Security Level: Internal

2G/3G BTS DBS RRU TMA Installation Introduction


www.huawei.com
Quality Department
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential

Objectives
Master the features of the Equipment

Master the hardware installation method of

RRU, DBS, BTS and TMA


Master the hardware installation method of the
cables of the RRU
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 2

Reference
Huawei DBS Hardware Installation

HUAWEI TECHNOLOGIES CO., LTD.


Huawei Confidential
Page 3

Huawei BTS Hardware Installation

RRU User Gu

Appearance of the RRU


Note: The mounting brk position of the RRU can be changed
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Page 4

RRU Main Function


The RRU receives RF signals from the antenna system, down-converts the RF signal
s to IF signals, and then transmits them to the BBU or the macro NodeB after amp
lification, analog-to-digital conversion, digital down-conversion, matched filte
ring, and Digital Automatic Gain Control (DAGC).
Support 12dB, 24dB gain TMA
RTW
P statistic and report Interference scan function
Standing wave detect and repor
t (VSWR if a problem sweep remove fly lead and sweep to antenna) Support ASIG (A
ntenna Interface Standards Group) 2.0
Receiver reference sensitivity typical val
ue -125.5dBm
Intermodulation sensitivity -115dBm
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 5

Appearance and Panels of RRU


HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 6

LEDs on RRUs
Label Color Status Description
RUN
Green
ON
OFF 1s on, 2s off 0.5s on, 0.5s off
The module has power input, yet the module is faulty
The module has no power input or is reporting alarms The module is operational S
oftware is being loaded to the module The module is reporting alarms (excluding
VSWRrelated alarms The module is operational The module is running No specific m
eaning
ALM
Red
ON OFF
TX_ACT
Green
ON OFF
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 7

LEDs on the RRU


Label VSWR CPRI_ W Color Red Red/g reen Status ON OFF ON (green) ON (red) 0.5s O
N, 0.5s OFF (red) OFF CPRI_E Red/g reen ON (green) ON (red) Description VSWR-rel
ated alarms are reported No VSWP-related alarm is reported The CPRI link is norm
al The optical module receives local alarms related to LOS The CPRI is out of lo
ck The optical module is not in position or is powered off The CPRI link is norm
al The optical module receives local alarms related to LOS
0.5s ON, 0.5s OFF (red)
OFF
The CPRI is out of lock
The optical module is not in position or is powered off
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 8

RRU Installation
RRU hardware installation consists of:
Installing three RRUs
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 9

RRU Installation
Installation of RRU
1. The RRU replaces the TMAs 2. Use existing fly leads from Ant to TMAs 3. Ensure
using a torque wrench to connect the fly leads to RRs 4. Use existing Labels on f
ly leads 5. Connect the power cable supplied to each RRU 6. Connect the Optical
cable supplied to CPRI W port
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 10

RRU Installation
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 11

RRU Installation
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 12

Installing the PGND cable of RRU


Connecting the PGND cable (only RRU is installed)
The green and yellow PGND cable is a single cable with a cross-sectional area of
16 mm2. Both ends of the cable are OT terminals to connect to the grounding
bolt on the RRU module. If you prepare the cable by
yourself, it is recommended to use a copper-based cable with a minimum cross-sec
tional area of 16 mm2.
PGND
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 13

Installing the Power Cable of RRU


1: Measure the length of the cable route
It is better to measure the length of power cable before cutting, sometimes the
survey info is not correct. You can get the cable length info from the cable mar
ker. Use a measuring tape or first use one power cable and route it to the corre
ct position before cutting the power cable. Then repeat the process over for the
remaining two sectors.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 14

Installing the Power Cable of RRU


2: Put color rings
You must put a color ring on the power cable when you are starting to install th
e power cable. Each ring for every sector to ensure that the sectors are not swa
pped. One ring for sector one. Two rings for sector two. Three rings for sector
Three. This must be done to avoid sector swap at either end of the connection.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 15

Installing the Power Cable of RRU


3: Surge Protection Straps
Make sure that the surge protection straps are installed correctly. Seal the con
nection correctly according to the connector sealing specification. If the kits
are not supplied write it in the Site file for follow up and retrofit. Inform th
e QA department for monitoring process.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 16

