Beruflich Dokumente
Kultur Dokumente
STARTUP POWER
BHARTIYA RAIL BIJLEE COMPANY LIMITED
(BRBCL)
NABINAGAR, AURANGABAD (BIHAR)
i.
ii.
iii.
iv.
CONTENTS
Certificate
Acknowledgement
Declaration
NABINAGAR THERMAL POWER PLANT (NTPP)
1) Introduction
2) Construction power Single line diagram(SLD)
3) Construction power Sub-station
a) Metering Transformer
b) Isolator
c) PT(Potential/voltage transformer)
d) VCB(Vacuum Circuit Breaker)
e) CT(Current transformer)
f) Power transformer
i. Core
ii.
Winding
vi.
Breather
iii.
iv.
v.
Tap changer
Conservator
OTI & WTI
vii.
Cooling Tubes(Radiator)
viii.
Buchholz relay
ix. Explosion Vent
g) Capacitor Bank(50KVAR each)
4) Control room
a) Main incomer
b) Outgoing feeder
c) BPT(Bus potential transformer)
d) Outdoor capacitor bank
e) Bus coupler
f) VCB
g) DC Source and its charger
5) Ringmain(11 KV)
a) Single-pole
PAGE 1
b)
c)
d)
e)
f)
2-pole
3-pole
4-pole
Over/under ground cable
GOAB
g) Guard wire
6) Distribution transformer
a) Specifications
b) Performance
c) Distribution Board
d) Capacitor bank
9) SWITCHYARD
a) SURGE ARRESTER
b) CAPACITOR VOLTAGE TRANSFORMER (CVT)
c) POWER LINE CARRIER COMMUNICATION (PLCC) WAVE TRAP
d) CURRENT TRANSFORMER (CT)
e) EARTHING SWITCH
f) SINGLE BREAK ISOLATOR
g) BUS-BAR
h) CIRCUIT BREAKER (CB)
i) INTER-CONNECTING TRANSFORMER (ICT)
j) MISCELLANEOUS SERVICE TRANSFORMER (MST)
10) STATION TRANSFORMER (ST)
11) SWITCH GEAR
A) SA/SB
B) UA/UB
12) DIESEL GENERATOR (DG)
PAGE 2
PAGE 3
LOCATION
The project site is situated on a State highway which is 25 km south of NH2 from Barun, 9 km from Nabinagar Road Railway Station and 100 km
from Gaya Airport.
INPUTS
Water requirement for the project is 60 cusec which is allocated from the
upper stream of the Sone River (Indrapuri Barrage). Coal requirement for
the project is 5 MTPA. The coal linkage of 5 MTPA has been accorded from
Pachra & Pachra south block, North Karanpura Coalfield of Central
Coalfields Limited (CCL) which is approx. 215km from the project site.
BENEFICIARIES
The beneficiaries for the power generated from NTPP are : Indian Railways
- 90 % and Bihar State - 10 %. PPA has been signed with both of the
beneficiaries.
INSTALLED CAPACITY
Unit
Date of Commissioning
2016 March
status
250
Commissioned [5]
250
Under Erection
250
Under Erection
250
Under Erection
PAGE 4
Since, the plant is under construction so, it needs power from outside source
(Badem grid) to run electrical construction tools and equipment which are
utilized in building different sites (erection). Electrical equipment such as
welding machines, cutting machines, electric blowers etc. requires electric
power. This electric power is feed to the equipment through different
Distribution transformers (11/0.415KV). These distribution transformers
are fed from the Ringmain (11KV).This ringmain is energised from a
control room having two incomers, both from Sub-station (33/11KV)
located beside the control room . This system is composed of different
apparatus and arrangements for proper distribution and Keeping safety all
above.
Ring main here doesnt form a complete ring. The two incomers are
connected through a bus coupler placed at control room. If any of the
supply from any of the incomer is interrupted then the bus coupler is
switched on and the supply from one of the incomer (Charged) is connected
to the bus through the bus coupler and if both the incomers are charged then
the bus coupler is kept in off position. This way the 11kv ring main is
always kept charged.
