible, locate the door for ladder access off of the roadway. Orient the hinge for the access doors such that doors swing away from traffic. Access doors
can be placed on the side of box pier caps if they are protected from superstructure runoff. If not,
locate in the bottom of the cap.
Bolted internal connections are preferred to welded connections. Fillet welds are preferred to full
penetration welds.
Avoid details that may be difficult to fabricate due to clearance problems. Assume that welders
need an access angle of at least 45 degrees and require 18 in. of clear working distance to weld a
joint. The AISC Manual of Steel Construction contains tables with entering and tightening clearance dimensions for bolted connections.
Paint the interior of boxes white for inspection visibility and for corrosion protection. Provide
drainage holes with rodent screens at the low points of the box.
Piers Adjacent to Railways:
Piers located within 50 ft. of the centerline of railroad tracks are not required to have crash walls
incorporated into their design. Article 3.6.5.1 eliminated that requirement.
Piers located within 25 ft. of the centerline of railroad tracks must have crash walls.
Crash walls must meet the following geometric requirements: (AREMA 2.1.5.1 and C-2.1.5.1)
Bridge Section
11- 25
Design Manual
Top of crash wall shall extend a minimum of 6 ft. above top of railroad track when pier is
between 12 ft. and 25 ft. from centerline of tracks and 12 ft. above top of railroad track when
pier is 12 ft. or less from centerline of tracks.
Bottom of crash wall shall extend a minimum of 4 ft. below ground line and 6 ft. below
the base of the rail.
Crash wall shall extend one foot beyond outermost columns and be supported on footing.
Face of crash wall shall be located a minimum of 6 in. outside the face of pier column or
wall on railroad side of pier.
Minimum width of crash wall is 2.5 ft..
Minimum length of crash wall is 12 ft..
See Figure 2.2.3-3 Crash Wall Details for a graphic of the above criteria.
Bridge Section
11- 26
Design Manual
Bridge Section
11- 27
Design Manual
Bridge Section
11- 28
Design Manual
Bridge Section
11- 29
Design Manual
Bridge Section
11- 30
Design Manual
Bridge Section
11- 31
Design Manual
Bridge Section
11- 32
Design Manual
Bridge Section
11- 33
Design Manual
Bridge Section
11- 34
Design Manual
Bridge Section
11- 35
Design Manual
Bridge Section
11- 36
Design Manual
Bridge Section
11- 37
Design Manual
Bridge Section
11- 38
Design Manual
Bridge Section
11- 39
Design Manual
Bridge Section
11- 40
Design Manual
11.5.8 Columns
Columns may be circular (preferred), rectangular, or variable in section. The minimum
recommended diameter for a round column is 2-6. Larger diameters should be in 6 in.
increments. The recommended minimum size of a square column is 2 ft.. Size the columns to be 6
in. smaller than the outside shaft for the construction purposes.
Columns shall be designed as tied columns. For compression controlled = 0.80 allowing for a
variation from the column value to the flexural value of = 0.90 for tension controlled, pure
bending as the axial load strength decreases from 0.8[0.85 fc (Ag-Ast+fy*Ast)] or Po, whichever
is smaller, to pure bending with no axial load.
KDOT, in partnership with KSUs Civil Engineering Department, has produced useful software
for the design and analysis of reinforced concrete columns for bridge structures. This software is
available for download and use through KDOT Authentication and Resource Tracking (KART)
found at http://kart.ksdot.org/. The software has the ability to analyze the design, unconfined and
fully confined sections of a column. For new construction the designer should limit the load
points (moment and axial) to fall within the design interaction curve.
See Article 5.7.4.2 for reinforcement requirements of compression members. The minimum
reinforcement shall be 1% of the gross area of the column or per Equation 5.7.4.2-3 which ever is
larger. The KDOT preferred lateral reinforcement in round columns is the spiral tie with a 6"
pitch. Currently, the maximum diameter of spiral reinforcing is 72 in.. For square, rectangular or
large diameter columns (> 6 ft.) use individual lateral ties with a maximum spacing of 1 ft.. A
closer spacing should be used near the junction of the column with the beam or footing.
Reinforcing dowels projecting from a spread footing are normally provided extra long. This is to
provide adequate splice length in the event the footing has to be lowered slightly in the field due
to adverse foundation conditions.
Columns on bridges which come in contact with salt water drainage or spray are required to have
some form of protection. Protection may be in the form of extra concrete cover over the
reinforcing steel, use of a concrete sealer or, in some cases, epoxy coated bars may be used.
See 3.4.4 Thermal Force Considerations for a brief explanations of modulus of elasticity to be
used in the computation of thermal stresses in the columns, a value of one-third of that used in
dynamic loads can be used.
Columns for structures located in KDOT Seismic Zone IB or IC will have additional
reinforcement located at the top and bottom of the column extending into the pier beam or footing
to form plastic hinge zones per Figure 3.4.8-1 FLOW CHART FOR SEISMIC LOADS
See Appendix B Example Calculations: for a method to compute stresses in columns due to
change in deck length and the distribution of forces to each pier.
Bridge Section
11- 41
Design Manual
Live Load
The live load is the HL-93 truck or tandem loading which must be checked for the
H.E.T. load rating and may control. The lane loadings are assumed to occupy a
width of 10 ft. and are placed anywhere within the 12 ft. design traffic lane as to
produce the maximum stresses in the pier. When a pier is loaded with three or
more design traffic lanes the live load is reduced by a multiple presence factor.
When there is only one design traffic lane the factor is 1.20. See Table 3.6.1.1.2-1
for the multiple presence factors.
Impact is included in the design of the pier beam and the columns, but not in the
design of the foundation if the entire element is below ground.
For girder type superstructures, live loads are transmitted to the pier through the
girders. Live loads are transmitted to the girders from the slab using simple beam
distribution. Care should be taken not to use the maximum girder reaction
(computed when designing the girders) at all girder locations on the pier beam, as
this will result in unrealistically high live load reactions.
For slab type superstructures, the truck and lane live load is applied to the pier
without transverse distribution. The truck load is applied as a concentrated load
and the lane load is applied as a uniform load. The reaction at the pier computed
using the live load distribution factor (E) needs to be factored back into a single
wheel line reaction.
Piers adjacent to railroad tracks may require a crash wall. See Figure 2.2.3-3 Crash
Wall Details for a graphic describing the conditions and criteria for use.
(b)
Dead Load
Dead loads include the estimated weight of the superstructure (including estimated
future wearing surface), the dead weight of utilities and the weight of the
substructure.
(c)
Bridge Section
11- 42
Design Manual
Breaking Force (BF) = The greater of: N [640 x BL) + DT] (0.05) (m) or
N (DT) (0.25)(m) (BF in lbs.)
N = number of lanes likely to become one directional in future.
BL = over-all bridge length (ft.)
m = multiple presence factor (Article 3.6.1.1.2)
DT = design Truck or Tandem
This force is meant to simulate the forces caused by vehicles braking or
accelerating. It is to be applied 6 ft. above the floor. When this force is applied to
free-standing skewed piers, the transverse component (to centerline of pier) is
applied 6 ft. above the roadway and the longitudinal component (to centerline of
pier) is applied at the bearings.
BF to each pier =
BF
x Average Span Length
Bridge Length
(d)
Wind Loads:
Wind loads are divided into three types; (1) wind on live load, (2) wind on
superstructure, and (3) wind on substructure.
Wind loads include transverse and longitudinal loads which may act on both the
piers and the superstructure including wind load on bridge mounted signs and on
live loads.
For most usual girder and slab bridges use the wind loading as specified in Article
3.8.1.2.
(e)
Temperature
Use method A for calculating Temperature Ranges. See LRFD Section 3.4.4 for
usage and considerations of thermal force effects. The change in length of the
superstructure and pier cap due to temperature changes causes deflections in the
columns. These deflections result in moments in the columns. The magnitude of
the design moment will depend on the amount of deflection, length and size of
column and the fixity assumed at the column ends. See Appendix B Example
Calculations: for stresses in monolithic piers due to thermal forces.
For continuous structures with the pier columns monolithic with the
Bridge Section
11- 43
Design Manual
superstructure, there is a neutral point on the bridge which does not move when the
temperature changes. This point needs to be determined either by examination or
by trial and error taking into account column stiffness.
For a continuous structure resting on bearing devices, the maximum longitudinal
load an expansion bearing device can transmit to the pier is the friction force. If the
longitudinal force exceeds the friction force, the excess is transferred along the
bridge to a fixed support.
The friction force acts parallel to the direction of movement and is assumed to act
at the bearing elevation at each expansion bearing.
For friction-type bearings, the longitudinal force is given by:
ks x DL
0.20
0.10
Table 14.7.2.5-1
For rocker bearings, the longitudinal rolling and sliding resistance is given by:
See Figure 11.5.9-1 below for further information
( 20r + 2 )
DL ---------------------100R
where: DL
r
R
The above formula assumes a sliding friction coefficient of 0.20. Use this value
when determining the force transferred to the bolster (fixed) pier. This low friction
value (0.2) assumes the rockers are new and will transfer the maximum force to the
bolster pier. For computing the friction force transferred to expansion piers, a
sliding friction coefficient of 0.5 to 0.8 may be assumed to simulate rockers which
have, over time, become rusty and partially frozen. Again, this will give the
maximum force which can be expected in the expansion piers.
Bridge Section
11- 44
Design Manual
Figure 11.5.9-1
Bridge Section
11- 45
Design Manual
When elastomeric bearings are used, the longitudinal force is given by:
G x A x Delta/T
where
G
A
Delta
T
=
=
=
=
The shear modulus G, varies with durometer, temperature and time. Use the
maximum value permitted based on a durometer of 60. See Table 14.7.6.2-1 for
shear modulus values.
The thermal force on a fixed pier is the resultant of the unbalanced forces acting on
all the substructure units. For cases where the unbalanced frictional force is equal
to zero, the fixed pier shall be designed for at least the total longitudinal force
applied to an expansion pier.
In some cases, it may be cost effective to use isolation bearings to control the
transfer of forces to the substructure. Isolation bearings are similar to an
elastomeric bearing with the addition of a lead core. By varying the size of the lead
core and the overall rubber height, the designer can manipulate the distribution of
horizontal forces to the substructure thus achieving reduced column and
foundation design forces. See AASHTO Guide Specifications for Seismic
Isolation Design, June 1991.
(f)
Seismic
See LRFD Section 3.4.8 and Section 5.1.6.3 for seismic detailing and
loading
All of Kansas is located in the Seismic Zone 1 which means no detailed seismic
analysis is required for bridges in Kansas. However, connection to the
superstructure from the substructure must be designed for specified forces and
must also meet minimum bearing support length requirements. The force effects
from accelerations must be transmitted from the superstructure to the foundation
through the anchorages. The connections between the footing and the column and
the column and the pier beam must be detailed accordingly. See Article 3.10.9.2
for information on Zone 1 force effects.
Bridge Section
11- 46
(g)
Design Manual
Ice Pressure
In the absence of more precise data, the following shall be used as minimum
design criteria:
1)
2)
3)
Ice loads would normally not be considered except on larger rivers such as the
Kansas or Missouri Rivers. The need to include ice pressure in the design of a
structure should be made at the field check.
(h)
Drift
Piers located in streams which are susceptible to transporting large amounts of
drift and debris shall be designed to withstand the corresponding increase in
stream pressure due to drift accumulation on the pier. The amount of drift build-up
is a matter of judgment, but as a guide, the size of the drift may be approximated as
follows:
(1)
(2)
The vertical depth could extend from the flow line to the computed
high water elevation.
Bridge Section
11- 47
(i)
Design Manual
Scour
Scour is not a load per se, however by changing the conditions of the channel its
effects need to be considered in the design of the substructure per Article 2.6.4.4.2.
The bridge should be fully functional while in a scoured condition for all Load
Combinations when subjected to a 100 year flood or less. Check the 100-year
flood, the overtopping flood (if less than the 100-year flood) and other events if
there is evidence such events would create deeper scour than the 100-year or
overtopping floods. Use strength and service combinations for the Design Flood
per Article 3.7.5
When checking the effects of a 500 year flood, the bridge should survive the
effects of stream flow, dead load, live load and wind load while in a scoured
condition. Consider the Extreme Event for the Check Flood without the ice load
when investigating this situation.
Stream forces shall be applied to a depth based on the scour evaluation. When
checking the lateral resistance of the piling or drilled shafts, no lateral support
from the soil above the estimated scour line shall be assumed.
See Section 2.3.9.3 Scour Analysis for further discussion on scour.
(j)
(k)
Dynamic Allowance
Do not apply the Dynamic Allowance (IM) to lane loads, pedestrian loads or to
foundation elements which are buried. Use a value of 33% for all limit states other
than fatigue per Article 3.6.2.
(l)
Centrifugal Force
This force effect applies only to structures which have radial forces. The
Centrifugal Force (CF) will be applicable for horizontally curved bridges
according to Article 3.6.3.
Bridge Section
11- 48
Design Manual
2)
Footing on pile:
a. With top of pier integral with superstructure = 0% fixity (pinned)
b. With top of pier hinged at superstructure or free-standing pier = 100% fixity
(fixed)
3)
For piers constructed integrally with footings and skewed more than 10, the
bottom of columns shall be considered fixed.
The pier is analyzed as a frame bent by the available analysis procedures considering sidesway of
the frame due to loading.
Volume III US (LRFD)
Version 1/14
Bridge Section
11- 49
Design Manual
11.6 Walls
The following 11.7 Wall Policy outlines policy concerning the review and acceptance of various
earth retaining structures and noise or sound walls.
Bridge Section
11- 50
Design Manual
Rails:
Railings should not be set directly on retained earth structures. Either set the railing inside the
wall or put a compressible material between the top of the wall and the bottom of the railing. MSE
walls used in conjunction with railing subject to vehicle impact shall be designed to withstand a
horizontal force of TL-4 loading distributed according to AASHTO Specifications. The maximum cantilever height above the earth reinforcement for top panels is 3.5 ft. including the coping.
Compatibility:
Designers are cautioned whenever a MSE wall is adjacent to a hard structural member (abutment,
footing, etc.). It is best to avoid this situation if possible. Avoid tying the MSE footing, the wall,
or a wall cap to unyielding members. The MSE wall could settle and crack anywhere it is tied to
or sitting on an unyielding member. One solution to the differential settlement issue is to provide
a slip joint in the wall between the yielding and unyielding members. See Figure 11.6.1-1 MSE
Retaining Walls (integral abutment < 2 of movement). Consult with KDOT Geotechnical Services about the use of slip joints.
Horizontal Movement:
When an MSE wall is used to retain fill at an abutment, the MSE wall should be a minimum of 8
ft. from the face of the abutment. This will minimize pressure on the wall from the potential pile
and abutment movement (temperature translation). Use a minimum of 9 in. of geofoam between
the MSE wall and abutment and use an Abutment Aggregate Drainage System behind the abutment.
The following guidelines are to be used when choosing abutment type adjacent to MSE walls:
For bridges with a total movement less than 2 in. and a skew angle of 30 degrees or less use
integral abutments with an isolation casing and cap, back fill the piles with pea gravel, leave
15ft. of the top unfilled per Figure 11.6.1-1 MSE Retaining Walls (integral abutment < 2 of
movement). Isolate the coping movement from the approach slab.
Use the bid item Cased Piles for integral abutments adjacent to MSE walls. This bid item is
measured from 5 ft. below the MSE wall to the bottom of the abutment beam. See Special
Provision.
For bridges with movements greater than 2 in. or skew angle greater than 30 degrees use a
free-standing abutment with counterforts, battered piles or U-Shaped abutments with piles in
the wing.
Use PTFE bearing devices with free standing abutments.
Embed the lower abutment beam to a maximum depth of between 1 and 2 feet within the
MSE mass.
The use of semi-integral abutments adjacent to MSE walls no longer be be used .
Vibrations:
When an MSE wall is used to retain fill at an abutment, it is KDOTs practice to drive abutment
piling before the MSE wall is constructed. Pile driving vibrations after MSE construction may
significantly consolidate the structural fill of the MSE wall.
11- 51
Bridge Section
Design Manual
tect the straps (reinforcing) of the MSE wall. See Figure 11.6.1-1 MSE Retaining Walls (integral
abutment < 2 of movement).
Downdrag:
At locations where downdrag forces on the piling are noticeable due to foundation settlement
(Note: read the Geotechnical Report) or where settlement may occur from pile driving in different
stages of staged construction, the piling should be coated with bitumen to reduce side friction. As
an alternate, the piling may be sleeved, the piling in those conditions should be reviewed for
performance of lateral movement (temperature) and unsupported length.
Backfill Limits:
Where the plans and Geotechnical Report require the wall to be constructed on fill, (generally fill
with specific strength requirements) note the limits of the special foundation soils on the MSE
wall details. The Road (earthwork) x-sections will show the same limits. In some locations, similar soil placement may be required behind the structural fill mass. Note these locations in the MSE
wall details and in the cross-sections.
Drainage:
In locations where drainage problems are anticipated or are of concern, use modular block type
MSE facia. Modular block will drain through the wall and do not require interceptors.
Bridge Section
11- 52
Design Manual
Bridge Section
11- 53
Design Manual
11.6.4 General
Information furnished by FHWA concerning application of the various earth retaining structures
should be considered as reference material in the selection of an appropriate system. Prefabricated wall systems (proprietary or generic) should be included in competition with conventional
reinforced concrete retaining walls where considered appropriate. In considering the use of proprietary walls, the Designer should, when requested, provide assistance to a wall supplier of an
approved system which can attain the project objectives. Special Provisions for earth retaining
structures will require proprietary wall suppliers to provide a qualified and experienced representative on the project site to assist the Contractor at the start of wall construction. For the duration
of construction of the project, the representative will be available on an as needed basis, as
requested by the Engineer.
In addition, the Supplier or his representative, must submit back-up material to include
the following:
(A)
(B)
(C)
(D)
Bridge Section
11- 54
(E)
(F)
(G)
(H)
(I)
(J)
(K)
Design Manual
After the above material is submitted, a thorough geotechnical and structural review will be performed concerning the design, construction practicality and whether or not the system would be
appropriate for the particular project.
Bridge Section
11- 55
5.
(B)
Design Manual
Concerning the cost of items influenced by the selection of one wall over another-1.
2.
3.
4.
Geometric
1.
2.
Subsurface investigation report including specific design values for the following
parameters:
1.
2.
3.
Bridge Section
11- 56
(C)
Design Manual
Design Requirements
1.
Generally, reinforced earth retaining walls would not be economical for wall
heights less than 10 ft..
2. For a permanent mechanically stabilized earth wall, the reinforcement
elements are to be designed to have an adequate corrosion resistancedurability for a minimum service life of 75 years.
3. Minimum safety factors shall be as follows: 2.0 for overturning, 1.5 for
sliding and 1.2 for temporary slope stability.
4. Determination of allowable bearing pressures should consider the flexibility
of the retaining system. In general, the minimum factor of safety for bearing
of soil foundations should be at least 2. This is the ratio of the ultimate
bearing capacity to the allowable bearing pressure in which the ultimate
bearing capacity is the maximum bearing pressure the foundation material
will sustain without exceeding the shearing strength of the foundation
material. Embedment depth and settlement is to be considered in the
analysis.
5. Internal design requirements for mechanically stabilized earth wall elements:
Allowable reinforcement material stress is 0.55Fy for steel. Safety factor
against reinforcement pullout should be 1.5. Pullout resistance should be
based upon the capacity achieved at a maximum deformation of inch.
6. Magnitude, location and direction of external loads due to bridges, overhead
signs and lights, traffic surcharge and rapid groundwater drawdown.
7. Limits and requirements for drainage features beneath, behind or through the
retaining structure.
8. Backfill requirements for both within and behind the retaining structure.
Both material and placement requirements should be specified to include
gradation, plasticity index, electrochemical, soundness, maximum loose lift
thickness, minimum density and required moisture content.
9. Special facing panel and module finish or color.
10. KDOT guidance concerning construction specification requirements or
special provisions.
Bridge Section
11- 57
Design Manual
A plan and elevation sheet or sheets for each wall, containing the following:
1.
2.
3.
4.
5.
6.
7.
An elevation view of the wall which shall indicate the elevation at the top of
the wall, at all horizontal and vertical break points and at least every 25 ft.
along the wall, elevations at the top of leveling pads and footings, the
distance along the face of the wall to all steps in the footings and leveling
pads, the designation as to the type of panel or module, the length, size and
number of mesh or strips and the distance along the face of the wall to where
changes in length of the mesh or strips occur and the location of the original
and final ground line.
A plan view of the wall which shall indicate the offset from the construction
centerline to the face of the wall at all changes in horizontal alignment, the
limit of the widest module, mesh or strip and the centerline of drainage
structures or drainage pipe which is behind or passes under or through the
wall.
General notes required for design and construction of the wall.
All horizontal and vertical curve data affecting wall construction.
A listing of the summary of quantities provided on the elevation sheet of
each wall for all items including incidental items.
Cross section showing limits of construction and in fill sections, limits and
extent of select granular backfill material placed above original ground.
Limits and extent of reinforced soil volume.
(B)
All details including reinforcing bar bending details. Bar bending details shall be
in accordance with KDOT Standards.
(C)
All details for foundations and leveling pads, including details for steps in the
footings or leveling pads, as well as allowable and actual maximum bearing
pressures.
(D)
All modules and facing elements shall be detailed. The details shall show all
dimensions necessary to construct the element, all reinforcing steel in the element,
and the location of reinforcement element attachment devices embedded in the
facing.
(E)
All details for construction of the wall around drainage facilities, overhead
sign footings and abutment piles shall be clearly shown.
Bridge Section
11- 58
Design Manual
(F)
All details for connections to traffic barriers, coping, parapets, noise walls and
attached lighting shall be noted on the plans.
(G)
(H)
The design parameters used will be found in the subsurface investigation report.
The assumptions made in the report will be used in the design of the wall system.
Deviations in the design parameters used or changes which will effect the
assumptions made, will first be cleared with the subsurface investigation reports
authors.
(I)
Two sets of design drawings and detail design computations shall be submitted to the Bureau of
Structures and Geotechnical Services. The computations shall include a detailed explanation of
symbols and computer programs used in the design of walls. All designs and construction details
will be checked by the Bureau of Structures and Geotechnical Services against the preapproved
design drawings and procedures for a particular system. Design details and plans shall be
reviewed by the Bridge Squad Leader.
Bridge Section
11- 59
Design Manual
Bridge Section
11- 60
Design Manual
Geotechnical Section
Bridge Section
11- 61
Design Manual
fully restrained elements and connection to the parapet designed for Extreme Event II loading
conditions. Noise walls placed adjacent to Bridge Structures which can fall into traffic or shoulder
lanes will have continuity elements included in the design.
Noise wall taller than 10 present inspection problems when they are mounted on bridges and
therefore, it is not recommended unless prior agree by the Bureau of Structures and Geotechnical
Services.
If the noise wall is mounted on a structure use a 110 mph wind speed. For ground mounted noise
walls use Figure 15.8.2-1 for wind speed determination.
Noise wall mounted on top off MSE walls will be supported by drilled shafts set behind the face
of the wall at least four shaft diameters. Use only modular block type walls (MBW) for this application. KDOT has performed extensive research which shows the performance of MBW with laterally loads drilled shafts in the reinforcement zone, and therefore, have a high level of
confidence with the performance of these wall systems.
Minimum Criteria for noise walls mounted on top of MSE wall:
Wind Load
Max. Height
Max. Shot
Spacing
Min. Shot
Length
50 #/sq. ft.
20 ft.
15 ft.
15 ft.
The top of drilled shaft, for noise walls mounted on top of MSE walls, will have movements limited to 1(in each direction) and the lateral loads must be resisted exclusively by the drilled shafts.
The mobilized soil pressures resisting the shaft rotation must resist all lateral load applied to the
noise wall. The retaining wall facing elements and MSE wall reinforcing should not to counted
on to provide resistance to the lateral loading. The shaft length and diameter should be adequate
to limit the deflection and to transfer the load to the soil mass.
Bridge Section
11- 62
Design Manual
WALL POLICY
11.7 Wall Policy
INITIAL WALL LAYOUT
Wall design and layout is a multi-disciplinary process involving, as a minimum, the Geotechnical
Section, Road Design Section and Bridge Design Section. In addition, many other functional units
within the agency may have input regarding use of these structures. The Project Manager (The
Bureau of Road Design or Consultant) coordinates with all of the design units involved in a project.
When the need for a retaining wall or noise wall has been identified, the Road Design Leader and
their staff (or KDOTs consultant) is responsible for establishing the preliminary geometric layout
of the walls. The layout includes identifying the alignment of the wall, providing a profile along
the planned ground line at the face of the wall, a profile of the planned top of wall elevation,
cross-sections detailing the wall and the physical features within the wall influence zone which
may impact the wall design, construction and performance.
Types of walls covered in this policy:
Retaining walls
Noise walls
Wall combinations
GENERAL GUIDELINES FOR DESIGN
Wall location and design is influenced by many factors and features. Some of these include but
are not limited to:
Geometric Constraints
Right-of-Way
Structural Requirements
Geotechnical conditions
Constructability
Drainage
Drainage Structures
Guard Fence or Barrier
Utility Accommodation
Foundations for other structures or
walls
Walls will be considered individually and as a system of inter-related wall systems or wall combinations (some wall systems are multi-tiered or are a combination of retaining and noise walls).
All walls are influenced by some of the variables listed above and by the interaction between
Bridge Section
11- 63
Design Manual
these variables. Therefore, each wall layout will also show an associated typical section(s) and
actual plan and elevation views of the planned wall and its location with respect to the other features which may influence the alternatives to be considered. It is imperative to detail all known
interactions of these many elements to prevent costly modifications during construction. Road
and Bridge Staff will coordinate the alignment and profile development for each wall and conduct
careful reviews for conflicts with existing or planned features.
WALL TYPES
Retaining Walls
Mechanically Stabilized Earth (MSE) wall systems are typically constructed with one of three
facing systems: Modular Block, Reinforced Concrete Panel or Welded Wire Facing. Most facing
and soil reinforcements are proprietary systems designed to be flexible in nature. Plan details are
developed by KDOTs structural design staff in coordination with KDOTs Geotechnical Unit and
Road Design staff.
Cast-In-Place (CIP) walls are typically considered to be a structural design feature since both
external stability and structural strength or internal stability will satisfied. The details are developed by KDOTs structural design staff or design consultant. In all other respects the design must
be coordinated with both the Geotechnical Unit and Road Design staff. The practice of developing separate detail sheets (as with other wall types discussed above) is appropriate. Where
included in projects with other retaining wall systems, it may be appropriate to include cast in
place wall quantities on the summary sheets with other walls.
Noise Walls
Noise walls generally require more structural engineering expertise than MSE wall systems.
Another principal difference in the development of noise wall details is the determination of the
location of these elements, i.e. noise wall locations are based on the need, as determined by the
Environmental Section, to provide noise abatement measures. See Appendix D Noise Abatement
Policy for KDOT Noise Abatement Policy. Noise wall alignment, height and profiles are accommodated in the design process in a manner similar to retaining walls and are therefore included in
this wall guide.
Noise walls when extending onto bridges over traffic should have a detailed noise analysis performed by a qualified specialist to document the impacts to local receivers if the wall were not
placed on the bridge. From this detailed analysis a decision can be made as to whether the wall
should be extended across the bridge. When extending noise walls on bridges which extend over
traffic, the wall element and connection to the barrier will be evaluated for TL-4 vehicular impact.
Bridge inspection access equipment is severely limited if the wall is over 10 ft. in height, measured at the bridge barrier. Placing noise walls on bridges over streams can impact the ability of
Bridge Management to perform in-depth inspections and should be considered in the development process.
Bridge Section
11- 64
Design Manual
Landscape Walls
Landscape retaining walls, as defined by KDOT, consist of wall systems meeting all 5of the following requirements:
A total height less than 6 ft. measured from top of footing to top of wall profile at all points
along the length of the wall.
The maximum live load surcharge of 100 pound per square foot is not exceeded.
The slope of the material retained by the wall does not slope toward the wall at a rate of 6:1 or
steeper within the area 6 behind the wall.
The wall is not a part of a multiple tiered wall, which as a system would have a total height
greater than 6ft..
Loss of life, serious loss of function or access to adjacent necessary services/structures, or
significant property damage is unlikely in the event of failure.
The development and design details of these walls are different than other wall applications. A
geotechnical investigation is not required. Design staff will prepare details showing the alignment, top of wall profiles and typical section views, etc. These walls are not considered to have
the potential for high risk to public safety; therefore they are not numbered, tracked or inspected
following construction. Landscape walls typically consist of modular block or cast in place construction.
Refer to the memo on: Appendix E Landscape Retaining Wall Policy Revision 1
WALL DATABASE
The Project Manager will request a Wall Serial Number for each wall except Landscape Walls.
The Bureau of Structures and Geotechnical Services maintains the data base which contains information on all walls other than Landscape Walls and all walls attached to bridge barriers. Consult
the Bridge Sections Management Systems Analyst for the correct number. Assistance is available
if needed. See Attachment #1 for the Serial Number request form. See Attachment #5 for wall
type abbreviations used for serial number requests and construction plan notes.
WALL DEVELOPMENT PROCESS
The Road Design Leader will coordinate with the KDOT functional units involved in a project.
Bridge Section staff will be responsible for some portions of the project development process
when retaining walls or noise walls are planned as part of a project. When the need for a retaining
wall or noise wall has been identified, the Bridge Squad assigned to the project and the Geotechnical Unit will be included in the coordination needed for plan development. In the early development of the wall layout concepts, the Bridge staff and the Soils Section gives input concerning
type, size, location, structural viability and cost of the proposed solution.
The transmittal of plans at this stage of project development, Plans to the Bureau of Structures
and Geotechnical Services, is intended to focus on surface geology and those features which are
needed to help define right-of-way requirements (vertical cuts, benching, maximum cut or fill
slopes, etc.). A study of the surface geology early in the project development may provide
Volume III US (LRFD)
Version 1/14
Bridge Section
11- 65
Design Manual
Bridge Section
11- 66
Design Manual
Noise Abatement Policy ) and the roadside geometrics are completed. Plan sheets and details
needed to define the wall are similar to retaining wall systems, but in the case of noise walls,
the supports for the walls are the key elements which must be located and structurally
designed.
FIELD CHECK
Structural concerns regarding walls will be discussed and documented during the Bridge Field
Check. These include, but are not limited to which are attached to the bridge, support the bridge
berms or those which abut or straddle other structures.
The Field Check memo will address issues associated with walls. These issues will be documented on large projects in the Wall Field Check Report.
Use the assigned wall Serial Number to reference all walls in the Field Check Report.
Subsequent to the field check, the Road Design or consultant design staff will assist in the preparation of Wall Field Check Templates Attachment #2 for each wall on the project. Attachment #3
addresses wall stationing. Bridge staff will help in development of the reports. The Wall Field
Check reports (one for each wall), if used, will become part of the Field Check Memo(s).
The Bridge Section will assume responsibility for all walls other than Landscape Walls after Field
Check. This includes communications with the Project Manager, the Consultant, and Soils Section. This also includes projects which do not have bridges in the scope. It is critical to have all
members of the design team inform the Bridge Section of changes or problems as these projects
progress.
After field check the Bridge Section will request a Geotechnical Investigation for both Soil
parameters and foundation recommendations. KDOT Geotechnical Section will provide foundation recommendations for all walls.
Bridge Section
11- 67
Design Manual
Road
Road
Road
Road
Road
Sheet Description
Title Sheet (0) Walls will be included in the scope on the title sheet.
Retaining Wall & Noise Wall Layout (2) providing wall number, baseline, station and offset to both ends of the wall, overall wall length and wall
type (See Bridge Manual for listing of acronyms.) as well as an index to
wall drawings.
Summary of Retaining Wall and Quantities (3) listing all retaining walls on
the project. Include notes which clarify the basis of measurement and basis
of pay for the wall itself and the basis for estimating the select granular
backfill volumes which are subsidiary. The basis of payment and measurement shall be shown for the geomembrane and all additional subsidiary
items shall be called out.
Retaining Wall & Noise Wall Layout (1) for large projects where numerous
walls are proposed or where the sheet will be of help in orienting the plan
user to the general location of the various walls within the project. This
sheet is for general reference, but should accurately depict the location of
the walls as related to the baseline geometrics of the project. At a minimum, each wall should be labeled with its Serial Number.
Retaining Wall General Notes (4, 5) for each retaining wall system
included in the plans. Included in the plans are the approved system suppliers for each retaining structure as detailed in the Report of Retaining/
Noise Wall Investigation. Design criteria, design loading, geotechnical
parameters, safety factors, construction requirements and numerous other
requirements must be included in the plans or specifications. These
requirements are the foundation upon which the system providers will
develop their wall design. The General Notes sheets or the specifications
must provide this information.
Bridge Section
11- 68
Bridge
Road
Road
Road
Design Manual
Bridge Section
11- 69
Road
Retaining Wall Typical Section Details (12, 13) are a more detailed typical
section for specific walls on the project. These sheets provide further
details regarding foundation, drainage, controlling clearances, slopes, etc.
The typical section should depict the typical excavation / embankment
details such as the location of retained fill and select fill, the basis of the
quantities estimated in the plans and, if not covered by a standard specification or special provision, identify items which are considered to be subsidiary. Typical Sections are sometimes needed to depict unique situations
along the length of the wall (Noise Wall/Retaining Wall Section shows a
combination of a noise wall drilled shaft behind a retaining wall). An outline of the proposed construction sequence will be provided for each wall
detailed. Further, these sequence notes may provide specific time restrictions such as time needed for settlement prior to paving operations if
applicable for the wall depicted. Traffic barrier Refer to Traffic Barrier
policy/detail sheets.
Bridge
Road
Design Manual
Road Cross Sections (24, 25, 26) Provide the needed views as well as
detailing special considerations such as the influence of, or interface with,
drainage pipes and structures. Proper storm drainage interception and discharge are important to long term performance of the retaining systems.
Noise wall plan development is similar to developing drawings for retaining wall systems. Generally noise wall systems require more structural design than retaining wall systems. The Bridge
Section will be responsible for these sheets following field check and will make all requests to the
Geotechnical Unit. The Project Manager will be responsible for the development of the initial
plan profile through field check and will conduct all presentations to the public dealing with the
proposed noise wall concepts.
Bridge Section
11- 70
Sheet Description
Bridge
Bridge
Road
Bridge
Bridge
Bridge
Bridge
Bridge
Bridge
Bridge
Design Manual
Noise Wall General Notes and Index of Drawings (17). Bridge Section
will be responsible for completing and reviewing this sheet.
Noise Wall Quantities & Foundation Summary (18).
Noise Wall Plan and Profile (23) will include a construct note (three
sided box) referencing the wall by station, baseline offset, description
and serial number in the plan view. The limits of need should be
shown in the profile view and a summary of required steel post lengths
and panel sizes should be provided for the fabricators information.
Road and Bridge Sections and the Environmental Section must coordinate their efforts to assure the details provided adequately address the
intended noise mitigation requirements.
Noise Wall Drilled Shaft Data (19). This sheet will provide a summary
of the drilled shafts being used for noise wall foundations on the project; it will include shaft diameters, shaft lengths, length of rock sockets
and the bill of reinforcing for the drilled shafts.
Noise Wall Drilled Shaft Details (22). This sheet will be provided for
noise walls supported on drilled shaft foundations. Similar sheets may
need to be developed for special situation involving alternative noise
wall foundations such as spread footings or strip footings, etc.
Noise Wall Drilled Shaft Data (19). This sheet is for noise walls
behind mechanically stabilized earth walls. The sheet will provide all
drilled shaft design loads along with a summary of design soil parameters. The Bridge Section will work with the Geotechnical Unit to provide all information which will be required by the wall manufacturer to
complete his design for internal stability of the MSE wall system. This
sheet should be referenced on the MSE wall plans.
