7/Monitoring and Controlling the Project

Chapter 7
Monitoring and Controlling the Project
This chapter addresses issues related to monitoring and controlling the project. Monitoring
refers to collecting, recording and reporting information about the project while controlling uses
this information to bring actual performance into agreement with the plan. The chapter begins
with an overview of the plan-monitor-control cycle. Emphasis is given to the importance of
designing the planning-monitoring-controlling process. Next the issue of data collection and
reporting is discussed including the topics of data collection and types of data, data analysis,
types of reports, and meetings. Following this, the earned value approach is presented. As the
chapter notes, earned value represents a way to capture both in-process performance and cost on
a certain date as measured against budget or schedule. Finally the chapter concludes with a
discussion of project control, the design of the control system, and scope creep.

Cases and Readings


Some cases appropriate to the subject of this chapter are:
Harvard: 9-193-013 American Airlines: The InterAAct Project (A) and
9-193-014 (B) This 17-page (and 11-page) set of cases describes the
design and implementation of an extensive knowledge information system
project. The implementation is in trouble in the A case and must be
reassessed. The (B) case describes the outcome of the successful
implementation. (A) 17 page teaching note (5-194-095) is available.
Western Ontario: 9-91-E009 Riverview Childrens Hospital This 14page case concerns an upcoming audit while in the middle of an information
system changeover that is in difficulty. The manager has to decide whether
to go ahead with the implementation or wait until the audit is over, either
alternative having serious negative consequences.
Harvard: 9681-091 Corning Glass Works: The Z-Glass Project This
excellent, 15-page case shows how a project can get into trouble on many
fronts: strategically, technically, and behaviorally. Involves a turn-around
project for a new production process that is getting worse instead of better.
Involves issues of monitoring, control, strategy, organization, and behavior.
Lots of data to work with. A 14 page teaching note (5-683-045) is available.

80

7/Monitoring and Controlling the Project

Harvard: 9-396-312 BAE Automated System (B): Denver


International Airport Baggage-Handling System This 3-page follow-up
to the (A) case (see Chapter 1) describes the control actions finally taken to
address the airport baggage system problem. A 32 page teaching note for
the (A) and (B) cases (5-399-099) is available.
Some readings appropriate to the subject of this chapter are:
T.L. Fox et al. Tools of the Trade: A Survey of Project Management
Tools (Project Management Journal, September 1998). The article reports
the results of a survey of PMI members concerning the computer tools they
employ. The results identify the tools they use, their level of use, what they
are used for, satisfaction with the tools, training received on the tools, and
the adequacy of the tools. Software beyond project management packages
are included in the survey.
H.J. Thamhain et al. Criteria for Controlling Projects According to
Plan (Project Management Journal, June 1986). This article reports on a
study of hundreds of project managers and the challenges and barriers they
perceived in successfully controlling projects. The potential problems leading
to schedule slips and budget overruns are identified and compared to the
directly observed reasons. Also, the general managers reasons for the slips
and overruns are compared to the project managers reasons and significant
differences are noted. Last, the criteria that seem to be important to control
are listed and discussed.
The value of this article for managers is the insight it gives concerning what
needs to be controlled to bring about successful projects. The major factors
are defining a detailed project plan that includes all key project personnel,
reaching agreement on the plan among the project team members and the
customer, obtaining the commitment of management, defining measurable
milestones, and detecting problems early.

81

7/Monitoring and Controlling the Project

Answers to Review Questions


1. Why cant the PM use the organizations current information
system for project monitoring and reporting?
There are two main reasons why the PM cant use the organizations
current information system for project monitoring and reporting:
o These systems are often set up to report information at certain specific
periods (e.g., the end of the month or quarter). The information
required to control a project often does not conform to such rigid
timetables.
o The organizations system is usually structured to deal with the
organizations standard divisions, and departments. Projects rarely
conform to these boundaries.
2. What does it mean to say that project monitoring and control are
on the opposite sides of project selection and planning?
o Project selection and planning specify the goals for the project. The
plan also details what activities and schedule must be met; things the
project manager must control.
o Project monitoring and control seek to ensure that the project is
making progress toward the achievement of these goals.
3. The monitoring system is the direct connection between project
planning and control. Why is this true?
Project planning specifies the activities, resource usage, and the goals for
the project while control seeks to ensure that the project is making
progress toward the achievement of these goals.
Monitoring is concerned with collecting and reporting information. As
such, monitoring connects planning and control in that the plan specifies
the types of data that need to be collected and the reporting becomes the
basis of control.

