Beruflich Dokumente
Kultur Dokumente
TECHNICAL REPORT
POTENTIAL OF ENERGY EFFICIENCY IN
EXISTING BUILDING
JKR HEADQUARTERS BLOCK F,
Prepared by:
CK TANG, GBEET SDN BHD
Email: ck@gbeet.com
for
December 2011
FOREWORD
This technical report is prepared under the scope of Building Sector Energy Efficiency Program
(BSEEP) for Malaysia in November to December 2011.
Building Sector Energy Efficiency Project (BSEEP) has for its goal the reduction in the annual
growth rate of GHG emissions from the Malaysia buildings sector. The project objective is the
improvement of the energy utilization efficiency in Malaysian buildings, particularly those in the
commercial and government sectors, by promoting the energy conserving design of new
buildings and by improving the energy utilization efficiency in the operation of existing
buildings. The realization of this objective will be facilitated through the removal of barriers to
the uptake of building energy efficiency technologies, systems, and practices.
This report is prepared by CK Tang of GBEET SDN BHD whom was employed as a short term
BSEEP consultant from November to December 2011 for this work.
The views expressed in this document, which has been reproduced without formal editing, are
those of the authors and do not necessarily reflect the views of the neither JKR nor Government
of Malaysia nor UNDP.
gBEET
CK TANG
GBEET SDN BHD
Zehn Bukit Pantai A103,
Jalan Bukit Pantai,
59100 Kuala Lumpur
Malaysia.
Email: ck@gbeet.com
December 2011
TABLE OF CONTENTS
Foreword ............................................................................................................................................................................. 2
Executive Summary ......................................................................................................................................................... 6
1. Introduction ................................................................................................................................................................ 11
1.1 Building Energy Simulation .......................................................................................................................... 12
1.2 Weather Data ...................................................................................................................................................... 14
1.3 Basic Input Data ................................................................................................................................................. 15
1.4 Operation Daily and Weekly Profiles ........................................................................................................ 17
2. Base Simulation Model vs Measured Data ...................................................................................................... 24
2.1 Energy Results Comparison .......................................................................................................................... 24
2.2 Temperature and Humidity Comparison ................................................................................................ 33
2.3 Data Center In Block F ..................................................................................................................................... 35
3. Energy Efficiency Retrofits Potential for Block F ........................................................................................ 37
Electricity tariff ..................................................................................................................................................... 37
3.1 Base Case 0: The Comfortable Base Case Scenario .............................................................................. 38
3.2 Base Case 0: AsIs Base Case Scenario ...................................................................................................... 39
3.3 Case 1: Fix AirTightness of Block F ........................................................................................................... 40
3.4 Case 2: Better Comfort .................................................................................................................................... 41
3.5 Case 3: Small Power Reduction at Night .................................................................................................. 42
3.6 Case 4: Office Electrical Lighting Efficiency ............................................................................................ 44
3.7 Case 5: Light Switches and/or Occupancy Sensor in Office Space ................................................ 45
3.8 Case 6: Occupancy Sensor in Toilets ......................................................................................................... 47
3.9 Case 7: Lift Efficiency ....................................................................................................................................... 48
3.10 Case 8: CO2 Sensor with Motorised Fresh Air Damper ................................................................... 49
3.11 Case 9: Better Comfort Again, Reduce Room Temperature .......................................................... 50
3.12 Case 10: Reduce Chilled Water Flow Rate ............................................................................................ 51
3.13 Case 11: Increase Chilled Water Supply Temperature to 9C ...................................................... 53
3.14 Case 12: High T Chilled Water System ................................................................................................ 54
3.15 Case 13: Fix Duct Leakages, Rebalance Air Flow ............................................................................... 56
3.16 Case 14: Increase Temperature SetPoint ............................................................................................ 57
3.17 Case 15: Reduce AHU Supply Air Flow Rate ........................................................................................ 58
3.18 Case 16: Low Lost Air Filters ..................................................................................................................... 60
3.19 Case 17: Fan Efficiency ................................................................................................................................. 62
3.20 Case 18: VAV System, Off Coil Temp 14C ............................................................................................ 63
3
3.21 Case 19: VAV System, Off Coil Temp 16C ............................................................................................ 65
3.22 Case 20: Increase Lift Lobby Temperature to 26.5C ...................................................................... 67
3.23 Case 21: Chiller Efficiency ........................................................................................................................... 68
3.24 Case 22: Variable Speed Chiller ................................................................................................................ 70
3.25 Case 23: Condenser Flow Rate 2.5 gpm/ton ....................................................................................... 72
3.26 Case 24: Condenser Flow Rate 2.0 gpm/ton ....................................................................................... 74
3.27 Case 25: Primary/Secondary Chill Water Flow ................................................................................. 76
3.28 Case 26: Primary Variable Chill Water Flow ....................................................................................... 77
3.29 Case 27: Chilled Water Pump Efficiency ............................................................................................... 78
3.30 Case 28: Condenser Water Pump Efficiency ........................................................................................ 80
3.31 Case 29: Pump Motor Efficiency ............................................................................................................... 82
3.32 Case 30: Cooling Tower Efficiency ........................................................................................................... 83
3.33 Case 31: VSD on Cooling Tower, 30.5C ................................................................................................ 85
3.34 Case 32: VSD on Cooling Tower, 29.5C ................................................................................................ 88
3.35 Case 33: VSD on Cooling Tower, 28.5C ................................................................................................ 89
3.36 Case 34: VSD on Cooling Tower, 27.5C ................................................................................................ 90
3.37 Case 35: VSD on Cooling Tower, 26.5C ................................................................................................ 91
3.38 Case 36: Oversized Cooling Tower, 26.5C .......................................................................................... 92
3.39 Case 37: 200 Lux General Lighting, 19 W Task Light ....................................................................... 93
3.40 Case 38: 200 Lux General Lighting, 11 W Task Light ....................................................................... 96
3.41 Case 39: 200 Lux General Lighting, 5 W Task Light ......................................................................... 97
3.42 Case 40: Daylight Sensor for Toilets ....................................................................................................... 98
3.43 Case 41: Improved AirTightness & Add Heat Recovery Wheel ................................................. 99
3.44 Case 42: Change Glazing To Single Glazing Clear .......................................................................... 101
3.45 Case 43: Daylight 3.5 m Depth From Facade ..................................................................................... 103
3.46 Case 44: Daylight 4.5 m Depth From Facade ..................................................................................... 105
3.47 Case 45: Performance Film on Glazing ................................................................................................ 106
3.48 Case 46: Change To Performance Double Glazing .......................................................................... 107
3.49 Case 47: Roof Insulation, 50mm Polystyrene ................................................................................... 108
3.50 Case 48: Roof Insulation, 100mm Polystyrene ................................................................................. 109
3.51 Case 49: Roof Insulation, 150mm Polystyrene ................................................................................. 110
3.52 Case 50: Air Temperature SetPoint: 24.5C ..................................................................................... 111
3.53 Case 51: Resize HVAC As Per Current Need ...................................................................................... 113
3.54 Case 52: Resize HVAC @ 12 W/m Small Power ............................................................................. 115
3.55 Case 53: Small Power Back To Measured Value .............................................................................. 116
3.56 Case 54: Small Power @ 12 W/m ........................................................................................................ 118
4
3.57 Case 55: 25% Energy Reduction in Data Center .............................................................................. 119
3.58 Case 56: 50% Energy Reduction in Data Center .............................................................................. 121
EXECUTIVE SUMMARY
It is difficult to find a good case study in Malaysia about optimizing energy efficiency in existing
building. There are many reasons for this lack of good case study, one of which being that most
buildings in Malaysia are normally demolished and rebuilt rather than refurbished. The few
recently retrofitted buildings in Malaysia were refurbished without consideration for energy
efficiency, due largely to the lack of public information on the potential of energy efficiency in
existing building. This represents a loss of opportunity to optimize the building energy
efficiency for these retrofitted building.
This document was made to showcase the potential energy efficiency gain of retrofitting an
existing building fitted with technologies that are more than 20 years old with the current
energy efficient technology available today. The study was based on a computer simulation of
an existing building where a detailed energy audit was conducted on this building in 2008. The
energy audit report provided sufficient data to enable the total energy consumption of the
building to be modeled within 0.1% accuracy of the total building energy consumption in the
simulation model as compared to the measured values.
Upon establishing this accurate base case scenario, energy efficiency strategies were applied on
to the simulation model of the building, testing each strategy for its annual energy savings that
can be provided by each design feature.
A total of 58 simulation cases were tested by this study. The combined maximum energy
reduction potential of these tested 58 cases was simulated to be 50.1%, providing an average of
0.9% energy reduction per energy efficiency feature.
Key Lessons Learned from this study
1. It is possible to reduce existing building energy consumption by more than 50%.
2. There is no single silver bullet for energy efficiency in existing building where energy
reduction can be brought down by 50% with just the implementation of one single
design feature. Minor improvement made on every potential energy reduction features
in the building provides the efficiency gain step by step until it reaches 50% energy
reduction for the whole building.
3. Air leakage in old buildings is a major source of energy leakages in building.
4. By implementation of energy efficiency features, the reduced capacity of the chiller
would itself, provides a significant budget for the implementation of energy efficiency
features.
5. This study also showed that it may be possible for a building owner to change the chiller
to a larger capacity, due to the complaints received from the building occupant that the
existing building airconditioning system is not providing enough cooling for them. This
extra cost for a larger chiller could be used instead for improvement in energy efficiency
features of the building while keeping the capacity chiller the same as shown in this
study or perhaps even reduce the size of the existing chiller.
6. Reducing building cooling load has a domino effect in energy efficiency for the
building. Once the building cooling load is reduced, the airconditioning supply air flow
rate and chilled water flow rate can be reduced as well. The reduction of air and water
flow rate reduces fan/pump power by a cubic factor because they follow the fan/pump
affinitys law. For example, a reduction of 15% flow rate reduces energy consumption of
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
the pump or fan by almost 40%. The heat generated by the pump or fan would also be
reduced by 40%, thereby further reducing cooling load requirement on the chiller.
It may not be necessary to implement variable speed drive (VSD) for every equipment in
the building. In this study for Block F, the cooling load was measured to be fairly
constant and consistent every working day, the implementation of VSD on the AHU
(converting it into a variableairvolume system), and on the chilled water supply
(primary/secondary) provided marginal efficiency gain. However, it should be
highlighted too that if the building cooling load changes in future, the building would
lack the ability to response efficiently without having VSD in the building. Moreover,
VSD is not an expensive item and can be easily installed onto an existing system.
It is more energy efficient to oversize a cooling tower to provide as cold as possible
condenser return water temperature to the chiller to gain chiller efficiency
improvement than to seek fan energy reduction in cooling tower via the use of VSD.
However, this may be system specific, i.e. depending on the existing chiller performance
curve. Future technical guideline from BSEEP will address this issue in more detail.
It is more energy efficient in Block F building to reduce flow rate of condenser water
flow rate to 2.0 gpm/ton (instead of the typical flow rate of 3.0 gpm/ton) to save on
pumping energy, while accepting a small decrease in chiller efficiency. However, this
may also be system specific, i.e. depending on the existing pump efficiency, pump head
and chiller performance curve. . Future technical guideline from BSEEP will address this
issue in more detail.
Heat recovery wheel would only work in an airtight building. The exhaust air duct has
to be carefully designed to cater for the expected exhaust air flow rate.
Chiller efficiency has improved significantly over the past 20 years. This efficiency
improvement (money saved) can pay for the cost of the new chiller over the life time
of 15 years for chillers.
In a variableairvolume (VAV) system, where the AHU fan power is low (as in Block F
after the reduction of air flow rate), it would be more energy efficient to set the AHU to
have higher off coil temperature to reduce moisture removal (increasing relative
humidity, while ensuring that room relative humidity stays within the recommended
range). Fan energy to delivery cooling to the room increases due to the lower air
temperature differences, however, the saving from less moisture removal, saved more
energy for the chiller than the increase in fan power used. Future technical guideline
from BSEEP will address this issue in more detail.
