Beruflich Dokumente
Kultur Dokumente
Operational Team
KALSAN-II
U/C SACHAN
STAND POST
(1.5' X 1.5'X 2.25')
Detail of Materials
Detail of Quantities
Sub
Head
No
Description
Length
in ft
Breadth
in ft
Depth/Ht
in ft
No of
Units
Pad
4.50
4.50
1.00
1.00
20.25
Cft
stand post
0.75
0.42
1.00
1.00
0.32
Cft
5.41
1.00
1.00
1.00
5.41
Cft
25.98
Cft
Pad
4.50
4.50
0.33
1.00
6.68
Cft
stand post
0.75
0.42
0.33
1.00
0.10
Cft
5.41
1.00
0.33
1.00
1.79
Cft
Sand
(cft)
Gravel/
Crush
(cft)
Shingle
Unskilled
Labour
Men-days Men-days
0.57
8.57
Cft
8.57
0.13
4.50
4.50
0.33
1.00
6.68
Cft
stand post
0.75
0.42
0.33
1.00
0.10
Cft
5.41
1.00
0.33
1.00
1.79
Cft
8.57
Cft
Total
4
Cement
(Bags)
Shingle bed
Total
3
Unit
Total
2
Quantity
Labour
Skilled
Labour
0.90
4.50
9.00
0.27
0.97
2.60
6.50
13.00
0.39
1.42
0.20
0.40
0.86
3.49
4.00
4.00
0.33
1.00
5.28
Cft
stand post
0.75
0.75
3.42
1.00
1.92
Cft
6.00
1.00
0.58
1.00
3.48
Cft
4.50
0.25
0.58
2.00
1.31
Cft
3.25
0.25
0.48
1.00
0.39
Cft
(Drain side)
3.00
0.25
0.48
1.00
0.36
Cft
1.00
1.00
0.50
1.00
0.50
Cft
13.24
Cft
Seat pad
Total
deduct for drain flow
Net Total
6.00
0.33
0.33
1.00
0.65
Cft
12.59
Cft
10.00
Rft
No.
No.
No.
3.50
24
11.00
22.00
8.57
WATSAN
Operational Team
CRS-Mansehra
21.00
24
66.00
132.00
51.43
5.14
20.94
WATSAN
Operational Team
KALSAN-II
U/C SACHAN
VALVE CHAMBER
Detail of Materials
Detail of Quantities
Sub
Head
No
Description
Length
in ft
Breadth
in ft
Depth/Ht
in ft
No of
Units
Quantity
Unit
4.00
4.00
2.50
1.00
40.00
Cft
4.00
4.00
0.25
1.00
4.00
Cft
3.50
1.00
2.25
2.00
15.75
Cft
Short Wall
1.50
1.00
2.25
2.00
6.75
Cft
22.50
Cft
6.75
Cft
Stone
15.75
Cft
Total
5
6
Sand
(cft)
0.50
1.87
2.50
4.00
Cft
Long Wall
3.50
1.00
0.16
2.00
1.12
Cft
Short Wall
1.50
1.00
0.16
2.00
0.48
Cft
1.60
Cft
0.20
1.00
13.50
Sft
0.23
0.84
2.25
Sft
2.79
11.34
1.50
1.50
2.25
4.00
23
Unskilled
Labour
Men-days Men-days
5.00
0.12
0.45
0.90
2.03
0.05
0.18
0.18
0.27
15.75
1.00
Stone
(cft)
7.00
0.25
1.50
Gravel/
Crush
(cft)
Labour
Skilled
Labour
0.88
4.00
CRS-Mansehra
Cement
(Bags)
4.00
Total
2.00
0.06
7.00
15.75
1.31
3.81
WATSAN
Opertaional Team
KALSAN- II
U/C SACHAN
SOURCE TANK
Detail of Quantities
Sub
Head
No
Description
