Objectives
Master the features of the Equipment
Reference
Huawei DBS Hardware Installation
RRU User Gu
LEDs on RRUs
Label Color Status Description
RUN
Green
ON
OFF 1s on, 2s off 0.5s on, 0.5s off
The module has power input, yet the module is faulty
The module has no power input or is reporting alarms The module is operational S
oftware is being loaded to the module The module is reporting alarms (excluding
VSWRrelated alarms The module is operational The module is running No specific m
eaning
ALM
Red
ON OFF
TX_ACT
Green
ON OFF
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 7
RRU Installation
RRU hardware installation consists of:
Installing three RRUs
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 9
RRU Installation
Installation of RRU
1. The RRU replaces the TMAs 2. Use existing fly leads from Ant to TMAs 3. Ensure
using a torque wrench to connect the fly leads to RRs 4. Use existing Labels on f
ly leads 5. Connect the power cable supplied to each RRU 6. Connect the Optical
cable supplied to CPRI W port
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 10
RRU Installation
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 11
RRU Installation
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 12
After Photos
Photos
1. 2. 3. 4. 5. Take photos of the installation of the RRUs. Take photos of the Op
tic Cable in the CPRI W position and power cable installation. Take Photos of th
e earth cable. Take photos of the sealing of the fly leads. Take photos of the l
abels.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 32
Install the equipment according to the placement indicated in the Photo. BBU ins
tallation of DBS NodeB DBS rack has 10U space. BBU3900 will occupy 2U space and
DC box will occupy another 1U space. 5U space can be used future expansion. indi
cates the BBU installation position or as specified by the standards.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 39
After Photos
Photos
1. 2. 3. 4. 5. Take photos of the position of the cabinet. Take photo of the equ
ipment. Take photo of the power connection. Take photo of the RRU power connecti
on. Take photo of the BBU optic cable connection.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 43
E1 Installation
Install the E1
Connect one end of the E1 cable to the E1/T1 port on the GTMU, and
other end out of the cabinet along the right side of the cabinet.
connector of the E1 cable to the E1/T1 port on the GTMU. Take note
G installations 2E1 Cables are required at all times. Make sure that
ied.
E1 Cable
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 44
E1 Installation
1.Strip the jacket off the E1 cable near the grounding point at the lower right
corner of the cabinet to expose the shielding layer. 2.Thread the E1 cable throu
gh the grounding clip. Then, tighten the screw on the grounding clip to make the
shielding layer of the E1 cable in full contact with the grounding clip. Finall
y, connect the grounding cable on the grounding clip to the grounding screw on t
he cage.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 45
E1 Installation
E1 Installation
Ensure that the connection is done correctly and to the correct Krone Block acco
rding to the connection diagram.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 46
2G hardware Installation
Cabinet Placement
1. 2G expansion cabinet will be stacked on the first 2G BTS cabinet. In the scen
ario the two 2G BTS cabinets cant meet the requirement of huge capacity expansion
, the third 2G cabinet will be near the 3G Node B.
2.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 47
2G hardware Installation
Possible Installation
1. 2G installation could be stacked one on top of the first cabinet.
2. shows the cabinet position. The 150mmdistance shall be remaining for heat loa
ding and easyoperation of future cabinet expansion.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 48
2G hardware Installation
1: Free Equipment
Un fasten all ancor screws on the equipment specified to be swapped.
2: Free B mons
Un fasten the B mons and pull away from the mounting grid.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 49
2G hardware Installation
3: Move Equipment
Pull the equipment away from the wall and of the U rails.
4: U rail Installation
Place the template on the U rails and fasten the U rails to the floor.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 50
2G hardware Installation
5: Base plate Installation
Place the BTS base plate on the U rail and secure it tightly with the correct bo
lts supplied are the correct torque.
6: Wire Grid
Fit the grid against the wall as specified with all swaps.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 51
2G hardware Installation
7: BTS Placement
Place the BTS 3900 on the base plate.
8: Cable routing
Run the power cables to the DB board secure the cables according to the specific
ation for installation of a CB. Do not use the cable indiscriminately and measur
e the correct length before cutting.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 52
2G hardware Installation
9: CB Connection
Connect the power cable in the correct manner. Always double check electrical in
stallations.
