Beruflich Dokumente
Kultur Dokumente
Residential morcellement at
Gros Billot New Grove
District of Grand-Port
Rose Belle Sugar Estate Board
Morcellement Layout
APRIL 2014
Annex B
Residential morcellement at
Gros Billot New Grove
District of Grand-Port
Rose Belle Sugar Estate Board
Title Deed
APRIL 2014
Annex C
Residential morcellement at
Gros Billot New Grove
District of Grand-Port
Rose Belle Sugar Estate Board
Land Conversion Permit
APRIL 2014
Annex D
Residential morcellement at
Gros Billot New Grove
District of Grand-Port
Rose Belle Sugar Estate Board
Engineering Report
APRIL 2014
CONTENTS
PART A: GEOTECHNICAL SURVEY
Page
A1
SUMMARY
A2
SITE GEOLOGY
A3
SITE LOCATION
A4
A5
SOIL STRATIGRAPHY
A6
CONCLUSION
INTRODUCTION
B2
B3
RESULTS
B4
CONCLUSION
INTRODUCTION
11
C2
11
C3
11
WATER DEMAND
12
D2
RETICULATION
12
INTRODUCTION
13
E2
RETURN PERIODS
13
E3
HYDROLOGICAL ANALYSIS
14
E4
PARAMETER (ARF)
18
E5
PERMISSIBLE VELOCITY
18
E6
SIZING OF DRAIN
18
E7
COMPUTATIONS
19
ANNEXURES
ANNEXURE 1: SEPTIC TANK DETAILS
II
III
IV
IV
SUMMARY
A geotechnical survey was undertaken on the site earmarked for development with a
view to:
(a) identify the geological characteristics of the site
(b) assess the soil geomorphology
(c) identify any geological failures or issues including high water table
(d) identify solutions, if any, in case of problems
The tests and terminologies used as part of this report are in accordance with BS 1377:
1990 and BS 5930: 1999.
A2.
SITE GEOLOGY
Except for some consolidated coral and shell debris in isolated remnant raised beaches,
and the coral reefs and beach and sand dunes around most of the coast, Mauritius is
entirely volcanic. Simpson recognised an Older volcanic series and a younger volcanic
series between which there was a long period of erosion. The younger volcanic series
was subdivided into the Early and Late Lavas.
The project site located in the region of New Grove originates from the intermediate
lavas of the Younger Volcanic Series. These rocks deposited from lava flows and are
generally vesicular olivine fine-grained basalt and are usually grey to dark in colour. The
site geology is indicated by FAO/MSIRI map as indicated below:
A3.
SITE LOCATION
The proposed site for development is found at Gros Billot, New Grove. The site is
predominantly covered by sugarcane cultivation and partly covered by bushes. Site
visits have revealed that the site does not accommodate any endangered flora and is not
classified as an ESA (Environmentally Sensitive Area). No watercourses as classified
under the Rivers and Canals Act. The site topography is relatively flat with plot slopes
varying between 2% and 6%.
A4.
A5.
SOIL STRATIGRAPHY
The stratigraphy is characterised by the topsoil being reddish brown in colour with a
high organic content and numerous roots to a depth of approximately 150mm. Below
150mm, the soil stratigraphy shows firm mottled reddish yellowish brown slightly
sandy silt. Moderately weathered rocks are also witnessed within the different trial pits.
No trace of the water table have been identified and there were no presence of caves.
In light of the soil properties and characteristics, it can be safely assumed that the
allowable bearing capacity would be in the region of 200 kN/m2; a value for than
adequate for construction of residential/low rise commercial buildings.
The was no sign of any caves within the project vicinity and no sign of water was
observed in the trail pits.
A typical soil profile is indicated in the sketch below:
A dark brown in the top-most 300 mm, with a higher organic material content.
A reddish brown silty clayey material layer with a lower organic content which merges
and going down to the bottom of the trail pits.
A parent material beyond the depth of 2.50 m.
A6.
CONCLUSION
Detailed design will involve undertaking laboratory tests in order to assess and
confirm the preliminary geotechnical survey undertaken by digging trial pits. The
laboratory tests undertaken will include:
a. Determination of moisture content
b. Proctor test
c. CBR test
d. Atterberg limit
e. Sieve analysis
The above will enable accurate determination of the soil characteristics during the
pavement structure design. No particular foundation problem are foreseen during
the construction of residential buildings although further investigation will be
necessary and undertaken during the implementation of the morcellement project.
