Sie sind auf Seite 1von 8

ID

Task
Mode
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Task Name

Duration

Start

Finish

Software Development

97 days

Thu 7/7/16

Sun 11/20/16

2.5 days
4 hrs
1 day
1 day
0 days
11.5 days
5 days
3 days
4 hrs
1 day
1 day
1 day
0 days
14.5 days
2 days
5 days
4 days

Thu 7/7/16
Thu 7/7/16
Thu 7/7/16
Fri 7/8/16
Mon 7/11/16
Tue 7/12/16
Tue 7/12/16
Tue 7/19/16
Fri 7/22/16
Fri 7/22/16
Mon 7/25/16
Tue 7/26/16
Wed 7/27/16
Wed 8/3/16
Wed 8/3/16
Fri 8/5/16
Fri 8/12/16

Mon 7/11/16
Thu 7/7/16
Fri 7/8/16
Mon 7/11/16
Mon 7/11/16
Wed 7/27/16
Mon 7/18/16
Thu 7/21/16
Fri 7/22/16
Mon 7/25/16
Tue 7/26/16
Wed 7/27/16
Wed 7/27/16
Tue 8/23/16
Thu 8/4/16
Thu 8/11/16
Wed 8/17/16

2 days
1 day

Thu 8/18/16
Mon 8/22/16

Fri 8/19/16
Mon 8/22/16

17
18

4 hrs

Tue 8/23/16

Tue 8/23/16

19

Scope
Determine project scope
Define preliminary resources
Secure core resources
Scope complete
Analysis/Software Requirements
Conduct needs analysis
Draft preliminary software specifications
Review software specifications
Incorporate feedback on software specifications
Develop delivery timeline
Secure required resources
Analysis complete
Design
Review preliminary software specifications
Develop functional specifications
Develop prototype based on functional
specifications
Review functional specifications
Incorporate feedback into functional specifications
Obtain approval to proceed

Project: Software Development


Date: Tue 7/5/16

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 1

Predecessors

2
3
4
5
7
8
9
10
11
12
13
15
16

ID

Task
Mode
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Task Name

Design complete
Development
Review functional specifications
Identify modular/tiered design parameters
Assign development staff
Develop code
Developer testing (primary debugging)
Development complete
Testing
Develop unit test plans using product specifications
Develop integration test plans using product
specifications
Unit Testing
Review modular code
Test component modules to product
specifications
Identify anomalies to product specifications
Modify code
Re-test modified code
Unit testing complete
Integration Testing
Test module integration

Project: Software Development


Date: Tue 7/5/16

Duration

Start

Finish

Predecessors

0 days
31 days
1 day
1 day
1 day
15 days
15 days
0 days
40 days
4 days

Tue 8/23/16
Fri 8/12/16
Tue 8/23/16
Wed 8/24/16
Thu 8/25/16
Fri 8/26/16
Thu 9/1/16
Thu 9/22/16
Mon 9/26/16
Mon 9/26/16

Tue 8/23/16
Mon 9/26/16
Wed 8/24/16
Thu 8/25/16
Fri 8/26/16
Fri 9/16/16
Thu 9/22/16
Thu 9/22/16
Sun 11/20/16
Thu 9/29/16

20

4 days

Mon 9/26/16

Thu 9/29/16

21

15 days
5 days
2 days

Fri 9/30/16
Fri 9/30/16
Fri 10/7/16

Thu 10/20/16
Thu 10/6/16
Mon 10/10/16

30,28
28,33

3 days
3 days
2 days
0 days
12 days
5 days

Tue 10/11/16
Fri 10/14/16
Wed 10/19/16
Thu 10/20/16
Fri 10/21/16
Fri 10/21/16

Thu 10/13/16
Tue 10/18/16
Thu 10/20/16
Thu 10/20/16
Mon 11/7/16
Thu 10/27/16

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 2

21
23
24
25
26FS-75%
27
21

34
35
36
37
38

ID

Task
Mode
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61

Task Name

Identify anomalies to specifications


Modify code
Re-test modified code
Integration testing complete
Training
Develop training specifications for end users
Develop training specifications for helpdesk support
staff
Identify training delivery methodology (computer
based training, classroom, etc.)
Develop training materials
Conduct training usability study
Finalize training materials
Develop training delivery mechanism
Training materials complete
Documentation
Develop Help specification
Develop Help system
Review Help documentation
Incorporate Help documentation feedback
Develop user manuals specifications
Develop user manuals
Review all user documentation