It is energy efficient to reduce general lighting level down to 200 lux level while
providing task light for the building occupants. The power consumption of the task light
itself (tested from 19W down to 5W task light) has a very small impact on the building
energy efficiency.
The energy efficiency gained from daylight harvesting is not significant in this study
because the building already has a very low lighting power density and a very efficient
chilled water system in place before daylight harvesting option was considered in this
study. In a building where the mechanical and electrical equipment are not energy
efficient, the benefit from daylight harvesting will be significantly higher.
Daylight harvesting in building has the potential to improve building occupant
performance, reduces sick leaves and give an overall better environment to the office
space.
Once the building airconditioning system has been made very energy efficient, passive
features such as high performance double glazing, daylight harvesting using light shelve
7
is shown to have poor financial feasibility. However, if these passive features were
implemented before the airconditioning system is improved, its financial feasibility
would be much better.
The implementation of energy efficiency strategies in JKRs Block F building (~24,000 m) was
simulated to reduce the building energy consumption by RM 660,000/year or RM 2.30
/m/month. The chiller size reduction due to the energy efficiency features employed onto the
building provided an immediate saving of RM 4.2 million. The saving of RM 4.2 million can used
to finance a major part (if not all) of the proposed energy efficiency retrofit for this building.
A summary of the 58 simulation steps employed is tabled below for quick reference.
Cases ShortDescriptions
BEI
%Saved
B0
ComfortableBaseCase
172.7
6.7%
B1
BaseCaseAsIs
161.9
0.0%
C1
AirTighttheBuilding
156.1
3.5%
C2
ImproveComfort
164.3
1.5%
C3
ReduceSmallPoweratNight
160.7
0.7%
C4
5.2%
C5
ReduceLightingPower
153.4
Office Use of Occupancy Sensor/Lighting
Switches
148.7
C6
ToiletUseofOccupancySensor
148.5
8.3%
C7
50%Liftshutdownafter7pm
147.8
8.7%
C8
FreshAirSupplyRegulatedbyCO2sensor
141.5
12.6%
C9
ImproveComfort
144.8
10.5%
C10
ReduceChillWaterFlowRate
142.8
11.8%
C11
IncreaseChillWaterSupplyTempto9deg
141.5
12.6%
C12
HighDeltaTemperatureChillWater
140.3
13.3%
C13
FixDuctLeakages
140.9
12.9%
C14
IncreaseAHUsetpointtemperature
139.3
13.9%
C15
ReduceAHUflowrate
120.7
25.4%
C16
Useoflowpressurelossairfilters
118.2
27.0%
C17
ImproveFanEfficiency
117.6
27.3%
8.1%
RM/year
Saved
(88,481)
46,787
(20,036)
9,717
69,401
107,861
109,566
114,994
166,438
139,400
156,031
166,543
176,302
171,230
184,654
336,747
356,921
361,995
8
C18
UseVAVsystemwithoffcoiltempof14deg
117.5
27.4%
C19
UseVAVsystemwithoffcoiltempof16deg
116.7
27.9%
C20
LiftLobbyAirTemp27deg
116.3
28.2%
C21
ChillerEfficiency(COPof6.3)
107.2
33.8%
C22
UseofVSDChiller
104.3
35.6%
C23
ReduceCondenserWaterFlowto2.5gpm/ton
102.2
36.8%
C24
ReduceCondenserWaterFlowto2.0gpm/ton
101.5
37.3%
C25
Useofprimary/secondarychillwatersystem
101.6
37.2%
C26
Useofprimaryvariablechillwatersystem
101.4
37.3%
C27
Improvechillwaterpumpefficiency
101.0
37.6%
C28
Improvecondenserwaterpumpefficiency
100.3
38.0%
C29
Improveallpumpmotorefficiency
100.1
38.1%
C30
Improvecoolingtowerfanefficiency
99.1
38.8%
C31
CoolingTowerVSDfan,setpoint30.5deg
99.4
38.6%
C32
CoolingTowerVSDfan,setpoint29.5deg
98.9
38.9%
C33
CoolingTowerVSDfan,setpoint28.5deg
98.6
39.1%
C34
CoolingTowerVSDfan,setpoint27.5deg
98.5
39.2%
C35
CoolingTowerVSDfan,setpoint26.5deg
98.4
39.2%
C36
39.1%
C38
Oversizecoolingtower
98.6
Reduce Light Level to 200 lux, wt 19w Task
Light
91.9
Reduce Light Level to 200 lux, wt 11w Task
Light
91.2
C39
ReduceLightLevelto200lux,wt5wTaskLight
90.8
43.9%
C40
DaylightSensorinToilet
90.6
44.0%
C41
UseofHeatRecoveryWheel
88.1
45.6%
C42
UseofClearGlazing
89.3
44.9%
C43
DaylightHarvestinginOffices,3.5mdepth
85.6
47.1%
C37
43.2%
43.6%
363,039
369,343
373,068
447,149
470,948
487,653
493,340
493,044
494,356
497,921
503,378
504,805
513,573
511,245
515,110
517,577
518,393
518,850
517,554
572,190
577,581
581,589
582,760
603,168
593,841
624,004
9
C44
DaylightHarvestinginOffices,4.5mdepth
84.6
47.7%
C45
ApplyPerformanceFilmonClearGlazing
83.7
48.3%
C46
UseofDoubleGlazingHighPerformance
82.7
48.9%
C47
Roofinsulationwith50mmpolystyrene
82.4
49.1%
C48
Roofinsulationwith100mmpolystyrene
82.1
49.3%
C49
Roofinsulationwith150mmpolystyrene
82.3
49.1%
C50
IncreaseAirTemperature(comfortmaintained) 81.1
49.9%
C51
ResizeHVAC
80.7
50.1%
C52
ResizeHVACwith12W/m2smallpower
80.9
50.0%
C53
SmallPowerbacktoBaseCase(nochange)
84.6
47.8%
C54
SmallPowerupto12W/m2
117.2
27.6%
C55
DataCenterreduces25%energy
107.3
33.7%
C56
DataCenterreduces50%energy
97.4
39.8%
631,580
639,522
647,467
650,120
652,510
650,522
660,487
663,840
662,187
632,288
365,450
446,177
526,911
It should be noted that the strategies and savings listed in the above table is valid for Block F
building only. The details of why each of this strategy worked for Block F is fully described in
detail part of this document. Other existing building may have different problems and the
savings from each strategy described above may be different for a different building.
10
1. INTRODUCTION
This technical report was made to provide the result of an energy efficiency potential study on
an existing building. The Block F, JKR Headquarters building in Jalan Salahuddin, Kuala Lumpur
was selected for this study. This building has undergone a comprehensive energy audit in year
2008 by Cofreth (M) Sdn Bhd and has provided adequate measured data for a detailed energy
simulation to be modeled accurately and calibrated to the building actual operating condition.
In this study, the annual energy consumption of the base building simulation model was able to
be calibrated into less than 1% differences from the Energy Auditor report, using matching peak
power data as provided in the Energy Auditor report.
58 simulation runs were conducted on this building with a total of 52 energy efficiency
strategies and scenarios tested. The summary of result is as shown via the figure 1 and 2 below.
Figure 1, showed a reduction of Building Energy Index (BEI) from 172.7 kWh/m/year down to
80.9 kwh/m/year, a reduction of 50.1%.
200
180
160
140
120
100
80
60
40
20
0
B0
C1
C3
C5
C7
C9
C11
C13
C15
C17
C19
C21
C23
C25
C27
C29
C31
C33
C35
C37
C39
C41
C43
C45
C47
C49
C51
kWh/m2/year
BlockFSimulatedBEIPotential
%AccumulatedEnergyReduction
60%
50%
40%
30%
20%
10%
10%
B0
C1
C3
C5
C7
C9
C11
C13
C15
C17
C19
C21
C23
C25
C27
C29
C31
C33
C35
C37
C39
C41
C43
C45
C47
C49
C51
0%
Figure 2 Potential Accumulated Energy Reduction in Percentages from Measured Case Scenario
The result of this study showed that only five (5) out of 52 energy efficiency features proposed
for the building yield more than 4% savings when used singularly. On average, each proposed
11
energy efficiency feature for the building only reduces approximately 1%. However, when all
the proposed energy efficiency features are used in combination, the building was be able to
save 50% energy from its base measured condition.
Figure 3 Building Plan
Figure 4 Cross Section of Building
12
Figure 5 Energy Simulation Model
Figure 6 Picture of Block F at Jalan Salahuddin
13
Building energy simulation is a powerful tool, allowing one to simulate energy performance for
a variety of scenarios. It can simulate the performance of building energy consumption based on
8760 hours of weather data of dry bulb temperature, wet bulb temperature, wind speed, wind
direction, direct solar radiation, diffuse solar radiation and cloud cover. Building energy
simulation captures the interactive effects of the mechanical systems, occupancy requirements
and the building envelope. The purpose of running building energy simulation in this study is to
test the potential of energy efficiency of Block F, using various energy efficiency retrofit
strategies that are applicable for this building.
Building simulation is used in this case to evaluate the energy use in existing buildings as a basis
for understanding the current energy use and to predict energy reduction associated with
building retrofits.
The building energy simulation tool used for this study is the IES <Virtual Environment>
version 6.4.0.6 from UK (http://www.iesve.com). It meets the requirement of Ashrae Standard
140 and Cibse AM11 for a building dynamic energy simulation tool. This software is
comprehensive enough to allow all the types of passive and active energy efficient strategies to
be studied for the purpose of this report.
The values are integrated over a period of one hour, but the exact time interval has not been specified.
14
It should be noted that energy simulation program require 2 extra data that were not collected
by the Malaysian Meteorological Service, namely the direct and diffuse radiation. The missing
radiation data was calculated for the TRY via Erbs Estimation Model from the horizontal global
solar radiation by Reimann.
Comparison of this set of weather data were made against the data provided by the
International Weather for Energy Calculation (IWEC) and the weather data provided by
Meteonorm. It was found that the TRY is more accurate in predicting the direct and diffuse
radiation split of the Kuala Lumpur weather data because it accurately predicted that the direct
radiation is higher in the morning than in the evening, on average throughout the year, due to
the higher frequency of rainfall in the afternoon/evening hours in a tropical climate such as
Malaysia.
Although not perfect, the TRY is currently the most accurate set of weather data for energy
simulation available today for Kuala Lumpur and it has been used in many energy simulations of
various buildings in Malaysia with satisfactory results. This weather data was also used for the
development of the constants in the Overall Thermal Transmission Value (OTTV) equation
found in the latest Malaysia Standard (MS) 1525, Energy Efficiency in NonResidential Building.
16
2. Off Lights
17
3. 8 6 weekday working (People Occupancy)
4. Office SmPwr
18
5. Infiltrations
19
6. Lobby Lgts
7. Stairs Lights
20
8. Toilet Lights
21
9. Lift Pwr
22
23
Date
Jan0131
Feb0128
Mar0131
Apr0130
May0131
Jun0130
Jul0131
Aug0131
Sep0130
Oct0131
Nov0130
Dec0131
Summedtotal
SimulatedResults
Totalenergy(MWh)
316.8979
291.7742
340.1605
301.8921
340.8951
322.0787
307.8406
333.5537
300.0826
318.7742
307.8691
300.6721
3782.491
The simulated total annual energy consumption of the building of 3,782 MWh/year is only 2.2%
lower than measured value of 3,866 MWh/year.
24
SimulatedTotalEnergyConsumption(kWh)onWeeklyBasis
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Sat
Sun
Mon
LV
Tue
ChillerSystem
Wed
Thu
Fri
Total
The simulation of the energy consumption of the Low Voltage (LV) circuit, Chiller System and
Total matches fairly well with the measured values.
The maximum demand of the chilled water production also matches closely between the
measured value (447 MW) and the simulation value (469 MW).
