Coaza
PROYECTO
INFRAESTRUCTURA VIAL
OBRA
CONSTRUCCION DE
DE CARRETERA
CARRETERA
CONSTRUCCION
TROCHA CARROZABLE
CARROZABLE
TROCHA
COAZA UMACHULLO
UMACHULLO
COAZA
UBICACIN
:
REGION
DEPARTAMENTO
PROVINCIA
DISTRITO
LOCALIDAD
: PUNO.
: PUNO.
: CARABAYA.
: COAZA.
: UMACHULLO.
ADMISTRACION DIRECTA
PRESUPUESTO TOTAL: 48,768.52 Nuevos Soles
Alcalde
Juntos Si Podemos !
PERIODO 2,003 - 2,006
______________________________________________________________________________________________________________
INDICE
Pg.
PRESENTACIN
CAPITULO I
MEMORIA DESCRITIVA
I.
ASPECTOS GENERALES
1.1.
1.2.
17
1.3.
17
1.4.
18
1.5.
18
19
II.
IDENTIFICACIN
2.1.
19
b.
c.
d.
20
20
20
21
21
______________________________________________________________________________________________________________
2.2.
22
2.3.
24
2.4.
26
2.5.
26
III.
FORMULACION
3.1.
27
27
3.1.2. Anlisis del Sistema de Actividades
27
a.
Actividad Turstica.
b.
Actividad Agrcola.
c.
Actividad Artesana
d.
Actividad Minera.
28
28
28
29
3.2.
29
Anlisis de Demanda
a.
b.
Tipos de Trafico
c.
Demanda actual
29
29
29
3.3.
29
Anlisis de la Oferta
a.
b.
c.
29
30
30
3.4.
30
Identificacin de Beneficios.
31
______________________________________________________________________________________________________________
IV.
V.
Partidas Proyectadas.
Metrado y Anlisis de Costos Unitarios
Presupuesto de Obra.
Ejecucin de Obra.
EVALUACION
5.1.
5.2.
5.3.
33
b.
33
c.
34
VI.
Capacidad de Gestin
Financiamiento de gastos de mantenimiento
BSE LEGAL
34
CAPITULO II
ESTUDIOS DE INGENIERIA
I.
Estudios Existentes
38
1.1.
b.
Informacin Cartogrfica
38
c.
Informacin Meteorolgico
38
Reconocimiento, Evaluacin de campo del Proyecto.
39
a.
Trazo Vial, Caractersticas geomtricas
39
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
______________________________________________________________________________________________________________
b.
39
c.
39
d.
40
e.
42
f.
42
g.
43
ESTUDIOS DE INGENIERIA
I.
INTRODUCCION
1.1
46
1.2
47
1.3
50
1.4
52
Geomorfologa
Geologa del trazo
Geotecnia de Cimentaciones
Estudio de canteras y Fuentes de Agua
INTRODUCCION
Objetivos
Antecedentes
Situacin Actual
Erosin
Centros Poblados
Impactos por la Construccin
Normas de Comportamiento
Normas Generales para la Jefatura de Proyecto
Normas Generales de Comportamiento del Personal
______________________________________________________________________________________________________________
63
GENERALIDADES
68
II.
ESTUDIO DE HIDROLOGIA
68
Caractersticas de las cuencas hidrogrficas.
68
68
69
70
71
72
72
73
74
III.
74
75
IV.
Metodologa empleada.
Aspectos climticos y vegetacin
Anlisis de la Precipitacin.
Anlisis de las Precipitaciones mximas en 24 horas.
Anlisis de frecuencia
Intensidades mximas de precipitacin pluvial
Caudales de Diseo.
Compatibilizacion Hidrulica.
ESTUDIO DE DRENAJE
74
Drenaje Longitudinal.
Drenaje Transversal.
CONCLUSIONES Y RECOMENDACIONES
75
CAPITULO III
METRADOS, INSUMOS, COSTO
Y ESPECIFICACIONES TECNICAS
I.
______________________________________________________________________________________________________________
III.
IV.
V.
VI.
VII.
PRESUPUESTO DE OBRA
115-116
79
96
99
105
ESPECIFICACIONES TECNICAS
9.1.
120
Consideraciones Generales
Consideraciones Particulares
121
121
Compatibilizacion y Complementos
122
9.2. Especificaciones tcnicas de Obra.
155
13.3. Compatibilizacion y Complementos
01.00.00
01.01.00
01.01.01
01.01.02
01.02.00
01.02.01
01.02.02
123 -
______________________________________________________________________________________________________________
EXPLANACIONES
CORTES
CORTE DE MATERIAL SUELTO
CORTE ROCA SUELTA MANUALMENTE
CORTE ROCA FIJA
PERFILADO
PERFILADO Y COMPACTADO EN ZONA DE CORTE
DESQUINCHE Y PEINADO DE TALUDES MANUALMENTE
RELLENOS
RELLENO CON MATERIAL PROPIO CON EQUIPO
RELLENO PRESTAMO DE CANTERA
03.00.00
03.01.00
03.01.01
03.02.00
03.02.01
03.02.02
03.02.03
03.02.04
FLETES
FLETES TERRESTRES
TRANSPORTE DE PIEDRA DESDE CANTERA EN VOLQUETE
TRANSPORTE DE MATERIAL LASTRE DESDE CANTERA
CAPITULO IV
PLANOS INSUMOS, COSTO
I.
PLANOS
1.1
157
II.
ENSAYOS EN LABORATORIOS
2.1 Result. de Anlisis y Clasificacin de Cantera Huayrapata
159- 180
III.
PANEL FOTOGRAFICO
187
182-
______________________________________________________________________________________________________________
IV.
ANEXOS
PRESENTACIN
El
proyecto:
CONSTRUCCIN
DE
LA
CARRETERA
TROCHA
constante
han
estado
identificando,
proponiendo,
______________________________________________________________________________________________________________
10
______________________________________________________________________________________________________________
CAPITULO I
11
______________________________________________________________________________________________________________
MEMORIA DESCRIPTIVA
12
______________________________________________________________________________________________________________
MEMORIA DESCRIPTIVA
I.
ASPECTOS GENERALES
NOMBRE DEL PROYECTO
:
: 0392,313.26
: 8448,383.37
: 0003,770.00 m. s. n. m.
CARACTERSTICAS DE LA ZONA
La zona del presente proyecto presenta una topografa
accidentada presentando una pendiente promedio de 45 a
70 con un porcentaje de 25 % En general el lugar donde se
ubicara la carretera se encuentra entre las cumbres y
quebradas de la zona noroeste del Departamento de Puno,
la superficie del suelo esta conformada de tierra casi
agrcola por que presenta estrato de pizarra.
13
______________________________________________________________________________________________________________
MAPA VIAL
14
______________________________________________________________________________________________________________
15
______________________________________________________________________________________________________________
PLANO GEOLOGICO
16
______________________________________________________________________________________________________________
17
______________________________________________________________________________________________________________
PLANO CLAVE
18
______________________________________________________________________________________________________________
19
______________________________________________________________________________________________________________
Km.
5+030.00
Km.
Km.
Km.
Km.
Enrrocado 10 m.
Badn
Badn
Enrrocado 12 m.
m.
1+600.00
2+500.00
3+040.00
3+200.00
8m.
m.
20
______________________________________________________________________________________________________________
asume
tal
UNIDAD FORMULADORA:
Municipalidad Distrital de Coaza.
B.
UNIDAD EJECUTORA:
Municipalidad Distrital de Coaza.
C.
UNIDAD FINANCIADORA:
Municipalidad Distrital de Coaza.
PARTICIPACIN DE
LOCALES.
LOS
BENEFICIARIOS
AUTORIDADES
ANTECEDENTES:
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
21
______________________________________________________________________________________________________________
22
______________________________________________________________________________________________________________
IDENTIFICACIN
DEFINICIN DEL PROBLEMA
En el mbito de influencia del proyecto la mayor parte
de los ingresos son generados por las actividades de
23
______________________________________________________________________________________________________________
a.
24
______________________________________________________________________________________________________________
b.
c. CARACTERSTICAS
SOCIOECONMICAS
CULTURALES DE LA POBLACIN.
25
______________________________________________________________________________________________________________
d.
e.
LINEA DE BASE
La poblacin involucrada en el proyecto, observa
los siguientes indicadores, los cuales constituyen lnea
de base para determinar la mejora y/o deterioro
situacional con la implementacin del proyecto,
medido al intermedio y al final del horizonte del
proyecto:
a. Existencia de vas peatonales de trnsito
inadecuado que comunica el distrito de Coaza.
b. El trnsito de vehculos proyectado al final del
horizonte del proyecto al ao 2500 asciende a 3600
unidades, de ejecutarse el proyecto.
c. La tasa de crecimiento de la poblacin es de 0.16%
anual.
d. La densidad poblacional es de 21%.
26
______________________________________________________________________________________________________________
Efectos:
27
______________________________________________________________________________________________________________
ARBOL DE PROBLEMAS
Efecto Final:
(CAUSAS Y EFECTOS)
BAJOS NIVELES DE
COMERCIALIZACION DE
PRODUCTOS DE LA ZONA
INEXISTENCIAS DE INGRESOS EN
LOS ENTES ECONOMICOS POR LA
ACTIVIDAD TURISTICA
ALTOS COSTOS DE
TRANSPORTE
RECURSOS TURISTICOS
EXISTENTES NO EXPLOTADOS
ACTUALMENTE
PRODUCTOS DE LA ZONA
INACCESIBLES A OTROS
MERCADOS
DEFICIENTE ACCESIBILIDAD DE
LA VIA DE COMUNICACIN
TERRESTRE
LLUVIAS
RENCIALES
LA FLUID
EZ DEProf. Juan ESTRADA
INEXISTEARAUJO
NCIA DE / GESTIONTOR
Alcalde:
2003-2006
ESTACIONALES Y
MEDIOS DE
SISTEMA DE
PRESENCIA DE
TRANSPORTE DE
DRENAJES
VIENTOS
ALTO TONELAJE
DESINTERES REFERENTE AL
MEJORAMIENTO VIAL
28
DESINTERES EN
EL
MANTENIMIENTO
DE LA VIA POR
PARTE DE LA
POBLACION
DEFICIENTE
APOYO DEL
GOBIERNO
CENTRAL EN EL
MANTENIMIENTO
DE LA VIA
______________________________________________________________________________________________________________
29
______________________________________________________________________________________________________________
ALTOS NIVELES DE
COMERCIALIZACION DE
PRODUCTOS DE LA ZONA
Medios:
BAJ OS COSTOS DE
TRANSPORTE POR
INCREMENTO DE TRANSPORTE
NI VEL DE VI DA ADECUADA DE
PRODUCTOS
Fines:
ESTADO DE CARRETERA EN
CONDICIONES ADECUADAS
PARA EL TRANSITO
MANTENIMIENTO
CONSTANTE DE LA VIA
CONSERVACION DE LA
CARRETERA EN BUENAS
CONDICIONES
CIRCULACION DE
VEHICULOS SIN PROBLEMAS
30
Construccin de la carretera trocha
carrozable tramo Coaza Umachullo.
