Beruflich Dokumente
Kultur Dokumente
TABLE OF CONTENTS
SECTION
Page
TABLE OF CONTENTS
1.1
DISCLAIMER/INTRODUCTION
Disclaimer
Introduction
Bentall Centre Contacts
Approval Process
1.
Tenants/Contractor Contact
2.
City of Vancouver and Regulatory Bodies
3.
Tenants Architect/Interior Designer
4.
Drawing Review
5.
Signage Review
6.
Contractors Documentation
1.4
1.4
1.5
1.6
1.6
1.7
1.9
1.9
1.9
1.10
2.1
2.2
General
Base Building Changes
Demising Walls
Safety
Electrical
Communications
Energy Conservation
Integral Work
Mechanical
HVAC
Auxiliary Air Conditioners
Structural
Plumbing
Curtain Wall
Material Selection
Coring and Penetrations
3.1
3.1
3.2
3.2
3.2
3.4
3.4
3.5
3.5
3.5
3.6
3.7
3.8
3.9
3.9
3.10
Ceilings
Doors
Lighting
Perimeter Induction Units
Interior Walls
Demising Walls
Fire Protection
Sprinklers
Public Corridors
Elevator Lobbies
Security
Floor Areas
Freight Elevator Sizes
Drapery
Telephone and Communications
Construction Clean Up
Fire Safety Plan
Page
4.1
4.1
4.2
4.3
4.4
4.4
4.4
4.5
4.6
4.6
4.7
4.7
4.7
4.8
4.8
4.9
4.9
WorkSafeBC
Noise
Odours
Insurance
Deliveries
Security
Damage and Repair
Curtain Wall
Housekeeping
Waste Removal / Recycling
Administration
Onsite Supervision
Theft
Smoking
5.1
5.1
5.2
5.2
5.3
5.3
5.4
5.4
5.4
5.5
5.5
5.6
5.6
5.6
ATTACHMENTS
1.
Entry Door Specifications, Door Signage & Access Card Readers (Page 6.1)
2.
3.
Demising Wall, Seismic T-Bar, Sound Baffle at Induction Unit & Light Fixture
Specs (Page 8.1)
4.
5.
6.
7.
8.
9.
10.
11.
DISCLAIMER
This information has been prepared to provide Tenants with a convenient source of
building information relevant to the Bentall Centre.
While every effort has been made to ensure the accuracy of the information contained
herein, Ivanho Cambridge Inc. assumes no responsibility for any errors, omissions,
and/or revisions to this information.
This manual sets out general procedures with respect to the operation of the Complex.
The terms, covenants, and conditions contained in the Tenant's Lease with the
Landlord supersede any of the procedures set out in this manual.
This manual is confidential and proprietary to Ivanho Cambridge Inc. It is released
solely for the purposes of communicating policies and procedures to the tenants of
Bentall Centre. Copying or use for any other purpose is strictly prohibited.
INTRODUCTION
Located in the heart of downtown Vancouver on Burrard Street between Dunsmuir and
Pender Streets, the Bentall Centre is the largest integrated office complex in Western
Canada. The Bentall Centre's four towers encompass a total area of approximately 1.5
million square feet of office and retail space.
It is intended that the high standard of design and building finishes of the Bentall Centre
will be carried through into the Tenant Improvements, and to that end, these guidelines
have been prepared.
The purpose is to assist and introduce the Tenant and/or their designer or contractor to
the base building design, systems, contacts and opportunities inherent to the Centre.
Utilizing these guidelines will enable the Tenant to renovate and occupy their premises
without unnecessary delays, alterations and expense.
Questions concerning leases, building management and occupancy should be directed
to Bentall Centre Management.
There is a strict approval process in place, and questions regarding information and/or
approvals concerning planning, construction and scheduling should be directed to the
Bentall Centres Tenant Coordination team.
These guidelines are to be read in conjunction with and form a part of the lease
document. In the event of any conflict between these guidelines and the lease, the
provisions of the lease shall prevail.
Page 1.4
778-328-5978
778-328-5989
abriard@canderel.com
778-328-5982
778-328-5989
brosenlund@canderel.com
778-328-5960
778-328-5989
Suite 1525, Bentall Tower II
555 Burrard Street
Box 226
Vancouver, BC V7X 1M9
Page 1.5
APPROVAL PROCESS
1.
Page 1.6
2.
Page 1.7
The relevant and applicable authorities include, but are not limited to, those listed
below. The Tenant must consider all those pertinent to the project.
City of Vancouver
Building Permits - Health Department
Fire Department
Page 1.8
3.
4.
Drawing Review:
The Tenant or designer will submit for approval preliminary drawings that will
provide sufficient detail to illustrate the intended design theme. The Tenants
preliminary drawings will be checked from the standpoint of physical
compatibility; and upon review, working drawings and specifications of the
Tenant's work will be required [two (2) copies of prints].
The Tenant or designer will submit 2 full sets (must be 24 x 36) of architectural,
mechanical and electrical drawings and specifications as well as an electronic
copy of these drawings to the Tenant Coordination team. Drawings will be
reviewed and comments provided within 10 business days. Once reviewed, the
Landlords consultant will proceed to design the electrical, plumbing, HVAC,
reflected ceiling and sprinkler drawings. The costs for these drawings will be the
Tenants responsibility.
It is the Tenants or designers responsibility to come to site to verify existing
measurements.
5.
Signage Review:
All signage drawings must have prior written approval. (See Attachment 1 for
Building Standard requirements.)
The Tenant and the chosen general contractor or designer will also provide to
the Tenant Coordination team:
NOTE: The Tenant Coordination team must approve the use of all subcontactors and subtrades.
Page 1.9
6.
Contractors Documentation:
Prior to the commencement of any work, the General Contractor is required to
read the latest version of the Construction Manual and forward the following
documentation
to
the
Construction
&
Projects
Coordinator
at
billy.rosenlund@ivanhoecambridge.com
Trades list complete with contact names & numbers (including all
subtrades)
Worksafe BC Certificate
Electronic copy of drawings (pdf and cad) and 2 hard copies (see
Drawing Review on page 1.9)
Corridor & elevator lobby carpets must be protected with RAM Board ( see
Attachement 7)
Page 1.10
Landlords Consultant:
Omicron Consulting Group, Flow Consulting, Integral Group and Stantec are the four
Landlords base building consultants and are strongly recommended to perform all
Structural, Mechanical, Electrical and Fire Safety design work on all new construction
and renovation projects in the Bentall Centre. If desired, it is also possible to use an
alternate reputable Mechanical and Electrical Consultant upon approval from the
Bentall Centre Tenant Coordination team. However, please be advised that it is
mandatory that one of the recommended Landlords consultants review and approve all
related Mechanical and Electrical drawings executed by outside agencies prior to work
commencement; as well as inspect and submit a final Mechanical and Electrical
inspection report to Bentall post-construction. If choosing to use the services of an
alternate consultant, the tenant must be in agreement that the landlords pre-qualified
consultant will review, and recommend changes to the drawings where required, at the
tenants expense.
The recommended consultant will be responsible to supply the Landlord with two sets
of hard copy prints (24x36) of final design plans (one for Tenant Coordination team
and one for the Engineering Department). For future reference, as-built drawings
(AutoCad), design specifications, maintenance manuals, air conditioning balancing
reports and all pertinent information related to the project, must be emailed to the
Construction & Projects Coordinator. All drawings done by outside agencies must be
presented to the Landlord in an acceptable electronic form for inclusion in the Bentall
Centre electronic database. If you have further inquiries as to this process, please
contact the Tenant Coordination team at 778-328-5962.
Landlords Recommended Consultants:
Omicron
Fifth Floor, 595 Burrard Street
Vancouver, BC V7X 1L4
Flow Consulting
Suite 104 740 Nicola Street
Vancouver, BC V6G 2C1
Integral Group
Suite 180 200 Granville Street
Vancouver, BC V6C 1S4
Stantec
Suite 1100 111 Dunsmuir Street
Vancouver, BC V6B 6A3
Landlords Consultants
Page 2.1
General Contractors
Canadian Turner Construction
Suite 990 355 Burrard Street
Vancouver, BC V6C 2G8
Pagliaro Projects
3940 Charles Street
Burnaby, BC V5C 3K8
Page 2.2
Construction Clean-Up
SerVantage Services Corp.
#101 245 Fell Avenue
North Vancouver, BC V7P 2K1
Demolition
LPS Demolition
#120-2544 Douglas Road
Burnaby, BC V5C 5W7
Page 2.3
Environmental Consultants
Pinchin West
Suite 200 13775 Commerce Parkway
Richmond, BC V6V 2V4
Golder Associates
500-4260 Still Creek Drive
Burnaby, BC V5C 6C6
Page 2.4
Glazing Contractors
Accurate Glass Ltd.
#112-9 Burbidge Street
Coquitlam, BC V3K 7B2
Geo Glassworks
7379 203B Street
Langley, BC V2Y 1V1
Team Glass
1711 Franklin Street
Vancouver, BC V5L 1P6
Page 2.5
Lathams
th
#100-1060 West 8 Ave.
Vancouver, BC V6H 1C4
Stolz Mechanical
111-4268 Lozells Avenue
Burnaby, BC V5A 06C
Painting Contractors
Westcan Painting & Decorating Ltd.
1820 Pandora Street
Vancouver, BC V5L 1M5
Page 2.6
TYCO
200-750 Cambie Street
Vancouver, BC V6B 2P2
Sprinkler Contractors
Phaser Fire Protection
th
Unit #1,19080 96 Ave.
Surrey, BC V4N 3R3
Systems Balancing
K.D. Engineering Co.
239 East 6th Avenue
Vancouver, BC V5T 1J7
Page 2.7
CE Communications Ltd.
2233 Quebec Street
Vancouver, BC V5T 3A1
Symtech Canada
Suite 101 - 3650
Bonnville Place
Burnaby, BC V3N 4T7
th
4 Utility Inc.
7590 Lowland Drive
Burnaby, BC V5J 5A4
Page 2.8
DESIGN CRITERIA
BASE BUILDING, ELECTRICAL AND MECHANICAL
The following are the base building design criteria for the Bentall Centre. The design
criteria listed below may not be changed or altered without prior written consent
from the Landlord.
1.
General:
1.1.
1.2. Bentall Towers 1, 2 and 3 were originally built using asbestos containing
materials (ACM) for the fire proofing. Every effort has been made over the
years to remove the asbestos, but some areas still contain ACM. Prior to
any construction work in tenant areas as well as base building mechanical
rooms and electrical closets, the tenant coordination department must be
contacted to determine if the area in question has been cleared. It is the
responsibility of the contractor and the tenant to inform all workers of the
potential risk. It is also the responsibility of the contractor and tenant to
ensure a hazardous material survey of all potential materials in their space
has been conducted prior to the start of construction as per Worksafe
regulations.
2.
The office towers are classified as Group D and conform to the Group
D classification. Any changes to that classification will be at the
Tenants expense.
2.2.
Building standard materials and finishes may not be altered without the
written consent of the Landlord. If changes to the base building are
permitted, the Tenant must provide a letter indicating their undertaking to
reinstate the demised premises to the base building standard at lease
termination.
Design Criteria
Page 3.1
3.
Demising Walls:
3.1.
4.
Safety:
4.1. The following have been designated emergency crossover floors:
Note: Floor number 13 is not used in the Bentall Centre.
Tower One:
Tower Two:
Note: 4 floor PBSC has installed crash bars and doors do not lock.
Note: 4 floor has cross over signage but is not listed as such on other doors.
Tower Four:
On these floors, the exit stairwell doors cannot be locked at any time.
(See Base Building Standards - Security.)
4.2.
5.
In the event of a fire alarm, all electronically secured doors must release.
All installations must conform to the current local bylaws and codes and
must be approved by the City of Vancouver building inspection
department.
Electrical:
5.1.
All electrical loads shall be metered at the Landlords discretion and all
installation and material costs will be at the expense of the Tenant.
5.2.
5.3.
All electrical work shall be as per the current Canadian Electrical Code
C22.1-Part 1.
5.4.
Power and tel/data wiring shall be routed through interior partitions and all
feeds shall be through ceiling spaces or through the floor slab. All wiring
Design Criteria
Page 3.2
All junction boxes are to be marked with an indelible marker, indicating the
voltage of the wiring outside the junction box, panel identification and
breaker number of the wiring in each junction box.
5.6.
All electrical and communication wiring that penetrates a fire rated wall,
floor or slab must be treated with the appropriate fire seal and fire
stopping must be replaced, if necessary, according to V.B.B.L.
3.1.7.1.(2). If a construction or renovation project is left with the fire
stopping damaged or without a proper fire seal, the Tenant and the
Tenants contractor will be held accountable.
5.7.
5.8.
Landlord will provide the main electrical light switches to each area that
is connected to the Building Management System. All areas in the
Tenants space will require switches to control the lighting. These
switches are for service work on the fixtures and to conserve energy. All
lighting must be designed so the fixture and any component can be
serviced easily.