82

7/Monitoring and Controlling the Project

4. Why is it probably a good idea to avoid periodic reports, except in


specific cases such as reports tied to the organizations
accounting system?
It is probably a good idea for two reasons:
o It is more appropriate to let schedules, milestones, scope changes,
problems, and the project teams general need for information dictate
the timing of reports.
o There is a tendency for recipients to ignore periodic reports.
5. Aside from the obvious benefits for project control, what other
benefits might result from a good project reporting system?
Other benefits from a good project reporting system include:
o Less wasted time reporting information that is not used.
o Better informed team members and stakeholders, and
o A better record of the project that can be used to facilitate future
project planning.
6. If the calendar should not dictate reporting frequency, what
should?
The need for information should dictate the report frequency. For
projects, it is more appropriate to let milestones, scope changes,
problems, and the project teams general need for information dictate the
timing of reports.
7. Using earned value analysis, explain how the total cost of a
partially completed can be estimated.
The total cost of a partially completed project can be estimated by
dividing the amount spent to date by the estimate of the projects
percentage completion. However, in general, this is not an effective way
to estimate the cost of a partially completed project.
A considerably more accurate approach is apt to be that of summing the
costs of completed activities and a knowledgeable guess on the cost
incurred on activities underway.

83

7/Monitoring and Controlling the Project

Suggested Answers to Discussion Questions


8. When making an estimate for the time and cost to execute a
project, should the time and cost required to develop the
planning, monitoring, and controlling systems be included as
well? Should the actions required to monitor and control a
project be included in the projects action plan or WBS?
Yes, the time and cost required to develop the planning, monitoring, and
controlling systems should be included in the projects budget. Similarly,
the actions required to monitor and control the project should be included
in the WBS. These are essential tasks for the successful completion of the
project.
9. The chapter includes an example of a firm where the PM
dispensed with all the planning formality because no one ever
looked at it anyway. What did the PM think the purpose of such
planning was in this firm? What should the firm do in the future
to correct this problem?
It appears the PM in this case believed that project planning was not
important since no one looked at it. Therefore, the PM likely believed that
project planning was a waste of time that distracted him/her from more
important work. The result was a major loss of business.
To correct this situation the company needs to:
o Emphasize the importance of planning to the ultimate success of the
project. This may require formal training programs, perhaps including
case studies that demonstrate the types of problems encountered in
projects that were inadequately planned.
o Ensure that management become more involved in project planning
and review project plans.
o Modify the system used to review the performance of project managers
to include project planning.

84

7/Monitoring and Controlling the Project

10. In such fields as psychology and sociology, verbal


characterizations are frequently used to show the amount of
some factor. How might one set up such a measure for a project
management characteristic such as the energy of the project
team?
Team members could be asked to score on a 5 or 7 point scale the extent
of their agreement/disagreement to statements such as:
o I look forward to coming to work each day.
o I find facing and resolving new challenges stimulating.
o I often take immediate action when I discover a problem.
11.

How might one measure team morale?

There are a wide variety of instruments in the organizational behavior


literature available for accessing team morale. Again, using a 5 or 7 point
scale, team members could be asked to rate the extent of their
agreement/disagreement to statements such as:
o I enjoy working with my fellow team members.
o I have confidence that our project team can satisfactorily resolve any
issues that may arise.
o I would welcome the opportunity to be assigned to another project
team.
12. How can the PM circumvent the problem that the monitoring
system can only report on activities that have passed, thus
telling the PM what has already gone wrong but not what will go
wrong in the future?
One way the project manager can use the monitoring system to predict
future problems is to extrapolate trends in the data to the future and then
compare this projection with the plan. Indeed, a better use of the
monitoring system would be to use the information to anticipate future
problems rather than reacting to them once they occur. Along these lines,
the monitoring system could also include lead indicators as symptoms
of problems.

