Sie sind auf Seite 1von 12

JANGAREDDYGUDEM NAGARPANCHAYAT

Material Lead Statement for 2014-15


Sl. No.

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
28
29

Description

Cost of Cement OPC


Cost of Sand for Mortor Concrete Items
Cost of Sand for Motor
Cost of Sand for filling
Aggregates 6 mm Nominal size
Aggregates 10 mm Nominal size
Aggregates 13.2/12.5 mm Nominal size
Aggregates 20 mm Nominal size
Aggregates 25 mm Nominal size
Aggregates 40 mm Nominal size
Aggregates below 5.6mm
Aggregates 22.4 mm to 2.36mm
Aggregates 22.4 mm to 5.60 mm
Aggregates 45 mm to 22.4 mm
Aggregates 63 mm to 45 mm
Aggregates 11.2 mm to 0.09 mm
Aggregates 13.2 mm to 0.09 mm
Aggregates 13.2 mm to 5.6 mm
Aggregates 53 mm to 22.4 mm
Aggregates10 mm to 5 mm
Aggregates 25 mm to 10 mm
Aggregates Below 5.6 mm
Cost of Gravel
Cost of Stone Dust/
Quarry rubbish
Cost of Steel (Fe - 415)
Cost of Bricks
20 MM HBG Metal (Graded)

Source (name of
quarry)

Local
Prakkilanka
Prakkilanka
Prakkilanka
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
EGK Road
Local
Ravikampadu

Unit

1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum
1 Cum.
1 Cum.
1 MT
1000 No
0.70 cm
0.10 cm
0.10 cm
0.10 cm

Cost at source Lead in K.M.

6400.00
462.00
51.90
606.00
51.90
606.00
51.90
735.00
44.00
935.00
44.00
1097.00
44.00
1365.00
44.00
1313.00
44.00
845.00
44.00
557.00
44.00
914.00
44.00
1040.00
44.00
1145.00
44.00
662.00
44.00
704.00
44.00
798.00
44.00
919.00
44.00
872.00
44.00
875.00
44.00
1129.00
44.00
557.00
44.00
357.00
44.00
81.00
44.00
45000
4700
9.00
20mmHBG Metal
12mmHBG Metal
10 mm HBG Metal
6 mm HBG Metal

Conveyance
Charges

609.10
609.10
609.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
546.10
206.82
1894.04
1626.04
1464.04
1264.04

20 MM HBG Metal (Graded)

Deduct 14 %
contractor Seign-charges
profit

74.80
74.80
74.80
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
67.06
-

40.00
40.00
40.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
50.00
-

67.06
67.06

50.00
50.00

25.40
1325.82
162.60
146.40
126.40

38.50

1761.24

Total Rate.

6400.00
1036.30
1180.30
1180.30
1264.04
1464.04
1626.04
1894.04
1842.04
1374.04
1086.04
1443.04
1569.04
1674.04
1191.04
1233.04
1327.04
1448.04
1401.04
1404.04
1658.04
1086.04
886.04
610.04
45.00
4970.72

ELURU MUNICIPALITY DATA 2010-2011


S.No
1

Description

Unit

Quantity

Rate

day

3.64

250.00

Amount

Earthwork in excavation for structures as per drawing


and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305
MORD / 304 MORTH (Page No.484)
Ordinary soil
Manual Means Upto 3 m depth unit - 1 cum
Taking out put 10 cum

a)

Labour
Mate
Mazdoor (Unskiled)

910.00

25 % labour

227.50

1137.50
(b+c) over heads & contractor profit 14%

159.25
1296.75 10 Cum

Rs.129.68

1 cum

day

0.31

215.00

1 cum
1 cum

886.04
-

Filling in foundation trenches as per drawing and


technical specification Clause 305.3.9 MORD & 304
MORTH ( Page No. 488) RBR FN-DN-2

Quarry Dust filling out put 6cum


a)

b)

Labour
Mate
Mazdoor (Unskilled)
25 % on Labour (Rs.66.65)
Material (Filling)
Cost of Dust
Add Seionarage charges

66.65
16.66
5316.21
5399.52
755.93
5468.61
911.44

( C& D) over heads & contractor profit 14%


Rate per cum
3

Filling in foundation trenches as per drawing and


technical specification Clause 305.3.9 MORD & 304
MORTH ( Page No. 488) RBR FN-DN-2

Sand filling
a)

b)

Labour
Mate
Mazdoor (Unskilled)
25 % on Labour (Rs.66.65)
Material (Filling)
Cost of sand
Add Seionarage charges
( C& D) over heads & contractor profit 14%
Rate per cum

day

0.31

250.00

1 cum
1 cum

1180.30
-

77.50
19.38
7081.79
7178.66
1005.01
8183.68
1363.95

Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixer.