If the components can not be serviced easily, a
surcharge for maintenance may be added.
5.9.
Tower One has 60 breakers per floor; Towers Two, Three and Four have
84 breakers per floor. The breakers shall be allocated to serve the ratio
of floor area. All plug outlets must be marked on the cover plate with the
breaker number that serves that outlet.
5.9.1. The Landlords Consultant will design all lighting plans, types of fixtures
and switch locations and is responsible to confirm that they meet the
building standards. The cost of this service is the Tenants expense.
The Landlord must approve all electrical plans before any work can
proceed. All electrical panels must be clearly marked. All wiring to the
lighting and power supply must be a minimum of A.W.G. #12.
5.10. All exit lights that are installed must be EMERGI-LITE C8EX50 Series or
equivalent (LED, long life being the critical component).
Design Criteria
Page 3.3
5.
Electrical: continued
6.
7.
Communications:
6.1.
6.2.
6.3.
6.4.
Energy Conservation:
Every effort must be made by designers to reduce the energy consumption by
using:
7.1.
7.2.
7.3.
7.4
Design Criteria
Page 3.4
8.
Integral Work:
8.1.
Integral work is work that alters the structure or services for which the
Landlord is responsible. In order to prevent the voiding of maintenance
and construction guarantees, integral work required on behalf of the
Tenant will be executed by the Landlord at the Tenant's expense.
8.2.
9.
Mechanical:
9.1
10.
The existing systems are relatively flexible, i.e. plumbing fixtures can be
accommodated outside of the core; packaged air conditioners, additional
thermostatic controls and minor exhaust systems can usually be added at
the Tenant's expense.
HVAC:
10.1
The building air conditioning system is designed for 150 square foot per
person. This ratio can be exceeded but during peak loads the space
temperature will be higher than the building design temperature.
WorkSafe BC accepts the ASHRAE Standard 62-1998, which is 20 to 26
degrees Celsius.
10.2
The base building system is an induction unit system that supplies warm
and cold air in the perimeter offices, in all buildings. The interior air supply
system has induction mixing boxes for Towers One and Two, a constant
volume with reheat for Tower Three and a variable air volume in Tower 4.
The concourse areas have terminal reheat systems.
10.3
The normal operating hours are Monday to Friday from 6:00 a.m. to 6:00
p.m. and Saturday from 8:00 a.m. to 1:00 p.m.
Design Criteria
Page 3.5
11.
10.4
When the air conditioning is not operating, the building system will
maintain a non-occupied temperature of 19 degrees Celsius during the
winter and 28 degrees Celsius during the summer. This is to prevent the
building overcooling or overheating.
10.5
All new and renovated air conditioning systems must be balanced or rebalanced to the new load requirements by one of the preferred system
balancing contractors, prior to the tenant move in (See Consultants &
Preferred Contractors, Subcontractors, Systems Balancing). The final
report will be sent to the Landlords Consultant, who will verify the report to
the design criterion and will keep a copy on file. Upon final approval,
within 7 calendar days, the Landlords Consultant will provide a duplicate
copy to the Landlord. The air conditioning systems design and operating
features must follow the WorkSafe BC rule Indoor Air Quality. 4.70 to
4.77.
10.6
11.2
The Mechanical Contractor that installs auxiliary air conditioning will also
install any controls.
11.3
All Tenants are responsible to maintain their own auxiliary air conditioning
units and service contracts.
11.4
11.5
Design Criteria
Page 3.6
12.
unit capacity
location
Service Contractor
11.6
All auxiliary air conditioners that are not metered through the Tenants
meter will be charged at a per ton per year rate for all office applications
and all 24 hour application. This cost will be automatically included in the
monthly fixed rental amounts (cost is subject to change upon written
notice). The utility cost will be the same as the buildings utility cost. For
more information on the current rates per ton per year please contact the
Operations Assistant at 778-328-5967.
11.7
Structural:
12.1
12.2
Certain percentages and locations of floor areas are available for coring
and outlets should be planned in these areas and their locations
coordinated with the Tenant Coordination team.
12.3
12.4
12.5
Heavy point loads such as safes, piston reaction from service elevators,
etc. should be located near column locations, girders or beams near their
support (i.e. columns, shear wall, or cores).
Design Criteria
Page 3.7
13.
12.6
Heavy distributed loads such as rolling files (typical loads are between
150 and 200 lbs psf) should be located as close as possible to the
elevator shaft/core walls. Aisle-ways should be located as close as
possible to these areas to reduce the average loading in this area.
12.7
Typical floor slabs use waffle slab and/or joist construction (Tower Four is
the exception, being constructed with girders and beams supporting a one
way slab). This type of construction can tolerate holes being cut in the
slab or even significant sections of the slab being removed entirely with
minimal effect on its structural integrity. As a guideline, any holes should
be located between the joists or tees of the waffle slab or in the slab
sections of the floor framing. Cutting into the joists, tees, beams or
girders should be avoided as this will most likely require the area to be
reinforced.
Plumbing:
13.1
Drain and vent connections are available at service core walls in each
ceiling space for connection of the Tenants in-suite plumbing.
13.2
Hot and cold water supplies for domestic use are located adjacent to the
core in the ceiling space of each floor.
13.3
13.4
13.5
All supply and return piping connecting any air conditioning unit must be
certified L hard copper, the condensate pipe can be D.W.V. copper.
13.6
13.7
13.8
All piping over two inches shall be cast iron schedule 40.
13.9
13.10 Contractor to inform Consultant 24 hours prior to initial Pressure Test, and
confirm type of test and pressure being applied.
Revised: July 2015
Design Criteria
Page 3.8
Step 1: Contractor to set up a time and date for the Consultant to witness
the test at the beginning of the test as well as the end of the test. A
hydrostatic test is mandatory. Continue test for 24 hours. Apply pressure
at a minimum of 1.5 times of the maximum operating pressure or 150 Psi,
whichever is greater. Contractor to use the pressure gauge from Bentall
Engineering staff that has the capability of recording the pressure reading
chronologically over the pressure test period. A low pressure air test is to
be completed prior to hydraulic test for any minor flaws in the system prior
to hydraulic test. Complete log data is to be signed by the testing
contractor and submitted to the Consultant & Building Manager prior to
substantial completion review. Include data print outs in the final
documentation in the operation and maintenance manuals.
Step 2: If pressure reduction is identified at any time, remove the test,
identify the leakage, drain the system, and repair the pipe/fitting. Retest
the system starting from step 1. Do not remove test until instruction
received by the consultant.
14.
Curtain Wall:
14.1
15.
Material Selection:
15.1
15.2
Design Criteria
Page 3.9
16.
15.3
All contractors working within the Bentall Centre are strongly encouraged
to recycle construction materials. See Section 9 of Rules and Regulations
page 5.6.
15.4
From time to time used products and materials from other construction
jobs within the Bentall Centre become available, i.e. doors, furniture etc.
When possible, and if not used immediately, they are stored for future
use. Contractors are encouraged to contact the Tenant Coordination
team to find out if there are any used materials available for use in their
construction project.
Design Criteria
Page 3.10
Ceilings:
1.1.
1.2.
Ceiling heights are 8 8 +/- throughout except for lobby areas, which are
8 4 or more.
1.3.
Designers should limit the use of solid ceilings due to the following:
1.4
1.3.1.
1.3.2.
1.3.3.
2. Doors:
2.1
Page 4.1
2.
Doors: continued
2.1.2.
NOTE:
3.
Lighting:
3.1
Page 4.2
3.
Lighting: continued
3.2
Power for lighting is 277 volts in Towers One and Two, and 347 volts in
Towers Three and Four. The standard fixture alignment is in a northsouth direction for Towers One, Two and Four and shall not be altered.
Tower Three alignment is in an east-west direction and shall not be
altered without the Landlords written permission.
3.3
All lighting must comply with the WorkSafe BC recommended light levels:
3.3.1.
3.3.2.
3.3.3.
3.4
The following is the base building standard for ballasts in all Towers:
3.5.1
3.5.2
4.
50 fc
35 fc
35 fc
The following is the base building standard for lamps in all Towers:
3.4.1
3.5
3.6
3.7
3.8
If required by the Landlord, the Tenant shall install its own separate check
meter / revenue capable meter for the Leased Premieses at its own
expense and in a location designated by the Landlord.
24 High
24 High
25 High
25 High
Page 4.3
4.
5.
4.2.
4.3.
Important note: All furniture must be at least 8 inches away from the
perimeter induction unit so it can operate properly and for servicing.
Heavy furniture and built-in furniture must be at least 18 inches away
from the induction units and if the furniture covers more than two induction
units an accessible panel will be required for servicing the units.
4.4.
The Janitorial Contractor cleans the induction units once per year. If the
contractor can not obtain access to the unit(s), the Tenant will be required
to move the furniture prior to cleaning. The Janitorial Contractor will
inform the Tenant when the units are about to be cleaned. All costs for
the relocation of furniture are the sole cost of the Tenant.
Interior Walls:
5.1.
6.
7.
7.
Fire Protection:
7.1
7.2
In the event that the City of Vancouver requests that valve cabinets be
relocated or additional cabinets be supplied to accommodate the Tenants
design, such changes would be designed, constructed and supervised by
the Landlord or its agents and charged to the Tenant. Two fire or valve
cabinets or valve stations are provided on each floor of Towers One, Two
and Three. As floors are upgraded, the fire hose cabinet will be removed
and replaced with a valve station cabinet.
7.3.
Page 4.4
7.4.
7.5.
7.6.
8. Sprinklers:
8.1.
8.2.
8.3.
When part of the sprinkler system has been taken out of commission for
renovation work or repairs, 72 hours notice (three business days) is
required, except for emergencies. All sprinkler impairments must be done
between the hours of 6:30AM - 10:30PM (Monday Friday) or from
8:00AM 3:00PM on weekends. It is mandatory that the sprinkler
contractor be present for the sprinkler re-fill which can only be done after
6:00PM on weekdays. On weekends, the re-fill must be completed by
4:00PM. (For example, if you request the sprinkler impairment to be done
from 8AM noon, you must come back to the site at 6:00PM for the refill).
8.4
All sprinklers must be operational at all times unless they are being
maintained or work is being performed on them. If at any time there is
part of a system, or all of the system, that can not be put into normal
operation a fire watch must be put into effect. The appropriate fire watch
8. Sprinklers: continued
Page 4.5
will be at least one person per floor and four persons per building on patrol and in
contact with the Fire Department.
8.5
9.
10.
Public Corridors:
9.1.
All public corridor demising walls must be extended to the underside of the
slab by a single sheet of gyproc, and the joints must be fire and smoke
rated (See Attachment 3). If there is a return air damper or a supply air
mixing box above the corridor, the transition must be fire rated and be
accessible for maintenance purposes refer to V.B.B.L. 3.3.1.3. (1). The
Landlords Consultant will ensure this feature. Note: A public corridor
means a corridor that provides access to an exit from more than one suite.
9.2.
9.3.
In the event of tying into existing flooring, floor must be levelled to match.
Landlord to be advised prior to commencement.
Elevator Lobbies:
10.1. The ceiling on a multi-tenanted floor is a barrel type gypsum board.
10.2. The wall covering is building standard vinyl on 1/2" gypsum board.
10.3. The flooring in the lobby is either a porcelain or marble border and base,
with a carpet inlay.
10.4. The elevator lobby on a single-tenanted floor can be designed to Tenant's
specifications, subject to approval of the Landlord.
10.5. Access panels are required in all hard ceilings. Location and details to be
determined onsite with Landlord prior to installation (i.e junction boxes,
lighting ballasts, shut-off valves). Final review required by Landlord upon
completion.
Page 4.6
11.
Security:
11.1. The entire Bentall Centre goes into lockdown from 6:00 p.m. to 6:30 a.m.,
Monday to Friday and 24 hours on weekends and holidays. During
lockdown, security clearance is required to move around the Bentall
Centre from floor to floor. This is obtained by contacting Bentall Centre
Security at 778-328-5990 (See Rules & Regulations, Security for more
information). As another measure of security the stairwell doors are also
locked down, excluding crossover floors. Any full floor Tenant must be
aware that stairwell entrances are locked and can be keyed to the master.
11.2. Contractors are required to sign out a contractor identification badge from
the Bentall Centre Security Desk. The foreman may sign out more than
one badge for their staff. It is mandatory for the badge to be worn by all
staff, and be visible at all times while on site.
11.3. Tenant security issues can be addressed with our Security, Fire & Life
Safety Manager at 778-328-5964.
12.
13.
14.
(s.f.)
(m)
(s.f.)
(m)
Tower One
12,200
1,133
11,090
1,030
Tower Two
9,900
920
9,000
836
Tower Three
15,400
1,431
14,130
1,313
Tower Four
16,700
1,551
15,030
1,396
Tower Two:
Tower Three:
Tower Four:
Drapery:
Page 4.7
14.1. All exterior window drapery backing must be black in colour, and approval
is required from the Tenant Coordination team prior to installation. No
track is provided although a track may be installed directly to the
underside of the metal T-Bar and fastened through the ceiling tile to
suitable blocking above. Venetian blinds must not be removed during
construction, but must be covered. Blocking, if required, must not be
combustible, i.e. wood. (If removal is required for construction purposes,
this must be done by only the Landlord contact Tenant Coordination
team for details.)
