Sie sind auf Seite 1von 23

SAP November 2014

Process Integration (PI) User Guide for setting up


Early Year Update 2015 Interface
Version 1.0

1|P a ge

SAP November 2014

Contents
1.

HOW TO DOWNLOAD PI CONTENT .............................................................................................. 3

2.

PI Configuration for a new EYU scenario ...................................................................................... 4

3.

Setting up of Receiver HR_GB_EFO_RESP_OUT .......................................................................... 15

4.

Setting up EYU for 2015 ............................................................................................................. 15

2|P a ge

SAP November 2014

1. HOW TO DOWNLOAD PI CONTENT


GO to SAP Service Marketplace:

http://service.sap.com/sp-stacks

Then follow the path given below


SAP Software Distribution Centre
Download
Support Packages and Patches
A-Z Index
Choose E for ERP
ESR Content (XI Content)
Click on XI Content E-Filing GB
Download the File Patch0 for XI Content E-Filing GB 1.0 SP 27
To download the File SAP HR Files, use the following path
SAP Software Distribution Centre
Download
Support Packages and Patches
A-Z Index
Choose E for ERP
ESR Content (XI Content)
XI Content HR
Depending on the system you are on.
SAP HR 600
SAP HR 604 or
SAP HR 608
Please download the latest patch.

3|P a ge

SAP November 2014

2. PI Configuration for a new EYU scenario


Note:
If you already have EYU configured for 2014, please go to section 3 of this guide.
Otherwise follow sections 1 and 2 taking care to use the 2015 objects which are
highlighted.
STEP 1:
Open the Configuration Wizard

4|P a ge

SAP November 2014

STEP 2: Choose Party Communication

5|P a ge

SAP November 2014

STEP 3:
Choose internal System and make sure adapter type is XI. Choose the basis version appropriate
to your PI system.

6|P a ge

SAP November 2014

STEP 4: Here the Service QI3_002 is the Service of our DEV R/3 System.
INTERFACE: HR_GB_EFO_EYU_OUT_15
NAMESPACE: http://sap.com/xi/HR

Press continue twice

7|P a ge

SAP November 2014

STEP 5: Choose Party and make sure adapter type is set to HTTP

8|P a ge

SAP November 2014

STEP 6

Interface Name : HR_GB_EFO_EYU_IN_15


Name space : http://sap.com/xi/E-FILING_GB/2015

9|P a ge

SAP November 2014

STEP 7:
Specify a sender agreement. Press continue

10 | P a g e

SAP November 2014

STEP 8:
INTERFACE NAME : HR_GB_EFO_EYU_OUT_15

11 | P a g e

SAP November 2014

STEP 9:

INTERFACE NAME: HR_GB_EFO_EYU_IN_15

12 | P a g e

SAP November 2014

STEP 10:
Specify the communication channel that you have created for your Business
component. The screen shot above shows the communication channel as in our
test systems.

13 | P a g e

SAP November 2014

STEP 11:
SCENARIO NAME : PAYE_EYU_GB_15
Finish and generate your configuration objects in the Scenario of your choice

14 | P a g e

SAP November 2014

3. Setting up of Receiver HR_GB_EFO_RESP_OUT


The 2015 EYU uses the same receiver as for the previous RTI and EOY
configurations. If HR_GB_EFO_RESP_OUT is already set up for EOY/ IYMV/
RTI configuration, it can be re-used and does not need to be changed.

4. Setting up EYU for 2015


If you have already configured EYU for 2014, follow the next section to set
up EYU for 2015.
3.1 Configure a new receiver determination
1. Select the Configuration scenario you have in your system. E.g.
PAYE_EYU_GB_14, or choose an another one to copy
2. Right click on receiver determination and copy objects

3. Rename the objects according to your naming standards and press the
create button
15 | P a g e

SAP November 2014

4. In the newly created configuration scenario, create each configuration


object as shown below.
5. Receiver determination

16 | P a g e

SAP November 2014

6. Add the interface and namespace as shown above and copy. A new page
opens as shown below.

17 | P a g e

SAP November 2014

If you do

not see the interfaces, please change the search and try again

18 | P a g e

SAP November 2014

7. Select the interface as shown above and press apply


8. Add the Component and party as shown in the diagrams below

9. Save your changes and move on to the configuration tab

19 | P a g e

SAP November 2014

10. Expand the receiver and click on the Sender interface


HR_GB_EFO_EYU_OUT_15 which displays the configuration objects on the
right screen. Follow the creation of each of the object as shown in the
following screens

20 | P a g e

SAP November 2014

11. Interface determination

Operations/Interface mapping

21 | P a g e

SAP November 2014

12. Receiver Agreement

13. Your end configuration should look like this.

22 | P a g e

SAP November 2014

Save and activate your change list. You have now configured the EYU
scenario for 2015