Beruflich Dokumente
Kultur Dokumente
Wind
Energy
GE Energy
February 26, 2007
ecomagination
Agenda
Offshore Wind Market Drivers
Offshore Environmental Challenges
Severe Design Envelopes
Environmental Data
Installation
Operation & Maintenance
Design Considerations
Foundation Systems
Economics and Future Design
Options
Summary
ecomagination
2
February 26, 2007
Offshore Wind
Market Drivers
ecomagination
3
February 26, 2007
40
North Atlantic
30
20
10
Wave Breaking
Probability
50
North Sea
0
100
Years
1
Years
1
Day
Return Period
Constraints:
Risks/Costs: Technology; Construction; Operational;
Maintenance
Accessibility: Difficult service environment
Storm Conditions
10 MW GE Wind
at Utgrunden, Sweden
Installations
AGR
C
9%
13.6 14.0
15.3
11.8
ROW
Asia Pacific
North
America
Europe
05
06
07
08
Source: EER
Performance
Cost
Operating Availability
Track Record
Service Package
8
COE/NPV/IRR
Local Content
Latest Technology
7
Focus on Energy
Production and Cost
Offshore
Environmental
Challenges
Severe Design Envelopes
ecomagination
7
February 26, 2007
Salinity, Humidity
& Temperature
Ship Impact
(Breaking) ice
(Breaking) Waves
Hurricanes
Aesthetics
Currents Tides
Earthquake
Foundation
Behavior
WTG
% Cost
Marine
Life
Transition
Piece
Geotechnical Uncertainty
Foundation
Water Depth
Foundation &
Installation Costs
pile
Water Depths
US Average Depth = 15 m
Europe Avg. Depth = 11 m
Maintainability &
Availability
ecomagination
8
February 26, 2007
Hurricanes A US Issue
Hurricanes are Real Threat
No existing industry Design Guidelines
Hurricane
Statistics over
100+ years
35
30
25
Source : Unisys Hurricane Database
(pre 2005 data)
20
Total #
15
10
Eye Speed
5
Minimum Wind
Max 0
Wind Speed 110 115 120 125 130 135 140 150 155 160 165
Maximum Wind
Micrositing Analysis
#-Atlantic
27
20
29
12
12
# - GOM
12
mph
Ms
Nonlinear Contact
Spring, Ks
x3
l2
M1
vs
x1
l1
Penetration
Mudline
Foundation Spring, Kf
Ships Discretization
Indentation
Case
Vessel Type
Ferry
DWT
(metric
tons)
1500
Action
Ferry
1500
Head-on at 12
knots
0.95*
Fishing Boat
300
Head-on at 12
knots
< 0.25
Barge
1200
Drifting at 3
knots
< 0.62
Yacht
20
Head-on at 15
knots
0.05
Moored
Service
Vessel
75
Wave Induced
Impact from
Mooring
0.28
Drifting at 3
knots
Tower
Utilization
Factor*
0.65
Offshore
Environmental
Challenges
Environmental Data
ecomagination
11
February 26, 2007
Meteorological
Mast at the
proposed Cape
Wind Farm
Detailed wind speed / wave height profile obtained from an onsite meteorological tower
Occurrence of extreme weather phenomena such as hurricanes
(Cat 3 and above)
Understanding of seabed stability at wind farm site
Centrifuge is an example of
potential geotechnical risk
mitigation reviews
Geotechnical Soil Conditions
Example of an Offshore
Cone Penetration Test Rig
Offshore
Environmental
Challenges
Installation
ecomagination
14
February 26, 2007
Foundation Installation
Offshore Project Resource Challenges
Transportation
Cables
Towers
Foundations
Nacelles
Heavy Duty Equipment Availability
Specialized Equipment Required:
- Heavy-lift jack-up barges & cranes
- Large pile-driving hammers & eqpt
- Marine cable-laying equipment
Specialized Manufacturers & Suppliers Required:
Heavy steel rolling/welding
Submarine cable production
Foundries for cast hubs & frames
Sea Cable
Installation
Pile Transport
Pile Placement
Nacelle Loading
Nacelle Lift
Tower and
Nacelle
Fully
Assembled
ecomagination
16
February 26, 2007
6 miles to Port
Arklow
7 x 3.6s WTGs
Stone-dumping Vessel
Offshore
Environmental
Challenges
Operation and Maintenance
ecomagination
18
February 26, 2007
~15-25%
of Total
COE
Decreased
Availability
Cost Variance
Unplanned ~80%
Offshore Service
Access
Jack Up Barge Cost
Material Cost
Labor Cost
Decreased
Production
Planned ~20%
O&M Costs
Large Portion of COE
Significant Variance
Decreased
Revenue
Offshore Access
Unplanned O&M
Planned O&M
4X
10X
Field Services
Enhanced Offshore
Equipment Designs
Advanced Controls for Load
Mgmt & Performance
Design for Serviceability
Continuous Improvement
Reliability & Performance
Modifications & Upgrades
Offshore
Environmental
Challenges
Access
ecomagination
22
February 26, 2007
Offshore Accessibility
Accessibility to WTGs in Varied Weather Conditions a Must
Drives Installation & Commissioning Cycles
Key to High Reliability
Multiple Options for Varied Site Conditions
Frog, Ladder, Offshore Transfer System (OTS) (OAS), Water Bridge, Wind Lift,
BoardSafe, Fast craft hoisting system, (Davit & RIB), Ramp access system, Wire rope
access, Floating cubicles, Offshore Entry/Evacuation system, Hydraulic ramp
Access Systems
Vessels
(OAS)
Water Bridge
Access Considerations
Arklow provided an excellent test ground - extreme
sea conditions .continuous improvement
Currently using purpose built vessel on the market
Have safely transferred personnel in 2+ meter
waves
Trials have proven safe access capable in 2.5
meter waves.significant improvement in 6
months
Improved purpose built vessels under development
% Accessibility Arklow
Purpose Built Vessel 2.5m
84.66%
75.34%
Conventional Vessel 1m
41.64%
Vessel designed for wind turbine access
ecomagination
24
February 26, 2007
Offshore Wind
Turbine Design
Foundations
ecomagination
25
February 26, 2007
Wind Energy
20 - 300+m
5,000 - 30,000 ton
10% - 20% of vertical load
10 - 30m
100 - 300 ton
70% - 150% of vertical load
(Water depth +100m) x
Horizontal load
20 - 200
~5m
1.5 - 5.0 MW per WTG
Lateral Strength
?
> 25-30 m Foundation
Gravity Foundation
Near Shore
Monopile
20 m, 6 Miles
Monopile
Transition Piece Key
Hammering
Natural Frequency Barrier at <30 m
Economical at 3-4MW
ecomagination
28
February 26, 2007
Nmin = 8.5rpm
rotor, 800rpm
generator
Frequency (Hz)
1.6
1.2
Nrtd = 15.3rpm
rotor, 1440rpm
generator
0.8
6P +/-10%
(2X Blade
Pass Freq)
Nmax = 21.3rpm
rotor, 2000rpm
generator
3P +/-10%
0.4
n = rotor speed
nR = Rated
rotor speed
0
0
0.2
0.4
0.6
0.8
1
Relative Rotor Speed (n/n R)
1.2
1.4
Foundation Technologies
0 20m : Monopile & gravity foundations are most
prevalent; Resonance constraints from rotor
operation leads to increasing tonnage &
manufacturing limits.
.
Monopile
20 m, 6 Miles
Gravity Foundation
Near Shore
Economics &
Design
Trends/Options
ecomagination
31
February 26, 2007
$MM
Cost
W/ 5MW Turbines
ecomagination
32
February 26, 2007
Questions
ecomagination
33
February 26, 2007