14.2. Contact Landlord prior to construction, to determine if they will be removed
from site by Landlord.
14.3. If any blinds are installed other base building standard, Landlord will
require them to be removed at Tenants cost.
14.4. The standard blind supplied by the Landlord is:
1 Perforated Matte Black Horizontal
14.5. The following alternative is also available at Tenant cost:
1 Solid Matte Black Horizontal
15.
Page 4.8
16.
16.2
To clean the induction units, the cleaning contractor must adhere to the
following procedures:
16.1.1.
16.1.2.
16.1.3.
16.1.4.
16.1.5.
16.1.6.
16.1.7.
16.1.8.
16.1.9.
17.
Page 4.9
1.
WorkSafeBC:
1.1
2.
Noise:
2.1.
2.2.
The Tenant's contractor shall not use ramset, Hilti, Kangyo or other
explosive percussion or vibrating tools during normal business hours.
2.3.
Welding and painting equipment will not be used during normal business
hours. When such equipment is used, an isolation pad must be placed to
buffer the noise. Prior to ANY hot work commencing, a Hot Work
Permit must be obtained from the Bentall IV Security desk.
2.4.
2.5.
Page 5.1
3.
4.
Odours:
3.1.
Due to odours that the following materials produce, they can not be
applied during normal business hours (Monday to Friday. 6:00 a.m. to
6:00 p.m.) due to WorkSafeBC requirements: lacquers, oil based paint,
enamel paints, lacquer based contact cement, carpet glues, sealers,
burning equipment, gas welders, or anything that may produce noxious
fumes. If there are any questions with regard to product(s) to be used,
contact the Tenant Coordination team.
3.2.
Insurance:
4.1.
4.2.
4.3.
4.4.
Page 5.2
5.
6.
Deliveries:
5.1
5.2
5.3.
At all times, only the freight elevators may be used for the transportation
of construction personnel and the movement of tools and materials.
5.4.
Some form of protection must be installed from the freight elevator to the
suite door during all construction deliveries on multi-tenanted floors.
5.5.
Important Note: Gypsum board and other heavy items may only be
stacked 24" inches high and only across beam lines and near core walls
or columns.
Security:
6.1
6.2
Once the contractor and trades have provided proper security information,
they can be supplied building access cards that will allow them access to
the designated area of construction. It is mandatory that identification be
supplied before access cards are granted. These cards are cancelled
once the job has been completed, and there will be an administrative
charge for unreturned cards billed to the Tenant. For further information
on this charge, please contact the Construction & Projects Coordinator at
778-328-5962.
Page 5.3
7.
8.
9.
Curtain Wall:
8.1
8.2
Housekeeping:
9.1
The Tenant's contractor shall keep premises clean and remove garbage
daily. They must arrange with Housekeeping for locating and storing of
large refuse containers which must be located after 6:00 p.m. and
removed by 6:00 a.m. the following morning. Bins are not available
from the Landlord. No construction material is to be deposited into the
Bentall Centre compactors.
9.2
9.3
Page 5.4
10.
10.2
11.
Administration:
11.1. At least five days prior to the commencement of any work, the Tenant
Coordination team must be advised of the time and date of
commencement, contractors name and phone number, contact names
and phone numbers (including emergency number) and similar
information for the architect/designer responsible for the project. Please
contact Construction & Projects Coordinator for mandatory preconstruction paperwork required (see Attachment 7).
11.2. It is strictly forbidden for contractors, sub-contractors and their
tradespeople to ask tenants for the use of a telephone unless it is an
emergency safety issue (i.e. fire, injury, smoke fumes, etc.).
11.3. The Tenant's contractor shall confine operations to the Leased area and
arrange for the security of the Tenant's Leased area and equipment,
materials, etc. during the construction period.
11.4. The Tenants contractor will be responsible for any disruption to an
existing tenant in the form of power outages or computer failure caused by
power outages if caused by their contractors negligence.
Page 5.5
11.5. The Tenants contractor will not use the washrooms on multi-tenanted
floors for construction purposes, such as cleaning paintbrushes or
emptying buckets.
12.
On-Site Supervision:
12.1. All construction projects within the Bentall Centre that are over 4,000
square feet will require the general contractor to be on-site full time for the
duration of the project. That failing, a superintendent/foreman must be
appointed and on-site at all times to be responsible for all subtrades.
13.
Theft:
13.1. During the construction process the landlord will not be responsible, under
any circumstances, for any loss or damage to the Tenants materials,
fixtures or equipment, whether due to Tenants failure to properly secure
the premises or for any other reason whatsoever. Also, the Landlord will
not be responsible for any supplies and/or equipment belonging to the
contractor left on site at any time.
14.
Smoking:
14.1
Page 5.6
ATTACHMENT 1
Attachment 1
Page 6.1
Attachment 1
Page 6.2
Attachment 1
Page 6.2
Attachment 1
Page 6.3
Attachment 1
Page 6.4
Attachment 1
Page 6.5
Attachment 1
Page 6.6
Attachment 1
Page 6.7
Attachment 1
Page 6.8
Attachment 1
Page 6.9
Attachment 1
Page 6.10
Attachment 1
Page 6.11
Attachment 1
Page 6.12
Attachment 1
Page 6.13
ATTACHMENT 2
Attachment 2
Page 7.1
Attachment 2
Page 7.1
ATTACHMENT 3
Attachment 3
Page 8.1
Attachment 3
Page 8.2
Attachment 3
Page 8.3
Attachment 3
Page 8.4
Attachment 3
Page 8.5
Attachment 3
Page 8.6
Attachment 3
Page 8.7
Attachment 3
Page 8.8
Attachment 3
Page 8.9
Attachment 3
Page 8.10
Attachment 3
Page 8.11
Attachment 3
Page 8.12
ATTACHMENT 4
PROCEDURES FOR SPRINKLER WORK AND NOTIFICATION OF IMPAIRMENTS
Request Authorization and Scheduling
The information listed below is to be provided to the Construction & Projects Coordinator by email
(brosenlund@canderel.com). In Billys absence, Darcie Breen will be taking care of all impairment
notifications. All requests for impairments should be copied to her at dbreen@canderel.com.
Alternatively, requests can be sent by fax to 778-328-5989.
IMPAIRMENT
Name of Contractor:
On-site Contact Name:
On-site Contact Phone:
Location of Impairment (include Suite & Street address):
Reason for Impairment:
Project it Relates to:
Fire Alarm By-pass Required: Yes or No
Dates of Shutdowns: see Important Notes below
Time of Shutdown (start & finish): see Important Notes below
Estimated time system will come back on line: (1 hour after done work)
Comments:
IMPORTANT NOTES:
Above information must be provided at least 3 business days prior to the impairment taking place
and a separate request provided for each date of shutdown. All sprinkler impairments must be
done between the hours of 6:30AM - 10:30PM (Monday Friday) or from 8:00AM 3:00PM on
weekends. It is mandatory that the sprinkler contractor be present for the sprinkler re-fill which can
only be done after 6:00PM on weekdays (for example, if you request the sprinkler impairment to be
done from 8AM noon, you must come back to the site at 6:00PM for the refill). On weekends, the
re-fill must be completed by 4:00PM. In the case of an emergency the information should be
provided as soon as possible. If soldering, disc cutting, welding etc. is to take place a Hot Work
Permit must be obtained from the Bentall Centre Security Desk.
Note: Do not consider the scheduling of a sprinkler shutdown as a work authorization. The Contractor must
have a Work Authorization Form filed with Security or they must be listed on an approved trade list relating to
the particular project. Keys/passes must be registered and picked up from Security. They must be returned
before leaving the complex.
Attachment 4
Page 9.1
Contractors must report to the Bentall Centre Security Desk (Tower IV) to confirm the
schedule, depending on where the work is to occur. Note: Hot work not permitted if a
sprinkler impairment is in same area.
2.
Prior to commencement of work the contractor must ask Security to turn off the
devices pertaining to the nature of the work, i.e. flow tamper, smoke detector if
welding, soldering, disc cutting, grinding is to take place.
3.
4.
Any contractor who has questions/concerns should address them to the Bentall
Centre Security Desk (Tower IV).
Completion of Job, System Refill and Restoring of the Fire Prevention System
1.
Bentall Centre Security shall ensure that Chubb Security is off line.
3.
Bentall Centre Security shall inform the Engineers of the intent of contractors to fill the
system.
4.
Contractors shall be instructed to wait in an appropriate area of the complex until they
get acknowledgment from the Engineer and approval to refill.
5.
The Engineer will then switch off the fire pump and put the building into a by-pass
mode to make sure the fire prevention system is in secure mode but will still remain
active.
6.
The Engineer will then personally advise the contractor that they have approval to
commence filling up the system in a moderate pressure fill up. They are to instruct the
contractor to check the job for leaks etc.
7.
After fill up is complete, contractors shall personally inform Bentall Centre Security
when they have completed the fill and checked for leaks.
8.
Security shall then inform the Engineer that the system is full.
9.
The Engineer will then check that the fire prevention system (as relates to pressure)
gauges etc. are normal and switch on the fire pump.
10.
The Engineer will then inform Bentall Centre Security to put devices back on-line and
then inform Chubb to return to on-line protection again.
Attachment 4
Page 9.2
A floor sprinkler system can be refilled from a stand pipe or riser, but an Engineer
must be called one hour prior, via Bentall Centre Security, to switch off the fire pump.
Note:
The fire pump has to be put back on by 22:30 hrs at the latest.
No Engineer is obliged to stay passed 23:00 hrs. If they are required to stay past
this time an overtime charge will be invoiced to the Contractor creating the
situation.
2.
No attempt shall be made to refill the system using the standpipe/main riser without
the fire pump switched off. Highly sensitive devices can trigger the main fire pump to
start thus creating an alarm condition.
2.
After the system is drained, if not already existing, a low point/refill access must be
installed preferably in or near the janitor closet, with a ball valve and a cap/plug to be
screwed in after job completion.
3.
A back fill pump kit must be used. A Back flow preventer and two (2) check valves
must be part of the refill line. This is because the domestic cold water of the building
is being used to refill. A reference pressure gauge must also be on line to confirm that
the water pressure pumped into the sprinkler system does not exceed the reference
pressure at the floor where refill is taking place. System pressure has to be known or
determined before the refill operation.
4.
Attachment 4
Page 9.3
CONTACT SECURITY PRIOR to commencing sprinkler work or any other work that may
create dust, smoke or fumes at 778-328-5990.
FAMILIARIZE YOURSELF with the locations of pull stations, fire phones, sprinkler valves and
fire extinguishers.
IF YOU KNOCK OFF A SPRINKLER HEAD, close the isolation valve immediately. Isolation
valves are in the stairwells in the towers and in various locations on penthouse, mall, and
parkade levels.
EMERGENCY STAIRWELL DOORS must remain closed at all times. The stairwell is not to
be used to improve air circulation to your work area; propping these doors open is a serious
violation of the fire code.
SPRINKLER WORK:
*
Fire hoses must be supplied by sprinkler fitter, laid out and connected to valve station.
If you are moving a hose cabinet, arrangements must be made in advance with
building management for a separate security patrol of unprotected areas.
FIRE ALARM (FAST BELL): If you hear this bell, evacuate down the closest safest stairwell
and exit the building unless otherwise instructed.
IF YOU DISCOVER OR START A FIRE, activate a red fire alarm pull station immediately.
Close doors around the fire to prevent it from spreading. Use a fire phone to give details to
building emergency response personnel. If the fire is small, extinguish it with an extinguisher.
If you are using a torch or other equipment that could start a fire, you must have your own fire
extinguisher with you. The building provides two extinguishers on each floor in the towers
and at the bottom of the red and blue stairwells at the mall or lobby level.
Attachment 4
Page 9.4
Attachment 4
Page 9.5
Attachment 4
Page 9.6
Attachment 4
Page 9.7
Attachment 4
Page 9.8
Attachment 4
Page 9.9
Attachment 4
Page 9.10
ATTACHMENT 5
BENTALL CENTRE
HOT WORK PROCEDURES
Policy
Cutting, grinding, welding, soldering, thawing pipe, torch applied roofing all are examples of
hot work, any operation that involves open flames or produces heat and/or sparks. Any hot
work operation introduces potential uncontrolled ignition sources into the facility, whether the
work is being done by our employees or by an independent contractor. Every hot work
operation must be weighed carefully for need and risk. Bentall has instituted a Hot Work
Permit Policy to ensure that any hot work done at the facility will be conducted in the safest
manner possible. Prior to any work being done, a Hot Work Permit in the form attached
must be obtained from the Bentall Centre Security Desk (Tower IV). Hot Work is permitted
24/7. The only restriction is that Hot Work can not coincide with a sprinkler impairment in the
same area.
Procedures
1.