Length
in ft
Breadth
in ft
Depth/Ht
in ft
No of
Units
Quantity
Unit
7.00
7.00
1.50
1.00
73.50
Cft
7.00
7.00
0.50
1.00
24.50
Cft
7.00
1.50
3.50
2.00
73.50
Cft
Short Wall
2.00
4.00
3.50
2.00
56.00
Cft
129.50
Cft
38.85
Cft
Stone
90.65
Cft
1.00
4.00
Cft
Total
4.00
Stone
(cft)
Labour
Steel
#3 bars
(kg)
Binding
wire (kg)
Skilled
Labour
Unskilled
Labour
Men-days Men-days
2.28
2.50
12.50
10.67
40.00
0.50
2.50
25.00
0.76
2.77
5.18
11.66
0.12
0.45
90.65
0.25
20.00
45.50
kg
4.00
3.50
4.00
56.00
Sft
0.93
3.50
0.73
1.12
7.00
2.25
4.00
63.00
Sft
0.16
0.39
1.13
1.76
7.56
7.50
0.33
1.00
18.71
Cft
4.00
10.00
0.88
1.78
2.00
2.00
0.33
1.00
1.32
Cft
17.39
Cft
7.50
Net Total
8.2
Sand
(cft)
Steel
#4 bars
(kg)
4.00
8.1
Cement
(Bags)
Gravel/
Crush
(cft)
5.00
50.00
1.37
20.00
0.46
Steel
(#3 @ 6" c/c as main steel)
7.56
15.00
19.30
kg
7.50
10.00
12.80
kg
32.10
kg
18.71
Cft
Total
9
7.56
10
Binding wire
2.33
kg
11
3.00
12
6.00
13
5.00
14
GI Plug 1"
1.00
No
15
4.00
Sft
2.00
7.50
2.00
0.33
1.00
38.00
0.32
0.37
0.19
Rft
0.06
0.12
Rft
0.12
0.24
Rft
0.10
0.20
0.10
CRS-Mnasehra
0.32
18.76
20
68.89
50.00
90.65
50.00
38.00
1.69
9.56
23.34
WATSAN
Operational Team
fy
g pcc =
g Steel=
50 ksi
max =
U/C SACHAN
0.021
0.15 k/cft
490 lb/cft
6.5
40
hmin
(in)
Proposed
h (in)
2.67
Effective
depths
(in)
Design Le
wall
(ft)
(ft)
thickn Clear lengths Le
along L
along W along along
along along ess
L
W
(ft)
L
W
(1)
(2)
(1)
(2)
2.5
3
1.5
8 6.71
8
6.75
8
8
self wt./ft
(k/ft)
0.0495
Asmin =
0.002bh =
Along Short span (main steel)
Asmax =
bd =
max
As
(sq.in)
0.096
a
(in)
0.16
a/2
(in)
0.08
Asmax =
As
(sq.in)
0.096
a
(in)
0.16
max
a/2
(in)
0.08
0.096 sq.in
d=
3 in
0.742 sq.in
d=
W=
Proposed
Remarks
Greater than Mu=4.44 k-in
Proposed
2.5 in
bd =
0.618 sq.in
(d-a/2) Design moment Md
(in)
(k-in)
2.42
10.45
Remarks
Greater than Mu=4.44 k-in
10 ft
Bar length
#
length
#
bars
of
As
Area of bar Ab # bars in propo in full bars
(sq.in) Bar No.
(sq.in)
1ft span
sed span
(ft)
0.096
0.096
3
4
0.11
0.196
0.9
0.5
2
1
L=
20
10
0.096
0.096
3
4
0.11
0.196
0.9
0.5
2
1
CRS- Mansehra
20
10
=
34
30
Bar length=
#
length
#
bars
of
As
Area of bar Ab # bars in propo in full bars
(sq.in) Bar No.