Noise Wall Concrete Panel Details This sheet contains the details to
be used by the noise wall concrete panel fabricator.
Noise Wall Structural Steel Details (22) This sheet contains the details
for the steel post, base plates, post bracing systems which may be
required and the anchor bolts for use by the fabricator of the structural
steel noise wall components.
Miscellaneous Noise Wall Structural Details(22). These sheets provide a sample of possible structural details which may need to be
included in the plans. These details may include details for attaching
noise wall to concrete safety barriers, additional details for connecting
the safety barrier to the shoulder pavement for adequate transfer of the
noise wall loads, details for access ports for fire safety and details for
various block outs such as drains and sign truss foundations. Traffic
barrier Refer to Traffic Barrier policy/detail sheets.
Bridge Section
11- 71
Design Manual
OFFICE CHECK
The Road Section, the Geotechnical Section and Bridge Section will coordinate the review of
plans to identify any errors or omissions. The resolution of these items will also be coordinated.
SHOP DRAWINGS
After the project is let, the Contractor will submit the required shop drawing for any fabricated
wall system or component.
The Fabricator sends shop drawings for wall systems or components to the Bridge Section and to
the Geotechnical Section. They also send shop drawings to the KDOT Consultant if applicable.
The Bridge Section or the bridge design consultant is responsible for reviewing the shop drawings. This review includes the geometrics, panels, footings, etc. The Fabricator adapts the design
to utilize their product within the plan tolerances (minimums, maximums and geotechnical
requirements). For example, the Fabricator may lower the leveling pad to a uniform elevation and
provide steps in the elevation of the pad to fit his panel dimensions. These changes may affect
other details such as drainage accommodation or clearance to utilities or sanitary sewers etc.
These influences will be addressed in the shop drawings. Review of these changes may require
the involvement of the Road Section staff.
The Geotechnical Section reviews the adequacy of the Fabricators designs and the geotechnical
stability of all walls. When both the Structural and Geotechnical issues have been addressed, the
approved shop drawings are distributed.
The Bridge Section distributes the approved shop drawings and accompanying correspondence.
(See Attachment #4 for Approved Shop Detail correspondence distribution list). Bridge Design
sends a copy of correspondence only (no shop drawings) to Road Design.
CONSTRUCTION ISSUES
The Division of Operations and the Bureau of Structures and Geotechnical Services will work
together when there are construction problems.
The District will inform the Project Manager and the Geotechnical Unit if there are construction
problems with walls and when applicable, the consultant designers will be apprised of the construction issues.
Contact the Bureau of Structures and Geotechnical Services if there are construction problems or
questions. Do not contact the proprietary Wall Manufacturer/Fabricator directly if the wall is a
Mechanically Stabilized Earth Type Wall. Do not direct Operations staff or Consultants to contact
the Wall Manufacturer. The Bureau of Structures and Geotechnical Services will coordinate the
appropriate communications with the Wall Manufacturing entity for MSE structures.
Do not develop or implement solutions for wall problems. This may relieve the Wall Manufacturer of liability. While KDOT solutions may be the correct option; contact the Bureau of Structures and Geotechnical Services first. KDOT may develop solutions, but wait for Geotechnical
Services to give guidance.
Bridge Section
11- 72
Design Manual
REVISED PLANS
The District staff will notify the Road Design Leader, the Bridge Designer and Geotechnical Services of all proposed wall changes. If wall revisions require revised shop drawings, the process of
reviewing and distributing the revised drawings is similar to a new submittal.
The Fabricator will submit revised shop drawings. Bridge Design or KDOTs Consultant will
review the structural acceptability of the shop drawings. Materials and Research will re-evaluate
the MSE wall shop drawings for adequacy of geotechnical design.
Bridge Design will distribute the approved revised shop drawings as per their normal practices.
(Attachment #4)
The Road Project Manager will revise and distribute revised wall plan sheets following normal
revised sheet procedures. The Bridge Section will revise and distribute revised plan sheets for
walls affecting elements of the bridge system. (Sheets are assigned to Road or Bridge based on
the original author. See the preceding section title Typical Plan Details for general guidance.)
Revised wall plan sheets must be transmitted quickly to avoid construction delays.
BUREAU OF LOCAL PROJECTS
The Bureau of Local Projects (Local Projects) will follow the policies listed above on local entity
projects which affect the State System. Generally, Geotechnical Services is not involved with
Local Projects walls. However, there may be special cases where Local Projects requests the
expertise of Geotechnical Services.
ATTACHMENTS
Index
Attachment #1Wall Serial Number Request
Attachment #2 Wall Field Check Template
Attachment #3 Wall Stationing Guidelines
Attachment #4 Distribution of Shop Plans
Attachment #5 Wall Structure Type Abbreviations
Bridge Section
11- 73
Design Manual
Title Sheet
Bridge Section
11- 74
Design Manual
Bridge Section
11- 75
Design Manual
Bridge Section
11- 76
Design Manual
Bridge Section
11- 77
Design Manual
Bridge Section
11- 78
Design Manual
Bridge Section
11- 79
Design Manual
Bridge Section
11- 80
Design Manual
Bridge Section
11- 81
Design Manual
Bridge Section
11- 82
Design Manual
Bridge Section
11- 83
Design Manual
Bridge Section
11- 84
Design Manual
Bridge Section
11- 85
Design Manual
Bridge Section
11- 86
Design Manual
Bridge Section
11- 87
Design Manual
Miscellaneous Details
Bridge Section
11- 88
Design Manual
Bridge Section
11- 89
Design Manual
Bridge Section
11- 90
Design Manual
Bridge Section
11- 91
Design Manual
Bridge Section
11- 92
Design Manual
Bridge Section
11- 93
Design Manual
Nose Wall
Bridge Section
11- 94
Design Manual
Bridge Section
11- 95
Design Manual
Bridge Section
11- 96
Design Manual
Bridge Section
11- 97
Design Manual
Bridge Section
11- 98
Design Manual
Bridge Section
11- 99
Design Manual
Bridge Section
11- 100
Design Manual
Attachment #1
Bridge Section
11- 101
Design Manual
Attachment #2
7
8
RM MMM.MM
RR-CCC-MM.MM (WWWW/BBB)
7
8
1.
2
3.
4.
5.
6.
7.
8.
RM MMM.MM
RR-CCC-MM.MM (WWWW/BBB)
Bridge Section
11- 102
Design Manual
Attachment #3
Figure 1
SBO - 3
Bridge Section
11- 103
Design Manual
Attachment #4
Approved Shop Detail Distribution List
Fabricator
Contractor (General and Sub-Contractor)
District Engineer w/a
Area Engineer w/a
Area Construction Engineer w/a
Metro Engineer and/or FEA if applicable w/a
Operations Engineer, Bureau of Construction and Materials w/a
Asst. Chief, Bureau of Construction and Materials
Bureau of Road Design
Pavement Section
Consultant (if applicable) w/a
State Geotechnical Engineer w/a
Management System Analyst, Bridge Section w/a
Bridge County Files ==> Records and Workflow Management
Projectwise
Notes:
Shop drawing format and distribution shall conform to Section 105.10b of the KDOT Standard Specifications for Road and Bridge Construction
Bridge Section
11- 104
Design Manual
Attachment #5
DATABASE CHARACTER WALL TYPE CODES
CANSYS / PONTIS / BROMS alpha character fields
Material Type
A = Aluminum
B = Stone
C = Corrugated Metal
D = Geotextile Fabric
E = Earth (soil)
F = Composite (Fiberglass, PVC, etc.)
G = Galvanized Steel
H=
I = Wrought Iron
J=
K=
L = Lightweight Concrete
M = Stone Masonry
N = None (for BROMS temporary use)
O=
P = Prestressed Concrete
Q=
R = Reinforced Concrete
S = Steel
T = Timber
U = Unknown (for BROMS temporary use)
V=
W = Weathering Steel
X = Post-Tension Concrete
Y = Precast Concrete
Z=
Superstructure/Structure Type
AT = Soil Nail/Tie-Back
BN = Bin
CT = Cantilever
ER = Earth
GB = Gabion
GV = Gravity
MB = Mechanically Stabilized Earth, Block
ML = Mechanically Stabilized Earth, Panel
PF = Panel Frame
SD = Soldier Pile
SH = Sheet Pile
SV = Semi-Gravity
Design Type
A = Aesthetic (Wall)
X = Retaining (Wall)
Y = Hydraulic (Wall)
Z = Noise (Wall)
Bridge Section
11- 105
Design Manual
Bridge Section
11- 106
Design Manual
New Structures
Use one of the following AASHTO Specifications taken from Article 3.6.5.1 to protect the pier if
the pier is within the clear zone.
Design the pier to withstand impact.
Use an embankment to protect the pier from vehicular impact.
When the distance from the back of the barrier to the pier is less than or equal to 10-0, use a
54 barrier designed for a TL-5 loading condition.
When the distance from the back of the barrier to the pier is greater than 10-0, use a 42
barrier designed for a TL-5 loading condition.
Note: KDOT has not crash tested a 42 or 54 barrier for TL-5 loading but, has detailed the reinforcement based on, Development of 42 and 51 TALL SINGLE FACE, F-SHAPE CONCRETE BARRIERS (Faller, R. 2002) defining that reinforcement.
Existing Structures
Use this guide along with the risk of a specific structure as a method of determining the level of
protection required. Evaluate the capacity of the column and the connections to the foundation
and pier beam elements to determine the resistance. Factors which affect this resistance include,
but are not limited to:
The continuity of the superstructure and the ability for full or partial stress reversal and redistribution of force effects.
The continuity of the superstructure to the substructure and any frame action which might aid
in the distribution of force effects.
The condition of the bearing devices and ability to resist translations and rotations.
The degree of redundancy of the substructure.
The continuity of the substructure to the foundation system.
The amount of confinement reinforcement within the column and potential ultimate reserve
capacity beyond the design capacity. Refer to Section 3.5.1.6.3.
The cost compared to the risk.
Allowable Damage
The intent of this protection is so that upon impact the structure is prevented from collapsing. A
repair may require closing or partial closing of the structure or the roadway passing below. The
level of allowable damage and the extent which the structure is out of service must be measured
compared to the cost of the protection. In congested urban areas where loss of service may not be
acceptable, the level of protection should be increased.
Bridge Section
11- 107
Design Manual
Bridge Section
11- 108
Design Manual
Median Protection
Bridge Section
11- 109
Design Manual
Bridge Section
11- 110
Design Manual
Bridge Section
11- 111
Design Manual
Bridge Section
11- 112
Design Manual
Bridge Section
11- 113
Design Manual
Bridge Section
11- 114
Design Manual
Bridge Section
11- 115
Design Manual
Bridge Section
11- 116
Design Manual
b)
&
M = Ph
E=
I=
a=
T
L
h
P
=
=
=
=
M = Ph/2
Bridge Section
11- 117
Design Manual
= 1.05"
= 0.60"
Deflection at Piers:
Pier
a)
Pad + Col
Bridge Section
11- 118
Design Manual
The Shear Modulus (G) varies with durometer, temperature and time. Use 60 durometer pads with
a G(max) = 300 psi. for temperature fall and G(min) = 150 psi for temperature rise. Run two sets
of calculations.
b)
P1 ( 10x12 in/ft. ) -5
Col = ---------------------------------------------------------= 5.54x10 (P1)
6
4
3 ( 29x10 ) ( 5x71.7 in. )
T1
= Col
= 18,952 lbs./Abut.
At Pier #1 = Pier #3
P2 ( 2 )
-5
Pad = ----------------------------------------------------- = 0.51x10 (P2)
18 ( 12 ) ( 300 ) ( 6 pads )
3
P2 ( 30 12 in/ft. ) -5
Col = -------------------------------------------------------------= 1.75x10 (P2)
6
3 ( 3.6 10 ) ( 3 82, 448 )
Pad + Col = 2.26x10-5 (P2)
T2
= Pad + Col
0.60" = 2.26x10-5 (P2)
P2
= 26,549 lbs/Pier
Bridge Section
11- 119
Design Manual
= 0.597
P1 + P2 + P3 = P4 + P5
@ Abut. #1:
3
3
P(H)
P1 ( 10 12 in/ft. )
Col = ------------------- = -------------------------------------------------------------3 ( E ) ( I ) 3 ( 29 10 6 ) ( 5 71.7 in 4 )
= 5.54 10
-5
(P1)
= T1
Bridge Section
11- 120
Design Manual
@ Pier #1:
PT
P2 ( 2 )
-5
Pad = ------------------- = --------------------------------------- = 0.514 10 (P2)
LWGN 18 ( 12 ) ( 300 ) ( 6 )
3
P2 ( 25 12 )
- = 1.011x10 5
Col = -------------------------------------------------------------6
3 ( 3.6 10 ) ( 3 82, 448 )
T2
Pad + Col
T2 = 1.525 10
-5
(P2)
(P2)
@ Pier #2:
3
P3 ( 30 12 ) -5
Col = ----------------------------------------------= 1.747 10 (P3)
6
3.6 10 ( 247, 344 )
= T3
@ Pier #3:
P4 ( 2 )
-5
Pad = --------------------------------------- = 0.514 10 (P4)
18 ( 12 ) ( 300 ) ( 6 )
3
P4 ( 18 12 )
- = 0.377x10 5 (P4)
Col = ----------------------------------------------------6
( 3.6 10 ) ( 247, 344 )
T4
Pad + Col
T4 = 0.891 10
-5
(P4)
@ Abut. #2:
3
P5 ( 10 12 )
- = 5.540 10 -5 (P5)
Col = -------------------------------------------------6
( 29 10 ) ( 5 71.7 )
= T5
Solve for P:
@ Abut. #1:
@ Pier #1:
@Pier #2:
T1
+ 0.00702 ( X )
= 1.018
-----------------------------------------------P1 = --------------------------5
-5
5.54 10
5.54 10
T2
0.597 + 0.00702 ( X )
P2 = ----------------------------= ------------------------------------------------5
-5
1.525 10
1.525 10
T3
+ 0.00702 ( X )
= -----------------------------------P3 = -----------------------------5
-5
1.747 10
1.747 10
Bridge Section
11- 121
Design Manual
@Pier #3:
T4
0.597- 0.00702 ( X )
P4 = -----------------------------5- = -----------------------------------------------5
0.891 10
0.891 10
@Abut. #2:
T5
0.00702 ( X )P5 = -----------------------------5- = 0.807----------------------------------------------5
5.540 10
5.540 10
126.7 X
460.3 X
401.8 X
787.9 X
126.7 X
1,903.4 X
X = 12.6 ft.
Therefore,
P1 =
P2 =
P3 =
P4 =
P5 =
The controlling column temperature force is located at Pier #3 (P4). If it is determined this force is
too large, the designer could select one of the following options: (a) Increase the height of the pad
to make it more flexible. (b) Specify an isolation bearing design to redistribute the forces. (c)
Equip the elastomeric pad with a teflon sliding surface.
Moment of Inertia Adjustment for Free-Standing Skewed Piers
A skewed, free-standing column bent pier will inherently be stiffer in the longitudinal direction
then a non-skewed pier. This increase in stiffness due to the skew will produce larger moments in
Bridge Section
11- 122
Design Manual
the columns. To compute the resultant Moment of Inertia for the Pier (Ir), the following procedure
may be used:
For two, three, four and five column piers of equal height and size of column;
Izz = (4) Iyy (see derivation below)
Iyy = Io (N)
N = Number of columns
Io = Moment of Inertia of one column
Skew
Iyy
Izz
Ir
0
10
20
30
40
50
1
1
1
1
1
1
4
4
4
4
4
4
10
19
1.35
1.75
2.24
2.76
90
4.00
Adjustment of moments of inertia should be used for skews greater than 20 degrees.
Bridge Section
11- 123
Design Manual
Derivation:
Stiffness is inversely proportional to deflection, therefore;
I zz =
k
k
and I yy =
y
z
z
z
I zz
=
or I zz = ( I yy )
y
y
I yy
z = Deflection in Z direction =
P 13
3 EI o (N)
P 13
y = Deflection in Y direction =
12 EI o (N)
I ZZ
z
P 13 / 3 EI o (N)
= ( I yy )
= I yy
y
P 13 / 12 EI o (N)
I zz = I yy (4)
Bridge Section
11- 124
Design Manual
Z 0 H
X1 3
X2 9
Qp 16000
Dimensionless Parameters......
n ( Z)
1.77 m1 n ( Z)
F1( Z)
X1
m1
m 2 n ( Z) 2
1
X2
m2
1.77 m2 n ( Z)
F2( Z)
m 2 n ( Z) 2
2
Qp
2 F1( Z)
H
Qp
2 F2( Z)
H
p2( Z)
2
p1( Z)
-1
254.88
-1
4.16
2
-2 464.051
4
-2 14.941
-3 393.333
-3
-4 260.997
-4 40.215
-5 162.121
6
64.01
-8
41.932
-9
28.32
-10
19.681
-7 51.162
-8 48.156
6
-9 43.704
-10 38.685
8
10
8
10
20
0.78
m1 0.4 1.5
H
Q
p
40
Ph1
1.488 u 10
Ph2
R1
6.45
R2
0.78
m2 0.4 1.5
H
Q
p
Is the Live Load Supported by the Sheet Pile (1=yes & 0=no) .........................................
Ph1
60
p2( Z)
R1
48.15
-6 51.561
-7
28.32
-5
4
-6 100.693
Ph1
p2( Z)
Ph1 if LL ! 0
Ph2
Ph2
48
R2
3.15
LL 1
Ph2 if LL ! 0
0 otherwise
0 otherwise
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
Bridge Section
11- 125
Design Manual
Solution taken from Braja M. Das," Principles of Foundation Engineering" pp. 334-340
Soil Parameters
Internal Friction angle.....................
32
110
w 62.4
sat 125
L1 10
L2 0
L L1 L2
Step 1
Ka tandeg 45
Kp tandeg 45
10
2
Slope:
m ' ( Kp Ka)
Step 2
p 1 L1 Ka
p2
L1 ' L2 Ka
Step 3
L3
p2
' ( Kp Ka)
L3
1.832
Step 4
P
1 p L p L 1 p p L 1 p L P P
1 1 1 2
2
1
2
2 3
h1
h2
2
2
2
Step 5
z'
3.535 u 10
L2 1
L2 1
L1
L1
p1 L2 L3 p 2 p 1 L2 L3 p2 L3 L3
2 2
3 2
P
3
P R L 3 P R L
h1 1 3 h2 2 3
1
p 1 L3 L2
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
z'
4.582
Bridge Section
11- 126
Design Manual
Step 6
p5
3.918 u 10
p5
Step 7
A'1
p5
' ( Kp Ka)
A'1
8 P
A'2
21.236
A'3
' ( Kp Ka)
A'2
' ( Kp Ka)
153.298
A'3
A'4
P 6 z' p 5 4 P
2
' ( Kp Ka)
3.495 u 10
A'4
1.266 u 10
Step 8
L4 15
Guess:
Given
4
L4
13.664
Step 9
p 4 p 5 ' L4 ( Kp Ka)
6.439 u 10
p4
Step 10
p 3 ' ( Kp Ka) L4
2.521 u 10
p3
Step 11
L5
p 3 L 4 2 P
L5
p3 p4
3.055
Dt L3 L4
Dt
15.496
Da
20.145
Z'
2 P
' ( Kp Ka)
Z'
6.191
Max. Moment
M max P ( z' Z')
M max
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
Bridge Section
11- 127
S
M max 12
all
Design Manual
24.632
L
0
L2
p1
p2
0
0
L3
f
p 2 Dt L5 m Dt L5
p4
Dt
0
Dt
<========
n 1 7
x
1000
y f
10
Depth,(ft)
2
yn
10
20
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
Bridge Section
11- 128
Design Manual
xn
Pressure,
Pressure
Bracing Calculations
The following solutions are based on the the following assumptions:
(1) The active earth load is supported by the sheet.
(2) The live load is supported by the H-pile Bracing.
(3) The uniform distributed load = tributary area.
(4) Walers are simply supported at the ends
(5) Length to fixity is 7'-0" below dredge line.
Bracing Parameters
d1 5
d2 5
d3 2
Lhp 10
Section of Whalers....................
Sw 43
Sv 66.8
10
d1
d2
2
if d2 ! 0
d2
t2
d3
2
if d3 ! 0
( L t1) otherwise
L otherwise
t3
d3
2
L ( d1 d2 d3) if d3 ! 0
0 otherwise
w1
t1
w2
p1( Z) dZ
t1
t1 t2
w3
p2( Z) dZ
t1
p1( Z) dZ
t1 t2
t1 t2 t3
w1
1.938 u 10
w2
246.153
w3
52.829
t1
p2( Z) dZ
t1 t2
p1( Z) dZ
t1 t2
p2( Z) dZ
t1 t2 t3
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
Bridge Section
11- 129
w2
Design Manual
w2 if d2 ! 0
w3
w3 if d2 ! 0
0 otherwise
0 otherwise
w1 Lhp
M w1
M w2
8
M w1 12
w1
w2
Sw 1000
w1
w2 Lhp
M w3
8
M w2 12
w3
Sw 1000
w2
6.759 ksi
w3 Lhp
8
M w3 12
Sw 1000
w3
0.859 ksi
0.184
ksi
Mv
w1 Lhp
2
[ ( L 7 ) d1]
w2 Lhp
2
v
[ ( L 7 ) d1 d2]
M v 12
Sv 1000
22.194
w3 Lhp
2
[ ( L 7 ) d1 d2 d3]
ksi
Sheet pile wall in sand with live load and water and bracing (ver 1.0).MCD
Bridge Section
11- 130
Design Manual
Noise Abatement
Effective
August 28, 1996
PREFACE
Traffic noise impacts vary with highway location relative to human activities and traffic
characteristics. The Kansas Department of Transportation (KDOT) evaluates traffic noise in
accordance with federal regulations and, as impacts become more severe, noise mitigation
measures are investigated. In order to address these issues in a consistent and objective manner,
the following policy and procedure statements are provided.
Authority
The Federal Highway Administration's Procedures for Abatement of Highway Traffic
Noise and Construction Noise is found in 23 CFR 772. The KDOT noise policy is based
upon this FHWA regulation, and is deemed to be consistent with it.
1)
Bridge Section
11- 131
Design Manual
in cost, but through a joint effort of those involved, an appropriate balance of cost and
responsibility can be achieved. Policy and procedure stated in this document reflects this
systems approach to traffic noise reduction.
2)
Noise Prediction
All predictions of noise levels on KDOT highway projects will be made using a noise
prediction model approved by the FHWA. In predicting noise levels and assessing noise
impacts, the posted speed limit at the time of the existing traffic noise study will be used.
3)
Noise Levels
a.
Descriptor
Noise studies for KDOT projects will use Leq, the equivalent sound level.
b.
Existing Levels
Leq values existing in a project corridor before construction will normally be
determined through field measurements. However, in certain cases, these values
can be obtained through execution of the Model.
c.
Noise Abatement
Criteria LeqdV)
Approach
defined as
57 dBA
56 dBA
67 dBA
66 dBA
C
72 dBA
71 dBA
In addition, impacts are deemed to occur when future predicted no barrier levels
Bridge Section
11- 132
Design Manual
substantially exceed existing levels. KDOT has an agreement with FHWA that
defines impacts. These definitions are:
0-5 dBA increase
6-10 dBA increase
11-15 dBA increase
> 15 dBA increase
- No impact
- Minor impact
- Moderate impact
- Severe impact
Barriers
a.
Barrier Projects
KDOT will only construct noise barriers as part of highway construction or reconstruction projects. KDOT will not participate in the Type II program of
retrofitting existing highways with noise barriers until Federal standards are
established exclusively for Type II and other enhancement projects (See 23 CFR
772.5(i) and 772.7 (b)).
b.
Insertion Loss
Insertion loss is the difference in Leq with and without the barrier (barrier minus
no barrier level). The insertion loss goal for each impacted sensitive receptor is
5 dBA or more.
c.
Location
In at-grade or fill situations, barriers should be built as close to the highway as
possible. If necessary, barriers can be located on top of jersey-type barriers, and
placed at the edge of shoulder, ( approximately 10-12 feet from traffic). If jerseytype barriers or methods of crash protection are not used, noise barriers should be
outside the 30 foot clear zone.
When barriers are constructed at or near the shoulder line, consideration must be
given to safety, drainage, and ice and snow removal.
In cut situations, barriers should be placed as close to the right-of-way line as
possible. This will maximize noise reduction effects of the barrier. In all cases
barriers should be constructed on KDOT right-of-way.
Bridge Section
11- 133
Design Manual
d.
Height
For aesthetic and cost reasons, barriers should be tall enough to provide adequate
noise reduction, and no taller. For KDOT projects, the maximum height of any
barrier above the ground line will be 16 feet. Barriers taller than 16 feet would
probably result in negative visual impacts on the surrounding properties.
Also for aesthetic reasons, barrier height should be limited as follows: The
distance from the barrier to any inhabited buildings should be at least four times
the barrier height. For example, if the distance from the barrier to a row of
protected houses is 44 feet, the maximum height of the barrier should be 11 feet.
e.
Length
Barriers shall be designed with the shortest length possible. Typically, barriers
will need to extend beyond the last receiver by a distance four times the distance
from the receiver to the barrier.
f.
End Treatment
Abrupt endings of barriers should be avoided. Barrier heights should be tapered
to the ground and vegetation may be used to soften the end appearance.
g.
Access
Working space behind the barrier with provisions for access should be provided,
or maintenance agreements with other public bodies or private individuals should
be made.
h.
Materials
The principal issues involved in material selection are aesthetics, community
desires, constructability, and maintenance. Normally, concrete and masonry based
materials are the most suitable in addressing these issues. Wood barriers are a less
expensive alternative, but must be carefully designed and monitored in terms of
treatment and water content in order to minimize maintenance problems. Metal
barriers are easily damaged, and are often not received positively regarding
aesthetics. Vegetative screens do not produce meaningful noise reduction, due to
a lack of material density.
Bridge Section
11- 134
Design Manual
i.
Cost
Because a small number of people benefit from a relative large expenditure of
funds, barriers, if constructed, must be determined to be reasonable, feasible, and
cost effective. For KDOT projects cost effectiveness is defined as barrier cost per
receiver at or below the national average guideline for barrier cost effectiveness.
This guideline was determined to be $25,000 in 1995 dollars, based upon studies
performed for KDOT.
When determining cost effectiveness of a potential barrier, each sensitive receptor
receiving 5 or more dBA insertion loss is counted as one receiver, and each
receiving 3-4 dBA insertion loss is counted as one half receiver.
The cost data in Table 1 should be used when computing the barrier cost per
receiver. These data have been incorporated into the NOISE software library. It
is the intent of KDOT to update the values in Table 1, as well as the $25,000
barrier cost per receiver national criterion, as needed.
It should be noted that the data in Table I are to be used in conjunction with the
guideline for cost effectiveness. THEY ARE FOR COMPARISON PURPOSES
ONLY. Actual barrier costs will vary.
It should also be noted that the comparison of proposed barrier costs using the
guideline is to assist KDOT in making decisions about barrier feasibility. Any final
decision on barrier construction will be based on a variety of factors.
Barrier Height
Range in feet
01-05
05-10
10-15
15-20
20-25
Concrete
Wood
Metal
48.66
79.11
1-17.18
155.28
193.34
105.79
193.33
302.74
412.13
521.55
18.77
94.21
220.91
347.61
474.30
28.09
136.79
272.66
408.53
544.39
Bridge Section
11- 135
Design Manual
j.
Maintenance
The goal for all barriers constructed by KDOT is minimum maintenance cost.
Each barrier design should be performed with this goal in mind.
k.
Aesthetics
Successful barrier projects not only adequately reduce noise levels, but also receive
positive response regarding appearance (aesthetics). In order to assure this positive
response, care should be taken in selecting a color scheme and surface texture, and
use of landscaping should be considered in design.
1.
m.
Isolated Receivers
Barriers will not be constructed for individual residences or other isolated
receivers.
5)
Bridge Section
11- 136
Design Manual
2.
3.
6)
Sensitive Receptors
Although all activities that have a NAC are reviewed, single family residences have
the highest priority for limited highway construction funds.
Approved:
E. Dean Carlson,-Secretary
Kansas Department of Transportation
Bridge Section
11- 137
Design Manual
FROM:
DATE:
SUBJECT:
The Approved Proprietary Retaining Wall System list developed by our Agency
has performed well for many years. However; the premise of all our design standards
requires us to design to AASHTO minimum specifications. The conservative nature of
the AASHTO criteria has actually hindered development of the MBW (Modular Block
Wall) usage in low impact settings. An example would be to build a two foot exposed
height retaining wall (3 blocks) while embedding the system 3 feet (4 blocks) and using
reinforcement 8 feet in length. Although these design standards are widely considered
too conservative, no significant effort has been made yet to address these deficiencies in
AASHTO.
Until these discrepancies are addressed by AASHTO, we recommend a policy
(henceforth known as the Landscape Retaining Walls Policy or LRW Policy), whereby
the less restrictive National Concrete Masonry Association Design Standards for
Segmental Retaining Walls can be utilized for MBW systems on urban and secondary
routes providing the following criteria are met:
The total height of the retaining wall must be less than 6 feet.
The live load surcharge cannot exceed 100 psf.
The system cannot be defined as a critical structure whose failure would cause
loss of life, serious loss of function or access to adjacent necessary services/structures, or
result in significant property damage.
Multiple tiered walls will not be considered landscaping walls even if the
individual height of the component retaining walls is less than 6 feet.
This policy will allow the use of a granular leveling pad. (rev. 12.30.08)
Please contact us at (785)296-3008 after your review and revisions of the
proposed policy so that we can proceed with its further development.
AJG:JJB:jjb
Ken Hurst, P.E., State Bridge Operations Engineer
C:
Loren Risch, P.E., State Bridge Design Engineer
Ron Seitz, P.E., Chief, Bureau of Local Projects
Mike Popp, P.E., Operations Engineer
Corky Armstrong, P.E., Roadway Design Engineering Manager
Joshua Welge, P.E., Soils Engineer
Luke Metheny, Engineering Associate III
Blair Heptig, Foundations Specialist
Bridge Section
11- 138
Design Manual
12 BURIED STRUCTURES
Table of Contents
12.1 Geometry ................................................................................................................1
12.1.1 Definitions ..................................................................................................................1
12.1.2 Length .........................................................................................................................3
12.1.3 Skew or Rotation Angle .............................................................................................3
12.1.4 Wingwalls ...................................................................................................................4
Bridge Section
12 - i
Design Manual
List of Figures
Figure 12.1.1-1 Single/Multiple Cell RCB .....................................................................................5
Figure 12.1.1-2 RCB Plan Views ...................................................................................................6
Figure 12.1.1-3 Box Size Definitions .............................................................................................7
Figure 12.1.1-4 Bridge Box, 10 to 20 Structure (500 Series), or Road Culvert .........................8
Figure 12.1.2-1 RCB Plan View and Section .................................................................................9
Figure 12.1.3-1 Normal, Skewed and Rotated Crossing ..............................................................10
Figure 12.1.4-1 Wingwall Flare Angle .........................................................................................11
Figure 12.1.4-2 Embankment at Wingwalls .................................................................................12
Figure 12.1.4-3 Wingwall Dimensions for 0 Degree Skew RCBs ..............................................13
Figure 12.1.4-4 Wingwall Dimensions for 30 Degree Skewed RCBs ........................................14
Figure 12.1.4-5 Wingwall Dimensions for 45 Degree Skewed RCBs ........................................15
Figure 12.1.4-6 Straight Wingwall Details ...................................................................................16
Figure 12.1.4-7 Wingwall Dimensions for Straight Wings ..........................................................17
Figure 12.1.4-8 Straight Wingwall Plan Details ...........................................................................18
Figure 12.3.1-1 Live Load Distribution .......................................................................................20
Figure 12.3.6-1 Summary of Loading Conditions ........................................................................22
Figure 12.3.6-2 Buoyancy Effects on Backfill Materials .............................................................23
Figure 12.3.7-1 Design Fill Height Category ..............................................................................24
Figure 12.3.7-3 Unequal Fill Height ............................................................................................27
Figure 12.5.5-1 Settlement of Culvert ..........................................................................................32
Figure 12.6.1-1 Model of Culvert .................................................................................................33
Figure 12.6.2-1 Strength Design ...................................................................................................35
Figure 12.7.2-1 Design Assumptions - Vertical Cantilever ..........................................................42
Figure 12.7.2-2 Typical Backfill and Toe Dimensions ................................................................43
Figure 12.8.1-1 Precast Box Culvert Details ................................................................................46
Figure 12.8.2-1 Precast Arch Details ............................................................................................50
Figure 12.8.2-2 Closure Pour .......................................................................................................51
Figure 12.9.1-1 Minimum Box Length With Guardrail ...............................................................55
Figure 12.9.6-1 RCB Auxiliary Details (Std BR020b) .................................................................56
Figure 12.9-3 Typical Culvert Extensions (Std RD080) ..............................................................57
Figure 12.9-4 Bridge Excavation (Std BR100) ............................................................................58
Figure 12.9-5 Alignment & Details for Guardrail Protection on Low Fill Culverts (Std RD617c) .
59
Bridge Section
1 2 - ii
Design Manual
List of Tables
Table 12.4.1-1 LRFD Load Factors. .............................................................................................29
Appendixs
Appendix A Kansas Automated RCB System .............................................................................60
Appendix B Wingwall Moment & Reaction Coefficients ............................................................73
Appendix C LRFD RCB Mathcadd Loads ...................................................................................76
Appendix D Doubly Reinforced and Shear Capactiy of Concrete ...............................................87
Appendix E Miscellaneous Example Details ................................................................................90
Bridge Section
1 2 - iii
Design Manual
12 BURIED STURCTURES
The following criteria are intended as guidelines in the structural design and detail of cast-inplace (CIP) reinforced concrete box culverts. The criteria are applicable to culverts for which
KDOT has direct design responsibility and for which KDOT has a responsibility for plan review.
It is not intended that these guidelines answer all questions of design or details of design. Additional information will be added to this document, as needed, for clarification. It is expected that
the applicability of these guidelines to actual field conditions or to designs outside the limits considered in this report will be verified by an Engineer. The hydraulic design and selection of culvert
size are discussed in other documents.
This section also contains information on precast box culverts and precast arch strucures.
Reference to the KDOT Design Engineer considered to be appropriately either the State Road
Engineer or the State Bridge Engineer.
Unless otherwise noted, AASHTO references are to the 2007 American Association of State
Highway and Transportation Officials LRFD Specifications for Highway Bridges, including the
2009 interims.
12.1 Geometry
12.1.1 Definitions
For purposes of this report, a reinforced concrete box culvert is considered to consist of two components: a rectangular conduit (box, barrel, etc.) to convey water and a retaining structure (headwalls, wingwalls, etc.) to prevent erosion of the embankment fill. The wingwalls provide a
hydraulic transition at the entrance and exit of the conduit.
The standard designation for the size of a box culvert shall be the span followed by the rise (see
Figure 12.1.1-1 Single/Multiple Cell RCB). For example, a 10 x 8 designation is a box culvert
with a span of 10 ft. and a rise (height) of 8 ft. The designation for a multiple cell box culvert shall
be the number of cells followed by the cell size. For example, a 3-10 x 8 is a triple cell box culvert
with each cell measuring 10 ft. span by 8 ft. rise. For Standard Box Culverts, all cells of a multiple
cell box culvert shall be the same size. The span by rise designation shall be measured as the clear
distance from the inside faces of walls, and the clear inside distance from top to bottom slabs. For
normal practice, the rise dimension is considered vertical and the end face of the RCB is assumed
to be constructed vertical. The span by rise designation is an indication of the hydraulic flow area.
The structural-design span length for slab and wall members shall be determined by the applicable AASHTO specifications.
Bridge Section
12 - 1
Design Manual
For purposes of classification, a box culvert can be classified as a Bridge Box, a 10 ft. to 20 ft.