______________________________________________________________________________________________________________
EL
OBJETIVO
31
______________________________________________________________________________________________________________
FORMULACION
AREA DE INFLUENCIA DEL PROYECTO
El rea de influencia directa de la carretera se estima en
12,266.40 Km2 correspondiente a la Provincia de Carabaya;
mientras que el rea indirecta alcanza los 61,186.22 Km2,
sta ltima incluye toda la Regin Puno, la poblacin
estimada de la regin Puno al ao 2000 asciende a los
1130,775 habitantes, segn el Instituto Nacional de
Estadstica e Informtica - 2005. Con la construccin de la
carretera el mbito de influencia del proyecto estar
integrado principalmente a los siguientes espectros
dinmicos ms importantes de la actividad socio-econmicos
del departamento:
32
______________________________________________________________________________________________________________
a.
ACTIVIDAD TURISTICA
La actividad turstica en los Distritos de Coaza,
Ajoyani, Ayapata, Macusani, etc. es de suma
importancia, por contar con recursos de orden
paisajstico y natural en todo el rea y otros, asimismo
destacan el de orden histrico y cultural como restos
arqueolgicos; manifestaciones de orden folklrico,
fiestas patronales, religiosas, etc. los cuales
constituyen
atractivos
que
en
la
actualidad
representan un potencial importante para la actividad
turstica.
Los factores limitantes para un mayor aporte de
esta actividad a la economa regional, es la FALTA DE
INFRAESTRUCTURA VIAL ADECUADA Y SUFICIENTE. Los
paisajes y lugares de recreo son necesarios para el
desarrollo social del poblador; es as que se cuenta con
un basto paisaje variable.
b.
ACTIVIDAD AGRICOLA
La actividad agrcola a nivel del distrito de
Coaza, tiene una superficie cultivable de 25,600 Has,
que representa el 45% del distrito y 6% de la
provincia, de los cuales el 46,8% de superficie est
33
______________________________________________________________________________________________________________
c.
ACTIVIDAD ARTESANIA
Es
una
actividad
complementaria
a
la
agropecuaria y est orientada mayormente a la
produccin textil. La produccin artesanal se realiza
con una tecnologa tradicional, donde se utilizan
instrumentos manuales como telares rsticos, ruranas,
agujas, combos, cinceles y otros, por el cual el 0.5 %
se dedica a este tipo de actividad.
Los principales rubros en esta actividad son la
textilera (frazadas, llijllas, mantas, ponchos, bayetas,
chompas, chullos, etc.), la produccin lo destinan
mayormente para el autoconsumo, dejando un
pequeo margen para la venta, lo cual est supeditado
a los recursos econmicos que disponga cada
productor.
d.
ACTIVIDAD PECUARIA
Este tipo de actividad viene a ser tambin otro
de los recursos de sobre vivencia del total de la
poblacin existente el 60% se dedica a la actividad
pecuaria criando en gran porcentaje a : vacas, ovejas,
llamas, etc. .
e.
ACTIVIDAD MINERA
34
______________________________________________________________________________________________________________
Este
tipo
de
actividad
viene
a
ser
complementaria puesto que el 16% del total de la
poblacin se dedica a la explotacin del oro de forma
artesanal, donde se utilizan herramientas manuales
como picos, palas, barrenos, combos, cinceles y otros.
Los principales rubros en esta actividad es el oro, la
explotacin lo destinan mayormente para el
autosostenimiento realizando en pequeas cantidades,
lo cual est supeditado a los recursos econmicos que
dispongan.
ANALISIS DE DEMANDA
a.
b.
TIPOS DE TRAFICO
En esta parte se considera el trfico peatonal y de
cargas los auqunidos sin proyecto.
c.
DEMANDA ACTUAL
La demanda se concibe como el flujo peatonal que
circula por el camino de herradura; para estimar la
demanda actual se ha efectuado encuestas del trfico
peatonal con un mnimo diario de 50 personas en el
tramo del proyecto a ejecutarse. Por IMDA se entiende
que es el ndice Medio Diario Anual, el que se define
como el nmero de personas promedio anual que
circula diariamente 70, personas por el Tramo Coaza
Pampawasi Chimina Umachullo.
35
______________________________________________________________________________________________________________
3.3.
ANALISIS DE LA OFERTA
a.
b.
c.
36
______________________________________________________________________________________________________________
= Valor de tiempo
VET
= 1.67 Soles/Hora
No Pasajeros
= 40 promedio
Das ao
= 365
TV
= Tiempo de viaje
VT = 1.67 x 40 x 365 x 1
VT = 24,382.00 p/persona
a.
IDENTIFICACIN DE BENEFICIOS
37
______________________________________________________________________________________________________________
BCOV
costos
COVsp =
COVcp
Beneficio
total
por
ahorro
de
operativos vehicular
Costo Operativo
Vehicular total
sin
proyecto
=
Costo Operativo Vehicular total
con
proyecto.
IV.
01.00.00
01.01.00
OBRAS PROVISIONALES
01.01.01
GLB
01.01.02
M2
01.02.00
OBRAS PRELIMINARES
01.02.01
TRAZO Y REPLANTEO
KM
01.02.02
M2
01.02.03
M3
02.00.00
EXPLANACIONES
02.01.00
CORTES
02.01.01
M3
02.01.02
M3
02.01.03
M3
02.02.00
PERFILADO
38
______________________________________________________________________________________________________________
02.02.01
M2
02.02.02
M3
02.03.00
RELLENOS
02.03.01
M3
02.03.03
M3
03.00.00
03.01.00
OBRAS DE ARTE
03.01.01
03.02.00
OBRAS DE DRENAJE
03.02.01
M2
03.02.02
M3
03.02.03
CUNETAS
03.02.04
04.00.00
ENSAYOS EN LABORATORIOS
04.01.00
04.01.01
05.00.00
FLETES
05.01.00
FLETES TERRESTRES
05.01.01
M3
05.01.02
M3
06.00.00
VARIOS LIMPIEZA
06.01.00
LIMPIEZA DE LA OBRA
06.01.01
39
M3
UND
GLB
______________________________________________________________________________________________________________
Costo Directo
641,177.55
S/.
Gastos Generales
S/.
Gastos Supervisin
48,088.32
:
S/.
Gastos de Liquidacin
S/.
:
48,088.32
:
16,029.44
============
PRESUPUESTO TOTAL DE
S/.
705,295.31
V.
EVALUACION
5.1
40
______________________________________________________________________________________________________________
a.
EN LO INSTITUCIONAL
La
poblacin
beneficiaria,
coordinaran
mutuamente a nivel de autoridades polticas, agentes
municipales, alcalde, etc.), con el fin de tomar
acuerdos para la solucin de algn problema.
Existe coordinacin con las entidades tales como
Ministerio de Transportes y Comunicaciones mediante
el Unidad de Caminos Rurales de Puno y Gobierno
Local como ente promotor y ejecutor del desarrollo Vial
del Distrito de Coaza teniendo en cuenta el firme
propsito de viabilizar el proyecto.
b.
CAPACIDAD DE GESTIN
Como gobierno local y autoridad mxima y
autnoma de la jurisdiccin comprendida dentro del
Distrito de Coaza junto a sus autoridades, y
ciudadanos vienen promoviendo y coordinando para su
ejecucin del presente proyecto.
c.
FINANCIAMIENTO
MANTENIMIENTO
DE
COSTOS
DE
41
______________________________________________________________________________________________________________
VI.
BASE LEGAL
Se ha tomado en consideracin la Directiva para la
Programacin, Formulacin y Aprobacin del Presupuesto
Participativo Institucional para el presente ao fiscal 2004
a).-
j).-
k).-
l).-
Resolucin
Vice
Ministerial
N
14899EF/13.03
42
______________________________________________________________________________________________________________
43
______________________________________________________________________________________________________________
CAPITULO II
44
______________________________________________________________________________________________________________
ESTUDIOS DE INGENIERIA
45
______________________________________________________________________________________________________________
a. Estudios Existentes
En lo que respecta a los estudios existentes, se ha
recabado informacin de Perfiles de Proyecto donde, de su
archivo, se ha verificado el Tramo de Ayusuma - Umachullo de
fecha agosto de 2001.
El perfil antes citado, es una ficha de informacin,
adecuacin y actualizacin de un estudio, que en el ao 1988
ejecuto la Municipalidad Provincial de Carabaya, por encargo de
la Corporacin Departamental de Desarrollo de Puno. Cabe
destacar de dicho perfil el planteamiento de una apertura de
carretera trocha carrozable sobre el nivel del terreno natural,
una velocidad directriz de 25 km./h, superficie de rodadura de
4.00 m y bermas de 1.50 m a cada lado, y una pendiente
mxima de 6.05 %.
A pesar de la antigedad de dicho estudio, el mismo
aporta valiosa informacin respecto a los tipos de suelos de la
subrasante, caractersticas de canteras, caractersticas del trazo,
secciones y otros.
En lo referente a informacin complementaria sobre la
zona que comprende el estudio se ha revisado y analizado el
Programa de Inventario y Evaluacin de los Recursos Naturales
del Departamento de Puno, elaborado por el Instituto Nacional
de Planificacin, Oficina Nacional de Evaluacin de Recursos
Naturales (ONERN), del ao 1965. As mismo se ha consultado
el Convenio Estadstico 1993 - 94, editado por el Instituto
Nacional de Estadstica e Informtica (INEI).
b. Informacin Cartogrfica
La informacin cartogrfica se ha obtenido del Instituto
Geogrfico Nacional (I. G. N.), que consiste en la Carta Nacional
a escala 1:100,000 y planos Cartogrficos a escala 1:25,000 de
la Direccin de Catastro, dicha informacin esta contenida en
las Hojas 28 X Ayapata.
Del mismo Instituto se ha obtenido tambin la
informacin de elevaciones para el control altimtrico del
estudio.
c.
Informacin Meteorolgica.
La informacin bsica a ser usada en los diseos del
estudio, es la relativa a los registros de precipitacin pluvial
existentes. En el caso presente, la informacin se ha obtenido
46
______________________________________________________________________________________________________________
1.1.
RECONOCIMIENTO, EVALUACION DE CAMPO DEL
PROYECTO
a.
b.
47
______________________________________________________________________________________________________________
c.
Levantamiento Topogrfico.
La segunda etapa del estudio comprendi a los
trabajos de campo correspondientes al trazo y estacado del
eje longitudinal, la ubicacin de los P. I. (s), B. M. (s),
nivelacin y seccionamiento de cada estaca, ubicacin de
canteras, ubicacin de las obras de arte como, Badenes y
tajeas, muestreo para el estudio geotcnico del suelo y la
cantera, todos de acuerdo a las progresivas y de la tangente.
d.
15
Km/hr.
Radio Mnimo
25 m.
Radio Mnimo Excepcional 15 m.
Peralte Normal
6 %.
Peralte Excepcional
10 %.
Ancho de Va
4.50 m.
Pendiente Mxima Normal 8.5 %.
Pendiente Mxima Excepcional
11.0 %.
Pendiente Mnima
0.5 %.
Bombeo
3 %.
Talud en corte:
Roca fija (V. H.)
10.1
Roca suelta
3:1
Conglomerado
3:1
48
25
______________________________________________________________________________________________________________
Tierra Compacta
Tierra Suelta
Talud en relleno:
Enrocado
Terrenos varios
Cunetas
2:1
1:1
1:1
1:1.5
0.30 x 0.50 m.
Clase.
