Beruflich Dokumente
Kultur Dokumente
A. 21 %
B. 29.17 %
A. 5,937.50
B. 6.65 %
C. 25.0 %
C. 12 months
D. 10.29 %
B. 4.00 %
B. 16.28 %
B. 11.75 %
A. 12.07 %
A. P18,000
A. 3.90 %
C. P39.45
B. 9.14 %
D. 19.72 %
D. 8.24 %
D. 13.73 %
B. 12.00 %
C. 11.57 years
D. P705.42
C. Quarterly
C. P54.66
C. 14.2 years
A. P1,549.64
B. P 152.88
A. P 3,260.34
A. P 15,030.03
D. P 19,624.49
B. P 717.17
B. P 1,185.54
B. P 7,731.29
C. P 4,860.00
D. P 2,504.57
D. P 6,922.93
A. P 142,999.08
D. P 43,763.20
A. 3.0%
B. P 1,144.81
C. P 236.20
A. P 2,000.00
C. 9 years
A. $ 5,000,000.00
D. 1,053
B. P 3,927.27
C. P 9,250.00
A. 1,000 feet
B. 2,632
A. 37.11%
A. 16.28%
A. 15.92% ; 13.73%
A. 13.64%
A. P18,800
B. P4133.33
D. P5,000
D. 21.4%
A. 32%
B. P1,513.56
C. 11.75
B. P46,729
A. 4% ; 4.17%
B. 66.6%
B. 15.8%
B. P76.92
C. P15,614.59
B. P13,498.60
B. 11.57 years
D. P13,265.83
A. P163,475.37
C. P6750
A. 8%
C. 4.55 years
A. P200,000
C. 8%
C. 8.03%
A. 7.28%
B. 14.2 years
A. 5.13%
A. 12.75%
A. 21.97 years
A. P3.87
A. P24,751.34
A. 3.92%
A. 3%
A. 19.72%
A. 21.51%
B. 6%
A. P155
B. P77.66
A. 0.333
D. 6%
C. 7%
A. 1.60844
C. P705.42
B. P256,000
C. 8%
C. 8%
C. 8%
A. 1.61607
D. P519,327.95
A. P507,267.28
D. 0.616783
C. 8 years
C. 6.25 years
D. 6.18 years
B. P15,000.00
A. P16,550.00
C. P17,492.94
C. 8.24%
C. 8.24%
D. 7.96%
C. 0.787566127
C. 0.787566127
B. 1.487886717
A. 8.33%
A. 1.377128
D. 0.726149
A. 6.00%
D. 6.09%
D. 5.87%
B. 8.00%
B. 7.92%
A. P800,000.00
D. P907,009.21
B. P911,059.20
B. P44,086.60
A. 4.56 years
A. 9.5%
B. 7%
D. 8%
A. 8%
C. 5.8%
B. P30,655.68
C. P82938.28
A. 14.49%
A. P71,781.47
D. 19.72%
D. 11.83%
C. 19.48%
B. P6,040.20
C. P16,712.03
D. 20.15 years
D. P621,170
A. P690,849
B. 5 years
B. quarterly
A. P120,289.51
C. P18,548.39
A. 16.6%
A. 2.94%
A. 6%
C. 5.66%
A. P291,500
B. P8000
B. P125,000
A. P3,250,000
C. 4 years
A. P50,000
A. 10 years
B. P146,000
B. P900,000
C. P1,200,000
C. P1,185,769.76
C. P2,400
D. P2,670
C. 8%
D. P30,000
A. P33,200
A. P7,545.45
B. P652,333.33
A. P64 M
C. P2,294.44
B. 8 years
C. P857
B. P350
D. 19 years
C. P300,000
A. P679,454.27
A. P21,357.42 ; P68,642.58
C. P12,420
A. Straight Line
B. Declining Balance
C. Sinking Fund
A. P430,629.00
A. P180,000
A. P14,000
A. P15,000
C. P400.00
B. 12.07%
A. 1 hour
D. 18%
C. 6.58%
B. P43,750
A. P3.80
C. P32,000
D. P4,200
A. 37.5%
B. 166
D. P860
A. 26 days
Average hauling
distance
2.5 km
Monthly rental
P35,000 P6,500
B. P1,207,500
Salaries
P750,000
Depreciation
P2,250,000
Installing and
dismantling of machine P20,000 P10,000
At Site A, it would be necessary to hire 2
flagmen at P150 per working day. The job
can be completed in 32 weeks working 6
days a week. The project requires 16,670
cubic meter of asphalt mix per kilometre of
road. If the asphalt mix is to be hauled by a
contractor at P42 per cubic meter per km of
haul. How much is site B more expensive
than site A?
Interest
P700,000
Maintenance
P300,000
A. P4.90
Site A
A. P949,645
Miscellaneous P200,000
2.75 km
Site B
A. 28.33%
C. 12 months
D. P829,592.50
Processing
Method
P5,500
90
P2,500
80
P400
70
B. P1,916,858.24
A. Processing method A
C. P473,000
C. 16.67%
C. 25.0%
A. P5,937.50
A. P46,728.97
D. 10.29%
C. P11,800
D. 37.11%
B. 4.00%
C. 4.17%
D. P25,250
A. P28,000
B. 16.28%
B. 11.75%
D. P5,166.67
A. 12.07%
A. 19.05%
C. P4,133.33
A. P18,800
D. 13.64%
A. 15.92%
D. 13.73%
B. P1,233.55
C. P18,348.62
B. 15.69%
D. P666.39
A. 3.90%