25
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Max
(kW)
4,293
468,746
4,595
4,781
4,488
4,621
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Total
ChillerDaily(kWh)
3,023
3,338
3,466
3,284
3,368
16,480
727
542
728
529
750
565
713
491
726
526
3,644
2,653
Water
The IES software used for this simulation lump together the cooling tower and condenser pump
power together as heat rejection power used. In addition, it was also not possible to simulate
alternate chiller COP used on the same or alternate days. Only one chiller is modeled in the
simulation while the measured result contains two (2) chillers with two different COP.
26
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Total
Table 7 Measured AHU Electricity Consumption
Max Demand
(kW)
AHUDaily(kWh)
171.54
1,973
1,973
1,973
1,973
1,973
9,864
The daily AHU energy consumption in the simulation model was simulated to be lower than the
measured value based on the average peak power measured at every AHU. It was later
discovered by JKR that the measured value of AHU circuit includes one precision air
conditioning unit used by the data center. When the energy consumption of this precision air
conditioning unit is removed from the measure value, the numbers matches between the
simulation and measured values.
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Total
25.00
Load
126
126
363
363
363
363
363
1,941
The simulated weekly lift (vertical transport) energy consumption matches the measured value
accurately.
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Total
758
758
3,737
3,737
3,737
3,737
3,737
19,441
338.76
The lighting and small power energy consumption was also matched well the simulation value
of 19,441 kWh per week, being 6.3% lower than the measured value of 20,757 kWh per week.
27
Total Lighting +
Small
Power Total Lights Total Small
(kWh)
(kWh)
Power(kWh)
Annual
Load
(kWh)
1,051,104
Percentages(%) 100%
701,779
67%
349,324
33%
The distribution of lighting and small power energy consumption has to be split by the energy
auditor manually because they were sharing the same measured circuitry. The energy auditor
derived the energy split between the small power energy to the lighting power energy in a ratio
of 2:1. This ratio was maintained in the simulated result as shown in table 14.
Days
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Total
The simulated faade lighting energy for a typical week is 143 kWh as compared to measured
value of 110 kWh per week for a difference of 30%. The simulation was based on the energy
audit report of peak faade lighting load of 1.98 kW each night. However since the faade
lighting contributes to a small fraction of the building total energy use, this figure has a very
small influence in the whole building scenario.
28
Descriptions
Measured(kWh)
ChilledWaterProductionSystem
1,188,724
AirHandlingUnits(AHU)
603,640
Air Handling Units, without weekend and
nights
517,090
LightingandSmallPower
1,085,851
DomesticPump
14,783
VerticalTransport
101,587
Others(EssentialSupply)
871,804
Total (using AHU without weekends and
nights)
3,779,839
Simulated(kWh)
1,188,216
512,909
%
diff
from
Measured
0.0%
15.0%
512,909
1,051,104
107,610
922,647
0.8%
3.2%
100.0%
5.9%
5.8%
3,782,486
0.1%
Table 18 Simulated Base Case Energy Breakdown by System compared to Measured values
The comparison between the measured and simulated annual energy consumption yield a net
difference of 0.1%. The chilled water production has a 0.0% differences because the simulation
was calibrated to match the measured value.
20kW, approximately
75% of nonchillers
operating hours
The simulation of the airhandlingunits (AHU) energy consumption was 15% lower than the
measured value. The simulation was based on the average measured peak AHU power
consumption as the input basis. Further investigation showed that the measured AHU energy
consumption includes a precision airconditioning unit used by the data center. The energy
29
consumption by the precision airconditioning unit should not be part of the AHU energy
consumption. The precision airconditioning unit energy consumption should be lumped
together with the data center energy consumption.
It was estimated from Figure 9 that the precision airconditioning unit consumes on average, 20
kW during operation and it is running every alternate few hours. A quick estimate from the
figure 9 showed that this precision airconditioning unit is running approximately 75% of the
hours during the time the AHU is not running.
Chiller Operating Hours = 7am to 6:30 pm (11 hours), Monday to Friday = 11.5 hours x 5
days/week x 52 weeks = 2990 hours per year.
Hours AHU running without chiller running = (8760 2990) x 75% = 4327.5 hours per year.
Precision Air Conditioning Unit, Energy Consumption Estimate during weekends and night time
= 4327.5 hours x 20 kW = 86,550 kWh/year.
Measured energy use by the AHU only = 603,640(measured)86,550(estimateofprecisionair
conditioningunit)=517,090kWh/year.
180
160
140
Power (kW)
120
100
80
60
40
20
0
Sat
Sun
Mon
Tue
Wed
Thu
Fri
Sat
30
Descriptions
AHU
AHUwithoutweekendsandnights
Chillers
HeatRejection(CoolingTower&Condenser
Pump)
ChilledWaterPumps
Others
Total (using AHU without weekends and
nights)
Measured
(kWh)
603,640
517,090
858,977
Simulated
(kWh)
512,909
512,909
863,176
%difffromMeasured
15.0%
0.8%
0.5%
179,445
141,475
8,827
189,792
135,248
5.8%
4.4%
100.0%
1,705,814
1,701,126
0.3%
Table 20 Simulated Base Case Energy Breakdown for Chilled Water System compared to measured values
The chilled water system breakdown comparison between the simulated and measured case
also yields similar accuracy range. The simulated chiller annual energy consumption is higher
by 0.5% because it was calibrated to match as closely as possible. The simulated heat rejection
annual energy consumption is higher by 5.8%, while the chilled water pump is lower by 4.4%.
The Others, i.e. switch board & other standby losses, was measurable but was not simulated,
again this is a small fraction compared to the whole building energy consumption.
The building energy index (BEI) was computed by the energy audit report to be 158.81
kWh/m/year. This BEI was calculated based on the measured airconditioning area of 24,345.4
m. However, the simulation model created from the building plans yields a smaller air
conditioned area of 23,367.86 m, or 4% lower than the measured area. Since all the simulation
cases run are based on the simulation model, the simulation airconditioned area of 23,36.86 m
is used as the basis for all computation made in this document, including the BEI.
31
Descriptions
Measured
24,345.40
AirConditionedArea(m2)
Simulation
Model
%
diff
from
Measured
23,367.86
4.0%
3,782,490.7
23,367.86
161.87
The area differences can be attributed to the different methodology used to measure the
building. The simulation case modeled the building using drawings found, while energy auditor
conducted site measurement to estimate the building airconditioned area.
In this study, the simulation model airconditioned area (m) is used consistently in the entire
report. This will cause the base scenario Building Energy Index (BEI) to have a slight differences
as compared to the energy auditors report.
32
29.5
29.0
28.5
28.0
27.5
27.0
26.5
26.0
25.5
25.0
24.5
00:00
95
90
Percentage (%)
Temperature (C)
However, feedback from the building occupants in JKR indicates that the offices above the 8th
floor are significantly warmer than offices below the 8th floor. The simulated temperature and
humidity of office space and lobby is shown in the figures below.
85
80
75
70
65
06:00
12:00
18:00
00:00
60
00:00
06:00
12:00
18:00
00:00
The typical days air temperature in the offices during office hours was simulated to be just
below 26C. On a hot day, it go up as high as 27C and on a cold day, it reduces down to 24C.
The relative humidity was simulated to be well above 70% almost at all time with a max of
82~83%. These numbers seems to match the measured values fairly well.
33
95
90
Percentage (%)
Temperature (C)
29.5
29.0
28.5
28.0
27.5
27.0
26.5
26.0
25.5
25.0
24.5
00:00
85
80
75
70
65
06:00
12:00
18:00
60
00:00
00:00
06:00
100
95
90
85
80
75
70
65
06:00
12:00
18:00
60
00:00
00:00
06:00
12:00
18:00
00:00
100
95
Percentage (%)
Temperature (C)
00:00
28.5
28.0
27.5
27.0
26.5
26.0
25.5
25.0
24.5
24.0
23.5
00:00
18:00
Percentage (%)
Temperature (C)
28.5
28.0
27.5
27.0
26.5
26.0
25.5
25.0
24.5
24.0
23.5
00:00
12:00
90
85
80
75
70
65
06:00
12:00
18:00
00:00
60
00:00
06:00
12:00
18:00
00:00
34
35
SimulatedBaseCaseEnergyConsumption
ofDifferentSystems
Simulated(kWh)
Others(Essential
Supply)
DomesticPump
LightingandSmall
Power
AirHandlingUnits
VerticalTransport
1,400,000
1,200,000
1,000,000
800,000
600,000
400,000
200,000
ChilledWater
ProductionSystem
35.0%
30.0%
25.0%
20.0%
15.0%
10.0%
5.0%
0.0%
Case51EnergyConsumption
ofDifferentSystems
1,400,000
1,200,000
1,000,000
800,000
600,000
400,000
200,000
Simulated(kWh)
Others(Essential
Supply)
VerticalTransport
DomesticPump
LightingandSmall
Power
AirHandlingUnits
ChilledWater
Production
System
35%
30%
25%
20%
15%
10%
5%
0%
Figure 22 Case 51 Energy Efficient Scenario Data Center remains the same as Base Case
36
200
180
160
140
120
100
80
60
40
20
0
B0
C1
C3
C5
C7
C9
C11
C13
C15
C17
C19
C21
C23
C25
C27
C29
C31
C33
C35
C37
C39
C41
C43
C45
C47
C49
C51
C53
C55
kWh/m2/year
BlockFSimulatedBEIPotential
ELECTRICITY TARIFF
An electricity tariff rate of 0.35 RM/kWh is used in this document to compute all economic data.
37
The asis base case scenario (Base Case 1) has an average air temperature of 25C
and an average relative humidity above 70%. This is consistent with the measured
data provided by Energy Auditors report. From the asis base case 1 scenario
simulation, it was found that the chiller capacity was inadequate to cater for the
existing building cooling load.
In this simulation case, base case 0, the chiller capacity was increased to cater for
the actual cooling load requirement.
Design
Details
172.7
Energy Saved
kWh/year/m (%)
6.7%
253,000
88,500
NA
Budget
Available
for
NA
Investment (RM)
Remarks:
This scenario was made to compute the peak chiller load required to keep the entire building
comfortable. A very likely scenario, if energy efficiency is not addressed in this building, the
building owner would have to order a chiller of 995 Ton capacity to address the comfort issue
faced by the occupants of this building.
The computed peak cooling load of 3,500 kW (995 Ton) for this building scenario represent
approximately a cooling load of 150 W/m (47 Btu/hr per ft) of airconditioned space. The
existing chiller capacity of 1330 kW is equivalent to 57 W/m (18 Btu/hr per ft). It is likely that
this chiller capacity was selected during the days (early 1990s) when small power load in
building was low with very few users of personal computer in the building.
38
The asis base case scenario (Base Case 0) has been simulated using the data of
measured values from Energy Auditors report.
All input data for the simulation case is exactly as per measurement value on site
with the exception of the chiller coefficient of performance (COP) or kW/ton, which
was calibrated.
For the base case simulation study, the COP of the chiller was calibrated to give the
correct annual energy consumption of the chiller.
Details
The Energy Auditors report mentioned that there were 3 different chillers in Block
F, which is used one at a time, every alternate day, due to the configuration of the
chill water pipe circuit. Chiller #1 was out of order during the period of
measurement conducted by the energy auditor. The kW/ton of the 2 measured
chillers are:
Where,
0.81 kW/ton = 4.34 COP
0.72 kW/ton = 4.88 COP
It was not possible to run simulation based on 2 different chillers COP every
alternate day. It was then decided to calibrate the chiller COP of the simulation case
to match with the actual measured annual energy consumption of both the chiller
for the building.
Calibrated COP of the single stage screw chiller for the base case yielded a value of
4.88 (0.72 kw/ton) to match the simulated annual chiller energy consumption to the
measured annual chiller energy consumption within a small error margin 0.5%.
BUILDING BEI (kWh/m/year)
161.9
Energy Saved
kWh/year/m (%)
NA
NA
NA
NA
Budget
Available
for
NA
Investment (RM)
Remarks:
The calibrated single stage screw chiller COP of 4.88 provided an annual chiller energy
consumption of 863,176 kWh/year. This value matched with the measured chiller energy
consumption of 858,977 kWh/year with a difference of 0.5% only.