Structure (Formerly known as 500 Series), or a Road Culvert. (See Figure 12.1.1-2 RCB Plan
Views, Figure 12.1.1-3 Box Size Definitions, and Figure 12.1.1-4 Bridge Box, 10 to 20 Structure (500 Series), or Road Culvert
Bridge Box: A bridge box is defined as a structure having a length greater than 20 ft. measured
along the centerline of the roadway from the inside faces of both exterior walls (including
all span widths and the thickness of all interior walls). The total length along the centerline
of project shall consider the effects of the skew or rotation. For example, a 20 x 10 box culvert constructed normal to centerline of project is not a bridge. A 20 x 10 box culvert constructed skewed or rotated to centerline of project would be classified as a bridge. A 2-10
x 8 box culvert would be classified as a bridge, i.e. two (2) 10 ft. clear spans plus an interior wall exceeds 20 ft.
10 ft. to 20 ft. Structures, (Formerly known as 500 Series Boxes): Box culverts with a total
width of 10 ft. or greater (measured perpendicular to the centerline of box) to less than or
equal to 20 ft. (measured along the centerline of the roadway) are considered 10 ft. to 20
ft. Structures. Measurements are taken from the inside faces of both exterior walls and
include all span widths and the thicknesses of all interior walls.)
Road Culvert: A Road Culvert is defined as a structure having a length of less than 10 ft. from the
inside faces of both exterior walls measured perpendicular to the centerline of the box.
RCB vs. RFB: Box culverts are further defined as RCBs (Pinned) and RFBs (Fixed).
A Pinned box is designed with the walls and slabs assumed to be simple spans
(independent of one another). Normally there is only one layer of steel in the walls of
pinned boxes (unless the cell height is greater than 10 ft.). In addition, pinned boxes do not
have fillets in the corners of the box.
Fixed (also referred to as Rigid Frame) boxes are designed with the slabs and walls
assumed to be continuous (connected to one another). Therefore, in Rigid Frame Boxes
(RFBs), there will always be an L-shaped reinforcing bar in the corners of the box near
the outside face. This corner reinforcing bar distributes some of the load from the slab to
the wall and vice-versa. Rigid Frame culverts always have two layers of steel in the wall.
All KDOT Rigid Frame Boxes have fillets in the corners of the box. This fillet helps
provide rigidity to the frame.
On the Plan/Profile Sheets and Title Sheet, in the note that specifies location, size and type
of box culverts; label pinned boxes as RCBs, and label fixed boxes as RFBs.
The State Road Office is responsible for the design and detail generation of Road Culverts and
10 ft. to 20 ft. Structures. The State Bridge Office is responsible for Bridge Boxes. The 10 ft.
to 20 ft. structures have a unique serial number for their respective county. This requires coordination with the Bridge Special Assignments Section in acquiring a serial number.
Bridge Section
12 - 2
Design Manual
12.1.2 Length
The length of an RCB is considered to be the horizontal length measured along the centerline of
the culvert from exterior face to exterior face and shall be rounded up to the nearest inch. The
Roadway length (right or left) is the horizontal distance from the centerline of roadway (or project) to the roadway side of the hubguard and is measured normal (90) to the centerline of roadway (or project). The Roadway Length is a parameter used in determining guardrail
requirements, encroachments in the safety recovery zone, and other features of Geometric Roadway Design. As an example, a 10 x 8 x 272-3 RCB has a horizontal length (to the nearest inch)
of 272-3, but may have combinations of Roadway Left and Roadway Right depending on
the grade of the box and the angle of skew or rotation. Roadway lengths are rounded to the nearest
0.01 ft. (see Figure 12.1.2-1 RCB Plan View and Section). For normal practice, it is sufficient to
station the location to the nearest ft.
Bridge Section
12 - 3
Design Manual
12.1.4 Wingwalls
Wingwalls are referred to as flared when the axis of the wingwall forms an acute angle with the
centerline axis of the box. Straight wingwalls are an extension or continuation of the box walls.
(See Figure 12.1.4-8 Straight Wingwall Plan Details) Wingwalls constructed at 90 to the barrel
or constructed parallel to centerline of roadway are not considered hydraulically efficient and are
not recommended for use on KDOT Standard RCBs. Flared wingwalls will be used on the Standards at the entrance ends of culverts for hydraulic reasons. However, straight wings may be
specified at the entrance end when the hydraulics and additional costs are adequately considered.
Straight wings, compared to flared wings, for a rise of 8.0 ft. or less may be economically specified for single cell boxes. For multiple cell boxes, the cost for straight wings, including the floor,
may exceed the cost for flared wings; however, at sites where erosion aprons are specified,
straight wings may be appropriate. Otherwise, flared wings will be used at the exit end.
The flare angle for normal or rotated culverts will be 45 degrees. For Standard 30 and 45
skewed boxes, the flare angle will be as shown on Figure 12.1.4-1 Wingwall Flare Angle.
The reference point for wingwall geometry is considered the intersection of the back face of the
wingwall and the exterior face of the box. The length of the wingwall is measured from the free
end to the reference point along the back face of the wall. (see Figure 12.1.4-2 Embankment at
Wingwalls)
Length of flared walls will be based on a local embankment slope behind the wing of 3.5:1 and a
2:1 slope in front of the wing. (see Figure 12.1.4-2 Embankment at Wingwalls) The computed
length of the wall will be rounded up to the next 6 inches. The elevation at the end of flared walls
shall be computed from the flow line with a 2:1 slope and the height at the end of the wing shall
be rounded up to the nearest inch. Flared wingwalls are available for standard box heights from 3
ft. to 20 ft. (See Figure 12.1.4-3 Wingwall Dimensions for 0 Degree Skew RCBs, Figure 12.1.44 Wingwall Dimensions for 30 Degree Skewed RCBs, and Figure 12.1.4-5 Wingwall Dimensions for 45 Degree Skewed RCBs for flared wingwall dimensions)
Length of straight walls will be based on a local embankment slope beyond the hubguard of 3:1.
(see Figure 12.1.4-6 Straight Wingwall Details) The computed length of the wall will be rounded
up to the next 6 inches. The elevation at the end of the straight walls shall be computed at the end
of the wall as h/4 above the flow line (2.5 ft. maximum) and rounded up to the nearest inch. (see
Figure 12.1-8) Straight wingwalls are available for standard box heights from 2 ft. to 10 ft. (See
Figure 12.1.4-7 Wingwall Dimensions for Straight Wings for straight wingwall dimensions)
Bridge Section
12 - 4
Design Manual
Bridge Section
12 - 5
Design Manual
Bridge Section
12 - 6
Design Manual
Bridge Section
12 - 7
Design Manual
Bridge Section
12 - 8
Design Manual
Bridge Section
12 - 9
Design Manual
Bridge Section
12 - 10
Design Manual
Bridge Section
12 - 11
Design Manual
Bridge Section
12 - 12
Design Manual
Bridge Section
12 - 13
Design Manual
Bridge Section
12 - 14
Design Manual
Bridge Section
12 - 15
Design Manual
Bridge Section
12 - 16
Design Manual
Bridge Section
12 - 17
Design Manual
Bridge Section
12 - 18
Design Manual
12.2 Material
12.2.1 Concrete
Grade 4.0(AE)
Grade 4.0
fc = 4,000 psi
fc = 4,000 psi
Grade 4.0 concrete shall be used for design and construction of Reinforced Concrete Boxes
except that Grade 4.0 (AE) concrete shall be used in the top slab at locations where the top slab is
the riding surface (or where the actual fill is 2 ft. less) and it is expected that the top slab will be
exposed to frequent applications of deicing salts. Air-entrained concrete should be used in conjunction with epoxy-coated reinforcing steel (see Section 12.6.3 Detailing for corrosion protection for reinforcing).
When specified by the plans or required by the Plan Engineer, a seal course of unreinforced concrete (Commercial Grade) may be used.
12.2.2 Reinforcing
ASTM A615
Grade 60
Fy = 60 ksi
Maximum length of bars #5 through #11 shall not exceed 60.0 ft. Maximum length of #3 and #4
bars shall be 40.0 ft. This is a field handling consideration. See Section 12.6.3 Detailing for size,
spacing, and clearance requirements.
Bridge Section
12 - 19
Design Manual
12.3 Loads
12.3.1 Vehicle Load (LL)
KDOT uses a one ft. strip method to analyze the top slab of culverts. The HS20 live load or design
tandem only shall be used (Article 3.6.1.3.3 for spans in the longitudinal direction), whichever
produces the greatest stress. Per Article 3.6.1.3, the lane load included in the HL-93 load is not
used for box culverts. Where traffic travels parallel to the span, the designs will be limited to one
lane loaded and use a multiple presence factor of 1.2 per Article C3.6.1.3.3. In rare cases where
the traffic travels perpendicular to the span a special analysis is required. KDOT will not make
any corrections for skewed structures, per Article 12.11.2.4. Live load need not be considered for
single cell structures where the fill is greater than 8 ft., or for multi-cell structures with the fill
height greater than the overall box width. See Appendix C LRFD RCB Mathcadd Loads for
example calculations.
Bridge Section
12 - 20
Design Manual
12.3.3 Distribution
Per Article 4.6.2.10, where the depth of fill is less than 2.0 ft., the live load shall be distributed
over a distance E, measured perpendicular to the span, and Espan measured parallel to the span per
Equations 4.6.2.10.2-1 and Equations 4.6.2.10.2-2 respectfully. KDOT uses 1.00 for the Live
Load Distribution Factor (LLDF). This assumes the distribution of the live load through depth of
fill will be consistent with soil.
When the depth of fill is 2.0 ft. or more (Article 3.6.1.2.6), the live load is distributed over a rectangular area starting from a contact patch of 10 in. x 20 in. per Article 3.6.1.2.5. KDOT uses a
22.5 degree angle, 0.500:1 from each side of the patch to the top of the culvert. This article also
allows the use of a 0.575:1 factor for granular fill which would increase the size of the rectangular
area and decrease the load intensity. Unless special circumstances exist, which would change the
overburden material on the culvert from that covered in KDOTs Standard Specifications, the
default of 0.500:1 is used.
For the design of KDOT Standard Culverts, it is assumed that the culvert is founded on a yielding foundation using embankment construction methods. The vertical earth load shall be the soil
weight with applicable design factors.
The foundation is considered to be on springs (compression only) derived from an average modulus of subgrade reaction of 125 pci. These springs replace the distribution of load (reaction) to the
bottom slab specified in Article 12.11.2.3. The passive resistance of the walls is similar to the
floor. The value of the reaction is half that of the floor reaction. These spring supports, representing the soil, at the foundation are based on a modulus of subgrade reaction recommended by
KDOTs Geotechnical Engineer. This may be unconservative for culverts founded on rock. Structures founded on rock may require a special design, and can be investigated for by adjusting the
spring constant and determining the effects.
Bridge Section
12 - 21
Design Manual
Pressure Theory uses equivalent earth pressure and is appropriate for long heeled cantilever walls
and backfill material which is free draining. Acceptable backfill materials will meet criteria
specified in the 12.5.4 Backfill.
The following values are used for the design of KDOT Standard Reinforced Concrete Box Culverts:
Saturated Soil Unit Weight ...................................................... 135 pcf
Soil Weight Unit Weight ......................................................120 pcf
Coefficient of at-rest earth .................................................... 0.50
Because the designer may not be sure which method of construction will occur in the field, KDOT
assumes that Embankment rather than Trench type construction is used. This assumption
results in conservative values for the unfactored vertical earth loads per Article 12.11.2.2.
Bridge Section
12 - 22
Design Manual
Water Effects:
The height of the water table will be taken to be level with the top of the box. The internal effect
assumes that the box is completely full. The soil below the top of the barrel is considered submerged; soil in the EH (earth horizontal) load is buoyant. Use the effective unit weight to calculate this force effect, except for structures with fill heights less than 10 ft. as described below.
Hydrostatic forces (WA) are applied to both the exterior and interior portions of the barrel that
maximize the force effects. The vertical force effect for (WA) is used on the bottom slab. These
two effects are to be considered independent effects which are combined to maximized the greatest effect. The assumed effects of water and buoyancy are shown in Figure 12.3.6-2 Buoyancy
Effects on Backfill Materials.
Special Considerations:
In Kansas, road ditches and creeks in small drainage areas have a water surface elevation which
changes rapidly with each hydraulic event. The probability of saturating the soil in the backfill, as
described in the previous section, is low. The Standard KDOT RCB with less than 10 ft. of fill
will not be designed for this condition, as it would be overly conservative most of the time. If the
designer anticipates the possibility of a sustained high water event, for example in a flood plain or
at a detention storage location, then a custom design may be warranted.
Bridge Section
12 - 23
Design Manual
At Grade Box
*Note: Driving directly on the top slab or with a nomial amount of pavement is the only time 0.0
ft. should be used as the fill height.
For superelevated roadway sections as shown in the graphic, the design fill height may be either a
minimum fill, or a maximum fill section. Investigate both to determine the most conservative
design.
Bridge Section
12 - 24
Design Manual
Fill Heights:
1)
The designer needs to specify the proper depth of fill on the RCB. Design fills
should be specified as follows:
Actual Fill
0
> 0.5 ft.
> 2 ft.
> 3 ft.
> 5 ft.
> 10 ft.
> 15 ft.
> 20 ft.
> 25 ft.
> 30 ft.
> 35 ft.
> 40 ft.
> 45 ft.
<
<
<
<
<
<
<
<
<
<
<
<
<
0.5 ft.
2 ft.
3 ft.
5 ft.
10 ft.
15 ft.
20 ft.
25 ft.
30 ft.
35 ft.
40 ft.
45 ft.
50 ft.
Fill to specify
on plans
0.0*
2 ft.
3 ft.
5 ft.
10 ft.
15 ft.
20 ft.
25 ft.
30 ft.
35 ft.
40 ft.
45 ft.
50 ft.
Bridge Section
12 - 25
Design Manual
For At Grade Boxes an equivalent soil fill height should be used, considering mass and thickness of the pavement, pavement base, and sub-base. The design value shall be noted on the plans.
For other than At Grade Boxes, the weight of pavement and base may be assumed as earth density at 120 pcf.
Design Fills over 50.0 ft. will be considered as special circumstances and will require a review by
the KDOT Design Engineer.The design fill value is a representative design parameter not
intended for use in field construction or for hydraulic analysis.
In special circumstances where unusual variance in fill heights may occur and savings may be
effected as in the case of large and/or long boxes under high fill, more than one Design Fill
Height may be used and shall be so noted on the plans. Culverts designed with more than one
Design Fill Height will require a documented economic analysis to be reviewed by the KDOT
Design Engineer. Where a design life is needed for economic evaluation, a design life of 75 years
will be assumed. The minimum length of culvert section with multiple Design Fill Height shall be
60.0 ft.
Unequal Fill: For locations where unequal fill could be a concern, such as when a box culvert is
installed parallel to the embankment slope, use an RFB. When the differential in fill height is
equal to or greater than 20% a special analysis is required.
Bridge Section
12 - 26
Design Manual
Bridge Section
12 - 27
Design Manual
Bridge Section
12 - 28
Design Manual
Minimum
Maximum
DC
0.90
1.25
1.00
DW
0.65
1.50
1.00
LL,IM,LS
0.00
1.75
1.00
EH
0.50
(Article 3.11.7)
1.35
1.00 or 0.50
(Article 3.11.7)
EV
0.90
1.30
1.00
WA
0.00
1.00
1.00
* ES
0.50
(Article 3.11.7)
1.50
1.00 or 0.50
Bridge Section
12 - 29
Design Manual
12.5.4 Backfill
Soil used to backfill reinforced concrete boxes shall have a liquid limit less than 50, and a plasticity index less than 22. Backfill soil shall be essentially free of all organic matter. High plasticity
and organic soils are not considered free draining materials and should not be used. Soils unacceptable for use as backfill are CH, MH, OH, and OL type soils. Where soils of this type are
encountered, a clean, granular backfill will be required. Specifying granular backfill in areas
where there are expansive soils, will help reduce soil pressures and are consistent with design
assumptions.
Bridge Section
12 - 30
Design Manual
12.5.5 Camber
Unless other information is furnished by a soils report, camber will be shown for design fill
heights over 20 ft. The camber used will vary linearly from the maximum deflection to zero
deflection at the end of the box.
If a field investigation will not be performed to determine foundation settlement, an estimate may
be determined from the report, Guidelines on the Use of Soils Information for Box Design. The
graph in Figure 12.5.5-1 Settlement of Culvert, contains a set of five settlement curves for five
generalized soil types. These curves relate fill height to settlement up to a maximum fill height of
20 ft. For fill heights greater than 20 ft., settlement may be estimated by adding together the
equivalent thicknesses. (ie the settlement for 30 ft. of fill equals to the settlements for 10 ft. plus
20 ft. added together)
The five settlement curves were developed using the assumption of a 20 ft. compressible layer. If
there is less than 20 ft. of compressible material below the culvert in the foundation, the settlement may be proportioned relative to the thickness of the compressible layer. (ie the settlement for
a culvert with a 10 ft. compressible layer would be taken as 0.5 that shown for that curve)
Bridge Section
12 - 31
Design Manual
Bridge Section
12 - 32
Design Manual
Bridge Section
12 - 33
Design Manual
Bridge Section
12 - 34
Design Manual
a pinned frame acting as simple beams in the corners. For RCBs intermediate supports at
walls in multiple cell boxes are considered as knife edge supports.
Because the bottom slab is cast against foundation stabilization, none of the bottom of the
bottom slab is neglected for computation of design depth.
Use shear = 0.85 and moment = 0.90 per Table 12.5.5-1 for buried structures. This
assumes tension controlled regions. Flexure and axial force interaction and design capacities
are evaluated as rectangular column sections as shown below.
For minimum reinforcement requirements as described in Article 5.7.3.3.2. the phi factor
implied in the 1.2xMcr is 1.0. the gross concrete section is used as well as a singly reinforced
cracked section for calculating Asreqd.
Figure 12.6.2-1 Strength Design
Bridge Section
12 - 35
Design Manual
Bridge Section
12 - 36
Design Manual
12.6.3 Detailing
Skewed or Rotated RCB:
Skewed or rotated structures will be designed and detailed with reinforcing, placed normal to the
centerline of the box.
Reinforcing:
Truss bars (crank shaft bars) for single cell Rigid Frames or for multiple cell RCB design will normally not be required and are not recommended. Spacing of the interior face of reinforcing may
be independent of the exterior face for rigid frame boxes. However, for ease of placing, it is preferable that all reinforcing in a particular face (exterior or interior) shall be placed at the same
spacing. For normal practice it is intended that the wall reinforcing will be placed vertical. Detailing practice will reflect that intention. Minimum spacing shall be 5 in. centers. Spacing increments will be in in. intervals. The limits of bar shall be #4 through #11 sizes.
New Boxes:
All clearances are 2 in. where permanently in contact with the earth and 1 in. otherwise.
Because KDOT concrete mixes are cement rich with a low W/C ratio, the cover on the nonearth contact face was reduced by in. (per Article 5.12.3). The clearance for the bottom mat
of reinforcement will be 2 in. Table 5.12.3-1 states that members cast against the earth will
have 3 in. of clearance. However, because KDOT uses a granular foundation stabilization, it
is not considered cast against the earth. This is considered a Class I exposure for crack control.
For the top of the top slab with a fill height of 0 ft., Class II exposure is used for crack control; otherwise Class I is used.
When the top slab will be exposed to frequent applications of deicing salts, epoxy coated
reinforcing bars and air-entrained (AE) concrete should be specified in the top slab. Epoxy
coated bars and (AE) concrete should not normally be specified for box sizes less than 6 ft. x
6 ft. or when the roadway is not surfaced. The default for the RCB design program is to use
epoxy reinforcement and (AE) concrete when the fill height equal to or less than 2 ft.
Box Extensions:
All of the above criteria may also apply to box culvert extensions. Normally, epoxy coated
reinforcing and (AE) concrete will not be used for extensions except in urban areas where the
extension will be subject to deicing salts.
The depth of fill to specify for extensions shall be the fill depth at the end of the existing box
culvert.
See road design standard drawing RD080 (Figure 12.9-3 Typical Culvert Extensions (Std
RD080) for extension details.
Bridge Section
12 - 37
Design Manual
Member Size:
Thickness of concrete members shall be designed in increments of in. The wall thickness shall
preferably be not less than 2/3 the largest slab thickness. The minimum wall thickness shall not be
less than 7 in. for spans 6 ft. and greater, and not less than 6 in. for spans less than 6 ft. Minimum
slab thickness will be 6 in. The minimum fillet size shall be 4 in. x 4 in.
Bridge Section
12 - 38
Design Manual
DC stability
0.90
DC bearing
1.25
EV stability
1.00
EV bearing
1.35
EH
1.50
Class I Exposure
1.00
Bridge Section
12 - 39
Design Manual
Assumptions Continued:
Clearance to reinforcing will be 2 in. from formed surfaces in contact with the earth and
1 1/2 in. clear for surfaces that are not. For the bottom of the footings cast on foundation stabilization the clearance to the reinforcing steel will be 2 in., and the top reinforcing steel
cover is 2 in. regardless of fill height.
Fatigue limit state need not be investigated according to Article 5.5.3.
Member sizes will preferably remain constant throughout the length of the wall. The minimum wingwall thickness will be 7 in. The front face will be reinforced for shrinkage and
temperature for walls over 9 in. thick. The footing will be detailed monolithic with the bottom slab of the RCB. Reinforcement will extend continuously from the wall footing into the
bottom slab.
Bridge Section
12 - 40
Design Manual
Design Parameters:
The following will be assumed for the Standard KDOT wingwall design:
All passive pressure in front of the toe and wall will be neglected.
Wingwalls are designed as vertical cantilever walls: (See Figure 12.7.2-1 Design Assumptions - Vertical Cantilever)
Wingwall Design Soil Parameters as follows:
Lateral Pressure ........................................... Rankine Active Earth Pressure Theory
Live Load Surcharge ......................
Use 2-0 of overburden as equivalent force
Granular Backfill Material.....................................................................Density 120 pcf
Ultimate Bearing Pressure ...............................................................................6,000 psf
Phi Factor for Bearing is ..........................................................................................0.45
Phi Factor for Sliding is ..........................................................................................0.80
Coefficient or Active Earth Pressure....................................................................... 0.33
Internal Friction Angle............................................................................................ 30
Stability .................. Check that the resultant is within the middle 1/2 of the footing
(using 3/4 of the maximum wall height)
A friction factor of 0.50 assumes that the foundation condition will be a granular material
with a tan = 0.50.
Bridge Section
12 - 41
Design Manual
Bridge Section
12 - 42
Design Manual
Bridge Section
12 - 43
Design Manual
Bridge Section
12 - 44
Design Manual
Bridge Section
12 - 45
Design Manual
Bridge Section
12 - 46
Design Manual
Grade Separation
Stream Crossing
Maximum Span:
60-0
42-0
Live Load:
HL-93
HL-93
Foundation:
Precast (free-standing)
CIP (free-standing)
Free Board:
N/A
2-0 @ Overtop
Minimum Fill:
2-0
2-0
Wings/Headwall:
Backfill Material:
Barrier:
* Note: Fully resolved forces will result in the accounting of the forces through
connections and members resulting in minimal damage to the arch structure or
headwall. Contact the Local Projects Team Leader for barrier loading requirements.
** Use granular backfill meeting the requirements of SB-1,SB-2,SCA-2, 3 or 5.
Design Criteria:
1. The structure will be designed in accordance with the current AASHTO LRFD edition
and latest interim requirements for structurally reinforced concrete structures.
2. The design plans will include a Contour Map, Construction Layout and Geology Sheet
with Geology Report. The Geology Report shall bear the seal of the Professional
Geologist. The geology sheet will show the limits of the maximum potential scour
line, include long-term degradation, contraction scour, local scour and lateral
migration.
3. Skews in excess of 45 will not be permitted.
Bridge Section
12 - 47
Design Manual
4. Rise measured from top of cast-in-place footing to the bottom of the bridges top slab
shall, in excess of 16 ft. will not be permitted.
5. A minimum cover of 2 ft., measured from the pavement surface at the roadway edge,
will be provided. Provide distribution slab. See Figure 12.8.1-1 Precast Box Culvert
Details (Standard BR031) for additional criteria.
6. The bottom of the foundation footings shall be a minimum of 4 ft. below streambed
thalweg elevation unless field conditions dictate otherwise.
7. Streambed slab, cut-off wall or other suitable means is required unless streambed is
non-erodible bedrock.
Design Responsibilities:
1. Foundation and bridge sizing consideration will follow all span structure requirements
including design high water and free board clearances. Show the maximum potential
scour on the geology sheet.
2. For stream crossings, hydraulics and waterway opening requirements should be
handled similar to other bridge projects with bridge hydraulics evaluated as
appropriate for the spans involved. Stream Stability analysis shall be performed per
Section 2.3.9. Include a completed Hydraulic Assessment Checklist (HAC) for each
proposed site. The HAC can be downloaded at: http://kart.ksdot.org
3. Foundation borings are required for all projects. The soils and foundations design
including precast portions (i.e. slope stability, settlement, spread footings, piling,
etc....) will be performed and sealed by a Licensed Professional Engineer. Suppliers of
three-sided precast concrete bridges should be contacted for precast loads, reactions,
etc. to be utilized in the foundation designs.
4. The actual design and rating of the Precast Arch Culverts is the responsibility of the
supplier. Shop plans for the Arch Culvert sections along with formal structural
calculations will be submitted to the State Bridge Office for approval. Shop plans shall
be certified by the supplier as being designed and load rated in accordance with
current AASHTO LRFD Specifications. The supplier should also indicate additional
backfilling requirements beyond those found in the KDOT Specifications. Show the
limits of those backfilling requirements.
5. Precast wings and headwall are not allowed for stream crossings. CIP end section
requirements will follow BR031. See Figure 12.8.1-1 Precast Box Culvert Details for
additional criteria.
Bridge Section
12 - 48
Design Manual
Details:
The connection of the exterior to first interior arch segment as shown in Figure 12.8.2-1
Precast Arch Details helps distribute horizontal earth and vehicular impact loads
imparted to the headwall. The joint seal system consists of butyl rope placed in the joint,
with the adjacent areas of the joint primed. A water-proof rubber seal is then bonded
over the joint per KDOTs specifications.
Bridge Section
12 - 49
Design Manual
Bridge Section
12 - 50
Design Manual
Protection:
For arch structures which are assembled from two separate halves and require a closure pour at
the crown of the structure, it shall be detailed and constructed as shown in Figure 12.8.2-2 Closure
Pour, a butyl rope will be placed in the beveled joint where the two arch halves meet and where
the individual arch sections abut at the sides. A longitudinal section at the crown will be protected
by coating the cured closure pour concrete with a primer recommend by the manufacturer and
covered by an rubber adhered to the primer. The closure pour concrete shall be Gr. 4.0 (AE) Air
maintained placed and consolidated according to KDOT Specifications.
Bridge Section
12 - 51
Design Manual
12.9 Miscellaneous
12.9.1 Guardrail
Unless there is a sidewalk on the bridge, it is desirable that bridge rails on At Grade and LowFill Boxes be limited to installations in excess of 50 ft. total span. Where guardrail is required, it
preferably shall be continuous over culverts less than 50 ft. total span. For installations that
require a bridge rail, a Corral rail will be used, unless determined otherwise at field check. The
minimum length of boxes for guardrail installation will be as shown in Figure 12.9.1-1 Minimum
Box Length With Guardrail. The designer will consider corral rail for fill heights up to 1-0. Corral rail should be use when warranted by traffic count, height of drop into the structure, or route
classification. When guardrail is used, consult Road Design for guidance.
Bevel
4 inches
6 inches
8 inches
10 inches
Bridge Section
12 - 52
Design Manual
12.9.4 Hubguard
The hubguard is a detail at the top slab at the end of the RCB to retain a minimum depth of fill
to establish vegetation and prevent embankment erosion. In some instances, the hubguard retains
the roadway surfacing and shoulder. The minimum height of the hubguard shall be 5 in. above the
culvert.
The hubguard height h and width t varies depending on the box span length. See sketch
below.
For spans < 16 ft.; h = 1.50 ft., t = 0.75 ft.
For spans > 16 ft.; h = 1.67 ft., t = 1.25 ft.
The exception to the above criteria is when the value (S + 5 in.) exceeds 1.5 ft. (for spans less than
16 ft.) or 1.67 ft. (for spans greater than or equal to 16 ft.). In this case, h will equal (S + 5 in.)
up to a maximum of 1.75 ft. (for spans less than 16 ft.) or 1.92 ft. (for spans greater than or equal
to 16 ft.). This may occur on culverts under high fills. For h greater than 1.75 ft. (or 11.92 ft.),
the standard wingwall details may need to be modified to accommodate the increased hubguard
height. However, this should be an infrequent occurrence.
Bridge Section
12 - 53
Design Manual
Bridge Section
12 - 54
Design Manual
Bridge Section
12 - 55
Design Manual
Bridge Section
12 - 56
Design Manual
Bridge Section
12 - 57
Design Manual
Bridge Section
12 - 58
Design Manual
Figure 12.9-5 Alignment & Details for Guardrail Protection on Low Fill Culverts (Std
RD617c)
Bridge Section
12 - 59
Design Manual
Bridge Section
12 - 60
Design Manual
Bridge Section
12 - 61
Design Manual
Bridge Section
12 - 62
Design Manual
Pinned vs. Fixed: (See Section 12.6.4 Practical Considerations for Structure Type)
RCB Details Request Forms (4 pages)
KDOTs automated RCB request forms are available through the KDOT Authentication Resource
Tracking (KART) http://kart.ksdot.org/
Bridge Section
12 - 63
Design Manual
Figure 1
Figure 2
Bridge Section
12 - 64
Design Manual
Figure 3
Figure 4
Bridge Section
12 - 65
Design Manual
Quantity calculations:
1. Air entrained concrete quantities include the top slab, the hubguards and on skewed extensions, the top edge beam abutting the old
hubguard (See Std. RD080 & RD510 SI). On rigid frame (fixed) boxes, the walls and fillets above the optional construction joint shown
on the details are also air entrained concrete. Epoxy coated resteel includes all "S", "K" and "G" bars.
2. Extensions: The software asks for the "Length of Existing Bottom Slab Beyond Outside Edge of Hubguard." This existing slab serves
as part of the floor for the new extension. (See KDOT Standard Number RD080 & RD510 SI) Concrete corresponding to the volume
(Normal width of box * Dimension A * Slab Thickness) of the existing slab is subtracted from the floor concrete quantities. This is the
only adjustment to the box concrete quantities, even though the existing flared wings and footings would decrease the concrete needed.
The program also adjusts (decreases) the number of F1, F2 and F3 bars and shortens the F4 bars. The length of the vertical wall bars (W1
and W2) over the extension are not adjusted and may need to be shortened in the field.
3. Hubguard concrete quantities are included in the box concrete. "G" bars are included in the box steel quantities.
WIDTH
SPAN HUBGUARD
HUBGUARD HEIGHT
For all spans, hubguard height must be > 5" (125 mm).
4. Box Length - On new boxes this dimension is used to calculate quantities. On extensions it is added to the details as information only. Box
length is the total length of the box once construction is complete.
Roadway - The Roadway is added to the details as information only. It is not used in any quantity calculations. The Roadway dimension is the
total roadway once construction is complete.
Extension Lengths - On extensions, this value is used to calculate quantities rather than the box length.
Miscellaneous:
Submit your completed "KDOT STANDARD RCB/RFB DETAIL REQUEST FORM" to:
(State and Federal Projects)
Bridge Section
12 - 66
Design Manual
KKK
KKKK
KKK
KKKK
KKK KKKK
KKK KKKK
KKKKKKK
KKKKK
KKKK
KKKKK
KKKKKKK
KKK KKKK
KKK
KKKK
KKK
KKKK
DDDDDDDDD
DDDDDDDDDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDD
DDDDDDDDDD
DDDDDDDDD
OOOOOOO
OOOOOOOOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOO
OOOOOOOOO
OOOOOOO
TTTTTTTTTTT
TTTTTTTTTTT
TTT
TTT
TTT
TTT
TTT
TTT
TTT
TTT
TTT
TTT
PAGE NO. 1
111-2 K-BNCH-04
22.22
1+000
Anderson Co.
111
99
2
45
Left
0
16
14
71.25
76.25
70
75
Bridge Section
12 - 67
Design Manual
PAGE NO. 2
SIZE
F1
F2
F3
F4
S1
S2
S3
S4
S5
K1
>>> K1 Bar INFO.
SPACING
in
NUMBER
5
6
7
4
6
6
7
4
4
6
LENGTH
ft
6.0
226
6.0
572
6.0
226
0.0
160
6.0
226
6.0
570
6.0
226
0.0
80
0.0
72
6.00
256
INCREMENT 6.00 in SHORT
34.167
8.916
12.000
37.917
34.167
8.416
14.500
37.917
37.917
18.250
2.500 ft
LONG 34.000
K2
7
6.00
228
>>> K2 Bar INFO. INCREMENT 6.00 in SHORT
20.000
6.000 ft
LONG 34.000
ft
ft
W1
W2
W3
W4
G1
G2
S2
S2
F2
F2
5
6
4
5
8
10
HORIZONTAL LEG
VERTICAL LEG
VERTICAL LEG
HORIZONTAL LEG
12.0
12.0
0.0
12.0
0.0
0.0
=
=
=
=
5.083
3.333
4.333
4.583
298
296
204
296
4
4
15.417
15.417
37.917
15.417
48.333
48.333
ft
ft
ft
ft
10.500
11.000
10.000
10.000
in
in
in
in
Note: Clearance
top slab =
2.0 in
Bridge Section
12 - 68
Design Manual
PAGE NO. 3
Bridge Section
12 - 69
Design Manual
PAGE NO. 4
561.384
362.849
85.760
85.760
27.015
207.793
164.661
106.843
16.542
16.542
24.735
0.000
20611.640
0.000
8931.756
621.201
8931.756
621.201
1505.723
93920.020
758.000
379.000
379.000
656.000
328.000
328.000
583.856
583.856
OF
OF
OF
OF
CONCRETE
FND STBL
RESTEEL
GRAN BK
TOTAL COST
=
=
=
=
$
$
$
$
329.00
41.51
0.71
46.00
= $
376079.80
/
/
/
/
yd^3
yd^3
lb
yd^3
Bridge Section
12 - 70
Design Manual
Bridge Section
12 - 71
Design Manual
Bridge Section
12 - 72
Design Manual
Bridge Section
12 - 73
Design Manual
Bridge Section
12 - 74
Design Manual
Bridge Section
12 - 75
Design Manual
2/24
Input
RCB or RFB (use p for RCB and f for RFB) .......................................
Type "f"
Span 20 ft
Culvert Height measured from the top of floor to bottom of slab. (ft) .....
Height 8 ft
H 3 ft
Cell 2
soil 125
lbf
ft
ko 0.50
Fill 1.0
Fillet 16 in
Database
box_type num_cel
span
height
fill
f
2
20
8
3
f1_size f1_spabar f2_size f2_spabar f3_size
6
5.5
6
6
8
ko
Wall int
8 in
Wall ext
9 in
Slabtop
12.5 in
Slabbot
13.5 in
Bridge Section
12 - 76
Design Manual
2/24
Loads
Dead Loads
self weight:
The top slab weight is applied to the top of the box. The wall weight and the top slab weight
are applied to the bottom slab in an upward uniform pressure. The bottom slab weight load is
directly applied to the resisting soil.
earth vertical
The design fill is measured from the top of the top slab to the top of the pavement. A soil
structure interaction factor is applied. Article 12.11.2.2.1
F'e 1.0 0.20
Equation 12.11.2.2.1-2
Bc
Fe
Fe shall not exceed 1.15 for installations with compacted fill along the sides of the
box section, or 1.40 for installations with uncompacted fill along the sides of
the box section.