Installing the Power Cable of RRU


RRU only support the -48V DC power cable Step 1: Route the power cable. One end
of the cable is two OT terminals, and the
other end is bare. The OT terminals need to be made on site. Use the correct cri
mping tool. Take a photo of the procedure.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 17

Installing the Power Cable of RRU


Step 2: Add two OT terminals to one end of the power cable
A. Determine l the lengths of power cable for different operation according to t
he scales on the cover plate of the cabling cavity as shown: B. Based on the det
ermined lengths, remove the jacket and shielding layer from the power cable. The
n remove the jacket of a specified length from each wire.
D. Remove about 15mm jacket from the power cable
C. Add an OT terminals to each wire
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 18

Installing the Power Cable of RRU


Step 3: Remove the waterproof fillers from the cable troughs of the cabling cavi
ty. Route
the power cable along its dedicated cable trough. Place the waterproofing filler
s not used back into the openings. Take a photo..
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 19

Installing the Power Cable of RRU


Step 4: Open the cover over the terminals for the power cable
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 20

Installing the Power Cable of RRU


Step 5:Remove the screw on the strap labeled PGND. Step 6: Press the strap on th
e exposed shielding layer of the power cable, then tighten the
screw.
Step 7: Connect the OT terminal on the blue -48V DC wire to the terminal labeled
NEG(-).
Connect the OT terminal on the black or brown GND wire to the terminal labeled R
TN(+). Then tight the screw. Step 8: Close the cover. Step 9: Bind the -48V DC p
ower cable to the binding slot in the lower angle piece.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 21

Installing the Power Cable of RRU


Step 10: Connect the other end of the power cable grounding.
a. Remove about 50mm jacket from the power cable. b. Twist the shielding layer o
f the power cable into one strand, and then wrap the strand with heatshrinkable
tube of 5. d. Wrap the power cable with the heatshrinkable tube of 14 at the point
where the shielding layer is removed . f. Connect the PGND cable to the shieldi
ng grounding bar of power supply equipment. g. Add OT terminals to the blue 48 V
wire and the black GND wire, and then connect the OT terminals to the wiring ter
minals on the power supply.
C. Add a OT terminal to the other end of the PGND cable.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 22

Installing the Power Cable of RRU


Step 11. DCDU-03
Connect the RRU power cable to one of the LOAD0 to LOAD6 (12amp) terminals on th
e DCDU-03.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 23

Installing the Power / Optic Cable of RRU


HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 24

Installing the Power / Optic Cable of RRU


1.Opening and Closing the Cover Plate of the RRU Cabling Cavity
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 25

Opening and Closing of the lid


HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 26

RF Jumper of the RRU


The RF jumper of the RRU is of two types
Antenna jumper: transmits and receives
RF signals. Both ends of the antenna jumper have DIN connectors.
Ensure to seal
the connectors according to the TMA and RRU specification.
Waterproofed Joints
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 27

Installing the Optic Cable of RRU


1: Put color rings
You must put a color ring on the fiber cable when you are starting to install th
e fiber cable. Each ring for every sector to ensure that the sectors are not swa
pped.
2: Protect the connector
We must place protection for fiber cable, because it is easy to damage the fiber
connectors. Do not bend the fiber pig tail it will get damaged.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 28

Installing the Optic Cable of RRU


3: Clamp Installation
Clamps has to be installed inside a tower unless specified and all ways on a lat
tice tower from the RRU to the entry plate.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 29

Installing the Optic Cable of RRU


4: Fiber / Clamp Installation
All ways ensure that the rubber insulation is installed taking great care. Faste
n the clamps as firmly as possible. It must be installed in a straight line.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 30

Installing the Optic Cable of RRU


5: Fiber entry plate
All ways ensure that the cables are sealed correctly at the entry plate. It need
s to be fed through a coupling. When removing the feeders from the gland plate e
nsure to seal them correctly.
6: Fiber Preparation
Ensure that the optic Fiber is pulled up the tower at the same rate. Do not allo
w it to kink or twist. The fiber needs to be installed in the clamps in a straig
ht line without any twists.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 31