Contractors are to report to the Bentall Centre Security Desk when arriving on site,
in accordance with existing procedures for contractor access.
2.
When signing in, the Contractor is to advise Bentall Centre Security Desk if they
are carrying out hot work.
3.
Security is to confirm that a work authorization exists for the particular Contractor,
relating to the space they will be working in.
4.
The Contractor is to fill out Part 1 of the new Hot Work Permit, including the
precautions checklist. It is the responsibility of the Contractor doing the work to
ensure that all necessary precautions have been taken. The Contractor and
Security are to then sign Part 1 of the form and Security should record the time
Attachment 5
Page 10.1
that the permit expires on that particular day. Note: A new form will be required for
each day the Contractor is doing hot work. The permit expiry date should be the same as
the date it is completed.
5.
Security is to ensure that the Contractor has a fire extinguisher of suitable class in
case of a fire. If not, then the Contractor is to borrow one from the Bentall Centre
Security Desk and return it at completion of the work. Due to the limited number of
extinguishers available it is preferable that each Contractor has an extinguisher of
their own.
6.
Security is to remove Page 1 of the Hot Work Permit and keep it at the Bentall IV
Security desk. Part 1A of the Permit is to be given to the Contractor for their
record. Part 2 of the Permit is to be given to the Contractor to display on site.
7.
The Contractor is to record the time hot work began on Part 2 of the Permit.
8.
The Contractor is to hang Part 2 of the permit on the fire phone located on the
particular floor where the work is being carried out.
9.
At completion of hot work the Contractor is to record the time the work was
finished on Part 2 of the Permit and they are to sign the Fire Watch Signoff
section of Part 2. This shall be left posted at the site for Securitys final checkup.
10.
The Contractor shall then report to security and advise them that hot work is
finished.
11.
Three hours after work is completed, Security shall reinspect the site and collect
Part 2 of the Permit.
12.
The Final Checkup section of Part 2 should be signed off by Security to confirm
that the site was found fire safe.
13.
Security shall attach Part 1 of the permit to Part 2 and forward both parts to the
Bentall Centre Security Desk for filing.
Attachment 5
Page 10.2
Safety Precautions
Attachment 5
Page 10.3
Attachment 5
Page 10.4
Attachment 5
Page 10.5
ATTACHMENT 6
BENTALL CENTRE
MECHANICAL SYSTEM COMMISSIONING AND MINOR RETROFIT
Scope of Work
The commissioning contractor will provide all labour and supervision for inspection and
testing to ensure that the new and/or existing mechanical systems and equipment and
their associated temperature controls perform effectively and efficiently, in accordance
with the Engineers drawings and specifications.
There are two scenarios that the scope of this work entails;
1) Where the building owners are undertaking demolition of a space vacated by a
tenant and returning the space back to base building specifications. This will require
the commissioning contractor to bring base building equipment up to spec prior to
tenant improvements beginning once the space has been re leased.
2) Where a new tenant is undertaking improvements prior to occupying the space.This
requires the commissioning contractor to coordinate the start-up, putting into
service, and performance testing of all new systems and equipment. The
commissioning contractor will conduct inspections and performance tests required
for all new, modified or reused mechanical components, systems and controls to
determine their operating condition.
Based on the test results for all the systems and equipment, the commissioning
contractor will identify performance deficiencies and recommended corrective actions
and where authorized to proceed shall arrange for and carry out the corrective action in
the following categories:
a) Contract Deficiencies: List all items that are the responsibility of the installing
mechanical trades that are incomplete or deficient.
b) Performance Deficiencies: For the area that is being renovated, identifying and
listing all performance deficiencies for the overall mechanical systems, including
reused existing equipment.
c) Recommended Actions: For each of the contract deficiencies, determine the trade
or company responsible for taking corrective action to complete the contract
obligations. For each item that is not part of the contract work, recommend the
corrective action required and identify a rough cost estimate to carry out remedial
action.
d) Remedial Work: As the corrective actions are identifiedfollowing inspections and
performance tests, a report is to be submitted to Bentall Centre listing these items,
recommendations and estimate of costs. Once any item, or items have been agreed
to by Bentall Centre Management, schedule and carry out the recommended
actions as soon as possible.
Attachment 6
Page 11.1
A)
B)
Total Air Delivery to Occupied Spaces: Adequate air delivery is required to all
occupied areas to provide the required free cooling using mixed air at 55 F (13
C) when available. For office spaces is the CFM per sq ft for all areas in a
normal range, e.g. 0.65 to 1.0 CFM per sq ft interior, 1.0 to
1.25 for north exposure, 1.25 to 1.6 for east exposure, 1.5 to 2.25 for south and
west exposures. All occupied areas should be provided with air supply and air
distribution should be even. Air supply temperature should never be less than a
minimum of 13 C (55 F) to avoid cold drafts.
C)
D)
E)
Major Equipment Capacity: The major equipment must have adequate total
capacity to deliver at least the sum of all the individual capacities, e.g. a boiler or
chiller must have enough heating or cooling capacity to meet the maximum
demand when all sub systems are calling for cooling. For some systems, e.g.
Variable Air Volume) there is a diversity allowance, i.e. a dependence on the
probability that not all zones will be calling for heating or cooling at the same time.
Attachment 6
Page 11.2
F)
Outdoor Air Intakes: O/A Intakes must have adequate area so that there are no
air noise problems or excessive static pressure problems when the fan system
operates on (worst case) 100% outdoor air. O/A intakes should be sized for about
500 FPM based on the NET free area. For most louvers, the net free area is only
about 50% of the gross area. Exhaust air louvers may be higher, e.g. 800 FPM.
G)
H)
I)
J)
Relative Humidity Requirements: For most typical office areas the relative
humidity may vary between a minimum of 20% to 60% R.H. with few complaints.
The ideal R.H. for people is 50% R.H. In special cases, where there is special
computer equipment, the relative humidity requirements are governed by the
requirements of the special contents in one or more areas of the building. In such
cases, it is usually only necessary to provide special humidification or
dehumidification for the special rooms.
K)
Energy Issues: All buildings should have normal energy measures included. For
example, shutdown of fans during unoccupied periods, night setback for
temperatures, no cooling during unoccupied times, limit heating to 21 deg C and
cooling to about 23 deg C; avoid simultaneous heating and cooling, limit outdoor
air to zero when building is unoccupied and to minimum during cold weather
conditions.
L)
Access For Servicing Equipment: Adequate service space around and to all
equipment components is required so that it is likely to be serviced and so that
when it needs to be repaired or replaced it may be done without using
extraordinary means.
Attachment 6
Page 11.3
M) Return Air Issues: There must be a clear path for the return air to be able to
return to a fan system through ceiling spaces, transfer grilles, return air grilles etc.
N)
Building Pressure: Buildings with mechanical cooling should in most cases have
a slight positive pressure, e.g. 0.1 (25 Pa) during all operating conditions with all
exhaust fans operating. Areas that have odours should be under a negative
pressure.
Temperature Control
The commissioning contractor is to itemize the temperature control system sequences
of operation for all the new and existing mechanical systems that serve the tenant area
that is being modified. The commissioning contractor is to conduct checks of the
control sequences to verify that they are performing as per the design intent and in the
best interests of the Owner and occupants regarding comfort and energy utilization. If
there are significant performance deficiencies in the control sequences that are spot
checked, the commissioning contractor will recommend and conduct additional checks
(after authorization) until the control systems are all performing as intended.
If remedial actions are required the commissioning contractor shall make
recommendations for resolving the performance problems. If an engineering consultant
is required to make engineering design decisions, the commissioning contractor will
make arrangements to have the necessary work carried out once work is authorized by
Bentall Centre Management.
Scheduling of Commissioning
The commissioning contractor will schedule commissioning work to coincide with the
timing of the work performed by the mechanical trades. The commissioning contractor
will arrange for, coordinate, and chair as many commissioning meetings as required to
ensure that any issues related to the mechanical system commissioning can be
resolved in a timely manner.
Attachment 6
Page 11.4
Attachment 6
Page 11.5
demo will be to determine that all base building equipment operates as it should prior to
new tenant improvements commencing).
Thermostats are to be positioned in locations appropriate to the area served by their
respective boxes. Thermostats and sensors are not to be located where they will be
affected due to close proximity to devices that expel heat. That is for example, near
PCs, copiers, printers, etc. It is important that thermostats and sensors remain
accessible to tenants and building staff once the location of furniture in the suite is
complete. This may require the relocation of thermostat(s) after tenant has moved in to
allow access. All sensors/thermostats are to be mounted whereby their removal and
subsequent replacement over time does not degrade the integrity of their attachment.
Bentall and ESC Automation will have completed induction unit upgrades complete with
DDC programming. As such, the installation of any new thermostat and/or the
relocation of any existing thermostat must be done only by ESC Automation and then
approved by Bentall Centre Management. See below for contact information:
Tom Westendorf - Phone: 604-574-8403 Email: tomw@escautomation.com.
Shantel Thompson - Phone: 604-575-5921 Email:sthompson@escautomation.com
The General Contactor is expected to carry any and all costs by ESC Automation.
Over time, sensor hangers on many perimeter induction units throughout the Centre
have gone missing. The commissioning contractor will note where these are missing
and notify Bentall Centre Management as to the number required for each job.
BENTALL ONE
Interior Zone (Jetronic Induction Boxes)
- Inspect physical condition of the 4 Jetronic boxes (linkages, dampers, pneumatic
actuators, etc).
- Check operation of the 4 Jetronic boxes.
- Perform any minor adjustments and/or repairs to make systems operable.
Perimeter Zone (Induction Units)
- Inspect physical condition of the perimeter induction units.
- Check condition and operation of temperature controllers, thermostats, expansion
bulbs, and control valves.
- Check operation of internal balancing dampers.
- Inspect pneumatic lines for leaks and/or pinches.
- Perform minor repairs.
Attachment 6
Page 11.6
Balancing Scope
- Based on mechanical drawings specifications, balance the 4 Jetronic systems.
- Adjust the 2 static pressure controllers serving the 4 Jetronic boxes.
- Adjust outlet pressures of perimeter induction units to base building settings.
- Calibrate all thermostats.
BENTALL TWO
Interior Zone (Jetronic Induction Boxes)
- Inspect physical condition of the 4 Jetronic boxes (linkages, dampers, pneumatic
actuators, etc).
- Check operation of the 4 Jetronic boxes.
- Perform any minor adjustments and/or repairs to make systems operable.
Perimeter Zone (Induction Units)
- Inspect physical condition of the perimeter induction units.
- Check condition and operation of temperature controllers, thermostats, expansion
bulbs, and control valves.
- Check operation of internal balancing dampers.
- Inspect pneumatic lines for leaks and/or pinches.
- Perform minor repairs.
Balancing Scope
- Based on mechanical drawings specifications, balance the 4 Jetronic systems.
- Adjust the 2 static pressure controllers serving the 4 Jetronic boxes.
- Adjust outlet pressures of perimeter induction units to base building settings.
- Calibrate all thermostats.
BENTALL THREE
Interior Zone (Constant Volume Boxes)
- Inspect physical condition and ensure operation and adjustability of the 4 interior
boxes.
- Inspect thermostats.
Attachment 6
Page 11.7
Balancing Scope
- Based on mechanical drawings specifications, balance the 4 variable volume boxes.
- Adjust outlet pressures of perimeter induction units to base building settings.
- Calibrate all thermostats.
BENTALL FOUR
Interior Zone (VAV Boxes)
- Inspect physical condition and ensure operation and adjustability of the 6 interior
boxes.
- Check physical condition and operation of thermostats.
- Check physical condition of floor sensors where applicable.
- Perform minor repairs.
Perimeter Zone (Induction Units)
- Inspect physical condition of the perimeter induction units.
- Check condition and operation of temperature controllers, thermostats, expansion
bulbs, and control valves.
- Check operation of internal balancing dampers.
- Inspect pneumatic lines for leaks and/or pinches.
- Perform minor repairs.
Balancing Scope
- Based on mechanical drawings specifications, balance the 6 VAV boxes.
- Adjust outlet pressures of perimeter induction units to base building settings.
- Calibrate all thermostats.
Attachment 6
Page 11.8
Tower One
Tower Two
Tower Three
Tower Four
North
1.6
North
1.9
North
1.25
North
1.8
East
1.8
East
2.5
East
1.7
East
1.9
South
1.8
South
2.5
South
1.7
South
1.9
West
1.6
West
1.9
West
1.7
West
1.8
Corner
1.7
Corner 1.7
Corner
1.85
Corner 1.42
Attachment 6
Page 11.9
ATTACHMENT 7
INSURANCE CERTIFICATE REQUIREMENTS FOR BENTALL CENTRE
Please note that, according to our policy, your insurance certificate must include
the following details exactly as shown below:
In the "Description of Operations/Contract:" section, please add all of the following
Information (or alternatively you can describe the job location name and address):
CERTIFICATE HOLDER
Canderel Pacific Management Inc.
555 Burrard Street, Suite 1525
Box 226
Vancouver, BC V7X 1M9
INSURED
Your company name and Bentall Centre address including suite number.
