Beruflich Dokumente
Kultur Dokumente
Standards affected:
NR/L3/CIV/020: Design of Bridges [Issue 1]
1 Reason for issue
Parapet height requirements have been reviewed following a detailed assessment of railway risks that can
be partially mitigated by parapets on overline bridges and footbridges. The research indicates that for new
overline structures or parapet upgrades, an increased parapet height will often be appropriate to mitigate the
risks so far as is reasonably practicable (SFAIRP).
In determining the revised parapet height requirements, consideration has also been given to:
Network Rails initiatives to reduce suicide, trespass, electrocution, vandalism and cable theft on the
railway;
the increased use of overhead electrification on the network in the future; and
the potential automation of railway operations in the future.
Electrical (a.c.) protection clearance requirements for structures over OLE have been updated to align with
recently published Railway Group Standard GL/RT1210: AC Energy Subsystem and Interfaces to Rolling
Stock Subsystem.
Electrical (d.c.) protection clearance requirements for structures over OLE have been clarified.
2 Scope
This Letter of Instruction applies to:
a) all schemes introducing a new energy sub-system;
b) all schemes introducing upgrades or renewals of existing energy sub-systems, where renewal and
upgrade is as defined in the Railway (Interoperability) Regulations 2011;
c) all bridges that are renewed, up-graded or newly installed;
d) all outside party bridge schemes yet to commence detailed design.
With the exception of installation or replacement of fencing or parapet mesh infill/extensions, minor works or
non-structural repairs are not subject to this Letter of Instruction.
This Letter of Instruction shall be complied with by Network Rail and its contractors from the compliance date
of publication. When this Letter of Instruction is implemented, it is permissible for projects that have formally
completed GRIP Stage 3 (Option Selection) to continue to comply with the issue of any relevant Network
Rail and Railway Group Standards current when GRIP Stage 3 was completed reached (unless the
designated standard owner has stipulated otherwise in the accompanying briefing note) and not to comply
with the new requirements contained herein with the exception of schemes subject to authorisation under the
Interoperability Regulations. Applicable schemes (or parts thereof) that are yet to be authorised under the
Railway (Interoperability) Regulations are to retrospectively comply with this Letter of Instruction.
Page 1 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
3 Changes
Clause/subclause
Change
Reference
documentation
1300/2014/EU
1301/2014/EU
1303/2014/EU
GL/RT1210
GL/GN1610
GM/RT1041
British Standards
BS EN 50122
Page 2 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
7.2
Strengthening,
alteration and
repair works
9.1 Regulations,
legislation and
standards
9.7 Legal
obligation and
commercial
liability issues
liabilities;
load-carrying obligations;
9.9.4 Electrical
protection,
earthing and
bonding
The design of a structure shall minimise the risk of electric shock so far as
is reasonably practicable (SFAIRP) and is obliged to meet the requirements
of The Electricity at Work Regulations (notably regulations 4(1) and 7).
Page 3 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
The design of a structure carrying or passing over a.c. electrified lines shall
comply with the electrical and mechanical requirements of GL/RT1210: AC
Energy Subsystem and Interfaces to Rolling Stock Subsystem (see also
10.10).
The design of a structure carrying or passing over d.c. electrified lines is
obliged to comply with the electrical protection requirements of
GE/RT8025: Electrical protective provisions for electrified lines until
publication of GL/RT1212: DC Energy Subsystem and Interfaces to Rolling
Stock Subsystem which the design is then obliged to complied with.
Passive provision for potential future a.c. electrification of the railway shall
be provided for new structures that carry or span over non-electrified or
d.c. electrified lines unless located on a line where planned electrification is
not reasonably foreseeable. The Designer shall agree with Network Rail,
the extent of passive provision to be provided prior to AiP submission.
Bonding that is required exclusively for signalling purposes is outside the scope
of this standard.