(sq.in)
1ft span
sed span
(ft)
10 ft
wt. of
steel
(kg)
200
100
10 ft
wt. of
steel
(kg)
200
100
34
30
= L
Remarks
Proposed
bars @ 6" c/c)
10 ft
(#3
= W
Remarks
Proposed
bars @ 6" c/c)
(#3
68 kg
17
WATSAN
Operational Team
SAY
CRS- Mansehra
75 kg
17
WATSAN
Operational Team
KALSAN- II
U/C SACHAN
STORAGE TANK:
1500 US GALLONS
Detail of Materials
Detail of Quantities
Sub
Head
No
Description
Length
in ft
10.67
6.67
10.17
6.7
Breadth
in ft
2
2
3
6.1
Depth/Ht
in ft
1
1
0.5
0.5
No of
Units
2
2
1
1
Total
Quantity
Unit
42.68
26.68
15.26
20.44
105.05
Cft
Cft
Cft
Cft
Cft
Cement
(Bags)
Sand
(cft)
Gravel/
Crush
(cft)
Stone
(cft)
Shingle
(cft)
Labour
Steel
#3 Steel
#4
bars (kg) bars (kg)
Binding
Wire
(kg)
Skilled
Labour
Unskilled
Labour
Men-days
Men-days
2.31
Shingle as in Bed
6.67
6.67
0.5
22.24
Cft
10.67
6.67
10.17
7.17
2
2
3
7.17
0.5
0.5
0.5
0.5
2
2
1
1
21.34
13.34
15.26
25.70
75.64
Cft
Cft
Cft
Cft
Cft
7.50
37.50
75.00
2.34
8.55
7.17
7.17
0.25
12.85
Cft
2.60
6.50
13.00
0.40
1.45
10.17
7.17
1.5
1.5
1
1
2
2
30.51
21.51
52.02
cft
cft
cft
10.40
26.00
52.00
2.44
4.94
60.60
30.60
52.02
kg
kg
Cft
1.04
0.61
0.31
0.52
190.69
134.44
325.13
34.34
290.79
87.24
203.55
Cft
Cft
Cft
Cft
Cft
Cft
Cft
11.63
26.17
36
122.80
kg
2
2
10.07
7.10
17.17
cft
cft
cft
20.60
11.90
kg
kg
5
Ring Beam (18"X12")
5.1 RCC (1:2:4)
Long sides
Short sides
Total
22.24
0.33
5.2 Steel
Main steel (4, #4 bars)
Shear stirrups (#3@ 12" c/c)
5.3 Centring and shuttering
6
200
4.5
17.34
1.5
40
2
10.17
7.17
1.5
1.5
6.25
6.25
2
2
Total
Deduct for 2 seismic bands
Net Total
30% (1:6) CSM
Stone
7
11.25
8
Seismic Bands
8.1 @ 2' from top of ring beam
8.11 RCC (1:2:4)
Long sides
short sides
10.17
7.17
1.5
1.5
0.33
0.33
Total
70.00
35.00
10.67
0.61
0.31
80.00
203.55
130.00
3.60
9.00
1.23
18.00
1.23
0.81
1.63
8.12 Steel
Main steel (2,#4) bars
Shear stirrups(#3 @ 12"c/c)
CRS-Mansehra
68
1.75
40
27.00
15.00
21/22
0.21
0.12
0.21
0.12
WATSAN
Operational Team
Detail of Materials
Detail of Quantities
Sub
Head
No
Description
Length
in ft
Breadth
in ft
Depth/Ht
in ft
5.25
10.17
7.17
1.5
1.5
0.33
0.33
No of
Units
Quantity
Unit
6.40
kg
2
2
10.07
7.10
17.17
cft
cft
cft
68
1.75
40
20.60
11.90
kg
kg
5.25
6.40
kg
Cement
(Bags)
Sand
(cft)
Gravel/
Crush
(cft)
Stone
(cft)
Shingle
(cft)
Labour
Steel
#3 Steel
#4
bars (kg) bars (kg)
10.00
3.60
9.00
Binding
Wire
(kg)
Skilled
Labour
Unskilled
Labour
Men-days
Men-days
0.06
18.00
0.06
0.81
1.63
27.00
0.21
0.12
0.21
0.12
10.00
0.06
0.06
15.00
7.17
0.33
5.5
26.03
cft
Short wall
6.5
0.33
5.5
23.60
cft
49.63
cft
67.40
kg
Total
9.2 Steel
Horizontal(#3 @6"c/c)
Vertical (#3 @6"c/c)
44
52
Total
11
70.80
kg
138.20
kg
10.17
5.58
226.99
Sft
10.67
2
10.67
2
0.333
0.333
1
1
37.91
1.33
36.58
68.00
37.91
12
6
1
4.00
Cft
Cft
Cft
kg
Cft
Rft
Rft
No.