Segn a la importancia y de acuerdo a las Normas
para el Diseo de Caminos Vecinales. Se considera
trocha carrozable y vecinal de tercera categora
debido al servicio rural y por ser camino Inter.
Distrital, teniendo en cuenta que se considera
como la categora mas baja de camino de
transitabilidad
para
vehculos
automotores,
construido con un mnimo movimiento de tierras,
suficiente nicamente para proveer un a superficie
de seccin transversal que permita el paso de un
vehculo y cuyos alineamientos horizontales y
verticales se ajustan a la inflexiones del terreno.
Velocidad Directriz.
Es
la
velocidad escogida para el diseo,
entendindose que ser la mxima que se podr
mantener de acuerdo con la superficie de
rodadura y a la topografa del terreno. La
velocidad directriz es de un mximo de 25 Km. / h,
siendo la mas adecuada para este tipo de
carretera, pudiendo desminuir en los desarrollos
forzados.
Superficie de Rodadura.
Establecida
de acuerdo al tipo de movilidad
prevista que es la de 4.50 metros. Se prevee el
diseo de pazueletas de estacionamiento con
dimensiones mnimas utilizables de 3 x 30 m. a
distancias no mayores a 400 metros.
Superficie de calzada.
La calzada o razante terminada es la suma de la
superficie de rodadura mas el ancho de las
bermas, siendo en nuestro caso el ancho de la
calzada igual a la superficie de rodadura por no
estar proyectadas las bermas.
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
49
______________________________________________________________________________________________________________
Superficie de la Sub-Rasante.
El ancho de la Sub.- Rasante es el ancho necesario
en el cual se depositara el material de prstamo o
de corte correspondiente esta dada de acuerdo al
talud y la altura del pavimento Sub. Base, Basre,
segn sea el caso de cada tramo.
Bombeo.
El Bombeo considerado para el caso especifico es
de 3 % en toda su longitud, considerando que esta
ser sustituida por peralte en las curvas.
Taludes.
Los taludes variaran de acuerdo al tipo de material
diseado para el terrapln, esto obedece a los
resultados obtenidos en laboratorio los cuales
deben garantizar la consistencia del talud una vez
sometidos a su mejoramiento correspondiente.
Pendientes.
La pendiente considerada para este tipo de
carretera segn las Normas Para el Diseo de
Caminos Vecinales es de 0.5 %, cualquiera fuera la
pendiente topogrfica.
Radios.
El radio permitido por las Normas Para el Diseo
de Caminos Vecinales dan un radio mnimo de 30
metros y un radio mnimo excepcional de 15
metros debido al complejo topogrfico se adoptan
radios mnimos excepcionales adaptndose en los
puntos crticos.
R=
Vd
1.28 (p + f)
Donde:
Vd = Velocidad Directriz.
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
50
______________________________________________________________________________________________________________
p = Pendiente.
F = Factor de friccin lateral.
Peralte.
El peralte es determinado en funcin ala velocidad
directriz y al radio de la curva, siendo muy cambiante
en los tramos con bastantes curvas.
El peralte estar dado por:
P=
V
2.28 R
Donde:
P = Peralte % expresado enteros
V = Velocidad de diseo en Km/h.
R = Radio de las curvas en metro.
Sobre ancho.
El Sobre ancho es la ampliacin de la superficie de
calzada a causa de una curvatura, esta es considerada
de acuerdo a la velocidad directriz y el radio de la
curva.
e.
f.
Conclusiones y Recomendaciones
El Proyecto que se ha elaborado tiene como base todos
los aspectos ya sealados anteriormente y otros que se
describen en los Captulos que siguen a la presente
Memoria Descriptiva y la fundamentacin tcnica del
presente estudio, y se puede sintetizar en las siguientes
conclusiones y recomendaciones:
El Proyecto debe ser considerado como
construccin u obra completamente nueva.
51
una
______________________________________________________________________________________________________________
e.
Geologa y Geotecnia.
Impacto Ambiental.
Estudio Hidrolgico y Drenaje.
52
______________________________________________________________________________________________________________
GEOLOGIA Y GEOTECNIA
53
______________________________________________________________________________________________________________
54
______________________________________________________________________________________________________________
ANEXOS
Reportes de Mecnica de Suelos por Cimentacin
Reportes de Mecnica de Suelos por Canteras
55
______________________________________________________________________________________________________________
GEOLOGIA Y GEOTECNIA
I.
INTRODUCCION
Objetivos
El objetivo principal es determinar y evaluar las condiciones
geomorfolgicas, geolgicas, geotcnicas y ssmicas de la
cimentacin del trazo carretero proyectado entre las localidades de
Coaza Umachullo, del Distrito de Coaza.
Situacin Actual
El camino de herradura que une las localidades de Coaza
Pampawasi Chimina Umachullo se encuentra parcialmente
abandonado, por falta de un adecuado mantenimiento del camino.
Este Camino es considerada como principal, puesto que por la
via hacen traslado de sus productos, motivo por el cual es
imprescindible su construccin a nivel de trocha carrozable.
Relieve fisiogrfico
El trazo carretero esta proyectado por la misma ruta actual
con variaciones, en algunos tramos, de orden tcnico; se desarrolla
sobre el actual camino de herradura existente en las laderas de los
cerros y margen izquierda del ro Coaza (aguas arriba) y pasa la
parte de Pampawasi para luego descender hasta la cocota del
riachuelo, para posterior mente ascender de forma constante hasta
dar con la localidad de Chimina para luego mantener la pendiente
variable hasta la localidad de Umachullo.
La superficie de la ruta proyectada tiene un relieve con
pendientes llanas a ligeramente inclinadas llegando a un mximo
en pendiente del 6.5 %, con accidentes topogrficos negativos.
1.1
GEOMORFOLOGIA
Unidades Geomorfolgicas
56
______________________________________________________________________________________________________________
b.
a.
Evaluacin Histrica
De acuerdo a las unidades y sub-unidades descritas la
historia geomorfolgico del tramo Coaza - Umachullo tendra
la siguiente evolucin:
Durante la Era del Paleozoico se depositaron rocas
sedimentarias de ambiente marino: Grupo Ajoyani, a fines del
Mesozoico y en el Terciario inferior fueron instruidos por
soluciones cidas:
Diorita, y a finales del Terciario y principio del
Cuaternario se habra acumulado barros volcnicos: Basalto
Andestico.
Durante la poca del Cuaternario antiguo ocurre la
glaciacin y la desglaciacin respectiva, originando un relleno
del clsico y pizarroso en toda la cuenca tectnica de Coaza
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
57
______________________________________________________________________________________________________________
Unidades Geolgicas
a.
2.
3.
4.
58
______________________________________________________________________________________________________________
b.
c.
d.
Geologa Estructural
Las diferentes unidades geolgicas descritas tienen sus
contactos sellados, es decir, que no indican la existencia de
recientes movimientos de las rocas, en perodos anteriores si
existieron movimientos tectnicos que coadyuvados con las
intrusiones los estratos del Paleozoico fueron afectados, lo
que si es evidente observar los buzamientos de los estratos
que generalmente buzan hacia el Oeste con ngulos de 40 a
50 (C Umachullo), en el C Chimina y Pampawasi existe un
anticlinal con eje axial orientado de Norte a Sur cuyas alas
tienen una inclinacin de moderado a fuerte 45 o y 75 E
debido a los esfuerzos compresionales. La formacin
Umachullo debido a su reciente depositacin tiene estratos
sub. Horizontales, es decir que no esta deformada etipica
mente.
59
______________________________________________________________________________________________________________
Sismicidad Regional
Histricamente en el rea del proyecto no ocurri
sismos que habran destruido edificios ni origin
deslizamientos de tierras, sin embargo, este parmetro tiene
sus manifestaciones en reas fuera del proyecto considerado
como activo e inestable, los cuales son:
Por el lado Este el rea de Macusani - Ollachea con
ocurrencia de sismos y intensidades de IV hasta VII; por el
lado Nor-Oeste en el rea comprendida entre Sicuani Bangui
- Cuzco, es muy activa con ocurrencia de sismos e
intensidades entre V-VIII; por el lado Sur comprende la Costa
del Pacfico desde Arica-Arequipa-Lima, es una rea muy
activa con sismos frecuente e intensidades entre IV-IX; y
finalmente por el lado Sur-Este esta la zona de la Paz Bolivia
con sismos de intensidades entre III-VII.
Estas cuatro reas activas e inestables delimitan al rea
del proyecto y la ausencia de sismos entre las localidades de
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
60
______________________________________________________________________________________________________________
GEOTECNIA DE CIMENTACIONES
Exploraciones
La Jefatura de proyecto y la supervisin de obra han
visto por conveniente realizar calicatas prospectivas con
profundidades de hasta 1.2 m. ubicadas estratgicamente
del cual se obtuvo muestra que fue analizada, de donde se
obtuvo resultado principalmente de la clasificacin SUCS y
propiedades fsicas, los cuales nos han permitido conocer el
tipo de suelo y la apreciacin respectiva y tomar como
cantera para el acopio de material para rellenos.
Tipo de Suelo
Realizado el anlisis granulomtrico se ha clasificado
una variedad de suelos los cuales tienen las siguientes
caractersticas:
61
______________________________________________________________________________________________________________
PROGRESIVAS
CATEGORIA
LONGITUD MTS.
0+000 8+767.40
CLASE
8,767.40
Suelo
Estabilidad de Talud
Dentro del subtramo se encuentran
cerrado como son:
Progresiva
Obras
m.
Complemet.(*)
0+980 4+995
4+995 7600
Inclin. H
Talud
Reposo
zonas de corte
Talud de Relac.
H:V Reposo
63
63
1:2
1:2
a
a
a:
b:
No requiere
c:
d:
TALUD V:H
Roca Fija
Roca Suelta
Conglomerado
Tierra Compacta
Tierra Suelta
Arena
10:1
4:1
3:1
2:1
1:1
1:2
62
______________________________________________________________________________________________________________
UBICACIN
km 22
OBSERVACION
Rellenos, Base y Sub-base
63
______________________________________________________________________________________________________________
Ensayos Realizados:
La cantera indicada ha sido muestreada por los
proyectistas para la determinacin de sus propiedades
mecnicas, fsicas, de acuerdo al uso al que sern destinadas.
Los resultados de los ensayos se indican en los cuadros.
Evaluacin Geotcnica de resultados
Para la ejecucin de la obra se utilizara la cantera de
acuerdo a los resultados obtenidos, con los valores mnimos
exigidos en las especificaciones tcnicas para carreteras del
laboratorio GEOTECNICO.