39
In a separate report made by Cawangan Alam Sekitar dan Tenaga (CAST), JKR in
2010, the measured value of total fresh air intake for Block F was found to be a very
high value of 1.65 airchanges per hour (ach). This includes both the fresh air intake
and infiltration of outdoor air into building.
The measured high intake of fresh air is caused by the partially opened windows
and doors at that time as shown in these pictures below.
Details
The base case has a combined mechanical supply fresh air and infiltration rate of
1.65 ach.
This simulation case study assumed that all these air leakages are fixed. The fresh
air intake from the AHU room is maintained at 10% flow rate of the supply air. The
building is assumed to exfiltrate all the fresh air supplied from the AHU room.
For the simulation in this case, it is assumed that the same airtemperature is
maintained for the offices room as per the base case scenario to compute the energy
saving potential by reducing infiltration of fresh air into building. However, since
the building was not comfortable in the 1st place, it is likely that any improvement
made to the building will be targeted towards providing comfort rather than
providing energy saving.
156.1
Energy Saved
kWh/year/m (%)
3.5%
134,000
46,800
10
Budget
Available
for
RM 468,000 for whole building or
Investment (RM)
RM 190 per m glazing
Remarks:
Improving the building airtightness while maintaining the same comfort condition as the base
case would provide a significant building energy reduction of 3.5%. However, due to the reason
that existing condition is not comfortable for the occupant in this building, it is expected that
upon improvement made to the building airtightness, comfort condition will be provided to the
building via the reduction of air temperature for the offices.
40
Due to the reason that the chiller installed for the building is inadequate to provide
the necessary cooling to the entire building, the average air temperature was
simulated to be 25C.
However, once the building airtightness has been improved, the chiller would be
able to provide the more cooling necessary for the average air temperature to be
reduced from the average of 25C.
Details
The base case simulation study takes into account of the air leakages in the duct. The
measured temperature in the AHU room is approximately 1C lower than the office
room temperature. It has been calibrated in Case 9 simulation (when the chiller
capacity is adequate to provide the necessary cooling to the building) to allow a by
pass (leakages) of 20% of supply air into the return air stream to achieve this 1C
lower than the office room temperature.
The airtemperature set point was to be set to 20C in the AHU room. However, the
simulation showed that it was only possible for the offices to have an average air
temperature of 23.8C. In this simulation study, the chiller capacity was still
inadequate to keep the room below 23.5C. The average air temperature of 23.8C
was maintained until Case 9, where the cooling load of the building has been
brought down low enough for the existing chiller capacity to provide the necessary
cooling to maintain 23.5C.
164.3
5%
191,000
66,800
NA
Budget
Available
for
NA
Investment (RM)
Remarks:
Improvement to the building airtightness would allow the building to have a more comfortable
(colder) air temperature. The improvement in comfort causes the loss of all the gain made from
improving the building airtightness.
41
Small power use in block F building during night time and weekend was measured
to be approximately 25% of the peak daytime load.
Details
These are small power use due to standby power consumption of computers,
monitors, printers, refrigerators and any other electrical equipment that is plugged
to the power point. Even a phone charger that is left on the power point (no phone
connected) would have 2~5 watt standby power consumption if the switch on the
power point remain switched on. All these equipment standby power consumption
and a few office equipment that were not switched off, lead to the measured 25%
base load during night time and over the weekend of small power consumption.
No. of
lamps/
fitting
No.
of
fitting
s
Total
No. of
lamps
Watts
(lamp +
ballast)
Total
Watts
No. of
Faulty
Lamps
Total
Watt for
Faulty
Lamps
Actual
Lighting
Power
(W)
Staircase L
20
80
80
17
Office R
12
40
480
480
17
Office (Director)
20
60
60
17
Office (Director)
40
120
120
17
Meeting Room
18
40
720
720
17
Meeting Room
12
12
26
312
312
17
Meeting Room
20
160
40
120
17
Meeting Room
Eng
Accreditation
18
144
18
126
20
180
180
Level
Room
No./Description
17
17
Table 22 Sample Cut out of Appendix 4.4.2 from Energy Auditor Report of Lighting Power
42
It is assumed in this simulation that this 25% of the peak daytime load at night can
be reduced to 10% with the use of timers to switch off equipment that are shared
and is not required to run at night. The potential items that can be switched totally
off during nonoccupied hours are personal computers, printers, water dispensers,
microwave ovens, and etc.
Power management in personal computers would help to contributes to this saving
by ensuring that computers that are accidentally left on at night would
automatically hibernate or shut down after a period of no activity on it.
BUILDING BEI (kWh/m/year)
160.7
Energy Saved
kWh/year/m (%)
2.2%
85,000
29,800
43
There are a few options for energy efficiency in electrical lighting for an existing
building. Two of these options are described below.
Option 1: Replace existing T8 lamps (magnetic ballast) with T5 lamps with a
convertor and built in electronic ballast. This option does not require the light
fittings to be changed and would reduce the energy consumption the lamps from 40
watts to 30 watts each (including ballast lost). This provides a 25% power reduction
immediately. This option would allow the office electrical lighting power density to
be reduced from measured value of 11.7 W/m down to 9 W/m (25% reduction).
Option 2: Replace the entire light fittings with newer better light distribution
fittings. The new light fittings with T5 lamps and electronic ballast would allow the
office electrical lighting power density to be reduced from 11.7 W/m down to 7.5
W/m or even lower.
Details
This simulation case study reduces the electrical lighting power consumption in
offices from 11.7 W/m down to 9 W/m.
153.4
Energy Saved
kWh/year/m (%)
4.5%
171,000
59,700
44
As in most offices, higher ranked staffs in Block F are allocated with their own
personal room. A typical walk about in Block F would shows that higher ranked
staffs hold more responsibilities and are normally busy attending meetings outside
their own room. Most of them would only be in their own room approximately 50%
of the time.
This case study assumes that in general 20% of building occupants are not in their
place due to reasons such as attending meeting outside the building, attending
meeting in a densely populated meeting room, on holidays or having sick leave of
absent. The provision of light switches or occupancy sensor allows their personal
room lights to be switched off when they are not in the room.
Measured lighting profile from the Low Energy Office (LEO) of Ministry of Energy in
parcel E4/5 in Putrajaya indicates that more than 50% of the lights can remain
switched off during peak working hours due to the reason above.
In the LEO building, occupancy sensor was placed in every room, however, it was
also noted that building occupant do switch off the lights on their own as they
walked out of their own personal offices as long as the location of the switch is
strategically placed such that the building occupant is not required to take any extra
steps to switch off the lights as they walk out of the room. The lighting switches are
located at location where if the left hand is used open the door, the lighting switch is
placed on the right hand for the building occupant to turn it off easily and viceversa
when the right hand is used to open the door.
Unfortunately, due to the occupancy sensors provided in the LEO building, it
remains uncertain if placing the lighting switches strategically is enough to
guarantee energy saving without the use of occupancy sensor.
Details
This simulation case study assumes that the electrical lighting power consumption
in offices reduces by 20% from 9 W/m down to 7.2 W/m.
148.7
Energy Saved
kWh/year/m (%)
2.9%
110,000
38,500
For cost efficiency and reduced maintenance issue, it is recommended to use strategically
located lighting switches that allows for personal control of the lighting need. This type of
solution would need the building occupants to have awareness of energy efficiency to ensure
that they will switch off the lights when it is not necessary to be used.
However for general open office spaces where there is no distinct person responsible for the
lighting, occupancy sensor is recommended to ensure that the lights are switched off when no
one is using the space.
46
Public space such as toilet is a location where lighting switches will not work
because no one is really responsible for toilet lights. This type of space requires the
use of occupancy sensors.
There exists occupancy sensors that can sense occupants behind light weight
partitions such as wooden doors/partition that are normally found in toilets.
These motions sensors can be used to switch off the lights when it senses that there
is no one in the toilet anymore.
Details
This simulation case assumes that 50% of the working hours the lights in toilets are
switched off.
148.5
Energy Saved
kWh/year/m (%)
0.1%
5,000
1,700
47
It was found that the lift left on standby all the time, even during nonworking hours.
The standby lift power during nonoccupancy hours was measured to be
approximately 5 kW on average.
Chart J : Load Distribution for Vertical Transport
(For a typical workweek start from Saturday to Friday - 7
days)
80
60
kW
40
20
0
-20
Time
Figure 24 Measured Lift Power over 1 week
All the lift cannot be shut down totally because there are building occupants that
worked up to late nights and will require the lift to be operational.
However, it would be possible to shut down 50% of the lift to be totally, leaving only
3 out of 6 lifts to be operating during nonoffice hours.
Details
This simulation case assumes that lift power consumption reduced from 5 kW to 2.5
kW during nonoccupied hours.
147.8
Energy Saved
kWh/year/m (%)
0.4%
16,000
5,400
48
CO2 sensor with motorized fresh air damper will control the amount of fresh air
intake into buildings by measuring the CO2 level from the return air. The more
people are in the offices, the higher the CO2 amount and the more fresh air would be
provided to the offices to maintain air quality automatically.
The less people is in the offices, the less CO2 amount is detected and less fresh air is
required to be supplied to the office and still provides a conditions of good air
quality. By reducing the amount of fresh air provided, the building will save energy
because the energy for cooling and drying of fresh air is a significant part of the total
energy consumption in building.
Details
141.5
Energy Saved
kWh/year/m (%)
3.9%
147,000
51,400
49
Details
It is now possible to maintain the offices air temperature at 23.5C with the existing
chiller capacity. Temperature set point in the AHU has to be adjusted to 22.5C,
while room temperature is maintained at 23.5C. This difference in temperature is
caused by leakages in the supply air duct. Calibrated simulation showed that it
requires 20% of the air flow rate to be leaked back into the AHU to be able to
maintain a temperature difference of 1C in Block F.
144.8
Energy Saved
kWh/year/m (%)
2.0%
77,000
27,000
NA
50
The existing chilled water flow rate was measured to be 24% higher than the chiller
specification. This high flow rate has caused the supply chilled water temperature to
be supplied at 10.4C (50.7F) instead of the set point of 6.7C (44F) mostly
because the chill water does not stay long enough for it to be chilled down to 6.7C.
It is possible to reduce the flow rate by installing a variable speed drive (VSD) or by
changing the motor or/and pump to match the correct flow rate and pump head of
the system.
Details
In this simulation study, chilled water flow rate was reduced to the specified flow
rate for the 380 ton chiller with a chilled water flow temperature difference of 5.6C
(10F).
The chilled water supply temperature was also reduced to 6.7C (44F) from 10.4C
(50.7F) previously, along with the reduction of chilled water flow rate. The pump
affinity law is used to compute the new pump head at the new flow rate.
Due to the reduced chill water supply temperature, the COP of chiller was simulated
to be reduced from the previous average COP of 5.04 down to an average of 4.4 in
this case scenario.
142.8
Energy Saved
kWh/year/m (%)
1.3%
48,000
16,600
Law 1c. Power is proportional to the cube of shaft speed:
where
From this law, it was possible to calculate the pump head and pump power reduction due to the
reduction of chilled water flow rate.
52
Chiller efficiency improves when the temperature differences between the return
condenser temperature and the supply chill water temperature is reduced. This can
be done by reducing the condenser return water temperature or by increasing the
chill water supply temperature.
Details
In this case the chilled water temperature is increased from 6.7C to 9C to improve
the efficiency of the chiller, since the chiller was previously supply chill water at
10.5C.
COP of chiller improved 6.4% from 4.40 to 4.68.
141.5
Energy Saved
kWh/year/m (%)
0.8%
30,000
10,500
53
Details
High T (high temperature differences) chill water design reduces pump power by
reducing the flow rate of the chill water supplied. However, it requires that the AHU
cooling coil to be sized adequately to provide a higher leaving chill water
temperature from the cooling coils.
The heat capacity of flowing water is governed by the equation shown below.
Where;
Q = Cooling load (kW)
m = Mass flow rate of water (kg/s)
Cp = Specific heat capacity of water 4.187 kJ/kg C approx. 4.2 kJ/kg C.