Sft
Net Total
Steel (#3 @ 6" c/c) (as per detail)
12.2 Centring and shuttering
13 GI over flow pipe 1.5" dia.
14 GI wash out pipe 1.5" dia
15 GI Plug 1.5 "
16 Steel man hole cover (2'x2')
10.67
10.67
0.333
10.00
50.00
2.33
130.00
0.57
1.42
7.40
18.50
1.38
37.00
75.00
CRS-Mansehra
25.00
56.33
21/22
212.92
263.00
203.55
22.24
270.00
1.38
4.09
6.36
1.72
0.76
0.24
0.12
3.48
0.75
0.38
0.48
0.24
28.73
68.23
0.68
274.00
4.98
4.71
WATSAN
Operational Team
S.NO
Length of
Name of Line pipe
in
" ft "
Sector
Zone
Projected
Popolation
(persons)
Design Q in
US GAL
Total
Head
Losss
Hydraulic Grade
U/End
L/End
Ground
Level
Terminal
Pressrure in
ft of water
Supply Main
1
ST1--WST
4200
All
All
257
2.14
0.75
1.51
29.10
122.22
5750
5627.78
5558
69.8
Distribution NetWork
1
WST--1
100
108
1.35
0.75
1.20
19.30
1.93
5558
5556.07
5500
56.1
1--2
20
28
0.35
0.5
0.53
5.82
0.12
5556.1
5556
5500
56.0
1--3
2250
81
1.01
0.5
1.03
21.00
47.25
5556.1 5508.85
5450
58.9
WST--4
20
108
1.35
0.75
0.90
11.30
0.23
5557.77
5550
7.8
4--5
320
14
0.18
0.5
0.53
5.82
1.86
5557.8 5555.94
5535
20.9
4--6
800
95
1.19
0.75
0.90
11.30
9.04
5555.9 5546.86
5425
121.9
6--7
500
20
0.25
0.5
1.05
21.00
10.50
5546.9
5536.4
5450
86.4
6--8
500
81
1.01
0.75
0.90
11.30
5.65
5546.9 5541.25
5420
121.3
ST2--9
400
41
0.51
0.5
0.52
5.80
2.32
5451
91.7
5558
5545
5542.68
CRS-Mansehra
19
WATSAN
Operational Team
Remarks
Proposed
Proposed
Proposed
Proposed
Proposed
Proposed
Proposed
Proposed
Proposed
Proposed
CRS-Mansehra
19
WATSAN
Operational Team
KALSAN-II
U/C SACHAN
DESIGN CRITERIA
DESIGN PERIOD
Design Period
20 years
DESIGN POPULATION
No. of persons/H.H for present population
Design growth rate
=
=
7.5
3%
1.8
SECTOR NO. 1
# of persons/
H.Hs H.H
1 ZONE 1
Present population
(July 2006)
Persons
G.R.F
7.5
60
0
TOTAL
1.8
60
Design
population
(July 2026)
Persons
108
0
108
SECTOR NO. 2
# of persons/
H.Hs H.H
8
7.5
Present population
(July 2006)
Persons
G.R.F
60
1.8
TOTAL
60
Design
population
(July 2026)
Persons
108
108
SECTOR NO. 3
# of persons/
H.Hs H.H
3
7.5
Present population
(July 2006)
G.R.F
Persons
23
1.8
257
Design
population
(July 2026)
Persons
41
41
Persons
1 Schools
NO.
