19
ACTIVITY SEQUENCE
All HT, LT SWGR ,Battery chargers are charged
Raw water pump in service & Clarified water treatment plant in service.- Pr. 2.5 ksc
SACW pump in Service- Pr. 4.5 ksc
Instrument and Service Air Compressors in service- Pr. 7 ksc
Service water pump in service -Pr. 6 ksc
CW pumps in service- Pr. 2 ksc, All Condenser pass charged., CT fan in service
TG-ECW , SG-ECW & ACW pumps in service Pr.7, 10 & 4 ksc
Generator PSW System in service- Tank level>500mm, disch pr. 7.5 KSC. Stator water
flow 110 -120 T/hr.Winding DP is 1.4 to 2.2 KSC. Conductivity 2.5-5 micro siemens/cm.
Gen Filling with Air & Gen Seal Oil system charging Pp Disch Pr 10 KSC, Seal oil to
Hydrogen DP is 0.6 to 0.9 KSC
TG Lub Oil pump,& JOP in sevice- Lub Oil pr 1.2 ksc, JOP pr 80 ksc, Lub oil Temp 4042 0C,DP across plate filter (150 to 300 mm) & Duplex filter are normal
Baring Gear in service- Barring Gear motor current 35 to 40 Amps.
Shaft eccentricity is 0.04 mm. Turbine speed: 1.1 RPM
Control Fluid pump in service- Pr 50 ksc , temp 48-50 0C,
Aux PRDS hdr Charging- Pr.16 ksc, Temp HT-310 0C, LT-210 0C
Gen CO2 & H2 Filling- H2 pr.in Gen. is 3.8-4.0 ksc , purity > 99%
Hot Well filling & CEP in service- Hotwell level 400 mm, disch Pr 30 ksc, Dea level
Control station &LP heater water side lineup, CPU in service
Dea. Filling & FST heating , level 2000 mm, Temp 105 0C
MDBFP in service - Scoop 15-18 % & R/C open, ,Chemical Dozing system in service
,FRS & HPH water side lineup
Condenser Vacuum pulling & Turbine seal steam charging- Vacuum Pumps (02) are in
service and Third pump is in stand by mode, Seal steam Pr. 1.05 to 1.25 KSC. Seal steam
temp 160 to 180 C in cold header. Spray system is lined up for desuperheater. Aux steam
HT header pressure is 16 KSC and temp is 310 C. Drain valves of Hot and Cold headers
of seal steam are open (05 nos.) Cond Vacu < 0.28 ksc, LP turbine exhaust hood spray line
up
Boiler Filling- Open all vents of Boiler & close Eco,WW & intermediate Header drains,
Open Start up system all isolating valves, Put WR &ZR valve in auto. The warming
system for the boiler start-up system is isolated
Start Filling the Boiler with DM Water Initially maintain flow rate 220 T/Hr ( 10 % of
TMCR), When WR opens > 30 % increase the feed water flow to 660 T/ Hr ( 30 % of
TMCR), Boiler is filled when WR Full open and ZR 15 % open for 2 minute and separator
level is stable Maintain again flow rate 220 T/Hr ( 10 % of TMCR) Close the ECO vents
Water Recirculation via Boiler for Clean-up-Water flows through the economizer and
evaporator, and discharges the boiler through the WR valve to the flash tank and via
connecting pipe to the condenser. From the condenser, the water flows through the CPU &
remove impurities, then returns to the FST Measure the chemical property of water
(iii) Ensure drain valves of HP CV & cross over pipes to HPT are open
(iv) Ensure drain valves of IP CV & cross over pipes to IPT are open
(v) Ensure drain valves of IP -LP cross over pipes are open
(vi) Ensure LP Bypass warm up & drain valves are open
(vii) Ensure drain valves of M S, CRH & HRH pipelines are open to Flash tank.
ENSURE GATE VALVES ON STEAM EXTRACTIONS FROM TURBINE ARE
CLOSED
ENSURE CRH NRVS BYPASS VALVES ARE CLOSED.
ENSURE HPC & IPC FLANGE HEATING VALVES ARE CLOSED
ENSURE ALL TURBO-SUPERVISORY READINGS ARE WITHIN LIMIT
Raise HPC & crossover pipe temp. upto 340 deg C
Preheating of Stop & Control Valves
At MS temp of 4420C and HRH temp of 400-4200C
Latch the turbine & ensure HP & IP stop valves are open
Start preheating of HP SV & HPCV , IPSV & IPCV
Ensure turbine speed should not exceed 600 rpm during heating.
Ensure Shaft eccentricity at HPC front
0.07 MM (when barring gear is ON)
0.10 MM (when RPM < 1150 ), 0.25 MM (when RPM > 1150 )
Heating is complete if metal temperature of HP/IP SV, HP & IP CrossHP Casing temperature is >350 0C
Mill C I/S after closer of HP bypass increase total firing up to 30 % equalized feeder
rating after second mill is proven & increase load
Raise the load to 150 MW
Steam pr. at IP I/L 16 KSC and at HP I/L100 KSC up to 25 % load
In 15 min and then soaking for 40 min.
Gradually increase MS & RH temp to 450 & 470 C at 30 % load (195MW)
Firing Rate should never exceed the rate necessary to match total steam
generation. Watch WW tube metal temp. Increase load up to 30 % 195MW at
Turbine loading rate 0.5 MW/min
MS Flow 600 T/Hr, MS & RH temp to 415 &410 0C
For further Turbine loading up to 530 MW, loading rate shall be
3 MW/min
at permanent HP CV opening, i.e. sliding pressure mode
Operation
The speed of temperature increase for live steam and reheat upstream of turbine
shall not exceed 0,7/min
After reaching 30 TMCR load Reduce oil firing maintaining total firing rate same by
taking another mill i/S
HPH charging : Charge just after Change over
LOAD RAISING TO 660 MW
Start 4th. mill A at 300 MW (temp. 480/480, pr.150/20)
Charge extraction steam to deaerator from IPC 6th Stage
Connect HPH, close drains on steam extraction pipelines to HPH
Cut-in second TDBFP from auxiliary header.
RAISE LOAD TO 330 MW & CHANGEOVER TDBFP SOURCE to IP
extraction
Steam pr. at IP I/L : 24 KSC and at HP I/L :150 KSC
M S temperature: 450 0C, HRH temp. 455 0C
Start 5th mill E at 400 MW
(MS/HRH temp. 510/300C, MS/HRH pr. 180/30 KSC,
MS flow 1320T/hr)
RAISE LOAD TO 450 MW (MS/HRH temp. 470/4850C;
MS/HRH pr. 215/37KSC, MS Flow 1500 T/hr)
Stop HPC & IPC flange heating
Start 6th mill at 530MW
MS/HRH temp. 510/5100C;
MS/HRH pr 240/40 KSC , MS flow: 1680T/hr) and switch to constant
press mode
RAISE LOAD TO 660 MW (MS Flow to 2024 T/hr )in constant press
mode
Take 7th mill if required.
Steam pr. at IP I/L : 48 KSC and at HP I/L :247 KSC
M S temperature: 538 0C, HRH temp. 565 0C
Change the pressure controller mode to Load controller at rated M S & HRH
temperature