Canteras para Materiales
Cantera Chimina
a.-
b.-
c.-
d.-
E.-
F.-
g.-
Fuentes de Agua
Se ha considerado una fuente de agua necesaria para la fase
de obra la misma que es:
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
64
______________________________________________________________________________________________________________
RIO ACASIRI
(Mataro Chico)
LIMITE
__________________________________________________________________________________________________________________________________________________________
65
>15
>1-150
>6 como
0.6%
en
______________________________________________________________________________________________________________
IMPACTO AMBIENTAL
INTRODUCCION
-
OBJETIVOS
ANTECEDENTES
SITUACION ACTUAL
EROCION
CENTROS POBLADOS
Impactos en el Usuario
66
______________________________________________________________________________________________________________
2.-
NORMAS DE COMPORTAMIENTO
-
NORMAS INICIALES
Sobre la Vegetacin
De los Trabajadores
De los Componentes
CONCLUSIONES
INTRODUCCION
Objetivos
Con la ejecucin del proyecto: Construccin de la carretera
de Trocha Carrozable de Coaza - Umachullo en su realizacin de
las actividades propias del lugar generaran impactos leves,
medianos y positivos segn al medio al que afecta, para lo cual el
proyecto prev la aplicacin de medidas correctivas para mitigar
efectos negativos y potenciar efectos positivos. Considerando que
el proyecto se refiere a una obra de construccin, donde no habr
muchos cambios en el trazo del alineamiento existente en parte,
se estima que la ocurrencia de impactos ambientales estar
asociada bsicamente al manejo de las reas de uso temporal
67
______________________________________________________________________________________________________________
(patio de acumulacin
maquinarias).
de
materiales
de
construccin
Antecedentes
En vista que la proteccin del medio ambiente en un
proyecto de nivel definitivo requiere de propuestas puntuales, an
tratndose de la construccin de la carretera, por el cual la
revisin del Manual Ambiental para el Dise de Vas del Ministerio
de Transportes nos ha servido de base para las recomendaciones
pertinentes, sobre las cuales se centra el tema actual.
Desde esta ptica es posible aseverar que el dao ambiental
de mayor impacto ya sea producido durante la construccin de la
carretera, aunque un importante impacto positivo ha significado la
integracin de esta regin a la vida econmica del pas. Sin
embargo, es necesario resaltar que no por que sea inevitable
provocar impactos negativos sobre el ambiente, se debe dejar de
construir infraestructura econmica o se debe dejar de usar los
recursos naturales en beneficio del hombre, pues justamente la
responsabilidad del hombre estriba en mitigar los impactos
negativos, hasta alcanzar un punto en que el dao producido sea
nfimo en relacin a los beneficios que se obtendrn, sin perjudicar
el ambiente en alto grado, ni en forma permanente,
apropiadamente los impactos negativos y su mitigacin, adems
de rescatar tambin apropiadamente los positivos.
El camino de herradura actualmente existente discurre por
la cuenca de Tinguri En trminos prcticos de impacto ambiental,
la influencia del ro sobre la carretera no es muy importante,
debido a que no se encuentra cercano a la va.
Desde el punto de vista pluviomtrico, en la zona de Tinguri,
Coaza, ubicada a 3,900 m. s. n. m, la precipitacin media anual
gira en torno a los 720 mm de precipitacin promedio anual con
valores mensuales que oscilan entre los 364 mm, siendo secos en
los meses invernales.
Situacin Actual
El rea en estudio presenta una topografa en su mayora
accidentada, con la presencia de quebradas, lo que hace que este
tramo sea difcil en su desarrollo, presentando ms bien algunos
problemas especialmente por la falta de drenaje y mantenimiento.
Segn la Oficina Nacional de Evaluacin de Recursos
Naturales (ONERN), y el Instituto Nacional de Recursos Naturales
(INRENA), el rea se encuentra en la denominada "Provincia
fisiolgica del Altiplano".
68
______________________________________________________________________________________________________________
69
______________________________________________________________________________________________________________
b.-
c.-
NORMAS DE COMPORTAMIENTO
70
______________________________________________________________________________________________________________
Normas Iniciales
Todas las especificaciones tcnicas contenidas en el
presente tem, debern ser orientacin preferencial para La
Jefatura de Proyecto.
Se optara por otras alternativas, solo cuando estas
signifiquen un mejoramiento ambiental del Proyecto, conocer los
lineamientos ambientales emanados por la DGMA, as como las de
cumplir con todas las leyes, reglamentaciones y dems normas
vigentes emanadas por las diferentes autoridades ambientales.
La Jefatura del Proyecto debe procurar producir el menor
impacto ambiental durante la construccin, sobre los suelos,
cursos de agua, calidad del aire, organismos vivos y comunidades
campesinas. Toda contravencin o acciones de personas que
trabajen en la obra que originen dao ambiental, deben ser de
conocimiento del Inspector de la obra, quien informara a la DGMA.
La Jefatura del Proyecto ser responsable de efectuar las
acciones correctivas apropiadas, a su costo, bajo la supervisin de
los anteriores, sin perjuicio de las sanciones legales a que hubiera
lugar. Los daos a terceros causados por incumplimiento de estas
normas, son de responsabilidad de la Jefatura del Proyecto, quien
deber recuperarlos a su costo.
La Jefatura del proyecto har divulgacin del presente
manual a sus trabajadores, por medio de conferencias y avisos
informativos y preventivos sobre los asuntos ambientales.
Normas Generales para la Jefatura de Proyecto
La Jefatura del Proyecto por su parte deber cumplir con las
siguientes normas durante la construccin, adems de velar por
que las dems se cumplan a cabalidad.
Sobre la Vegetacin:
71
______________________________________________________________________________________________________________
72
______________________________________________________________________________________________________________
73
______________________________________________________________________________________________________________
74
______________________________________________________________________________________________________________
75
______________________________________________________________________________________________________________
Del Campamento:
76
______________________________________________________________________________________________________________
77
______________________________________________________________________________________________________________
ESTUDIO HIDROLOGICO Y
DRENAJE
78
______________________________________________________________________________________________________________
GENERALIDADES
Objetivos
II.-
ESTUDIO DE HIDROLOGA
Caractersticas de las Cuencas hidrogrficas
Metodologa empleada
Aspectos climticos y vegetacin
Anlisis de precipitacin
-
Anlisis de frecuencias
ESTUDIO DE DRENAJE
Drenaje longitudinal
Drenaje transversal
IV.-
CONCLUSIONES Y RECOMENDACIONES
79
______________________________________________________________________________________________________________
GENERALIDADES
Las subcuencas hidrogrficas por donde atraviesa el tramo
de la Carretera Coaza Umachullo son subcuencas pequeas y
con medianas aportaciones al ro Coaza y ro Umachullo.
En estas subcuencas se producen precipitaciones que varan
de medianas a altas entre los meses de Noviembre a Marzo,
llegando a ser considerablemente bajas entre los meses de Abril a
Octubre, en el mejor de los casos.
Se ha obtenido informacin de precipitaciones pluviales
como son densidades mximas en 24 horas
II.
ESTUDIO DE HIDROLOGA
La cuenca Hidrogrfica por donde atraviesa el tramo de la
carretera Coaza
Umachullo se encuentra ubicada en el
Departamento de Puno llamada la Cuenca de Umachullo y Cuenca
de Tinguri conformada por los ros de los mismos nombres y que
ambos ros alimentan al ro Coaza o llamado mas all tambin
Inambari de Carabaya, la que se verifica aproximadamente a 7
Km. al Nor- Oeste de la localidad de Coaza a un altura de 3900
m.s.n.m.
80
______________________________________________________________________________________________________________
B).
C).
81
______________________________________________________________________________________________________________
c)
d)
82
______________________________________________________________________________________________________________
UBICACIN
Latitud
E
387,718.18
AltitudPeriodo de Registro
Longitud
3,900.00
1968 1982
N 8448,382.89
Umachullo
1968 1982
387,718.18
3,900.00
N 8448,382.89
83
______________________________________________________________________________________________________________
X= + K
Donde:
X = Evento mximo del perodo
= Media de la serie de datos
= Desviacin Standard
K = Funcin de la longitud de la serie de datos
ANLISIS DE FRECUENCIA
Este anlisis tiene por objeto determinar la mxima
precipitacin que se espera ocurra en promedio, una vez cada
cierto nmero de aos (perodo de retorno). La determinacin
correcta del perodo de retorno es un aspecto importante del
anlisis. Los criterios bsicos que norman dicha determinacin,
son los siguientes:
Posibles daos
adyacentes.
terrenos
agrcolas
propiedades
FECTOR DE FREC
ESTACION
ESTACION
ker
MACUSANI
84
COAZA
______________________________________________________________________________________________________________
(Aos)
(mm)
(mm)
0.956
40.92
1.681
47.52
2.096
51.30
2.376
53.86
2.599
55.88
3.275
62.05
3.951
68.20
44.87
10
54.21
15
59.56
20
63.16
25
66.03
50
74.74
100
83.44
0.875
ESTACION ESTACION
MACUSANI
UCHUHUMA
(mm/h)
(mm/h)
5
10
15
20
25
50
100
12.43
14.40
15.52
16.28
16.88
18.72
20.55
12.78
15.18
16.56
17.48
18.22
20.46
22.70
CAUDALES DE DISEO
Compatibles con la vida til de las obras que se requieren
disear, las descargas de diseo sern estimadas con el caudal
del perodo de retorno correspondiente, el que estar determinado
por la intensidad mxima horaria previamente calculada con ese
perodo de recurrencia.
De esta forma, el caudal de diseo es calculado mediante la
frmula del Mtodo Racional, cuya expresin es como sigue:
85
______________________________________________________________________________________________________________
Q = 0.278*C*I*A
Donde:
Q = Descarga mxima (m3/seg)
C = Coeficiente de escorrenta que esta en funcin
de las caractersticas geomorfolgicos de las
cuencas.
I = Intensidad mxima horaria (mm/hora)
A = rea de cuenca hidrogrfica (Km2)
En el siguiente cuadro se presentan los Caudales mximos
en (m3/s) para las diferentes Sub-Cuencas que se presentan en la
Cuenca del Ro Coaza y que interceptan a nuestra carretera en
estudio, teniendo en cuenta la influencia de la Intensidad Mxima
Horaria para un perodo de retorno de 50 aos.
CAUDALES MAXIMOS (M3/SEG) CUENCA RO COAZA PARA UN
PERODO RETORNO DE 50 AOS
Nombre de Sub Cuenca
Cerro Chimina
Ubicacin
22+308
Area (Km2)
9.00
Caudal (m3/S)
10.24
Qc> = Qm
Donde:
Qc = Descarga del canal calculada con la frmula de
Manning.
Qm= Caudal mximo del escurrimiento superficial
(aportacin de la Sub-Cuenca).
86
______________________________________________________________________________________________________________
III.
ESTUDIO DE DRENAJE
Para el diseo del drenaje transversal el criterio adoptado es
el de construir Badenes o Tajeas de albailera de piedra,
dependiendo fundamentalmente de su capacidad de resistencia a
la capa de relleno necesaria. Para elevar la subrasante, segn el
diseo geomtrico de la va.
DRENAJE LONGITUDINAL
Para la evaluacin y el control de las aguas pluviales que
puedan afectar la plataforma de la carretera, se ha considerado
las obras de drenaje que se describen a continuacin, a fin de que
las agua que discurran sean evacuadas ya sea por el nivel natural
se drenaje o por un baden o tajea.
A).
CUNETAS DE DRENAJE
De acuerdo a las normas de Carreteras para una
regin lluviosa las dimensiones mnimas son de 1.00 * 0.50
m (profundidad* ancho). Las cunetas se ubicarn a todo lo
largo de la carretera en las zonas de corte. (Ver plano de
detalles).
Los taludes de las cunetas deseadas por la
configuracin topogrfica, generalmente ubicadas en los
puntos de mayor drenaje natural y de su capacidad de
evacuacin del badn o tajea.