# students in 2006
1
20
# students in
2026
36
taking half as
outsiders
18
TOTAL
1 Mosques
NO.
1
CRS-Mansehra
Population in 2026
257
# attending
mosques (10%)
25.7
15/16
Daily req. @ 3
gpcd GPD (Imp)
77.1
Engr. Amir Jamal Qureshi
WATSAN
Operational Team
TOTAL
2 Animals
Large animals
Small animals
No.
No.
# in 2006
9
# in 2006
2
# in
2026
14
daily
requirement @
12 GPD (Imp)
168
# in
2026
3
daily
requirement @ 6
GPD (Imp)
18
231
GPD (Imp)
0.19
GPM (US)
2.33
3.17
GPM (US)
2.33
GPM (US)
2.33
77.1
GPM (US)
OK
GPM (US)
3355
GPD (US)
3355 GALLONS (US)
PROPOSED
CRS-Mansehra
15/16
WATSAN
Operational Team
KALSAN-II
U/C
SACHAN
TRANSPORTATION COST
TRANSPORTATION COST UP TO NEAREST ROAD SITE
Total
quantity Unit Transp. Rate (PKR)
Sr.#
Item Description
1 Cement
99
Bags
75
per bag
2 Sand
359
cft
0
per cft
3 Gravel
452
cft
25
per cft
4 Shingle
74
cft
25
per cft
5 Steel & Binding wire
642
kg
5
per kg
6 Stone
310
cft
25
per cft
7 Pipe materials
1
LS
5500
per job
8 Steel manhole cover
3
No.
150
per No.
TOTAL
7 % of Total Cost
Amount
Amount
(PKR)
(USD)
7425
123.8
0
0
11300
188.3
1850
30.8
3210
53.5
7750
129.2
5500
91.7
450
7.5
37485
0 % of Total Cost
Amount
Amount
(PKR)
(USD)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 % of Total Cost
Amount
Amount
(PKR)
(USD)
0
0
0
0
0
0
0
0
0
0
0
0
14 % of Total Cost
Amount
Amount
(PKR)
(USD)
4950
82.5
17950
299.2
22600
376.7
3700
61.7
3210
53.5
15500
258.3
7 Pipe materials
8 Steel manhole cover
1
3
LS
No.
5000
80
per job
per No.
TOTAL
CRS-Mansehra
14
624.75
0
0
Remarks
Remarks
Remarks
0
0
5000
240
83.3
4
73150
1219.1667
110,635.00
1,843.92
Remarks
5 trips per day each 1cft
5 trips per day each 1cft
5 trips per day each 1cft
5 trips per day each 1cft
5 trips per day each 1cft
21
% of Total Cost
WATSAN
Operational Team
KALSAN-II U/C
FITTINGS AND FIXTURES' DETAIL
SACHAN
NEW INSTALLATION
Sr
#
Item Description
1 Sockets 3/4"
Sockets1.5"
2 (wash out main tank)
3 Unions 3/4"
4 Ball valve 3/4"
5 GI Elbows 3/4" ( 90 deg)
6 GI Elbows 1.5" ( 90 deg)
7 GI T 2"-3/4"(source tank)
1
2
3
4
5
6
Sr
#
Sockets 3/4"
Unions 3/4"
Sockets 1/2"
Unions 1/2"
GI T's (3/4"-1/2")
Ball valve 3/4"(out let)
Item Description
Total length
(RFt)
Total
Qty
(No.)
SAY
(No.)
Unit cost
(PKR)
Total Cost
(PKR)
193
17
3284
45
90
42
2
2
2
1
DISTRIBUTION SYSTEM
1420
4
57
1420
1
14
1500
4
60
1500
1
15
4
48
3
3
3
2
56
204
21
62
122
2705
612
63
186
244
65
16
69
17
7
1
17
56
13
45
26
204
1110
914
897
776
182
204
4200
Qty/100
Rft (No.)