All work upto plinth level
(Page No.661) BLD-CSTN-2-5
Unit 1 cum
A.Materials
Cement
kg
162.00
coarse aggregate 40 mm
cum
0.90
fine aggregate (sand) Motor
cum
0.45
Seiniorage charges for CA
cum
0.90
Seiniorage charges for FA
cum
0.45
Water (including for curing) (M189 P.No.34)
kl
1.20
B. Machinery
Concrete mixer 10/7 cft (0.2/0.8 cum capacity
hour
1.00
C.Labour (300/200 Diesel P.No.130
Mason 1st class
day
0.10
Mazdoor Unskilled
day
1.39
25 % on Labour (Rs.327.35)
Water charges 1% Rs.327.35

#REF!
1374.04
1180.30
0.00
0.00
77.00

#REF!
1236.63
531.13
0.00
0.00
92.40

248.40

248.40

285.00
215.00

28.50
298.85
81.84
3.27
2960.16
414.42
3374.58 1 Cum

Contractor profit 14%

Providing Concrete for Plain reinforced concrete in


open foundations using 40mm nominal size graded
hand stone aggregate,machanically mixed,placed in
foundation and compacted by vibration including
cutting for 14 days complete as per drawings and
techinical specifications for Height up to 5Mts
Plain Cement concrete Naminal mix (1:3:6) using
2/3rd 40 mm &1/3rd 20mmfor side wall drains.
a. Materials
Cement
coarse sand
40mm aggregates
20mm aggregates

MT
cum
cum
cum

0.22
0.45
0.60
0.30

6400.00
1180.30
1374.04
1705.62

1408.00
531.13
824.42
511.69

Hour

0.40

248.40

99.36

day
day

0.10
1.39

285.00
215.00

28.50
298.85
81.84
3151.85

B. Machinery
Mechanical concrete mixer 0.40/0.26 cum capacity
c. Labour
Mason 1st class
Mazdoor Unskilled
add 25 % Mpl Allowance
d) Form work @10% on cost of material ,labour and
machinery

315.19
3467.04
485.39
3952.43

Over head & contractors profit @14%


Rate/1 Cum

Supplying, fitting and placing HYSD bar reinforcement


in foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over
laps and wastage, where they are not welded
Unit = 1 MT
(a) Material
HYSD bars including 5 per cent for overlaps and wastage
Binding wire

1.050

45000.00

kg

6.00

55.00

47250.00
330.00

(b) Labour for cutting, bending, shifting to site, tying


and placing in position

10.00

300.00
215.00

61.58

/1 Kg

cum

0.15

cum

0.15

#REF!
0.00

#REF!
0.00

day

0.60

day

0.96

285.00
215.00

171.00
206.40
94.35
#REF!
#REF!
#REF!
95.32

Plain Cement concrete Naminal mix (1:3:6) using


20 mm &12mm graded metal with machine
mixing. (Page No.661)
Unit 1 cum
a. Materials
Cement
coarse aggregate 20 mm
coarse aggregate 12 mm
fine aggregate (sand)
Seiniorage charges for CA
Seiniorage charges for FA
Water (including for curing)
B. Machine mixing

kg
cum
cum
cum
cum
cum
kl
Hour

220.00
0.60
0.30
0.45
0.90
0.45
1.20
0.40

#REF!
1705.62
1510.62
1180.30
0.00
0.00
77.00
248.40

#REF!
1023.37
453.19
531.13
0.00
0.00
92.40
99.36

Water tanker 6Kl capacity

hour

0.13

345.00

44.85

c. Labour
Mason 1st class
Mazdoor Unskilled
25 % on Labour

day
day

0.10
1.39

285.00
215.00

28.50
298.85
81.84
#REF!

Blacksmith / Bar bender


Mazdoor (Unskilled)
Labour on 25%
Sundries on Material
(d) Overheads on (a+b)
(e) Contractors profit on (a+b+c)

day
day

10.00

3000.00
2150.00
1287.50
54017.50
7562.45
61579.95 1 Tonne

PLASTERING
Plastering with CM (1:4), 12 mm thick (page No.680)
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)

Labour on 25 %
contractor profit 14%
10 sqm
1 sqm

d) Form work @ 4% on cost of material, labour and


machinery

#REF!
#REF!