Tower 1 505 Burrard Street
Tower 2 555 Burrard Street
Tower 3 595 Burrard Street
Tower 4 1055 Dunsmuir Street
Vancouver, BC
ADDITIONAL INSURED
For Towers 1 & 2:
Maple Red Financial Management Canada Inc., 9751254 Canada Inc. and Canderel Pacific Management
Inc
For Tower 3:
Maple Red Financial Management Canada Inc., 9751319 Canada Inc. and Canderel Pacific Management
Inc.
For Tower 4 and the ALRT:
Maple Red Financial Management Canada Inc., 9751327 Canada Inc. and Canderel Pacific Management
Inc.
COVERAGE REQUIRED
All risks Property insurance that includes coverage for earthquake and flood.
General Liability insurance in an amount no less than $5,000,000.00. (according to lease)
Boiler and Machinery (if you operate a boiler or pressure vessel)
Insurance certificates should be sent to:
Canderel Pacific Management Inc.
Suite 1525 555 Burrard Street, Box 226
Vancouver, B.C., V7X 1M9
PLEASE EMAIL CERTIFICATE DIRECTLY TO: brosenlund@canderel.com (hard copy in mail is
NOT required)
Revised: July 2015
Attachment 7
Page 12.1
Attachment 7
Page 12.2
Attachment 7
Page 12.3
REMINDER CHECKLIST
GENERAL CONTRACTOR RESPONSIBILITIES
General Contractor:
Tenant Name & Contact Person:
Tenant Address:
Please note that as the General Contractor for the above Bentall tenant, it is mandatory that the following
items be completed prior to the tenant moving in. Please check these items off, sign, and email below
documents to tenant Coordination Dept (brosenlund@canderel.com).
Mandatory Items Prior to Tenant Moving In
General Contractor is responsible to contact the Mechanical and Electrical Consultant 48 hours prior to installation of all
ceiling tiles, to arrange final inspection
Hand over ceiling air return plenum sensors to Bentall, when applicable
Copy of Occupancy Permit signed off by City Inspector (this often comes after move-in which is acceptable)
Copy of Final Building Permit signed off by City Inspector - send to Billy Rosenlund
Copy of Air Balance Report, to be done by KD Engineering or Western Mechanical send to Billy Rosenlund
Copy of Final Mechanical and Electrical Inspection Reports from Consultant send to Billy Rosenlund
General Contractor to provide Designer and Mechanical & Electrical Consultant with letter stating that all mechanical
and electrical deficiencies have been completed send to Billy Rosenlund
Designer/General Contractor to provide Bentall with electronic CAD copies of Architectural, Mechanical and Electrical
As-Builts send to Billy Rosenlund
General Contractors
Printed Name:
General Contractors
Signature:
Date:
Attachment 7
Page 12.4
Attachment 7
Page 12.5
Statement of Acknowledgement
I acknowledge that I have received and read the July 19, 2016 version of the Bentall Centre
Construction Manual and confirm that I will abide by the rules and regulations governed by the
Construction Guidelines.
(Print Name)
(Signature)
(Company Name)
(Date)
Attachment 7
Page 12.6
Bentall One
Bentall Two
Bentall Three
Bentall Four
Retail Mall
WORK TO BE PERFORMED (select only one box and provide detailed description of work below):
move furniture items in/out, furniture relocation
(See Notes at the bottom of the form)
repair & maintenance
major construction
cleaning
No (See notes section at the bottom for details about when a Security Officer is required.)
Yes
Please submit a separate Work Authorization Form for each contractor requiring access.
CONTRACTOR
COMPANY:
OFFICE PHONE:
one form per contractor
ON-SITE
ON-SITE CONTACT
EMPLOYEES:
PHONE NUMBER:
DATE ACCESS
REQUIRED:
START TIME:
24 hours notice required
COMPLETION
DATE:
END TIME:
Notes:
1.
Furniture moves and large deliveries can only be done before 06:00AM or after 6:00PM, Monday through Friday or 24 hours on weekends.
2.
Freight elevators must be booked 24 hours in advance for deliveries or moves; please contact the Bentall Security Control Centre at 778-328-5990.
3.
Elevators can only be booked before 06:00AM or after 6:00PM, Monday through Friday or 24 hours on weekends. Construction materials to be delivered no
later than 6:30AM.
4.
Deliveries (from 6:00PM-6:00AM) through the loading dock will require a Security Officer to be hired to patrol the loading dock area. Security
Officers must be booked 24 hours in advance by contacting the Security Director on 778-328-5973 (rates vary depending on notice given).
Office Use:
1
2
VERIFIED BY BENTALL CENTRE SECURITY SHIFT SUPERVISOR: _______ WORK ORDER #: _____________________
ASSIGNED TO:
_____________________
LS/NS
MG/MM
AB/BL
Attachment 7
TENANT
Page 12.7
INFO
ATTACHMENT 8
Attachment 7
Page 12.8
Riser rooms:
As room is very limited, it would be rare for the Riser Manager to allow any equipment, junction or breakout boxes etc. to be installed in the riser rooms. Instead these should be located either in the Service
Providers or Tenants leased space. Approved firestopping must be installed in all penetrations and all
cables and conduits must be labelled on each floor.
Labelling:
All new cables being installed shall be labelled in one of the following ways:
1) if a riser cable (passing between floors) the label shall be fastened between 5 and 6 feet above
the floor so it is clearly visible.
2) if a horizontal cable (between the riser room and a tenant space) the label shall be fastened close
to the termination block, cabinet or panel and at both ends, every 30 linear feet.
All labels shall be created electronically (ie: Brother label or similar) and indicate the following:
1) Service Provider
2) source & destination location
3) cable number
Example:
Service
Provider
Bentall
Tower #
Source
Room #
Destination
Room #
Attachment 7
Cable
#
Installer
Page 12.9
Sasco Contractors
Unit 111 - 3070 Norland Avenue
Burnaby, BC V5B 3A6
Attachment 7
Page 12.10
Telecommunications Contractors
Radian Communications
6660 McMillan Way
Richmond, BC V6W 1J7
Houle Electric
3735 Myrtle Street
Burnaby, BC V5C 4E7
Netricom
4305 Canada Way
Burnaby, BC V5A 1J3
th
4 Utility Inc.
7590 Lowland Drive
Burnaby, BC V5J 5A4
Consulting Engineers
Omicron
Suite 500 595 Burrard Street
Vancouver, BC V7X 1L4
Telecommunications Service Providers
Telus
Bell Intrigna Inc.
Microcell Solutions Inc.
Avellann Networks
Greater Vancouver Tansportation Authority
Group Telecom Services Corp.
MetroNet Communications
Attachment 7
Page 12.11
ATTACHMENT 9
Attachment 9
Page 14.1
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Attachment 9
Page 14.2
Demo all domestic water work lines back to core wall. Cut and provide new
valves and cap end.
Demo all drains, vents. Cap-off at core wall.
Fire stop all penetrations in slab.
Remove all redundant hangers.
Demo all condensate lines.
Attachment 9
Page 14.3
GENERAL NOTES
1.
2.
3.
4.
5.
6.
7.
Bid pricing shall be base upon all specified equipment, devices and fixtures
as noted on the drawings and in the electrical specification. Identify any
alternatives individually on the form of the tender pricing for
review/acceptance.
A copy of the latest electrical specification shall be kept on site at all times.
The electrician shall familiarize himself with the requirements of the
specifications as it applies to this project. Current Omicron specification is
dated September 2009 (no revisions).
Refer to specifications regarding seismic restraint cable requirements for all
new and existing lighting fixtures.
Remove all unused base building fixtures from the site. No base fixtures to
be retained by owner unless otherwise noted to the contrary. Refer to
specifications.
In no case shall any new power or communications cables be supported from
any t-bar or mechanical supports. All conduits, BX and communication
cables shall be supported independently from building basic structure. Refer
to specifications for additional information.
Confirm power and communications outlets and mounting heights with
interior designer prior to outlet rough-in. Refer also to interior designers
drawings and details.
Show all lighting circuits used for all new and existing (including base building
fixtures) on record drawings.
Attachment 9
Page 14.4
ATTACHMENT 10
Attachment 10
Page 15.1
Attachment 10
Page 15.2
Attachment 10
Page 15.3
Attachment 10
Page 15.4
BENTALL CENTRE
RETAIL CONSTRUCTION
MANUAL
Attachment 11
Page 16.1
CONSTRUCTION GUIDELINES
General Instructions to Tenants
I n o r d e r t o e xp e d i t e t h e c o m p l e t i o n o f a l l Te n a n t s t o r e s wi t h t h e l e a s t a m o u n t o f
i n c o n ve n i e n c e t o a l l c o n c e r n e d , t h e f o l l o wi n g r u l e s a n d r e g u l a t i o n s wi l l b e
a p p l i c a b l e t o a l l Te n a n t s u p o n s t a r t i n g t h e i r c o n s t r u c t i o n . Th e s e r e g u l a t i o n s wi l l
b e e n f o r c e d t o e n s u r e n o i n t e r r u p t i o n s a r e c a u s e d b y Te n a n t c o n t r a c t o r s t o o t h e r
b u s i n e s s o r p u b l i c m o ve m e n t s .
1.
N o Te n a n t wo r k m a y p r o c e e d p r i o r t o t h e L a n d l o r d s wr i t t e n
a p p r o va l , wh i c h wi l l n o t b e u n r e a s o n a b l y wi t h h e l d o r d e l a ye d .
2.
P r i o r t o c o m m e n c e m e n t o f Te n a n t wo r k , t h e Te n a n t C o n t r a c t o r s h a l l
p r o vi d e t h e L a n d l o r d wi t h p r o o f o f C o n s t r u c t i o n L i a b i l i t y I n s u r a n c e i n
a c c o r d a n c e wi t h t h e c o ve r a g e r e q u i r e d u n d e r t h e t e r m s o f t h e O f f e r
to Lease, construction subtrades list and other Pre-construction
P a p e r wo r k a s d e t a i l e d o n P a g e 1 6 . 2 5 .
3.
Th e Te n a n t s h a l l m a i n t a i n wo r k s u p o n t h e P r e m i s e s i n a c l e a n a n d
o r d e r l y c o n d i t i o n a n d s h a l l p r o m p t l y r e m o ve a l l wa s t e , u n u s e d
materials, equipment and in particular, all flammable goods from
site. Landlord compactors cannot be used for this purpose. Fire
e xt i n g u i s h e r s m u s t b e m a i n t a i n e d o n t h e P r e m i s e s b y t h e Te n a n t a s
m a y b e d i r e c t e d b y a l o c a l F i r e P r e ve n t i o n O f f i c e r o r t h e L a n d l o r d .
Ma l l s e r vi c e c o r r i d o r s a n d e xt e r n a l a r e a s a r e t o b e k e p t c l e a r a t a l l
t i m e s a n d t h e L a n d l o r d r e s e r ve s t h e r i g h t t o r e m o ve a l l Te n a n t s
m a t e r i a l s , e t c . , f r o m s u c h a r e a s a t t h e Te n a n t s e xp e n s e wi t h o u t
further notification.
4.
Th e Te n a n t s h a l l e n s u r e t h a t p r o p e r p r o vi s i o n f o r f i r e p r o t e c t i o n o f
the Leased Premises is maintained during the construction and
f i xt u r i n g p e r i o d .
5.
Th e L a n d l o r d , o r h i s C o n s u l t a n t s o n h i s b e h a l f , s h a l l h a ve a c c e s s t o
t h e wo r k wh e n e ve r i t i s i n p r e p a r a t i o n o r p r o g r e s s , a n d t h e Te n a n t
s h a l l p r o vi d e p r o p e r f a c i l i t i e s f o r s u c h a c c e s s a n d i n s p e c t i o n . Th e
p u r p o s e o f s u c h i n s p e c t i o n i s t o e n s u r e t h a t n o u n a u t h o r i ze d wo r k i s
carried out.
6.
Th e Te n a n t wi l l b e e n t i r e l y r e s p o n s i b l e f o r t h e s e c u r i t y o f t h e L e a s e d
P r e m i s e s d u r i n g c o n s t r u c t i o n a n d t h e f i xt u r i n g p e r i o d , a n d s h a l l t a k e
a l l n e c e s s a r y s t e p s t o s e c u r e t h e s a m e . Th e L a n d l o r d s h a l l h a ve n o
liability for any loss or damage including the theft of building
materials, equipment or supplies.
7.
Te n a n t C o n t r a c t o r s a n d s u p p l i e r s wi l l b e s u b j e c t t o wo r k r e s t r i c t i o n s
wh i c h m a y b e i m p o s e d b y t h e L a n d l o r d .
8.
I t i s t h e r e s p o n s i b i l i t y o f t h e Te n a n t t o e n s u r e t h a t h i s c o n t r a c t o r s
e xe r c i s e a l l c a u t i o n i n m a t t e r s r e l a t i n g t o p u b l i c s a f e t y a n d t o c o m p l y
wi t h t h e s t a n d a r d s e s t a b l i s h e d b y a u t h o r i t i e s h a vi n g j u r i s d i c t i o n .