Bridge Section
12 - 77
Design Manual
2/24
embankment construction:
We Fe soil Bc H
Loading per one foot strip
EV
earth horizontial:
0.2
We
B ft
c
ko soil z' ft
p EH ( z')
p EH ( H )
Equation 12.11.2.2.1-1
EV
kip
ft
Equation 3.11.5.1-1
kip
ft
0.4
EHtop p EH ( H )
p EH ( z)
0.8
kip
ft
EHbot p EH ( z)
Bridge Section
12 - 78
Design Manual
2/24
Eflow
ft
10.4 ft
Eflow
Distribution for Wheels Through Earth Fill (contact area factor) .................
LLDF 1.00
Lt 10 in
Equation 4.6.2.10.2-2
3.8 ft
Espan
32 kip MPF ft
E E
flow span
50 kip MPF ft
E E
flow span
TruckE
TandemE
0.963
kip
ft
1.505
kip
ft
In lieu of a more precise analysis, or the use of other acceptable approximate methods of
load distribution permitted in Section 12, where the depth of fill is 2.0 ft. or greater,
wheel loads may be considered to be uniformly distributed over a rectangular area with
sides equal to the dimension of the tire contact area, as specified in Article 3.6.1.2.5, and
increased by either 1.15 times the depth of the fill in select granular backfill, or the depth
of the fill in all other cases. The provisions of Articles 3.6.1.1.2 and 3.6.1.3 shall apply.
Where such areas from several wheels overlap, the total load shall be uniformly distributed
over the area
Bridge Section
12 - 79
Design Manual
2/24
DistW
10.7 ft
DistrL_TR 10 in LLDF H
DistrL_TR
Tandem
DistrL_T 10 in 4 ft LLDF H
DistrL_T
3.8 ft
7.8 ft
Tandemfill
32 kip MPF ft
Dist Distr
W
L_TR
Truckfill
50 kip MPF ft
Dist Distr
W
L_T
Tandemfill
0.939
kip
ft
0.718
kip
ft
For single-span culverts, the effects of live load may be neglected where the depth of fill is more
than 8.0 ft. and exceeds the span length; for multiple span culverts, the effects may be neglected
where the depth of fill exceeds the distance between faces of end walls.
Bridge Section
12 - 80
Design Manual
2/24
0 if H ! 8 ft Cell = 1
0 if H ! Cell Span Wall int ( Cell 1 ) Cell ! 1
TruckE if H 2 ft
0.939
LL truck
kip
ft
Truckfill if H t 2 ft
Distrtruck
Espan if H 2 ft
DistrL_TR otherwise
LL tandem
Distrtruck
3.8 ft
LL tandem
0.718
0 if H ! 8 ft Cell = 1
0 if H ! Cell Span Wall int ( Cell 1 ) Cell ! 1
TandemE if H 2 ft
kip
ft
Tandemfill if H t 2 ft
Distrtandem
Espan if H 2 ft
DistrL_T otherwise
Distrtandem
7.8 ft
Fatigue uses only one truck / MPF and fixed axle of 30 ft.
LL fat
LL truck
MPF
LL fat
0.8
kip
ft
Bridge Section
12 - 81
Design Manual
2/24
DE
IM
33 1.0 0.125 DE
100
1 if
H
ft
33 1.0 0.125 DE
100
1 t 1.0
Equation 3.6.2.2-1
1.0 otherwise
IM
1.21
IMfat
15 1.0 0.125 DE
100
1 if
15 1.0 0.125 DE
100
1 t 1.0
Table 3.6.2.1-1
1.0 otherwise
IMfat
1.09
Bridge Section
12 - 82
Design Manual
2/24
( 1.0ft ) if H 1.0ft
H1
3 ft
H otherwise
Note: This is taken at the max. location in plan using
the Tandem = 25 kip.
HLL H1 Height
HLL
11 ft
HLL
HLL 12
1 y 1
1
ft
ft
x 1
x 1
( x 1 )
1 y
1
12
ft
( y 1 ) ft
Dimensionless Parameters......
Z
H1
m
X
H1
x y
x1
0.28 n
0.16 n 2
x1
if m
1 y
nx1
m 2 n 2
1 y x 1
1.77 m
1 y
0.4
otherwise
QL
F
H 2
1
pLL
Bridge Section
12 - 83
Design Manual
2/24
The increase in pressure (in ksf) as a function of Depth for Point Load
0
pLL.Res
5
x y
( 0ksf ) if Z
pLL
Zx 1
x y
x 1
H1
otherwise
10
15
1.5u 10
pLL
x 5
wLL
1 y
pLL.Res
Height
Res stack
ft
max wLL
y 1
ft ft
12
wLL
0.173
ft
kip
kip
ft
Bridge Section
12 - 84
Design Manual
10
2/24
( Height y ) water ft
p WA ( 0 )
0.499
p WA ( Height )
kip
WA p WA ( 0 )
ft
0.000
kip
ft
Design Considerations
I 1.00
Load Modifiers Ductility........................... 1.00
Redundancy .................. 1.05
Importance .................... 1.00
D 1.00
R 1.05
Wall Thickness
Interior wall thickness,(in)...............................................................
Wall int
8 in
Wall ext
9 in
Slabtop
12.5 in
Slabbot
13.5 in
Bridge Section
12 - 85
11
Design Manual
2/24
Loading Summary:
Earth Loads
_____________________________________________________________
Vertical ...............(entire top slab)................................
0.380
EV
EHtop
EHbot
kip
ft
0.188
kip
0.823
kip
ft
ft
_____________________________________________________________
0.939
LL truck
ft
LL tandem
0.718
Distrtruck
3.8 ft
Distrtandem
kip
max wLL
kip
ft
7.8 ft
0.173
kip
ft
LL fat
kip
ft
________________________________________________________________
Water
0.783
IMfat
1.21
1.09
________________________________________________________________
WA
0.499
kip
ft
Bridge Section
12 - 86
Design Manual
January 6, 2012
Purpose: Hypothesize that shear capacity of concrete slabs under earth fill is greater than current
AASHTO specifications allow.
Doubly Reinforced Concrete Section With Moment and Axial Loads Less than Ultimate Strength
Figure 1
F
Nu As fs = A's f's
=0
M
Nu d
=0
h
2
1 b k d A' f
2
s
c
1 b k d A' f d k d
2
s
c
Where:
Nu ..................................... Applied Axial Force
Mu ..................................... Applied Moment
kd...................................... Depth to the Neutral Axis
fc = Ec c
fs = Es s
f's = 2 Es 's
Input:
v 0.85
fy 60ksi
c 0.8
Es 29000ksi
fc 4ksi
Vp 0kip
f 0.9
M u 28.375kip ft
Vu 29.37kip
b v 12in
h 11in
Vs 0kip
d v 7.92in
Vc 14.57kip
d e 8.5in
Nu 4.17kip
d'e 2.0in
As 1.58in
A's 1.896in
d'' d e
e
Mu
Nu
h
2
d''
d''
3 in
84.655 in
p
e
de
9.959
Ec 33 145
1.5
fc
psi
psi
As
p'
bv de
n
Es
Ec
A's
bv de
n
7.958
Bridge Section
12 - 87
Guess:
Design Manual
The following was derived from Figure 1 for a cracked, doubly-reinforced concrete section using
The equations from ACI Publication SP-3 "Reinforced Concrete Design Handbook - Working
Stress Method" Third Edition, 1965:
j 0.84502
i
de
1j
1.093
m n p i ( 2n 1 ) p'
q n p i ( 2n 1 ) p'
z
de
k
1
d'e
m 2q m
( 2n 1 ) A's
k bv de
1
2
k de
( 2n 1 ) A's
k bv de
1
1
0.412
0.2
0.34275
d'e
d'e
k de
k de
d'e
0.452
j (1 z k)
c k de
2.913 in
0.84502
Nu
j As i
fs
n
e
de
1 k
d'e
k d
e
f's 2 fs
1
k
4.17 kip
Mu
28.375 kip ft
2
2
fs
28.467 ksi
s
fc
1.865 ksi
c
f's
9.308 ksi
's
fc b v k d e f's A's fs As
fs
Es
fc
Ec
f's
Ec
0.00098162
0.0005119
's
0.00255427
5.279 kip
h k de
h
h
f's A's d'e fs As d e
2
3
2
2
fc b v k d e
28.698 kip ft
Bridge Section
12 - 88
Design Manual
Now that the stresses and strains are calculated, try to justify higher shear capacity for this section. The section defined
above fails for the applied shear load. For Article 5.8.3.4.2 let us try using the actual calculated strain to solve for shear.
Article 5.8.3.4.2
ag 0.75
4.8
51
1 750 s
39
V.c 0.0316
fc
ksi
sxe
sxe
29deg 3500deg s
12 in
16.606 kip
V.c
1.38
ag 0.63
2.765
in
ksi b v d v
v V.c
32.436 deg
Vu
Vr < Vu
14.11 kip
29.37 kip
Still No Good.
This helps some, but Vs still = 0 and Vr is not greater than Vu. Let us see how much shear capacity is left in the existing
reinforcing in dowel action. Article 5.10.11.4.4 allows for dowl action in a compression memember.
Article 5.10.11.4.4
Use leftover As for Dowel Action. Concrete shear, Vc = 0 but is replaced by the 0.75*Nu term in this calculation.
Notice, we used a 0.6 factor on the available area for shear that is missing in AASHTO and ACI.
fy f's
fy
fy fs
fy
As_comp_leftover A's
As_comp_leftover
As_tension_leftover As
2
1.602 in
As_tension_leftover
0.83 in
Vn
90.688 kip
Vr v Vn
Vr
77.08 kip
Vu
29.37 kip
Vr > Vu
This helps as well, but since we don't strictly fall into the category of Article 5.10.11.4.4 for an RCB, the following approach
will be followed:
V.s 0.6 As_tension_leftover As_comp_leftover fy
Vc
Conclusion:
V.r
86.81 kip
Vu
29.37 kip
Vr > Vu
Using a more refined tension strain with the above relationship may yield higher values for calculating shear
capacity. AASHTO 5.10.11.4.4 allows for dowel action in a compression member at an extreme event limit
state. For concrete slabs under earth fill, using the left over tension and compression A s can enhance the
shear capacity in the section. The conclusion is that KDOT will design our slabs for maximum moment and
check the ultimate shear capacity of the section based on the left over A s using the above method.
Bridge Section
12 - 89
Design Manual
Bridge Section
12 - 90
Design Manual
Bridge Section
12 - 91
Design Manual
Bridge Section
12 - 92
Design Manual
Bridge Section
12 - 93
Design Manual
Bridge Section
12 - 94
Design Manual
Bridge Section
12 - 95
Design Manual
Bridge Section
12 - 96
Design Manual
13 RAILINGS
Table of Contents
13.1 General ...................................................................................................................1
13.2 Design Requirements .............................................................................................1
13.3 Curbs ......................................................................................................................2
13.4 Railings/ Barriers ....................................................................................................2
13.5 Fencing .................................................................................................................24
13.6 Sidewalks .............................................................................................................30
13.7 Temporary Barrier ................................................................................................34
13.8 Light Standard Support ........................................................................................38
13.9 Americans with Disabilities Act Accessibility Guidelines ..................................42
13.10 Guard Fence - Bridge Rail Transition ................................................................45
13.11 KDOT BRIDGE RAIL POLICY .......................................................................45
List of Figures
Figure 13.4-1 Kansas Bridge Summary Sheet (A) .........................................................................5
Figure 13.4-1 Kansas Bridge Summary Sheet (B) .........................................................................6
Figure 13.4-3 Guidelines for the 32" Kansas Corral Rail (Std. BR182C) .....................................8
Figure 13.4-4 Guidelines for the 32" Kansas Corral Rail (Std. BR182E) .....................................9
Figure 13.4-5 Guidelines for the 27" Kansas Corral Rail (Std. BR183A) ...................................10
Figure 13.4-6 Guidelines for the 27" Kansas Corral Rail (Std. BR183D) ...................................11
Figure 13.4-7 Guidelines for the 27" Kansas Corral Rail (Std. BR183E) ...................................12
Figure 13.4-8 Guidelines for the F4 Barrier Curb (Std. BR184A) ..............................................13
Figure 13.4-9 Guidelines for the F4 Barrier Curb (Std. BR184B) ..............................................14
Figure 13.4-10 Kansas Corral Rail Quantities (27") ....................................................................15
Figure 13.4-11 Kansas Corral Rail Quantities (32") ....................................................................16
Figure 13.4-12 F-Shape Barrier Curb Quantities (32") ...............................................................17
Figure 13.4-13 F-Shape Barrier Curb Quantities (42"& 51 - Vertical Face) .............................18
Figure 13.4-14 F-Shape Barrier Curb Quantities (42" & 51" Sloping Face) ...............................19
Figure 13.4-15 Typical 51" F-Shape Barrier Curb Details ..........................................................20
Figure 13.4-16 Kansas Barrier Summary Sheet (A) ....................................................................21
Figure 13.4-16 Kansas Barrier Summary Sheet (B) ....................................................................22
Figure 13.4-17 32 Corral Rail with Expansion Joint ..................................................................23
Figure 13.5-1 Railroad Overpass Fencing ...................................................................................25
Figure 13.5-2 Railroad Overpass Fencing ....................................................................................26
Figure 13.5-3 Pedestrian Fence Details (Std. BR170) ..................................................................27
Figure 13.5-4 Railroad Fence Details (Std. BR171) .....................................................................28
Figure 13.5-5 Railroad Pededtrian Protective Fence (UP & BNSF RR) (Std. BR171A) .............29
Figure 13.6-1 5-0 Bridge Sidewalk (Design Speed > 40 mph) ...............................................31
Figure 13.6-2 5-0 Bridge Sidewalk (Design Speed < 40 mph) .................................................32
Figure 13.6-3 Bicycle Safety Railing ...........................................................................................33
Volume III US (LRFD)
Version 1/14
Bridge Section
13 - i
Design Manual
Figure 13.7-1 Anchorage of Type F3 Temporary Safety Barrier to Bridge Deck ........................35
Figure 13.7-2 Barrier Protection for Repair Projects ....................................................................36
Figure 13.7-2 Temporary Expansion Barrier ...............................................................................37
Figure 13.8-1 Lighting Standard Support Without Sidewalk (Preferred) ....................................38
Figure 13.8-2 Lighting Standard Support Without Sidewalk (Alternate) ...................................39
Figure 13.8-3 Lighting Standard Support With Sidewalk (Preferred) .........................................40
Figure 13.8-4 Lighting Standard Support With Sidewalk (Alternate) .........................................41
Figure 13.9-1 Plate Over Expansion Joint ....................................................................................43
Figure 13.9-2 Americans With Disabilities Act Accessibility Guidelines (ADAAG) .................44
Figure 13.11-1 Details of Thrie Beam Guard Fence Transition (Std. RD613) ............................49
Figure 13.11-2 Gutter Detail at Bridge Ends (Std. RD614) .........................................................50
Figure 13.11-3 W-Beam with Rubrail Bridge Approach Transition (Std. RD615) .....................51
Figure 13.11-4 W-Beam with Rubrail Bridge Approach Transition Details (Std. RD616) .........52
Figure 13.11-5 Thrie Beam Bridge Approach Transition (Std. RD612) ......................................53
Appendixs
Appendix A Historic Rail .............................................................................................................54
Appendix B KDOT 3R Standard Bridge Rails ........................................................................66
Appendix C Non Standard Rails ..................................................................................................70
Bridge Section
13 - ii
Design Manual
13 RAILINGS
13.1 General
Section 13 of the LRFD Specifications addresses the design of railings. "Railings" are used as a
generic term in the specifications. Railings include outside traffic safety barriers or parapets as
well as medians and bicycle and pedestrian railings.
The design requirements for railings utilized on KDOT bridges have undergone changes in recent
years as the Federal Highway Administration (FHWA) has established crash-testing requirements
and AASHTO Specifications have been revised. Additionally, a desire for more attractive railings
has influenced the style of railings on projects where aesthetics is a consideration. Please discuss
at field check as KDOTs participation will be limited in scope and dollar amount percentage.
Minimal aesthetic enhancement is allowed where it makes sense such as in high visiblity urban
areas. Aesthetic enhancements should be limited to durable items such as form liners and concrete
coloring. High maintenance aesthetics such as surface staining/painting and ornate railings should
be avoided. Aesthetic enhancements, if used, should stay below 5% of the structure cost and be
appropriate for the location. If ornate railings are requested by cities and approved for use in the
project, an agreement will be established limiting the responsibility for maintenance, by the state,
to structural concerns only.
Incidences involving objects thrown from railroad overpasses onto rail traffic below has led to
the adoption of protective screening requirements by the railroad. The rapid increase in bicycle
trails and traffic has increased attention on bicycle railings. This section of the LRFD Bridge
Design Manual details our policies regarding the design of bridge railings for KDOT projects.
Bridge Section
13- 1
Design Manual
objects just behind the railing (such as light poles), must address safety concerns presented by this
encroachment including:
1)Snagging on posts - which can result in the attachment (i.e., post) penetrating the
occupant compartment or causing the vehicle (i.e., hood) to penetrate the cab.
2)Spearing - objects, such as a horizontal railing member, penetrating windshields
and injuring occupants.
3)Debris falling onto traffic below. (i.e., impacted noise wall panels)
Attachments within the area of encroachment shall be designed to break away before severely
damaging the vehicle, contain any debris from damaging traffic below, and have no members,
such as rail ends, which might spear the occupant compartment. Ends of rails shall be sloped at
45 degrees or flatter to reduce the chance of spearing. Posts shall be setback from the face of railing to minimize snagging.
Small sections of curb or sidewalk placed in front of railings cause vehicles to vault up onto the
railing. For this reason sidewalks with a projection between 9" and 3'-6" from the face of railing
are not allowed and curb heights are limited to a maximum of 8".
13.3 Curbs
Where curb and gutter sections are used on the roadway approach, a closed section of rail on the
bridge should match the road curb, except it may exceed the road curb height on the approach.
Bridge curbs serve mainly the purposes of drainage control and in limited capacity to delineation
of pedestrian walkways. Curbs shall be designed in accordance with Article 13.7. Current KDOT
policy is not to use brush curbs on bridges other than for city streets with speed limits less than or
equal to 40 mph and not designated as a school routes or bike paths.
Bridge Section
13 - 2
Design Manual
The corral-type rail may be either an open section or a closed section, depending upon whether or
not bridge drainage at the curb line is a requirement. Most rural bridges using the corral railing
will be of the open type, which allows bridge drainage over the side.
For overpass bridge structures over a railroad, highway, or a local road, no drainage is allowed to
drop on the railroad right-of-way or the shoulder-to-shoulder width of the road underneath. For
long overpass bridges, openings may be provided for drainage over protected berm slopes; use
details similar to those shown in the Bridge Design Standard BR104d .
The common height of the Kansas Corral Rail is 27 or 32 inches. The common heights of the Barrier Rail is 32, 42, 51 or 54 inches. The preferred railing is the 32 inch Kansas Corral Rail or the
32 inch F4 Barrier Rail. Bridges on curves with a radius of 500 ft. or less should have a rail
height of 42 inches on the extrados as an additional safety precaution. The 51 inch Barrier Rail is
used in the median as a glare barrier and a 54 barrier mounted to the shoulder is use for pier protection.
For railroad overpass structures the barrier height is a function of the shoulder width. Use a 32"
barrier with 6-0 shoulders and use 42" with 4-0 shoulders. Provide the 42" barrier for the 40 shoulders for a distance of 25-0 from centerline of track or access road. (See Figure 13.5-1
Railroad Overpass Fencing).
Transitions for different height rails will be 12:1 maximum. Adjacent structures with a median
gap of two feet or less are considered one structure with a closed median. Adjacent structures
more than two feet apart are treated as individual structures.
Sample standard rail details shown in the following graphics are intended for use on either slab
bridges or girder bridges; with or without curbs. They are detailed so they can be inserted directly
into a set of plans.
At locations in the rail were discontinuities occur, such as at bridge expansion joints and at end
sections without an end block, half the reinforement spacing from that shown on the design standard for the F4 barrier. Provide this extra reinforcement for a length equal to the depth of the
vertical break.
Railing types are ranked by a Testing Level (TL- X) designation to indicate the level of protection
a rail provides. The larger the number in the (X) position the greater the protection.
Table A13.3-1 indicate the forces and loading geometry for the given test levels. In the past, the
designation used for this same reason was Performance Level (PL-X), this designation is no longer used.
Bridge Section
13- 3
Design Manual
Testing
Application
27
Corral Rail
PL-1 /TL-2
BoLP
32
Corral Rail
or Barrier
PL-2 /TL-4
State System
Pier Protection
42
(32+10)
Barrier
PL-2 /TL-4
RR/Glare
Pier Protection
42
Barrier
PL-3 /TL-5
Pier Protection /
Curves
51
(32 + 19)
Barrier
PL-2 /TL-4
Median/Glare
54
(42+12)
Barrier
PL-3 /TL-5
Pier Protection
Shoulder or
Median
If the design of the structure includes a sidewalk, a concrete barrier rail will be used between the
traveled way and the sidewalk. For State routes with design speed less than or equal to 40 mph,
the minimum height of the separator railing above the sidewalk shall be 24 inches and the railing
surface shall be smooth to avoid snag points for pedestrians or cyclists, See Figure 13.6-2 5-0
Bridge Sidewalk (Design Speed < 40 mph) for additional details. The exception previously noted
is for locally owned structures with speeds less than or equal to 40 mph and not located on a
school walk route for which current Figure 13.7.1.1-1 may be considered for use. For design
speeds over 40 mph or if a high volume of bike traffic is expected and the risk involved if a cyclist
would fall over the separator is great, use a minimum railing height of 42 inches. A height of 42
inches would enable a falling cyclist to grasp the railing. See Figure 13.6-1 5-0 Bridge Sidewalk (Design Speed > 40 mph) for additional details.
The height of the railing on the outside edge of the sidewalk shall be a minimum of 42 inches for
pedestrians and a minimum of 54 inches for bicycles.
To obtain the height of 42 inches on the outside of the sidewalk, a metal rail on top of a concrete
riser or a short height of chain link fence may be used Figure 13.6-3 Bicycle Safety Railing.
Bridge Section
13 - 4
Design Manual
Bridge Section
13- 5
Design Manual
Bridge Section
13 - 6
Design Manual
Figure 13.4-2 Guidelines for the 32" Kansas Corral Rail (Std. BR182B)
Bridge Section
13- 7
Design Manual
Figure 13.4-3 Guidelines for the 32" Kansas Corral Rail (Std. BR182C)
Bridge Section
13 - 8
Design Manual
Figure 13.4-4 Guidelines for the 32" Kansas Corral Rail (Std. BR182E)
Bridge Section
13- 9
Design Manual
Figure 13.4-5 Guidelines for the 27" Kansas Corral Rail (Std. BR183A)
Bridge Section
13 - 10
Design Manual
Figure 13.4-6 Guidelines for the 27" Kansas Corral Rail (Std. BR183D)
Bridge Section
13- 11
Design Manual
Figure 13.4-7 Guidelines for the 27" Kansas Corral Rail (Std. BR183E)
Bridge Section
13 - 12
Design Manual
Bridge Section
13- 13
Design Manual
Bridge Section
13 - 14
Design Manual
Bridge Section
13- 15
Design Manual
Bridge Section
13 - 16
Design Manual
Bridge Section
13- 17
Design Manual
Bridge Section
13 - 18
Design Manual
Figure 13.4-14 F-Shape Barrier Curb Quantities (42" & 51" Sloping Face)
Bridge Section
13- 19
Design Manual
Bridge Section
13 - 20
Design Manual
Bridge Section
13- 21
Design Manual
Bridge Section
13 - 22
Design Manual
Bridge Section
13- 23
Design Manual
13.5 Fencing
It is KDOTs practice to provide an economical, functional and durable fencing system for structures over the railroad track area or with pedestrian sidewalks. Chain link fence on bridges over
the Interstate in urban areas shall be 6-0 high.
Over railroads, provide a straight chain link fence on the barrier to a height of 10-0 on both sides
for all highway overpass structures. When a sidewalk is involved, provide a 8-0 high chain link
fence with a curved top. Examples of rail and fence are shown on Figure 13.5-2 Railroad Overpass Fencing.
For handrails to be painted, a duplex system is reccomended. Duplex is a galvanized base coating
which has powder coating as the top surface. For pedestrian and architectural fencing a duplex/
PVC system is reccomended. The woven chain link fence is galvanize, then dip coated in PVC.
The posts and all hardware are galvamized then powder coated. The designer will select either
galvanized or duplex coating. If duplex is choosen, the designer will select either black, green or
dark green as the color.
Use a leveling nut detail to attach all hardware, devices, fencing, plates or rails to concrete members using a detail similar to the detail shown in Figure 13.6-3 Bicycle Safety Railing.
For grade separation structures over major routes, use either a corral rail with closed panels over
traffic lanes or use a barrier rail to prevent snow, during snow plowing operations, from squeezing
out through the open panels and landing on passing traffic below the bridge. This is especially
important for fly-overs at multi-level interchanges.
See Figure 13.9-1 Plate Over Expansion Joint for policy on plating expansion gaps in railing and
barriers.
Fencing will be designed to resist, as a minimum, Article 13.8.2 loads and conditions.
Bridge Section
13 - 24
Design Manual
Bridge Section
13- 25
Design Manual
Bridge Section
13 - 26
Design Manual
Bridge Section
13- 27
Design Manual
Bridge Section
13 - 28
Design Manual
Figure 13.5-5 Railroad Pededtrian Protective Fence (UP & BNSF RR) (Std. BR171A)
Bridge Section
13- 29
Design Manual
13.6 Sidewalks
Generally, sidewalks are provided on bridges located in urban areas. Where a sidewalk is a
requirement, it shall have a minimum usable clear width of 5-0 to accommodate bicycles and
vehicles for the handicapped. Pedestrian Overpass structures are to comply with the Americans
with Disabilities Act Accessibility Guidelines concerning maximum grades and handrail
requirements (See 13.9 Americans with Disabilities Act Accessibility Guidelines and Figure
13.9-2 Americans With Disabilities Act Accessibility Guidelines (ADAAG)). Sidewalks on
bridges which have expansion joints will have plates covering the opening. The maximum plate
thickness will be 3/8 and will be attached to one side of the joint with the other side free to move,
see Figure 13.9-1 Plate Over Expansion Joint for example details. Bevel the edges of the plate
with a maximum slope of 3:1 and radius the edge to prevent having an exposed sharp edge. Designated bikeways, which connect to an existing trail or where there is a trail formally planned,
shall have a minimum 8-0 sidewalk width. As a rule, keep pedestrians and bicyclist separated.
Designated bicycle paths or equestrian paths are special cases and will be discussed at the Field
Check.
Handrail:
Handrail will be used on both sides of the sidewalk where the slope exceeds the ADAAG requirements given in the KDOT Rail Summary, this may be terminated where the slope does not exceed
the ADAAG requirements.
Include Handrail on both sides of sidewalks on designated school routes or when requested by
KDOT District Offices.
Loads:
Sidewalk floors, stringers and their immediate supports shall be designed for a liveload of 85
pounds per square foot of sidewalk in accordance with Article 3.6.1.6
Main supporting members and stringer shall have no less carrying capacity than would be
required if no sidewalk existed.
A wheel load is not applied to a sidewalk when the barrier curb is located between the traveled
way and the sidewalk.
Drainage:
Drainage of the sidewalks over streams or unimproved areas may be drained over the side. However, drainage should not be permitted to fall over the side for overpasses and urban areas where
dripping water or freezing snowmelt could create a nuisance. In this case, the drainage should be
carried along an edge lip to the end of the bridge or dropped on unimproved areas. If the bridge
has a deck drain system then slope the sidewalk toward the roadway and use the bridge drainage
system.
All transverse expansion joint openings in the sidewalk shall be bridged with a steel plate.
See previous Section 13.4 Railings/ Barriers for railings to be used with sidewalks.
Bridge Section
13 - 30
Design Manual
Bridge Section
13- 31
Design Manual
Bridge Section
13 - 32
Design Manual
Bridge Section
13- 33
Design Manual
Bridge Section
13 - 34
Design Manual
Bridge Section
13- 35
Design Manual
Bridge Section
13 - 36
Design Manual
Bridge Section
13- 37
Design Manual
Bridge Section
13 - 38
Design Manual
Bridge Section
13- 39
Design Manual
Bridge Section
13 - 40
Design Manual
Bridge Section
13- 41
Design Manual
Bridge Section
13 - 42
Design Manual
Bridge Section
13- 43
Design Manual
Bridge Section
13 - 44
Design Manual
Bridge Section
13- 45
Design Manual
B. If other than A or B routes, refer to Section 13 for the AASHTO LRFD Bridge
Design Specifications to determine Testing Level required. If the Test Level Selection
Criteria indicates a TL-2 level is required, use a 27 high corral rail. If a TL-4 level is
required, usea 32 high rail. (If TL-5 railing is required, use a 42 Barrier.)
C. All Structures not covered in Section I.
1. Place curbs in spans over Railroads and Traveled Ways.
2. Omit curbs at other locations unless requested otherwise by District at time of field
check.
III. Retrofit or replacement of Bridge Rails shall be made in accordance with Section I and
Section II on existing structures if other work is being done to the structure with Federal
funds (Overlay, Widen, or Major Repairs).
IV. All widened structures shall meet the requirements of Section I or Section II. If a structure is widened on one side only, both rails shall match or be replaced. A determination
should be made during field check.
V. If a rail is to be replaced, it shall be as per Section I or Section II.
VI. Retrofit of different rail types should be as follows:
A. The Safety Curb plus metal rail will need no modification if the height above the gutter
line remains 2'-3 or greater. See Appendix A Historic Rail for examples.
B. The 1'-6 Safety Curb plus offset rail shall be modified or replaced as follows:
(See Appendix A Historic Rail for an example.)
1. Replace on all structures under Section I.
2. Replace on all structures with an AADT greater than 4,000** on the structure and the
posted speed limit is greater than 35 mph. For AADT less than 4,000** but greater
than 2,000; the type of retrofit should be determined consistent with existing conditions.
3. Place double nested guard fence or thrie-beam if AADT is less than 2,000** and the
deck in the overhang is in good condition. If there is considerable overhang deck to be
replaced full depth, then the curb should be replaced.
C. The 9" concrete curb plus offset wall and metal rail shall be replaced if AADT is greater
than 4,000** and the posted speed limit is greater than 35 mph. See Appendix A Historic Rail for an example. For AADT less than 4,000**, the type of retrofit will be determined consistent with existing conditions.
Bridge Section
13 - 46
Design Manual
D. All corral rails without the hooked bar in the post shall be considered for modification or
replacement. See Appendix A Historic Rail for examples. For a hooked bar example, see
Type E in Appendix A Historic Rail.
1. Considerations
a. Bridges under Section I shall have the rail replaced.
b. Bridges with AADT greater than 4,000** and the posted speed limit is greater
than 35 mph shall have the rail replaced.
c. If the deck is to be overlaid using Federal funds and if the plan rail height after
the overlay is less than 2-2, the rail shall be replaced.
d. All other rails will be judged on a case-by-case basis.
Accident rate and geometrics should be considered.
Strength of the existing rail is a consideration.
Most corral rail with curbs built after 1965 are considered adequate unless the
accident rate or site conditions indicate replacement should be considered.
Retrofit with guard rail or thrie-beam is not recommended.
E. Missouri has successfully crashed tested a 32" New Jersey safety shape Barrier which had
been reduced to a 30" Barrier by adding a 2" overlay to the deck. Based on this test and
FHWA approved Barrier rail, KDOT would request a design waiver when overlaying a
bridge constructed with a 32" Barrier Rail.
F. All other types of rails shall be considered on a case-by-case basis.
1. Compare them to the four basic types as outlined above.
a. Bridge rails on bridges with AADT less than 2,000** and rail heights equal to or
greater than 2'-1 should in general be satisfactory.
b. Rails with brush curbs greater than a 9" width (See Appendix A Historic Rail)
shall be modified or replaced if the AADT is greater than 4,000**. Thrie-beam
may be used to modify the brush curb on all but interstate bridges.
VII. All of these rules may be overridden if the existing structure is scheduled to be modified or
replaced within 5 years.
Bridge Section
13- 47
Design Manual
KDOT Bridge Section has a listing of bridge railings which have passed the crash test criteria
based on NCHRP 230, NCHRP 350 or the performance level criteria found in the 1989 AASHTO
Guide Specifications for Bridge Railings. These railings are acceptable for use on Federal-aid
projects.
Crash Tested Railings:
The 27" and 32" Concrete Corral Rails have been crash tested for the TL-2 and TL-4 level respectivly. The 32" Concrete Barrier has also been crash tested for the TL-4 level.
The Kansas 42" Concrete Barrier is equivalent to the 32" concrete barrier with extra screening.
(TL-4)
A 42" F-shaped concrete barrier has been tested and passed Testing Level 5. See TRB paper
950924, Performance Level 3 Bridge Railings Jan. 1995. If a TL-5 F-Shaped Barrier is
required, recommend reducing the vertical reinforcing spacing from 1-0 to 8".
The 51" Concrete Barrier used in a median is equivalent to the TL-4 Concrete Barrier.
Use a 54 Barrier Rail for new structures to protect substructure elements within the clear zone.
When the distance from the back of the barrier to the element being protected is less than 10-0
per Article 3.6.5, refer to the Appendix A Structure Protection Guidelines in Section 3.11 of the
KDOT LRFD Bridge Design Manual for guidelines.
The standard rails noted above should be used whenever possible. Other crash tested rails may be
used in special cases. Unique designs of bridge rail using Chapter 13 of the AASHTO LRFD
Bridge Design Specifications must be approved by the Bridge Office before use.
**NOTE: The values shown for AADT are for only one structure on divided highways.
Bridge Section
13 - 48
Design Manual
Figure 13.11-1 Details of Thrie Beam Guard Fence Transition (Std. RD613)
Bridge Section
13- 49
Design Manual
Bridge Section
13 - 50
Design Manual
Figure 13.11-3 W-Beam with Rubrail Bridge Approach Transition (Std. RD615)
Bridge Section
13- 51
Design Manual
Figure 13.11-4 W-Beam with Rubrail Bridge Approach Transition Details (Std.