Tenindose las condiciones convenientes para el uso
del mtodo de dimensionamiento y espaciamiento por
observacin de Estructura de Drenaje Existente, ya que este
Proyecto es una constriccin de la carretera trocha
carrozable.
C)
ZANJAS DE DRENAJE
87
______________________________________________________________________________________________________________
DRENAJE TRANSVERSAL
El diseo del drenaje transversal contempla la ubicacin de
puntos de pase de las permanentes y eventual que cruzan la va,
la ubicacin y dimensiones de las mismas se han basado en la
observacin de las actuales estructuras cuyo funcionamiento se
considera adecuado.
Se ha considerado el cambio completo de las actuales
estructuras (artesanales) y su reemplazo por nuevas. De acuerdo
al estado de las obras de arte se han proyectado badenes y tajeas.
IV.
CONCLUSIONES Y RECOMENDACIONES
a.-
b.-
c.-
88
______________________________________________________________________________________________________________
CAPITULO III
89
______________________________________________________________________________________________________________
METRADOS
90
______________________________________________________________________________________________________________
Cuadros de Metrados
ndice de Metrados:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
Cuadro
General de Metrados
de metrado de Explanaciones.
de Metrado de Badenes y Tajeas.
General de Metrados
General de Metrados
General de Metrados
General de Metrados
General de Metrados
General de Metrados
General de Metrados
General de Metrados
91
______________________________________________________________________________________________________________
92
______________________________________________________________________________________________________________
93
______________________________________________________________________________________________________________
94
______________________________________________________________________________________________________________
95
______________________________________________________________________________________________________________
96
______________________________________________________________________________________________________________
97
______________________________________________________________________________________________________________
98
______________________________________________________________________________________________________________
99
______________________________________________________________________________________________________________
100
______________________________________________________________________________________________________________
101
______________________________________________________________________________________________________________
102
______________________________________________________________________________________________________________
103
______________________________________________________________________________________________________________
104
______________________________________________________________________________________________________________
105
______________________________________________________________________________________________________________
106
______________________________________________________________________________________________________________
107
______________________________________________________________________________________________________________
108
______________________________________________________________________________________________________________
109
______________________________________________________________________________________________________________
110
______________________________________________________________________________________________________________
ANLISIS DE COSTOS
UNITARIOS
111
______________________________________________________________________________________________________________
112
______________________________________________________________________________________________________________
113
______________________________________________________________________________________________________________
114
______________________________________________________________________________________________________________
115
______________________________________________________________________________________________________________
116
______________________________________________________________________________________________________________
DESAGREGADO DE COSTOS
INDIRECTOS
117
______________________________________________________________________________________________________________
118
______________________________________________________________________________________________________________
119
______________________________________________________________________________________________________________
120
______________________________________________________________________________________________________________
121
______________________________________________________________________________________________________________
CUADRO DE
REQUERIMIENTO DE
MATERIALES
122
______________________________________________________________________________________________________________
123
______________________________________________________________________________________________________________
CUADRO DE MANO DE
OBRA
124
______________________________________________________________________________________________________________
125
______________________________________________________________________________________________________________
CUADRO DE EQUIPOS Y
HERRAMIENTAS
126
______________________________________________________________________________________________________________
127
______________________________________________________________________________________________________________
PRESUPUESTO TOTAL DE
OBRA
128
______________________________________________________________________________________________________________
129
______________________________________________________________________________________________________________
130
______________________________________________________________________________________________________________
CRONOGRAMA DE
EJECUCION
131
______________________________________________________________________________________________________________
132
______________________________________________________________________________________________________________
ESPECIFICACIONES
TECNICAS
133
______________________________________________________________________________________________________________
134
______________________________________________________________________________________________________________
ESPECIFICACIONES TECNICAS
CONSTRUCCIN DE CARRETERA TROCHA CARROZABLE
COAZA UMACHULLO
8 + 767.40 Km.
COAZA CARABAYA PUNO.
CONSIDERACIONES GENERALIDADES
a.-
b.-
c.-
CONSIDERACIONES PARTICULARES
a.-
135
______________________________________________________________________________________________________________
c.-
COMPATIBILIZACIN Y COMPLEMENTOS
El objetivo de las especificaciones tcnicas es dar las pautas
generales a seguirse en cuanto a calidades, procedimientos y acabados
durante la ejecucin de la obra, como complemento de los planos,
memorias y programas de actividades. Todos los materiales debern
cumplir con las normas ITINTEC correspondientes.
El contenido tcnico vertido en el desarrollo de las
especificaciones tcnicas del sistema es compatible con los siguientes
documentos:
136
______________________________________________________________________________________________________________
01.00.00.0
CARTEL DE OBRA
ENLUCIDOS Y MOLDURAS
02.00.00.0
137
______________________________________________________________________________________________________________
02.01.00.00
KM
M2
EXPLANACIONES
02.02.01.0 CORTES
02.02.01.1 CORTE DE MATERIAL SUELTO M3
02.02.01.2 CORTE ROCA SUELTA MANUALMENTE
M3
138
______________________________________________________________________________________________________________
03.01.00.0
PRUEBAS DE CALIDAD
(PROCTOR
FLETES
05.00.00.0OTROS
05.01.00.0
OBRA
05.01.01.0
05.01.01.1
UND
05.01.02.0
05.01.02.1
PLACAS RECORDATORIAS
COLOC DE PLACA DE IDENTIFICACION Y/O RECORDAT
LIMPIEZA DE LA OBRA
LIMPIEZA GENERAL DE OBRA
GLB
CARTEL DE OBRA
GENERALIDADES:
Esta construccin temporal constar de: Cartel de Obra provisional, que
tendr la finalidad de anunciar le topologa de la obra, la cual tendr un
rea de acuerdo a las necesidades que requiera y establezca el presente
proyecto.
139
______________________________________________________________________________________________________________
01.01.00.0
OBRAS PRELIMINARES
140
______________________________________________________________________________________________________________
01.02.00.0
MOVIMIENTO DE TIERRAS
141
______________________________________________________________________________________________________________
DESCRIPCIN:
En est partida se realizar excavaciones en las zonas donde
est proyectado el cimiento corrido de concreto 1:10 + 30%
de piedra grande.
MTODO DE EJECUCIN:
Luego de realizar la limpieza del terreno, se tomar como
referencia un B.M. a partir del cual sern determinados todos
los niveles necesarios durante la ejecucin de la obra.
Seguidamente se proceder a la excavacin manual en
terreno normal de zanjas para el cimiento corrido de una
longitud de 2.20 por un ancho de 0.50 y una profundidad de
0.60 metros.
MTODO DE MEDICIN:
El volumen de la excavacin se obtendr multiplicando el
ancho de la zanja por su altura promedio, luego
multiplicando esta por la longitud excavada. (M3).
01.03.00.0
142
______________________________________________________________________________________________________________
DESCRIPCION
Esta partida comprende la colocacin del acero de refuerzo
en muros. El refuerzo se colocar con precisin y ser de
acero de 3/8 y estribados con aceros de de fierro liso de 1
/4
anclados
en
cada
0.25
metros
y
apoyado
adecuadamente sobre soportes de concreto, que garanticen
el recubrimiento adecuado de las barras de refuerzo.
METODO DE EJECUCION
Las barras de aceros se colocarn antes de ser encofrados
en su posicin indicada en los planos con una tolerancia no
mayor de 1 cm. Todos los cruces de armaduras debern ser
"atortolados" con alambre negro N 16 de manera que en
conjunto formen una "canasta" rgida que impida el
movimiento de las armaduras durante la colocacin y
vibrado del concreto.
METODO DE MEDICION
Se medir en kilogramos (KG)
143
______________________________________________________________________________________________________________
01.04.00.0
144
______________________________________________________________________________________________________________
01.05.00.0
PINTURAS
145
______________________________________________________________________________________________________________
02.00.00.0
GENERALIDADES:
Es la apertura de un tramo en el terreno de un ancho de va para hacer
servicialidad de vehculos motorizados y no motorizados, el cual se
construir en base cortes y rellenos desde el eje trazado para la
carretera.
02.01.00.0
OBRAS PROVISIONALES Y
PORELIMINARES.
Corresponden a todas las construcciones o servicios que se
prevn con caractersticas netamente temporales. Las
cuales debern estar convenientemente ubicadas y/o
inatalasdas.
02.01.01.0 OBRAS PROVISIONALES.
146
______________________________________________________________________________________________________________
DESCRIPCIN:
Se entienden que los Campamentos sern construidos
al inicio de la Obra. El rubro de campamentos esta incluido
en los Costos Indirectos en tal sentido La Jefatura de
Proyecto, deber disponer de facilidades para su personal
(Ingenieros, empleados, obreros) con la provisin de
campamentos, almacenes y talleres adecuado, asimismo de
Oficinas tanto para el Ingeniero como para La Jefatura de
Proyecto.
Los campamentos, almacenes, talleres y oficinas
debern estar provistos de instalaciones elctricas, agua
potable, sanitarios, asimismo con su mobiliario, enseres,
menajes y facilidades necesarias para su funcionamiento y
comodidad de los usuarios.
La ubicacin fsica de los Campamentos, as como la
confeccin de los planos de construccin sern propuestos
por La Jefatura de Proyecto y aprobados por el Ingeniero
antes de su ejecucin.
El campamento se construye con la finalidad de
realizar estancia en el mismo lugar de la obra puesto que al
mismo tiempo servir como almacn y otros servicios de
guardiana, etc.
METODO DE EJECUCIN:
Se instalara al iniciar el trabajo respectivo
correspondiente al proyecto, el mismo que ser
aprovisionado para su traslado cuando se requiera,
conforme va avanzando la obra.
METODO DE MEDICION:
Su medicin se realizar considerando el total del
establecimiento el cual ser en Global (GBL).
147
______________________________________________________________________________________________________________
DESCRIPCIN:
Este trabajo comprende en llevar al terreno lo
plasmado en los planos, respetando las medidas y
ubicaciones de todos los elementos existentes en los planos.
Adems se definirn sus linderos estableciendo las marcas y
seales en forma fija. Los ejes sern fijados en el terreno
mediante estacas, balizas o tarjetas los mismos que estn
siendo colocados en forma progresiva a cada 20 metros
debiendo ser aprobados previamente por el Ingeniero
Inspector.
METODO DE EJECUCIN:
Los alineamientos y gradientes sern dispuestos y
aprobados por el Ingeniero segn el progreso de la obra y
ser localizado para causar el menor inconveniente, que sea
posible, en la prosecucin de la obra, sin afectar la bondad
de la misma.
La Jefatura de Proyecto no efectuar excavacin, ni
colocar otros materiales que puedan causar inconvenientes
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
148
______________________________________________________________________________________________________________
149
______________________________________________________________________________________________________________
a)
Nivelacin
Se considera todos los trabajos topogrficos:
planimtricos y altimtricos, que son necesarios para
hacer el replanteo del proyecto, eventuales ajustes del
mismo, apoyo tcnico permanente y control de
resultados.
El mantenimiento del Brench Marks, plantillas de
cotas, estacas auxiliares de las progresivas, etc. sern
cuidadosamente observados, a fin de asegurar que las
indicaciones de los planos sean llevados fielmente al
terreno y que la obra cumpla una vez concluida, con
los requerimientos y especificaciones del proyecto.