Contractor profit 14%

RCC grade M20 ( Nominal Mix) for culvert slabs & Bed
blocks
a) Material
Cement
Coarse sand
20mm aggregates
10mm aggregates
b) Labour
Mason I class
Mazdoor (Unskilled)

#REF!
4136.08
Rate/ 1 cum
MT
Cum
Cum
Cum

0.33
0.45
0.54
0.36

6400.00
1180.30
1894.04
1464.04

2112.00
531.13
1022.78
527.05

day
day

0.10
1.39

285.00
215.00

28.50
298.85

Add 25% Mpl. Allowance


c) Machinery
Mechanical concrete mixer 0.40/0.26 cum capacity
Generator 33KVA

81.84
hour
hour

0.40
0.40

248.40
0.00

d) Form work @10% on cost of material, labour and


machinery

470.15
5171.66
724.03
5895.70

Over head & contractors profit @ 14%


Rate/ 1 cum

10

Providing and Laying of Hot Applied Thermoplastic


Compound 2.5mm thick including reflectorising glass
beads onb bituminous surface at 250 gms per area
,thickness of 2.5mm is exclusive of surface applied
glass bead as per IRC ;35 the finishing surface to be
level ,uniform and free from streaks and holes
etc.complete for finished item of work (with all lift and
lead).
Page 225 of MORT&H 803 SDB
Unit :Sqm
Taking Out Put = 640 Sqm
a) Labour
Mate
Mazdoor (Unskilled)
Add 25% Mpl. Allowance
Sub Total (A)
B) Machinery
Road Making Mechine @ 80 Sqm Per Hour
Tractor -Trolley
Sub Total (b)
C) Material
Hot Applied Thermoplastic Compond
Reflectorising Glass beads
Sub Total (b)

day
day

0.50
2.00

215.00
215.00

107.50
430.00
134.38
671.88

hour
hour

8.00
8.00

90.00
345.00

720.00
2760.00
3480.00

litre
Kgs

2000.00
65.00

200.00
65.00

400000.00
4225.00
404225.00
408376.88
57172.76
465549.64
727.42

44.5

44.50

Over head & contractors profit @ 14%


Rate/ 1 Sqm

11

Carting away of excavated earth/ debris to a lead of 3 Km.


The rate including conveyance charges, labour charges for
loading, unloading, etc., complete as directed by the
departmental officer in charge of the work
Conveyance for 3 Km

12

99.36
0.00
4701.51

Supply, delivery of 450mm dia Np3 class RCC s/s


pipes including earth work lowering, laying, jointing
across CC/BT/WBM roads
Basic Rate
5KM Conveyance

Contractor Profit 14%

1549.00
40.90
159.55
1749.45
244.92
1994.37

AEE (PH)
Eluru

Deputy Executive Engineer (PH)


Eluru

Executive Engineer (PH)


Eluru

JANGAREDDYGUDEM NAGARPANCHAYAT
DATA - 2014-15

Earthwork in excavation for structures as per drawing and technical specifications Clause
305.1 including setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH (Page No.484) RBR FN-DN1 and as directed by the departmental officer incharge of work as per s.s

Ordinary soil
Manual Means Upto 3m depth unit 1.00 Cum
Taking out put 10 Cum
Labour
Mate
Mazdoor (Unskiled)
day
20% labour
Total
13.615% over heads and contractor profit

3.64

295.00

1073.80
214.76
1288.56
175.44
1464.00 10 Cum
146.40 1 Cum

Cement Concrete Pavement

RBR-CCPV-5

Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates
conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and
appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork
(steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates
including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes,
compacted using needle, scareed and plate vibrators and finished in continuous operation
including provision of contraction and expansion, construction joints, applying debonding strips,
primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints,
admixtures as approved, curing of concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as per drawing and Technical Specification
Clause 1501 MORD. Unit = cum Taking output = 75 cum (172.50 t)(100 x 3.75 x 0.200)
a)Labour
Mate
Mason (1st class)
Mason (2nd class)
Mazdoor (Unskilled)
Mazdoor (Skilled)
Surveyor
Mazdoor (Semi-Skilled)
Municipal Allowance on Labour 20%