PAGE 5
word substation comes from the day before the distribution system becomes
grid. On the basis of types this sub-station can be put in distribution type
sub-stations category. The function of this sub-station system is designed in
such a way that whenever a fault occurs, it isolates the faulted system from
sensitive or vulnerable devices. De-energizing faulted equipment protects it
from further damage, and isolating a fault helps keep the rest of the electric
grid operating with stability. For isolation of the 4MVA power transformer
different techniques and circuit breakers (CB) are used such as VCB, over
current trip relay, Isolator switchesetc. This sub-station also have 2
capacitor banks to maintain the power factor of the supply which is
disturbed by loads (Inductive loads mainly).
b: Isolator Switch
The circuit breaker always trip the circuit but open contact of breaker cannot
be visible physically from outside of the breaker and that is why it is
recommended
Not to touch any electrical circuit or equipment just by switching off the
circuit breaker. So for better safety there is an arrangement at this substation
so that one can see open condition of the section of the circuit breaker
before touching it. Isolator is basically a mechanical switch which isolates a
part of circuit from system as when required. Electrical isolator separates a
part of the system from rest for safe maintenance works. Isolator is a
manually operated mechanical switch which separates a part of electrical
power system normally at off load condition. In construction power sub-
PAGE 7
station Double Break isolator are used. These have three stacks of post
insulator carries a tubular or flat male contact which can be rotated
horizontally with rotation of central post insulator. This rod type contact is called
moving contact. The female types of contacts are fixed on the top of the other post
insulators which fitted at both sides of the central post insulator. Rotation of the central
post is done by a driving lever mechanism at the base of the post insulator and it
connected to operating handle of the isolator through a mechanical tie rod which is hand
operated.
c: Potential transformer
Potential transformer or
voltage transformer gets used
in electrical power system for
stepping down the system
voltage to a safe value which
can be fed to low ratings
meters and relays.
Commercially available relays
and meters used for protection
and metering, are designed for
low voltage. This is a simplest
form of potential
transformer. A voltage transformer theory or potential transformer
theory is just like a theory of general purpose step down transformer.
Primary of this transformer is connected across the phase and ground.
Just like the transformer used for stepping down purpose, potential
transformer i.e. PT has lower turns winding at its secondary.
phase angle between primary and secondary voltages. The errors in potential
transformer or voltage transformer can be best explained by phasor diagram,
and this is the main part of potential transformer
A vacuum circuit
breaker is such kind of
circuit breaker where the
arc quenching takes
place in vacuum. The
technology is suitable for
mainly medium voltage
application. For higher
voltage vacuum
technology has been
developed but not
commercially viable.
Vacuum offers the
highest insulating strength. So it has far superior arc quenching properties
than any medium. For example, when contacts of a breaker are opened in
vacuum, the interruption occurs at first current zero with dielectric strength
between the contacts building up at a rate thousands of times higher than that
obtained with other circuit breakers. When the contacts of the breaker are
opened in vacuum (10^-7 to 10^-5 torr), an arc is produced between the
contacts by the ionisation of metal vapours of contacts. However, the arc is
quickly extinguished because the metallic vapours, electrons and ions
produced during arc rapidly condense on the surfaces of the circuit breaker
contacts, resulting in quick recovery of dielectric strength.
Service life of vacuum circuit breaker is much longer than other types of
circuit breakers. There is no chance of fire hazard as oil circuit breaker. It is
much environment friendly than SF6 Circuit breaker. Beside of that
contraction of VCB is much user friendly. Replacement of vacuum
interrupter (VI) is much convenient.
e: Current Transformer(CT)
A CT is an instrument transformer in which the secondary current is
substantially proportional to primary current and differs in phase from it by
ideally zero degree. A CT is similar to a electrical power transformer to
some extent, but there are some difference in construction and operation
principle. For metering and indication purpose, accuracy of ratio, between
primary and secondary currents are essential within normal working range.
