ADDC Design / Under construction NOC Main requirements

After getting NOI through ADDC Website www.addc.ae (E-NOI), you are requested to study the effect of
your project on ADDC Assets and submit to get NOC from the concerned departments considering the
below requirements. ADDC will not be able to study your Application unless you submit all the following
requirements each in a separate file for design stage first and then for construction stage.

Kindly upload the below requirements as ZIP Files using WinZip, folder for Water
and folder for Electricity. File name inside each folder to be same as the requirement.
A. Design NOC requirements (To be attached separately with any NOC Application):
1. A valid copy of NOI letter (not more than two months from issue date) issued by ADDC Website
www.addc.ae E-NOI.
2. CAD drawing DWG file (Version 2007) in WGS84-Z40 with PDF files to show the conflict of
your project with ADDC Assets (Water / Electricity).
3. Proposed Route.

4. Letter to explain the type of NOC (Protection / Relocation or both of ADDC Assets). You have to
indicate the type of Conflicted Asset (e.g. HV Cables, LV Cables, Street Light, Main Water Pipe
DIA, Water House Connection, .Etc.).
5. Conceptual Protection / Relocation Method Statements for ADDC Assets including Schematic or
Conceptual Cross Section in CAD drawing DWG file (Version 2007) in WGS84-Z40 (Detailed
method statements and detailed construction drawings must be submitted by the Contractor during
Construction NOC application process).
6. In case there is no conflict with ADDC Assets as shown in ADDC information submitted along
with NOI letter, NOC requestor has to explain this in his Application / Letter.
7. A document describing the risks associated with the proposed Protection/Relocation work.
(Detailed Risk Assessment must be provided by Contractor during Construction NOC application
process).
8. For Road / landscaping Projects, Water / Electricity Future Ducts Proposal to be submitted.

B. Construction NOC (To be attached separately with any NOC Application):


1. General undertaking Letter confirming full responsibility to execute all work at your own cost
related to replacement/repair of any damaged ADDC Assets in full compliance with
ADWEA/ADDC Standard Specification, all as per ADDC policy.
2. A valid copy of NOI letter (not more than two months from issue date) issued by ADDC Website
www.addc.ae E-NOI.
3. CAD drawing DWG file (Version 2007) in WGS84-Z40 and also PDF files to show the conflict of
your project with ADDC Assets (Water / Electricity).
4. Town Planning Sector Abu Dhabi Municipality planning validation approval for the works
(Route Approval), Approval Letter and Approved Drawings must be attached.
5. Letter to explain the type of NOC (Protection / Relocation or both of ADDC Assets). You have to
indicate the type of Conflicted Asset (e.g. HV Cables, LV Cables, Street Light, Main Water Pipe
DIA, Water House Connection, .Etc.).
6. Detail Protection / Relocation Method Statements for ADDC Assets including detail Cross Section
in CAD drawing in WGS84-Z40.
7. In case there is no conflict with ADDC Assets as shown in ADDC information submitted along
with NOI letter, NOC requestor has to explain this in his Application / Letter.
8. Detailed Risk Analysis / Assessment associated with the work in all the cases.
9. For Road / landscaping Projects, Water / Electricity Future Ducts Proposal to be submitted.