RD616)
Bridge Section
13 - 52
Design Manual
Bridge Section
13- 53
Design Manual
Bridge Section
13 - 54
Design Manual
Bridge Section
13- 55
Design Manual
Bridge Section
13 - 56
Design Manual
Bridge Section
13- 57
Design Manual
Bridge Section
13 - 58
Design Manual
Bridge Section
13- 59
Design Manual
Bridge Section
13 - 60
Design Manual
Bridge Section
13- 61
Design Manual
Bridge Section
13 - 62
Design Manual
Bridge Section
13- 63
Design Manual
Bridge Section
13 - 64
Design Manual
Bridge Section
13- 65
Design Manual
Bridge Section
13 - 66
Design Manual
Bridge Section
13- 67
Design Manual
Bridge Section
13 - 68
Design Manual
Figure 3.13-3 Guidelines for the New Jersey Barrier Curb (Std. BR180A)
Bridge Section
13- 69
Design Manual
Bridge Section
13 - 70
Design Manual
Bridge Section
13- 71
Design Manual
Bridge Section
13 - 72
Design Manual
Bridge Section
13- 73
Design Manual
List of Figures
Figure 14.2.1-1 Bridge Approach ...................................................................................................3
Figure 14.2.1-2 Approach Slab Joint Table for Steel Bridges ........................................................4
Figure 14.2.1-3 Approach Slab Joint Table for Concrete Bridges .................................................4
Figure 14.2.1-4 Membrane Sealant................................................................................................. 5
Figure 14.2.1-5 Hybrid Joint ...........................................................................................................6
Figure 14.2.2-1 Maximum Finger Plate Gap ..................................................................................7
Figure 14.2.2-2 Finger Plate Expansion Device .............................................................................8
Figure 14.2.2-3 Sliding Plate Expansion Device ............................................................................9
Figure 14.2.3-1 Modular Expansion Device .................................................................................10
Figure 14.2.4-1 Strip Seal Expansion Device (Preferred Details) ................................................11
Figure 14-9 Combination Bearing Device (Steel/Elastomer) .......................................................21
Figure 14-6 Rocker Clearance(See Appendix E Rocker Clearance Calculator) ..........................23
Figure 14-7 Example-Elastomeric Bearing Device ......................................................................25
Figure 14-8 Example- TFE Elastomeric Bearing Device .............................................................26
Figure 14-10 Typical Details of Rocker Bearing Device .............................................................27
Figure 14-11 Typical Details of Bolster Bearing Device .............................................................28
Figure 14-13 Prestressed Girders W/ Expansion Devices ............................................................29
Figure 14-13 Expansion Bearing Friction ....................................................................................30
Bridge Section
14 - 1
Design Manual
Appendixes
Appendix A Longitudinal Temperature Forces and Movements .................................................31
Appendix B Finger Joint Geometry .............................................................................................40
Appendix C Elastomeric Bearing Design Example (Method A) ..................................................43
Appendix D Steel Rocker Example ..............................................................................................45
Appendix E Rocker Clearance Calculator ....................................................................................53
Bridge Section
14 - 2
Design Manual
Bridge Section
14 - 1
Design Manual
Bridge Section
14- 2
Design Manual
Bridge Section
14 - 3
Design Manual
6.50E-06
Minimum Gap:
1.5
in
120
F
Expansion Length (ft)
Temp (F)
100
125
150
175
200
225
250
275
300
325
120
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
350
1 1/2"
110
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
100
1 5/8"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 7/8"
1 7/8"
1 7/8"
2"
2"
2"
90
1 3/4"
1 3/4"
1 7/8"
1 7/8"
2"
2"
2 1/8"
2 1/8"
2 1/4"
2 1/4"
2 3/8"
2 5/8"
80
1 3/4"
1 7/8"
2"
2"
2 1/8"
2 1/4"
2 1/4"
2 3/8"
2 3/8"
2 1/2"
70
1 7/8"
2"
2 1/8"
2 1/8"
2 1/4"
2 3/8"
2 1/2"
2 5/8"
2 5/8"
2 3/4"
2 7/8"
60
2"
2 1/8"
2 1/4"
2 3/8"
2 3/8"
2 1/2"
2 5/8"
2 3/4"
2 7/8"
3"
3 1/8"
50
2"
2 1/8"
2 3/8"
2 1/2"
2 5/8"
2 3/4"
2 7/8"
3"
3 1/8"
3 1/4"
3 3/8"
40
2 1/8"
2 1/4"
2 3/8"
2 5/8"
2 3/4"
2 7/8"
3"
3 1/4"
3 3/8"
3 1/2"
3 5/8"
30
2 1/4"
2 3/8"
2 1/2"
2 3/4"
2 7/8"
3 1/8"
3 1/4"
3 3/8"
3 5/8"
3 3/4"
4"
20
2 1/4"
2 1/2"
2 5/8"
2 7/8"
3"
3 1/4"
3 1/2"
3 5/8"
3 7/8"
4"
4 1/4"
10
2 3/8"
2 5/8"
2 3/4"
3"
3 1/4"
3 3/8"
3 5/8"
3 7/8"
4 1/8"
4 1/4"
4 1/2"
2 3/8"
2 5/8"
2 7/8"
3 1/8"
3 3/8"
3 5/8"
3 7/8"
4 1/8"
4 1/4"
4 1/2"
4 3/4"
-10
2 1/2"
2 3/4"
3"
3 1/4"
3 1/2"
3 3/4"
4"
4 1/4"
4 1/2"
4 3/4"
5"
-20
2 5/8"
2 7/8"
3 1/8"
3 3/8"
3 5/8"
4"
4 1/4"
4 1/2"
4 3/4"
5"
5 3/8"
-30
2 5/8"
3"
3 1/4"
3 1/2"
3 7/8"
4 1/8"
4 3/8"
4 3/4"
5"
5 1/4"
5 5/8"
6.00E-06
Minimum Gap:
1.5
in
90
F
Expansion Length (ft)
Temp (F)
100
125
150
175
200
225
250
275
300
325
350
375
400
120
1 1/4"
1 1/4"
1 1/8"
1 1/8"
1 1/8"
1"
1"
7/8"
7/8"
3/4"
3/4"
3/4"
110
1 3/8"
1 3/8"
1 1/4"
1 1/4"
1 1/4"
1 1/8"
1 1/8"
1 1/8"
1 1/8"
1"
1"
1"
7/8"
100
1 3/8"
1 3/8"
1 3/8"
1 3/8"
1 3/8"
1 3/8"
1 3/8"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
1 1/4"
5/8"
90
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
1 1/2"
80
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 5/8"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
1 3/4"
60
1 3/4"
1 3/4"
1 7/8"
1 7/8"
1 7/8"
2"
2"
2 1/8"
2 1/8"
2 1/4"
2 1/4"
2 1/4"
2 3/8"
50
70
1 3/4"
1 5/8"
1 7/8"
1 5/8"
1 7/8"
2"
2 1/8"
1 3/4"
2 1/8"
1 7/8"
2 1/4"
1 7/8"
2 1/4"
1 7/8"
2 3/8"
1 7/8"
2 3/8"
2"
2 1/2"
2"
2 5/8"
2"
2 5/8"
2 1/8"
40
1 7/8"
2"
2"
2 1/8"
2 1/4"
2 1/4"
2 3/8"
2 1/2"
2 5/8"
2 5/8"
2 3/4"
2 7/8"
3"
30
1 7/8"
2"
2 1/8"
2 1/4"
2 3/8"
2 1/2"
2 5/8"
2 3/4"
2 3/4"
2 7/8"
3"
3 1/8"
3 1/4"
2 1/2"
2 5/8"
10
20
2 1/8"
2 1/4"
2 3/8"
2 1/2"
2 5/8"
2 3/4"
3"
3 1/8"
3 1/4"
3 3/8"
3 1/2"
3 5/8"
3 3/4"
2 1/8"
2 1/4"
2 1/2"
2 5/8"
2 3/4"
3"
3 1/8"
3 1/4"
3 1/2"
3 5/8"
3 3/4"
3 7/8"
4 1/8"
-10
2"
2 1/4"
2 1/8"
2 3/8"
2 1/4"
2 3/8"
3"
3 1/8"
2 3/4"
3 1/4"
2 7/8"
3 1/2"
3"
3 5/8"
3 1/8"
3 7/8"
3 1/4"
4"
3 3/8"
3 1/2"
2 5/8"
2 3/4"
4 1/4"
4 3/8"
-20
2 1/4"
2 1/2"
2 3/4"
2 7/8"
3 1/8"
3 1/4"
3 1/2"
3 5/8"
3 7/8"
4 1/8"
4 1/4"
4 1/2"
4 5/8"
-30
2 3/8"
2 5/8"
2 3/4"
3"
3 1/4"
3 1/2"
3 5/8"
3 7/8"
4 1/8"
4 1/4"
4 1/2"
4 3/4"
5"
Bridge Section
14- 4
Design Manual
Bridge Section
14 - 5
Design Manual
Bridge Section
14- 6
Design Manual
Bridge Section
14 - 7
Design Manual
Bridge Section
14- 8
Design Manual
Bridge Section
14 - 9
Design Manual
Bridge Section
14- 10
Design Manual
Bridge Section
14 - 11
Design Manual
Bridge Section
14- 12
Design Manual
Bridge Section
14 - 13
Design Manual
Bridge Section
14- 14
Design Manual
14.5 Material
Steel:
Do not use weathering steel in rocker bearing, pot bearing, bolster devices, or backing plates
bonded to Teflon or welded to stainless steel. Painted ASTM A709 Gr. 36 or Gr. 50 is generally
used.
Gr. 70 is not available in non-weathering steel and Gr. 100 is difficult to get in small quantities.
If a high strength material is required (higher than Gr. 50), ASTM A514 is a suitable non-weathering material that comes in Gr. 90 and Gr. 100, and is available in small quantities. Sole plates may
be made of weathering steel when used with elastomeric expansion devices.
When specifying stainless steels for use in bearing devices, use the following designations (both
designations may be required on the plans):
ASTM A240 Type 304 for plates.
ASTM A276 Type 304 for bars and shapes.
When specifying mild steel for pins used in the construction of steel bearings, specify ASTM
A108 Gr. 1018 for pins 4 in. or less in diameter.
For pins greater than 4 in., Article 6.4.2 of the AASHTO specifies steel forgings as per ASTM
A668. Steel forgings are not guaranteed to be weldable, therefore only use the ASTM A668 specification for pins which are not to be welded.
For pins greater than 4 in. which are to be welded, specify ASTM A572 Gr. 42 (max 6 in. plates)
or Gr. 50 (max 4 in. plates). Two plates can be welded together in the shop and machined into two
half pins. Therefore, two 6 in. plates can produce two half pins with a maximum diameter of 12
in. Likewise, two 4 in. plates can produce two half pins with a maximum diameter of 8 in..
Corrosion Protection: For mechanical bearing devices use stainless steel for the half-pin, shoe and
cradle. When the limit of practicality is reached for stainless steel use mild steel. Prime the entire
device with inorganic zinc and top coat all surfaces except the contact surfaces. The bearing surfaces receive a dry film lubricant (graphite) to reduce the friction.
Bearing Seat Mats:
A lead mat, cotton duck, or neoprene pad is required between the steel masonry plate and the
concrete surface to provide uniform distribution of load.
Sliding Surfaces:
Use dimpled non-lubricated virgin unfilled teflon.
Bridge Section
14 - 15
Design Manual
Anchor Bolts:
Type I and Type II anchor bolts are now designated as AASHTO M314 Grades 36, 55 or 105
when Grade 36 is specified a weldable Grade 55 is an acceptable replacement.
Old Type I = Gr. 36
Type II = Gr. 55
= Gr. 105
Use ASTM A563 nuts and ASTM F436 washers.
All anchor bolts, nuts and washer will be galvanized. Anchor bolts are swagged according to
KDOT Standard Specification 1615.
Guides:
Use ASTM A709 painted or galvanized materials for guides.
Bridge Section
14- 16
Design Manual
Bridge Section
14 - 17
Design Manual
Bridge Section
14- 18
Design Manual
require a bearing with less bearing area and more flexibility. See Appendix .C Elastomeric Bearing Design Example (Method A) for further information.
Design Method B is intended for higher compressive stresses and more slender bearings. Bearings designed by Method B must be subjected to more rigorous testing. The plans must show
what method was used for design to indicate more stringent testing is needed on the bearings.
The Designer must verify that the method used for design appears on the Shop Drawings.
Use the following note and verify in shop detail review:
NOT2223 BEARING (TFE/ELASTOMERIC)(Method _):
Bearing devices at abutment(s) X and pier(s) X shall be fabricated with an elastomer satisfying:
- Shear Modulus of XX psi @ 73F, tested and reported per AASHTO M -251, Section 8.8.4
- Shore A Durometer Hardness of XX
- Low Temperature Grade 3 requirements
- Type A certification for elastomeric bearing device acceptance is required
*** Use either "A" or "B". Bearings designed by Method "A" are preferred. Designer must fill in
X and the __ for the particular bearing design
*** For Method A design remove bullet item for shear modulus, for Methods B design
remove bullet item for shear hardness.
The reinforcement shall consist of steel plates (fabric not allowed) and shall be designed for tension as per Article 14.7.5.3.5. The KDOT minimum thickness of the reinforcing plates shall be
1/8. Holes in plates should be avoided. KDOT Specifications cover the steel types allowed for
the reinforcement, and therefore, unless there is reason to use a different type steel, it is not necessary to call out the type on the plans.
The elastomer shall be neoprene with a durometer of 60 unless a TFE sliding surface is used, in
which case a durometer of 70 should be used for method A. Tapered elastomer layers shall not
be used. For Method B use a maximum shear modulus of G < 175 PSI.
A load plate should be vulcanized to the laminated bearing and attached to the beam to equally
spread the load on the pad. Tapered load plates may be used to reduce eccentricity on the bearing.
The load plate may be attached to the bearing seat or girder by bolts or welding. When welding
the load plate to the girder, use a minimum 1 in. thickness of load plate. This thickness is needed
so the bond between the pad and the sole plate is not compromised when the plate is welded to the
girder flange.
Adhesive bonding is not recommended for attaching the bearing to the bearing seat or girder,
because cold bonding of rubber is not reliable.
Designers should provide accommodations to inspect, repair or replace shallow elastomeric bearings, including: a provision for jacking the girders. Check all details and address constructability,
Bridge Section
14 - 19
Design Manual
14.11 Hardware
Anchor Bolts:
Configure the details of the Bearing Device to allow practical and convenient filling of the anchor
bolt well.
Detail the reinforcing bars below the bearing devices to clear the anchor bolts. Preformed anchor
bolt holes are an advantage for keeping the pier cap reinforcing steel out of the anchor bolt area.
Use corrugated polyethylene tubing to form holes so the anchor bolts will not pull out. Place a
note on the plans requiring the holes to be filled with glycol alcohol if the temperature is below
freezing.
For flexibility of construction, on steel rockers or bolsters, use field-welded lugs on the masonry
plate. Construction practices and thermal changes can create problems in the fit-up of girders. The
bearing plates may need field adjustment and welded lugs facilitate this correction
See Figure 6.3-1 Alignment of Bearing Devices for alignment of bearing devices on curved
bridges.
For expansion type devices, detail the threads on the anchor bolt so it is impossible to tighten
down on the shoe plate or sole plate and restrict rotations.
Bridge Section
14- 20
Design Manual
Bridge Section
14 - 21
Design Manual
Retainers:
Angle type retainers are preferred to long anchor bolts through the sole plate. See Figure 14-7
Example-Elastomeric Bearing Device for details. Option (B) should be used when the height of
the device exceeds 5 inches or large lateral forces exist.
Side retainers are to be designed for all appropriate limit states including the transfer of a percentage of the live and dead load if so required by KDOTs seismic detailing requirements.
Bridge Section
14- 22
Design Manual
Bridge Section
14 - 23
Design Manual
Bridge Section
14- 24
Design Manual
Bridge Section
14 - 25
Design Manual
Bridge Section
14- 26
Design Manual
Bridge Section
14 - 27
Design Manual
Bridge Section
14- 28
Design Manual
Bridge Section
14 - 29
Design Manual
Bridge Section
14- 30
Design Manual
b)
&
E=
I=
a=
T
L
h
P
=
=
=
=
M = Ph
M = Ph/2
Bridge Section
14 - 31
Design Manual
= 1.05"
= 0.60"
Deflection at Piers:
Pier
Pad + Col
Bridge Section
14- 32
a)
Design Manual
P1 ( 10x12 in/ft. ) -5
Col = ---------------------------------------------------------= 5.54x10 (P1)
6
4
3 ( 29x10 ) ( 5x71.7 in. )
T1
= Col
= 18,952 lbs./Abut.
At Pier #1 = Pier #3
Bridge Section
14 - 33
Design Manual
P2 ( 2 )
-5
Pad = ----------------------------------------------------- = 0.51x10 (P2)
18 ( 12 ) ( 300 ) ( 6 pads )
3
P2 ( 30 12 in/ft. ) -5
Col = -------------------------------------------------------------= 1.75x10 (P2)
6
3 ( 3.6 10 ) ( 3 82, 448 )
Pad + Col = 2.26x10-5 (P2)
T2
= Pad + Col
0.60" = 2.26x10-5 (P2)
P2
= 26,549 lbs/Pier
Bridge Section
14- 34
Design Manual
= 0.597
P1 + P2 + P3 = P4 + P5
@ Abut. #1:
3
3
P(H)
P1 ( 10 12 in/ft. ) Col = ------------------- = -------------------------------------------------------------3 ( E ) ( I ) 3 ( 29 10 6 ) ( 5 71.7 in 4 )
= 5.54 10
-5
(P1)
Bridge Section
14 - 35
Design Manual
= T1
@ Pier #1:
PT
P2 ( 2 )
-5
Pad = ------------------- = --------------------------------------- = 0.514 10 (P2)
LWGN 18 ( 12 ) ( 300 ) ( 6 )
3
-5
P2 ( 25 12 )
10 (P2)
- = 1.011
Col = -----------------------------------------------------------------------------------------6
3 ( 3.6 10 ) ( 3 82, 448 )
T2 = 1.525 10
-5
(P2)
@ Pier #2:
3
P3 ( 30 12 )
- = 1.747 10 -5 (P3)
Col = ----------------------------------------------6
3.6 10 ( 247, 344 )
= T3
@ Pier #3:
P4 ( 2 )
-5
Pad = --------------------------------------- = 0.514 10 (P4)
18 ( 12 ) ( 300 ) ( 6 )
3
-5
P4 ( 18 12 )
10 - (P4)
- = 0.377
Col = -------------------------------------------------------------------------------6
( 3.6 10 ) ( 247, 344 )
T4 = 0.891 10
-5
(P4)
@ Abut. #2:
3
P5 ( 10 12 )
- = 5.540 10 -5 (P5)
Col = -------------------------------------------------6
( 29 10 ) ( 5 71.7 )
= T5
Solve for P:
@ Abut. #1:
@ Pier #1:
@Pier #2:
T1
1.018 + 0.00702 ( X )
P1 = -------------------------= ------------------------------------------------5
-5
5.54 10
5.54 10
T2
+ 0.00702 ( X )
P2 = ----------------------------= 0.597
------------------------------------------------5
-5
1.525 10
1.525 10
T3
+ 0.00702 ( X )
P3 = ----------------------------= ------------------------------------5
-5
1.747 10
1.747 10
Bridge Section
14- 36
Design Manual
@Pier #3:
T4
0.00702 ( X )---------------------------------------------P4 = -----------------------------5- = 0.597-5
0.891 10
0.891 10
@Abut. #2:
T5
0.807- 0.00702 ( X )
P5 = -----------------------------5- = -----------------------------------------------5
5.540 10
5.540 10
126.7 X
460.3 X
401.8 X
787.9 X
126.7 X
1,903.4 X
X = 12.6 ft.
Therefore,
P1 =
P2 =
P3 =
P4 =
P5 =
The controlling column temperature force is located at Pier #3 (P4). If it is determined this force is
too large, the designer could select one of the following options; (a) Increase the height of the pad
to make it more flexible; (b) Specify an isolation bearing design to redistribute the forces; or (c)
Equip the elastomeric pad with a teflon sliding surface.
Moment of Inertia Adjustment for Free-Standing Skewed Piers
A skewed, free-standing column bent pier will inherently be stiffer in the longitudinal direction
then a non-skewed pier. This increase in stiffness is due to the skew producing larger moments in
Bridge Section
14 - 37
Design Manual
the columns. To compute the resultant Moment of Inertia for the Pier (Ir), the following procedure
may be used:
For two, three, four and five column piers of equal height and size of column;
Izz = (4) Iyy (see derivation below)
Iyy = Io (N)
N = Number of columns
Io = Moment of Inertia of one column
Skew
Iyy
Izz
Ir
0
10
20
30
40
50
1
1
1
1
1
1
4
4
4
4
4
4
10
19
1.35
1.75
2.24
2.76
90
4.00
Adjustment of moments of inertia should be used for skews greater than 20 degrees.
Bridge Section
14- 38
Design Manual
Derivation:
Stiffness is inversely proportional to deflection, therefore;
I zz =
k
k
and I yy =
y
z
z
z
I zz
=
or I zz = ( I yy )
y
y
I yy
z = Deflection in Z direction =
P 13
3 EI o (N)
P 13
y = Deflection in Y direction =
12 EI o (N)
I ZZ
z
P 13 / 3 EI o (N)
= ( I yy )
= I yy
y
P 13 / 12 EI o (N)
I zz = I yy (4)
Bridge Section
14 - 39
Design Manual
Bridge Section
14- 40
Design Manual
Bridge Section
14 - 41
Design Manual
Bridge Section
14- 42
Design Manual
Reactions
DL 100.0 kip
DLmax 102.12kip
LL 102.8 kip
Shore Hardness....
Shore 60
Reinforcement Yield (ksi).... Fy 36ksi
Allowable Fatigue Stress Range (ksi).. FTH 24ksi
(Table 6.6.1.2.5-3)
Rotations
( DL + LL + Uncertainties + Lack of Parallelism AASHTO 14.4.2.1)
LL rotation (radians)............. LL 0.0023
acr 35 %
s 4.3 %
s.cy LL
Translations
s s.st s.cy
0.0085 rads.
Trange 150
s Trange Lengthexp
1.1700in
fixedL 0
fixedT 1
1.17 in
L 12in
W 16in
16.000in
h ri 0.5in
h ri
0.500 in
n 4
12.000in
Cover 0.25in
tsteel 0.125in
Ht
h rt n h ri 2 Cover
Abulge ( L W) 2 h ri
S
Ht
3.13 in
h rt
2.5 in
Abulge
L W
S
Abulge
6.9
28.0 in
n
Page1
Check
11.8
< 20
(AASHTO 14.7.6.1)
Y:\Bridge Manuals\Bridge Design Manual\Development\LRFD\Chapter 3 Design\Section 3.14 Joints and Bearings\MathCadd_files\JSR v 1.2.0 10/05/10
Bridge Section
14 - 43
Design Manual
4.0 in or
5.3 in
L W
Performance Ratio
3 3
H
Stability min
allow
1.067 ksi
LL
0.535 ksi
L W
allow
0.958
allow
h hrt_min
2.34 in
2.50 in
h rt
h rt
Performance Ratio
PR 0.936
Uplift Stress
h ri n
1.114 ksi
2 s
PR
allow
2
L s
h hrt_min 2 s
Performance Ratio
TL
LL
LL
3.1 in
0.781
Stability
DLmax LL
TL
L W
Ht
Compressive Stress
Performance Ratio
0.839 ksi
Uplift
Uplift
TL
0.786
TL
1.067 ksi
ll
s DLmax
DLmax LL
s LL
DLmax LL
dl dl n h ri Cover acr 1
dl
0.065 in
allowable 0.125in
ll ll n h ri Cover
ll
0.049 in
dl ll
Performance Ratio
3.0 hri TL
h s max
0.0625in
Fy
0.909
allowable
Performance Ratio
hs
0.063 in
hs
tsteel
0.500
L W
hs
FTH
Thickness Provided
0.125 in
tsteel
Thickness Provided
Performance Ratio
hs
0.022 in
hs
tsteel
0.178
tsteel
0.125 in
Gmax L W s
h rt
Performance Ratio
Hm
17.97 kip
5 Hm
DL
0.899
20.0 kip
Y:\Bridge Manuals\Bridge Design Manual\Development\LRFD\Chapter 3 Design\Section 3.14 Joints and Bearings\MathCadd_files\JSR v 1.2.0 10/05/10
Bridge Section
14- 44
Design Manual
Unfactor Loads
A. Stage I
(Girder Self Wt. +15%)+(8.7 in Deck)+(Deck Fillet about Girder)
Combined DC Reaction = 218.2 kips
B. Stage II
(Corral Rail with out Curb)+ (15 psf future wearing surface)
Combined DC Reaction = 17.4 kips
Combined DW Reaction = 20.9 kips
C. Stage III
The controlling live load is the truck train + laneload.
LL+IM Reaction - 90% (157.4 kips +106.5 kips) = 237.6 kips
Bearing Stress on Pier Beams Concrete
(Article 5.7.5)
Bridge Section
14 - 45
Design Manual
m = 4 2.0 = 2.0
P n = 0.85f A 1 2
P r = 0.70 0.85 2 f c A 1
To determine the required bearing area, equate Pr to the factored reaction and solve for A1.
741.8kip = 0.70 0.85 2 fc A 1
2
741.82kip
A 1 = ----------------------------------------------------------------------------- = 143.26in
2
0.70 0.85 2 ( 4.351 ) k ip in
fc = 4.351ksi
Article 14.7
D2
W = Width of the bearing
D1 = Diameter of the rocker or roller surface
D2 = Diameter of the mating surface
Fy = Minimum yield strength of the weakest steel at the contact surface
Es = Youngs modulus for steel
A. Factored Reaction
P = 1.0 ( 218.2kip + 17.4kip ) + 1.0 ( 20.9kip ) + 1.0 ( 237.6kip )
P = 235.7kip + 21.0kip + 237.6kip
P = 494.2kips
Bridge Section
14- 46
Design Manual
B. Trial No.1
Calculate the required width of contact needed for an assumed diameter of rocker.
D1 = 24.0 in.
D2 = for a flat surface
Fy = 50 ksi ASTM A709M Gr.50
E = 29000 ksi
8W 24.0in
494.2kip = ------------------------------ 1 24.0in
---------------
( 50ksi ) ---------------------29000ksi
192.1in w
494.2kip = ----------------------------- ( 0.086ksi )
1
W = 494.2kip
---------------------- = 29.8in Too long, will increase D1 to 35.4in.
421.2ksi
C. Trial No.2
D1 = 35.4in.
All other same as Trial No.1
2
35.4in
50.0 ksi
494.13kip = ------------------------- -----------------------
29000ksi
35.4in
1 ---------------
W = 494.1kip
---------------------- = 20.2in OK, Use 24.0in.
963kip
Bearing on Pin Article 6.7.6.2.2 Use Type 304 Stainless Steel for Pins
Strength I Limit State
The factored bearing resistance, (Rpb )r , on pins shall be:
( R pb ) r = b ( R pb ) n
Article 6.7.6.2.2-1
in which:
( R pb )n = 1.5tDf y
t = Thickness of plate
D = Diameter of pin
b = Resistance Factor for bearing Article 6.5.4.2=1.0
Fy = 30.0 ksi ASTH A240M Type 304 Stainless steel for plate
From sheet #1 of the design calculations for bearing devices.
Factor Reaction = 741.8 kips
Calculate the required width of the bridge plates against the pin.
Assume a pin Diameter of 4.5 in.
741.8kip = 1.5t 4.5in 29.73ksi
Volume III US (LRFD)
Version 1/14
Bridge Section
14 - 47
Design Manual
741.8kip
t = --------------------------------------------------- = 3.7in
1.5 4.5in 29.7ksi
Use 3 bridge plates. Required width of each 3.7in
------------ = 1.22in
3
Use 3-1.5in wide bridge plates.
Bending of Rocker Plate
Strength I Limit State
Area I
Area I
Total temp.movement
= 6.5 10
A. Trial No. 1
W = 11.8 T = 2.4 R = 17.7
W- = 38.942ok
= 2ArcSin -----(E)
2R
M = R 1 cos
--- = 1.0 (D)
2
2
R - ------------------------W ( R M -)
Area I = ------------360
2
2
Bridge Section
14- 48
Design Manual
12 ( 2.0 ) = 8.0in 4
I = -------------------------(B)
12
W = 741.8kips
------------------------ = 30.9kip in (A)
24.0
2
WL - = 30.9kip
in 3.85in - = 229kip in
Moment = -----------------------------------------------------------2
2
2
229kip in ----Mc
2- = 28.6ksi
f s = ------- = -------------------------------------4
I
8.0in
f s = 28.6ksi ok Factored resistance = 50.0ksi
Bridge Section
14 - 49
Design Manual
4
( 2.50 )
I = 24.0
---------------------------------- = 31.25in
12
2
in 24 ( 7.9 )
Moment = L
---------- = 1.96kip
--------------------------------------------------------------------Moment = 1, 467kip in
2
2
2.5
1, 467 ---------Mc
2 - = 58.7ksi 50ksi NG
f s = -------- = ----------------------------I
31.25
B. Trial No.2
Width = 15.75, Length = 24.0, Thickness = 2.75
3
( 2.75 ) - = 41.6
I = 24.0
--------------------------------12
2.75
1, 467 ---------2 - = 48.5ksi 50ksi
f s = Mc
-------- = ----------------------------OK
I
41.6
Bridge Section
14- 50
Design Manual
Rocker Clearance
To confirm that the rocker has sufficient movement capacity must be greater than 1/2 of the
total temperature movement rotation. From page 5 that rotation was calculated as 12 . To
provide tolerance use a of 12 .
= Rsin = 0.47
Use of .50 which gives a
of
12.83
V DZ
Design Long Wind Press, P D = P B -----------------10, 000
Volume III US (LRFD)
Version 1/14
Bridge Section
14 - 51
Design Manual
60
skew
= V B = 100mph
2
( 100 )
P D = 0.019ksf ------------------ = 0.019ksf
10, 000
Exposed Area = [ Web Depth + Bolt Flange Thickness + Deck Thickness + Rail Height]
(141.3 + 3@ 157.5 + 118.1)
Exposed Area = (65.0 + 1.6 + 8.7 + 32.0)731.9
Exposed Area = 107.5 x (731.9x12) = 944,151 in2
Total Long Wind Load = 6,556 ft2 x 0.019 ksf = 124.6 kip
124.6kip
Long Wind Load/Bolster = ---------------------- = 24.9kip
5Bolster
Stability
For stability, Ry should remain within the middle 1/3 of the width (kurn), W, of the base
plate.
For Strength III Limit State will use 0.90 load factor for dead load and 1.40 load factor for
wind load.
To satisfy stability: Sum moment about o (the center of the bottom plate)
W
W
0.9P DL ----- = 1.4xWindLxH
0.9 ( 218.2kip + 17.4kip ) ----- = 1.4 23.8kip H
6
6
1.4 24.9kip H 6 = 0.986H <== required size
W = ---------------------------------------------------0.9 ( 235.6kip )
Bridge Section
14- 52
Design Manual
Bridge Section
14 - 53
Design Manual
Bridge Section
14- 54
Design Manual
List of Figures
Figure 15.5.1.1-1 LFD Rating Factors ............................................................................................9
Figure 15.10.1.1 Loadrate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 1 .....................25
Figure 15.10.1.2 Loadrate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 2 .....................26
Bridge Section
15 - 1
Design Manual
Figure 15.10.1.3 Load Rate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 3 .................27
Figure 15.13.1.1 Legal and Load Rating Trucks - (Exhibit A) .................................................32
Figure 15.13.1.2 Maximum Load Table (Exhibit B) ................................................................33
Figure 15.13.1.3 Rating Summary Example (Exhibit C) ..........................................................35
Figure 15.13.1.4 Structural Steel Designations and Strengths (Exhibit D) ...............................36
Figure 15.13.1.5 KDOT Impact for Underfill Structures (Exhibit E) .......................................37
Figure 15.14.1.1a BRIDGE POSTING PHILOSOPHY AND GUIDANCE ...............................38
Figure 15.14.1.1 Posting Level Example Sheet ............................................................................40
List of Tables
Table 15.3-1 ....................................................................................................................................3
Table 15.11.1 Example of Condition Adjusted Data ....................................................................29
Table 15.11.2 CANSYS Translation ............................................................................................30
Bridge Section
15 - 2
Design Manual
Bridge Section
1 5- 1
Design Manual
Bridge Section
15 - 2
Design Manual
20.0 tons
27.0 tons
12.5 tons
25.0 tons
Top
36.0 tons
36.0 tons
22.5 tons
36.0 tons
Middle
40.0 tons
40.0 tons
Bottom
65.0 tons
85.0 tons
N/A
109.9 tons
N/A
Beyond the standard load rating trucks, other legal truck configuration may be used for analysis
for posting purposes. Any legal truck configuration shown in Figure 15.13.1.1 Legal and Load
Rating Trucks - (Exhibit A), which causes a higher stress level on a specific structure shall be
used for posting.
The choice of the KDOT Standard Load Rating Trucks is based on several years of truck weight
data collected in Kansas and on the recommended AASHTO Maintenance Rating Trucks.
The three AASHTO Maintenance or Posting trucks (Type 3, 3S2, 3-3) are also Kansas Maximum
legal trucks for their lengths. They fit the AASHTO Bridge Gross Weight Formula (Formula
B)which is included as a part of the Kansas Statutes K.S.A 8-1909.
The H and HS-type trucks used to rate are used because of their familiarity in design and because
they are generally conservative. For posting purposes, their heavier axles must be reduced to ten
ton (maximum legal single axle weight) and the other axles reduced proportionately to create a
critical truck.
I
Bridge Section
1 5- 3
Design Manual
If we had chosen to rate using the Kansas Legal 20-ton 2-axle truck, which has two 10-ton axles
spaced at ten feet, it is possible to raise the ratings by as much as 60% or more. This is an
unconservative approach because the Legal 20-ton truck only causes higher stresses for
two-span structures with spans between 9 and 11 feet and by only a small percentage. The
example below further illustrates why this is an unconservative approach. The example is based
on a 21.5 foot simple span steel beam bridge.
H-Truck
Legal
Type 3
Inventory
2.90 Ton
4.50 Ton
4.20 Ton
Operating
6.20 Ton
9.20 Ton
9.10 Ton
If we had chosen to post using the Legal load ratings it would be possible to post at 9 Ton. By
doing so, we would also be allowing a 9-Ton H-truck which would exceed the operating rating by
almost 50%. A 9-Ton H-Truck on this bridge would cause a stress level equal to the Yield Stress.
Bridges are load rated for Inventory and Operating Ratings based on the HS vehicle as required in
the FHWA Recording and Coding Guide(13), December, 1995. For additional information concerning rating and posting on local roads and streets, see the Supplemental Coding Guide for
Bridge Inspection and Rating(15), March 1993, KDOT Bureau of Local Projects.
The Kansas Legal trucks are derived from maximum axle loads in the standard truck configurations and lengths. The maximum axle loads allowed on the Kansas highway system are 10 tons
for a single axle and 17 tons for a dual axle, with a maximum weight not to exceed 42.75 tons (40
tons on the Interstate), without special permits. The weight on a group of axles is limited by Kansas statutes K.S.A. 8-1908 and 8-1909, as shown in Exhibit B. Those limits may be found in
the bridge table found in the publication Truckin Through Kansas.(20) This guide for the motor
carrier industry is created by a joint effort of the Kansas Department of Revenue, the Kansas Corporation Commission and the Kansas Department of Transportation. www.truckingks.org
The table is used to check each possible combination of axle weights and spacings which occur on
a particular truck up to and including the whole truck. The table is based on an AASHTO Bridge
Gross Weight Formula (Formula B) which is shown below.
W=500 (L*N / (N-1) + 12*N + 36)
Where W is the weight of the axles in pounds, N is the number of axles and L is the
extreme spacing of the axles in feet under consideration.
Bridge Section
15 - 4
Design Manual
Bridge Section
1 5- 5
Design Manual
Bridge Section
15 - 6
Design Manual
1 5- 7
Bridge Section
Design Manual
Bridge Section
15 - 8
Design Manual
Bridge Section
1 5- 9
Design Manual
The posting level must be less than or equal to the Operating rating. A common level of posting is
at approximately midway between inventory and operating rating. (On a steel structure this would
be about 65% of the yield stress in the steel.) The public authority responsible for inspection and
maintenance of the structure has the authority to post anywhere within this range. It may not be
prudent or advisable to commonly post near the operating rating.
It is recommended for each city or county to develop a posting or signing policy consistent in
their signing if they have not already done so.
KDOTs posting policy is to post between the inventory and operating levels. We have no specific
level, but consider load ratings, deterioration, age, traffic, truck traffic, location, structure type and
involves the use of engineering judgment. (See Section 15.14 Bridge Posting Philosophy and
Guidance for a method to arrive at posting levels.)
At the present time on state highways, the level of posting on a bridge is determined by using the
LFD rating. To date, no LRFR ratings have been used.
If in an enforceable situation, a speed limit may be posted to reduce impact and raise or eliminate
the need for posting. This option is not normally considered feasible and has not been used by
KDOT. KDOT will continue to recommend against this option.
A bridge incapable of carrying three (3) tons at operating level must be closed. The LFD Method
of analysis should be considered when determining what level to post or close a structure.