The design of earthing and bonding systems for a structure (including its
metallic elements and services) is obliged to meet the requirements of:
Exposed metal elements and metal services shall be bonded to the traction
return rail or earth wire. Concrete reinforcement (including pre-stressing
anchorages) shall be bonded only if it is accessible or electrically connected
to accessible metalwork.
Page 4 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
the reinforcement in substructures for earthing.
Where required by Network Rail, the design shall include provision for (a) fitting
bonding/earthing studs to the structure, and (b) installing remote earth test-points.
Where a structure spans an overhead electrified railway, the design shall
consider the waterproofing of the structure and managing run-off to prevent
damage by water draining on to, or in the proximity of, the overhead
electrification, causing flash over.
Where a new Outside Party structure spans an overhead electrified railway,
or existing Outside Party structure spans a new or upgraded overhead
electrification system, electrical protection (clearances and earthing and
bonding system) shall be in accordance with the principles of GL/RT1210
and NR/SP/ELP/21085 and be agreed with the Outside Party.
The Designer shall strive to produce an effective and economic earthing and
bonding system that takes due account of the traction power supply system,
overhead line equipment, and other electrical components and equipment at the
site. The design documentation for the system shall meet the requirements of
NR/SP/ELP/21085 and is subject to acceptance by Network Rail.
9.9.5 Protection
from stray
currents
10.8 Security
and access
Where third rail d.c. electrification is present, the design shall consider the risk of
corrosion generated by stray currents. The Designer shall agree with Network
Rail, prior to the AiP submission, any stray current mitigations that are to be
incorporated into the design.
Jumping or falling off, trespass via, or objects thrown over bridge parapets,
account for the majority of structure related risks to the railway.
Bridge parapets and fencing in the vicinity of a structure shall be designed
such that unauthorised access to the railway infrastructure is prevented so
far as is reasonably practicable, and are obliged to be compliant with The
Railway Safety (Miscellaneous Provisions) Regulations 1997 (Regulation
3)).
The design of the layout of fencing in the vicinity of a structure shall be such that
the fences and structure form an adequate and continuous barrier against
trespass onto the railway. The requirements for providing security to the railway
are given in NR/L2/TRK/5100: Management of Fencing and Other Boundary
Measures.
Consideration shall be given to providing (a) access gates in fences, and (b)
access steps down earthworks, near to a structure to facilitate its examination
and maintenance.
To reduce the risk of unauthorised access to the railway, people shall be
deterred from climbing the parapets on an overline bridge or footbridge
(for example, by increasing the height of parapets, attaching mesh screens,
installing anti-vandalism cages or anti-trespass spikes) and accessing the
outer faces of the overline structure.
Details of the access arrangements (provision and prevention) shall be identified
in the AiP submission.
10.9 Road
restraint systems
Page 5 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
retaining walls.
The height of new/renewed vehicle parapets above adjoining paved surface
over the railway shall not be less than the following:
1800mm for bridges over an automatic/driverless railway
1800mm for bridges frequently used by equestrian traffic
1800mm for bridges where there is a high risk of trespass or vandalism
or suicide
1800mm for parts of bridges over OLE where electrification protection
by safety clearance requirements are not achieved (see 10.10)
*1800mm for other overline bridges and upgraded parapets that span over
the railway where pedestrians, animals, pedal cycles and
vehicles drawn by animals are not excluded by Order (* see note
1 below)
1500mm for other bridges (e.g. motorway bridges and bridges not over
the railway where the above higher risk categories dont apply)
Note 1. For new or renewed overline bridges where pedestrians are not
excluded by Statutory Order, the 1800mm minimum height requirement
may be reduced to 1500mm where either the structure is sited at a lowrisk location, or the provision of 1800mm (min) high parapets over the
railway is not practicable or appropriate (e.g. due to geometrical,
technical, safety or planning limitations), provided that (a) the height
reduction has been justified by appropriate site-specific risk
assessment, and (b) the justification is included with supporting
evidence within Form 001 and Form 002 design submissions and is
accepted by the Network Rail Asset Manager (Civils) and (for reduced
height parapets over OLE) Network Rail Asset Manager (E&P).