Normally accuracy of current transformer required up to 125% of rated
current; as because allowable system current must be below 125% of rated
current.
PAGE 10
Rather it is desirable
the CT core to be
saturated after this
limit since the
unnecessary
electrical stresses due
to system over
current can be
prevented from the
metering instrument
connected to the
secondary of the CT
as secondary current
does not go above a desired limit even primary current of the CT rises to a
very high value than its ratings. So accuracy within working range is main
criteria of a CT used for metering purpose. The degree of accuracy of a
metering CT is expressed by CT accuracy class or simply current
transformer class or CT class.
But in the case of protection, the CT may not have the accuracy level as
good as metering CT although it is desired not to be saturated during high
fault current passes through primary. So core of protection CT is so designed
that it would not be saturated for long range of currents. If saturation of the
core comes at lower level of primary current the proper reflection of primary
current will not come to secondary, hence relays connected to the secondary
may not function properly and protection system losses its
reliability.Suppose, you have one CT with current ratio 400/1 A and its
protection core is situated at 500 A. If the primary current of the CT
becomes 1000 A the secondary current will still be 1.25 A as because the
secondary current will not increase after 1.25 A because of saturation. If
actuating current of the relay connected the secondary circuit of the CT is
1.5 A, it will not be operated at all even fault level of the power circuit is
1000 A. The degree of accuracy of a protection CT may not be as fine as
metering CT but it is also expressed by CT accuracy class or simply
current transformer class or CT class as in the case of metering current
transformer but in little bit different manner.
PAGE 11
f: Power transformer
The power transformer used for construction power is a 4MVA step down
transformer having rated voltage level 33/11 KV. It is ONAN cooling type
transformer. Like other power transformer it is used for
the transmission purpose at heavy load, high voltage 33 KV & 100%
efficiency. It also having a big in size as compare to distribution
transformer, it used in generating station and Transmission substation .high
insulation level.
Power transformers are used for transmission as a step up devices so that
the I2r loss can be minimized for a given power flow. These transformers
are designed to utilize the core to maximum and will operate very much
PAGE 12
near to the knee point of B-H curve (slightly above the knee point
value).This brings down the mass of the core enormously.
Naturally these transformers have the matched iron losses and copper
losses at peak load (i.e. the maximum efficiency point where both the
losses match).
PAGE 13
(ii): Windings
PAGE 15
To minimize the number of winding taps and thus reduce the physical size of
a tap changing transformer, a 'reversing' tap changer winding may be used,
which is a portion of the main winding able to be connected in its opposite
direction (buck) and thus oppose the voltage.
There are mainly two types of tap changer:
1-No-Load Tap Changer (NLTC), off-circuit tap changer (OCTC) , orDeEnergized Tap Changer (DETC)
2- On circuit tap changer or On Load Tap Changer (OLTC)
PAGE 16
(iv): Conservator
When transformer is loaded and when ambient temperature rises, the volume
of oil inside transformer increases. A conservator tank of transformer
provides adequate space to this expanded transformer oil. It also acts as a
reservoir for transformer insulating oil. When volume of transformer
insulating oil increases due to load and ambient temperature, the vacant
space above the oil level inside the conservator is partially occupied by the
expanded oil. Consequently, corresponding quantity of air of that space is
pushed away through breather. On other hand, when load of transformer
decreases, the transformer is switched off and when the ambient temperature
decreases, the oil inside the transformer contracts. This causes outside air to
enter in the conservator tank of transformer through silica gel breather.
The Conservator is a cylindrical component of the transformer. The
conservator is located at the top of the transformer. The Conservator is
designed to act as a reservoir for the transformer oil. The level of the oil in
the transformer can rise and fall due to temperature. The increase of
temperature can be caused either by a rise in ambient temperature or due to
increased load on the transformer.
PAGE 17
In this way the value of the winding temperature indicated by the instrument
will be equal to the one planned by the transformer manufacturer for a given
transformer load.
