Beruflich Dokumente
Kultur Dokumente
setting,
wind generator,
I. INTRODUCTION
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
A
If
(
CTR TAP
(1)
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
Control Center
Substation(S/S)
Remote
Controllable
Connection Switch
Feeders
Communication
Server
Master Station
Data Acquisition
and Monitoring
Feeder Automation
Data Maintenance
RTU
RTU
RTU
Data Acquisition of
Substation
-Active Power etc.
-FCB Status (ON/OFF)
FCB Control(ON/OFF)
Customer
Communication Line
FTU
Data Acquisition of
SW Status(ON/OFF)
SW Control(ON/OFF)
RTU : Remote Terminal Unit
FTU : Feeder Terminal Unit
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
1CW
2CW
3CW
4CW
TAP/
LEVEL
setting
4.7 /
0.0879
2.75 /
0.101
1.95 /
0.0978
1.95 /
0.0479
fault
current
(A)
1
operation
time
(S)
fault
current
(A)
2
operation
time
(S)
fault
current
(A)
3
operation
time
(S)
0.0243
0.1726
0.5534
0.0734
0.1989
7630
2278
1331
fault
current
(A)
4
operation
time
(S)
1.4073
0.4131
939
0.0999
0.1943
0.0952
1CW
2CW
3CW
4CW
original setting
fault
current(A)
TAP/LEVEL
1231
4.7/0.0879
1471
2.75/0.101
1471
1.95/0.0978
1.95/0.0479
operation
time(s)
0.6287
0.1939
0.0947
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
positive torque
60
IR
negative torque
30
VST
directional contact close
zero torque line
F1
RY
RY
IF
Bus 2
2CW
2CCW
Bus 3
3CW
3CCW
Bus 4a
4CCW
Substation
S/S
1CCW 6CW 6CCW 5CW 5CCW 4CW
Bus 6
Bus 5
Bus 4b
IF
F1
V
IF
(a)
(b)
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
6
TABLE III
PROPOSED SETTING AND OPERATING TIME OF CLOCKWISE PROTECTIVE RELAYS
relay
Relay
setting
1CW / 6CW
2CW
3CW
4CW
5CW
6CW
TAP
4.45
2.5
1.7
1.25
0.85
0.85
LEVEL
0.0856
0.1036 0.1085
0.102
0.1071
0.0524
operation
time(s)
Bus 1
Bus 2
Bus 3
Bus 4a
1CW 2CCW 2CW 3CCW 3CW 4CCW
If1
Substation
S/S
WG1
WG2
If2
--
2.8139
0.9084
0.4135
0.1942
0.0950
Bus 5
Bus 6
Bus 4b
WG4
WG3
Fig. 11. Fault Current Flows of the Closed-Loop Distribution System with 4
WGs
Fig. 12.
Fault
current(A)
1CW
TAP/LEVEL
Time(s)
TAP/LEVEL
Time(s)
738
4.45/ 0.0856
2.6540
4.65/ 0.0772
2.9041
2CW
929
2.5/ 0.1036
0.3526
2.9/ 0.0915
0.4321
3CW
929
1.7/ 0.1085
0.1682
1.9/ 0.091
0.1755
4CW
1842
1.25/ 0.102
0.0316
2.3/ 0.0991
0.0762
5CCW
929
1.7/ 0.1085
0.161
1.9/ 0.091
0.159
6CCW
929
2.5/ 0.1036
0.2873
2.9/ 0.0915
0.3378
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
Bus with WG
Relay
2,4a,4b,6
2,6
2,4a
4a,4b
TAP/LEVEL
6CW
2.65/ 0.0481
2.05/ 0.0479
1.4/ 0.0500
1.6/ 0.0497
5CW
1.6/ 0. 0982
0.95/ 0.1056
1.3/ 0.1038
1.5/ 0.1035
4CW
2.3/ 0.0991
1.4/ 0.0989
1.9/ 0.0995
2.25/ 0.0973
3CW
1.9/ 0.0910
1.9/ 0.1062
1.9/ 0.096
1.7/ 0.0929
2CW
2.9/ 0.0915
2.9/ 0.0973
2.85/ 0.0953
2.6/ 0.0907
1CW
4.65/ 0.0772
4.55/ 0.0798
4.5/ 0.0795
4.55/ 0.0825
Direction
unit
51
Permission
&
OR
Communication
Channel
Trip Brk
Trip Brk
Permission
OR
&
Direction
unit
51
If1
If2
Bus 6
Bus 5
Bus 4b
WGs
Fig. 15. Fault Current Flow from the Substation and Wind Generators at
Bus 6
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication.