85

7/Monitoring and Controlling the Project

13. How might using electronic media to report project information


lead to problems with control?
There are two main ways the use of electronic media could lead to
problems with control:
o The PM spends more time managing the electronic media (e.g., the
project management software) than actually managing the project.
o The speed that information can be transmitted can create problems.
For example, an inaccurate entry could immediately trigger an
exception report causing team members to shift their focus to an
erroneous or irrelevant issue.
14. Explain how the earned value chart captures all three
objectives of a project: performance, cost, and schedule.
A cost variance is calculated as the difference between Budgeted Cost of
Work Performed (BCWP) and the Actual Cost of Work Performed (ACWP).
If the ACWP is larger than the BCWP, the variance is negative indicating
that more was spent for the work performed than was budgeted. The
schedule variance is calculated as the difference between the BCWP and
the Budgeted Cost of Work Scheduled (BCWS). A negative schedule
variance indicates a behind schedule situation. In terms of performance,
the earned value chart indicates whether progress is up to expectation,
the baseline planned for this point in time.
15. Why isnt there an earned value reporting convention that
allows progress on a task to be credited when the task is half
completed? Wouldnt this be more accurate than giving credit
only when the task is fully completed?
It would be if, and only if, there was a reliable way to estimate the 50%
completion point.
Note: The answer to Question 7 notes a better way to proceed with an inprocess cost estimation.
16. When would spending and schedule variances be more
informative than ratios? When would ratios be better?
o Spending and scheduling variances are more informative when trying
to understand the in-process performance for a given project at a
particular point in time.

86

7/Monitoring and Controlling the Project

o Ratios are more informative when trying to compare the performance


across projects, project managers, or the progress of a project over
time.

87

7/Monitoring and Controlling the Project

17. How should a PM reconcile the dual purposes of control:


conserving resources and regulating results through the use of
resources?
The bottom line with control is that you dont want the costs of the control
systems to exceed the benefits.
18. Identify situations where each of the following control tools
might be useful: earned value charts, benchmarking, critical
ratios, control charts, variance analysis, trend projections.
o Earned value charts are useful for monitoring the progress of inprocess projects.
o Benchmarking is useful in the project planning phase in helping
determine project goals and resource requirements. Benchmarking
can also be used to access an organizations project management
systems and procedures.
o Critical ratios, control charts, and variance analysis are also useful for
monitoring the progress of in-process projects. In particular, the
critical ratio is a single measure that includes performance, cost and
schedule. Plotting the critical ratio on a control chart provides
opportunities to spot patterns that may lead to problems.
o Trend projections can be performed on any of the data collected by the
monitoring and control system to estimate future values of the data
and take corrective actions before the situation becomes a serious
problem.
19. How might the existence of a change control system affect the
behavior of a client, or a project team member, who desires to
make a change in the project?
By adding greater scrutiny, a change control system may reduce the
number of change requests, particularly casual requests for changes.
20. In order to manage for overall project success, control must
be exercised at the detailed work level for each aspect of project
performance or no significant change will occur. Does this mean
that the PM should micromanage the project? If not, what does it
mean?
It does not mean that the project manager should micromanage the
project. Rather, it suggests that each project team member needs to
monitor and control his or her own work.

88

7/Monitoring and Controlling the Project

21. Select a hypothetical project (e.g. designing and building a


Web site, installing a new machine in an assembly line, or
conducting a major inspection and repair of a passenger aircraft),
and briefly describe an example of how each of the following
types of control data might be used for project control:
(a)
Frequency counts
(b)
Raw numbers
(c)
Subjective numeric ratings
(d)
Indicator and surrogate measures
Designing and building a new Web site, gave the following types of data
control:
(a) Frequency counts:

Spelling errors per page, number of incorrect


links, pages that take longer than 30 seconds
to load.
(b)Raw numbers:
Time for pages to download, size of graphic
files, number of lines of code.
(c) Subjective numeric ratings
Quality of webpages, ease of navigation,
search capabilities.
(d)Indicator and surrogate Time spent at a site could be used as a
surrogate
measures
for user satisfaction.
22. Of all the rules for conducting meetings, the most difficult to
enforce is the injunction against the weekly (or daily) standard
project progress report (the show and tell meeting). Why is
this, and under what circumstances do you think such meetings
are justified?
One reason it is hard to not have the weekly progress meeting is that
people like to (a) report on the aspect(s) of the project with which they are
familiar and (b) demonstrate what they have accomplished.
The weekly progress meeting might be appropriate early in the project
when coordination is required but team members are still getting to know
each other and have not had an opportunity to develop informal
communication channels.

89

7/Monitoring and Controlling the Project

23. If your project management software calculates earned value,


or any other standard item to be reported, differently than the
Project Management Institute suggests, should you deal with this
matter in management reports? If so, how?
The important thing about variances is that you understand what they
mean and interpret them correctly in reports. Whether the sign is positive
or negative when the cost is over budget or behind schedule is not that
important as long as you understand what the calculation is telling you.
Being able to properly interpret the variance and act accordingly is the
critical task.
Therefore, making a point in a report to note that the software package
calculated a specific item differently that the standards set by the PMI is
not that important, interpreting the number correctly and discussing the
implications are.
24. Logically, when using earned value data in the critical ratio
formula, should the budgeted cost be the planned value or the
earned value? What problems occur with each choice?
The critical ratio (CR) is the product of the schedule ratio times the cost
ratio:
CR = (actual progress/scheduled progress) x (budgeted cost/actual
cost).
The budgeted cost can be either the planned value or the earned value. If
the planned value (i.e., the budgeted cost of the work scheduled) is used
then it may be identical to actual cost (giving a value of 1) and thus may
suggest that the project is on budget. However, if the earned value (i.e.,
the budgeted cost of the work performed) is used then it may be
considerably less than 1 showing that considerable work still needs to be
done on the project resulting in a cost overrun.

Solutions to Problems
25.

The project in this problem is in its 26th week.

Actual cost of work performed (ACWP) = $270,000


Budgeted cost of work performed (BCWP) = $272,000

90

7/Monitoring and Controlling the Project

Budgeted cost of work scheduled (BCWS) = $261,000


Cost/spending variance = BCWP ACWP = $272,000 270,000 = $2,000
Schedule variance for the project = BCWP BCWS = $272,000 261,000 =
$11,000
Schedule Performance Index (SPI) = BCWP/BCWS = $272,000/261,000 =
1.042
Cost Performance Index (CPI) = BCWP/ACWP = $272,000/270,000 = 1.007
In summary, less has been spent than the baseline plan, and given what
has been spent, more progress has been made than was anticipated.
26. In this problem, the project has just completed the 87th item on its
action plan.
Actual cost of work performed (ACWP) = $156,000
Budgeted cost of work performed (BCWP) = $162,000
Budgeted cost of work schedule (BCWS) = $168,000
Cost/spending variance = BCWP ACWP = $162,000 156,000 = $6,000
Schedule variance = BCWP BCWS = $162,000 168,000 = -$6,000
Schedule Performance Index (SPI) = BCWP/BCWS = $162,000/168,000 =
0.964
Cost Performance Index (CPI) = BCWP/ACWP = $162,000/156,000 = 1.038
In this case, less has been spent than the baseline plan. However, given
what has been spent, less progress has been made than should have
been.
27.

The project being considered in this problem is in its 6th week.

Actual cost of work performed (ACWP) = $400 + 180 + 300 + 400 + 200
= $1480
Budgeted cost of work performed (BCWP) = $300 + 200 + 250 + .2(600) + .
2(400) = $950
Budgeted cost of work scheduled (BCWS) = 300 + 200 + 250 + .8(600) +
.5(400) = $1430
Cost/spending variance = BCWP ACWP = $950 1,480 = -$530
Schedule variance = BCWP BCWS = 950 1,430 = -$480
Schedule Performance Index (SPI) = BCWP/BCWS = $950/1,430 = 0.664
Cost Performance Index (CPI) = BCWP/ACWP = $950/1,480 = 0.642
In this instance, more has been spent than the baseline plan and, given
what has been spent, less progress has been made than should have
been.
91