After Photos
Photos
1. 2. 3. 4. 5. Take photos of the installation of the RRUs. Take photos of the Op
tic Cable in the CPRI W position and power cable installation. Take Photos of th
e earth cable. Take photos of the sealing of the fly leads. Take photos of the l
abels.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 32

DBS Hardware Installation


Cabinet Placement
3G expansion will be mostly software license expansion, but if a new cabinet has
to be installed, the second 3G NodeB cabinet will be stacked up on the first 3G
cabinet.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 33

DBS Hardware Installation


1:Move the Node B
Move the Node B forward after it has been loosened from the u rail.
2: Move the U Rail
Move the u rail to fit the template provided.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 34

DBS Hardware Installation


3: 3G Cabinet Installation
Before installing the cabinet make sure that the grid are installed correctly an
d firmly as specified by the site supervisor and as per photo.
4: 3G Cabinet Installation
After assembling the cabinet according to the assembly instructions. Place the c
abinet in the correct position as specified by the Site Supervisor and site inst
allation standard. Ensure that the cabinet is fastened securely to the C Profile
.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Page 35

DBS Hardware Installation


5: CB Connection
Connect the power cable in the correct manner to the CB. Always double check ele
ctrical installations.
6: Cable routing inside DB Board
Routing to be done neatly and according to the electrical specifications. Use th
e correct tools when working on the DB board.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 36

DBS Hardware Installation


7: Cable routing inside trunking
Rooting to be done neatly and according to the electrical specifications.
8: Cable routing
Routing to be done neatly and according to the electrical specifications. Route
it neatly down the cable tray in the correct position.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 37

DBS Hardware Installation


9: OT Connection
Clean the wire correctly. Place the correct lug 25mm Power Cable. Use the correc
t crimping tool and crimp the lug and pull for security. No exses copper wire ma
y be seen.
10: Connection safe
Use the black heat shrink to secure and cover the open connections.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 38

DBS Hardware Installation


Equipment Placement

Install the equipment according to the placement indicated in the Photo. BBU ins
tallation of DBS NodeB DBS rack has 10U space. BBU3900 will occupy 2U space and
DC box will occupy another 1U space. 5U space can be used future expansion. indi
cates the BBU installation position or as specified by the standards.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 39

DBS Hardware Installation


HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 40

DBS Hardware Installation


Power Cable
Connect the OT terminal of the power cable to the LOAD7 or 8 (6amp) terminal on
the DCDU, and then fix the 3W3 connector of the power cable to the PWR port on t
he BBU
Load 7 or 8
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 41

DBS Hardware Installation


Install the CPRI optical cable
Connect one end of the optical cable to the CPRI0, CPRI1, or CPRI2 port on the G
TMU panel of the BBU and the other end to the CPRI_W port on the RRU.
Insert the
optical module into the CPRI0, CPRI1, or CPRI2 port, and then turn outwards the
puller on the optical module. Insert one end of the CPRI optical cable into the
optical module, and then lead the CPRI optical cable out of the cabinet along t
he right side of the cabinet.
Wrap the fiber tail with the winding pipe. The TX
port on the BBU is connected to the RX port on the RRU; the RX port on the BBU i
s connected to the TX port on the RRU
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 42

After Photos
Photos
1. 2. 3. 4. 5. Take photos of the position of the cabinet. Take photo of the equ
ipment. Take photo of the power connection. Take photo of the RRU power connecti
on. Take photo of the BBU optic cable connection.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 43

E1 Installation
Install the E1
Connect one end of the E1 cable to the E1/T1 port on the GTMU, and
other end out of the cabinet along the right side of the cabinet.
connector of the E1 cable to the E1/T1 port on the GTMU. Take note
G installations 2E1 Cables are required at all times. Make sure that
ied.
E1 Cable
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 44

then lead the


Fix the DB26
that on the 3
it is suppl

E1 Installation
1.Strip the jacket off the E1 cable near the grounding point at the lower right
corner of the cabinet to expose the shielding layer. 2.Thread the E1 cable throu
gh the grounding clip. Then, tighten the screw on the grounding clip to make the
shielding layer of the E1 cable in full contact with the grounding clip. Finall
y, connect the grounding cable on the grounding clip to the grounding screw on t
he cage.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 45