VI. CONCLUSIONS
This paper has presented the adaptive relay setting method
for distribution systems with wind generators. The sample
distribution systems with an open-loop configuration and a
closed-loop configuration are studied for the design of the
adaptive relay setting method, according to the operational
status (startup and shutdown) of wind generators. The function
of adaptive relay setting is activated when the ADAS system
detects a change in operational status of the wind generators.
The relay settings are then revised and loaded to the
corresponding protective relays to ensure good protective
coordination of distribution.
With the integration of wind generators in open-loop
distribution feeders, fault current from the bulk transmission
system is reduced because of the greater residual voltage
during fault contingency. The relay settings of TAP/LEVEL
are adjusted to prevent violations of coordination time interval
(CTI) constraint between relays.
For distribution systems with a closed-loop configuration,
the magnitude and direction of fault currents vary with the
locations and numbers of wind generators in operation.
Directional overcurrent relays are applied to trip the boundary
line switches of the faulted section to isolate the fault. The
TAP/LEVEL setting for clockwise and counter-clockwise
protective relays are then adjusted according to the change of
the operational scenario of wind generators to achieve proper
protective coordination.
The POTT protective scheme has also been proposed to
simplify the protective coordination for closed-loop
distribution systems.
The ADAS system has been considered by Taipower to
provide adaptive relay settings according to the change of fault
currents caused by network configuration and operation of
wind generators. Using this technique, more wind generators
can be integrated into smart distribution systems without
causing improper coordination.
VII. REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
VIII. BIOGRAPHIES
Chao-Shun Chen (M84-SM06) received the B.S. degree from National
Taiwan University in 1976 and the M.S, Ph.D. degree in Electrical
Engineering from the University of Texas at Arlington in 1981 and 1984,
respectively.
From 1984 to 1994 he was a professor of Electrical Engineering at
National Sun Yat-Sen University. From 1989 to 1990 he was with Empros
Systems International. In 1994 he worked as the Deputy Director General of
Department of Kaohsiung Mass Rapid Transit. In.1997 and 1998 he was with
the National Taiwan University of Science and Technology as a professor.
From 1998 to 2008 he was with the National Sun Yat-Sen University as a
professor. Since 2008, he is a chair professor at I-Shou University and a joint
professor at National Sun Yat-Sen University. His major areas of interest are
computer control of power systems, smart grid technologies, and renewable
energy.
Cheng-Ta Tsai received the M.S. degree in Electrical Engineering from
National Sun Yat-Sen University in 2004. He is presently pursuing a Ph. D.
degree in Electrical Engineering at National Sun Yat-Sen University.
Shih-Chieh Hsieh (M92) received the M.S. and Ph.D. degrees in
electrical engineering from Texas A&M University in 1992 and 1996,
respectively. He is with the Department of Electrical Engineering, I-Shou
University, Kaohsiung City, Taiwan. His current research interests are in
distribution automation and planning.
Cheng-Ting Hsu (M90) received the B.S., M.S., and Ph.D. degrees in
electrical engineering from National Sun Yat-Sen University, Kaohsiung,
Taiwan, in 1986, 1988, and 1995, respectively. From 1990 to 1992, he was a
Power Electronics Engineer with Phoenixtec Power Company Limited,
Taipei, Taiwan. He is presently a Professor of electrical engineering at
Southern Taiwan University of Science and Technology, Yung-Kang City,
Taiwan.
Chia-Hung Lin(S95-M98) received the B.S. degree from National
Taiwan Institute of Technology in 1991, M.S. degree from University of
Pittsburgh in 1993, and Ph. D. degree in Electrical Engineering from
University of Texas at Arlington in 1997.
He is presently a full professor at National Kaohsiung University of
Applied Sciences. His areas of interest are distribution automation and
computer applications to power systems.
Copyright (c) 2013 IEEE. Personal use is permitted. For any other purposes, permission must be obtained from the IEEE by emailing pubs-permissions@ieee.org.