10: Power Cable Routing
Routing to be done neatly and according to the electrical specifications. Use th
e correct tools when working on the DB board.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 53
2G hardware Installation
11 : OT Connection
Clean the wire correctly. Place the correct lug 25mm Power Cable. Use the correc
t crimping tool and crimp the lug and pull for security. No exes copperware may
be seen.
12: Connection Safe
Use the black heat shrink to secure and cover the open connections.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 54
2G hardware Installation
13: Routing
Do not bend the cables to tight around the sharp edges of the cabinet.
14:DCDU Power
Connect the power to the DCDU securely and according to the specification.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 55
2G hardware Installation
15 a: 2G BBU
Continue with the power connections until all is correctly completed. Switch the
power on in the correct sequence.
15 b: 3G BBU
Continue with the power connections until all is correctly completed. Switch the
power on in the correct sequence.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 56
2G Hardware Installation
16: a Install the EMUA monitoring signal cable
If the MON1 port on the BBU is available, fix the RJ45 connector of the EMUA mon
itoring signal cable to the MON1 port on the UPEU and the DB9 connector to the c
orresponding port on the EMUA.
BBU
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 57
2G Hardware Installation
16: b Alarm cables
Connect the alarm cable as in the photo. Connect connector 1,2,3 and 4 for as fo
llow.
1: in Ext Alm 0 2: in Ext Alm 1 3: in Ext Alm 2 4: in Ext Alm 3
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 58
2G hardware Installation
17: Jumper Installation for BTS
On certain sites, the indoor jumper will be between BTS and combiner, while some
sites the jumper directly connects BTS with B mon. The actual connection and ju
mper length will be decided based on survey result.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 59
2G hardware Installation
Connector Type
(A) Connector of Feeder/Bom/Combiner
DIN-7/16-Straight-Female
(B) Connector of jumper
DIN-7/16-Straight-Male.
(C) Connector of BTS/NodeB
DIN-7/16-Female
(D) Connector of jumper
DIN-7/16-Right Angle-Male.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 60
2G hardware Installation
18: RF Connection
Ensure that the tools used are correct or calibrated to spec to ensure that the
connectors will be assembled correctly. Do the connection on the BTS side first.
Double check that the length is correct before cutting the Rf cable. Place the
connectors on the Radios and do the feed to the Bmons to secure position.
19: RF Connection
Now do the B mon side of the RF connection. Ensure that the tools used are corre
ct or calibrated to spec to ensure that the connectors will be assembled correct
ly.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 61
2G hardware Installation
20:Preperation
The Cut and clean must be done correctly. This will ensure that the connection o
f the connector is done correct the first time.
21: Connector assembly
Place the connector firmly on the RF cable. Screw it in clock wise about three t
urns. Feel connector should be firmly in place.
22: Connector Secure
Tighten the nut in the back of the connector. Then tighten the locknut. The conn
ector should be firm.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 62
2G hardware Installation
23: Sweep Preparation
Now you power down the equipment and loosen the RF connectors.
24: Equipment Movement
Remove the equipment from the container. Do not damage any equipment at any stag
e.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 63
2G hardware Installation
25: Before Sweeps
Do the sweeps of the old equipment and save every sweep.
26: Old RF Disconnect
Disconnect the old RF cables at the B mon side after the sweeps are complete.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 64
2G hardware Installation
27: New RF Connection
Connect the new RF cables to the B mon.
28: After Sweeps
After the connectors had been torque do the sweeps again to ensure correct insta
llation. Save the Before and after sweeps as this must be handed in with the Sit
e File.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 65
2G hardware Installation
29: Power on Radios
Ensure that the connector torques are done at the radio side. Then switch the ra
dios on from sector 0 1 2.
30:Alarm Cable
Make sure that the alarm cable connection on the EMUA has been don correctly. Co
nnect the alarm cables to the existing plugs and correct connection will be veri
fied as soon as the alarms are tested.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 66
Labels
Ensure that the labeling on the B mons are fitted and correct.
Ensure that the Labeling on the Radios are fitted and correct.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 71
Labels
Ensure that the labels leading into the DB Board are done and correct.
Ensure that the labels on the PDCA is done and correct on the DBS side.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 72
Labels
Ensure the labels are correct and fitted at the Power connection at the cabinet.
Ensure the labels are correct and fitted on the optics.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 73
Thank you