Deber compatibilizarse el nivel piso terminado de
cada una de las zonas teniendo en consideracin la
evacuacin de aguas pluviales, que por gravedad que
deben escurrir hacia lugares donde no altere el trabajo
ni a las vas pblicas.
b)
Trazo
Los ejes debern fijarse permanentemente por estacas
balizas o tarjetas en el terreno, en este ltimo caso
dos tarjetas por eje.
Se seguir para el trazo el siguiente procedimiento:
Se marcarn los ejes y a continuacin las lneas de
ancho de cimentaciones, en armona con los planos de
arquitectura y estructuras estos ejes debern ser
verificados por el Supervisor antes de que se inicie las
excavaciones, los planos de arquitectura explicitan el
nmero de ejes necesarios para efectuar el trabajo.
Los planos de arquitectura indicaran la ubicacin
exacta de los muros y el nmero de ejes necesarios
para efectuar el trabajo.
METODO DE MEDICION:
150
______________________________________________________________________________________________________________
DESCRIPCIN:
Comprende los trabajos de desarmado de aquellos
elementos que debern ser desmontados sin ser daados el
cual deber de ejecutarse manualmente como: estructuras
metlicas o de madera, puertas, ventanas, techos y muros
de adobe, etc.
METODO DE EJECUCIN:
Se llevar a cabo manuales como son los picos, palas,
barreno, etc., con las cuales se remover los elementos
materiales, esta partida abarcar todo el rea de ejecucin
en remocin de la Obra.
METODO DE MEDICION:
Su medicin ser en metros cuadrados (M2).
2.1.2.3
DESCRIPCIN:
151
______________________________________________________________________________________________________________
METODO DE EJECUCIN:
Se llevar a cabo manualmente tanto como las
herramientas de trabajo, esta partida abarcar toda el rea
de bofedales ubicados en el tramo correspondiente.
METODO DE MEDICION:
Su medicin de la roca se realizara por dimetros y
ser ceido en metros cbicos (M3).
02.02.00.0
EXPLANACIONES.
02.02.01.01
152
______________________________________________________________________________________________________________
DESCRIPCIN:
Esta partida consiste en la excavacin y corte de
material clasificado como material comn, segn lo indicado
en los planos del proyecto, y de acuerdo a las instrucciones
del Ingeniero.
METODO DE EJECUCIN:
La Jefatura de Proyecto realizar los trabajos de corte
en material comn, a lo largo de los trazos y niveles
indicados en los planos.
El material excavado que sea til para la construccin
de terraplenes, y conformacin de bermas ser acumulado y
transportado hasta el lugar de su utilizacin.
El material sobrante o de desecho ser eliminado fuera
de los lmites de la plataforma de la carretera, en los
botaderos designados por el Ingeniero.
El material transportado dentro de los 120 metros de
transporte libre, o eliminaciones laterales no ser sujeto de
pago.
Finalmente los taludes y plataformas de corte sern
terminados dentro del proceso de corte, de tal forma que
ningn punto de ella quede por debajo o ms de 5 cm de las
cotas exigidas.
La Jefatura de Proyecto deber tomar todas las
precauciones necesarias contra derrumbes y deslizamientos,
porque de producirse estos, sern de su entera
responsabilidad y no habr ningn pago adicional, tampoco
por sobre-excavacin.
El pago se efectuar al precio unitario del contrato por
m3, entendindose que dicho precio y pago constituir
compensacin total por toda la mano de obra, equipo,
herramienta e imprevistos necesarios para la ejecucin del
trabajo.
El traslado del material excavado a distancias mayores
a los 120 metros del lugar de excavacin que pudiera
ordenar el supervisor, se pagar con la partida de transporte
libre de 120 m.
METODO DE MEDICION:
Su medicin del material de corte se realizara el ancho
de la va por la altura respectiva que conforma el talud ser
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
153
______________________________________________________________________________________________________________
02.02.01.02
DESCRIPCIN:
Esta partida consiste en la realizacin de corte en
material de roca suelta como material poco comn, segn lo
indicado en los planos del proyecto, y de acuerdo a las
instrucciones del Ingeniero.
METODO DE EJECUCIN:
La Jefatura de Proyecto realizar los trabajos de corte
en material roca suelta poco comn a lo largo de los trazos y
niveles indicados en los planos.
El material se acumulara con maquinaria y equipo
pesado por el mismo hecho que las rocas sueltas son de
grandes magnitudes.
Con estas rocas de grandes magnitudes se realizaran
trabajos de colocado y acomodo en lugares denominados
bofedales donde se hallan concentrados reas de humedad.
Para contrarrestar a la humedad se realizara trabajo de
empedrado con roca suelta, el mismo que servir como base
fija y drenaje natural entre sus espacios para luego ser
rellenada con material que predomina en la cantera.
Finalmente se respetaran el ancho va la misma que se
estipula
en captulos
anteriores
de 7.00
metros
respectivamente.
METODO DE MEDICION:
154
______________________________________________________________________________________________________________
02.02.01.03
DESCRIPCIN:
Esta partida consiste en el corte de material con
equipo como son la voladura de rocas, segn lo indicado en
los planos del proyecto, y de acuerdo a las instrucciones del
Ingeniero.
METODO DE EJECUCIN:
La Jefatura de Proyecto realizar los trabajos de corte
en roca fija a lo largo del tramo y a lo largo de los trazos y
niveles que se indica en los planos respectivos.
El material cortado de roca fija mediante voladura de
rocas ser utilizado para la construccin de badenes, tajeas
y muros de contencin.
El material sobrante o de desecho ser eliminado fuera
de los lmites de la plataforma de la carretera.
El material transportado dentro de los 120 metros de
transporte libre, o eliminaciones laterales no ser sujeto de
pago.
La Jefatura de Proyecto deber tomar todas las
precauciones necesarias para evitar destiempo durante la
ejecucin de la obra, realizando de forma adecuada y de
acuerdo a las normas para la voladura de rocas, porque de
producirse estos, sern de su entera responsabilidad y no
habr ningn pago adicional, tampoco por sobre-excavacin.
Para poder determinar el calculo de reas y volmenes
de cortes o rellenos se tiene diversos mtodos, desde lo
manual hasta sofisticado, pudindose calcular en estos
tiempos con gran exactitud.
Los cortes en los terrenos y en trabajos de carreteras
se realiza generalmente con maquinaria pesada y/o en
volmenes proporcionalmente de grandes magnitudes se
155
______________________________________________________________________________________________________________
02.02.02.0 PERFILADO
DESCRIPCIN:
ste trabajo consiste en perfilar y alinear la zona de
corte obedeciendo los taludes, de acuerdo al tipo de
material
predominante
para
evitar
deslizamientos
posteriores debido al corte.
METODO DE EJECUCIN:
Todo trabajo de desquinche se realizara manualmente
obedeciendo ordenes del ingeniero, y de acuerdo a las
pendientes permisibles este tipo de trabajo se realizara con
barretas, picos, etc.
METODO DE MEDICION:
156
______________________________________________________________________________________________________________
02.02.03.0 RELLENOS
Corresponde a trabajos de relleno en tramos donde se
requiera de material apropiado como el lastre. El relleno se
puede realizar con material propio o material de prstamo
puesto que segn el anlisis de cantera en casi todo el
tramo de la carretera predenomina el material llamado
lastre.
DESCRIPCIN:
En tramo donde se haya realizado los cortes seran
aprovechados para los lugares donde se requiera el relleno
con material propio del corte el mismo que conformara el
terrapln de la carretera
Este tem consistir en el empleo de material aprobado
provenientemente de las excavaciones, prstamo de cantera
de acuerdo con estas especificaciones y en conformidad con
las alineaciones, rasantes y dimensiones marcadas en los
planos o en la forma que indique el Ingeniero.
METODO DE EJECUCIN:
El material para este tem ser material seleccionado
de los cortes provenientes de canteras, as como el propio
material obtenido de los excedentes de cortes propios
transportados,
siempre
que
cumplan
con
las
especificaciones del terrapln en el cual dicho material ser
empleado.
El material excavado hmedo y destinado a la
conformacin de terraplenes y rellenos ser utilizado cuando
tenga un contenido de humedad dentro del rango de 2%
de lo ptimo.
Los rellenos debern ser ejecutados en capas de no
ms de 25 cm de espesor, compactado al 95% del Proctor
Modificado en la humedad ptima.
157
______________________________________________________________________________________________________________
METODO DE MEDICION:
El volumen de terraplenes o relleno, aceptado por el
Ingeniero, una vez colocado, compactado y perfilado ser
medido en m3 y estar de acuerdo a las alineaciones,
rasantes y dimensiones indicadas en los planos respectivos,
se medir con la unidad de medida que es el metro cbico.
(M3).
DESCRIPCIN:
Relleno con material de cantera (relleno, conformacin
del terrapln, reposicin de material orgnico).
METODO DE EJECUCIN:
Este tem consistir en el empleo de material aprobado
provenientemente de las excavaciones, prstamo de cantera
de acuerdo con estas especificaciones y en conformidad con
las alineaciones, rasantes y dimensiones marcadas en los
planos o en la forma que indique el Ingeniero.
El material para este tem ser material seleccionado
de los cortes provenientes de canteras, as como el propio
material obtenido de los excedentes de cortes propios
transportados,
siempre
que
cumplan
con
las
especificaciones del terrapln en el cual dicho material ser
empleado.
158
______________________________________________________________________________________________________________
METODO DE MEDICION:
El volumen de terraplenes o relleno, aceptado por el
Ingeniero, una vez colocado, compactado y perfilado ser
medido en m3 y estar de acuerdo a las alineaciones,
rasantes y dimensiones indicadas en los planos respectivos,
se medir con la unidad de medida que es el metro cbico.
(M3).
Descripcin
Esta partida comprende el transporte de las
herramientas, equipos y maquinaria pesada, al lugar de la
obra para su operacin y su salida de la misma una vez
concluidos los trabajos. La movilizacin incluye adems al
final de la obra, la remocin de instalaciones y limpieza del
sitio, as como el retiro de sus instalaciones y equipos.
Asimismo, bajo este tem se considera la instalacin de
equipos estacionarios (plantas de asfalto, chancadoras,
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
159
______________________________________________________________________________________________________________
b) Procedimiento
El traslado por va terrestre del equipo pesado, se
efectuar mediante camiones trayler; el equipo liviano como
(volquetes, cisternas, etc.), lo har por sus propios medios.
En el equipo liviano sern transportadas las herramientas y
todo equipo liviano (martillo neumtico, vibrador, etc.) que
no sea autotransportado.
La Jefatura de Proyecto antes de transportar su equipo
mecnico al sitio de la obra deber someterlo a la inspeccin
del Ministerio o al Ingeniero, con la relacin de las
caractersticas del equipo, como son: marca, modelo, tipo,
capacidad, peso, ao de fabricacin, etc. Tal Inspeccin
deber hacerse dentro de los 30 das despus del
otorgamiento de Buena Pro. Este equipo volver a ser
revisado por el Ingeniero en el sitio de la obra y podr ser
rechazado por ste en caso de no encontrarlo satisfactorio.
