Beruflich Dokumente
Kultur Dokumente
May 2015
Table of Contents
1. GENERAL INTRODUCTION ...................................................................... 2
1.1 PRINCIPLES AND PURPOSE ................................................................................................. 2
1.2 ADVANTAGES AND DISADVANTAGES ................................................................................ 3
1.3 EFFECTIVENESS, EFFICIENCY AND COSTS.......................................................................... 4
REFERENCES ............................................................................................. 13
University of Surrey
1. General Introduction
Appendix I of the Code of Practice for the Management of Highway Structures
summarises a set of available techniques for maintenance options for transport
infrastructures. In this document I will give a general overview of the Protective
Enclosure system used mainly for the maintenance of steel structures, which is
described in the codes BD67/96 and BA67/96 Enclosure of Bridges.
1.1 Principles and Purpose
The enclosure of steel bridges comprises a protective system around the main
supporting elements under the bridge deck. This enclosure will indeed shield the
steelwork against the corrosive environment, hence improving the durability and
reducing maintenance. Figure 1.1 shows the main elements of a bridge enclosure
using GRP panels.
University of Surrey
University of Surrey
Disadvantages
Added initial cost. The materials, erection and installation of the enclosure
panels will incur in substantial costs, which will be required to be assessed.
Advanced materials. The many requirements for the enclosure system are met
by the use of expensive and state-of-the-art materials which, in general, will be
more difficult to be supplied. These specialised components will need to be
low weight and maintenance-free themselves.
Air control. Provisions for proper ventilation and control of draughts should be
considered. The presence of the enclosure will inevitably alter the behaviour
under wind conditions and therefore careful assessment should be carried out.
Headroom. The installation of the enclosure will reduce the vertical clearance
available under the bridge, and hence, in situations where restrictions exist, it
may not be even possible to opt for this maintenance option.
Vandalism. The enclosure panels will prevent unauthorised access to the main
girders but will be subjected to vandals attacks themselves. That is, it must be
considered that the enclosure system may be prone to damage from impact or
vandalism incurring in additional cost due to repair or replacement.
Despite all the advantages mentioned above, the use of this maintenance option will
be largely governed by a cost-benefit analysis, as it will be explained below.
1.3 Effectiveness, Efficiency and Costs
According to tests conducted by the Transport Research Laboratory (TRL), the
corrosion rates measured for the enclosed steel panels tested were about 2% to 11%
(Irvine, 2001) of those of the same non enclosed specimens, proving its effectiveness.
4
University of Surrey
Moreover, upon the inspection in 2001 of one of the Second Severn approach road
bridges, the engineer noted that: the interior was found very dry and clean. The
system appeared to be working excellently with no sign of water ingress, damp, build
up of debris or corrosion occurring (Halliwell, 2004).
It is clear however that the efficiency of the system is subject to a cost-benefit
analysis, with future expenditures to be discounted to net present values. In this
regard, the enclosure solution may prove to be efficient only for very specific types of
structures (e.g. multi-girder composite bridge), of relatively large importance, with a
long time until obsolescence and with difficult accessibility.
This cost-effectiveness appraisal will generally be conducted over a 40-year time
period, considering all initial and subsequent direct and indirect costs. For the
situations described above, bridge enclosures have proved to be a long-term costeffective solution even for large discount rates (around 8%) that would diminish the
importance of the life-cycle analysis.
As shown when describing the advantages of the enclosure system, the reduction in
costs stems from: a) direct costs savings due to less time until first and subsequent
maintenance and inspection, b) indirect costs savings due to elimination or reduction
of road user delays and traffic accidents. The increasing importance of the indirect
costs from traffic delays and accidents shows that these savings could indeed be very
large.
As an example of a cost comparison analysis carried out, the table below shows the
savings justification for the retrofit of the Nevilles Cross Bridge in Durham. As a
reference, in (Ryall, 2001) an average cost of 150/m2 is proposed for the enclosure.
University of Surrey
University of Surrey
3. Case Studies
Two case studies will be presented: A19 Tess Viaduct and the Second Severn Bridge
Approach. The former included the enclosure as a retrofit measure while the latter
acknowledged the importance of the enclosure from the design phase.