9.
Th e r e s h a l l b e n o c o n f l i c t b e t we e n t h e Te n a n t C o n t r a c t o r a n d t h e
l a b o u r u n i o n a f f i l i a t i o n s t o wh i c h a n y L a n d l o r d s c o n t r a c t o r i s a
p a r t y.
Attachment 11
Page 16.2
1 0 . Th e L a n d l o r d s h a l l p r o vi d e t h e Te n a n t wi t h t e m p o r a r y s e r vi c e s t h a t
m a y b e r e q u i r e d d u r i n g c o n s t r u c t i o n p h a s e a t t h e Te n a n t s e xp e n s e .
1 1 . P r i o r t o t h e c o m m e n c e m e n t o f Te n a n t s wo r k , t h e L e a s e d P r e m i s e s
m u s t b e e n c l o s e d i m m e d i a t e l y wi t h t h e p e r m a n e n t s t o r e f r o n t . S h o u l d
t h e Te n a n t b e u n a b l e t o i n s t a l l t h e p e r m a n e n t s t o r e f r o n t d u e t o
d e l a ys i n d e l i ve r y, e t c . , t h e s t o r e f r o n t o p e n i n g m u s t b e e n c l o s e d b y
m e a n s o f s u i t a b l e b a r r i c a d e wi t h a d o o r a s a p p r o ve d b y t h e
L a n d l o r d . Th i s b a r r i c a d e i s t o b e c o n s t r u c t e d o f a q u a l i t y m a t e r i a l
c o m p l e t e wi t h a p a i n t f i n i s h .
1 2 . Te m p o r a r y s c a f f o l d i n g m o u n t e d o n r u b b e r wh e e l s m a y b e u s e d i n t h e
mall area to permit the installation of storefronts and sign panels.
Th e t yp e o f s c a f f o l d i n g t o b e u s e d i n t h e m a l l a r e a wi l l b e s u b j e c t t o
t h e L a n d l o r d s a p p r o va l . A l l wo r k b e n c h e s , b e n c h s a ws , t o o l s ,
e q u i p m e n t a n d c o n s t r u c t i o n m a t e r i a l s m u s t b e c o n f i n e d wi t h i n t h e
limits of the Leased Premises.
13. Access to the Leased Premises for both construction person nel and
m a t e r i a l h a n d l i n g wi l l b e r e s t r i c t e d t o c e r t a i n e n t r a n c e s a n d s e r vi c e
c o r r i d o r s a n d s h a l l b e d e s i g n a t e d f o r e a c h Te n a n t s u s e . P r i o r t o
c o m m e n c i n g t h e f i n i s h i n g wo r k , t h e Te n a n t m u s t c o n s u l t wi t h t h e
Landlord to obtain the entrance locations and ti ming of material
d e l i ve r i e s .
1 4 . A n y m e r c h a n d i s e , m a t e r i a l s o r e q u i p m e n t b e i n g d e l i ve r e d t o t h e
Leased Premises across the mall floor area must be done on dollies
wi t h r u b b e r t i r e s .
1 5 . O d o u r s : W C B r e q u i r e s t h a t t h e f o l l o wi n g m a t e r i a l s , d u e t o t h e o d o r s
t h e y p r o d u c e , n o t b e a p p l i e d d u r i n g n o r m a l b u s i n e s s h o u r s ( Mo n d a y
t o F r i d a y, 6 : 0 0 A M t o 6 : 0 0 P M) : l a c q u e r s , o i l b a s e d p a i n t s , e n a m e l
paints, lacquer based contact cement, carpet glues, sealers, burning
e q u i p m e n t , g a s we l d e r s , o r a n yt h i n g t h a t m a y p r o d u c e n o xi o u s
f u m e s . I f t h e r e a r e a n y q u e s t i o n s wi t h r e g a r d t o p r o d u c t ( s ) t o b e
u s e d , c o n t a c t t h e Ma n a g e r , B u i l d i n g P r o j e c t s a n d C o n s t r u c t i o n .
A u t o m o t i ve p a i n t s p r a ys a r e n o t a l l o we d .
16. Th e f o l l o wi n g l i m i t a t i o n s s h a l l b e o b s e r ve d b y t h e Te n a n t i n t h e
c o n d u c t o f Te n a n t s wo r k :
i.
N o s u s p e n d e d l o a d s wi l l b e a t t a c h e d t o t h e
u n d e r s i d e o f t h e c e i l i n g s t r u c t u r e wi t h o u t t h e
L a n d l o r d s wr i t t e n a p p r o va l .
ii.
N o wa l l m o u n t e d f i xt u r e s wi l l b e p e r m i t t e d o t h e r t h a n
t h o s e a p p r o ve d i n wr i t i n g b y t h e L a n d l o r d . Th e
Te n a n t a c k n o wl e d g e s t h a t t h e s t e e l s t u d a n d d r ywa l l
d e m i s i n g wa l l s a r e n o t d e s i g n e d t o s u p p o r t u n l i m i t e d
wa l l m o u n t e d f i xt u r e s .
iii.
Attachment 11
Page 16.3
1 7 . E xi s t i n g Te n a n t s c o n d u c t i n g r e n o va t i o n s m u s t p l a n a n d c a r r y o u t
r e n o va t i o n s s u c h t h a t t h e i r p r e m i s e s a r e c l o s e d f o r t h e s h o r t e s t t i m e
frame possible.
18. All sprinkler modifications, coring and roof penetrations are to be
completed by the Landlords designated Base Building Contractors
a n d c o o r d i n a t e d t h r o u g h t h e Ma n a g e r , B u i l d i n g P r o j e c t s a n d
C o n s t r u c t i o n . A l l wo r k c a r r i e d o u t b y t h e L a n d l o r d o n b e h a l f o f t h e
Te n a n t wi l l b e b a c k - c h a r g e d t o t h e Te n a n t .
1 9 . P l a s t i c p i p i n g o r t u b i n g i s n o t p e r m i t t e d t o b e u s e d wi t h d o m e s t i c
t yp e s e r vi c e s , i . e . c o f f e e u r n s , wa t e r f i l t e r s , p u r i f i e r s , r e f r i g e r a t o r s ,
ice makers, etc.
2 0 . Th e Te n a n t s h a l l e n s u r e t h a t h i s c o n t r a c t o r c o n t a i n s h i s wo r k wi t h i n
t h e L e a s e d P r e m i s e s , a t a l l t i m e s b e i n g r e s p o n s i b l e f o r wo r k i n g t o
rules and regulations defined herein or as may be imposed by the
L a n d l o r d t o e n s u r e t h a t Te n a n t s a r e wi t h o u t a n y o t h e r d i s t u r b i n g
i n f l u e n c e s . Th e r e f o r e , n o i s y wo r k m u s t b e c a r r i e d o u t d u r i n g
shopping centre non-business hours and at the Landlords
discretation.
21. Guidelines for hoarding installation prior to construction are as
f o l l o ws :
E n s u r e t h a t yo u r h o a r d i n g d o e s n o t p r o t r u d e m o r e t h a n 2 f e e t
f r o m yo u r l e a s e l i n e
H o a r d i n g m u s t b e p a i n t e d wh i t e wi t h d a r k g r e e n r u b b e r c o ve
b a s e . A n y o t h e r c o l o u r m u s t b e a p p r o ve d b y u s p r i o r t o
painting.
N o t h i n g t o f a s t e n t o m a l l t e r r a zzo . A n y d a m a g e s t o t e r r a zzo
m u s t b e r e p l a c e d a t yo u r e xp e n s e , u s i n g o u r c o n t r a c t o r .
D o o r t o s wi n g i n t o s p a c e . K e y m u s t b e p r o vi d e d t o B e n t a l l
Security for emergency purposes.
A n y s i g n a g e / g r a p h i c s o n h o a r d i n g m u s t b e a p p r o ve d b y u s
prior to installation.
H o a r d i n g m u s t c o n t a i n a l l d u s t / d e b r i s wi t h i n yo u r p r e m i s e .
Attachment 11
Page 16.4
L E AS E L I N E : t h e l e a s e l i n e r u n s a c r o s s t h e e n t i r e s t o r e f r o n t a t t h e
b a c k o f t h e d e m i s i n g c o l u m n s . R e f e r t o t h e s t o r e t yp e s o u t l i n e d i n
t h i s m a n u a l f o r t h e e xa c t l o c a t i o n o f t h e l e a s e l i n e .
2.
P O P - O U T S : s t o r e f r o n t i n g i s n o t p e r m i t t e d t o e xt e n d b e yo n d t h e
lease line in any form at Bentall Centre, due to building code
limitations.
3.
4.
M AL L T E R R AZ Z O F L O O R : i n a l l i n s t a n c e s , t h e m a l l t e r r a zzo f l o o r
m u s t b e e xt e n d e d t o t h e c l o s u r e l i n e b y t h e Te n a n t . Te r r a zzo f l o o r
must be purchased and installed by Landlords Contractor.
5.
M AL L C E I L I N G : c e i l i n g h e i g h t s va r y t h r o u g h o u t t h e m a l l . R e f e r t o
s p e c i f i c s t o r e f r o n t e xa m p l e s f o r a c t u a l s t o r e f r o n t h e i g h t s .
6.
C O N T R O L Z O N E : a l l e l e m e n t s wi t h i n 6 - 0 o f t h e l e a s e l i n e a r e
s u b j e c t t o L a n d l o r d r e vi e w, f o r s t o r e f r o n t Te n a n t s . F o o d c o u r t a n d
f o o d u s e c o n t r o l zo n e s a r e a l l a r e a s vi s i b l e t o t h e p u b l i c .
7.
B U L K H E AD S : a l l b u l k h e a d s m u s t b e f i n i s h e d b y Te n a n t wi t h
a p p r o ve d L a n d l o r d f i n i s h e s . A l l b u l k h e a d s t o b e p a i n t f i n i s h d r ywa l l ,
c o l o u r a s s p e c i f i e d b y L a n d l o r d . Th e i n t e n t i n u s i n g o n e c o l o u r f o r
t h e s i d e o f t h e b u l k h e a d f a c i n g t h e Ma l l , a s we l l a s b u l k h e a d
u n d e r s i d e , i s t o p r o vi d e a n e u t r a l b a c k g r o u n d f o r e a c h t e n a n t s s i g n .
8.
S T O R E F R O N T C L O S U R E : s l i d i n g , f i xe d g l a s s d o o r s o r a p p r o ve d
t yp e s o f f o l d i n g g r i l l e s ( c o m p l e t e wi t h e m e r g e n c y e g r e s s d o o r s . )
During store operating hours, sliding storefront closures must stay
wi t h i n a p p r o ve d e n c l o s u r e s wh i c h c o n c e a l t h e m f r o m p u b l i c vi e w.
C e i l i n g t r a c k s f o r f o l d i n g g r i l l e s m u s t b e r e c e s s e d . Th e l e a d a n d
t r a i l i n g p o s t s f o r f o l d i n g g r i l l e s m u s t b e e q u i p p e d wi t h t o p a n d
bottom locks in lieu of surface mounted striker posts. Folding grilles
m a y e i t h e r b e wi d e o p e n , o r h a ve t e m p e r e d g l a s s i n s e r t s .
Attachment 11
Page 16.5
9.
S T O R E F R O N T F I N I S H E S : i t i s t h e Te n a n t s r e s p o n s i b i l i t y t o f i n i s h
a l l s t o r e f r o n t a r e a s b e t we e n d e m i s i n g c o l u m n s , f l o o r a n d c e i l i n g .
Storefront bases must be of a material suitable to the purpose,
c a p a b l e o f wi t h s t a n d i n g t h e n o r m a l we a r o f f l o o r c l e a n i n g a g e n t s a n d
p o l i s h i n g m a c h i n e s . R u b b e r o r vi n yl s a r e n o t a c c e p t a b l e m a t e r i a l s .
1 0 . T E N AN T L I G H T I N G : a h i g h l e ve l o f c o m m e r c i a l q u a l i t y, a c c e n t
l i g h t i n g ( i n c a n d e s c e n t / h a l o g e n e t c . ) wi t h i n t h e s t o r e f r o n t i s
r e c o m m e n d e d . N o l i g h t i n g o u t s i d e o f t h e T e n a n t c l o s u r e l i n e wi l l b e
p e r m i t t e d . F l u o r e s c e n t f i xt u r e s wi t h o u t l e n s e s o r s u r f a c e m o u n t e d
f l u o r e s c e n t f i xt u r e s wi l l n o t b e p e r m i t t e d a n ywh e r e i n t h e p u b l i c a r e a
of stores.
1 1 . T E N AN T F L O O R I N G : Te n a n t s a r e e n c o u r a g e d t o i n c o r p o r a t e t h e u s e
o f s o m e h a r d s u r f a c e f l o o r i n g m a t e r i a l wi t h i n t h e i r s t o r e s ( i . e . t i l e ,
m a r b l e , e t c . ) i n a n a t t e m p t t o p r o vi d e a d d e d d e s i g n i n t e r e s t .