7/Monitoring and Controlling the Project

Critical ratio (CR) = (BCWP/BCWS)(BCWP/ACWP) = ($950/1430)


($950/1480) = 0.426
Budget at completion BAC) = $300 + 200 + 250 + 600 + 400 = $1,750
Estimated (remaining cost) to completion (ETC) = (BAC BCWP)/CPI =
($1750 950)/0.642 = $1246.11
Projected (total cost) estimated at completion (EAC) = ETC + ACWP =
$1246.11 + $1480 = $2726.11

92

7/Monitoring and Controlling the Project

28.

This assignment involves repeating problem 26 using MSP.

Students should begin by inputting the original planned project data into
MSPs entry table as it appears in the problem. Only the activity names,
predecessors, durations, can be entered in the Entry table.
The Gantt chart would look as follows:

The budgeted cost data is entered using the Cost Table. To enter this data
you select the View menu, then Tables, then select Cost from the drop
down list. Enter the budgeted cost information under the Fixed Cost
section of the table. Fixed costs are assigned by activities as opposed to
by resources. This problem is concerned about a cost of activity not a
resource cost. The table will look as follows:

Once the original data is in the action plan format, the students should
save the Baseline data so that a comparison to actual can be calculated
by MSP. To do this you need to go to the Tools menu, select Tracking, then
select Save Baseline, then click OK so that you are saving the baseline for
the entire project.
Once the baseline has been saved, students need to enter the actual data
provided in the problem. You next need to create a table to enter the
actual costs and percent complete. By default MSP automatically
calculates actual costs based on the percent an activity has been
completed. In this example we need to turn off this feature. To do this
you must select the Tools menu, then the Options line, then you select
Calculations Tab. Next you deselect the option Actual costs are
calculated by MSP. Once the automatic cost calculation is turned off, you
select Table from the View menu and then select the Tracking table from

93

7/Monitoring and Controlling the Project

the drop down menu to enter the information that you have on actual
costs and percent complete. Enter the information that is provided in the
case. The software will calculate the rest. Your spreadsheet/table should
look as follows:
Note: The start and finished dates will be based on the dates that you
start the project, in this example the project was started on January 15,
2001. If you choose not to enter a start date, MSP will default to using
todays date.]

Once you have entered the actual data, MSP will calculate the information
needed to answer questions #27 based on the date of comparison, in this
problem, that is the end of the sixth week. Using the start date of January
15th, the end of the sixth week would be February 23, 2001. (No matter
what your start date is, it is easy to see in MSP when the end of the sixth
week would be.)
You must first enter that date for the comparison, to do that you go to the
Project Menu, select Project Information and enter the date under Current
Date. Next, you are ready to view the earned value information for this
project. Select the View menu, then Table, then More Tables, from this
drop down menu select Earned Value table and click Apply. The following
is the chart that should appear:

By adding or subtracting the totals of the columns you can determine the
total project variances as outlined in Problem #26. Note: Please recall
that MSP reverses the calculations.

94

7/Monitoring and Controlling the Project

Incidents for Discussion Suggested Answers


St. Margarets Hospital
Question: what should Mary Lynn do?
Mary Lynn needs an aggregate measure of project performance for the three
projects in question. An earned value analysis would be an effective tool to
see if the projects are on schedule, behind, etc. She would be able to
determine the expected completion dates for the projects. Milestones should
also be built into the project plans so that she could measure clearly along
those progress points, for each project.
Stoneworth Paving Company
Question: if you were Preston, what characteristics would you be
looking for in a new control system?
For the future, Preston needs a control system that will better identify and
report on supplier constraints and dates, staffing, and quality. If the project
is to be expedited in order to catch up with the schedule, a control system
that is oriented toward a high-pressure, time-critical projects will be required.
Monitoring of the proper measures will also be critical.
Will a new control system be adequate for the problem? Explain.
A new control system is needed, but will not solve all of the problems, or
keep this project from being late.
Happy Customers
Question: what do you suggest Jeremy Smith do?
Jeremy needs to be sure control systems for monitoring the project are
incorporated into the plan. He should ask his project team to develop
additional steps and processes throughout the life of the project to include
more than an update of status. The controls should include a method to
accurately report duration changes from the original estimate, resource
utilization changes, etc. An earned value analysis during the project would
be appropriate. This type of analysis would allow the team to make
95

7/Monitoring and Controlling the Project

adjustments to the steps in the action plan in a timely fashion so that the
entire project is not affected. This would also allow Alex to monitor the
project more closely.