day
day
day
day
day
day
day

5.00
5.00
150.00
6.00
2.00
6.00

385.00
345.00
295.00
295.00
0.00
345.00

1925.00
1725.00
44250.00
1770.00
0.00
2070.00
51740.00
10348.00

Blacksmith for cutting of dowel bars


including
removal
of
burrs,
fabrications & fixing of dowel bars.
b) Machinery
Concrete mixer 0.28 / 0.4 cum
capacity (6 mixers) with weigh
batcher and suitable capacity
calibrated water tank
Needle vibrator
Screed vibrator
Plate vibrator
Concrete joint cutting machine for
initial & final cuts
Water tanker 6 kl capacity
Air Compressor (1 hour initial + 1
hour final)
c) Material
Crushed stone coarse aggregates,
grading will be as per Clause
1501.2.4.1
(Table
1500.1)
of
specifications @ 0.90 cum/cum of
concrete (25 mm & 12.5 mm
blending)
25mm HBG metal 2/3
12.5mm HBG metal 1/3
Add Seigniorage
Sand as per IS:383 and conforming
to Clause 1500.2.4.2 @ 0.45
cum/cum of concrete
Add Seigniorage
Cement @ 400 kg/ cum of concrete
Polythene sheet 125 micron
Mild steel dowel bar 25 mm dia of
grade S 240. 500 mm long 20 Nos.
at culvert/bridge slab and at
construction joint including 5 per
cent wastage.
(4 x 20 x 0.500) + 5 per cent
wastage = 42 m @ 2.80 kg per m =
117.6 kg.
Bitumen primer @ 200 ml per joint
for 23 joints
Bituminous sealant 800 ml per joint
for 23 joints
Jute rope 12 mm dia including 5 per
cent wastage
Debonding strips 3.75 m (length) x
10 mm (width) x 5 mm (thick) cut-out
of rubber filler board or similar
material including 5 per cent
wastage

day

1.00

0.00

0.00

hour

36.00

328.60

11829.60

hour
hour
hour
hour

9.00
9.00
9.00
4.00

165.70
42.00
0.00
0.00

1491.30
378.00
0.00
0.00

hour
hour

5.00
2.00

624.00
0.00

3120.00
0.00

cum

45.00

0.00

0.00

45.00
22.50
67.50

1842.04
1626.04
0.00

82891.58
36585.79
0.00

33.75

1036.30

34975.07

33.75

0.00

0.00

30.00

6400.00

192000.00

sqm

412.50

15.00

6187.50

0.00

0.00

cum

0.118

0.00

0.00

kg

5.00

41.00

205.00

litre

0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

Polythene sheathing, covering 2/3rd


dowel bars (20x23) and tight fit
including 5 per cent wastage

No.

483.00

0.00

0.00

Plasticizer 0.5 per cent by weight of


cement

litre

0.00

0.00

0.00

Curing compound (if used) @ 0.33


litre per sqm

litre

0.00

0.00

0.00

kl

18.00

103.00

1854.00

sqm

3.00

630.00

1890.00

Water for curing


Joint filler board 20 mm thick as per
IS:1838
(4 x 3.75 x 0.200 = 3 sqm)

435495.83
13064.88
448560.71
61071.54

d) Formwork @ 3% of (a+b+c)
e&f) Overheads & Contractors
Profit @ 13.615%
Cost for 75 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/75

509632.25
6795.10

/1 Cum

Granular Sub Base with Stone Dust


RBR-SBBS-12

ii

Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place
method normal Construction of granular sub-base by providing local material spreading
in uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at once and compacting with smooth wheel roller to achieve the desired
density complete as per Clause 401.4 as per Technical Specification Clause 408 MORD RBR-SBBS-12 P.338
Unit = cum
Taking output = 300 cum
a)Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
M.A 20% on Labour
b) Machinery
Motor grader 110 HP 50 cum per
hour
Three wheel 80-100 kN static roller
@10 cum per hour P.No.43
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per
hour
c) Material
Naturally Occuring Stone Dust (local
materials as per Table 400.13)
Seigniorage
Water - P-34

day
day
day

2.48
10.00

385.00
295.00

954.80
2950.00
780.96

hour

6.00

0.00

0.00

hour

30.00

1718.70

51561.00

hour

5.00

80.48

402.38

hour

12.00

0.00

0.00
0.00

cum

300.00

886.04

265810.53

KL

300.00
30.00

0.00
103.00

0.00
3090.00
325549.66

d&e) Overheads & Contractors


Profit @ 13.615%
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300

44323.59
369873.25
1232.91 /1 Cum

Granular Sub Base Gravel for side berms


RBR-SBBS-12

ii

Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place
method normal Construction of granular sub-base by providing local material spreading
in uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at once and compacting with smooth hand roller to achieve the desired
density complete as per Clause 401.4 as per Technical Specification Clause 408 MORD.
Unit = cum