T = The temperature difference between flow and return water. (C)
The equation above showed that by increasing the T, the mass flow rate of water
can be reduced to provide the same cooling capacity.
For this simulation case, the chilled water supply temperature was reduced from
9C to 6.7C (44F). The return chill water temperature was simulated to be 14C
(57F) base on the existing cooling coil configuration based on the conditions
described below.
The existing cooling coil configuration was not provided by the energy audit report.
The cooling coil configuration was derived from the assumed initial design
parameter. The following assumptions were made to size the cooling coil for this
study:
Descriptions
Values
23C @ 50% RH
12C
7C (44.6F)
12C (53.6F)
From the numbers above, it was possible to estimate the original cooling coil
configuration and then predict the behavior of the cooling coil based on new
conditions as tested by this case scenario of a high T chill water flow rate.
Based on the new condition of high T design, it can be computed that the existing
cooling coil configuration would reduce the chill water flow rate by 50%, and the
water off coil temperature at this condition would be 14C.
The average COP of chiller reduces from 4.68 down to 4.4, due to the lower
temperature of the supply chill water in this case.
54
140.3
Energy Saved
kWh/year/m (%)
0.7%
28,000
9,800
55
The existing supply air duct system in this building is known to be leaking because
the measured air temperature in the AHU room is colder than the office rooms
where the air is being supplied. This indicates that the supply air flow is leaking in
the false ceiling which is also the space for freereturn of the air back into the AHU
room.
On average there is a measured 1C difference between the air temperature in the
AHU room and the office rooms.
Details
In the simulation model, the air leakage from the duct was calibrated to have a
leakage rate of 20% to maintain a 1C difference between the office room
temperature and AHU room temperature. This leakage was modeled as a bypass
duct circuit directly back to the AHU room.
In this case study, the leakage is stopped totally, pushing the total air flow into the
airconditioned spaces. Several calibrations were made between the zones to
maintain similar air temperature between the different zones. This would be
equivalent to conducting air balancing at the diffusers to balance the air flow rate to
maintain the correct air temperature in each zone.
140.9
Energy Saved
kWh/year/m (%)
0.4%
14,000
5,100
56
The existing temperature setpoint of 22.5C is now providing the room with
temperature of 22.5C instead of 23.5C when the duct was leaking. A resetting of
the air temperature setpoint is made in this case.
Details
The setpoint temperature in the AHU is now raised to 23.5C to maintain comfort
condition.
139.3
Energy Saved
kWh/year/m (%)
1.0%
38,000
13,400
57
Existing AHU (air handling unit) delivers 5,737 l/s of cold air. After fixing the
building airtightness, improved the lighting power density and fixing the duct
leakage it is now possible to reduce the air flow rate while still being able to provide
adequate cooling to the room.
Resizing of the AHU flow rate was computed for this new scenario. It was found that
flow rate can be reduced to 3,753 l/s or 35% reduction from the existing air flow
rate.
Details
The supply air flow rate from the AHU is reduced to 3,753 l/s for each AHU.
Upon reducing the air flow rate, the fan total pressure was also reduced following
the fan affinitys law which is the same as pump affinitys law.
The fan affinity law says that, With fan diameter (D) held constant:
Law 1a. Flow is proportional to shaft speed:
Law 1b. Pressure or Head is proportional to the square of shaft speed:
Law 1c. Power is proportional to the cube of shaft speed:
where
Q is the volumetric flow rate (e.g. CFM, GPM or L/s),
N is the shaft rotational speed (e.g. rpm),
H is the pressure or head developed by the fan/pump (e.g. ft or m or Pa), and
P is the shaft power (e.g. W).
BUILDING BEI (kWh/m/year)
120.7
Energy Saved
kWh/year/m (%)
11.5%
435,000
152,100
Option 1
Reduce the pulley size at the motor or/and increase the pulley size at the fan.
Option 2
Install a VSD (variable speed drive) to reduce fan speed.
Option 3
Change the fan and motor combination to match new requirement.
The affinity law holds true when the pump/fan efficiency is the same (or close to the same) at
these different operating points. I.e. the pump/fan curves need to be checked to confirm that the
efficiency is still the same at the different operating point. Unfortunately, this check was not
possible in this study because the pump/fan curves for the AHU and pumps are no longer
available. However, using the affinitys law as it is for this study should be quite accurate
because the static head would be somewhat low at low flow rate, allowing it to follow the same
efficiency curve as the flow rate reduces which is typical of fan/pump curves.
59
Pressure drop through air filter in AHU is a cause of energy consumption in fan. The
higher the pressure drop, the more energy is used.
Details
The fan power consumption was measured in kW of fan power used. This fan power
is then converted into fan total pressure by assuming that the total fan efficiency is
60%. A fan total efficiency of 60% is typical of backward curve fans using
conventional motors.
Most type of electronic airfilters and certain type of mechanical air filters are
designed to have low pressure drop. It is quite common to find electronic air filters
that have a pressure drop of 80 Pa less than typical mechanical air filter for use in
AHU.
With this assumption, the base building was computed to have an average fan
pressure of 539 Pa at the measured average flow rate of 5737 l/s of air flow rate.
The reduction of flow rate to 3,753 l/s would reduce the fan total pressure to 231 Pa
using the fan affinitys law.
In this case the total pressure of the fan is reduced further by 80 Pa to 150 Pa.
BUILDING BEI (kWh/m/year)
118.2
Energy Saved
kWh/year/m (%)
1.5%
58,000
20,200
affinitys law , i.e. a pressure drop of 34 Pa only due to the lower air flow rate. Therefore, total
fan pressure in this case should be 231 34 = 197 Pa. The total pressure used in this study of
150 Pa is not correct and is 24% lower than it should be. Therefore the result provided by this
case is not correct at this stage. Another set of simulation will be conducted at a later stage to
correct this simulation case study.
61
Backward curve fan with an efficiency of 60~70% at the flow rate of 3200 to 6000
l/s is commonly used today by the building industry. However, in the past several
years, airfoil fan is getting popular in the market and these fans provide efficiencies
up to 85% for certain model and flow rates.
With a fan efficiency of 85%, motor efficiency of 90% and a fan belt efficiency of
97%, a total fan efficiency of 74% was possible. A conservative assumption of
improving the fan total efficiency to 70% was made for this case study.
Details
The fan total efficiency was improved from 60% to 70% efficiency.
117.6
Energy Saved
kWh/year/m (%)
0.4%
14,000
5,100
62
The base building airside airconditioning system uses Constant Air Volume (CAV)
system. The CAV system delivers air at a constant flow rate to the room; the room
temperature is then regulated by supply air temperature. If the room is cold, the
supply air temperature is increased to maintain temperature at comfortable level. If
the room is hot, the supply air temperature is reduced to cool the room to a
comfortable level.
A Variable Air Volume (VAV) system delivers air at a constant air temperature to the
room; the room temperature is then regulated by the supply air flow rate. If the
room is cold, the supply air flow rate is reduced. If the room is hot, the flow rate is
increased to cool the room to the comfort temperature set point.
The advantage of the VAV system is that it reduces fan energy use when the building
is running on part load because the fan speed is reduced.
A VAV system has two additional devices additional to a CAV system. These are the
VAV Box (or Boxes) with a motorised damper to control the flow rate into rooms
depending on the monitored air temperature, and a variable speed drive (VSD) to
control the speed of the AHU fans motor depending on the pressure sensed in the
duct. When the VAV damper open for more flow rate into the room, the pressure in
the duct drops, the VSD sensing a drop in pressure will increase the speed of the
motor to increase air flow rate to maintain the pressure in the duct at a particular
set point. When the VAV damper close to reduce flow rate into the room, the
pressure in the duct increase, the VSD sensing an increase in pressure will reduce
the speed of the motor to reduce the air flow rate to maintain the pressure in the
duct at a particular set point.
Details
A VAV system was modeled for the building, with each AHU having a peak flow rate
of 3,753 l/s at 150 Pa.
Off coil temperature was set at 14C in this case scenario.
A minimum air flow rate of 30% of the peak flow rate was also set.
117.5
Energy Saved
kWh/year/m (%)
0.1%
63
3,000
1,000
64
The simulation result of Case 18 showed that the airconditioned space relative
humidity was reduced from an average of 70% to 60%. This reduction of relative
humidity also increases chiller energy used because more energy is used to remove
moisture from the air (latent load).
A check on earlier simulation cases running on CAV system showed an average off
coil temperature of 17~18C. Due to this high off coil temperature, the moisture
content in the air is still relatively high causing, the fairly high relative humidity of
70% as simulated and measured at site.
Increasing the off coil temperature from 14C to 16C allows less dehumidification
at the cooling coil, thus providing energy reduction on latent heat removal.
However, at the offcoil temperature of 16C, the air flow rate has to be increased for
it to be able to remove adequate sensible heat from the air. This increases the fan
energy usage.
This case study is to test the overall benefit (or loss) by reducing moisture removal
while increasing fan energy use by the AHU system by increasing the offcoil
temperature to 16C.
Details
116.7
Energy Saved
kWh/year/m (%)
0.5%
18,000
6,300
As shown by both the charts above, the fan energy increases by ~9 MWh/year for the entire
building due to the higher off coil temperature set point while the chiller energy reduces by ~22
MWh/year.
66
Details
Air temperature set point for Lift Lobby was set to 26.5C
In a transitional space such as lift lobby, it is not necessary to keep these spaces at
23.5C. The VAV box supplying to this space can be adjusted to maintain an air
temperature of 26.5C at this zone to reduce energy consumption for the entire
building.
116.3
Energy Saved
kWh/year/m (%)
0.3%
11,000
3,700
67
The existing chiller in Block F was measured and then calibrated back to the typical
chiller rating condition by Energy Auditor. The report showed that one of the chiller
has a COP of 4.3 (0.82 kW/ton) and another one a COP of 4.88 (0.72 kW/ton). At
any moment of time, only one (1) chiller was running. These 2 chillers were run on
alternate days, giving opportunity for each of the chiller a day of rest.
Details
It will take a lot of time and effort to configure the simulation software to simulate
alternate chillers running every day. Due to the limited time available for this
project, only one chiller is modeled.
The calibration of the chiller efficiency was made based on all the measured data
used for the building energy model, such as the measured small power load, lighting
load, infiltration (fresh air), no of people and etc. It was found that a simulation
chiller COP of 4.88 (0.72 kW/ton) matches perfectly with the measured annual
electrical energy consumption of the chiller.
Due to the reason that the measured supply chill water temperature is on average
10.5C instead of the typical 6.7C (44F), the actual average simulated COP during
operation was at 5.1 (0.69 kW/ton) although the rated condition COP is 4.88 (0.72
kW/ton).
The existing building is using single stage screw chiller. The chiller performance
curve used for the simulation building up to this stage is based on a typical single
stage screw chiller provided by US Department of Energy (DOE) for their Equest
software. The DOE chiller curve fit that accounts for the condenser return water
temperature, chill water supply temperature and partload performance of the
chiller to compute the COP of the chiller.
In case 21, an energy efficient centrifugal chiller was selected to have a rated COP of
6.3 (0.56 kW/ton). Again the chiller performance curve used for this chiller is based
on DOE curvefit for a centrifugal chiller that accounts for the condenser return
water temperature, chill water supply temperature and partload performance of
the chiller.
107.2
Energy Saved
kWh/year/m (%)
5.6%
212,000
74,100
15
69
Chiller fitted with variable speed drive is already available in the market today. VSD
(variable speed drive) chiller would typically have higher efficiency at partload of
30% to 60% as compared to a typical screw or centrifugal chiller without variable
speed.
In climates with hot and cold seasons, VSD chiller has been shown to have COP
above 10.0 during season of low wetbulb temperature at part load scenario.
Unfortunately in Malaysia climate, where the wetbulb temperature is fairly
constant throughout the year, these VSD chillers would typically maintains (or just
marginally better than) the peak load COP.
In the existing building scenario, one (1) chiller is used for the entire day of peak
load and part load condition. The use of VSD chiller would help to provide better
performance during partload condition.
