How To Size A Hydropneumatic Tank in A

Pressure Booster System


March 19, 2013

By Chris Edmondson
Properly sized hydropneumatic tanks are a non-negotiable element in a domestic water
pressure booster system--including variable speed systems. Without a hydro pneumatic
tank, pumps will short cycle on and off during no flow periods. Even a leaky faucet can
cause pumps to operate unnecessarily without this pressurized reserve of water.
As important as these tanks are in a system, it is equally important that they be sized
correctly. Sizing is dependent on two factors:
(1) The length of time the designer theorizes that the booster pumps should remain off in
a no-flow condition. It is recommended that the pumps stay off between 15 to 30 minutes
(depending on the type of building) during periods of low demand to save energy and
prevent short cycling. Note that a hospital will typically need a larger tank in order for the
booster pumps to remain off for the same amount of time as an apartment building where
low usage periods are very consistent.
(2) The tank location in relation to the pressure booster pumps. Tanks that are placed on
the roof or at the high point in the system can typically afford to be smaller than those
installed at the discharge of the pressure booster.
With that in mind, an engineer can quickly determine the correct size tank for a given
application by consulting a few charts and doing some simple math.
Six Steps to a Properly Sized Tank!
Lets say you have an apartment booster system designed to deliver a maximum of 124
GPM. There is a minimum street pressure of 40 PSIG, and the booster system itself is
designed to generate 58 PSIG of pressure for a total maximum pressure of 98 PSIG.
Based on this scenario, these are the steps you would take to determine the proper size
hydro pneumatic tank:
Step 1. Determine what type of differential you want between the point that the booster
system cuts off (98 PSIG) and the time it cuts back on again. For the purpose of this

example, we will assume a 10 PSIG differential, so the pump would cut back on when
system pressure drops to 88 PSIG.
Step 2. Based on the type of facility, decide how long you would like pumps to stay off
during a period of no flow. In our apartment example, lets say that time period is 15
minutes.
Step 3. Determine the Acceptance Volume for the building type (apartment) and total
GPM (124) by consulting an Acceptance Volume chart (Table 1). Based on our example,
the Acceptance Volume we need is approximately 19 GPM. However, this chart is based
on a 30-minute shutdown instead of a 15-minute shutdown. So we divide 19 gallons by
two, giving us a 9.5-gallon Acceptance Volume.
Step 4. Determine your Draw Down Coefficient by finding the initial pressure and final
pressure on the Hydropneumatic Tank Draw Down chart in Table 2. In our example, the
initial pressure is 88 PSIG and the final pressure is 98 PSIG so the drawdown coefficient
is approximately .087.

Step 5. Determine the minimum tank volume by dividing the acceptance volume by the
Draw Down Coefficient. (See Table 3 for the equation.) Note that we have adjusted for a
15-minute shutdown instead of a 30-minute shutdown in our equation.
Step 6. Determine the minimum tank volume needed by dividing the Acceptance Volume
(9.5-gallons) by the Draw Down Coefficient (.087). This gives us our required tank size of
109-gallons.
It is important to remember that the above example is based on the premise that the
hydro-pneumatic tank is located at the same level as the booster system. If, on the other
hand, the tank were to be located at the top of the system instead the engineer would
need to subtract the elevation loses from the initial pressure and the final pressure in order
to arrive at the correct Draw Down Coefficient. The calculations remain the same, but this
change values will result in a much smaller tank.
Dont Forget to Pre-charge!
Hydro-pneumatic tanks are shipped from the manufacturer pre-charged to a pressure
level that is typically well below what the pre-charge should be at operation. Therefore the
engineer should specify the appropriate pre-charge on the drawings.