Taking output = 300 cum


a)Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
Add 20%
b) Machinery
Motor grader 110 HP 50 cum per
hour
Three wheel 80-100 kN static roller
@10 cum per hour
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per
hour
c) Material
Soil gravel mixture/quarry waste
(Local material as per Table400.13)
(Gravel)
Gravel 75%
Seigniorage Gravel
Water
d&e) Overheads & Contractors
Profit @ 13.615%
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300

day
day
day

2.40
8.00

385.00
295.00

924.00
2360.00
3284.00

hour

6.00

hour

30.00

1718.70

51561.00

hour
hour

5.00
12.00

80.48

402.38

cum

300.00 -

kl

0.00
0.00
30.00

0.00

0.00
0.00
103.00

0.00
0.00
3090.00
61621.38
8389.75

70011.13
233.37 /1 Cum

10

Detailed cum Abstract Estimate

Jangareddygudem Nagarapanchayat
Name of work: Drilling of Bores with Casing and Supply of HDPE Pipes at different
places of Town Limits in Jangareddygudem Nagarpanchayat
Estimate Cost : Rs.
15,00,000/Sl
No

Description of item

Nos

Measurments

Qty
Rate
L
B
D
Providing and Drilling of Bore well by rotary Bore to a finished
dia 350 which will be carrued out by Pilot bore of suitable dia
in all formations suitable for rotary drilling such as alluviaal
soils formations all consolodated formations etc and reaming
the bore to suit insertion of 175 mm dia PVC Blue casing Pipe,
Couplings, Bail plug, dummy development with 100 PSA Air
compressor Conductingyield test core charges cost of
consumables transportation charges and all other charges
required on the fixation of pipe assembles etc competed
excluding cost cost of necessary slotting charges and
assemble any where in the Dist. for the required depth and the
work will be carried out as per IS 2800 Part I and II 1979 etc
completed.
1
Dangey Nagar
1 x 1
- ### 100.00
New Office Building

1 x 1

- 70.00 70.00

Ramachandrapuram

1 x 1

- 80.00 80.00

Degree College

1 x 1

Subba Reddy Colony

1 x 1

- 80.00 80.00

Harijanapeta

1 x 1

- 80.00 80.00

Subbampeta By-Pass Road

1 x 1

- 90.00 90.00

Drilling Depth of Rotary Bore

Amount

### 100.00

###

Cost and supply of 175 mm Dia (10 kg/cm2) CM Class PVC


2 Blue Casing Pipe
1 x 7 ###
###
3

Per

980.00 Rmt

###

Rmt

588000.00

644000.00

Cost and supply of 175 mm Dia CI bail Plug


1 x 7

7.00

900.00

No

6300.00

1 x 7

7.00

650.00

No

4550.00

1 x 7

7.00

500.00

No

3500.00

175 mm Dia MS Clamp set

175 mm Dia Bore cap

Sl
No

Description of item

Nos

Measurments
L

Qty

Rate

Per

Amount

###

Rmt

474950.00

230.00 Rmt

80500.00

Manufacture, Supply, & Delivery of HDPE Pipes conforming to


IS 4984 - 1995 including transportation to any where in A.P,
excluding excise duty, sale tax and specials etc., complete.
(supply upto 90 mm dia in
5 coil & above 90 mm dia straight length in 6 m.)
(PE - 100 Grade) 12.5 kg/sqcm OD 90 mm
1 x 7 ###

###

Slotting Chares of 175mm Dia PVC Blue Casing pipe 10kgf


includingof 200 mm dia PVC Casing Pipe 6 kg/cm2 including
6 all incidental chagres etc complete..

Provision for Geologist survey


charges

1 x 7 ###

###

1 x 7

7.00

###

No

10500.00
23000.00

8 Unforcen Items

###
Provision for Vat @ 5%

91765.00

Provision for Labour Cess @ 1%

18353.00
###

Provision for User Charges @ 1%

19454.00

Provision for TC and Sc Charges @ 3%

58363.00
###
Say

Assistant Engineer,
Jangareddygudem Nagarpanchayat

###

Commissioner,
Jangareddygudem Nagarpanchayat

Das könnte Ihnen auch gefallen