96

7/Monitoring and Controlling the Project

The company should also develop a change control system for their work
with clients. Such a system will minimize the impact of the scope creep that
appears to happen at J. Z. Smith. They need a formal process to deal with
changes to the original project plan. Jeremy can design this system to
include his input. He can make sure that the budget and estimate of
completion dates are adjusted if he and the client both agree on the cost and
duration of any changes the client wants in the scope of the project.
Cable Tech, Inc.
Question: Does the monitoring and control method seem adequate?
No, the monitoring and control method is not adequate. Jean will not be able
to take effective action from headquarters, being removed from the site.
What are the potential problems?
Among some of the potential problems:
o Jean is located at headquarters and any delays in getting reports to her
will leave too long a period between occurrence of the attendance
problem and a response.
o The policies themselves are also in question. There is no flexibility in the
policies for differences in reasons between sites. In many cases the
problem may be the companys fault, beyond the control of the employee.
o The employees were never consulted on the design of these policies and
may reject their enforcement.
o Although punishment is provided for, rewards for good attendance are not
recognized so no positive motivation is being considered.
Additional Incidents for Discussion

97

7/Monitoring and Controlling the Project

Carver Insurance Company


Alex Franks joined Carver Insurance Company eight months ago. He is an
experienced management information systems executive who has been
given the task of improving the responsiveness of Carvers information
systems group to the end-user. After several months of investigation,
Alex felt he understood the current situation clearly enough to proceed.
First, approximately 90 percent of end-user requests came to
Information Services (IS) in the form of a project, or, more commonly,
one step of a project. Accordingly, Alex felt he should initially direct his
efforts toward integrating ISs approach to projects with the companys
formal project management system.
It has been Alexs experience that most problems associated with IS projects
suffer from poor project definition and inadequate participation by the enduser during the system design phase. Typically, the end-user does not
become heavily involved in the project until the new system is ready to
install. At that point, a great deal of work is required to adapt the system to
meet end-user requirements. Alex decided to institute a procedure that put
end-user cooperation and participation on the front end of the project. The
idea was to define the objective and design of the system carefully, making it
consistent with the end-users need. If that was done, system
implementation would be reasonably simple, rather than the always
disturbing initial introduction to the end-user of his or her new system.
Alex also recognized that something had to be done to control the
programming quality of ISs output. A more effective front-end approach to
IS projects would subject IS managers to more intense pressure to produce
results within users needs, including time constraints. Alex was concerned
that the quality of the IS output would deteriorate under those conditions,
especially given the lack of technical expertise on the part of the end-users
and outside project managers. To solve this problem, Alex recommended
creation of an IS quality assurance (QA) manager who would approve the
initial steps of the project and review each additional step. The QA manager
would have authority to declare any step or portion of the output inadequate
and to send it back to be reworked.
Questions: Is this a good control system for IS? Why or why not?
Does it represent a good control point for company projects using IS
to accomplish one portion of the project objective? What would be
your answer if you were a non-IS project manager?

98

7/Monitoring and Controlling the Project

This is a good control system for improving the user responsiveness of IS but may be
unresponsive to the larger needs of the firm, particularly if later activities depend on the
completion of ISs tasks. An external PM would be concerned about the delay on the IS
activities as they strive for meeting internal quality requirements.

Suggested Case Analyses and Solutions


St. Dismas Assisted Living Facility -- 5
Teaching Purpose: This installment of the Assisted Living Facility case addresses issues related
to project progress meetings and determining how much time has to be made up to get back to
the original baseline schedule.