La Jefatura de Proyecto no podr retirar equipo alguno
de la obra sin consentimiento escrito del ingeniero. La
desmovilizacin del equipo slo podr realizarse cuando
haya cumplido su labor para el cual fue requerido y con el
consentimiento escrito del Ingeniero.
c) Medicin
El pago por este concepto ser global y en el se
incluir el flete por tonelada de traslado de equipos
transportados y el alquiler del equipo que lo hace por sus
propios medios, durante el tiempo de traslado, as tambin
el montaje y desmontaje de las plantas procesadoras de
material, seguros por el traslado del Equipo e imprevistos
necesarios para completar la movilizacin y desmovilizacin.
d) Pago
El pago se har efectivo hasta el 50% del monto
ofertado por esta partida, cuando los equipos se encuentren
operando en la Obra. El 50% restante se abonar al trmino
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
160
______________________________________________________________________________________________________________
a) Descripcin
PROTECCION DE LA SUBRASANTE
En todo momento las cunetas y drenes al lado de la
subrasante sern mantenidas para drenarlos eficazmente.
Cuando se forman huellas de 5 cm o ms de profundidad, la
subrasante ser restaurada a su rasante y si es necesario
reconformada y recompactada.
En ningn caso se colocar la capa de base, capa de
rodadura o pavimento sobre terreno congelado o lodoso. El
almacenaje sobre la subrasante no ser permitido. Hasta
que la subrasante este verificada y aprobada no se colocar
ninguna capa de base, capa de rodadura o pavimento.
COMPACTACION
Despus de que la subrasante hubiera sido formada
segn el alineamiento, rasante y seccin transversal
correspondiente, deber ser completamente compactada.
La subrasante ser regada uniformemente antes del
aplanado y durante el mismo, a fin de asegurar que se
encuentre con la humedad apropiada.
En tramos donde el material de subrasante este
constituido por suelos arcillosos, limosos, arcillas-limosas y
en general plsticos y comprensible, se emplearan rodillos
pata de cabra, cuyas caractersticas permitan ejercer una
presin no menor de 250 lb/pulg2. en la zona de contacto de
las patas con el suelo y deber estar diseado de modo que
su peso pueda ser aumentado hasta obtener una presin de
hasta 500 lb/pulg2.
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
161
______________________________________________________________________________________________________________
c) Medicin
La preparacin y acondicionamiento de la subrasante
no se medir para pago directo.
d) Pago
El trabajo bajo este tem del contrato no se pagar
directamente, pero ser considerado como obligacin
subsidiaria de La Jefatura de Proyecto cubierta bajo los
precios unitarios para "Excavacin no Clasificada"
162
______________________________________________________________________________________________________________
02.02.00 EXCAVACION
PRESTAMOS
NO
CLASIFICADA
PARA
a) Descripcin
Esta partida contempla la excavacin de una capa de
0.3 m de espesor, sobre las reas que previamente
limpiadas y deforestadas, vayan a recibir sobre su superficie
materiales de relleno para la conformacin de los
terraplenes, se excluyen de esta partida las reas actuales
de va existente, siempre que la misma sea en todo su ancho
y en un espesor mnimo de 0.3 m de material orgnico.
b) Procedimiento
Los trabajos debern efectuarse nicamente en las
zonas que reciban rellenos para la formacin de taludes o
plataforma.
Para la ejecucin de esta partida se emplear el
equipo mecnico considerado en la propuesta de La Jefatura
de Proyecto, los mtodos y procedimientos a seguir sern
tales que garantice la adecuada remocin de la capa en el
espesor indicado.
La disposicin final de este material, considerado que
es altamente orgnico se realizar sobre las superficies
adyacentes en espesores no mayores a 0.15 m o mayores
siempre que se asegure el crecimiento de nueva vegetacin
para salvaguarda la esttica del medio ambiente.
c) Medicin
La unidad de medida de esta partida es el metro
cbico (m3) del trabajo ejecutado segn lo descrito
anteriormente.
d) Pago
El pago se efectuar segn el precio unitario del
contrato por m3, efectuado segn la partida "Corte y
eliminacin de material orgnico" dicho precio y pago
constituir compensacin total por toda la mano de obra,
163
______________________________________________________________________________________________________________
a)
Descripcin
b)
Materiales
c)
Fuentes de materiales
164
______________________________________________________________________________________________________________
0.5%
Mximo
10%
Mximo
d)
Mtodos de construccin
165
______________________________________________________________________________________________________________
e)
Compactacin
f)
Medicin
166
______________________________________________________________________________________________________________
g)
Bases de pago
a) Descripcin
b) Procedimiento
Materiales.- El material para la capa de base de piedra
triturada consistir de partculas duras y durables, o
fragmentos de piedra y un rellenado de arena u otro
material partido en partculas finas. La porcin de material
retenido por el Tamiz N4, ser llamada agregado grueso y
aquella porcin que pasa por el Tamiz N4, ser llamado
agregado fino. Material de tamao excesivo que se haya
encontrado en depsitos de los cuales se obtiene el material
para la capa de base grava, ser retirado por tamizado o
ser triturado, hasta obtener el tamao requerido, segn
elija La Jefatura de Proyecto. No menos de 50% en peso de
las partculas del agregado grueso, deben tener por lo
167
______________________________________________________________________________________________________________
requisitos de
empleando los
REQUISITOS DE GRANULOMETRIA
PORCENTAJE EN PESO QUE PASA LAS SIGUIENTE MALLAS
TAMAO DE LA MALLA
(abertura cuadrada
Gradacin
Gradacin
2 - pulg.
1 - pulg.
3/8 - pulg.
30-65
No4 - (4.76 mm)
25-55
30-60
No10 - (2.00 mm)
15-40
No40 - (0.420 mm)
8-20
No200 - (0.074 mm)
2-8
Gradacin
100
40-75
TIPO 1
Gradacin
100
-75-95
100
50-85 60-100
35-65
20-45
15-30
5-15
-100
50-85
25-50 40-70
15-30 25-45
5-15 8-15
<=
=
6%
25% Mx.
NO
DEBERA
CONTENER
A.A.S.H.O. T-176
30
80
0.5 % Mx.
10 % Mx.
168
MATERIA
______________________________________________________________________________________________________________
169
______________________________________________________________________________________________________________
170
______________________________________________________________________________________________________________
c) Medicin
El mtodo de medicin ser por metros cuadrados
compactados obtenidos del ancho promedio de base de
acuerdo a su espesor, por la longitud, segn lo indicado en
los planos y aceptados por el Ingeniero.
d) Pago
171
______________________________________________________________________________________________________________
04.00.00 TRANSPORTE
DE
MATERIAL
SUB-BASE
a) Descripcin
Esta partida consiste en el transporte pagado de
material desde la cantera hasta los puntos e conformacin
de los rellenos.
El criterio general para las partidas de transporte es
que el esponjamiento del material a transportar est incluido
en los precios unitarios; el carguo y descarguo estn
considerados en las partidas Transporte hasta 1 km (tem
04.01.01 Transporte de material Sub-base hasta 1 km)
Si la distancia de Transporte es mayor de un kilmetro,
el primer kilmetro, el resto se pagar con la partida
Transporte despus de 1 kilmetro.
b) Procedimiento
Los volmenes de material colocados en los rellenos
son determinados en su posicin final utilizando las canteras
respectivas. Las distancias y volmenes sern verificados y
aprobados por el Ingeniero. Para el caso de todo material, la
distancias de transporte sern iguales a las distancias que
corresponde entre el centro de gravedad del material en su
posicin original (cantera) y su posicin final (de cada
kilmetro de material colocado). La distancia de transporte
se medir a lo largo de la ruta ms corta determinada por el
Ingeniero. Si La Jefatura de Proyecto elige transportar por
camino ms largo, los cmputos para el pago se harn con
Alcalde: Prof. Juan ESTRADA ARAUJO / GESTION 2003-2006
172
______________________________________________________________________________________________________________
c) Medicin
El transporte para el movimiento de tierras se pagar
tomando en cuenta el volumen por la distancia de transporte
(m3 x Km).
Este transporte de material incluye el volumen de todo
material colocado para la formacin de terraplenes.
La cantidad de metros cbicos determinados en la
forma descrita anteriormente se pagar al Precio Unitario del
contrato para la partida "04.01.00 Transporte pagado para
una distancia menor o igual a 1 Km" y "04.02.00 Transporte
pagado para distancias mayores a 1 Km" respectivamente,
entendindose que dicho precio constituir compensacin
ntegra por toda mano e obra, equipo, herramientas e
imprevistos
necesarios
para
completar
la
partida
correspondiente.
04.06.00 TRANSPORTE
DESPUES DE 1 KM.
DE
MATERIAL
GRANULAR
a) Descripcin
Esta partida consiste en el transporte pagado de
material desde la cantera hasta los puntos e conformacin
de los rellenos.
El criterio general para las partidas de transporte es
que el esponjamiento del material a transportar est incluido
en los precios unitarios; el carguo y descarguo estn
considerados en las partidas Transporte hasta 1 km (tem
04.05.00 Transporte de material granular hasta 1 km)
173
______________________________________________________________________________________________________________
b) Procedimiento
c) Medicin
174
______________________________________________________________________________________________________________
02.03.00.0
DESCRIPCIN:
METODO DE EJECUCIN:
175
______________________________________________________________________________________________________________
METODO DE MEDICION:
176
______________________________________________________________________________________________________________
c) Medicin
M2
DESCRIPCIN:
METODO DE EJECUCIN:
METODO DE MEDICION:
177
______________________________________________________________________________________________________________
DESCRIPCIN:
METODO DE EJECUCIN:
Las piedras sern escogidas para tal trabajo los mismos que
tendrn las caractersticas de roca fija y de forma plana, el
mismo que dara una estabilidad a la tajea tanto como al
caudal que har pase por la estructura.
178
______________________________________________________________________________________________________________
METODO DE MEDICION:
2.3.2.3
CUNETAS
DESCRIPCIN:
Esta partida comprende la construccin de cunetas de
drenaje excavados en tierra de acuerdo con las presentes
especificaciones y en conformidad con la ubicacin del lado
derecho o izquierdo dependiendo del lado del corte que se
realizara.
METODO DE EJECUCIN:
179
______________________________________________________________________________________________________________
METODO DE MEDICION:
DESCRIPCIN:
METODO DE EJECUCIN:
180
______________________________________________________________________________________________________________
MANTENIMIENTO
a)
Descripcin
181
______________________________________________________________________________________________________________
b)
Medicin
c)
acuerdo
al
Pago
METODO DE MEDICION:
182
______________________________________________________________________________________________________________
03.01.00.0
PRUEBAS DE CALIDAD
04.01.00
03.01.02.2 PRUEBA
MODIFICADO
COMPACTACION
SUELOS
(PROCTOR
DESCRIPCIN:
183
______________________________________________________________________________________________________________
METODO DE EJECUCIN:
Medicin.-
184
______________________________________________________________________________________________________________
METODO DE MEDICION:
04.01.00.0
FLETES
04.01.01.1 TRANSPORTE
(ALMACEN)VJE
DE
MAT
185
DE
CONST
JULIACA-COAZA
______________________________________________________________________________________________________________
04.01.01.2 TRANSPORTE
M3/DIA
VJE
DE
AGREGADOS
LA
OBRA
R=24
DESCRIPCIN:
METODO DE EJECUCIN:
METODO DE MEDICION
186
______________________________________________________________________________________________________________
DESCRIPCIN:
METODO DE EJECUCIN:
METODO DE MEDICION
PARTIDA COMPLEMENTARIA
METODO DE EJECUCIN:
187
______________________________________________________________________________________________________________
05.00.00.0OTROS
05.01.00.0
OBRA
188
______________________________________________________________________________________________________________
DESCRIPCIN:
METODO DE EJECUCIN:
METODO DE MEDICION
189
______________________________________________________________________________________________________________
03.01.00.0
PRUEBAS DE CALIDAD
190
______________________________________________________________________________________________________________
CONCRETO
DESCRIPCIN:
Esta partida consiste en la aplicacin de pintura sobre el
cielo raso del aula.