Details
The DOE VSD centrifugal chiller performance curve fits was used to model this
chiller for this case. A rated peak condition COP of 6.3 (0.56 kW/ton) was
maintained for this study.
104.3
Energy Saved
kWh/year/m (%)
1.8%
68,000
23,800
15
70
The simulation of centrifugal VSD chiller showed marginally better performance than a typical
centrifugal chiller at peak load. However at part load of below 50%, the VSD chillers outperform
the centrifugal chiller by a bigger margin. In the case of Block F, there is a good reason for using
a VSD chiller because only one chiller is run at any one time (even at part load condition). The
VSD chillers will provide better efficiency at part load conditions as compared to a typical
centrifugal chiller.
However, chiller performance is actually quite specific to the manufacturer. This VSD chiller
curve fit provided by DOE may not match all VSD chillers from all different manufacturers. It is
recommended to study each manufacturer chiller curve fit individually to get the best
performance and at the best value of investment for this building.
71
Chiller can be run with condenser flow rate of 3 gpm/ton, 2.5 gpm/ton or as low as
2.0 gpm/ton of chiller load. The lower the flow rate of condenser water, the
efficiency of the chiller becomes lower. However, reducing the condenser flow rate
will reduce the condenser pump power by a cubic relationship (pump affinitys law).
This study is to compare which factor is more important for this building, the chiller
efficiency versus the condenser pump power.
Details
The flow rate of the condenser water was reduced from from 3 gpm/ton to 2.5
gpm/ton.
102.2
Energy Saved
kWh/year/m (%)
1.3%
48,000
16,700
72
Condensergpm/tonOptions
80
70
75.3
62.8
60
50.2
50
42.0
40
23.1
30
20
24.3
16.1
12.4
10.3
10
0
l/s
headm
3gpm/ton
2.5gpm/ton
kW
2gpm/ton
The existing building condenser pump has a pump head of 23.1 m of water. A reduction of the
flow rate to 2.5 gpm/ton reduces the pump head to 16.1 m of water and at 2.0 gpm/ton, the
pump head is then reduced to 10.3 m of water. At the lowest pump head, the pump power has
reduces by 70% from the existing condition. These numbers were all computed using the pump
affinitys law.
73
Chiller can be run with condenser flow rate of 3 gpm/ton, 2.5 gpm/ton or as low as
2.5 gpm/ton. The lower the flow rate of condenser water, the efficiency of the chiller
becomes lower. However, reducing the condenser flow rate will reduce the
condenser pump power by a factor of 3.
Therefore this study is to compare which factor is more important for this building,
the chiller efficiency versus the condenser water flow rate.
Details
Reducing the flow rate of the condenser water from 2.5 gpm/ton to 2.0 gpm/ton
reduces the pump peak power from
101.5
Energy Saved
kWh/year/m (%)
0.4%
16,000
5,700
74
Condensergpm/tonOptions
80
70
75.3
62.8
60
50.2
50
42.0
40
23.1
30
20
24.3
16.1
12.4
10.3
10
0
l/s
headm
3gpm/ton
2.5gpm/ton
kW
2gpm/ton
The existing building condenser pump has a pump head of 23.1 m of water. A reduction of the
flow rate to 2.5 gpm/ton reduces the pump head to 16.1 m of water and at 2.0 gpm/ton, the
pump head is then reduced to 10.3 m of water. At the lowest pump head, the pump power has
reduces by 70% from the existing condition. These numbers were all computed using the pump
affinitys law.
75
The existing building uses a constant chill water flow rate at the moment. Most
chillers requires constant flow chill water flow rate for it to operate safely without
causing the chiller to trip. Single primary only constant flow chill water is
commonly provided from the chiller to the AHU in the buildings due to its simplicity
in design. However, this kind of constant flow system is designed for the peak
cooling load of the year, therefore the system is designed at the highest flow rate
required to cool the building. Constant primary flow chilled water will continues to
flow at the full rate even when the building is running on part load.
There is a possibility to provide constant flow to the chiller while providing variable
flow to the AHU using a pipe configuration system called primarysecondary
variable flow system. The primary pump system refer to the pump/piping circuit
recirculating the chill water at a constant flow to the chiller, while the secondary
variable pump system refer to the pump/piping system that have a variable speed
drive (VSD) on the pump that will try to maintain the pipe pressure to deliver chill
water at the flow rate as needed by the buildings AHU load.
Energy is saved during part load condition when pump power is reduced in the
secondary pump to match the part load requirement of the AHU load.
Details
A constant flow primary pump with a head of 15m water was specified for this case
scenario with a variable secondary pump with a head of 7 m water was specified.
The low head at the secondary pump was due to the lower chilled water flow rate
applied in earlier cases.
101.6
Energy Saved
kWh/year/m (%)
0.0%
1,000
300
In the past, almost all chillers require constant flow of chill water for it to operate
without any problem. These days, chiller manufacturers have been able to
incorporate primary variable flow for their chillers.
This feature reduces initial cost because less pump requirement (as compared to a
primary/secondary system) and reduces operating cost as well due to reduced chill
water flow rate (i.e. it is not required to circulate the full flow rate through the
chiller at part load condition anymore).
Details
101.4
Energy Saved
kWh/year/m (%)
0.1%
4,000
1,300
77
Efficiency [%]
End Suction
(incl. vertical
&
close
impeller types)
[%]
Horizontal /
Vertical split
casing
(centrifugal
and
close
impeller types)
[%]
50 60
65 75
75 80
78 82
80 85
83 87
83 87
-
73 76
75 79
75 79
78 82
78 82
78 83
80 86
82 86
80 88
100
110 250
300 450
460 600
700 1000
1100 1500
1600 2500
2600 3600
3700 4000
> 5000
Vertical
multistage
&
Horizontal
multistage
/
Close Coupled
(close impeller
types)
[%]
55 75
68 75
70 75
Submersible
(semi
open
and
open
impeller types)
[%]
48 55
48 55
55 65
55 65
65 72
60 68
60 70
70 75
75 80
75 80
Process
Pump
(open
impeller
types)
[%]
48 52
48 52
48 52
48 52
48 52
-
For a flow rate of 1100 to 1500 gpm, a pump efficiency of 83 to 87% is shown to be
available in the market.
Details
It was possible to compute the pump total efficiency (motor and pump) from the
measured flow rate, pump head and power consumption of the pump motor. The
pump total efficiency computed was 40% from the measured numbers.
Assuming that the motor efficiency is at 80%, the existing pump efficiency is
computed to be 50%.
In this case the chilled water pump efficiency was raised to 85%.
Saved
0.3%
10,000
3,600
Budget
Available
for RM 14,300 / pump
Investment (RM)
2 existing chill water pump in plant room
Remarks:
The computed chill water pump efficiency of 50% is quite low, even for a 20 years old pump.
Further check reviewed that the minimum straight length of pipe of 5~6 pipe diameter before
the suction of pump is not followed in the existing installation as shown by the pictures below.
78
This installation mistake causes the efficiency of the pump to be lower than it should be. It
should also be noted that this mistake is also seen in many new buildings and seems to be one of
the bad industry practice that need to be addressed.
The budget available to improve pump efficiencies is approximately RM 14,300 per pump. This
would approximately cover the entire new pump cost. However, the earlier reduction of flow
rate provided a much higher budget to replace the pump in the 1st place. Therefore, this is a
budget to choose a better efficiency pump.
79
100
110 250
300 450
460 600
700 1000
1100 1500
1600 2500
2600 3600
3700 4000
> 5000
Efficiency [%]
End Suction
(incl. vertical
&
close
impeller types)
[%]
Horizontal /
Vertical split
casing
(centrifugal
and
close
impeller types)
[%]
50 60
65 75
75 80
78 82
80 85
83 87
83 87
-
73 76
75 79
75 79
78 82
78 82
78 83
80 86
82 86
80 88
Vertical
multistage
&
Horizontal
multistage
/
Close Coupled
(close impeller
types)
[%]
55 75
68 75
70 75
Submersible
(semi
open
and
open
impeller types)
[%]
Process
Pump
(open
impeller
types)
[%]
48 55
48 55
55 65
55 65
65 72
60 68
60 70
70 75
75 80
75 80
48 52
48 52
48 52
48 52
48 52
-
For a flow rate of 1100 to 1500 gpm, a pump efficiency of 83 to 87% should be
available in the market.
Details
It was possible to compute the pump total efficiency (motor and pump) from the
measured flow rate, pump head and power consumption of the pump motor. The
condenser pump total efficiency was also computed to be 40% from the measured
numbers.
Assuming that the motor efficiency is at 80%, the existing pump efficiency is
computed to be 50%.
In this case the condenser water pump efficiency was raised to 85%.
100.3
Energy Saved
kWh/year/m (%)
0.4%
16,000
5,500
81
The EFF 1, motor efficiency for 7.5 kW, is listed by the Energy Efficiency Guideline in
Malaysia to be higher than 90.1%.
Details
The existing assumption of 80% for both the chilled water pump motor and
condenser water pump motor was improved to 90% for this simulation case.
100.1
Energy Saved
kWh/year/m (%)
0.1%
4,000
1,400
Remarks:
The available budget of RM 2,860 per motor should be more than adequate to pay for a higher
efficiency new motor with efficiency higher than 80%.
Motor efficiency is not exactly constant at different part load. A sample efficiency curve of a
motor is provided below. Motor efficiency is fairly constant from full load until 30% of the full
load. At less than 30% of motor full load, the motor efficiency drop significantly.
82
The Malaysian Energy Efficiency and Conservation Guideline for Malaysian Industry
provided the following data for a 600 HRT cooling tower.
Cooling Tower Type
@ Pump
Head (m)
ROUND
COUNTERFLOW
SINGLE CELL
600
0.025
SQUARE COUNTERFLOW
SINGLE CELL
600
0.0357
3.7
SQUARE COUNTERFLOW
MULTICELL
600
0.025
3.4
SQUARE
CROSSFLOW
SINGLE CELL
600
0.0294
4.4
SQUARE
MULTI CELL
600
0.0275
3.3
CROSSFLOW
Details
The cooling tower in Block F building was measured to consume 0.0599 kW/HRT
for the existing cooling tower. This corresponded to the measured 19.4 kW of fan
power used by the cooling tower.
In this simulation case, the cooling tower power consumption is reduced to 0.0275
kW/HRT. This reduces the fan power to 10 kW.
99.1
Energy Saved
kWh/year/m (%)
0.7%
25,000
8,800
83
The new data available from the published energy efficiency guideline showed that it is possible
to reduce the cooling tower fan consumption by half as shown in the table provided in the
general descriptions. Care should be taken when selecting cooling tower to ensure that the
efficiency gain by the fan is not at the expense of the pump head. The energy caused by the
pump head can be computed using the condenser flow rate and pump total efficiency for the
cooling tower.
84
A variable speed drive (VSD) can be install on the cooling tower fan to reduce its
speed when the temperature setpoint of the return condenser water to the chiller is
achieved. This is done by installing a temperature probe on the bottom of the
cooling tower, measuring the temperature of the water at the bottom of the cooling
tower. Reducing the fan speed will reduce fan energy consumption by the cooling
tower.
However, the lower the temperature of condenser water returning back to the
chiller, the more efficient the chiller will become. Similarly, a higher condenser
water temperature is returned to the chiller, the chiller would become less efficient.
In climate where the wetbulb temperature of the air changes drastically due to
seasonal changes, it has been shown that it is beneficial to use a VSD on the cooling
tower. However, in Malaysia hot and humid climate, where the wetbulb
temperature is fairly constant, it is not known if it will provide the same amount of
savings.
Therefore, case study 31 to 36 is a test on the potential benefit of using VSD on the
cooling tower in this climate zone.
Details
A variable speed drive is specified for the cooling tower to reduce fan speed when
the return condenser water temperature as reached 30.5C.
99.4
Energy Saved
kWh/year/m (%)
0.2%
7,000
2,300
The chart above shows the annual heat rejection (cooling tower + condenser pump) energy as
simulated by this study. The condenser pump energy is constant in all the cases shown in the
chart above. Therefore, the energy differences between the cases are caused by the cooling
tower only. The highest cooling tower fan energy reduction is case 31, where a VSD is used to
reduce fan speed once the condenser return water temperature reaches 30.5C.
