1.

Load Evaluation
1.1 Dead load
Self-weight of the structure is taken into account by SAP program when performing the structural
analysis. Calculation of the dead load of structural elements is no needed.
Dead load from roof system. Following elements are used for roof system:
Purlins Z150/1.5, placed at 1 m distance :
Gpurlin 3.06

Gpurlin
=> gpurlin
9.81 = 0.03
2
2
1.00

groof.coverings 0.44
1.1 = 0.484 (1.1 - coeficient for other elements)
2
2
gk.roof gpurlin + groof.coverings = 0.514
2
Dead load from the slab.

gk.slab 6.76
2
1.2 Live loads SR EN 1991-1-1/NA-2006
The building is composed of 2 bodies: office building and industrial hall.
For categories of use:
- office building: category B - office areas
-industrial hall: category E2 - industrial use
Office building live loads:
-for floors:
qk.floor 2.5
2
-for partitions walls: self weight<3.0 kN/m =>

qk.partition 1.2
2

The roof is considered not accesible except for normal maintenance and repair, being in category H.
qk.roof 0.75
2
13S

d CR 1 1 3/2012

1.3 Snow Load CR 1-1-3/2012


s Is i Ce Ct sk
Is - importance-exposure factor. According to CR 1-1-3/2012, this structure can be classified
as class III.
Is 1.0
The structure has a normal exposure =>
Thermal coefficient :
Ct 1.0
i - shape coefficient

Slope of the roof is 10%.


5.71
i 0.8

Ce 1.0

The building is located in Timisoara.


sk 1.5
2
There are considered 3 cases of snow load distribution:
- non-drifted case :
s1 Is i Ce Ct sk = 1.2
2
-drifted case from one side and from the other side :
s2 Is i Ce Ct sk = 1.2
2
s3 Is 0.5 i Ce Ct sk = 0.6
2
1.4 Wind load CR 1-1-4/2012
we Iw cpe qp ze
Iw - importance-exposure factor. According to CR 1-1-4/2012, this structure can be classified as
class III
Iw 1.00

Computation of qp ze
qp.z cpq.z qm.z
cpq.z 1 + 7 Iv.z

Field category II:

z0 0.05
2

Field category II:

z0 0.05
zmin 2

b 2.66
> zmin

z 8.9

2.66
Iv.z = 0.205
z
2.5 ln
z0
cpq.z 1 + 7 Iv.z = 2.437
2

qm.z cr.z qb
The building is located in Timisoara.
qb 0.6
2

kr.z0 0.189
z 8.9
> zmin
z
cr.z kr.z0 ln = 0.979
z0
2

qm.z cr.z qb = 0.575


2
qp.z cpq.z qm.z = 1.403
2
Computation of cpe
h 8.9
b 18
h<b

For roof:
Slope of the roof is: 5.71
a) Wind direction: q=0
e min (b , 2 h)
b 36
h = 8.9
e min (b , 2 h) = 17.8

b) Wind direction: q=90


e min (b , 2 h)
b 18
h = 8.9
e min (b , 2 h) = 17.8

For walls:
a) Wind direction: q=0
e min (b , 2 h)
b 36
h = 8.9
e min (b , 2 h) = 17.8
d 18
e<d

h
= 0.494
d

Wind pressures:

1.5 Seismic load P100-1/2013


a) Definition of the design spectrum for horizontal seismic action
Se (T) ag (T)
The structure is located in Timisoara.

ag 0.2
TC 0.7

= 1.961
2
TB 0.14

TD 3

TC

0.7

TB

0.14

TD

0 2.5

a) Definition of the design spectrum for vertical seismic action


av 0.7 ag = 1.373
2

TCv 0.45 TC = 0.315


TBv 0.1 TCv = 0.032
TDv TD = 3
The normalized elastic reponse spectrum of absolute acceleration for vertical component of ground
movement, v (T) is given by the following relationships:
0 T TBv

0v 1
v (T) 1 +
T
TBv

TBv < T TCv

v (T) 0v

TCv < T TDv

TCv
v (T) 0v
T

TCv < T TDv


TDv < T 5 s

v (T)

0v

T
TCv TDv
v (T) 0v
2
T

0v 2.75

The vertical component of the seismic action will not be considered for this building. The building do not
have a great hight, so there is no important influence of the vertical component.
Destination of the building is industrial hall: Class III => I.e 1.0
The behaviour factor for the office building:
- for baced frames : q=6.5
-for non-braced frames : q=4
The structure will be design for DCH class.
The behaviour factor for the industrial hall: q=1.5
The structure will be design for DCL class.