If a structural rating is very low, the Local Authority should consider using the Load Factor
Method and post at the operating rating as the maximum posting value. This should only be done
with more frequent inspections, for short term or until repair or rehabilitation can be done.
This might allow a bridge to remain open (posted at 3 or 4 tons) rather than closed to traffic. If the
above is still not adequate to keep a bridge open, consider posting using an axle weight limit, but
this should probably be done only on simple span bridges with spans of less than 25 feet.
15.8 Signing
Weight limit signs shall be in accordance with the Manual on Uniform Traffic Control Devices(8)
(MUTCD). The single vehicle weight limit sign, R12-1, may be considered appropriate on State
Highway bridges where the load rating for the single-unit truck (H-truck or Type 3) is 10 ton or
less and also at entrances or side roads. All other bridges on the State System requiring posting
will be signed using the three-vehicle weight limit sign, R12-5.
On city and county structures, the use of the R12-5 sign is recommended, but any of the weight
limit signs in paragraph 2B-41, of the MUTCD, R12-1 through R12-5, are acceptable. As a matter
of principle, it is advisable to keep the sign variety (and the confusion) to a minimum.
The single-vehicle gross weight sign (on State highways, KDOT rounds to an even number of
tons) refers to the maximum weight of the vehicle, including its load, regardless of the type of
Bridge Section
15 - 10
Design Manual
vehicle. This sign is too restrictive for long vehicles and thus may lead to drivers ignoring it completely.
The three-vehicle gross weight sign goes into more detail by defining the total weight of the vehicle and its load for three basic truck configurations. Because of the lower individual axle weights,
increased axle spacing and the number of axles, heavier total weights for long trucks are allowed
using this sign. Thus, the R12-5 sign is recommended since it allows significantly higher gross
loads on long trucks while maintaining public safety.
The symbols shown on the R12-5 sign represents three general types of truck configurations. The
number of axles shown on the sign on each truck are not meaningful, they only serve to complete
a picture.
The upper truck symbol represents all single-unit trucks regardless of the number of axles on the
vehicles. The H-truck and the Type-3 truck as well as common dump trucks and ready-mix concrete trucks are included in the single-unit vehicles.
The middle truck symbol represents the truck-tractor semi-trailer configurations regardless of
the number of axles on the vehicle. The HS-truck, the Type-3S2 truck and a truck-tractor semitrailer with spread tandem axles is also in this category.
The lower truck symbol represents the truck-trailer (a single-unit truck pulling a full trailer) configuration regardless of the number of axles on the vehicle. This value is generally the maximum
gross load allowable and also includes all other longer combination vehicles.
For State System bridges, the posting numbers on the R12-5 sign are generally rounded to
increments of five (5) ton with the possible exception of the first number which may be rounded
to an even number if less than or equal to ten (10) ton.
These policies apply equally to long or short open spans, culverts, tunnels and other structures
which allow passage over obstructions.
Bridge Section
1 5- 11
Design Manual
Bridge Section
15 - 12
Design Manual
Modular Ratio, n
15
12
10
Bridge Section
1 5- 13
Design Manual
Lateral load distribution: Wheel load distribution width on an underfill structure is calculated as
the maximum of the above formula for at grade structures or 1.75 times the height of the fill.
Longitudinal load distribution: The Brass Culvert program which KDOT uses for RFB analysis
was created by the State of Wyoming by modifying the North Carolina Box program. It uses a
concept called Little Wheels to approximate partial uniform loads through fill when analyzing
an underfill Culvert. The method involves converting a wheel or group of wheels riding on pavement and fill to smaller wheels spread out at approximately 45 degrees and riding on the top slab
of the structure. See Below.
Bridge Section
15 - 14
Design Manual
Bridge Section
1 5- 15
Design Manual
NOTE: Several Hollow Tube Slabs have been repaired with Thick-Bonded Overlays (5"). These
renovated bridges are designed and load rated with the overlay being assumed to be composite
with the Tee-Section formed by the overlay and the concrete filled cells (See Sketch below).
Bridge Section
15 - 16
Design Manual
but they do represent a relative potential damage level (Service Load Criteria Checks). Therefore, the following allowable concrete tension stresses are used for Load Rating.
INV fc = Zero
OPER fc = 6 f c
This usually results in the concrete tension stress at the positive moment areas controlling the ratings. Long span structures may find the compression at the 1/20th point, the point of full strand
development, controlling. Still other structures may find the traditional analysis of the mild steel
over the piers controlling. Seldom will the Ultimate moment criteria control.
Prior to 1905-----------------------Fy
Inventory fs
Operating fs
= 26,000 psi
= 14,000 psi
= 19,500 psi
1905 to 1936-----------------------Fy
Inventory fs
Operating fs
= 30,000 psi
= 16,500 psi
= 22,500 psi
= 33,000 psi
= 18,000 psi
= 24,500 psi
= 36,000 psi
= 20,000 psi
= 27,000 psi
The inventory stresses shown above are approximately 55% of yield and the operating stresses are
approximately 75% of yield. See: Table 15.11.1 Example of Condition Adjusted Datafor additional information.
Bridge Section
1 5- 17
Design Manual
Structural steel girders or beams are made composite with the deck slab by the use of several
assorted connections, the most common of which is a welded stud on the top flange. The concrete
deck is normally placed without falsework which makes the composite section effective only for
the overlay, curbs, railing, and live loads. Non-composite loads include the beams, diaphragms,
stiffeners and the deck.
At present, KDOT does not load rate the composite shear connection but has assumed it to be adequate. This connection should be checked if it is questionable.
Composite moments shall be calculated by transforming the concrete slab to an equivalent area of
steel using the modular ratio n in the positive moment regions (midspan). In the negative
moment regions (piers and abutments), use a modular ratio of 3n or the slab reinforcing steel
whichever provides the greater stiffness. Composite capacities shall be calculated using the
modular ratio n in the positive regions and only the reinforcing steel in the deck for the negative
regions.
15.9.4 Timber
Wheel Line Distribution -- See Section 3.23.1 of the current AASHTO Standard Design Specifications(6).
Many structures will not have detailed plans and will have to be rated from field measurements.
Bridge Section
15 - 18
Design Manual
Due to the natural properties of timber, fatigue and impact are not normally considered in design
or load rating of timber structures. Timber does not hold up well under long term loads and is susceptible to creep if loaded for long periods of time. Once creep has taken place, timber does not
rebound significantly.
Unless better information is available, the weight of timber may be assumed to be approximately
50 pounds per cubic foot.
Vertical shear in timber beams does not normally control the load rating. Horizontal shear, bending stresses, axial loads on piling or bearing stresses at the supports probably will be the controlling stresses and each must be load rated.
The Allowable Stress Design Method is to be used to load rate timber structures. Currently, there
is no specification for load rating timber structures by the Load Factor Design Method. Further
guidance may be obtained from the Load and Resistance Factor Design Method Specifications(7)
and the 1992 U.S. Department of Agriculture manual Timber Bridges - Design, Construction,
Inspection and Maintenance(14) (Timber Bridge Manual).
See Section 13 of the current AASHTO Standard Design Specifications(6) for the allowable
inventory stresses to be used for load rating. The allowable operating stresses are 33% greater
than the inventory stresses.
For existing structures with no plans, the material type will have to be determined to establish the
appropriate allowable stresses. This may be done by reviewing the bill of lading or purchase order
if available. If not available, someone with experience with timber may be able to estimate the
grade and type of timber. If no other information is available, the following table contains some
allowable stresses KDOT has used in the past.
Bending Stress
Fb
Horizontal
Shear
Perpendicular
Compression
Design
1200 psi
120 psi
390 psi
Inventory
1170 psi
117 psi
381 psi
Operating
1600 psi
160 psi
520 psi
The Timber Bridge Manual(17), Chapter 3, has a series of treatment factors relating to preservatives and fire retarder treatments. Preservatives have a relatively small effect on the strength of the
wood but fire retardant treatments, if used, may cause a very significant reduction in allowable
stresses.
Bridge Section
1 5- 19
Design Manual
1.54 feet
120 pounds per cubic foot
24.5%
4.57 feet (Larger than 1.75*Fill)
8.5 inches
1.5 inches
0.62 sq. in. (#5 bars @ 6" spacing)
0.51 sq. in. (#4 & #5 bars @ 6" spacing)
Gr. 40 (Fy = 40 ksi)
Inv. fs = 20.0 ksi
Oper. fs = 28.0 ksi
Concrete Data:
Concrete Weight:
Concrete Strengths
Analysis Data:
Width, b:
Modular Ratio, n:
Environmental Factor, Z
Factors - , Pb, 1
12 inches
10
130
0.90, 0.0371, 0.85
Live Load Moments: In the following example, the live load moments are derived from the AISC
tables.(3) The moments (ft.-k) are calculated for one undistributed wheel line and include the maximum 30% impact. The spreadsheet adjusts these values for the amount of fill on the structure.
The Moments shown in the table below are in "foot-kips". The Gross Weight is in Tons.
Bridge Section
15 - 20
Rating
Truck
(Gross Wt.)
@1.4 pt.
@1.9F pt.*
@2.5 pt.
Design Manual
T-3
HS
T3S2
T3-3
T-130
T-170
20.0
40.34
18.65
34.45
25.0
26.99
15.80
20.28
36.0
40.34
19.80
34.58
36.0
23.71
15.62
18.49
40.0
22.38
13.01
17.29
65.0
32.58
18.58
23.86
85.0
32.38
24.10
26.10
*NOTE: The maximum moment at the support is taken at the face of the wall (1.9F). The 2.0
point (@ wall centerline) has been eliminated as a controlling point by arbitrarily increasing the
effective depth by 3 inches at this point. This is done because the supports are not knife-edge supports as assumed by the moment analysis. (Table values @ 1.9F are interpolated).
The distribution factor (0.219) shown on PAGE 1 of the spreadsheet (Figure 15.10.1.1 Loadrate
Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 1) is the inverse of 4.57, i.e. 1/E. The impact
factor shown on the spreadsheet (0.958) is a factor which reduces the 30% impact which is
already included, to approximately 24.5% (0.958 * 1.30). The T-130 and T-170 trucks have special adjustments to distribution and impact factors which are explained on the sheet with the truck
information, See Figure 15.10.1.2 Loadrate Reinforced Concrete Box (RCB) (WSD & LFD) Pg.
2.
Ms = As*Fs*j*d
(Eq. X-1)
The following example computes the inventory load rating for a Type-3 truck at the 0.4 point of
the first span (1.4 point).
As = 0.62 in.2 (#5 bars spaced at 6 inch centers.)
Volume III US (LRFD)
Version 1/14
Bridge Section
1 5- 21
Design Manual
Bridge Section
15 - 22
Design Manual
For a Type-3 truck @ the 1.4 point, find the maximum allowable live load stress for fatigue:
Initial Stresses:
LL (Max.)
LL (Min.)
DL
Ff
(+) 18.364
(-) 3.567
+6.853
22.279
Bridge Section
1 5- 23
Design Manual
R.F. =
7.40 - 2.112
= 0.934
26.993 * 0.219 * 0.958
Inventory Rating for Crack Control = 0.934 * 25 Ton = 23.34 Ton
See (Figure 15.10.1.3 Load Rate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 3) for Summary of Inventory Ratings for Fatigue.
The ratings for fatigue and crack control are not calculated at the operating level because they are
not of concern for the occasional permit load.
f c
= 0.9[(0.62)(40)(6.688)(1 - 0.6(0.00773)(40)]
3
= 140.1 inch-k/12 = 11.67 ft.-k
Rating Factor = Allow. Mom. - 1.3 (Dead Ld. Mom.)
1.3 * Actual LL Mom. * 1/E * Impact
=
11.67 - 1.3(2.112)
= 1.2122
1.3 * 26.993 * 0.219 * 0.958
Bridge Section
15 - 24
Design Manual
Figure 15.10.1.1 Loadrate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 1
Bridge Section
1 5- 25
Design Manual
Figure 15.10.1.2 Loadrate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 2
Bridge Section
15 - 26
Design Manual
Figure 15.10.1.3 Load Rate Reinforced Concrete Box (RCB) (WSD & LFD) Pg. 3
Bridge Section
1 5- 27
Design Manual
-----------------------------------
Condition adjust load rating based on the load factor TB(263-272) and TB(256,257,260,261)
if they exist, otherwise condition adjust based on the working stress rating TB(274-283) and
TB(254,255,258,259).
If the condition adjusted amount is less than the posting limit (Operating Posting Level) for a
truck type, change the adjusted amount to one more than the limit and place a 10 in the
TB(252). The limits by truck type are as follows:
*See Table 15.11.2 CANSYS Translation for TB definitions.
Bridge Section
15 - 28
Design Manual
Bridge Section
1 5- 29
Design Manual
CANSYSIFieldName
TB201
TB271
TB282
TB140
TB263
TB264
TB265
TB266
TB267
TB268
TB269
TB270
TB271
TB272
TB256
TB257
TB260
TB261
TB274
TB275
TB276
TB277
TB278
TB279
TB280
TB281
TB282
TB283
TB254
TB255
TB258
TB259
TB252
FieldDescription
MaintenancePostingsigntype
OperatingLoadfactorloadratingtype3S2truck(operating)
Operatingworkingstressloadratingtype3S2truck(operating)
Superstructureconditionrating(mostrecent)
OperatingloadfactorloadratingHtruck(inventory)
OperatingloadfactorloadratingType3truck(inventory)
OperatingloadfactorloadratingHStruck(inventory)
Operatingloadfactorloadratingtype3S2truck(inventory)
Operatingloadfactorloadratingtype33truck(inventory)
OperatingloadfactorloadratingHTruck(operating)
Operatingloadfactorloadratingtype3truck(operating)
OperatingloadfactorloadratingHStruck(operating)
Operatingloadfactorloadratingtype3S2truck(operating)
Operatingloadfactorloadratingtype33truck(operating)
T130Inventoryloadfactorloadrating
T130Operatingloadfactorloadrating
T170Inventoryloadfactorloadrating
T170Operatingloadfactorloadrating
Dateofworkingstressloadrating
OperatingworkingstressloadratingType3truck(inventory)
OperatingworkingstressloadratingHStruck(inventory)
OperatingworkingstressloadratingType3S2truck(inventory)
OperatingworkingstressloadratingType33truck(inventory)
OperatingworkingstressloadratingHTruck(operating)
OperatingworkingstressloadratingType3truck(operating)
OperatingworkingstressloadratingHStruck(operating)
Operatingworkingstressloadratingtype3S2truck(operating)
OperatingworkingstressloadratingType33truck(operating)
T130Inventoryworkingstressloadrating
T130operatingworkingstressloadrating
T170operatingworkingstressloadrating
T170operatingworkingstressloadrating
"empty"
Bridge Section
15 - 30
Design Manual
LFD Rating
Inv. Oper.
12.5
27.0
9.8 16.3
18.2 30.4
Semi Trailer
HS
T3S2
22.5
36.0
17.6 29.3
29.9 49.8
Truck-Trailer
T3-3
40.0
35.2 58.6
Truck
H
T-3
Since the rating trucks are between the Inventory and Operating ratings, this bridge may or may
not need to be posted depending on other factors such as deterioration, age, truck traffic, speed,
location, etc. If the decision is made to post the structure, the sign tonnages need to be determined.
See Section 15.14 Bridge Posting Philosophy and Guidance for an example method to arrive at
posting numbers.
If the ratings are low, a Type R12-1 sign with only one number would be appropriate (Not
Required). This sign is not recommended since it unnecessarily restricts the longer trucks.
If the decision is made to use a three-number sign, Type R12-5, a posting range for each vehicle
type is shown below.
Single Vehicle Range: 12 to 20 Ton
Semi-Trailer Range: 20 to 25 Ton
Truck-Trailer Range: 35 to 40 Ton
The three vehicle sign is recommended since it allows higher gross load on the longer trucks and
does not endanger the structure at the operating level.
An on-site inspection and judgement as to the condition of the structure and local traffic may be
required to determine where, within or below the ranges, this structure should be posted.
Bridge Section
1 5- 31
Design Manual
Bridge Section
15 - 32
Design Manual
Bridge Section
1 5- 33
Design Manual
Interior
Interior
Outer Bridge
Gross Weight
Interior Bridge
Axles 1 - 3
Interior Bridge
Axle 2 - 5
Outer Bridge
Axles 1 5
Gross Weight
Internal
Internal
Internal
Internal
Internal Bridge
Internal Bridge
Internal Bridge
Internal Bridge
Outer Bridge (Gross Weight)
- 52 -
Bridge Section
15 - 34
Design Manual
Bridge Section
1 5- 35
Design Manual
Bridge Section
15 - 36
Design Manual
Bridge Section
1 5- 37
Design Manual
Bridge Section
15 - 38
Design Manual
Bridge Section
1 5- 39
Design Manual
Bridge Section
15 - 40
Design Manual
References:
(1) Computation of Stresses in Bridge Slabs due to Wheel Loads, H. M. Westergaard, University
of Illinois, 1930.
(2) Wrought Iron and Steel Beams and Columns, 1893-1952, Herbert W. Ferris, AISC, 1953.
(3) Moments, Shears, & Reactions for Continuous Highway Bridge, AISC, 1983.
(4) The Manual for Bridge Evaluation, AASHTO, 2008. [MCEB-1]
(6) Standard Specifications for Highway Bridges, 17th Edition, AASHTO 2002. [HB-17-E2]
(7) LRFD Bridge Design Specifications, 5th Edition, 2010. [LRFD-US-5]
(8) Manual for Uniform Traffic Control Devices, 5th Edition, 2003. [MUTCD-5]
(9) Guide Specifications for Strength Evaluation of Existing Steel and Concrete Bridges (LRFD),
AASHTO, 1989. [GSEC]
(10) Guide Specifications for Fatigue Evaluation of Existing Steel Bridges, AASHTO, 1990.
[GSFEB]
(11) Guide Specifications for Fracture Critical Non-Redundant Steel Bridge Members, AASHTO,
1978. [GFC-2]
(12) Guide Specifications for Strength Design of Truss Bridges (LFD), AASHTO, 1985. [SDTB]
(13) Recording and Coding Guide for the Structure Inventory and Appraisal of the Nations
Bridges, FHWA, 1985. December, 1995
(14) Bridge Inspection Manual, Kansas Department of Transportation, Bureau of Design, Bridge
Management Section, January, 2007
(15) Bridge Inspection Manual, Bureau of Local Projects, January, 2011
(16) Code of Federal Regulations, 23 CFR Ch. 1, Part 658.5
(17) Timber Bridges-Design, Construction and Maintenance, U.S. Department of Agriculture,
August, 1992.
(18) Guide Specifications for the Design of Stress-Laminated Wood Decks, AASHTO, 1991
[SLWD]
(19) Alternative Load Factor Design Procedures for Steel Beam Bridges Using Braced Compact
Sections, AASHTO, 1991. [ALFD-2]
(20) Truckin Through Kansas, July, 2009 www.truckingKS.org
(21) Design Manual, Volume III, Bridge Section, KDOT, (Timber references: See Section V,
Falsework Design, Analysis and Inspection)
Bridge Section
1 5- 41
Design Manual
List of Tables
Table 16.1-1 FALSEWORK/FORMWORK ..................................................................................3
16 - 1
Bridge Section
Design Manual
List of Figures
Figure 16.3.2-1 Loads on Formwork and Loads on Falsework ......................................................7
Figure 16.3.2-2 Loads on Superstructure Supported Formwork ....................................................8
Figure 16.4.5-1 Formwork and Falsework Suggestions (1) .........................................................15
Figure 16.4.5-2 Formwork and Falsework Suggestions (2) .........................................................16
Figure 16-7-1-1 Deck Falsework on Girder Bridge ......................................................................19
Figure 16.8-6(a) Finishing Machine Sketch .................................................................................31
Figure 16.8.14(a) Example of TAEG 2.1 result summary ............................................................43
Figure 16.9-1 Example of Falsework Submission ........................................................................45
Bridge Section
16 - 2
Design Manual
2.
3.
4.
Three copies of detailed plans for falsework shall be submitted to the Field Engineer for review
prior to falsework construction on those structures not listed in 1 through 4 above.
See Table 16.1-1 FALSEWORK/FORMWORK for guidance concerning the types of structural
details which may require falsework/formwork plans to be submitted for Field Approval.
Seven copies of detailed plans for cofferdams and cribbing for footings on all structures adjacent
to railroad tracks, shall be submitted to the Engineer for review and approval by the railroad company and the Engineer.
Bridge Section
16 - 1
Design Manual
Work platforms or debris platforms used for concrete removal for widening or replacement of
bridges over traffic ways or railroads shall be considered falsework, and falsework plans and
methods of support shall be submitted to the Engineer for review. It is not required such plans for
platforms bear the seal of a registered Professional Engineer, however, they shall meet all requirements of falsework for structural adequacy and safety.
Falsework drawings shall be reviewed and considered satisfactory by the bridge section (or
design Consultant) before submission to other agencies. All falsework plans are to have the stamp
shown below (or similar) with the appropriate date and box marked. If corrections are noted, mark
the box titled, RECOMMENDED FOR APPROVAL (AS NOTED IN RED). Other considerations will be noted in the transmittal letter.
The Field Engineer will examine the falsework plan so the drawings show the type, size, grade,
and the finish of all lumber used. Also show the minimum size and type of falsework piling to be
used, design piling loads, assumed live loads, concentrated equipment loads, screed loads and
adequate details of the Contractor's proposed method of construction to permit checking by the
Engineer. The drawings shall also bear the seal of a licensed professional engineer. To document
that the review has been accomplished, the Field Engineer will date and initial the falsework plan.
The Engineer shall be allowed a reasonable time to review any working drawings submitted by
the Contractor for approval.
The Engineer may refuse permission to proceed with other phases of the work if he deems the
falsework unsafe or inadequate to properly support the loads to which it will be subjected.
All falsework plans must have a stamp similar to the one shown below. Locate the stamp as close
to the lower right hand corner of the sheet as possible.
DATE:
REVIEWER
Bridge Section
16 - 2
Design Manual
1) Designed by P.E.
Not required
for review
1) Culvert spans <
16 or heights <
14.
2) Formwork
3) Field approval of
as constructed
Falsework/formwork
Bridge Section
16 - 3
Design Manual
Bridge Section
16 - 4
Design Manual
16.3 LOADS
Formwork is considered to be the material or form which provides the shape to the concrete
placement and the immediate structural system which supports the form.
Falsework is the structural system supporting the formwork.
Temporary bents or supports for beam or girder erection are also considered falsework.
Timber:
Steel:
Formwork (light):
(heavy):
50 lbs/ft.3
490 lbs/ft.3
3-5 lbs/ft.2 (min.)
6-10 lbs/ft.2 (min.)
Timber and steel member densities from appropriate manuals may be used. A density of
lbs/ft.2 may be estimated for timber formwork down to the falsework.
10
Bridge Section
16 - 5
Design Manual
Bridge Section
16 - 6
Design Manual
Bridge Section
16 - 7
Design Manual
Bridge Section
16 - 8
Design Manual
16.4 ANALYSIS
In general, due to the condition of used material, the variance in quality of construction, unexpected construction loads and the consideration of safety for construction personnel and the traveling public, it will be KDOT's policy to use conservative values of allowable structural capacity.
Unless otherwise directed on the plans, used material will be permitted when it conforms to the
dimensions and material specified on the falsework plans. Used material shall be free of splits,
cracks, holes, etc. which will reduce the structural capacity. No. 2 Grade or better material is
required. The following information reflect particular species and grade; therefore, the allowable
are specific to the material. The designer will used the allowable based on the contractors specific
materials.
When the Contractor can certify his material is capable of supporting a greater stress, higher values may be used.
Bridge Section
16 - 9
Design Manual
K =
0.671 E F c
Bridge Section
16 - 10
E =
=
Design Manual
=
=
10 ton/pile
16 ton/pile
16.4.1.5 Fasteners
For lateral load and strength of fasteners consult the ACI 347 Formwork book. It is KDOT policy
to assume, for temporary structures, 100 percent of allowable design values may be used for lag
bolts, nails, spikes or thru bolts. When wind load is a design factor, connection values may be 125
percent of design values.
Bridge Section
16 - 11
Design Manual
If the compression flange is supported, this formula is sufficient to determine the section needed
to carry the applied load for a beam in bending. If the compression flange of a beam is not supported, the maximum allowable bending stress must be reduced to prevent flange buckling. The
strength of beams in lateral buckling is quite complex due to the many factors involved. However,
the following formula may be used to estimate the allowable stress:
f (maximum) = 12,000,000 18,000 psi
Ld/bt
where
L =
unsupported length (inches)
d =
beam depth
b =
flange width
t =
flange thickness
In determining the lateral support of compression flanges developed by other falsework members,
it is KDOT policy to neglect friction between the joists and top flange of a beam.
When bracing steel beams, it is important to realize timber cross-bracing alone will not prevent
flange buckling because timber struts alone resist only compression forces. The most effective
bracing system would use the wood cross-bracing in combination with steel tension ties secured
across the top and bottom of adjacent beams.
r =
radius of gyration
L =
unsupported length
(limiting L/r value is 120)
When the L/r limiting value is exceeded, additional bracing can be added to decrease L or use a
larger section to increase r.
The above formula assumes an effective length factor of 1. Determining the actual effective
length of a column with fixed or restraint ends is unnecessary. Treating columns ends in falsework
bents as being pinned is conservative for columns with end restraints.
Bridge Section
16 - 12
Design Manual
16.4.2.3 Shear
v = V/ht < 11,000 psi
where
h =
t =
depth of beam
web thickness
16.4.3 Deflection
NOTE: When checking deflections, use dead load only.
16.4.3.1 Formwork
The deflection for formwork should be limited to span/360 with a maximum of 1/16 for deck
plywood and 1/4 for walers.
16.4.3.2 Falsework
For falsework the deflection shall be limited to span/240 with a maximum of 1". Whenever the
deflection on falsework beams exceeds 1/4, adjustments should be made at the quarter points.
16.4.3.3 Uplift
Negative deflection may occur where falsework beams are continuous over a long span and a relatively short adjacent span. Beam lift-off can be prevented by loading the short span first, or by
restraining the end of the beam.
Cantilevered falsework spans will also produce an upward deflection which must be considered.
Movement may be controlled by blocking of the main span.
Bridge Section
16 - 13
Design Manual
2,000 psf
3,000 psf
6,000 psf
Soil can be classified as average if it is firm enough to walk on without indentation of the heel of
a shoe. Jacks may be required for adjustment of falsework due to settlement. Longitudinal bracing
between bents founded on sills may be required to provide stability from lateral forces.
16.4.5 Friction
Coefficient of Friction:
steel on steel
steel on wood
wood on wood
0.10
0.20
0.30
Do not rely on friction for lateral support. Vibration, uplift, partial loading, etc., can reasonably be
expected to reduce contact bearing during placement or erection.
Bridge Section
16 - 14
Design Manual
Bridge Section
16 - 15
Design Manual
Bridge Section
16 - 16
Design Manual
Bridge Section
16 - 17
Design Manual
2.
Standard Specifications for Highway Bridges, AASHTO, 17th Edition, 2002, Div.
II Construction, Section 3, Temporary Works
3.
4.
5.
6.
7.
Douglas Fir Use Book Structural Data and Design Tables, Western Wood
Products Association (formerly West Coast Lumbermen's Association), 1961
Edition
8.
9.
10.
11.
12.
13.
Charles G. Salmon and John E. Johnson, Steel Structures: Design and Behavior,
Second Edition, Harper and Row, New York, 1980.
14.
Design for Concrete Deck Overhang Loads AISC Marketing, Inc., June 15,
1990 (Final Report)
15.
Bridge Section
16 - 18
Design Manual
Bridge Section
16 - 19
Design Manual
Bridge Section
16 - 20
Design Manual
= 120 psf
= 2.2 psf
= 50.0 psf
Total load = 172.2 psf
Bridge Section
16 - 21
Design Manual
From Table 7-2 6th Edition (ACI-SP4), for a load of 175 psf, f = 1,545 psi (four or more supports)
& plywood:
Safe plywood support spacing = 20" (strong way) > 12" (ok)
(ok)
= 14" (weak way) > 12" (ok)
Note: For an explanation of strong way/weak way use of plywood, see Fig. 4-6, page 4-8
(ACI-SP4).
Check 2 x 4 deck joists
Given: Joists spaced at 1-0 centers and supported at 4-0 centers.
Total load to joists (x 1 spac.)
(from previous calculation)
Weight of 2 x 4 joists (50 pcf)
= 172.2 lbs/ft.
= 1.8 lbs/ft.
Total load = 174.0 lbs/ft.
Check bending:
2 x 4 section properties:
S = 3.06 in.3
I = 5.35 in.4
Codes (not AASHTO) limit deflection to 1/360 of span as a tolerance for appearance and having a
workable structure (see pg. 6-5 ACI Formwork). On a deck, deflection would have little adverse
effect unless it affected the finishing screed.
Bridge Section
16 - 22
Design Manual
Bearing Length= 1 + 1
L = 3 < 6
Referencing Section 16.4.1.3 Compression Perpendicular to Grain
+ 3 8- = 3-----------------+ 3 8- = 1.125
Factor = L
------------------L
3
Reaction
= 1.1 wL = 1.1 (174.0 lbs/ft.)(4.0) = 765.6 lbs.
Area
= (1.5) 2 x 2 = 4.5 in.2
Bearing stress: 765.6 lbs. / 4.5 in.2 = 170 psi < 450 psi (ok)
400(1.125) = 450 psi
Check 2 x 4 deck joists by Tables
From Dayton-Superior Formbook (pg. 8), (also see Table 7.5.2 ACI Formwork);
For f = 1,500 psi, load = 175 lbs/ft., 3 or more spans:
Maximum safe spacing of joists equals 56". To correct for values other than the tabular values
(such as f = 1,200 psi instead of 1,500 psi), use the following method:
Tabular values:
L1, f1, w1
Actual values:
L2, f2, w2
Bridge Section
16 - 23
Design Manual
f 1 = w 1 L 21 / 8S
M = wL 8 ; f = M / S;
f 2 = w 2 L 2 8S
2
2
w1 L1 f 2 / w2 f 1
L2 =
NOTE:When checking maximum formwork spacings using tables, the allowable bending, shear,
and deflection values have been satisfied and therefore need not be checked.
Check double 2 x 8 walers
Note: Overhang brackets, deck walers and hangers on girder bridges are defined as falsework
members. However, these members are subject to direct and nonredundant distribution of
loads and therefore it is KDOT's practice to design these members using the more
conservative formwork live loading.
Reaction of 2 x 4 joist on walers:
S = 13.14 in.3
S = 26.28 in.3
Bridge Section
16 - 24
Design Manual
773.4 ( 7 )
M = ------------------------------ = 4, 737 ft.-lbs.
8
3
L2 =
L f2 w1
-------------------=
w2 f1
Bridge Section
16 - 25
Design Manual
Waler Hangers
Reaction (simple beam) = wL/2
R = 574.2 lb./ft. x 7 / 2 = 2,010 lbs.
Contractor should indicate type of hanger used. Most hangers will accommodate this load.
Bridge Section
16 - 26
Design Manual
Overhang Brackets
Overhang brackets are difficult to check. The shapes are indeterminate and are usually selected
for a safe working load stipulated by the fabricator. A catalog print of the bracket is essential and
a check should be refused until one is received.
Things to watch:
1.
Is bracket being used within the dimensions shown? Extensions are available from
manufacturer. Bracket may also be blocked out with a 2 x piece in which case an end
cantilever may result.
2.
For a steel beam or girder the telescoping arm should kick into the bottom flange if
possible. There have been problems with bending webs resulting in finishing problems on
some steel bridges.
3.
Check the location of the rail for the finishing screed. It will usually be carried by the
overhang bracket.
Check load on bracket. Brackets are spaced the same as walers because of support hangers. (For
this example, bracket spacing is at 3-0 centers).
Bridge Section
16 - 27
Design Manual
Bridge Section
16 - 28
Design Manual
Finishing Machine:
Finishers generally run on at least 4 supports called bogies. A bogie has 2 wheels and travels
over a rail supported by the overhang brackets. Weights of finishers vary from 2,000 to 6,000 lbs.
The Contractor should supply finisher weight information.
For this example, assume the screed load is 5,700 lbs. Add additional weight for the power unit
end of finisher which is heavier than the idler end. Assume 75 lb. per wheel for the power unit.
Also include weight of a 200 lb. operator.
Total load per wheel = 5,700 lbs./8 wheels = 712.5 lbs./wheel
Add weight of 200 lb. operator = 200 lb./4 = 25.0 lbs./wheel
Add weight of power unit
= 75.0 lbs./wheel
Total Finisher weight per wheel
= 812.5 lbs.
(Use 815 lbs./wheel)
Compute wheel load per bracket using simple beam distribution:
= 1,080 lbs.
=
50 lbs.
=
88 lbs.
= 1,218 lbs.
= 450 lbs.
= 375 lbs.
= 825 lbs.
Bridge Section
16 - 29
Design Manual
Bridge Section
16 - 30
Design Manual
The above screed loading sketch is to be placed on a Miscellaneous Details sheet on all steel
girder bridge plans. The Bridge Designer will estimate the maximum screed loads allowable
based on the torsional capacity of the beam and the screed configuration shown above.
The following section (Check Torsional Stresses in Exterior Girder) presents a method for estimating torsional beam capacity. Another method which more accurately reflects the response of
the girder has recently been developed under the K-Tran Project (KU-96-3) entitled Torsion of
Exterior Girders of a Steel Girder Bridge During Concrete Deck Placement - A Design Aid. See
Chapter 6 Steel for additional discussion on torsion of exterior girders.
Bridge Section
16 - 31
Design Manual
24 basic unit
+ 2-12 extensions
=
=
=
=
=
4,200 lbs.
1,500 lbs.
5,700 lbs.
712.5 lbs./wheel
50.0 lbs./wheel
75.0 lbs./wheel
837.5 (Use 850 lbs./wheel)
Note: Using TAEG Software, the bridge designer shall show on the plans the maximum screed
load allowable based on the torsional capacity of the beam. (Max. 1,500 lbs./wheel)
See
Figure 16.8-6(a) Finishing Machine Sketch.
Bridge Section
16 - 32
Design Manual
Torsional loads may be computed using the method described in the AISC Marketing Report or
manually a follows:
Compute torsional moments due to screed machine:
Screed load should be moved along girder in between diaphragms to obtain the largest torsional
moments.
Bridge Section
16 - 33
Design Manual
= 827 lbs.
= 414 lbs.
Compute shear:
V = Pb2(3a + b)/L3
= 729 lbs.
= 293
= 414
= 121
1,557 lbs.
Bridge Section
16 - 34
Design Manual
L = 21
827(4.5)(16.5)2/(441)
2,297 ft.-lbs.
=
=
=
1,283
2,171
713
6,464 ft.-lbs.
Bridge Section
16 - 35
Design Manual
= 1,620 ft.-lbs.
= 258
= 675
= 1,725
=
98
= 4,376 ft.-lbs.
M = Pab2/L2
L = 21
995 lbs.(1.5)(19.5)2/(441)
-1,287 ft.-lbs.
=
=
=
=
=
=
-2,764
-3,084
-2,612
-1,713
- 754
- 99
-12,313 ft.-lbs.
FEM
Bridge Section
16 - 36
Design Manual
The maximum torsional moments due to uniform dead and live loads
at diaphragms:
(Mfw)max = -12,313 ft.-lbs.
at center of beam:
(M+)max = 6,349 ft.-lbs.
Apply a load factor of 1.3 to both dead and live loadings and screed load:
Total (Mfw)max (@ diaph.) = [-6,464 + (-12,313)] 1.3 = -24,410 ft.-lbs.
(AISC Tables = -24,146 ft.-lbs.)
Total (M+)max (@ centerline) = [+3,681 + 6,349] 1.3 = +13,039 ft.-lbs.