(vi): Breather
in the oil sealing cup acts as barrier between silica gel crystal and air when
there is no flow of air through silica gel breather. The colour of silica gel
crystal is dark blue but, when it absorbs moisture; it becomes pink.
Under loaded condition, warm oil increases in volume and comes to the
upper portion of the main tank. Then this oil enters in the radiator through
top valve and cools down by dissipating heat through the thin radiator wall.
This cold oil comes back to the main tank through the bottom radiator valve.
This cycle is repeated continuously till the load is connected to the
transformer. Dissipation of heat in the transformer radiator; can be
accelerated further by force air provided by means of fans. These fans are
fitted either on the radiator bank itself or fitted nearby the bank but all the
fans must be faced towards the radiator. Sometime, the cooling rate of
PAGE 20
convectional circulation of oil is not sufficient. That time an oil pump may
be used for speeding up oil circulation.
Buchholz relay in
transformer is an oil
container housed the
connecting pipe from
main tank to conservator
tank. It has mainly two
elements. The upper
element consists of a float.
The float is attached to a
hinge in such a way that it
can move up and down depending upon the oil level in the Buchholz relay
Container. One mercury switch is fixed on the float. The alignment of
mercury switch hence depends upon the position of the float. The lower
element consists of a baffle plate and mercury switch. This plate is fitted on
a hinge just in front of the inlet (main tank side) of Buchholz relay in
transformer in such a way that when oil enters in the relay from that inlet in
high pressure the alignment of the baffle plate along with the mercury switch
attached to it, will change. The Buchholz relay operation may be actuated
without any fault in the transformer. For instance, when oil is added to a
transformer, air may get in together with oil, accumulated under the relay
cover and thus cause a false Buchholz relay operation. That is why
mechanical lock is provided in that relay so that one can lock the movement
of mercury switches when oil is topping up in the transformer. This
mechanical locking also helps to prevent unnecessary movement of
breakable glass bulb of mercury switches during transportation of the
Buchholz relays.
PAGE 21
The lower float may also falsely operate if the oil velocity in the connection
pipe through, not due to internal fault, is sufficient to trip over the float. This
can occurs in the event of external short circuit when over currents flowing
through the winding cause overheated the copper and the oil and cause the
oil to expand.
PAGE 22
(x): Bushings
In electric power, a bushing is an insulated device that allows an electrical
conductor to pass safely through
a (usually) earthed conducting
barrier such as the wall of a
transformer or circuit breaker.
All materials carrying an electric
charge generate an electric field.
When an energized conductor is
near any material at earth
potential, it can cause very high
field strengths to be formed,
especially where the field lines are forced to curve sharply around the
earthed material. The bushing controls the shape and strength of the field
and reduces the electrical stresses in the insulating material. A basic
porcelain bushing is a hollow porcelain shape that fits through a hole in a
wall or metal case, allowing a conductor to pass through its centre, and
connect at both ends to other equipment. Bushings of this type are often
made of wet-process fired porcelain, which is then glazed. A semiconducting glaze may be used to assist in equalizing the electrical potential
gradient along the length of the bushing.
The design of any electrical bushing must ensure that the electrical strength
of the insulated material is able to withstand the penetrating 'electrical
energy' passing through the conductor, via any highly stressed areas. It must
also be capable of enduring, occasional and exceptional high voltage
moments as well as the normal continual service withstand voltage, as it is
the voltage that directs and controls the development of leakage paths and
not current.
PAGE 23
g: Capacitor Bank
PAGE 24
3: Control Room
PAGE 25
PAGE 26
PAGE 27
Unlike PT which measure incoming line voltage and protect line under
voltage protection 88% of voltage, Bus PT measures outgoing bus voltage
and protect bus under voltage with voltage protection 44% with time delay
3-5 sec, Like PT the BPT is used to step down voltage at measurement levels
for instrument transformer for measurement and relay feeding.
d: Outdoor Capacitor Bank
The outdoor capacitor bank is used to maintain the power factor of the load
side voltage and current. Due to inductive loads like welding machine,
blowers etc. when used at a time then the power factor of the system
decreases to around 7-8.5 to which causes losses and improper functioning
of the devices.