E1 Installation
E1 Installation
Ensure that the connection is done correctly and to the correct Krone Block acco
rding to the connection diagram.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 46

2G hardware Installation
Cabinet Placement
1. 2G expansion cabinet will be stacked on the first 2G BTS cabinet. In the scen
ario the two 2G BTS cabinets cant meet the requirement of huge capacity expansion
, the third 2G cabinet will be near the 3G Node B.
2.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 47

2G hardware Installation
Possible Installation
1. 2G installation could be stacked one on top of the first cabinet.
2. shows the cabinet position. The 150mmdistance shall be remaining for heat loa
ding and easyoperation of future cabinet expansion.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 48

2G hardware Installation
1: Free Equipment
Un fasten all ancor screws on the equipment specified to be swapped.
2: Free B mons
Un fasten the B mons and pull away from the mounting grid.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 49

2G hardware Installation
3: Move Equipment
Pull the equipment away from the wall and of the U rails.
4: U rail Installation
Place the template on the U rails and fasten the U rails to the floor.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 50

2G hardware Installation
5: Base plate Installation
Place the BTS base plate on the U rail and secure it tightly with the correct bo
lts supplied are the correct torque.
6: Wire Grid
Fit the grid against the wall as specified with all swaps.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 51

2G hardware Installation
7: BTS Placement
Place the BTS 3900 on the base plate.
8: Cable routing
Run the power cables to the DB board secure the cables according to the specific
ation for installation of a CB. Do not use the cable indiscriminately and measur
e the correct length before cutting.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 52

2G hardware Installation
9: CB Connection
Connect the power cable in the correct manner. Always double check electrical in
stallations.
10: Power Cable Routing
Routing to be done neatly and according to the electrical specifications. Use th
e correct tools when working on the DB board.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 53

2G hardware Installation
11 : OT Connection
Clean the wire correctly. Place the correct lug 25mm Power Cable. Use the correc
t crimping tool and crimp the lug and pull for security. No exes copperware may
be seen.
12: Connection Safe
Use the black heat shrink to secure and cover the open connections.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 54

2G hardware Installation
13: Routing
Do not bend the cables to tight around the sharp edges of the cabinet.
14:DCDU Power
Connect the power to the DCDU securely and according to the specification.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 55

2G hardware Installation
15 a: 2G BBU
Continue with the power connections until all is correctly completed. Switch the
power on in the correct sequence.
15 b: 3G BBU
Continue with the power connections until all is correctly completed. Switch the
power on in the correct sequence.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 56

2G Hardware Installation
16: a Install the EMUA monitoring signal cable
If the MON1 port on the BBU is available, fix the RJ45 connector of the EMUA mon
itoring signal cable to the MON1 port on the UPEU and the DB9 connector to the c
orresponding port on the EMUA.
BBU
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 57

2G Hardware Installation
16: b Alarm cables
Connect the alarm cable as in the photo. Connect connector 1,2,3 and 4 for as fo
llow.
1: in Ext Alm 0 2: in Ext Alm 1 3: in Ext Alm 2 4: in Ext Alm 3
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 58

2G hardware Installation
17: Jumper Installation for BTS
On certain sites, the indoor jumper will be between BTS and combiner, while some
sites the jumper directly connects BTS with B mon. The actual connection and ju
mper length will be decided based on survey result.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 59

2G hardware Installation
Connector Type
(A) Connector of Feeder/Bom/Combiner
DIN-7/16-Straight-Female
(B) Connector of jumper
DIN-7/16-Straight-Male.
(C) Connector of BTS/NodeB
DIN-7/16-Female
(D) Connector of jumper
DIN-7/16-Right Angle-Male.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 60

2G hardware Installation
18: RF Connection
Ensure that the tools used are correct or calibrated to spec to ensure that the
connectors will be assembled correctly. Do the connection on the BTS side first.
Double check that the length is correct before cutting the Rf cable. Place the
connectors on the Radios and do the feed to the Bmons to secure position.
19: RF Connection
Now do the B mon side of the RF connection. Ensure that the tools used are corre
ct or calibrated to spec to ensure that the connectors will be assembled correct
ly.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 61

