Beruflich Dokumente
Kultur Dokumente
Operation
Procedure
1.0
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
1 of 7
0
Introduction.
This method statement briefly describes the detailed procedure, material, equipment and
manpower in executing the site clearing and earthwork within the limits of the work in
safe manner and incompliance with drawings, Technical Specification and HSSE
requirements.
2.0
Scope of Work.
Pre-construction activities, preparation and site clearing of site area.
Construction of temporary truck access ramp for hauling.
Cut and fill of the whole works package area as per drawing to specific formation
level profile.
3.0
Location.
Six (6) Stations in Sugut, Sabah
4.0
Reference Used.
Technical Specification Section 2
Earthwork Drawing
BS 812 Testing Aggregates
BS 1377 Method of Test for Soil for Engineering Purposes
5.0
Standard
Operation
Prepared by:
Nur Farah Atika. K
Procedure
6.0
Resources.
6.1 Manpower
- Land Surveyor
- Test Laboratory
- Supervisor
- Site Foreman
- Lorry Driver
- Machine Operator
- General Workers
6.2 Plant, Machinery & Equipments
- Roller Compactor
- Rotary excavator with breaker
- Shovel
- Bulldozer
- Backhoe
- Tipper Lorry
- Water Truck/ Sprinkler
- Survey Equipment
6.3 Materials
- Backfill suitable material
7.0
Description Of Works.
7.1 Pre-Construction Preparation Works
Prior to commencement, there are several preparatory works shall be executed which
are as follows:a) Topographical and pre-com survey plan
b) Establish boundary limit
c) Set-up reference point for g/line, TBM and station
d) Submit temporary work and site logistic detailed drawing
e) Existing services drawing within the site area. All the existing services shall
be marked on site
Standard
Operation
Procedure
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
3 of 7
0
Standard
Operation
Procedure
7.7 Backfilling
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
4 of 7
0
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
5 of 7
0
a) Turf material shall be com grass or other approved locally sustainable grass or
vegetative covered.
b) Turf shall be approximately 250mm x 250mm and lay as close turfing in
stretcher bond pattern. Small gap between the turf shall be filled with approved
soil.
c) Spot turfing shall be laid at no more than 600mm spacing. The space
between the turf shall be filled with approved soil.
d) Regular watering and fertilizer shall be applied as necessary to maintain the
growth of the grass.
8.0
QAQC.
All inspection and test activities shall be undertaken in accordance with Technical
Specification requirements as tabled in the attached Inspection & Test Plan.
9.0
Standard
Operation
Procedure
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
6 of 7
0
b) All fuel storage tanks will be properly grounded and vented by provided
proper type fire extinguishers. Danger or No smoking or Open flames
signage will be prominently placed at these tanks.
c) Storage tanks above ground will be curbed to control the spread of spill
liquids in the event of leakage.
d) Welding activities (if any) will be performed in accordance with standards and
recommended practices. Fire extinguishing equipment will be provided in the
immediate vicinity of welding operations whenever combustible material is
exposed. Workmen will be shielded from welding rays, sparks, slag, etc. all
precautions will be complied in order to prevent fire outbreak during welding
or oxy-cutting activities.
e) Fire extinguishers will be placed at easy and readily accessible location,
properly maintained, regularly inspected and promptly refilled after use.
9.3 Incident Reporting
All lost time injuries, property damage accidents (excluding off-project vehicle
accident) and material losses in which the property damage/losses, will be reported to
the Client immediately after the accident or incident. Immediate notification will be
provided in advance prior to the written report.
9.4 PPE List
a) Safety Helmets
b) Safety Shoes
c) Hand Gloves
d) Safety Vest
e) Safety Mask
Standard
Operation
Procedure
10.0
Attachments.
10.1
Prepared by:
Nur Farah Atika. K
Check by: DK Noraini
Page
Revision
7 of 7
0