PAGE 28
e: Bus Coupler
feeder to associated bus. Both of the buses are energized and total feeders
are divided into two groups, one group is fed from one bus and other from
other bus. But any feeder at any time can be transferred from one bus to
other. There is one bus coupler breaker which should be kept close during
bus transfer operation. For transfer operation, one should first close the bus
coupler circuit breaker then close the isolator associated with the bus to
where the feeder would be transferred and then open the isolator associated
with the bus from where feeder is transferred. Lastly after this transfer
operation he or she should open the bus coupler breaker.
f: VCB (Vacuum Circuit Breaker)
hot spot. As it is vacuum, the metal on the contact surface is easily vaporized
due to that hot spot and create a conducting media for arc path. Then the arc
will be initiated and continued until the next current zero.
PAGE 31
Ideally, the ring circuit acts like two radial circuits proceeding in opposite
directions around the ring, the dividing point between them dependent on the
distribution of load in the ring. If the load is evenly split across the two
directions, the current in each direction is half of the total, allowing the use
of wire with half the current-carrying capacity. In practice, the load does not
PAGE 32
always split evenly, so thicker wire is used. The ring main at BRBCL for
construction power is of 11KV which is charged at two terminals coming
from the sub-station. This ring main doesnt form a complete ring.
PAGE 33
c: Triple Pole
PAGE 34
e: Underground Cable
Air Break Switches designed to isolate a circuit. They are usually employed
in outdoor installations. Special Arcing Horns are provided to quench the
arc which occurs when the current is interrupted. Their operation can also
PAGE 35
be mechanised it Break
Switches can be mounted
both horizontally and
vertically. Air Break
Switches are usually found in
groups of three, one for each
phase. These groups are
opened together. Hence, they
are also known as gang-operated switches. A breaker is a switching device
that operates automatically and is specifically intended to interrupt short
circuit currents (in addition to ordinary load currents). Circuit breakers can
be designed using air, oil, vacuum, or SF6 gas as the dielectric. Circuit
breakers are only found in substations.
g: Guard wire
Guard wire is used to protect the overhead live cables from falling on
machines or human due to some fault or melting of wire. This is generally
used over crossings or streets where there is possibility of presence of
humans or machines all the time under the cables.
PAGE 36
5: Distribution Transformer
Distribution transformers are used
for lower voltage distribution
networks as a means to end user
connectivity. (11kV, 6.6 kV, 3.3 kV,
440V, 230V). The distribution
transformer used at BRBCL for
construction power distribution is of
500KVA having voltage level of
11/0.415 KV. There are 16 total
distribution transformer installed in
BRBCL for construction power
distribution to step down 11kv to
0.415 kv.
Rating
Cooling
Type
Voltage Ratio
Frequency
: 500 KVA
: ONAN
: Two (2) winding
: HV- 11KV
LV -0.415 KV
: 50 Hz
PAGE 37
vii) Phases
: 3 phase
viii) % Impedance HV/LV : 4.5%
ix) Tap control
: Offcircuit
x)
Service
: Outdoor
xi) Duty
:
Continuous
xii) Vector group
: Dyn1
c: Distribution Board
A distribution board( also known
as panel board, breaker panel, or
electric panel) is a component of an
electricity supply system that
divides an electric power feed into
subsidiary circuits while providing
a protective fuse or circuit breaker
for each circuit in a common
enclosure. Normally, a main
switch, and in recent boards, one or
more residual-current devices
(RCD) or residual current breakers
with over current protection
(RCBO), are also incorporated. In
BRBCL these above shown
distribution boards are used in
construction power distribution
transformer substation for distributing the stepped down voltage (0.415 KV)
to near area for electrical equipments used for construction.