99

7/Monitoring and Controlling the Project

Question 1: What do you think the construction project manager


should have done when the Director of Security stopped attending
the project meetings?
The construction project manager has set up a very good communications
system to keep the project team informed, even if they were not able to
attend the meetings. Kyle Nanno should deliver the CEOs message to the
Director of Security, if he does not respond within the deadline date that Kyle
sets, Kyle should have Fred and the other members of the project team give
their input into the security panel location decision. Fred needs to take
appropriate disciplinary action against the Director of Security for not
fulfilling his job duties as a member of the project team.
Question 2: Do you think it is an effective communications tool to
send the construction project meeting minutes to the ALF steering
team and the President? Support your answer.
It is an effective means of communications to send project team meeting
minutes on this project to the construction team, especially as the project
nears completion and a great number of details need to be followed up on.
However, the Steering Team and the President do not necessarily need the
level of detail that they are given. If details of a project are provided, most
people will want to comment on it and be involved in any decisions that need
to be made. If this is not appropriate, then those people should only be
provided with information about what directly affects their area and told that
their input is important to the success of the project.
Question 3: How much time has to be made up for the original,
baseline schedule to be met?
The Gantt chart in the case has been updated as of 4/11/01. The project
shows a finish date variance of 14 days. The project as a whole is 14 days
behind schedule. They ran 15 days late on Phase 1 of the project. The
project was 14 days early on both Phase 2 and Phase 3 of the project.

100

7/Monitoring and Controlling the Project

Question #4: Develop an action plan and draw a Gantt chart for the
Parking Lot phase of the project. Answer Freds questions.
If everything goes as scheduled the Gantt chart for the Parking Lot
construction would look as follows:

If St. Dismus did not hear from the city until May 1, 2001, the Gantt chart
would be adjusted as follows: (New end date for the project would be
6/12/01.)

The latest date to be notified by the city to meet the June 15th deadline is
May 7th. This would make the end date of the project June 15th.
Question 5: What information does Fred need to make a decision
about building a hair salon?
This is an example of scope creep. The building of the hair salon was not in
the original project plan. Fred must determine, first if he wants to build a
hair salon for residents, he should have the COO and VP of marketing do a
complete business plan with a cost benefit analysis/return on investment for
this endeavor. After that is done, Fred must determine the impact that this
would have on the construction project. He must identify the additional
costs, changes necessary to the design and schedule.

101

7/Monitoring and Controlling the Project

Palmstar Enterprises, Inc.


Teaching Purpose: This case provides students with the opportunity to investigate the trade-off of
introducing a product late but staying on budget versus increasing the budget to complete the
project on schedule.
Question 1: What has a larger impact on Palmstars profits, delaying
the 2000cs introduction by 3 months or increasing the projects
budget by 30 percent?
Delaying the launch of the product by 3 months would result in a loss of
$18,000,000 (200,000 units $450/unit .2 contribution margin) in
contribution to profit and overhead. Adding resources to complete the
project on time would increase costs and therefore lower profits by $900,000
(30% of $3 million).
Therefore, not launching the 2000c on time would have a much larger impact
on Palmstars profits.
Question 2: Are there other factors you would consider in addition
to profit?
There are a variety of other factors that should be considered including
damage to Palmstars reputation and loss of market share. The analysis
could also be enhanced had information been available on how rapidly unit
prices decline in this market and Palmstars cost of capital. With this added
information, a discounted cash flow analysis could have been undertaken.
Question 3: What should Palmstar do? Why?
Clearly, Palmstar should spend the extra $900,000 to launch the 2000c on
time. This will maximize its profits, help to enhance its reputation, and help
preserve its competitive position. There is usually very little to be gained
from being late to the market.
Question 4: How generalizable do you think the results of your
analysis in this particular case are to other situations?
Very generalizable.
Companies often focus too much on the added cost of completing a project
on time but fail to investigate the benefits of getting a product to the market
sooner. The benefits of getting to market sooner increase as the intensity of

102

7/Monitoring and Controlling the Project

competition increases, as product life cycles shorten, and as pricing pressure


increases. These characteristics are all common in todays globally
competitive marketplace.

103