(AISC Tables = +13,402 ft.-lbs.)
(Note: AISC Tables and Torsion spreadsheet approximates the moment at centerline as 0.53 x
(DL + LL)FEM and 0.60 x screed load FEM.)
1)
w =
6( M fw )max
2
t f bf
6 ( - 292.9 K-in. )w = ---------------------------------------= 12.20 ksi
2
1 ( 12 )
Bridge Section
16 - 37
P
0.85( As ) F cr
Design Manual
M( C m )
1.0
M u (1 - P / As x F e )
F y KL
= F y 1
2
4 E r
F cr
K = 1,
r=
I yf / A f = [ ( ( 1 ) ( 12 ) / 12) / 12 ]
1/2
= 3.46
E
F e = ---------------2- = 54 ksi
KL
--------
r
3
J = b f t / 3 = 12 ( 1 ) / 3 = 4.0 in.4
2
S y = bd / 6 = ( 1 ) ( 12 ) / 6 = 24.0 in.4
2
Z = bd / 4 = ( 1 ) ( 12 ) / 4 = 36.0 in.4
M p = F y Z = 36 ksi ( 36.0 in. 4 ) / ( 12 ) = 108 ft.-K
M r = F y S = 36 ksi ( 24.0 in. 4 ) / ( 12 ) = 72 ft.-K
Compute Mu: (Ref. AISC LRFD Manual, 1st Ed., Appendix F)
Mu is dependent upon the cross-frame spacing (d). Need to determine what unbraced length will
allow the section to reach full plastic moment (Lp) and at what unbraced length the section is controlled by elastic lateral-torsional buckling (Lr).
Bridge Section
16 - 38
Design Manual
3,750 r JA f
L p = ------------------------------ ( if d < L p then M u = M p )
Mp
57, 000r JA f
C b E I yf GJ
L r = --------------------------------- if d > L r than M u = M p = ----------------------------------
Mr
Kd
If the cross frame spacing (d) falls in between Lp and Lr, Mu is computed from the following
straight-line approximation:
d - Lp
M p
M u = Cb M p - ( M p - M r )
Lr - L p
0.85 ( 12.0 in.2 ) ( 30.0 ksi ) 103.7 ft.-K 1 - ---------------------------------------- 12.0 in.2 54.0 ksi
0.51 + 0.17 = 0.68 < 1 (OK)
Estimate Angle of Rotation
The beam fixity at the diaphragms is somewhere between a fixed and pinned condition. Compute
the angle of rotation for both end conditions and average the results. The average angle of rotation
should be less than 1 (one) degree.
(ref. Torsional Analysis of Steel Members AISC, 1983.)
Bridge Section
16 - 39
Design Manual
= 10,914 ft.-lbs.
= 30,632 ft.-lbs.
= 41,546 ft.-lbs.
3
bt
12 ) ( 1 ) 3 + 16 ( 1.5 )3 + 51.5 ( 0.375 )3------- = (-------------------------------------------------------------------------------------= 22.9 in.4
3
3
ECw / GJ
a = 188 in.
Cw
h2 I1 I2
= --------------Iy
Bridge Section
16 - 40
Design Manual
z z2
z
L
z
= ma L 2 2 +cosh tanh sinh 10
.
GJ 2 a L
2a
tanh x = sinh x
cosh x
L = 252"
a = 188"
Substituting yields:
= 0.272852(0.035539)
= 0.00965 Radians = 0.55
z = L/2 = 126"
x
x
x
Bridge Section
16 - 41
Design Manual
= (c1I1-c2I2)/Iy
Bridge Section
16 - 42
Design Manual
12 x 1 [in.]
51 x .375 [in.]
16 x 1.625 [in.]
36 [ksi]
29000 [ksi]
5 [in.]
0.4375 [in.]
26 [in.]
36 [ksi]
29000 [ksi]
4 [in.]
YES
2.4 [in.^2]
2.4 [in.^2]
Bridge Section
16 - 43
Design Manual
Bridge Section
16 - 44
Design Manual
Bridge Section
16 - 45
Design Manual
Bridge Information:
1) 40-10 @ 48-40 Reinforced Concrete Haunched Slab
2) 44-0 Roadway
3) Slab thickness varies from 16" to 24 7/16 "
Bridge Section
16 - 46
Design Manual
Check section in interior span which has the 7 beams supported by 8 piling with the joints spaced
at 9" centers. (See Falsework sketch). Beams spaced at 7.42, piling spaced at 6.36.
Check Plywood Deck Form
Dead Load: (Assume slab depth as 1.86)
deck 1.86 x 160 lbs./ft.3
plywood
Live Load:
=
=
=
297.6 psf
2.2 psf
50.0 psf
349.8 psf
From ACI-SP4, Table 7-3, pg. 7-9, for a load of 400 psf:
Safe plywood support spacing
= 14" (strong way) > 9" (ok)
= 10" (weak way) > 9" (ok)
Check 2 x 8 Deck Joists
Given: Joists spaced at 9" centers and supported at 7.42 centers.
Total load to joists (from previous calculation) = 349.8 psf
Adjust for 9" spacing:
349.8 x
/12
= 262.4 lbs/ft.
=
3.8 lbs/ft.
266.2 lbs/ft.
Check bending:
2 x 8 section properties:
For continuous 3-span beam:
S = 13.14 in.3
Bridge Section
16 - 47
Design Manual
The allowable bearing stress may be increased by a factor related to the bearing area (See Section
16.4.1.3):
(L + 3/8)/L=
=
(3.5 + 0.375)/3.5
1.11
2,173 lbs. / 5.25 in.2 = 414 psi < 444.0 psi (ok)
Check lateral support rules (see Section 16.4.1.1). For a 2 x 8, the depth to width ratio is 4. The
ends shall be held in position and the member held in line. A 2 x 8 block between joists would be
adequate at the support and nailing the plywood along the joists would hold it in line. Bracing and
supporting makes the formwork more difficult to remove, but it should be specified.
Check bearing on horizontal 2 x 4's
Haunch is formed in various ways. Some contractors use variable form as shown above. Another
method is to step the longitudinal beams to more closely match the haunch.
Estimate load:
Concrete: 7.42 x 1.86 x 160 pcf= 2,208 lbs/ft.
Plywood: 7.42 x 2.2 lbs/ft.2 =
16 lbs/ft.
2x8s: 1.25 brds/ft. x 3.8 lbs/ft. x 7.42= 35 lbs./ft.
2,259 lbs/ft.
Bearing area (2 x 4 upright) = 1.5" x 3.5" = 5.25 in.2
Bearing stress = 2,259 lbs/ft. (1 ft.)/5.25 in.2 = 430 psi < 444 psi
(ok)
Bridge Section
16 - 48
Design Manual
Steel Beams
Steel beams may be old sections with an allowable stress of 18,000 psi. For old sections check
AISC Book on Iron and Steel Beams. Occasionally it is necessary to have field forces send in
dimensions of the beam.
Sx = 89.4 in.3
d = 18 in.
Beam: S 18 x 54.7
Ix = 804 in.4
Dead Load:
Concrete
[(1.33 + 2.04)/2](7.42)160 lbs/ft.3
= 2,000 lbs/ft.
Plywood
2.2 lbs/ft. x 7.42
= 16.3 lbs/ft.
2 x 8's
1.25 brds/ft. x 3.8 lbs/ft. x 7.42 = 35.2 lbs/ft.
Formwork for parabolic haunch
5.5 lbs/ft.
Beam
54.7 lbs/ft.
Total Dead Load
= 2,112 lbs/ft.
Uniform Live Load:
20 lbs/ft.2 x 7.42
75 lbs/lin.ft. (outside slab beam)
= 150 lbs./ft.
= 75 lbs./ft.
= 2,000 lbs.
= 200 lbs.
Bridge Section
16 - 49
Design Manual
Contractors will generally use material in his yard for steel beams. He also considers deflection
because if he furnishes a beam with too much deflection he will be giving concrete away.
Check Deflection
Simple beam concentrated load:
= 4ML2/48EI
= 5wL4/384EI = 5ML2/48EI
1/
16
12,000
7.95 ksi 12(18")/4.15 in.2
= 29.0 ft.
26.4K
Bridge Section
16 - 50
Design Manual
=
=
=
1K
2.2K
0.3K
29.9K = 15.0 tons
This should be a maximum load. Plans show to drive to 13 tons. Piling are driven using the ENR
formula which usually has an adequate factor of safety. Since the load computed for a maximum
condition and no distribution is considered, the load is probably okay. Since we (in design) have
no control over the type of pile used, it would be better to limit the load to about 12 tons. One
advantage to using timber piling is if they can drive it without splitting it, it will probably support
the load. Load should not go over 15 ton unless contractor can certify the material used.
Check Lateral Load
Design for a minimum lateral load of 2% of dead load or 100 lbs/lin. ft. KDOT recommends
a minimum of 2 x 6 bracing.
100 lbs/lin. ft. 16 span = 1.6 K/bent
2% Dead Load = Concrete + formwork
= (load/ft.2 width span) 0.02
= 2.11 K/ft. 44.5 16 ft.
7.42 ft.
= 202.5 x 0.02
= 4.05 K/bent
The 7-pile bents are in the abutment berm and are not critical.
The bracing for the 8-pile bents are probably critical for L/d.
L/d = 44.5 / 7 spaces 12"/ft. = 50.86
1.5"
Allowable stress = 0.30 E
(1/d)2
= 0.3 (1,500,000) = 174 psi
(50.86)2
Assume two braces per cross-section, therefore actual stress equals:
P/A = 4.05 K (1000) = 245.4 psi > 174 psi
2(1.5 x 5.5)
Bridge Section
16 - 51
Design Manual
Say okay since we are ignoring the lateral resistance of the piling. If this was a bent constructed
on a pad, would recommend using 3 x bracing to reduce L/d ratio and thus increase the allowable stresses.
Allowable lateral load on a 20d spike is approximately 176 lbs. (ACI-SP4, Table 4-8, for douglas
fir or southern pine). There should be a minimum of 4 spikes per pile, times eight piling equals 5.6
Kips, which should be sufficient to resist the lateral force provided all material is sound.
Bridge Section
16 - 52
Design Manual
Experienced practicing Engineers should have a grasp of the principles involved in stability.
Some factors affecting the overall stability or the partially constructed bridge elements include,
but are not limited to:
Self Weight of the partially constructed bridge elements and their respective centers of gravity.
Any existing bearing supports or members, including falsework, that are considered to help
support the partially constructed bridge elements. Care should be taken as to the actual supporting conditions at the instant the partially constructed bridge elements are considered
self-supporting.
Care should be taken in considering the unbraced length of the partially constructed bridge
elements. The number and location of diaphragms and cross bracing with consideration for
the number of bolts that are fully tightened plays a big role in this unbraced length calculation.
List all possible external loads that may reasonably be applied to the partially constructed
bridge elements. One of the common external loads to be considered will be wind. If the partially constructed bridge elements will remain in this temporary state for more that 24 hours,
there may be a need to have an extensive list of possible external loading conditions, especially if the safety of the traveling public is involved.
If the permanent bearing devices do not provide adequate support in all directions to stabilize the applied loads to the partially constructed bridge elements, list all additional supports,
their locations, and their intended resistance clearly on the erection plans. Note: friction is
not considered a positive connection and should be discounted when considering stability.
For calculations to support the above stated stability conditions, the Engineer may need to review
the following design guides and specifications. This is not considered an exhaustive list.
AASHTO LRFD Bridge Construction Specifications, Section 11.
AASHTO LRFD Bridge Design Specifications, Section 6.
AASHTO/NSBA Collaboration Document S10.1, Steel Bridge Erection Guide Specification.
Bridge Section
16 - 53
Design Manual
APPENDIX
APPENDIX 1: STATE BRIDGE OFFICE SI GUIDELINES .......................................................1
APPENDIX 2: STANDARD NOTES/SPECIAL PROVISION INDEX .......................................1
APPENDIX 3: BRIDGE PLAN PREPARATION GUIDELINES FOR RURAL SECONDARY,
URBAN AND OFF-SYSTEM .......................................................................................................1
APPENDIX 4: ENGINEERING AIDS ..........................................................................................1
APPENDIX 5: ENGINEERING MEMORANDUMS ...................................................................1
APPENDIX 6: Bid Tabs (Formats) ................................................................................................1
APPENDIX 7 ENGINEERING POLICY ......................................................................................1
APPENDIX 8 POST LETTING INFORMATION ........................................................................1
A - 1- 1
Bridge Section
Design Manual
Bridge Section
A1 - 1
Design Manual
SI BRIDGE GUIDELINES
TABLE OF CONTENTS
Conversion TableA1- .................................................................................................... A1-6
SI Units & Symbols ...................................................................................................... A1-7
Loads:............................................................................................................................ A1-8
Concrete : ...................................................................................................................... A1-9
Prestressing Strand :.................................................................................................... A1-10
Reinforcing Steel : ...................................................................................................... A1-10
Welded Wire Fabric : .................................................................................................. A1-13
Steel Bolts : ................................................................................................................. A1-15
Amendment to the Metric Policy Use of Metric Bolts & Nuts : ................................ A1-20
Structural Steel :.......................................................................................................... A1-21
Structural Shapes Designations: ................................................................................. A1-27
Foundations :............................................................................................................... A1-30
Soil: ............................................................................................................................. A1-30
Temperature: ............................................................................................................... A1-31
Roadway: .................................................................................................................... A1-32
Roadway Clearances :................................................................................................. A1-32
Decks: ......................................................................................................................... A1-33
Columns: ..................................................................................................................... A1-34
Hydraulics :................................................................................................................. A1-35
Detailing: .................................................................................................................... A1-36
Bridge Section
A1- 2
Design Manual
SI BRIDGE GUIDELINES
INDEX
AASHTO Specification
Amendment to the Metric Policy Use of Metric Bolts & Nuts : ............................... A1-20
ASTM Specifications
Reinforcing Steel : ..................................................................................................... A1-10
Steel Bolts : ............................................................................................................... A1-15
Structural Shapes Designations: ............................................................................... A1-27
Amendment to the Metric Policy Use of Metric Bolts & Nuts : .............................. A1-20
Welded Wire Fabric : ................................................................................................ A1-13
Columns:
Conversion procedure ............................................................................................... A1-34
Decks:
Clearances .................................................................................................................. A1-33
Cross-slope ................................................................................................................ A1-33
Deck Thickness ......................................................................................................... A1-33
Overlay Thickness .................................................................................................... A1-33
Triangular Molding ................................................................................................... A1-33
Detailing:
Detailing Practice ...................................................................................................... A1-36
SI Maintenance and Repair Project Guidelines .......................................................... A1-41
Foundations :
Pile Capacity ............................................................................................................. A1-30
Spread Footing Capacity ........................................................................................... A1-30
Hydraulics :
Clearances ................................................................................................................. A1-35
Drainage Area ........................................................................................................... A1-35
Flow .......................................................................................................................... A1-35
General ...................................................................................................................... A1-35
Hydraulic Assessment Checklist .............................................................................. A1-35
Velocity ..................................................................................................................... A1-35
Loads:
Alternate Military Load .............................................................................................. A1-8
Concrete ...................................................................................................................... A1-8
Design Truck ............................................................................................................... A1-8
Future Wearing Surface .............................................................................................. A1-8
General ........................................................................................................................ A1-8
Lane live load .............................................................................................................. A1-8
Pile Capacity Foundations : ....................................................................................... A1-30
Spread Footing Capacity Foundations :..................................................................... A1-30
Materials
Concrete : .................................................................................................................... A1-9
Prestressing Strand :................................................................................................... A1-10
Reinforcing Steel : .................................................................................................... A1-10
Volume III US (LRFD)
Version 1/14
Bridge Section
A1 - 3
Design Manual
Bridge Section
A1- 4
Design Manual
Bridge Section
A1 - 5
Design Manual
Conversion Table
Bridge Section
A1- 6
Design Manual
Bridge Section
A1 - 7
Design Manual
Loads:
SI
(kN/m3)
Concrete load for
falsework design
25
13.5
USCustomary
(pcf)
Vertical
Horizontal
US Customary
(psf)
SI
(kPa)
Future Wearing
Surface
Design Truck
Axle 1 (front)
Spacing 1
Axle 2
Spacing 2
Axle 3
Transverse Spa.
160
85
0.72
1.20
15
25
SI
US Customary
MS18-44
MS22.5-44
HS20-44
HS25-44
3.6 t= 35.6 kN
4.3 m
14.5 t = 142 kN
4.3-9.1 m
14.5 t = 142 kN
8 kips
14 ft
32 kips
14-30 ft
32 kips
1.8 m
6 ft
[NOTE: The HL-93 Live Load truck used in the LRFD Specifications is different than the
MS18-44]
Lane Load
Uniform load
Lane width
Concentrated
Loads
Alternate Military
Loading
Axle load
Axle spacing
11 t = 107 kN
1.2 m
24 kip
4 ft.
Wind
1.44 kPa
30 psf
(moment)
(shear)
0.64 kip/ft.
10 ft.
18 kip
26 kip
Bridge Section
A1- 8
Design Manual
Concrete :
Mixes:
Mass
*
B
A
AAA
4A
P/S
SI
US Customary
Gr 20 (20 MPa)
Gr 25
Gr 30*
Gr 35
Gr 35 - 45
(to nearest MPa)
2.5 - 3 ksi
3
4
5
5 - 6.5
2400 kg/m3
150 lbs./ft.3.
At present, use the bid item "Grade 30" (f'c = 30 MPa) only on new designs. This item is a
step towards performance specifications. The modifiers (AE, SA, SW, etc.) in parenthesis
will remain the same.
Old designs, such as RCB Standards, incidental construction and bridge repairs will
use the bid item "Grade 28" with f'c = 28 MPa on these details.
Use a performance based specification if Grade 35 concrete is required.
Bridge Section
A1 - 9
Design Manual
Prestressing Strand :
SI
US Customary
Specification:
ASTM A416M
ASTM A416
Grade:
Size:
Nom.
Dia.
Nom.
Area
Nom.
Dia.
Nom.
Area
10 mm
11
13
15
55 mm2
75
100
140
3/8"
7/16"
1/2"
0.6"
0.085 in.2
0.115
0.153
0.215
[NOTE: Use 13 mm, ASTM A416 Grade 1860 low relaxation strand]
13 mm, Gr 1860: Stress to 138 kN = 31 kip
Reinforcing Steel :
SI
US Customary
Specification:
ASTM A615M-96
ASTM A615
Grades :
Gr 40 (40 ksi)
Gr 60
Gr 75
#5 -#11= 60 max
#3-#4 = 40 max
Bridge Section
A 1 - 10
Design Manual
Bridge Section
A1 - 11
Design Manual
Bridge Section
A 1 - 12
Design Manual
SI
US Customary
Specifications:
Plain Wire
WWF Plain
Deformed Wire
WWF Deformed
ASTM A82
ASTM A185
ASTM A496
ASTM A497
SI
(MPa)
M55
M221
ASTM A82
ASTM A185
ASTM A496
ASTM A497
US Customary
(ksi)
Strengths:
Yield
400
450
60
65
70
72.5
75
80
500
550
SI
W/D
(mm2)
Sizes:
130
120
100
90
80
70
65
60
50
45
40
30
25
20
15
10
US Customary
W/D
d
2
(in * 100)
in.
d
mm
12.9
12.4
11.3
10.7
10.1
9.4
9.1
8.7
8.0
7.6
7.1
6.2
5.6
5.0
4.4
3.5
20
18
16
14
12
11
10
9
8
7
6
5
4 (4 ga)
3
2
1.4 (10 ga)
0.505
0.479
0.451
0.422
0.391
0.374
0.357
0.338
0.319
0.299
0.276
0.252
0.226
0.195
0.160
0.133
Bridge Section
A1 - 13
Design Manual
SI
Callouts:
US Customary
Examples
Plain wire
Deformed wire
150x150-MW60xMW60
75x75-MD130xMD130
6x6-W9xW9
3x3-D20xD20
Bridge Section
A 1 - 14
Design Manual
Steel Bolts :
SI
US Customary
Specifications:
ASTM A325M
ASTM A490M
ASTM A325
ASTM A490
Sizes :
0.625"
0.75"
0.875"
1"
1.125"
1.25"
1.375"
Standard
Hole
18
22
24
26
30
33
39
Oversize
Hole
20
24
28
30
35
38
44
Short
Slot
Long
Slot
18 x 22
22 x 26
24 x 30
26 x 32
30 x 37
33 x 40
39 x 46
18 x 40
22 x 50
24 x 55
26 x 60
30 x 67
33 x 75
39 x 90
Sheared
Edges
[LRFD Specs]
29
32
38
44
54
57
60
Note: Bolts and holes should use the same system on shop details. SI bolts and bolt hole sizes or
US Customary bolts and hole sizes. Do not mix.
Bolt Shear:
90 MPa = 13 ksi
131 MPa = 19 ksi
Bridge Section
A1 - 15
Design Manual
Bridge Section
A 1 - 16
Design Manual
Bridge Section
A1 - 17
Design Manual
[
I
n
s
e
r
t
S
I
v
s
.
U
S
b
o
l
t
c
o
m
p
a
r
i
s
o
n
s
N
u
c
o
r
]
Bridge Section
A 1 - 18
Design Manual
Bridge Section
A1 - 19
Design Manual
Bridge Section
A 1 - 20
Design Manual
Required
SI Metric
A325M
Bolt
Size
A490M
Optional SI Metric
Call-out
A325M
A490M
mm x mm
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
M20
A325
A490
Inches
n/a
n/a
n/a
12x1.75
16x2
20x2.5
22x2.5
24x3
27x3
30x3.5
36x4
38x4
M24
Equivalent USC
Bolt
Size
n/a
n/a
n/a
n/a
n/a
n/a
n/a
1/2
5/8
3/4
7/8
1
1-1/8
1-1/4
1-3/8
1-1/2
n/a
n/a
n/a
n/a
Structural Steel :
SI
US Customary
Specifications:
ASTM A709/A709M
AASHTO M270/M270M
ASTM A709/A709M
AASHTO M270/M270M
Grades :
Gr 36 ( 36 ksi)
Gr 50
Gr HPS 50W
Gr 70
Gr 100
Mass :
7840 kg/m3*
490 lbs/ft3
0.2833 lbs/in.3
20 J @ 4 C
27 J @ 4 C
15 ft-lbs @ 40 F
20 ft-lbs @ 40 F
Modulus of
Elasticity
29,000 ksi
Strengths :
Grade
(MPa)
Yield
(Fy)
Ultimate
(Fu)
Bridge Section
A1 - 21
Design Manual
250 MPa
345
345W
485W
690
690W
Rolled Sections :
250 MPa
345
345
485
690
690
400 MPa
450
485
620
760
760
SI sheet
thicknesses
SI plate
thicknesses
* indicates preferred
plate thicknesses
SI
(mm)
US
3.5
4.0
4.5
10 ga.
8 ga.
7 ga.
5
5.5
6
7
8
9
10 *
11
12 *
14
16 *
18
20 *
22
25 *
28
30 *
32
35 *
38
40 *
0.1875"
0.25"
0.3125"
0.375"
0.5"
0.625"
0.75"
1"
1.125"
1.25"
1.375"
1.5"
Bridge Section
A 1 - 22
Design Manual
45 *
50 *
55 *
60 *
1.75"
2.0"
22 mm
90 mm
600 mm
0.875"
3.5"
24"
Bridge Section
A1 - 23
Design Manual
Bridge Section
A 1 - 24
Design Manual
Bridge Section
A1 - 25
Design Manual
AISC is suggesting the following conversions for weld sizes. The State Bridge Office will comply.
US Customary
SI
(inch)
(mm)
1/8 ..............................................3
5/32 .......................................... 4
3/16 ......................................... . 5
1/4 .......................................... 6
5/16 ........................................ 8
3/8 ......................................... 10
1/2 ................ ......................... 12
3/4 ......................................... 20
1 .......................................... 25
Bridge Section
A 1 - 26
Design Manual
Bridge Section
A1 - 27
Design Manual
Bridge Section
A 1 - 28
Design Manual
Foundations :
SI
US Customary
62 MPa (0.25*250=62.5)
83 MPa (0.33*250=83.3)
9 ksi
12 ksi
Spread Footing :
Capacity
958 kPa
10 Ton/ft.2
Soil:
SI
Mass :
Fluid Pressure :
US Customary
1920 kg/m3
120 lbs/ft.3
30 psf
40 psf
45 psf
120 psf
Bridge Section
A1 - 29
Design Manual
Temperature:
Range:
Cold Climate
SI
US Customary
Steel
-35 to +50 C
-30 to +120 F
Concrete
0 to +80 F
+15 to +95 F
Steel
11.7 x 10-6mm/mm/ C
Concrete
10.8 x 10-6mm/mm/ C
15 C
60 F
Coefficient of
Thermal Expansion:
Bridge Section
A 1 - 30
Design Manual
Roadway:
SI
(m)
US Customary
(ft.)
3.7
12
Roadway Widths
7.4
8.6
9.8
11
12.2
13.4
24
28
32
36
40
44
SI Slope
0.000%
2.782%
Roadway Clearances :
SI
(m)
9.1
7.2
5.0
4.7
4.3
US Customary
(ft)
30'
23'-6"
16'-4"
15'-6"
14'
Bridge Section
A1 - 31
Design Manual
Decks:
SI
(mm)
US Customary
(in)
Deck Thickness
195
210
220
Use 5 mm increments for deck thickness.
7.5
8
8.5
Overlay Thickness
40
60
1.5
2.25
Cross-slope
1.60%
3/16"/ft.
Clearances
30
35
40
50
60
65
75
1
1.25
1.5
2
2.25
2.5
3
Triangular Molding
20
0.75
Milling - KDOT has milled decks a minimum of 1/4" in the past. For SI projects, minimum milling thickness is 10 mm. Use 5 mm mill thickness increments (10-35 mm by 5 mm thickness).
Bridge Section
A 1 - 32
Design Manual
Columns:
Convert column and drilled-shaft diameters to the nearest 10 mm smaller than the soft conversion
value. This allows the Contractor to use existing forms.
Examples:
Soft conversion:
Use this value
33" = 838.2 mm
830 mm
SI
(mm)
600
760
910
1 060
1 210
1 520
1 820
US Customary
(in)
24
30
36
42
48
60
72
Bridge Section
A1 - 33
Design Manual
Hydraulics :
Clearances :
SI
(m)
US Customary
(ft)
1 ( 50 year)
0.6 (100 year)
3
2
SI
US Customary
Velocity
m/s
fps
Flow
m3/s
cfs
Drainage Area
All elevations are shown in meters. Detail water surface elevations (backwater, highwater, etc.) to
the nearest hundredth of a meter. Do not add trailing zero.
Correct:
Incorrect:
Bridge Section
A 1 - 34
Design Manual
Detailing:
Detailing Practice:
a)
b)
On four digit numbers, do not include the space (i.e. this: 1440, not this: 1 400).
This applies unless there is reason to include the space such as in a table with columns. For five-digit numbers and larger, use a blank space, not a comma, to separate digits into groups of three. (12 345.7, 0.001 235)
c)
d)
e)
f)
When several dimensions measured in the same unit are combined in a single label
only use the suffix once.
Examples:
Ranges:
3 to 40 m
1500 to 3000 mm
13-15 km
Area:
40 x 70 m
RCB size:
Bridge Spans:
Existing Bridge:
New Bridge:
14.6-19.5-14.6 m RCSH
13.5-18-13.5 m RCSH
g)
When using the plus-or-minus sign (+) with a structural dimension, do not use
the "mm" suffix. Do not place a blank space between the number and the plus-orminus sign.
h)
If the dimension is embedded in text, do not put a blank between the suffix and the
plus-or-minus sign.
Bridge Section
A1 - 35
Design Manual
Examples:
Correct:
Correct:
300+
<------------------->
Place dowels every 300 mm+.
Incorrect:
300 mm+
<------------------->
Incorrect:
300 +
<------------------->
Incorrect:
i)
Use meters (m) for elevations and for roadway on the "Construction Layout" sheet.
Do not use the suffix (m) with elevations. Include the suffix (m) when a length is
measured in meters. (Measure in millimeters unless one of the rules calls for meter
measurements. The "m" suffix is required because a plan note on the title sheet
states that all dimensions without a suffix are assumed to be measured in
millimeters.)
j)
k)
l)
Use the following guides when detailing the bridge description which is placed
below the elevation view on the "Construction Layout" sheet:
Measure span lengths and roadway widths in meters to the nearest 0.1 meter.
Bridge Section
A 1 - 36
Examples:
Design Manual
Existing Bridge:
9.1-12.2-9.1 m
Reinforced Concrete Continuous Hanched Slab Spans
Pile Bent Abutments, Pedestal Type Piers
12.2 m Roadway
New Bridge:
13.5-18-13.5 m
Reinforced Concrete Continuous Haunched Slab Spans
Pile Bent Abutments, Pedestal Type Piers
12.2 m Roadway
m)
Show clearances to the nearest 0.01 m. Use the meter dimension with the "m" suf
fix when showing clearances on bridge details.
Geometric Clearances:
Vertical clearance: 5.00 m
Hydraulic Clearances:
High water clearance: 0.60 m
n)
All elevations are shown in meters. Show all structure and centerline elevations to
3 decimal places. Make sure that Bench Mark elevations on the Bridge Plans
match those on the Road Plans.
Detail water surface elevations (backwater, highwater, etc.) to the nearest hun
dredth of a meter. Do not add trailing zero.
o)
p)
Correct:
Incorrect:
123+023.456
Incorrect:
123+23.456
Bridge Section
A1 - 37
Design Manual
SSCCNN
where SS = bar size
CC = component designation
NN = bar number
Example:
Bar sequence in the bar list is by size first and then by alphanumeric of the bar
mark. Ordering bars by longest bar to shortest bar is not important. Do not rearrange the bar lists and details to provide the bar length sort.
It is preferable to place all reinforcing bar lists and bending diagrams on one or
two sheets located toward the back of the bridge plans just in front of any "standard" plan sheets. Placing all the reinforcing information in one location reduces
the possibility that the reinforcing bar fabricator will miss a sheet that includes
reinforcement details. Group bars by use (i.e., Piers (footing, column, pier beam),
Slab, Rail, etc.).
q)
Survey Descriptions: The benchmark, POT, and other surveying descriptions andinformation in the surveying notes often do not comply with standard SI dimensioning protocol (survey notes use meters as the implied unit of measure). It is
acceptable to alter the descriptions (add the "m" suffix after length measurements,
insert a blank, change upper case to lower case, etc.) to match standard detailing
procedures when copying the information to the "Construction Layout" and "Contour Map" sheets. Do not make changes which alter the meaning of the note or
description. The Road Office has already set this policy. It would be wise to coordinate the changes so that survey descriptions are the same. (Reference Jim Brewers memorandum to the Road Squad Leaders, 6/6/94).
When importing notes from Road Plans, it is not necessary to resize the text to
match the Bridge Plan notes. (#4 lettering minimum)
r)
s)
SI Maintenance and Repair Project Guidelines: Use the following guidance when
determining which measurement system to use when preparing repair details in the
Systeme International (SI) system for a structure originally constructed using the
US Customary system.
Bridge Section
A 1 - 38
Design Manual
The intent of these guidelines is to allow the Engineer to produce a set of plans
which uses the SI system whenever possible. However, there are times when the
Engineer would sacrifice clarity by using the SI system. The following rules will
clarify when it is acceptable to use the US Customary system to label an existing
structural member.
Measurements: Use the SI system to dimension all existing concrete elements. Round
converted dimensions to the nearest five millimeters. (Dimension an existing 8.5 slab as
215 mm). Use the SI system to dimension location information (2400 mm centerline to
centerline between an existing W36x210 rolled girder and the new W920x313 girder).
Bridge Descriptions: Use the SI system when dimensioning or describing an existing
structure which will be repaired or removed. Round span lengths, widths, and roadways
to the nearest 0.1 meter.
Reinforcing Steel: Label existing reinforcing steel using the US Customary designations
(#4, #8, etc.). Label SI bars using the ASTM A615M-96 designations (#13, #19, etc.) or
with a bar mark (13A4).
Rolled Structural Shapes: Use the US Customary designations for existing piling, wide
flange sections, channels, angles, pipes, tubes, etc. Include the units in the standard designations to clarify. (Examples: W36x210 plf, C12x20.7 plf, L4x4x1/4, 36 pipe).
Welded Plate Girders: Use the US Customary system to dimension plate sizes for existing
welded plate girders, diaphragms, and /or bracing. (Examples: 1x12 flange, 48 web,
42 bent plate diaphragm).
Bolts: Use the US Customary system to label existing bolt sizes and thread types. (Example: 7/8x0-3 HH bolt and HH nut, NC Thread).
Auxiliary Elements: Use the US Customary system to dimension or label existing products (Bearing pads, grates, fencing , signing hardware, et.).
Small Repair Projects: Use US Customary bolts and the US Customary designation for
replacement of rolled shapes on small repair jobs. Detailing will use SI dimensions.
Bridge Section
A1 - 39
Design Manual
Bridge Section
A 1 - 40
Design Manual
Bridge Section
A2 - 1
Design Manual
APPENDIX 3: BRIDGE PLAN PREPARATION GUIDELINES FOR RURAL SECONDARY, URBAN AND OFF-SYSTEM
The following information is furnished as a guideline so the procedural requirements and design
standards are met on construction plans for bridges for KDOT Bureau of Local Projects. While
not all-inclusive, the use of these guidelines should minimize revisions which may be required to
meet KDOT and FHWA criteria.
Bridge Plan Assembly (Use sheets as applicable) (In order of Assembly)
(a)
(b)
A separate Summary of Quantities for the bridge should be provided as the first sheet or on the
Construction Layout as appropriate.
Contour Map
Bridge Section
A3 - 1
Design Manual
1.
Plot contour map from Bridge Survey notes, road cross sections and topography notes. In
most cases, the contours should be plotted at 2 intervals. The centerline of project and/or
Survey centerline should be drawn in black ink. The scale for the contour map should be
1" = 50.
2.
On Contour Map show elevation sketch and waterway opening of all existing structures
and adjacent structures. Indicate the top of opening elevation of existing structures.
Include the field note on the map which pertains to the method of establishing the high
water and give elevation. Draw the proposed structure and channel changes with
geometrics on the contour map. Include all the data listed under (3.) which is available for
field check.
3.
4.
"The Bridge Contractor shall remove existing structure--Structure No. (___) (30 I-beam
spans and 20 wood approaches, stone abutments, concrete piers) prior to construction of
the channel change (or after new structure is completed and opened to traffic)." Add one
of the following notes as appropriate:
(a)
Bridge Section
A3 - 2
(b)
Design Manual
The Steel Beams (or appropriate material) shall be salvaged and stockpiled above
highwater for removal by County or City Forces.
Explanation - This applies when:
5.
a.
There is no channel change at the bridge site and present structure will
interfere with the construction of the new structure.
b.
A structure must be removed at or near the bridge site which has salvage
value and bridge equipment is necessary for removal.
(b)
Present structure has no salvage value and bridge equipment is not necessary for
removal.
6.
7.
"The Grading Contractor shall excavate the channel at the Bridge Site prior to
construction of the Bridge."
The contour interval, except in special cases, shall be 2 foot. For Railroad Layouts
indicate point elevations and direction of flow of railroad side ditches.
2.
Show at least two Bench Marks preferably with one on either side of the structure.
There are two main survey datum (NGVD29 and NAVD88) which can be used for
surveys. Basing a survey on a different datum results in different elevations. The State
Road Office prints the reference datum on the first plan-profile sheet. Since the Bridge
Plans frequently get detached from the Road Plans and sent to various places, show which
survey datum is being used by placing a note under the Bench Mark description.
For example:
Bridge Section
A3 - 3
Design Manual
B.M. # 16: 5/8" rebar with Alum. cap 8" below surface,
0 left of centerline Sta. 294+70, K-10. Elev. 1029.18
Sea Level Datum of NGVD 1929*. (*or NAVD 1988)
3.