2G hardware Installation
20:Preperation
The Cut and clean must be done correctly. This will ensure that the connection o
f the connector is done correct the first time.
21: Connector assembly
Place the connector firmly on the RF cable. Screw it in clock wise about three t
urns. Feel connector should be firmly in place.
22: Connector Secure
Tighten the nut in the back of the connector. Then tighten the locknut. The conn
ector should be firm.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 62

2G hardware Installation
23: Sweep Preparation
Now you power down the equipment and loosen the RF connectors.
24: Equipment Movement
Remove the equipment from the container. Do not damage any equipment at any stag
e.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 63

2G hardware Installation
25: Before Sweeps
Do the sweeps of the old equipment and save every sweep.
26: Old RF Disconnect
Disconnect the old RF cables at the B mon side after the sweeps are complete.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 64

2G hardware Installation
27: New RF Connection
Connect the new RF cables to the B mon.
28: After Sweeps
After the connectors had been torque do the sweeps again to ensure correct insta
llation. Save the Before and after sweeps as this must be handed in with the Sit
e File.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 65

2G hardware Installation
29: Power on Radios
Ensure that the connector torques are done at the radio side. Then switch the ra
dios on from sector 0 1 2.
30:Alarm Cable
Make sure that the alarm cable connection on the EMUA has been don correctly. Co
nnect the alarm cables to the existing plugs and correct connection will be veri
fied as soon as the alarms are tested.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 66

3G TMA hardware Installation


Fly lead Connection
None of the existing TMAs will be re-used, the connectors of new TMAs will also be
Female and the existing outdoor jumper will be re-used.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 67

3G TMA hardware Installation


Connector Type
(A) Connector of jumper (antenna side)
DIN-7/16-Straight-Male
(B) Connector of TMA (antenna side)
DIN-7/16-Female
(C) Connector of TMA (Equipment side)
DIN-7/16-Female
(D) Connector of jumper(Equipment side)
DIN-7/16-Straight-Male.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 68

3G TMA hardware Installation


1: Waterproof and Airproof for outdoor connector
Installation team should apply the waterproofing and airproof treatment to the o
utdoor connectors immediately after the installation.
2:Materials:
1. PVC insulation tape; 2. Rubber tape (3M 1.6mm*50mm rubber tape or Bishop [Ply
mouth] 1.65mm*51mm rubber tape)
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 69

3G TMA hardware Installation


3: Installation specification
1. Clean the feeder and connectors. 2. Wrap 2 layers of PVC tape before wrapping
the waterproof tape for the convenience of removing the tapes. 3. Uncoil the wa
terproof-insulating tape. Stick the end of the tape to the feeder at the point 2
to 5 cm above the connector. Note that the glued side should face the feeder. 4
. Stretch the tape until it is as 3/4 to 1/2 wide as its original shape. Make su
re that the stretched width is at least 1/2 of the original width, otherwise ove
r-stretching may damage the molecular structure of the tape and lower its reliab
ility. 5. Wrap up the feeder spirally upward while maintaining this stretching s
trength. Make sure that the overlapping area of adjacent tape layers is 1/2 of t
he stretched width, as shown below. 6. When wrapping to the point 2 to 5 cm unde
r the connector, reverse the direction to let the wrapping goes back towards sta
rting point. In this way, the feeder is wrapped up with 2 layers of waterproof t
ape. 7. After wrapping, squeeze the tape stuck to the feeder to make sure no air
remains between the tape layers. 8. After wrapping the waterproof-insulating ta
pe, it is necessary to wrap it up with PVC tape to prevent the wearing and aging
of the waterproof-insulating tape. 9. The wrapping of PVC tape is similar to th
at of waterproof-insulating tape. Start wrapping spirally upward with 1/2 width
of overlapping between adjacent layers. Reserve the wrapping direction to make 2
layer PVC tape cover. Make sure to maintain the stretching strength.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 70

Labels
Ensure that the labeling on the B mons are fitted and correct.
Ensure that the Labeling on the Radios are fitted and correct.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 71

Labels
Ensure that the labels leading into the DB Board are done and correct.
Ensure that the labels on the PDCA is done and correct on the DBS side.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 72

Labels
Ensure the labels are correct and fitted at the Power connection at the cabinet.
Ensure the labels are correct and fitted on the optics.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 73

Thank you
www.huawei.com