PAGE 38
d: Capacitor Bank
PAGE 39
There are many machines in the plant which needs to be running and many
heavy machines and equipment which needs to be tested before and after
their erection, which need hell lot of power and cant be provided from
BSEB. For keeping the main bus charged for further testing and running of
Auxiliary systems of the power plant we need heavy power which is
provided by Pusauli grid. After the production of plant get started, the 90%
of the power generated will be given to the same Pusauli grid from where it
will be utilized by Indian railways for their various projects and supply in
states like west Bengal, Jharkhand, Orrisa, Gujrat..etc. Presently the main
bus of the plant is charged and synchronised by the 400 KV line from
Pusauli grid.
This 400 KV high voltage is stepped down to 6.6KV for charging the bus.
The step down job is done using different transformers and meters for proper
and reliable supply. The area where this is done is known as Switchyard.
Switchyard
PAGE 40
PAGE 42
PAGE 43
The base box is filled with dried mineral oil, protecting the components from
environmental deterioration.
becomes easy to connect the houses with a high speed network access point
without installing new wirings. This technology has been in wide use since
1950 and was mainly used by the grid stations to transmit information at
high speed. Now a days this technology is finding wide use in
building/home automation as it avoids the need of extra wiring. The data
collected from different sensors is transmitted on these power lines thereby
also reducing the maintenance cost of the additional wiring. In some
countries this technology is also used to provide Internet connection. The
first significant step in the field was when two patents were issued to
American Telephone and Telegraph Company in the name of 'Carrier
Transmission over Power Circuits' in 1920. After four years later in 1924
two other patents were filed for the systems transmitting and receiving
communication signals over three phase power lines. PLCC technology can
be deployed into different types of applications in order to provide economic
networking solutions. Hence merging with other technologies it proves
useful in different areas. These are are utilized in Transmission &
Distribution Network, PLCC was first adopted in the electrical transmission
and distribution system to transmit information at a fast rate. Automatic
Meter reading applications use the PLCC technology to send the data from
home meters to Host Central Station.
PAGE 45
PAGE 46
E: Earthing Switch
Earthing switch connect the live parts/ line conductors and earth. This switch
is normally open. Earthing switch is used to earth the live parts during
maintenance and during testing. During maintenance although circuit is open
still there are some voltages on line, due to which capacitance between line
and earth is charged. Before proceeding to maintenance work the voltage s
discharged to earth, by closing the earth switch. Earthing switches are
mounted on the base of mainly line side isolator. Earthing switches are
normally vertically break switches. Earthing arms (contact arm of earthing
switch) are normally aligned horizontally at off condition. During switching
on operation, these earthing arms rotate and move to vertical position and
make contact with earth female contacts fitted at the top of the post insulator
stack of isolator at its outgoing side. The erarthing arms are so interlocked
with main isolator moving contacts that it can be closed only when the main
contacts of isolator are in open position. Similarly the main isolator contacts
can be closed only when the earthing arms are in open position.
PAGE 47
The contact arm is divided into two parts one carries male contact and other
female contact. The contact arm moves due to rotation of the post insulator
upon which the contact arms are fitted. Rotation of both post insulators
stacks in opposite to each other causes to close the isolator by closing the
contact arm. Counter rotation of both post insulators stacks open the contact
arm and isolator becomes in off condition. This motorized form of this type
of isolators is generally used but emergency hand driven mechanism is also
provided. Earthing switches are mounted on the base of mainly line side
isolator. Earthing switches are normally vertically break switches. Earthing
arms (contact arm of earthing switch) are normally aligned horizontally at
off condition. during switching on operation, these earthing arms rotate and
move to vertical position and make contact with earth female contacts fitted
at the top of the post insulator stack of isolator at its outgoing side. The
erarthing arms are so interlocked with main isolator moving contacts that it
can be closed only when the main contacts of isolator are in open position.