4.
The following streambed elevations should be indicated: water elevation at time of survey
with date; streambed elevation near the centerline; breakpoint channel change elevations.
5.
Indicate the highwater elevation which can reasonably be predicted at the bridge site from
existing highwater along the stream, from the valley profile, from the effect of new
construction, etc. Under certain conditions, the use of highwater direct from field notes
may be used; label as (H.W. and Date), otherwise label as Design H.W.
6.
7.
Include normal water elevation or actual water elevation with date at time of survey,
preferably water elevation at date of survey. Do not label as "normal water elevation" but
as "water elevation" and give date. Show ordinary Highwater (O.H.W.) Elevation. See
Attachment 2.3.4-2. Hydraulic Data for Open Span Bridges for definitions.
8.
9.
In elevation, show grade line and give percent of grade or vertical curve. If on a vertical
curve, a small sketch should be located in the upper left-hand corner of the sheet with the
vertical curve data and the limits of the bridge shown on the vertical curve sketch.
10.
Show berm (normally 4 to 5 feet) including slope of berm and top of fill on plan and
elevation. The berm elevation shall be set as follows:
Separated Abutments
R.C. Slab Bridges
Girder Bridges
11.
The bottom of abutment beams should be set 2-6" below top of berm for Girders and
Separated Abutments and 1-6" for Slab Bridges except if piling is not used then 3 feet
minimum below berm (or into rock). See Figure 2.1.3-4 Bridge Seat Clearancesketch.
Excavation boundary plane. Label as such and give elevation. This Plane is located 1.5
feet above Ordinary Highwater. Excavation Boundary Plane is used where wet excavation
Bridge Section
A3 - 4
Design Manual
is expected and does not normally apply to grade separations, Railroad Overpass
Structures, and R.C. Box Bridges. For explanation of "Ordinary Highwater", see Plan
Sheet Hydraulic and Hydrological Data for Open Span Bridges (Attachment 2.3.4-2.
Hydraulic Data for Open Span Bridges) in the Stream Crossing Section)
12.
13.
Show profile elevations, number and station of abutments and piers in elevation.
14.
Show elevations for top of piles, top and bottom of drilled shafts, bottom of footings and
top of berms.
15.
Locate and show test pile in plan and elevation. (Dash lines) Test piles shall be used only
where required and shall be shown with a penetration about 6 more than permanent piling
and should be listed in Summary of Quantities. If test piles are not used as permanent
piles, they shall be noted as such.
Geology information should conform to the "Minimum Guidelines for Bridge Foundation
Investigations - Attachment No. 1, Bureau of Rural and Urban Development Memo 85-3."
Clearly state on the plans where contractors can view the Geology Reports, Drill Logs and
Core Samples. This is especially important on consultant plans with consultant geology.
When "Test Piles (Special)" are required, the Pile Driving Analyzer (PDA) will be used to
monitor the driving of the test pile(s). The engineer will use the FHWA WEAP Pile
Analysis Program to provide the parameters for Standard Note 1010 when the piles are not
point bearing. See Attachment "A(1)" for Standard Specification.
16.
For most cases, the slope from the shoulder down to ground line at the end of abutment
wings should be 3:1. The edge of the 10:1 slope for Guard Fence back-up should be 4-0"
from the face of the Bridge Handrail.
17.
The berm slopes in front of abutments will generally be 2:1, however with proper
justification, these may be steepened to 1:1 or flattened to meet conditions at the bridge
site. Slopes steeper than 2:1 must be protected. For stream crossings where it is deemed
necessary to protect the slopes, rock or old concrete may be used. The bid item Slope
Protection (*) allows the use (with approval) of concrete rubble entirely or in
combination with the material designated on the plans. It also requires protruding
reinforcing steel in the broken concrete to be cut off.
If rock suitable for slope protection is available on the project, it may be placed as a
blanket on the earth slopes. The rock blanket should be designated as Slope Protection
(Shot Rock) with the thickness specified on the plans. A 2-0" thickness is preferred with
the 2:1 slopes. If a steeper slope is used, the berm should be constructed of rock or other
means provided to protect the slope. Special Corps of Engineers projects may require
riprap meeting Corps of Engineers Specifications.
Bridge Section
A3 - 5
Design Manual
18.
The Berm slopes for "project over" grade separation structures shall be as specified in No.
16 for earth. Place aggregate riprap on berms of structures over railroads and for "side
road over" project structures. Riprap requirements will be determined during the field
check. The riprap slope shall be a plane with a minimum slope of 1:1 but preferably a
2:1 slope should be used. Open ditches shall be maintained through grade separation
structures if practicable. The ditch bottoms shall be riprapped when it is determined there
is drainage through the structure. This ditch lining should extend up the shoulder slope to
provide a minimum depth of 2-0". The minimum width of ditch bottom should be 1-0".
The earth side slopes for county roads shall be 3:1 and shall be carried to and intersecting
with the plane of riprap. A clearance of 20-0" from the centerline of the tracks to the
abutment slopes will be required. Off-track maintenance may extend the 20-0" criteria
an additional 8-0" when justified by need. (See Figure 2.2.3-4 Desirable Design
Clearances (Railroad) in the Grade Separation Structures Section.)
19.
20.
Designate width of berm (normally 4 to 5 feet), slope of cut and bottom width channel
change, fixed and expansion ends of spans, roadway, centerline of project and shoulder
width of earthwork fill immediately adjacent to structure.
21.
Show roadway of the bridge which shall be in accordance with the latest design standards
for the road designed and the predicted traffic count. Design Load, Unit Stresses and
Method of Design should be indicated.
22.
Label piling as to number and length in elevation. Steel piles and concrete piles are
available in any lengths and the length should be given in 1-0" increments. Prestressed
piles may be limited in length by transportation to the site.
23.
24.
Bottom of footings or top of piles in footings shall be founded 4 to 6 feet below streambed
or channel change elevation. Where erosive action of the stream is expected due to a
channel change or scour, the depths of footings should be increased. Footing depths in
good rock may be decreased. The economy and desirability of deep footings (15-0" +), in
comparison to using short piles should be investigated. However, consideration should be
given to the ability of obtaining formation penetration when short piles (15-0" or less) are
used. Predrilling may be required.
In plan, show dimension and size of footings.
25.
Bridge Section
A3 - 6
26.
Design Manual
For Grade Separation Structures, in elevation show minimum vertical clearances for each
lane and the crown grade elevation of underneath roadway at the centerline of structure
and label as crown grade elevation.
In plan, show the point of minimum vertical clearance for each lane and dimension
horizontal clearance to face of columns on both sides of each lane. Consult design criteria
for proper clearances to be used.
27.
For Railroad Overpass Structures in elevation, give minimum vertical clearance from top
of rail for each track and show location of point in plan. Indicate the horizontal clearance
to face of riprap and face of columns. Give top of rail elevations at centerline of bridge.
Draw a sketch on the layout showing the construction clearance to be provided. For
skewed crossings show a cross section perpendicular to the railroad centerline and
extending up berm slopes. Where necessary, break the section along the centerline of the
railroad. Show the control dimension from the top of rail to bottom of ditches and the top
of toe of riprap. Show track centers, if more than one track is crossed, or if a future track is
to be provided. Give the railroad stationing and the tie to project stationing. For a
Railroad Overpass, it will be necessary to compute the Quantities of the bridge between
Railroad right-of-way lines or 50-0" either side of centerline of track. The Quantities
should be submitted to the Bureau of Construction for their use in computing Protective
Liability Insurance. See the Railroad Protective Liability Insurance sketch shown on
Figure 1.2.6-1 Railroad Protective Liability Insurance in the Grade Separation
Structures section of the Manual.
28.
Show in both plan and elevation the location, size, and owner of all utility lines such as
gas, water, sewer, telephone, and power lines.
29.
Cu.Yds.
Cu.Yds.
Cu.Yds.
Lbs.
Lbs.
Lbs.
Lbs.
Each
Lin. Ft.
Sq. Ft.
Lbs.
Each
Each
1 Cu.Yds.
0.1 Cu.Yds.
0.1 Cu.Yds.
10 Lbs.
10 Lbs.
1 Lbs.
1 Lbs.
Each
0.1 Ft.
0.1 Sq. Ft.
0.1 Lbs.
Each
Each
Bridge Section
A3 - 7
Design Manual
Units
Accuracy
Cast Iron
Lbs.
0.1 Lbs.
Drilled Shaft (Size)
Ft.
0.1 Ft.
Permanent Casing (Size) (Set)
Ft.
0.1 Ft.
Pile (Steel) (Size)
Ft.
1 Ft.
Ft.
1 Ft.
Pile (Concrete) (Size)
Pile (Prestressed Concrete) (Size)
Ft.
1 Ft.
Test Piles (Type) (Size)
Ft.
1 Ft.
Test Pile (Type) (Special)
Ft.
1 Ft.
Pre-Drilled Pile Hole
Ft.
1 Ft.
Area Prepared for Patching
Sq. Yds.
1 Sq. Yds.
Area Prepared for Patching (Full Depth)
Sq. Yds.
1 Sq. Yds.
Machine Preparation (Depth)
Sq. Yds.
1 Sq. Yds.
Pile Point (Cast Steel)
Each
Each
Portland Cement Overlay (Thick.)
Sq. Yds.
1 Sq. Yds.
Material for Silica Fume Overlay (Set)
Cu. Yds.
1 Cu. Yds.
Latex Surface Course (Thick.)
Sq. Yds.
1 Sq. Yds.
Modular Expansion Device
Lin. Ft.
1 Lin. Ft.
Strip Seal Assembly
Lin. Ft.
1 Lin. Ft.
Expansion Device (Finger Joint) or (Sliding Plate) Lin. Ft.
1 Lin. Ft.
Bridge Joint (Type)
Lin. Ft.
1 Lin. Ft.
Abutment Strip Drains
Sq. Yds.
1 Sq. Yds.
Granular Backfill (Wingwalls) (Set)
Cu. Yds.
1 Cu. Yds.
Foundation Stabilization (Set)
Cu. Yds.
1 Cu. Yds.
Bridge Drainage System
Unit shown on plans
Bridge Backwall Protection System
Sq. Yds.
1 Sq. Yds.
Substructure Waterproofing Membrane
Lump Sum
Lump Sum
or
Sq. Yds.
1 Sq. Yds.
Sq. Yds.
1 Sq. Yds.
Riprap (Reinforced Concrete) (Size)
Riprap (_____ Stone)
Sq. Yds.
1 Sq. Yds.
Tons
1 Tons
Slope Protection (Type)
or
Cu. Yds.
1 Cu. Yds.
Bridge Painting
Lump Sum
Lump Sum
Environmental Protection
Lump Sum
Lump Sum
Hydrodemoliton
Sq. Yds.
1 Sq. Yds.
Removal of Existing Structure
Lump Sum
Lump Sum
Trainees (Highway Construction) (No.) (Set)
Hrs.
1 Hr.
Field Office & Lab. (Type ____)
Each
Each
Mobilization
Lump Sum
Lump Sum
Mobilization (DBE)
Lump Sum
Lump Sum
Temporary Shoring
Lump Sum
LumpSum
Drilling and Grouting
Each
Each
Sonic Test
Each
Set
Core Hole (Investigative)
Lin Ft.0.1
Lin Ft.
In addition to the information noted above, the following notes should appear as required.
Bridge Section
A3 - 8
a.
Design Manual
Near plan view dimension of shoulder width and side slope, place the following
note:
"See Road Cross-Sections for Transition to normal section."
b.
"Rock Float: After normal pile driving practice has been complied with, special
procedures which may be necessary to seat the piling for Abutments No.
__________ and for Piers No. __________ in the _____________ Formation
which is made necessary by rock float shall be considered "Extra Work".
Example: If drilling, blasting, etc. are required, the above note shall be used as
appropriate.
c.
d.
Bridge Section
A3 - 9
Design Manual
Bridge Section
A3 - 10
Design Manual
Bridge Section
A3 - 11
Design Manual
A4 - 1
Bridge Section
Design Manual
A4 - 2
Bridge Section
Design Manual
A4 - 3
Bridge Section
Design Manual
(Quantities for 1/2" diameter bar with spacers & 6" pitch)
Weight of one cage = ( W L ) + C
A4 - 4
Bridge Section
Design Manual
(Quantities for 5/8" diameter bar with spacers & 6" pitch)
Weight of one cage = ( W L ) + C
A4 - 5
Bridge Section
Design Manual
(Quantities for 1/2" diameter bar with spacers & 12" pitch)
Weight of one cage = ( W L ) + C
A4 - 6
Bridge Section
Design Manual
(Quantities for 5/8" diameter bar with spacers & 12" pitch)
Weight of one cage = ( W L ) + C
A4 - 7
Bridge Section
Design Manual
(Quantities for 3/4" diameter bar with spacers & 12" pitch)
Weight of one cage = ( W L ) + C
A4 - 8
Bridge Section
Design Manual
For different spiral parameters, such as a different pitch, use the Excel Spreadsheet located on the
Bridge Server at:
K:/Bridge/Users/+Br Applications/Design Apps/EXCEL/Spiral Calcs.xls
or compute using the following equations:
TECHNICAL DOCUMENTATION
WEIGHT OF ONE SPIRAL CAGE = (W * L) + C
Formulas used to calculate "W" and "C":
W = (R * LOT * M S) + (M B * N)
C = ((2 * T * * (D-DS)) / 12.0) * M S
Where: W = Weight per foot of cage (includes weight of N spacer bars).
C = Weight of extra complete turns at the top and bottom of the cage.
R = Turns per foot of cage = 12.0/P
P = Pitch (in.)
LOT = Length of one turn on the pitch
0.5
= ( ( * ( D - DS ) )2 + P2 ) / 12
L = Length of cage (ft.)
D = Outside diameter of cage (in.)
DS = Diameter of spiral bar (in.)
MS = Weight of spiral bars. (lb/ft.)
MB = Weight of spiral spacer bars. (lb/ft.)
N = Number of spacer bars in the cage.
T = Number of complete turns at top and bottom of cage.
Spiral Size
#3
#4
#5
#6
DS
0.375
0.500
0.625
0.750
MS
0.376 lb/ft.
.668
1.043
1.502
N=2
D < 24",
N=3
D > 24",
N=4
D < 20",
MB = 0.75 lbs/ft
A4 - 9
Bridge Section
Design Manual
The nominal dimensions of a deformed bar are equivalent to those of a plain round bar having the
same weight per foot as the deformed bar. (From CRSI 1985 Manual of Standard Practice).
Place the following not on the plans:
The weight of spiral spacer bars are included in the weight of reinforcing steel. Spiral bars shall
conform to ASTM A615 or A82.
A4 - 10
Bridge Section
Design Manual
2
2
12 + 80.1106 = 81.0044
---------------------rev
81.0044 1rev
Total Length in 1ft. = ---------------------- ----------- = 81.0044
rev
1ft
1
lb
lb
Weight = 81.0044 -------- 0.668 ----- = 4.5092 ---- 12
ft
ft
Length of Spiral =
A4 - 11
Bridge Section
Design Manual
3spacers
lb
lb
Spacers ----------------------- 0.8 ------------------- = 2.4 ----ft
spacers
ft
lb
lb
lb
Total weight for spiral and spacers = 4.5092 ----- + 2.4 ----- = 6.9092 ----ft
ft
ft
Weight for 1 1/2 complete turns top and bottom = 3 * 80.1106 = 13.378 lb.
Total weight of 13-4 Section:
W = (sprial + spacer) length + 1 1/2 turns top and bottom turns
W = 6.9092
lb
----ft
A4 - 12
Bridge Section
Design Manual
3)
4)
5)
6)
7)
8)
9)
10)
Vertical Clearance
Landscape Retaining Wall Policy Revision 1
Bridge Section
A5 - 1
Design Manual
Bridge Section
A5- 2
Design Manual
Bridge Section
A5 - 3
Design Manual
Bridge Section
A5- 4
Design Manual
Bridge Section
A5 - 5
Design Manual
Bridge Section
A5- 6
Design Manual
Bridge Section
A5 - 7
Design Manual
Bridge Section
A5- 8
Design Manual
Bridge Section
A5 - 9
Design Manual
Bridge Section
A5- 10
Design Manual
Bridge Section
A5 - 11
Design Manual
Bridge Section
A5- 12
Design Manual
Bridge Section
A5 - 13
Design Manual
Bridge Section
A5- 14
Design Manual
Bridge Section
A5 - 15
Design Manual
Bridge Section
A5- 16
Design Manual
Bridge Section
A5 - 17
Design Manual
Bridge Section
A5- 18
Design Manual
Bridge Section
A5 - 19
Design Manual
Bridge Section
A5- 20
Design Manual
Bridge Section
A5 - 21
Design Manual
Bridge Section
A5- 22
Design Manual
Bridge Section
A5 - 23
Design Manual
Bridge Section
A5- 24
Design Manual
Bridge Section
A5 - 25
Design Manual
Bridge Section
A5- 26
Design Manual
Bridge Section
A5 - 27
Design Manual
Bridge Section
A5- 28
Design Manual
Bridge Section
A5 - 29
Design Manual
Bridge Section
A5- 30
Design Manual
Bridge Section
A5 - 31
Design Manual
Bridge Section
A5- 32
Design Manual
Bridge Section
A5 - 33
Design Manual
Bridge Section
A5- 34
Design Manual
Bridge Section
A5 - 35
Design Manual
Bridge Section
A5- 36
Design Manual
Bridge Section
A5 - 37
Design Manual
Bridge Section
A5- 38
Design Manual
Bridge Section
A5 - 39
Design Manual
Bridge Section
A5- 40
Design Manual
Bridge Section
A5 - 41
Design Manual
Bridge Section
A5- 42
Design Manual
Bridge Section
A5 - 43
Design Manual
Bridge Section
A5- 44
Design Manual
Bridge Section
A5 - 45
Design Manual
Bridge Section
A5- 46
Design Manual
Bridge Section
A5 - 47
Design Manual
Bridge Section
A5- 48
Design Manual
Bridge Section
A5 - 49
Design Manual
Bridge Section
A5- 50
Design Manual
FROM:
DATE:
SUBJECT:
The Approved Proprietary Retaining Wall System list developed by our Agency
has performed well for many years. However; the premise of all our design standards
requires us to design to AASHTO minimum specifications. The conservative nature of
the AASHTO criteria has actually hindered development of the MBW (Modular Block
Wall) usage in low impact settings. An example would be to build a two foot exposed
height retaining wall (3 blocks) while embedding the system 3 feet (4 blocks) and using
reinforcement 8 feet in length. Although these design standards are widely considered
too conservative, no significant effort has been made yet to address these deficiencies in
AASHTO.
Until these discrepancies are addressed by AASHTO, we recommend a policy
(henceforth known as the Landscape Retaining Walls Policy or LRW Policy), whereby
the less restrictive National Concrete Masonry Association Design Standards for
Segmental Retaining Walls can be utilized for MBW systems on urban and secondary
routes providing the following criteria are met:
The total height of the retaining wall must be less than 6 feet.
The live load surcharge cannot exceed 100 psf.
The system cannot be defined as a critical structure whose failure would cause
loss of life, serious loss of function or access to adjacent necessary services/structures, or
result in significant property damage.
Multiple tiered walls will not be considered landscaping walls even if the
individual height of the component retaining walls is less than 6 feet.
This policy will allow the use of a granular leveling pad. (rev. 12.30.08)
Please contact us at (785)296-3008 after your review and revisions of the
proposed policy so that we can proceed with its further development.
AJG:JJB:jjb
Ken Hurst, P.E., State Bridge Operations Engineer
C:
Loren Risch, P.E., State Bridge Design Engineer
Ron Seitz, P.E., Chief, Bureau of Local Projects
Mike Popp, P.E., Operations Engineer
Corky Armstrong, P.E., Roadway Design Engineering Manager
Joshua Welge, P.E., Soils Engineer
Luke Metheny, Engineering Associate III
Blair Heptig, Foundations Specialist
Bridge Section
A5 - 51
Design Manual
CALC.
TO
PAY
TO
SECTION
Class I Excavation
Cu.Yd.
0.10
204
Class II Excavation
Cu.Yd.
0.10
204
Cu.Yd.
0.10
204
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
ITEM
Class class Excavation
Bridge Section
A6 - 1
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yd.
0.10
0.1
710
Cu.Yds
.
0.10
0.1
SP
Cu.Yd.
0.10
0.1
SP
Cu.Yd.
0.10
0.1
SP
Sq. Yds
1.0
1.0
SP
Sq. Yds
1.0
1.0
713
Sq.
Yds.
1.0 Sq.
Yds.
Lbs.
10
711
Lbs.
10
711
Lbs.
10
711
Fiber Reinforcemnet
Lbs.
SP
Lbs
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
ITEM
710
Bridge Section
A6 - 2
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Lbs.
712
Each
Each
Lbs.
Each
Each
ITEM
712
712
712
Bridge Section
A6 - 3
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
LS
714
LS
714
LS
714
LS
714
Environmental Protection **
LS
714
LS
714
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
Lin. Ft.
0.10
715
ITEM
Bridge Painting (type)
Bridge Section
A6 - 4
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
715
Sq. Ft.
0.10
715
Lbs.
716
Each
706
Lbs.
706
Each
706
Each
706
Each
706
Each
706
Each
706
Each
706
Lin. Ft.
0.10
703
Lin. Ft.
0.10
703
Each
703
Each
703
Lin. Ft.
0.10
703
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
ITEM
Bridge Section
A6 - 5
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Lin. Ft.
0.10
704
Each
704
Lin. Ft.
0.10
704
Cased Pile
Lin. Ft.
0.10
SP
Lin. Ft.
0.10
702
Lin. Ft.
0.10
702
Lin. Ft.
0.10
702
Lin. Ft.
0.10
707
Lin. Ft.
0.10
707
Lin. Ft.
0.10
719
ITEM
Bridge Section
A6 - 6
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
719
Lin. Ft.
0.10
SP
Sq.
Yds.
0.10
717
Sq.
Yds.
0.10
717
Sq.
Yds.
0.10
717
Cu.
Yd.
0.10
717
Sq.
Yds.
0.10
717
ITEM
Lin. Ft.
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Bridge Section
A6 - 7
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
ITEM
Bridge Section
A6 - 8
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Handrail (Metal-Pipe)
Lin. Ft.
0.10
721
Handrail (Metal-Galvanized)
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
721
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
Lin. Ft.
0.10
828
ITEM
Bridge Section
A6 - 9
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lin. Ft.
0.10
828
Sq.
Yd.
0.10
723
Sq.
Yds.
0.10
724
Cu.
Yds.
0.10
SP
Sq.
Yds.
0.10
726
Cu.
Yds.
204
Temporary Shoring
LS
701
Falsework Inspection
LS
708
LS
202
Mobilization
LS
801
Mobilization (DBE)
LS
801
Traffic Control
LS
805
Hrs.
Each
803
Each
803
Each
803
Each
803
Each
803
LS
802
ITEM
Fence (Chain Link) (Special) (4'-6")
Bridge Section
A6 - 10
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Each
842
Each
842
Sq. Ft.
0.10
826
Each
Sq.
Yds.
Lbs.
Lbs.
711
Lbs.
711
Sq.
Yds.
0.10
731
Sq.
Yds.
0.10.
731
Sq.
Yds.
0.10
731
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
ITEM
Shot-Crete
826
711
Bridge Section
A6 - 11
Design Manual
ITEM
UNIT
CALC.
TO
PAY
TO
SECTION
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Sq.
Yds.
0.10
732
Hydrodemoliton
Sq.
Yds.
0.10
733
Lin. Ft.
0.1
734
Lin. Ft.
0.1
734
Lin. Ft.
0.1
734
Lin. Ft.
0.1
734
Foundation Stabilization
Cu. Yd.
204
Granular Backfill
Cu. Yd.
204
Cu. Yd.
204
Cu. Yd.
204
Cu. Yd.
204
Lin. Ft.
0.10
809
Lin. Ft.
0.10
809
Lin. Ft.
0.10
809
Bridge Section
A6 - 12
Design Manual
ITEM
UNIT
CALC.
TO
PAY
TO
SECTION
Sq.
Yds.
0.10
829
Sq.
Yds.
0.10
829
Sq.
Yds.
0.10
829
Sq.
Yds.
0.10
829
Sq.
Yds.
0.10
829
Sq.
Yds.
0.10
829
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Cu. Yd.
830
Geotextile Fabric
Sq. Yd.
0.10
830
Gabions
Cu.Yd.
0.10
832
Bridge Section
A6 - 13
Design Manual
UNIT
CALC.
TO
PAY
TO
SECTION
Lbs.
1610
LS
1610
Each
1610
Lin. Ft.
1610
Cu. Yd.
0.10
843
Cu. Yd.
0.10
843
Curb Repair
Lin. Ft.
0.10.
728
Each
SP
Each
810
Each
810
Each
810
Each
810
Each
810
Curing Environment
Lump
Sum
ITEM
Bridge Section
A6 - 14
Design Manual
Noise Abatement
Effective
August 28, 1996
PREFACE
Traffic noise impacts vary with highway location relative to human activities and traffic
characteristics. The Kansas Department of Transportation (KDOT) evaluates traffic noise in
accordance with federal regulations and, as impacts become more severe, noise mitigation
measures are investigated. In order to address these issues in a consistent and objective manner,
the following policy and procedure statements are provided.
Authority
The Federal Highway Administration's Procedures for Abatement of Highway Traffic
Noise and Construction Noise is found in 23 CFR 772. The KDOT noise policy is based
upon this FHWA regulation, and is deemed to be consistent with it.
1)
Bridge Section
A7 - 1
Design Manual
in cost, but through a joint effort of those involved, an appropriate balance of cost and
responsibility can be achieved. Policy and procedure stated in this document reflects this
systems approach to traffic noise reduction.
2)
Noise Prediction
All predictions of noise levels on KDOT highway projects will be made using a noise
prediction model approved by the FHWA. In predicting noise levels and assessing noise
impacts, the posted speed limit at the time of the existing traffic noise study will be used.
3)
Noise Levels
a.
Descriptor
Noise studies for KDOT projects will use Leq, the equivalent sound level.
b.
Existing Levels
Leq values existing in a project corridor before construction will normally be
determined through field measurements. However, in certain cases, these values
can be obtained through execution of the Model.
c.
Noise Abatement
Criteria LeqdV)
Approach
defined as
57 dBA
56 dBA
67 dBA
66 dBA
C
72 dBA
71 dBA
In addition, impacts are deemed to occur when future predicted no barrier levels
Bridge Section
A7 - 2
Design Manual
substantially exceed existing levels. KDOT has an agreement with FHWA that
defines impacts. These definitions are:
0-5 dBA increase
6-10 dBA increase
11-15 dBA increase
> 15 dBA increase
- No impact
- Minor impact
- Moderate impact
- Severe impact
Barriers
a.
Barrier Projects
KDOT will only construct noise barriers as part of highway construction or reconstruction projects. KDOT will not participate in the Type II program of
retrofitting existing highways with noise barriers until Federal standards are
established exclusively for Type II and other enhancement projects (See 23 CFR
772.5(i) and 772.7 (b)).
b.
Insertion Loss
Insertion loss is the difference in Leq with and without the barrier (barrier minus
no barrier level). The insertion loss goal for each impacted sensitive receptor is
5 dBA or more.
c.
Location
In at-grade or fill situations, barriers should be built as close to the highway as
possible. If necessary, barriers can be located on top of jersey-type barriers, and
placed at the edge of shoulder, ( approximately 10-12 feet from traffic). If jerseytype barriers or methods of crash protection are not used, noise barriers should be
outside the 30 foot clear zone.
When barriers are constructed at or near the shoulder line, consideration must be
given to safety, drainage, and ice and snow removal.
In cut situations, barriers should be placed as close to the right-of-way line as
possible. This will maximize noise reduction effects of the barrier. In all cases
barriers should be constructed on KDOT right-of-way.
Bridge Section
A7 - 3
Design Manual
d.
Height
For aesthetic and cost reasons, barriers should be tall enough to provide adequate
noise reduction, and no taller. For KDOT projects, the maximum height of any
barrier above the ground line will be 16 feet. Barriers taller than 16 feet would
probably result in negative visual impacts on the surrounding properties.
Also for aesthetic reasons, barrier height should be limited as follows: The
distance from the barrier to any inhabited buildings should be at least four times
the barrier height. For example, if the distance from the barrier to a row of
protected houses is 44 feet, the maximum height of the barrier should be 11 feet.
e.
Length
Barriers shall be designed with the shortest length possible. Typically, barriers
will need to extend beyond the last receiver by a distance four times the distance
from the receiver to the barrier.
f.
End Treatment
Abrupt endings of barriers should be avoided. Barrier heights should be tapered
to the ground and vegetation may be used to soften the end appearance.
g.
Access
Working space behind the barrier with provisions for access should be provided,
or maintenance agreements with other public bodies or private individuals should
be made.
h.
Materials
The principal issues involved in material selection are aesthetics, community
desires, constructability, and maintenance. Normally, concrete and masonry based
materials are the most suitable in addressing these issues. Wood barriers are a less
expensive alternative, but must be carefully designed and monitored in terms of
treatment and water content in order to minimize maintenance problems. Metal
barriers are easily damaged, and are often not received positively regarding
aesthetics. Vegetative screens do not produce meaningful noise reduction, due to
a lack of material density.
Bridge Section
A7 - 4
Design Manual
i.
Cost
Because a small number of people benefit from a relative large expenditure of
funds, barriers, if constructed, must be determined to be reasonable, feasible, and
cost effective. For KDOT projects cost effectiveness is defined as barrier cost per
receiver at or below the national average guideline for barrier cost effectiveness.
This guideline was determined to be $25,000 in 1995 dollars, based upon studies
performed for KDOT.
When determining cost effectiveness of a potential barrier, each sensitive receptor
receiving 5 or more dBA insertion loss is counted as one receiver, and each
receiving 3-4 dBA insertion loss is counted as one half receiver.
The cost data in Table 1 should be used when computing the barrier cost per
receiver. These data have been incorporated into the NOISE software library. It
is the intent of KDOT to update the values in Table 1, as well as the $25,000
barrier cost per receiver national criterion, as needed.
It should be noted that the data in Table I are to be used in conjunction with the
guideline for cost effectiveness. THEY ARE FOR COMPARISON PURPOSES
ONLY. Actual barrier costs will vary.
It should also be noted that the comparison of proposed barrier costs using the
guideline is to assist KDOT in making decisions about barrier feasibility. Any final
decision on barrier construction will be based on a variety of factors.
Barrier Height
Range in feet
01-05
05-10
10-15
15-20
20-25
Concrete
Wood
Metal
48.66
79.11
1-17.18
155.28
193.34
105.79
193.33
302.74
412.13
521.55
18.77
94.21
220.91
347.61
474.30
28.09
136.79
272.66
408.53
544.39
Bridge Section
A7 - 5
Design Manual
j.
Maintenance
The goal for all barriers constructed by KDOT is minimum maintenance cost.
Each barrier design should be performed with this goal in mind.
k.
Aesthetics
Successful barrier projects not only adequately reduce noise levels, but also receive
positive response regarding appearance (aesthetics). In order to assure this positive
response, care should be taken in selecting a color scheme and surface texture, and
use of landscaping should be considered in design.
1.
m.
Isolated Receivers
Barriers will not be constructed for individual residences or other isolated
receivers.
5)
Bridge Section
A7 - 6
Design Manual
2.
3.
6)
Sensitive Receptors
Although all activities that have a NAC are reviewed, single family residences have
the highest priority for limited highway construction funds.
Approved:
E. Dean Carlson,-Secretary
Kansas Department of Transportation
Bridge Section
A7 - 7
Design Manual
Bridge Section
A8 - i
Design Manual
Project
Specific
Standard
5200
6000
6010
6100
6110
6111
6115
6120
6130
701
702
30
35
300
1030
105
708
710
105
708
710
4100
4105
4115
4120
4100
4106
4110
4120
4130
4140
7800
7810
4130
4140
7800
7820
105
708
710
SP0707004
3000
3010
5210
6420
6520
6521
6522
6523
8700
105
708
710
SP0707014
3000
3010
5210
6420
6520
6521
8700
9001
9002
9003
105
708
SP070711
4140
4200
5100
5110
7000
7210
7215
7300
7301
7310
7311
7312
7320
7330
7400
3 weeks
Shoring
Railroad
6 weeks
Category (1)
4 weeks
Category (2)
4 weeks
Category A
(1)
Falsework
Erection
Demolition
Pour Sequence
Category B
4 weeks
Category C
4 weeks
Category A
(1)
Category B
4 weeks
Category C
4 weeks
Discuss
Possible
Changes at
Precon
Meeting
2 Weeks
6200
6210
6220
6410
6420
6600
6620
6625
7410
Recommend
Approval
In House
Shop Details
101 106
705 707
709 716
719 721
722 735
1609
Plan Review
Project
Specific
P.E. Stamp
Required
Plan Type
Note
Numbers to
Review
Lead Time
Required
Consultant
Information
Specs to
Review
# of Plan
Copies
No
No
**
No
Yes
**
Yes
Yes
Yes
Yes
Yes
Yes
Yes
District Policy
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Yes
Yes
Yes
No
Yes
Yes
Based on project complexity, the specifications and the notes listed in this document may only be the base
of what is required.
* Electronic submittal conforming to 105.10 (b) of the Standard Sepcifications for State Road and Bridge
Construction
Bridge Section
A8 - ii
Design Manual
The Kansas Department of Transportation (KDOT) will change two procedures regarding shop
drawings for structural steel bridges let January, 2010 and after.
First, KDOT will change to receiving and storing shop drawings in the digital Portable
Document Format (PDF). KDOT is currently using this technology on several projects. The
State Bridge Office, along with the Consultants and Fabricators involved, are pleased with the
results.
Submittal of hardcopy prints will no longer be accepted. Therefore the ability to scan and plot
drawings into an 11x17 standard PDF format is required.
KDOT can accept file sizes less than 5 MB as email attachments. Files larger than this will
require the use of an FTP site for file exchange.
Attachment 1 details the procedure KDOT will use for processing electronic shop drawings.
Attachment 2 details the procedure KDOT will use for processing revised electronic shop
drawings.
A second change is that KDOT Consultants need not put their approval stamp on each sheet of
the final Consultant-approved shop details. Instead, the Consultant will submit a memo bearing
their approval stamp along with the final details. The memo will also contain KDOTs Project
number and bridge number, the Consultants job number, the Fabricators job number, a list of all
the sheets, and any other information necessary to communicate the contents of the drawings that
are submitted (in the PDF file(s)).
Bridge Section
A8 - iii
Design Manual
The State Bridge Office and the Bureau of Local Projects, Bridge Team endorses this policy.
This memorandum addresses shop drawings specifically because the approval stamp procedures
for shop drawings are changing. However, KDOT will require all working drawings (shop
drawings, falsework plans, erections plans, shoring details, etc.) to be electronic submittals for
KDOT jobs. KDOT will provide details by memorandum and modification to the specifications.
Sincerely,
Jim L. Kowach
Chief, Bureau of Design
Kansas Department of Transportation
JLK:jkk
Attachments
c:
BUREAU OF DESIGN
Jim L. Kowach, P.E., Chief
Dwight D. Eisenhower State Office Building
700 S.W. Harrison Street; Topeka, KS 66603-3745 (785) 296-3531 Fax: (785) 296-6946
Hearing Impaired 711 e-mail: publicinfo@ksdot.org Public Access at North Entrance of Building
Bridge Section
A8 - iv
Design Manual
Attached is a file containing approved shop details, dated [Insert Date], for the [insert information about
shop plans].
The details in the file are identified as Sheet Numbers [insert sheet numbers] of your Job No. [insert Job
No.].
Sincerely,
Jim L. Kowach, P.E.
Chief, Bureau of Design
Bridge Section
A8 - v
Design Manual