1 2 . W I N D O W T R E AT M E N T S : W i n d o w t r e a t m e n t i s a n i m p o r t a n t p a r t o f
Te n a n t d i s p l a y a n d p r e s e n t a t i o n . Th e L a n d l o r d wi l l m a i n t a i n
c o n t i n u o u s r e vi e w i n t h e s e a r e a s . A l l wi n d o w l o c a t i o n s m u s t c o n f o r m
t o t h e f o l l o wi n g g u i d e l i n e s :
i.
ii.
S t o r e f r o n t d i s p l a y wi n d o ws s h o u l d m a i n t a i n a
t a s t e f u l t r e a t m e n t f o r p u b l i c vi e wi n g wi t h
continuous display upgrading.
U n d e r c e r t a i n d i s p l a y a p p l i c a t i o n s , wi n d o w
s c r e e n i n g wi l l b e a l l o we d . S c r e e n i n g m a t e r i a l s a n d
l o c a t i o n wi l l b e u n d e r s t r i c t r e vi e w.
iii.
W i n d o w p a i n t i n g wi l l n o t b e a l l o we d .
i v.
P o s t e r s a n d m a t e r i a l s u s e d f o r a d ve r t i s i n g wi l l n o t
b e p e r m i t t e d t o b e f i xe d t o t h e s t o r e f r o n t g l a s s
a r e a o r o n t h e d r ywa l l s u r r o u n d i n g t h e s t o r e .
v.
I l l u m i n a t e d wi n d o w a d ve r t i s i n g b o xe s wi l l n o t b e
permitted.
vi .
E q u i p m e n t , c l o s e d b a c k e d s h e l vi n g o r s o l i d wa l l
c o n s t r u c t i o n s h a l l n o t b a c k o n t o wi n d o w a r e a s .
Attachment 11
Page 16.6
Storefront Condition I
Attachment 11
Page 16.7
Storefront Condition II
Attachment 11
Page 16.8
Attachment 11
Page 16.9
Storefront Condition IV
Attachment 11
Page 16.10
Demising Columns
Typ i c a l l y e a c h C R U i s f r a m e d b y a d e m i s i n g b e e c h c o l u m n . C o l u m n s e xt e n d t o
e i t h e r a b u l k h e a d o r t h e m a l l c e i l i n g , d e p e n d i n g o n t h e l o c a t i o n . Th e i n t e n t o f t h e
d e m i s i n g c o l u m n i s t o s e p a r a t e Te n a n c i e s . A t yp i c a l d e m i s i n g c o l u m n i s 1 4 " wi d e .
1.
Te n a n t d e t a i l i n g a t t h e d e m i s i n g c o l u m n s c a n b e h a n d l e d ve r y s i m p l y
a n d e f f e c t i ve l y b y f o l l o wi n g a f e w s i m p l e g u i d e l i n e s . A l l Te n a n t
storefronting must be contained behind the demising columns.
2.
When the intent is to stay parallel with the back of the demising
columns, the Tenant shall contain the entire storefront element
b e h i n d t h e c o l u m n . At n o t i m e s h a l l a T e n a n t s t o r e f r o n t p r o j e c t
on the face or side of the demising column.
3.
B o xe d o u t f r e e s t a n d i n g d i s p l a y s h o wc a s e s i n t h e c e n t e r o f a
storefront, creates a central feature that introduces unique double
storefront entry access.
4.
W h e n t h e i n t e n t i s t o c r e a t e a p o p o u t e f f e c t , t h e Te n a n t s h a l l c o m e
out 12 minimum from the demising column before angling out
d i s p l a y wi n d o w, t h e s t o r e f r o n t e l e m e n t s h a l l n o t p r o j e c t o n t o t h e
face or side of the column.
5.
Attachment 11
Page 16.11
Attachment 11
Page 16.12
Signage
S i g n a g e i s a n i m p o r t a n t m e t h o d o f p o r t r a y i n g i m a g e a n d i d e n t i t y. Th e B e n t a l l
Centre has a standard signage program in place to ensure the first -class
a p p e a r a n c e o f t h e c o m p l e x. E a c h B e n t a l l C e n t r e t e n a n t i s r e q u i r e d t o i n s t a l l a n d
m a i n t a i n s i g n a g e . Te n a n t s i g n a g e wi l l b e l i m i t e d t o o n e m a i n s t o r e f r o n t s i g n f o r
e a c h m a l l e l e va t i o n .
Tenants are required to adhere to Bentall Centre
signage standards.
Temporary or non-building standard signs are not allowed to be taped to
building walls, demising columns, or other areas.
We appreciate your
cooperation in maintaining the professional image of the Centre.
A l l s i g n a g e m u s t h a ve L a n d l o r d s wr i t t e n a p p r o va l p r i o r t o s i g n
fabrication or installation on the storefront.
Store signage is for the purpose of identification only and must be limited
to trade names and logos.
N o m o vi n g c o m p o n e n t s a n d f l a s h i n g l i g h t s a r e p e r m i t t e d .
A d ve r t i s i n g o r i d e n t i f i c a t i o n o f p r o d u c t s a s p a r t o f t h e s t o r e f r o n t s i g n a g e
is not permitted.
F o r p e r m i s s i b l e s i g n d e t a i l s a n d c r o s s - s e c t i o n s s e e p a g e f o l l o wi n g
pages.
A l l s i g n s u b m i s s i o n s m u s t b e t o s c a l e a n d i n c o l o u r f o r i n i t i a l a p p r o va l
a n d r e vi e w.
S i g n a g e s h o p d r a wi n g s m u s t b e s u b m i t t e d f o r f i n a l a p p r o va l t o t h e
B e n t a l l C e n t r e Ma n a g e r , B u i l d i n g P r o j e c t s a n d C o n s t r u c t i o n p r i o r t o
signage fabrication and installation.
S i g n s m u s t b e f a b r i c a t e d a c c u r a t e l y wi t h s t r a i g h t l i n e s , c o n t i n u o u s
c u r ve s a n d s h a r p i n s i d e c o r n e r s wi t h n o vi s i b l e f a s t e n e r s .
Signs must show no hot spots in illumination and must be lit at all times
during mall opening hours.
S i g n m a n u f a c t u r e r s l a b e l s m u s t b e c o n c e a l e d f r o m p u b l i c vi e w.
All electrical sign components and attachments must conform to local
e l e c t r i c a l a n d b u i l d i n g c o d e s , a s we l l a s C . S . A . s t a n d a r d c o m p l i a n c e .
Th e f o l l o wi n g s i g n s a r e n o t p e r m i t t e d :
E xp o s e d n e o n i s n o t p e r m i t t e d e xc e p t a s a c c e n t g r a p h i c a s s h o wn i n t h i s
criteria.
Box signs
Painted letters on bulkhead.
Internally illuminated canopies.
Attachment 11
Page 16.13
Sign Criteria
Permissible Sign Detail and Cross Sections
Attachment 11
Page 16.14
Sign Criteria
Logo, Recessed Signs and Neon Accent Graphic Placement and Sizes
SIGN
SIGN
SIGNAGE
SIGNAGE
16 inches
inches in height on 22 inch
10 inches
SIGNAGE }
14 inches
Attachment 11
Page 16.15
SIGNAGE }
10 inches
Sign Criteria
Internally Illuminated Letter Placement and Sizes
14 inches
10 inches
14 inches
10 inches
14 inches
10 inches
Sign placement cannot be more than 12 inches away from demising column on both sides.
Attachment 11
Page 16.16
2.
Te n a n t f r o n t c o u n t e r h e i g h t m u s t n o t e xc e e d 3 ' - 0 " , e xc e p t wh e r e
g l a s s d i s p l a y c a s e s o r s n e e ze g u a r d s a r e u s e d . Ma xi m u m h e i g h t f o r
s n e e ze g u a r d g l a s s i s 4 ' - 6 " o f f t h e f i n i s h e d m a l l f l o o r .
3.
F l i p u p c o u n t e r s a n d s wi n g d o o r s m u s t b e i n c o n s p i c u o u s a n d m u s t
match counter profiles and finishes.
4.
Tr a y r a i l s m u s t n o t p r o j e c t p a s t t h e l e a s e l i n e , a n d m u s t b e
incorporated into counter design.
5.
A l l m e t a l t r i m s t o d i s p l a y c a s e s , s n e e ze g u a r d s a n d t r a y r a i l s m u s t
u s e a d e c o r a t i ve f i n i s h . Th e u s e s o f b r a s s , c h r o m e o r p o l i s h e d
copper are acceptable finishes. Commercial brushed stainless steel
wi l l n o t b e a p p r o ve d .
Attachment 11
Page 16.17
6.
W h e n e ve r a n e xh a u s t h o o d i s u s e d a n d i s e xp o s e d t o p u b l i c vi e w, i t
must be clad in acceptable materials and finishes.
7.
N o s i m u l a t e d wo o d g r a i n o r m a r b l e f i n i s h e s wi l l b e p e r m i t t e d wi t h i n
p u b l i c vi e w.
8.
A l l d o o r s t o r e a r a r e a s m u s t u s e a s e l f c l o s i n g d e vi c e , s o t h a t
s t o r a g e r o o m s a r e n o t vi s i b l e t o p u b l i c .
9.
Te n a n t s s h a l l b e r e s p o n s i b l e f o r a l l n e c e s s a r y s e c u r i t y.
1 0 . Te n a n t s m u s t u s e wa s h a b l e c e i l i n g s i n f o o d p r e p a r a t i o n a r e a s .
Attachment 11
Page 16.18
Attachment 11
Page 16.19
I n g e n e r a l , t h e f o l l o wi n g g u i d e l i n e s a p p l y t o a l l F o o d Te n a n t s :
1.
F l i p u p c o u n t e r s a n d s wi n g d o o r s m u s t b e i n c o n s p i c u o u s a n d m u s t
match counter profiles and finishes.
2.
A l l m e t a l t r i m s t o d i s p l a y c a s e s a n d s n e e ze g u a r d s m u s t u s e a
d e c o r a t i ve f i n i s h . Th e u s e o f b r a s s , c h r o m e , b r u s h e d s t a i n l e s s s t e e l
or polished copper are acceptable finishes.
3.
W h e n e ve r a n e xh a u s t h o o d i s u s e d a n d i s e xp o s e d t o p u b l i c vi e w, i t
must be clad in acceptable materials and finishes.
4.
N o s i m u l a t e d wo o d g r a i n o r m a r b l e f i n i s h e s wi l l b e p e r m i t t e d wi t h i n
p u b l i c vi e w.
5.
R e a r s t o c k s t o r a g e r o o m s a r e n o t t o b e vi s i b l e t o t h e p u b l i c a r e a . A l l
d o o r s t o r e a r a r e a s m u s t u s e a s e l f c l o s i n g d e vi c e .
6.
Te n a n t s s h a l l b e r e s p o n s i b l e f o r a l l n e c e s s a r y s e c u r i t y.
7.
Te n a n t s m u s t u s e wa s h a b l e c e i l i n g s i n f o o d p r e p a r a t i o n a r e a s .
Attachment 11
Page 16.20
1.
2.
3.
4.
5.
6.
Attachment 11
Page 16.21
Moving Guidelines
1.
General:
Th e m o ve r s h a l l p e r f o r m a l l s e r vi c e s r e q u i r e d t o m o ve t h e p r o p e r t y o f t h e Te n a n t a s
c o n t r a c t e d b y t h e Te n a n t . Th e s e s e r vi c e s s h a l l i n c l u d e p i c k u p a n d t r a n s f e r o f t h e
property to the designated location in the new building.
E a c h e m p l o ye e o f t h e m o ve r s h a l l b e b o n d e d a n d i s r e q u i r e d t o h a ve i d e n t i f i c a t i o n wi t h
m o vi n g c o m p a n y' s n a m e o n i t i n o r d e r t o m a i n t a i n t h e s e c u r i t y o f t h e p r e m i s e a n d t o
p r o vi d e e a s y i d e n t i f i c a t i o n b y B e n t a l l C e n t r e p e r s o n n e l .
A l l m o ve s m u s t t a k e p l a c e b e f o r e o r a f t e r b u s i n e s s h o u r s ( b e t we e n 5 : 3 0 P M a n d 7 : 3 0
A M) , Mo n d a y t h r o u g h F r i d a y o r a n y t i m e o n we e k e n d s . P l e a s e e n s u r e t h e Te n a n t
S e r vi c e s C o o r d i n a t o r i s m a d e o f a wa r e o f a n y i n t e n d e d m o ve s ( i n c l u d i n g l a r g e f u r n i t u r e
m o ve s ) o r S e c u r i t y m a y h a l t t h e m o ve .
N o i t e m s h o u l d b e l e f t u n a t t e n d e d i n t h e h a l l wa ys o r o n t h e l o a d i n g d o c k wh i l e o n
break.
Any damage to the building shall
contractor at the Tenants expense.