INTRODUCTION
In line with the requirements of the "EIA Guideline for proposed residential morcellement"
published by the Ministry of Environment and Sustainable development, the client,
Rose Belle Sugar Estate Board has commissioned a percolation tests. The
percolation tests were undertaken by SEKA Ltd and received approval from the
Waste Water Management Authority (WMA) in a correspondence dated 09
September 2003 and bearing reference WMA/238/8.
B2.
B3. RESULTS
The results of the percolation tests undertaken together with approval from the
Waste Water Management Authority (WWMA) are shown below.
B4. CONCLUSION
The percolation rate as observed from SEKA report below was found to be above
200 mm/hour. Under the Government Notice published (2nd Schedule) as
indicated below, the soil is highly permeable and an infiltration rate of 50l/m2/d
should be used for dimensioning the absorption pit or leaching field.
10
INTRODUCTION
The proposed site for development is not connected to an existing sewer network.
Waste water emanating from bathrooms, toilets and kitchen waste should therefore
be directed into an on-site waste water disposal system. The above system would be
applicable for all the residential plots.
C2
Typical details of the septic tank are shown at Annexure 1. The septic tank will
consist of three compartment tanks with a design retention period of 2 days to
allow for sedimentation and sludge digestion.
In fact in a correspondence dated 03 September 2003, the Waste Water
Management Authority (WWMA) has approved the septic tank - leaching field
arrangement in light of percolation rates obtained. Typical details of the absorption
pit are found at Annexure 2 and typical details of the leaching field are also shown
at Annexure 3.
C3.
= 0.9m3 = 900L
= 50l/m2/d
= 18m2
The above value in fact corresponds to the 20m2 area recommended by the Waste
Water Management Authority (WWMA) in its letter dated 03 September 2003.
11
WATER DEMAND
The water demand for the project site will be as follows:
No of residential plots
Water consumption per capita
Assuming 5 persons per dwelling,
Water consumption for residential plots per day
= 155
= 200L/capita/day
= 155 x 5 x 200
= 155,000L
= 155 m 3
D2.
= 10m 3
= 165 m 3
RETICULATION
Liaison and meetings will be required with the Central Water Authority (CWA) in
order to assess the connection point for the proposed morcellement. The design of
the internal water reticulation network will be finalised with the CWA upon issue of
the Letter of Intent (LOI) from the Morcellement Board. The following will be
taken into consideration during the design of the potable water reticulation
network:
a. Pipes will be routes within the road reserves
b. All pipes will be HDPE type
c. House connections will be 20mm pipes
d. Maximum velocity in pipes will be limited to 1.5m/s
e. Minimum pressure at household will be 1 bar
f. Pipes will be connected using electrofusion process as indicated below:
12
INTRODUCTION
An adequate storm water drainage network is required in order to channel surface
run off so as to minimise or eliminate damages which may be caused by such
surface run off. In the above scenario, the change of land use from a site previously
under shrubs and bushes to a residential area is likely to increase the surface run
off.
E2.
RETURN PERIODS
As a normal practice, the areas for major catchments have been determined using
the survey sheets of scale 1:25000 with 10m contour lines. However, since the
catchment areas attributed to the sites under study are relatively small and
localised, survey sheets of scale 1:2500 have been used to delimitate the
different
catchment
areas supplemented by necessary field surveys. The
direction of the surface runoff has been determined by the visual inspection of the
topography for the different sites.
Intensity (mm/min)
R a in f a ll I n t e n s it y ( m m / m in ) - R e t u r n P e r io d
13
Duration (minutes)
Return
Period
(Years)
10
15
30
60
120
T2
2.0868
1.7155
1.4153
1.1550
0.9354 0.6354
0.3699
T5
2.9185
2.2616
1.8416
1.4519
1.2297 0.9388
0.6126
T10
3.4693
2.6232
2.1239
1.6483
1.4246 1.1236
0.7733
T25
4.1650
3.0800
2.4805
1.8967
1.6709 1.3577
0.9763
T50
4.6812
3.4190
2.7450
2.0809
1.8536 1.5305
1.1269
T100
5.1936 3.7554 3.0076
(Source: Mauritius Meteorological Service)
2.2637
2.0349 1.7025
1.2764
(years)
10
10
25
50
HYDROLOGICAL ANALYSIS
As in Mauritius, most of the catchments under consideration are small and not
gauged, standard procedures for use on ungauged catchments have been used for
hydrological analysis.
14
A number of methods exist to estimate design flood discharge, the most popular
ones being the Rational Method, Generalised Tropical Flood Method and SCS-UH
Hydrograph Method.