Similarly the main isolator contacts can be closed only when the earthing
arms are in open position. As no arc quenching technique is provided in
isolator it must be operated when there is no chance current flowing through
the circuit. No live circuit should be closed or open by isolator operation. A
complete live closed circuit must not be opened by isolator operation and
also a live circuit must not be closed and completed by isolator operation to
PAGE 48
avoid huge arcing in between isolator contacts. That is why isolators must be
open after circuit breaker is open and these must be closed before circuit
breaker is closed. Isolator can be operated by hand locally as well as by
motorized mechanism from remote position. Motorized operation
arrangement costs more compared to hand operation; hence decision must be
taken before choosing an isolator for system whether hand operated or motor
operated economically optimum for the system. For voltages up to 145 KV
system hand operated isolators are used whereas for higher voltage systems
like 245 KV or 420 KV and above motorized isolators are used.
G: Busbar
H: Circuit Breaker
Breaker properties
PAGE 51
The principle of operation is similar to the air blast breakers, except that
SF6 is not discharged in the atmosphere. A closed-circuit, sealed
construction is used.
There are mainly three types of SF6 CB depending upon the voltage
level of application:
zero crossing, but the gas pressure will increase sufficiently to blow
the arc out. By connecting several interrupting heads in series, SF6
breakers can be constructed for voltages of up to 765 kV.
Specifications
a)
b)
c)
d)
e)
f)
g)
h)
i)
Rated output
: 16 MVA
Cooling
: ONAN
Type
: two (2) winding
Voltage Ratio
: 132/11.5 KV
Frequency
: 50 Hz
Phase
: Three (3)
Service
: Outdoor
Duty
: Continuous
Impedance at 75C
On 16 MVA base
At principal Tap
HV-LV
: 10% (+10% tolerance)
j) Winding Max Voltage
(KV)
: 132 KV(HV) 12(LV)
k) Lighting Impulse
Volt
PAGE 55
3: Station Transformer
Specifications
a)
b)
c)
d)
e)
f)
g)
h)
i)
Rated output
: 16 MVA
Cooling
:ONAN/ONAF
Type
: three (3) winding
Voltage Ratio
: 132/6.9/6.9 KV
Frequency
: 50 Hz
Phase
: Three (3)
Service
: Outdoor
Duty
: Continuous
Impedance at 75C
PAGE 56
On 16 MVA base
At principal Tap
HV-LV
PAGE 57
3: Switchgear
PAGE 58
High-voltage switchgear was invented at the end of the 19th century for
operating motors and other electric machines. The technology has been
improved over time and can now be used with voltages up to 1,100 kV.
Typically, switchgears in substations are located on both the high- and lowvoltage sides of large power transformers. The switchgear on the lowvoltage side of the transformers may be located in a building, with mediumvoltage circuit breakers for distribution circuits, along with metering,
control, and protection equipment. For industrial applications,
a transformer and switchgear line-up may be combined in one housing,
called a unitized substation (USS).
A: SA/SB
SA/ SB are energised from station transformer (ST) so for reference named
SA and SB. For two units there is one SA/SB. This has a current rating of
2750 amps. From this, those auxiliaries are charged that are common for
both the units i.e. utilized in both the units like MLDB, Air washer, screw
chiller, welding DBetc. currently st#1 is charged so a line from SA/SB
3200 amps is used charge under construction SC/SD of unit 3 and 4. From
SA there is 5 terminals connected, 1 is input from ST, 2nd one is output to
SC, 3rd and 4th one is charging UA and UB and 5th and last one is charging
PAGE 59
PAGE 60
B: UA/UB
Diesel generating sets are used in places without connection to a power grid,
or as emergency power-supply if the grid fails, as well as for more complex
applications such as peak-lopping, grid support and export to the power grid.
Sizing of diesel generators is critical to avoid low-load or a shortage of
power and is complicated by modern electronics, specifically non-linear
loads. In size ranges around 50 MW and above, an open cycle gas turbine is
more efficient at full load than an array of diesel engines, and far more
compact, with comparable capital costs; but for regular part-loading, even at
these power levels, diesel arrays are sometimes preferred to open cycle gas
turbines, due to their superior efficiencies.
Basically these are generators are used to keep charged certain auxiliaries of
plant which need to be running even when blackout happens in plant such
as ID fan, turbine valve, UPS charger for VCBs etc.
PAGE 62