Cases
Case 29
Case 30
Case 31
Case 32
Case 33
Case 34
Case 35
Case 36
Short Descriptions
A nonefficient cooling tower
An efficient cooling tower
VSD fitted on cooling tower with set point temperature of 30.5C
VSD fitted on cooling tower with set point temperature of 29.5C
VSD fitted on cooling tower with set point temperature of 28.5C
VSD fitted on cooling tower with set point temperature of 27.5C
VSD fitted on cooling tower with set point temperature of 26.5C
No VSD, but larger cooling tower with set point temperature of 25C (i.e. get the
return condenser water temperature as low as possible).
The chart below indicates that the lower the setpoint temperature for return condenser water
on the VSD for the cooling tower, the chiller energy consumption reduces further, indicating
that the lower return condenser water temperature increases the efficiency of the chiller.
Meanwhile, the chart above shows that the fan power of the cooling tower increases as the set
point temperature is reduces, indicating that more fan power is required to achieve the set
point temperature. At the setpoint temperature of 26.5C the fan on the cooling tower is
practically running full speed at all time.
86
The chart below display the annual total chill water system energy used for cases 29 to 36.
It is therefore more practical to consider the overall chill water system energy efficiency
scenario that would account for both the cooling tower fan energy, chiller energy and pumps
energy used by the chilled water system as shown in the chart above. Using a VSD on the cooling
tower with condenser return temperature set point of 30.5C (Case 31) is more inefficient than
the conventional cooling tower as in Case 30. The chilled water system energy reduces as the set
point temperature for the return condenser water is reduced for the cooling tower with VSD on
it. At the set point of 26.5C (Case 35), the cooling tower fan is practically running full speed at
all time.
This result indicates that it would be better to try to reduce temperature of the return
condenser water than to reduce the fan speed of the cooling tower for better energy efficiency.
In case 36, an oversized constant speed cooling tower is used instead to try to keep the return
condenser water temperature as low as possible at all time. This seems to be practical solution
as the energy efficiency lost is significantly small as compared to a cooling tower with VSD set to
26.5C, because there is no need to install a VSD on the outdoor fan which may have higher cost
due to weather proofing requirement and perhaps more maintenance issues as well.
87
Details
A variable speed drive is specified for the cooling tower to reduce fan speed when
the return condenser water temperature as reached 29.5C.
98.9
Energy Saved
kWh/year/m (%)
0.3%
11,000
3,900
88
Details
A variable speed drive is specified for the cooling tower to reduce fan speed when
the return condenser water temperature as reached 28.5C.
98.6
Energy Saved
kWh/year/m (%)
0.2%
7,000
2,500
89
Details
A variable speed drive is specified for the cooling tower to reduce fan speed when
the return condenser water temperature as reached 27.5C.
98.5
Energy Saved
kWh/year/m (%)
0.1%
2,000
800
90
Details
A variable speed drive is specified for the cooling tower to reduce fan speed when
the return condenser water temperature as reached 26.5C.
98.4
Energy Saved
kWh/year/m (%)
0.0%
1,000
500
91
In case 35, the VSD on the cooling tower have a setpoint temperature of 26.5C. The
results showed that it has the lowest airconditioning system energy consumption.
This showed that is more important to provide a lower temperature on the
condenser return temperature to the chiller than to save cooling tower fan energy.
In addition, at the setpoint of 26.5C, the cooling tower fan was practically running
full speed at all time.
Details
An oversized cooling tower was used with slightly higher power consumption to
cool the condenser water to coolest possible.
The cooling tower fan power was increased 10% from 10 kW to 11 kW in this
simulation study to mimic an oversized cooling tower.
98.6
Energy Saved
kWh/year/m (%)
0.1%
4,000
1,300
92
In recent years, there has been a gaining market acceptance to reduce general
lighting lux level in offices down to 150 lux level and then supplement lighting need
of building occupant with personal task light to provide up to 800 lux level when
required. This option allows each individual in the building to control their own
lighting preference at their own desk.
Case study 37 to 39 test the option of using task lights in Block F while reducing the
general lighting lux level down to 200 lux level. Reducing lux level in a building
would mean that it is possible to reduce the number of lamps in the building until it
achieves a lux level of 200 lux.
In general task light comes in 19, 11 or 5 W per task light.
Details
Allowing the general lighting level to be reduced from 350 lux level (existing
building scenario) at 9 W/m lighting power density to 200 lux level, allows the
general lighting power density to be reduced to 5.1 W/m via a process of de
lamping or redesigning the lighting layout entirely by removing unnecessary light
fittings for an average 200 lux level office building.
Then a task light of 19 W per person is added to the simulation. 80% of the task
lights are assumed to be switched on. 20% is assumed to be switched off due to
reasons that building occupants may not be in the office or is using the computers
and therefore, do not need more than 200 lux level. For a building occupant no of
1,000 people, 80% of 19 W of lighting per person works out to only 0.43 W/m of
the office space.
The average office lighting power use is now reduced to 5.57 W/m instead of the
5.88 W/m as in previous cases.
91.9
Energy Saved
kWh/year/m (%)
4.1%
156,000
54,600
=====================================================================
TABLE 2
=====================================================================
TASK CATEGORIES AND REFERENCE ILLUMINANCE LEVELS
ILLUMINANCE
CATEGORY
DIFFICULTY OF
VISUAL TASK
IMPORTANCE OF
SPEED & ACCURACY
non critical / critical
---------------------------------------------------------------------A
MOVEMENT THROUGH PUBLIC SPACES
50
- LUX - 75
(5) - FC - (7)
---------------------------------------------------------------------B
INFREQUENT READING OR WRITING;
100
150
High contrast & large size
(9)
(14)
---------------------------------------------------------------------C
FREQUENT (& easy) READING OR WRITING;
200
300
High contrast & large size
(19)
(28)
(e.g. typewritten page)
---------------------------------------------------------------------D
MODERATELY DIFFICULT READING OR WRITING; 300
450
low contrast or small size
(28)
(42)
(e.g. penciled mechanical drawings)
---------------------------------------------------------------------E
DIFFICULT READING OR WRITING;
500
750
low contrast & small size
(46)
(70)
(e.g. poor copy of a blueprint)
----------------------------------------------------------------------
=====================================================================
TABLE 2a
=====================================================================
ADJUSTMENTS TO REFERENCE ILLUMINANCES
(for different task background reflectences and worker ages)
AGE (A, in years)
> 30
30-40
40-50
50-60
60+
---------------------------------------------------------------------TASK
R > 0.8
|
1.0
1.2
1.5
2.0
3.1
BACKGROUND
0.8 - 0.6
|
1.2
1.5
1.9
2.6
3.9
REFLECTANCE
0.6 - 0.4
|
1.7
2.0
2.5
3.4
5.2
(R)
0.4 - 0.2
|
2.5
3.0
3.8
5.1
7.8
0.2 or less |
5.0
6.0
7.6
10.2
15.6
----------------------------------------------------------------------
The proposed strategy for Case 37 to 39, is to reduce the general lighting level down to the
minimum level of 200 lux and supplement with a task light that would allow the building
occupants themselves to choose their own preference of lighting level on their own desk,
allowing building occupants to light up their desk up to 800~1,000 lux when they need to.
It is actually still within the IES recommended illuminance to provide as low as 100150 lux for
general lighting, while at all desks, a task light is provided for illuminance up to 1,000 lux when
required. General office spaces (not at the desk), would be considered Category B space for
infrequent reading or writing spaces, such as access way between desks. Infrequent reading
may be made by building occupants while walking or standing on the access way between
desks.
94
Reducing lux level down to 200 lux illuminance in Malaysia may be uncomfortable to those that
are used to having 500 lux or more illuminance of general lighting. A few studies have shown
that it may be more important to have a brighter ceiling and walls than the actual lux level on
the desk. This may be done by using T5 pendent light fittings that light up the ceiling as well as
the desk and supplement the wall with wall lights to ease the occupants initial discomfort
feelings.
RMBudgetAvailable
RM
400
200
0
RMBudget
19W
11W
5W
273
300
320
95
Details
Allowing the general lighting level to be reduced from 350 lux level (existing
building scenario) at 9 W/m lighting power density to 200 lux level, allows the
general lighting power density to be reduced to 5.1 W/m via a process of de
lamping or redesigning the lighting layout entirely by removing unnecessary light
fittings for an average 200 lux level office building.
Then a task light of 11 W per person is added to the simulation. 80% of the task
lights are assumed to be switched on. 20% is assumed to be switched off due to
reasons that building occupants may not be in the office or is using the computers
and therefore, do not need more than 200 lux level. For a building occupant no of
1,000 people, 80% of 11 W of lighting per person works out to only 0.43 W/m of
the office space.
The average office lighting power reduces to 5.57 W/m.
91.2
Energy Saved
kWh/year/m (%)
0.4%
15,000
5,400
Additional RM 30/person
RMBudgetAvailable
RM
400
200
0
RMBudget
19W
11W
5W
273
300
320
96
Details
Allowing the general lighting level to be reduced from 350 lux level (existing
building scenario) at 9 W/m lighting power density to 200 lux level, allows the
general lighting power density to be reduced to 5.1 W/m via a process of de
lamping or redesigning the lighting layout entirely by removing unnecessary light
fittings for an average 200 lux level office building.
Then a task light of 5 W per person is added to the simulation. 80% of the task lights
are assumed to be switched on. 20% is assumed to be switched off due to reasons
that building occupants may not be in the office or is using the computers and
therefore, do not need more than 200 lux level. For a building occupant no of 1,000
people, 80% of 5 W of lighting per person works out to only 0.19 W/m of the office
space.
The average office lighting power use reduces to 5.34 W/m .
90.8
Energy Saved
kWh/year/m (%)
0.3%
11,000
4,000
Additional RM 20/person
RMBudgetAvailable
RM
400
200
0
RMBudget
19W
11W
5W
273
300
320
97
The toilets in Block F have natural daylight because all the toilets have a faade wall
with external windows. It is normally bright during working hours. However, since
the building is occupied from 7 am onwards, the toilet lights would be switched on
during those hours because the outdoor light is still low at 7 am. After the lights are
switched on early in the morning, it would normally remain on for the rest of the
day because no one is directly responsible for such public spaces such as the toilets.
The use of daylight sensor will automatically switch off the lights when it detects
that there is adequate lights in the toilet.
Details
Assumption is made in this case that 75% of the toilet lights can be switched off
whenever adequate daylight is available.
25% of the lights are assumed not to be linked to the daylight sensor because it may
be used by the cubicles that may not benefit from daylight.
90.6
Energy Saved
kWh/year/m (%)
0.1%
3,000
1,200
98
3.43 CASE 41: IMPROVED AIRTIGHTNESS & ADD HEAT RECOVERY WHEEL
General
Descripti
ons
If the building is retrofitted to be airtight, with an infiltration rate of 0.1 ach (air
change per hour), it would then be possible to consider the use of heat recovery
wheel to precool and predry the fresh air intake into the building with the
exhausted air from the building.
The heat recovery wheel reduces energy consumption in building by reducing the
cooling that is required of the fresh air intake by using the free exhaust air to pre
cool and predry it before it reach the AHU.
Details
Two heat recovery wheels with an efficiency of 50% for both sensible and latent
heat exchange were modeled for this case. One heat recovery wheel is used for each
stack of AHU in Block F.
In addition, 700 W of power consumption of each of the heat recovery wheel was
also modeled. This power consumption is required to rotate the wheel.
A pair of fan was also modeled for each the heat recovery wheel. A fan total
efficiency of 50% and a total pressure loss of 200 Pa were allocated for each fan to
compute the power requirement based on the flow rate supplied. These fans
provides the pressurized fresh air intake for all the AHU and also provides the
negative pressure to exhaust air from the toilets.