METODO DE EJECUCIN:
191
______________________________________________________________________________________________________________
ITINTEC 400.002
ITINTEC 339.036
ITINTEC 339.044
OBJETO
La presente norma establece un procedimiento para la
elaboracin y curado de probetas cilndricas de hormign en
obra
APARATOS
-
192
______________________________________________________________________________________________________________
193
______________________________________________________________________________________________________________
194
______________________________________________________________________________________________________________
195
______________________________________________________________________________________________________________
04.00.00.0
FLETES
GENERLIDADES:
Este rubro refiere al flete de transporte terrestre el mismo que involucra
costear el desgaste de herramienta y/o equipo que se realiza en la obra,
ya sea para el traslado de materiales, supervisin y otros.
04.01.00.0
FLETES TERRESTRES
DE
DESCRIPCIN:
Esta partida consiste en considerar el costo de transporte de
los materiales de construccin trasladados hasta el almacn.
METODO DE EJECUCIN:
196
______________________________________________________________________________________________________________
197
______________________________________________________________________________________________________________
MATERIALES
DE
CONSTRUCCION
DESCRIPCIN:
Esta partida consiste en transportar los materiales de
construccin requeridos en obra la cual se realizara desde el
almacn a la obra.
METODO DE EJECUCIN:
El trasporte de los materiales de construccin se realiza
mediante la movilidad propia de la entidad ejecutora o
mediante el alquiler particular del trasporte, transporte que
realizara desde la ciudad de Juliaca.
METODO DE MEDICION
Se medir por viajes (VJE)
04.01.01.5 TRANSPORTE DE VARIOS
DESCRIPCIN:
De manera general comprende la movilizacin y el traslado
del personal (Residente-Supervisor), y otros al lugar de la
obra.
METODO DE EJECUCIN:
Se utilizar el transporte terrestre para el traslado del
personal responsable de obra, supervisor de obra,
fiscalizadores de obra y otros para la buena marcha de la
obra, Tambin ser necesario el transporte terrestre para el
traslado de equipos y/o herramientas respectivamente.
198
______________________________________________________________________________________________________________
METODO DE MEDICION
Se medir en metro cbico (M3)
05.00.00.0
OTROS
GENERLIDADES:
Se realizara como trabajos complementarios como el colocado o el
membretado de la identificacin de la obra.
05.01.00.0
OBRA
DE
IDENTIFICACION
Y/O
DESCRIPCIN:
Consiste en la colocacin de la placa de identificacin para
identificar a la gestin a quien corresponde su ejecucin o la
que ejecuta la obra, el cual es de material de fierro fundido.
METODO DE EJECUCIN
La colocacin se har al finalizar la obra con anclajes
en el muro y concreto, que pueda asegurar su permanencia
199
______________________________________________________________________________________________________________
200
______________________________________________________________________________________________________________
PLANOS
201
______________________________________________________________________________________________________________
ndice de Planos :
1.
LEVANTAMIENTO TOPOGTAFICO:
2.
Plano Topogrfico.
Plano de Ubicacin.
PERFILES Y CORTES:
3.
Planimetra
PP - 01
Plano en Planta.
Plano de Cortes.
Plano de detalles
: D - 01
Plano de estructuras.
Plano de detalles
202
______________________________________________________________________________________________________________
PANEL FOTOGRAFICO
203
______________________________________________________________________________________________________________
204
______________________________________________________________________________________________________________
205
______________________________________________________________________________________________________________
ANEXOS
206
______________________________________________________________________________________________________________
Fuente: Anexo N 10
Datos Generales: Distrito
Distrito: COASA
Provincia: CARABAYA
Departamento: PUNO
Dispositivo de Creacin:
Nro. del Dispositivo de Creacin:
Fecha de Creacin: EPOCA INDEP.
Capital: COASA
Altura capital(m.s.n.m.) 3783
Proyeccin de Poblacin al 2002: 8687
Superficie: (Km2) 3572,92
Densidad de Poblacin (Hab/Km2): 2,4
Nombre del alcalde: Prof. ESTRADA ARAUJO, JUAN
Direccin: CALLE GRAU S/N
207
______________________________________________________________________________________________________________
Nombre
Area
Categoria
Viviendas
COASA
URBANO
PUEBLO
654
BENDITANI
RURAL
ANEXO
25
SANTO DOMINGO
RURAL
CAMPO MINERO
HUARACHANI
RURAL
OTROS
30
TAQUIPALCA
RURAL
ANEXO
20
UMACHULLO
RURAL
ANEXO
60
CHIMINA
RURAL
UNID.AGROPECUARIA
HUAYLLATIRA
RURAL
UNID.AGROPECUARIA
PUENTE MACEDO
RURAL
ANEXO
AYUSUMA
RURAL
OTROS
120
CAYANDIA
RURAL
ANEXO
55
TOTORANI
RURAL
UNID.AGROPECUARIA
ANCOCALANI
RURAL
ANEXO
10
PATA QUITUN
RURAL
OTROS
20
SACO
RURAL
OTROS
120
CUTICARCA
RURAL
ANEXO
28
CAPITANA
RURAL
OTROS
25
UCHUHUMA
RURAL
OTROS
85
INCUYO
RURAL
UNID.AGROPECUARIA
ANANA
RURAL
OTROS
50
HUANCHICANI
RURAL
CAMPO MINERO
MEDIA LUNA
RURAL
CAMPO MINERO
DRAGAPAMPA
RURAL
CAMPO MINERO
10
HUANACURI
RURAL
CAMPO MINERO
LAHUAMANI
RURAL
ANEXO
25
208
______________________________________________________________________________________________________________
RURAL
OTROS
90
CHAMACTIRA (CCASA)
RURAL
OTROS
LLUCHANE
RURAL
ANEXO
UMI-A (HUAYTALLATAIRE)
RURAL
UNID.AGROPECUARIA
15
PAMPAHUASI
RURAL
ANEXO
15
CCOLLPACCUCHO
RURAL
UNID.AGROPECUARIA
15
CAYRA-A (CCAYRANI)
RURAL
ANEXO
40
LAPUICANA
RURAL
UNID.AGROPECUARIA
MACHO BENDITANI
RURAL
ANEXO
10
SACHAPATA
RURAL
ANEXO
10
TAHUANA
RURAL
OTROS
70
CHINGO
RURAL
UNID.AGROPECUARIA
35
PUTUPATA
RURAL
ANEXO
HUARMITIRA
RURAL
UNID.AGROPECUARIA
RURAL
BARRIO O CUARTEL
30
PACOPACUNI
RURAL
UNID.AGROPECUARIA
18
ESQUENA
RURAL
OTROS
180
MOROCCOTA
RURAL
ANEXO
15
UMACHINQUINI
RURAL
ANEXO
30
AMAYANI
RURAL
ANEXO
23
USCURI
RURAL
ANEXO
OROYA
RURAL
CAMPO MINERO
10
CHABUCA
RURAL
CAMPO MINERO
30
PUCANA (LEQUELEQUENE)
RURAL
UNID.AGROPECUARIA
CHACAMARCA
RURAL
ANEXO
42
02.02.00.00
EXPLANACIONES
209
______________________________________________________________________________________________________________
02.02.01.00
CORTES
PLANOS
210
______________________________________________________________________________________________________________
ndice de Planos :
Listado de Planos Adjuntados
4.
5.
.
Km: 0+000 Km: 1+000
Km: 1+000 Km: 2+000
Km: 2+000 Km: 3+000
Km: 3+000 Km: 4+000
Km: 4+000 Km: 5+000
Km: 5+000 Km: 6+000
Km: 6+000 Km: 7+000
Km: 7+000 Km: 8+000
Km: 8+000 Km: 9+000
Km: 9+000 Km: 9+452.42
211
______________________________________________________________________________________________________________
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST - 01
Secciones
ST 01
6.
:P
7.
:P
212
______________________________________________________________________________________________________________
ENSAYOS EN LABORATORIO
213
______________________________________________________________________________________________________________
214
______________________________________________________________________________________________________________
215
______________________________________________________________________________________________________________
216
______________________________________________________________________________________________________________
217
______________________________________________________________________________________________________________
218
______________________________________________________________________________________________________________
219
______________________________________________________________________________________________________________
220
______________________________________________________________________________________________________________
221
______________________________________________________________________________________________________________
222
______________________________________________________________________________________________________________
223
______________________________________________________________________________________________________________
224
______________________________________________________________________________________________________________
225
______________________________________________________________________________________________________________
226
______________________________________________________________________________________________________________
227
______________________________________________________________________________________________________________
228
______________________________________________________________________________________________________________
229
______________________________________________________________________________________________________________
230
______________________________________________________________________________________________________________
231
______________________________________________________________________________________________________________
232
______________________________________________________________________________________________________________
233
______________________________________________________________________________________________________________
234
______________________________________________________________________________________________________________
235
______________________________________________________________________________________________________________
PANEL DE FOTOGRAFIAS
01
02
03
04
05
CARTEL DE OBRA
TROCHA CARROZABLE
ENSAYOS DE CAMPO Y LABORATORIO
FLETE TERRESTRE
OTROS
MONTO PRESUPUESTO
254,843.16
SON :
DOSCIENTOS CINCUENTICUATRO MIL OCHOCIENTOS CUARENTITRES Y 16/100
MATERIALES
16,578.11
MANO DE OBRA
82,149.58
EQUIPOS
142,040.63
COSTO DIRECTO
GASTOS GENERALES
GASTOS DE LIQUIDACION
GASTOS DE SUPERVISION
PRESUPUESTO TOTAL DEL PROYECTO
TOTAL PRESUPUESTO
Nota : Los costos unitarios sin I.G.V. son vigentes al :
04/04/2005
236
S/.
S/.
S/.
S/.
______________________________________________________________________________________________________________
237
______________________________________________________________________________________________________________
238
______________________________________________________________________________________________________________
239
______________________________________________________________________________________________________________
240
______________________________________________________________________________________________________________
241
______________________________________________________________________________________________________________
242
______________________________________________________________________________________________________________
243
______________________________________________________________________________________________________________
244
______________________________________________________________________________________________________________
245
______________________________________________________________________________________________________________
246
______________________________________________________________________________________________________________
247
______________________________________________________________________________________________________________
248
______________________________________________________________________________________________________________
249
______________________________________________________________________________________________________________
250
______________________________________________________________________________________________________________
251
______________________________________________________________________________________________________________
252
______________________________________________________________________________________________________________
253
______________________________________________________________________________________________________________
254
______________________________________________________________________________________________________________
255
______________________________________________________________________________________________________________
256
______________________________________________________________________________________________________________
257
______________________________________________________________________________________________________________
258
______________________________________________________________________________________________________________
PANEL DE FOTOGRAFIAS
259
______________________________________________________________________________________________________________
260