SUPPLY MAIN
4
168
4200
TAP STANDS
Qty/tap
Total
Total Tap
SAY Unit cost
stand
Qty
stands
(NO.)
(PKR)
(No.)
(No.)
6
10
60
80
32.75
6
2
12
15
13
6
1
6
8
13
6
1
6
8
85
TOTAL COST FOR FITTINGS AND FIXTURES
Total Cost
(PKR)
2620
195
104
680
14,867
ACCESSORIES' DETAIL
Location
Quantity
source tank
RFt
Unit
cost
(PKR)
132.65
source tank
RFt
93.9
563
source tank
RFt
62.35
312
No.
30
30
12
RFt
93.9
1127
main tank
wash out main
tank
Source tank,
main tank
RFt
93.9
563
No.
45
45
No.
600
1200
Valve chamber
No.
350
350
Sr
#
Item Description
GI Plug 1"
4 GI Over flow pipe 1.5" dia
5 GI wash out pipe 1.5" dia
6 GI Plug 1.5"
Steel Man hole cover
7 (2'x2')
Steel Man hole cover
8 (1.5'x1.5')
9 Barbed wire
CRS-Mansehra
wash out
source tank
main tank
unit
source tank
100
Ft
3.35
TOTAL COST FOR ACCESSORIES
25
335
4,923
WATSAN
Operational Team
KALSAN-II
U/C
SACHAN
A
1
2
3
4
5
6
7
8
Item Description
Quantity
CIVIL WORKS
Cement
99
Sand
359
Gravel
452
Shingle
74
Stone
310
Steel (#4 bars)
324
Steel (#3 bars)
308
Steel Binding wire
7
SUB TOTAL - A
Unit
Unit
Amount Amount
Rate
(PKR)
(USD)
(PKR)
Bags
cft
cft
cft
cft
kg
kg
kg
370
36630
0
0
0
0
15552
14784
336
67,302
610.5
0
0
0
0
259.2
246.4
5.6
1,122
3900
Rft
42.9
167310
2789
1420
Rft
42.9
60918
1015
32.75
25873
431
14867
11288
14,867
4,923
273,892
341,194
248
82
4,565
5,687
48
48
48
Remarks
PIPE WORKS
1 Supply main
3/4" dia
2 Distribution mains
3/4" dia
1/2" dia
790
Rft
Fitting & fixtures
3 (as per detail)
1
L.S.
4 Accessories (as per detail)
1
L.S.
SUB TOTAL- B
SUB TOTAL MATERIAL COST
TRANSPORTATION COST
Sr.#
1
2
3
4
5
6
7
8
Item Description
Cement
Sand
Gravel
Shingle
Steel & Binding wire
Stone
Pipe materials etc
steel manhole covers
Donkey Manual
up to nearest road
Jeepable
carriage carriage
site (PKR)
carriage (PKR) (PKR)
(PKR)
7425
0
0
4950
0
0
0
17950
11300
0
0
22600
1850
0
0
3700
3210
0
0
3210
7750
0
0
15500
5500
0
0
5000
450
0
0
240
Total
Amount
(PKR)
12375
17950
33900
5550
6420
23250
10500
690
Amount
(USD)
206
299
565
93
107
388
175
12
110,635
1,845
LABOR COST
Sr.#
Category
Quantity
unit
1 Unskilled Labor
118
man-days
2 Skilled Labour
46
man-days
3 Plumber
68
man-days
SUB TOTAL LABOR COST
6
4
6
15
Remarks
% of Total Cost
% of Total Cost
% of Total Cost
% of Total Cost
TOTAL COST
PKR
532,629
USD
8,877
PKR
13,316
USD
222
GRAND TOTAL
PKR
545,945
USD
9,099
CRS-Mansehra
13