3.1 A19 Tees Viaduct
Location and Description of the Bridge
The A19 Tees Viaduct in Middlesbrough refers to the 1.95km stretch of the A19
major trunk road as it spans over the River Tees, a series of railway lines, the
Marshalling Yards and other slip roads. The main section over the river comprises 9
spans of steel plate girders supporting a composite concrete deck slab. At the main
span of 117m, the superstructure depth varies from 3 to 5m.
University of Surrey
Inefficient gullies.
Generally speaking, corrosion and cracking of both concrete and steelwork was taking
place due to an insufficient drainage and the large presence of chlorides. Also, the
need to upgrade to the new live loads imposed in the structure and comply with
BS5400 would require substantial strengthening.
All the repair, maintenance and strengthening works were to be carried out, but a
major concern remained regarding the access to the main girders, which were very
large and spanned over a wide river. The cost of scaffolding or the use of auxiliary
gantries was deemed exorbitant, and investigation of a cost-effective solution was
required.
University of Surrey
University of Surrey
University of Surrey
The bridge was designed by Maunsell Structural Plastics and built by Balfour Beatty
Civil Engineering, starting construction in 1993.
The objective
The future maintenance and inspection of the steel plate girders was to be considered
at the design stage. That is, it was intended to provide permanent access to the steel
girders without interfering with the traffic below.
The solution
For 7 of the 24 structures, it was decided to provide an enclosure system for the soffit
of the superstructure, as this would not only avoid traffic disruption during
maintenance operations but also it would significantly reduce the corrosion rates of
the steel girders.
The ACCS Caretaker system developed by Maunsell was to be used, with an
estimated cost of 282/m2 (Hooks, et al., 1997). The GRP enclosure components are
essentially the same as described for the A19 Tees viaduct, with the GRP panels
hanging from the girders as shown in Figure 3.6.
Figure 3.6. GRP Enclosure for Second Severn Approach (Ryall, 2001)
The enclosure system would also provide support for formwork and workers during
the deck construction, and the design considered a construction load of 1.9kN/m2
with maximum deflection of L/120, in order to provide a safe and comfortable
working environment.
An important aspect of this enclosure system is its additional function as a fairing
system, with the special lateral GRP flares providing an aerodynamic shape for the
cross section. These curved panels would reduce the wind drag and optimise the shape
11
University of Surrey
without the need of a box girder deck, which would increase the cost compared to the
plate multi-girder.
Moreover, the fairing provides an aesthetically appealing bridge superstructure,
improving the design recognition and quality.
12
University of Surrey
References
References
Corus Construction & Industrial, 2005. Corrosion protection of steel bridges. [Online]
Available at:
http://resource.npl.co.uk/docs/science_technology/materials/life_management_of_mat
erials/publications/online_guides/pdf/protection_of_steel_bridges.pdf
[Accessed 2015].
Halliwell, S., 2004. In-Service Performance of FRP Structures. University of Surrey,
Guildford, Woodhead Publishing Limited, pp. 719-726.
Head, P. & Churchman, A., 1989. Design, Specification and Manufacture of a
Pultruded Composite Construction System. s.l., Imperial College of London, pp. 117162.
Head, P. & Templeman, R., 1986. The Application of Limit State Design Principles to
Fibre Reinforced Plastics. Nottingham, British Plastics Federation, pp. 69-77.
Hooks, J., Siebels, J. & Seible, F., 1997. Advanced Composites in Bridges in Europe
and Japan, Washington: FHWA.
Irvine, R., 2001. Bridge Enclosure. [Online]
Available at:
http://projects.bre.co.uk/composites/bridgeenclosures/bridgeenclosures.pdf
[Accessed 2015].
Lee, D. J. & Johnson, P. F., 1994. A19 Tees Viaduct. Strengthening and
Refurbishment. Proceedings of the ICE - Structures and Buildings, 104(2), pp. 145166.
Ryall, M., 2001. Bridge Management. Oxford: Butterworth-Heinemann.
Ryall, M., Parke, G. & Harding, J., 2000. Manual of Bridge Engineering. London:
Thomas Telford Ltd.
T. H. P., 2013. A Blog from the UK about Bridges and Bridge Design. [Online]
Available at: http://happypontist.blogspot.co.uk/2013/11/teesside-bridges-3-a19-teesviaduct.html
[Accessed 2015].
UK Highways Agency, 1996. Enclosure of Bridges - BD67/96 and BA67/96,
Standard and Advice Notes. s.l.:s.n.
13