For the purposes of the above reduced requirement, low-risk locations
are typically considered to have the following attributes:
-
Low risk of route crime (e.g. away from built up areas, schools,
other frequently used pedestrian routes, train depots and other
crime-susceptible installations); and
Low risk of suicide (footway less than 10m above the tracks); and
No/low risk of electrocution (e.g. no existing or planned OLE or
where protection by safety clearance [to OLE] is provided).
Where the width of the parapet top is greater than 100 mm but less than
about 250 mm (as would be the case with reinforced concrete
construction), one of the profiles given in BS 6779-2: Highway parapets
Page 6 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
for bridges and other structures. Part 2. Specification for vehicle
containment parapets of concrete construction.
2
3
10.10 Parapets
over OLE
Where the width of the top of the parapet substantially exceeds 250 mm
(as would be the case with brick sandwich construction),
10.10.1
Protective provisions against direct contact with exposed live parts of the
overhead line equipment are obliged to comply with BS EN 50122-1,
Section 2.2 of GL/RT1210 and the requirements below.
The protective provisions against direct contact shall be by safety
clearances or, where the safety clearances are not achievable, by
obstacles. The maximum reasonably practicable value of electrical
clearance shall be provided.
The minimum electrical clearances specified in this sub-section are
minimum clearances under all operating conditions. Accordingly an
appropriate allowance for temperature and dynamic movements shall be
added to the specified minimum clearance values.
Return conductors (or feeder conductors for auto-transformer OLE system)
shall be treated as live parts unless adequately insulated. Where protection
by safety clearance or protection by obstacles cannot be achieved for these
elements, the return/feeder cables shall be insulated and shielded (as
appropriate) in accordance with GL/RT1210 clauses 2.2.2.5 and 2.2.3.3.
For protection by safety clearance, the minimum clearances shall be the
public area dimensions set out in EN 50122-1:2011+A1:2011 clause 5.2.1,
Figure 3 (for Low Voltage (LV) systems), and Figure 4 (for High Voltage (HV)
systems).
Where protection of exposed live parts by safety clearances is not
achievable or appropriate (e.g. due to disproportionate costs), electrical
protection by an obstacle shall be provided and of a construction to
prevent unintentional direct contact with a live part; requirements as
follows.
Page 7 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
a) The obstacle (parapet and any extension) shall be of construction and
height to meet the minimum requirements detailed in Figures 10.10.1 to
10.10.3 and additional requirements below.
(Different requirements apply for public and restricted areas and for HV
and LV equipment. Restricted areas are areas of Network Rail
infrastructure where access is controlled for authorised persons only.
Other areas (including roads/motorways where pedestrians are
prohibited by Order) are deemed public areas).
b) Obstacles in public areas shall be designed so that is it difficult to
climb, stand or to walk on. An increased obstacle height (above 1.8m)
shall be considered in areas prone to regular trespass or vandalism.
c) Obstacles shall be fixed reliably and with the use of tamper proof
fixings; they shall only be removable with tools. Obstacles shall be
secured so that the distance to the live parts is maintained.
d) The obstacle shall have no gap to the standing surface.
e) Where mesh extensions or infill is specified, mesh shall be in
accordance with Chapter 8 of BS 6779-1. Mesh constructions of plastic
coated metal shall not be utilised.
f)
10.10.2
10.10.3
Warning signs
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
intermediate signs where appropriate (e.g. for bridges spanning numerous
overhead electrified lines).
Electrocution warning signs are obliged to be in accordance with BS EN
ISO 7010 (Type W501.BS) and designed in accordance with BS ISO 3864-1.
The hazard triangle shall be accompanied by the supplementary text
Danger - Live wires below as shown in Figure 10.10.4.