Project: Software Development


Date: Tue 7/5/16

Duration

Start

Finish

Predecessors

2 days
3 days
2 days
0 days
65.5 days
3 days
3 days

Fri 10/28/16
Tue 11/1/16
Fri 11/4/16
Mon 11/7/16
Fri 8/12/16
Tue 8/23/16
Tue 8/23/16

Mon 10/31/16
Thu 11/3/16
Mon 11/7/16
Mon 11/7/16
Sun 11/13/16
Fri 8/26/16
Fri 8/26/16

40
41
42
43

2 days

Tue 8/23/16

Thu 8/25/16

21

3 wks
4 days
3 days
2 days
0 days
43 days
1 day
3 wks
3 days
2 days
2 days
3 wks
2 days

Thu 9/22/16
Thu 10/13/16
Wed 10/19/16
Mon 10/24/16
Wed 10/26/16
Wed 8/17/16
Tue 8/23/16
Wed 9/7/16
Wed 9/28/16
Mon 10/3/16
Tue 8/23/16
Wed 9/7/16
Wed 9/28/16

Thu 10/13/16
Wed 10/19/16
Mon 10/24/16
Wed 10/26/16
Wed 10/26/16
Sun 10/16/16
Wed 8/24/16
Tue 9/27/16
Fri 9/30/16
Tue 10/4/16
Thu 8/25/16
Tue 9/27/16
Thu 9/29/16

46,28,47,48
49
50
51
52

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 3

21
21

21
55,26FS-50%
56
57
21
59,26FS-50%
60

ID

Task
Mode
62
63
64
65
66
67
68
69
70
71

Task Name

Incorporate user documentation feedback


Documentation complete
Pilot
Identify test group
Develop software delivery mechanism
Install/deploy software
Obtain user feedback
Evaluate testing information
Pilot complete
Software development complete

Project: Software Development


Date: Tue 7/5/16

Duration

Start

Finish

Predecessors

2 days
0 days
10 days
1 day
1 day
1 day
1 wk
1 day
0 days
4 days

Fri 9/30/16
Tue 10/4/16
Mon 7/25/16
Wed 7/27/16
Thu 7/28/16
Tue 11/8/16
Wed 11/9/16
Wed 11/16/16
Wed 11/16/16
Thu 10/13/16

Mon 10/3/16
Tue 10/4/16
Fri 8/5/16
Thu 7/28/16
Fri 7/29/16
Tue 11/8/16
Tue 11/15/16
Wed 11/16/16
Wed 11/16/16
Tue 10/18/16

61
62,58

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 4

13
65
44,66,63,53
67
68
69

Resource Names
J

Half 2, 2016
J

Management

Management
Project Manager
Project Manager

Project Manager
Project Manager
7/11
Analyst

Analyst
Analyst
Project Manager,Analyst
Analyst
Project Manager
Project Manager

Analyst
Project Manager,Analyst
Analyst
Project Manager
Project Manager
7/27
Analyst

Analyst
Analyst
Analyst

Analyst
Analyst
Management

Management
Management

Management
Management,Project Manager

Management,Project Manager

Project: Software Development


Date: Tue 7/5/16

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 5

Resource Names
J

Half 2, 2016
J

8/23

Developer

Developer
Developer
Developer
Developer
Developer

Developer
Developer
Developer
Developer
9/22

Testers

Testers

Testers

Testers

Testers

Testers
Testers

Testers
Testers

Testers
Testers
Testers

Testers
Testers
10/20
Testers

Testers

Project: Software Development


Date: Tue 7/5/16

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 6

Resource Names
J

Half 2, 2016
J

Testers

Testers
Testers
Testers

Testers
Testers
11/7

Trainers
Trainers

Trainers

Trainers

Trainers

Trainers

Trainers

Trainers
Trainers
Trainers
Trainers

Trainers
Trainers
Trainers
10/26
Technical Communicators

Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators

Project: Software Development


Date: Tue 7/5/16

Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Technical Communicators
Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 7

Resource Names
J

Half 2, 2016
J

Technical Communicators

Technical Communicators
10/4

Project Manager

Project Manager

Deployment Team

Deployment Team
Deployment Team
Deployment Team

Deployment Team
Deployment Team
11/16

Project: Software Development


Date: Tue 7/5/16

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 8

Das könnte Ihnen auch gefallen