2.
be
repaired
by
the
building
designated
Building Entry:
Mo ve r s a r e t o u s e o n e o f t h e t wo l o a d i n g d o c k s f o r a l l u n l o a d i n g a n d l o a d i n g . Y o u a r e
r e q u i r e d t o m a k e p r i o r a r r a n g e m e n t s w i t h B e n t a l l C e n t r e S e c u r i t y t o e n s u r e yo u r
m o ve t i m e d o e s n o t c o n f l i c t w i t h a n o t h e r m o ve .
3.
S u p e r vi s i o n , L a b o r , Ma t e r i a l a n d E q u i p m e n t :
Th e m o ve r s h a l l f u r n i s h a l l s u p e r vi s i o n , l a b o u r , m a t e r i a l , s u p p l i e s , a n d e q u i p m e n t
n e c e s s a r y t o p e r f o r m a l l o f t h e c o n t r a c t e d s e r vi c e s i n a n o r d e r l y, t i m e l y, a n d e f f i c i e n t
m a n n e r . A l l m a t e r i a l h a n d l i n g ve h i c l e s u s e d i n t h e i n t e r i o r o f t h e b u i l d i n g m u s t h a ve
r u b b e r - t i r e d wh e e l s a n d m u s t b e m a i n t a i n e d f r e e f r o m g r e a s e a n d d i r t .
4.
C r a t i n g , P a d d i n g , a n d P a c k i n g Ma t e r i a l :
Th e m o ve r s h a l l t a k e e ve r y p r e c a u t i o n b y m e a n s o f c r a t i n g a n d p a d d i n g t o s a f e g u a r d
property and the building from damage. All padding and packing materials are to be
r e m o ve d f r o m t h e b u i l d i n g b y t h e m o ve r . Th e m o ve r s h a l l a l s o f u r n i s h , i n s t a l l a n d
r e m o ve f l o o r , c a r p e t , t i l e , wa l l , a n d g l a s s p r o t e c t i ve m a t e r i a l s wh e r e n e c e s s a r y t o
protect the building from damage.
Attachment 11
Page 16.22
5.
Mo vi n g Ma t e r i a l s :
A g a i n , p l e a s e b e s u r e yo u r m o ve r a n d / o r d e l i ve r y ve n d o r u n d e r s t a n d s t h a t a l l l a r g e
c a r t o n s , c o n t a i n e r s , g a r b a g e , e t c . , m u s t l e a ve wi t h t h e ve n d o r . T h e r e i s n o b u i l d i n g
storage or trash facility to accommodate such items.
6.
S a f e t y/ S e c u r i t y:
I t s h a l l b e t h e r e s p o n s i b i l i t y o f t h e m o ve r / Te n a n t t o p e r f o r m t h e m o ve i n t h e s a f e s t
m a n n e r p o s s i b l e , a vo i d i n g b l o c k i n g o f b u i l d i n g c o r r i d o r s , b l o c k i n g e n t r a n c e s a n d e xi t s ,
a vo i d i n g t h e a c c u m u l a t i o n o f l a r g e a m o u n t s o f c o m b u s t i b l e m a t e r i a l s .
T h e m o ve r m u s t r e p o r t a n y e l e c t r i c a l p r o b l e m s o r e q u i p m e n t b r e a k d o w n s t h a t
o c c u r d u r i n g t h e m o ve , w h i c h m a y a f f e c t b u i l d i n g o p e r a t i o n . P l e a s e c o n t a c t t h e
B e n t a l l C e n t r e S e c u r i t y D e s k a t 7 7 8 - 3 2 8 - 5 9 9 0 i m m e d i a t e l y.
Attachment 11
Page 16.23
Pre-construction Paperwork
1. drawings (2 full sets size 24" x 36" delivered to Suite 1525 555 Burrard Street - Attention:
Al Briard, Director, Tenant Coordination Office Properties, Western Region, AND copy
emailed to abriard@canderel.com
2. WorkSafe certificate
3. Building Permit
4. Statement of Acknowledgement
5. Insurance certificate
6. Trades List
7. Work Authorization Form signed by tenant (if suite is occupied)
8. Work schedule (start and end dates)
9. Installation of hoarding, per Landlords requirements
Should you have any questions or concerns, please contact us at your convenience.
Al Briard
Director, Tenant Coordination Office Properties, Western Region
T. 778-328-5978
E. abriard@canderel.com
Billy Rosenlund
Construction & Projects Coordinator
T. 778-328-5962
E. brosenlund@canderel.com
Attachment 11
Page 16.24
Please note that, according to our policy, the insurance certificate must include the following details
exactly as shown below:
CERTIFICATE HOLDER
Canderel Pacific Management Inc.
555 Burrard Street, Suite 1525
Box 226
Vancouver, BC V7X 1M9
INSURED
Your company name and Bentall Centre address including suite number.
Tower 1 505 Burrard Street
Tower 2 555 Burrard Street
Tower 3 595 Burrard Street
Tower 4 1055 Dunsmuir Street
Vancouver, BC
ADDITIONAL INSURED
For Towers 1 & 2:
Maple Red Financial Management Canada Inc., 9751254 Canada Inc. and Canderel Pacific Management
Inc
For Tower 3:
Maple Red Financial Management Canada Inc., 9751319 Canada Inc. and Canderel Pacific Management
Inc.
For Tower 4 and the ALRT:
Maple Red Financial Management Canada Inc., 9751327 Canada Inc. and Canderel Pacific Management
Inc.
COVERAGE REQUIRED
All risks Property insurance that includes coverage for earthquake and flood.
General Liability insurance in an amount no less than $5,000,000.00. (according to lease)
Boiler and Machinery (if you operate a boiler or pressure vessel)
Insurance certificates should be sent to:
Canderel Pacific Management Inc.
Suite 1525 555 Burrard Street, Box 226
Vancouver, B.C., V7X 1M9
Attachment 11
Page 16.25
REMINDER CHECKLIST
GENERAL CONTRACTOR RESPONSIBILITIES
General Contractor:
Bentall Centre Tenant:
Tenant Address:
Please note that as the General Contractor for the above Bentall Centre tenant, it is mandatory that the following items be
completed and submitted prior to the tenant moving in. Please check these items off, sign, and email this form along with
applicable documentation to Billy Rosenlund, Construction & Projects Coordinator (brosenlund@canderel.com).
Architectural,
Mechanical and
General Contractors
Signature:
Date:
Attachment 11
Page 16.26
PARKING
Loading Zone Access
Th e B e n t a l l C e n t r e h a s t wo l o a d i n g zo n e s f o r d e l i ve r i e s a n d c o n t r a c t o r a c c e s s . Th e r e
are 15 minute parking restrictions in these areas.
To we r O n e L o a d i n g Z o n e : E n t r a n c e o n s o u t h s i d e o f P e n d e r S t r e e t . H e i g h t r e s t r i c t i o n
of 10".
To we r F o u r L o a d i n g Z o n e :
restriction of 10'.
E n t r a n c e o n s o u t h s i d e o f E ve l e i g h S t r e e t .
Height
Height Restrictions
Pender Parkade:
Ma xi m u m ve h i c l e c l e a r a n c e :
64
Th u r l o w P a r k a d e :
Ma xi m u m ve h i c l e c l e a r a n c e :
64
A s p e c i a l n o t e t o p a r k e r s : wi t h t h e a d d i t i o n o f s k i r a c k s a n d o ve r h e a d b i n s , ve h i c l e s
c a n e xc e e d t h e m a xi m u m c l e a r a n c e i n t h e p a r k a d e a n d d a m a g e t h e o ve r h e a d g a t e s . I f
yo u a d d a n y a t t a c h m e n t s t o yo u r ve h i c l e , p l e a s e e n s u r e yo u r e vi e w t h e ve h i c l e h e i g h t
restrictions.
Hourly
Day Parking: Parking rates based on duration of stay in the parkade and charged at
h o u r i n c r e m e n t s t o a d a i l y m a xi m u m .
Night/Weekend Parking: Different parking rates come into effect after 6:00 PM and
o n S a t u r d a ys , S u n d a ys , a n d S t a t u t o r y H o l i d a ys .
Attachment 11
Page 16.27
SECURITY
Th e B e n t a l l C e n t r e h a s s e c u r i t y p e r s o n n e l o n - s i t e 2 4 h o u r s p e r d a y t h r o u g h o u t t h e
ye a r t o s a f e g u a r d t h e c o m p l e x. Th e s e c u r i t y c o n t r o l c e n t r e f o r t h e c o m p l e x i s l o c a t e d
i n t h e m a i n l o b b y o f F o u r B e n t a l l C e n t r e . S h o u l d yo u n o t i c e a n y s u s p i c i o u s a c t i vi t y o r
face an emergency situation, please call:
CALL 778-328-5990
R e d f i r e p h o n e s l o c a t e d b y s t a i r we l l s i n c l u d i n g p a r k a d e s
I n t e r c o m i n e l e va t o r s
E m a i l a t b e n t a l l c e n t r e s e c u r i t y@ c a n d e r e l . c o m
Th e B e n t a l l C e n t r e h a s a b u i l d i n g c a r d - a c c e s s s ys t e m i n p l a c e t o s e c u r e t h e c o m p l e x
a f t e r h o u r s . Th e c o m p l e x i s s e c u r e f r o m 6 : 0 0 P M t o 6 : 0 0 A M, Mo n d a y t h r o u g h F r i d a y
a n d 2 4 h o u r s S a t u r d a y, S u n d a y, a n d S t a t u t o r y H o l i d a ys .
After hours, a building
a c c e s s c a r d i s r e q u i r e d t o g a i n a c c e s s t o t h e c o m p l e x. I n a d d i t i o n , a l l s t a i r we l l s a r e
l o c k e d t o d i r e c t t r a f f i c t o t h e b u i l d i n g e l e va t o r s ( wi t h t h e e xc e p t i o n o f c r o s s o ve r f l o o r s
as per fire code).
Security Manager
Th e B e n t a l l C e n t r e h a s a f u l l - t i m e Ma n a g e r , S e c u r i t y, F i r e & L i f e S a f e t y o n s i t e t o
o ve r s e e a n d c o o r d i n a t e s e c u r i t y a n d l i f e s a f e t y s e r v i c e s p r o vi d e d t o B e n t a l l C e n t r e
t e n a n t s . Th e S e c u r i t y, F i r e a n d L i f e S a f e t y Ma n a g e r i s r e s p o n s i b l e f o r o ve r s e e i n g o u r
s e c u r i t y c o n t r a c t , a l l s e c u r i t y s ys t e m r e q u e s t s , a n d t e n a n t s e c u r i t y i s s u e s . H e i s a l s o
a va i l a b l e t o m e e t wi t h yo u t o d i s c u s s s e c u r i t y m a t t e r s r e l a t i n g t o yo u r i n d i vi d u a l o f f i c e
premises and can be contacted directly at 778-328-5981 or, by email at
b e n t a l l c e n t r e s e c u r i t y@ c a n d e r e l . c o m , o r b y f a x a t 7 7 8 - 3 2 8 - 5 9 8 9 .
Attachment 11
Page 16.28
Security Procedures
Contractor Access
All modifications and contractor work which occurs after-hours within tenant premises must first
be authorized by both the tenant and the landlord. A work authorization form which details the
scope of work and grants access to the premises after-hours must be filled out and signed by the
tenant and the landlord. If the tenant requests the work to be done, the tenant must fill out the
form at www.bentallcentre.com and forward it to the Bentall Centre Security Desk located in
Tower 4 or email at bentallcentresecurity@canderel.com, or by fax 778-328-5989 for the
landlords signature. If the landlord requires the work, the landlord will fill out the form and come
to the tenant for a signature. This form is used for both landlord and contractor access to tenant
premises (except in the event of emergencies). The work authorization form is on the following
page.
Attachment 11
Page 16.29
BENTALL BUILDING:
Bentall Two
Bentall Three
Bentall Four
Retail Mall
major construction
cleaning
other
CONTRACTOR
COMPANY:
OFFICE PHONE:
one form per contractor
ON-SITE
EMPLOYEES:
DATE ACCESS
REQUIRED:
ON-SITE CONTACT
PHONE NUMBER:
START TIME:
24 hours notice required
COMPLETION
DATE:
END TIME:
1.This form must be returned 24 hours in advance to be processed properly. Forms should be either attached through Angus Anywhere at
www.bentallcentre.com or faxed to 778 328-5989 or returned to the Security Control Centre in the Bentall Four lobby at 1055 Dunsmuir St.
2. Freight elevators must be booked 24 hours in advance for deliveries. Contact the Bentall Security Control Centre (778-328-5990).
3. Elevators can only be booked before 06:00AM or after 6:00PM, Monday through Friday or 24 hours on weekends. Construction materials
to be delivered no later than 6:30AM.
4. Deliveries (from 6:00PM-6:00AM) through the loading dock will require a Security Officer to be hired to patrol the loading dock
area. Security Officers must be booked 24 hours in advance by contacting the Security Director on 778-328-5973 (rates vary depending on
notice given).
Attachment 11
Page 16.30