Danger
Live wires below
Figure 10.10.4 Electrocution warning sign
Page 9 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
a) Public areas
Scenario 2
Full height solid
parapet
R 3.50
1.50 #
hs = h o
ho
0.60
R 2.25
hs 1.25
0.60
1.50
3.50
1.50 + d
1.50
Protection by
obstacle envelope
(ho 1.80m)
0.50
2.25
0.50
3.00
Scenario 1
Solid parapet with
mesh extension
0.50
0.50
Protection by
obstacle envelope
(ho 1.80m)
Protection by clearance
envelope (all decks)
Protection by clearance
envelope (all decks)
b) Restricted areas
Scenario 2
Solid or imperforate
parapet 1.80m
1.00
ho
0.60
0.60
d
R 2.25
0.50
2.25
0.50
0.50
3.00
Protection by
obstacle envelope
(ho 1.50m,
ho < 1.80m)
1.00 #
ho
3.50
R 3.50
1.50
Scenario 1
Solid or imperforate
parapet 1.50m - 1.80m)
Protection by clearance
envelope (all decks)
0.50
Protection by
obstacle envelope
(ho 1.80m)
Key
Imperforate obstacle (deck or parapet)
EN 50122-1:2011 cl 5.2.1 Note 2 Alternative protection by clearance envelope where (imperforate) decks provide
protection
Protection by obstacle envelope (ho 1.80m with imperforate deck)
d
hs
ho
#
is the minimum permitted clearance in air between obstacle and live parts in accordance with GL/RT1210 cl. 2.2.3.2
Is the height of the solid section of parapet
Is the overall height of the parapet (including any mesh extension)
dimension may be reduced by the same extent as the height hs exceeds the value of 1.80m
Figure 10.10.1 Electrification clearances and parapet requirements for High Voltage systems
Page 10 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
a) Public areas
hs = h o
ho
hs 1.25
d
2.50
0.50
0.50
1.45
1.50
0.60
Protection by
obstacle envelope
(ho 1.80m)
1.45
3.00
R 3.00
1.45
Scenario 2
Full height solid
parapet
1.50 #
Scenario 1
Solid parapet with
mesh extension
R 1.45
0.60
0.50
0.50
Protection by
obstacle envelope
(ho 1.80m)
Protection by clearance
envelope (all decks)
b) Restricted areas
ho
3.00
ho
1.50
1.45
0.50
2.50
0.50
d
1.45
0.60
Protection by
obstacle envelope
(ho 1.50m,
ho < 1.80m)
Scenario 2
Solid or imperforate
parapet 1.80m
1.00
R 3.00
Protection by clearance
envelope (all decks)
1.00 #
Scenario 1
Solid or imperforate
parapet 1.50m - 1.80m)
R 1.45
0.60
0.50
Protection by
obstacle envelope
(ho 1.80m)
0.50
Key
Imperforate obstacle (deck or parapet)
EN 50122-1:2011 cl 5.2.1 Note 2 Alternative protection by clearance envelope where (imperforate) decks provide
protection
Protection by obstacle envelope (ho 1.80m with imperforate deck)
d
hs
ho
#
is the minimum permitted clearance in air between obstacle and live parts in accordance with GL/RT1210 cl. 2.2.3.2
Is the height of the solid section of parapet
Is the overall height of the parapet (including any mesh extension)
dimension may be reduced by the same extent as the height hs exceeds the value of 1.80m
Figure 10.10.2 Electrification clearances and parapet requirements for Low Voltage systems
Page 11 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
1.80
1.80
Parapet
Bridge deck
Parapet
< 1.80
< 1.80
b) Existing 1.25m-1.8m Parapet (or new 1.5m-1.8m Parapet where permitted) Protection by Clearance
Bridge deck
25
1.25
Parapet
2.