88.1
Energy Saved
kWh/year/m (%)
1.5%
58,000
20,400
10
ducts can be installed outside the building, locating it exactly where the fresh air intake is
brought into the building. The exhaust air duct can be placed at the existing exhaust fan location
of each toilet. Care should be taken that the volume of air passing through the toilet is not too
high that it causes discomfort draft sensation. It is also important to insulate the duct located
outside the building to minimize the heat gain from the exposure to the outdoor environment.
100
The existing single glazing in block F has a measured VLT (visible light
transmission) of approximately 10%. For a heavily tinted single glazing with a VLT
of only 10%, a typical SC (shading coefficient) is approximately 0.43. The lower the
SC value, the less heat is transmitted into the building. For a single glazing, without
lowemissivity properties, the SC value of 0.43 is as low as it can get.
Unfortunately, this glazing allows too little light for any effective use of daylight
harvesting in this building.
The above are pictures taken from Block F, providing an indication of the heavily
tinted glazing and blind usage. Note that, even with such low VLT values on the
glazing, window blind is still required to be used to prevent glare in the offices.
Details
The glazing SC value was changed from 0.43 to 0.95 for a clear glazing.
89.3
0.7%
27,000
9,300
10
It is also recommended to consider the use of lowe single glazing when this option is
considered for the building. The additional cost for a lowe single glazing is only marginally
higher than a typical tinted single glazing. The energy saved from the use of lowe single glazing
would be similar to Case 45, the use of film on clear glazing.
102
Changing the glazing to clear would allow daylight to be harvested. Energy efficiency
is gained when daylight is harvested and electrical lights are switched off.
Details
Daylight studies showed that is possible to harvest daylight up to 3.5 m depth from
the faade using simple horizontal venetian blind on the windows. These horizontal
blinds would allow glare to be controlled by tilting it to a level where the building
occupant view of the sky is reduced until visual comfort is achieved. Light are
allowed to bounce off the blinds into the room. This would require the louvers (of
the blind) to be reflective white or mirror like finish on the top side and non
reflective white paint on the bottom side of the louvers for glare prevention.
To ensure that electrical lights are switched off when daylight is available, it is
recommended to use daylight sensor. A daylight sensor can be programed to switch
electrical lightings off whenever daylight is adequate to lit up the space.
A depth of 3.5m daylight harvesting in this building would cover approximately 40%
of the office floor area. An assumption is made in the simulation that 40% of the
office lightings are switched off when outdoor horizontal illumination is above
10,000 lux level.
BUILDING BEI (kWh/m/year)
85.6
Energy Saved
kWh/year/m (%)
2.3%
86,000
30,200
10
It is very important to emphasis that daylight harvesting will only work in this climate when
glare comfort is addressed. It is proposed to use simple horizontal venetian blinds to harvest
daylight in Block F. These blinds should be tilted from horizontal (fully open position) until the
building occupant is visually comfortable from their usual sitting position. Normally this would
be between 20~35 from horizontal. The lower the tilt, the more daylight that can be harvested
deeper into the space, allowing more lights to be switched off when daylight is available.
The available budget of RM 120/m of glazing area, should be enough to pay for the horizontal
blinds required to benefit from this efficiency gain.
104
The installation of light a light shelve on the parapet wall level on the outside would
allow more light to be captured for the building. In addition, by tilting the ceiling
surface near the faade allows the capture light to direct it deeper into the office
space as shown in the diagram below.
Simulation study showed that it is possible to harness daylight another meter deep
from the faade, making the daylight harvested level to be 4.5m depth.
Details
A depth of 4.5m daylight harvesting in this building would cover approximately 55%
of the office floor area. An assumption is made in the simulation that 55% of the
office lightings are switched off when outdoor horizontal illumination is above
10,000 lux level.
Light shelve was modeled in Radiance to test the depth of daylight harvested.
84.6
Energy Saved
kWh/year/m (%)
0.6%
22,000
7,600
10
Details
The glazing properties was changed to a SC of 0.51 and an inside emissivity of 0.78
as provided by the specification of 3M Prestige 50 film. This selection was made
because the daylight harvesting requirement from the simulation study showed that
a minimum VLT of ~50% is required to maintain depth of daylight harvested.
83.7
Energy Saved
kWh/year/m (%)
0.6%
23,000
7,900
10
High performance double glazing has a better performance in terms of light to solar
heat gain ratio than performance window films. While allowing the same amount of
light to pass through the glazing, the high performance double glazing (spectrally
selective) has a lower SC (shading coefficient).
A typical high performance double glazing shown below displayed a Coloured
Indigo 48T double glazing with a VLT of 48% and a SC of 0.33.
Details
82.7
Energy Saved
kWh/year/m (%)
0.6%
23,000
7,900
10
107
The uninsulated flat roof is insulated with 50mm polystyrene foam. This will
reduce the Uvalue of the roof from 3.44 to 0.51 W/mK. Insulating the roof will
reduce energy consumption of the building by reduction of heat gain through the
roof during daytime.
Details
Materials Descriptions
Stone Chippings
Water Proofing Membrane
Dense Concrete Slab
Total Thickness
Thickness (mm)
10
5
150
~165
Materials Descriptions
Stone Chippings
Water Proofing Membrane
Polystyrene Foam
Dense Concrete Slab
Total Thickness
Thickness (mm)
10
5
50
150
~215
82.4
Energy Saved
kWh/year/m (%)
0.2%
8,000
2,700
10
108
The flat roof is insulated with 100mm polystyrene foam. This will reduce the U
value of the roof to 0.28 W/mK. Insulating the roof will reduce energy
consumption of the building by reduction of heat gain through the roof during
daytime.
Details
Materials Descriptions
Stone Chippings
Water Proofing Membrane
Polystyrene Foam
Dense Concrete Slab
Total Thickness
Thickness (mm)
10
5
100
150
~265
82.1
Energy Saved
kWh/year/m (%)
0.2%
7,000
2,400
10
109
The flat roof is insulated with 100mm polystyrene foam. This will reduce the U
value of the roof to 0.19 W/mK. Insulating the roof will reduce energy
consumption of the building by reduction of heat gain through the roof during
daytime.
Details
Materials Descriptions
Stone Chippings
Water Proofing Membrane
Polystyrene Foam
Dense Concrete Slab
Total Thickness
Thickness (mm)
10
5
150
150
~315
82.3
Energy Saved
kWh/year/m (%)
0.2%
6,000
2,000
10
Thickness
UValue
(W/mK)
% Savings from
Previous step
47
50mm
0.51
0.2%
48
100mm
0.28
0.2%
49
150mm
0.19
0.2%
110
Details
81.1
Energy Saved
kWh/year/m (%)
0.8%
28,000
10,000
NA
Temperature (C)
06:00
12:00
18:00
00:00
Legend:
Case 14 Comfortable Base Condition.
Case 49 Improved Building.
Case 50 Increased Air Temperature.
Dry Resultant Temperature = Operative Temperature
111
31
Temperature (C)
30
29
28
27
26
25
24
23
22
00:00
06:00
12:00
18:00
00:00
OperativeTemperatures
Dry resultant temperature: OFFICE1_F05 (c50_otemp25.aps)
Dry resultant temperature: OFFICE1_F05 (c49_rf_in150.aps)
Dry resultant temperature: OFFICE1_F05 (c14_tsetpt_higher.aps)
The two (2) charts above showed that although the air temperature was increased in Case 50,
the operative temperature is still the same as Case 14, where the air temperature was lower.
This is because in Case 49 & 50, the mean radiant temperature of the building fabric and from
the lights has reduced. Therefore, in Case 50, with the increase in air temperature, the comfort
condition is still the same as in Case 14 with lower air temperature.
Energy efficiency gain is obtained due to the higher air temperature provided to the building in
this case.
112
Details
The chill water system was resized at the current scenario where the small power
peak load is 4.1 W/m.
80.7
Energy Saved
kWh/year/m (%)
0.3%
10,000
3,400
NA
Sizing the peak chiller requirement of the base case (comfortable scenario), the chiller capacity
should have been approximately 1,000 ton capacity. This huge capacity was required to cater
for the building airleakages and other inefficiencies as listed in this study. However, the
113
114
It was felt that resizing the HVAC system with a peak small power load of 4.1 W/m
may not leave room for future expansion in the building for higher density
occupancy. The HVAC system was then resize with an assumption of 12 W/m as the
small power peak load.
Details
The HVAC system was resized assuming 12 W/m of peak small power load but
energy simulation was conducted using actual measured small power load of 4.1
W/m.
80.9
Energy Saved
kWh/year/m (%)
0.1%
5,000
1,700
NA
NA
115
Details
The small power load is returned back to the measured value of 4.1 W/m during
office hours and 1 W/m (25% of the peak load) during nonoffice hours. Previously
it was set to 4.1 W/m during office hours and 0.41 W/m (10% of the peak load)
during nonoffice hours.
84.6
Energy Saved
kWh/year/m (%)
2.3%
85,000
29,900
NA
116
Room
No./Description
No. of
lamps
/
fitting
17
17
17
17
17
17
17
17
17
Staircase L
Office R
Office (Director)
Office (Director)
Meeting Room
Meeting Room
Meeting Room
Meeting Room
Eng Accreditation
2
3
3
3
3
1
1
1
3
No. of
fitting
s
Total
No. of
lamps
Watts
(lamp+
ballast)
2
4
1
1
6
12
8
8
3
4
12
3
3
18
12
8
8
9
20
40
20
40
40
26
20
18
20
Total
Watts
No. of
Faulty
Lamps
Total
Watt
for
Faulty
Lamps
Actual
Lighting
Power
(W)
80
480
60
120
720
312
160
144
180
0
0
0
0
0
0
2
1
0
0
0
0
0
0
0
40
18
0
80
480
60
120
720
312
120
126
180
117
This is just a test scenario to predict the BEI of the building when the small power is
increased to 12 W/m as it would be in a densely occupied building.
Details
The small power was raised to 12 W/m with a base load at night and weekend of
25% of this daytime peak value.
117.2
20.2%
762,000
266,800
NA
118
Power Usage Effectiveness (PUE) and its reciprocal Data Center infrastructure
Efficiency (DCiE) are widely accepted benchmarking standards proposed by the
Green Grid to help IT Professionals determine how energy efficient data centers are,
and to monitor the impact of their efficiency efforts. Benchmarking tool is useful as
an indicator of data center energy efficiency.
Total Facility Power kW
IT Equipment Power kW
IT Equipment Power kW
Total Facility Power kW
Today, there exist many demonstration data center around the world where more
than 50% energy saving has been made. This can also be seen from the PUE indexes
showing PUE values from 1.2 to 3.0, indicating that very inefficient data center use
more than double the energy as compared to a very efficient data center.
The use of efficient IT equipment will significantly reduce cooling requirement
within the data center, which consequently will reduce the HVAC equipment needed
to cool them. Purchasing servers equipped with energyefficient processors, fans,
and power supplies, highefficient network equipment, consolidating storage
devices, consolidating power supplies, and implementing virtualization are the most
common ways to reduce IT equipment loads within a data center.
Details
An assumption that the data center annual energy consumption was reduced by
25%.
107.3
Energy Saved
kWh/year/m (%)
6.1%
231,000
80,700
data center where the current data center in Block F reduces its energy consumption by 25%.
This energy efficiency gain in data center may be achievable by the implementation of server
virtualization.
Virtualization technology is transforming todays IT community, offering new possibilities to
improve the performance and efficiency of IT infrastructure by a dynamic mapping of the PC
resources, enabling to run multiple applications and operating systems on a single physical
system.
120
Details
Today, there exist many demonstration data center around the world where more
than 50% energy saving has been made.
The use of efficient IT equipment will significantly reduce cooling requirement
within the data center, which consequently will reduce the HVAC equipment needed
to cool them. Purchasing servers equipped with energyefficient processors, fans,
and power supplies, highefficient network equipment, consolidating storage
devices, consolidating power supplies, and implementing virtualization are the most
common ways to reduce IT equipment loads within a data center.
An assumption that the data center annual energy consumption was reduced by
50%.
97.4
Energy Saved
kWh/year/m (%)
6.1%
231,000
80,700
121