However, since only relatively small catchment areas are being considered, the
Rational Method was found to be the most appropriate one and has been adopted
for the study.
The modified rational formula is:
where:
: Discharge (m3/s) for return period of T years
: Runoff coefficient for return period of T years
: Intensity (mm/hr) for return period of T years
ARF
Parameter
, the run-off coefficient relates to three parameters namely slope, soil
permeability and land use contained in the equation below:
where
are listed
in Table D1:
Return period / years
value
0.50
0.55
10
0.60
25
0.70
50
0.83
100
1.00
Table D1:
values
is the
The above coefficients would normally apply for relatively large catchment areas
incorporating both built up and undeveloped portions. The value of
incorporates three elements relating to topography (
vegetation
in turn
, permeability
and
Mean
catchment
slope
Classification
< 600
600 - 900
> 900
Less than 3%
Marsh/wetland
0.01
0.03
0.05
3% to 10%
Flat
0.06
0.08
0.11
10% to 30%
Hilly
0.12
0.16
0.20
Steep
0.22
0.26
0.30
Table D2:
Classification
< 600
0.03
0.06
0.12
0.21
Very permeable
Permeable
Semi permeable
Impermeable
Table D3:
values
values for different mean
annual precipitation (mm)
600 - 900
0.04
0.08
0.16
0.26
> 900
0.05
0.10
0.20
0.30
values
Classification
< 600
600-900
> 900
0.03
0.04
0.05
0.07
0.1
0.15
Sugarcane
0.17
0.2
0.25
No vegetation
0.26
0.28
0.30
Table D4:
The values of
the value of
and
values
where
= 0.5
16
For a duration
t < 1hr
I R t 0.29
t > 1hr
I R t 0.49
The value of R depends on the selected return period as shown in Table D5:
Return period / years
value
33
53
10
66
25
90
50
111
100
140
Table D5: R value
In the Rational Method, the storm rainfall is assumed to have a duration equal to
the catchment time of concentration,
is
substituted for t in the above equations for rainfall intensity. Different formulae
are available for calculating the time of concentration. A common formula is the
Bransby-Williams formula:
where
The above formula may give relatively small time of concentration, thus resulting
in very large rainfall intensity which may adversely affect the drain sizing. Hence
the rainfall intensity may be modified based on local experience or by altering the
formula used for calculating the rainfall intensity.
17
E4.
PARAMETER ARF
The area reducing factor (ARF) is introduced when large areas are considered.
This particular factor is introduced to take into account the fact that rainfall
intensity may not be same over vast extents. In the scenario considered, the area
can be assumed to be small and no ARF was considered.
E5.
PERMISSIBLE VELOCITY
The storm water flowing within the roadside drain should have a minimum slope,
normally 0.5% to ensure a self cleansing velocity of 0.75m/s. The threshold self
cleansing velocity depends on the type of material used for the size of drain.
Typical permissible velocities and manning's coefficients (roughness) are listed in
Table D6:
Material
Manning's
coefficient
Concrete
0.015
4.0 - 6.0
0.025
2.0 - 3.0
Gabions
0.030
2.0 - 3.0
Earth drain
0.035
1.8 - 2.0
Natural stream
0.050
1.8 - 2.0
SIZING OF DRAIN
In order to determine the size of drain, the carrying capacity of the drain should be
calculated assuming a drain size i.e 500mm
project.
18
for
the area under consideration, the drain size can be assumed to be adequate.
E7.
COMPUTATIONS
Based on the above information, the following were calculated:
= 0.082 m3/s
For the proposed 500mm by 500mm drain within the proposed morcellement, the
carrying capacity is calculated as follows:
= 0.357 m3/s
Given the carrying capacity of the drain exceeds the peak discharge, the drain size can be
considered as acceptable. The following annexures provide more information on the storm
water drainage network proposed:
Annexure 4 - Preliminary storm water drainage network
Annexure 5 - Typical roadside drain section
Annexure 6 - Typical soakaway pit details
19
ANNEXURE 1
SEPTIC TANK DETAILS
20
ANNEXURE 2
ABSORPTION PIT
21
ANNEXURE 3
LEACHING FIELD
22
ANNEXURE 4
PROPOSED STORM WATER DRAINAGE
23
ANNEXURE 5
ROADSIDE DRAIN SECTION
24
ANNEXURE 6
SOAKAWAY ABSORPTION PIT
25
Annex E
Residential morcellement at
Gros Billot New Grove
District of Grand-Port
Rose Belle Sugar Estate Board
Site Zoning
APRIL 2014