1.80
minimum
1.80
normal
Parapet extensions
d
<e
Bridge deck
Track centreline
f
a
Key
Page 12 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
10.11
Replacement of
road restraint
systems
10.14 Handrails
for Underline
Bridges
10.17
Footbridges:
general
requirements
1500mm
Low risk of route crime (e.g. within controlled areas within stations
or away from built up areas, schools, other frequently used
pedestrian routes, train depots and other crime-susceptible
installations), and
Low risk of suicide (footway less than 10m above the tracks), and
No/low risk of electrocution (e.g. no existing or planned OLE or
where protection by safety clearance [to OLE] is provided).
Page 13 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
Where footbridges (and their associated access steps or ramps) span over
or are adjacent to existing, new or modified overhead electrified lines, the
additional requirements of 9.9.4 and 10.10 shall also apply.
The use of mesh (to BS 7818) may be used for screens above 1500mm
above the adjacent footway where increased passenger or public visibility
is appropriate.
Appendix E
Information to be
included in the
AIP submission
Appendix F
OLE and Parapet
Height Decision
Flowcharts
(Informative
Guidance)
Title
9.9.4
10.10
Page 14 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
NEW STRUCTURE
Protection by Safety
Clearance
Design for 2.25m*
clearance to OLE
No
Low risk
environment
Parapet height
Min parapet height =
1.80m
(or where increased
visibility is
appropriate, 1.50m
with glazed or mesh
screen above to
provide overall
obstacle height of at
least 1.8m)
Is footway to
OLE vertical
clearance
2.25m*
practicable?
Yes
No
Protection by
Obstacle
Design to consider
options for
maximising
clearance to OLE
Yes
Parapet height:
Min parapet height =
1.50m
Minimum extent:
Between railway
boundaries
Minimum extent:
Between railway
boundaries
Parapet height
Min parapet height =
1.80m
(or where increased
visibility is
appropriate, 1.50m
with glazed or mesh
screen above to
provide overall
obstacle height of at
least 1.8m)
Minimum extent:
Between railway
boundaries
Figure F1: Parapet requirements for new structures over OLE (Public areas)
Notes:
Parapet heights greater than 1.8m may be required where OLE is beside the parapet (e.g. platform stairs) (see
10.10.1).
* 2.25m refers to minimum dimension for imperforate decks over HV OLE. For minimum dimensions for LV OLE
or for perforate decks over HV OLE, refer to Figures 10.10.1 to 10.10.3.
Page 15 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
EXISTING
STRUCTURE
Protection by
Clearance
Yes
Yes
Is footway to
OLE vertical
clearance
2.25m*?
Existing
parapet
height
1.8m?
Yes
No
Parapet
<1.5m or
high T&V
risk
No
Protection by
Obstacle
Existing
parapet
height
1.8m?
No
No
Yes
Upgrade of parapet
and/or security measures
to be considered, and
implemented where
appropriate (to control
risks SFAIRP)
Yes
Structure
strengthening
upgrade
planned
No
Parapet upgrade
unlikely to be justified
on grounds of cost
disproportionateness
Upgrade parapet
and/or security
measures to control
risks SFAIRP
Figure F2: Parapet requirements for existing structures over new/upgraded OLE (Public areas)
Notes:
Where upgraded parapet and/or security measures are required, the minimum upgraded obstacle height and
length shall be determined by site specific risk assessment; the raised obstacle should normally extend across
the full width of the railway (see Figure 10.10.3 (c)).
Parapet heights greater than 1.8m may be required where OLE is beside the parapet (e.g. platform stairs) (see
10. 10.1).
* 2.25m refers to minimum dimension for imperforate decks over HV OLE. For minimum dimensions for LV OLE
or for perforate decks over HV OLE, refer to Figures 10.10.1 to 10.10.3.
Page 16 of 18
Network Rail, The Quadrant, Elder Gate, Milton Keynes. MK9 1EN.
4 Recipients
Name
Post
Rubina Greenwood
Head of Buildings
Richard Stainton
Ben Wilkinson
David Castlo
Project/Programme Director
Steve Brame
Page 18 of 18