Beruflich Dokumente
Kultur Dokumente
an Updated P6 Schedule
JUNE 28, 2013 BY SEAN CAIN 17 COMMENTS
By selecting the F9 key or the Schedule hot key the Schedule dialog box will appear. There is a
Log to File function that creates a summary level report from the current project. The Log to File
box must be checked and a location for the file needs to be mapped by selecting the browse
button (box with four dots). If a log file has not been run in the current database a Specify Log
File dialog box will appear. To create the log select YES in the dialog box if prompted. See
graphics below.
Map and name the Log file to the desktop or a specific drive.
NOTE: This report should be run every time an update is done (i.e. weekly or monthly).
After running and printing the report each out of sequence activity should be reviewed and
corrected (if possible). Depending on the project there can be several different types of Out of
Sequence Progress occurring and each may have a specific solution.
After approval of the baseline schedule and the start of updating the project schedules, the
projects logic can always change depending on what is being installed in the field. In this
instance, the logic has changed and the Lighting Conduit Col 15-21 is now actually starting first,
but the existing logic (from the baseline) remains the same and is causing Out of Sequence
Progress by pushing out the Lighting Conduit Col 15-21 end date incorrectly. See the graphic
below.
By removing the Lighting Conduit Col 7-15 as a predecessor and making it a successor to
Lighting Conduit 15-21 the Out of Sequence Progress has been eliminated and the logic is now
modeling what is taking place in the field. However, in doing this, the Lighting Conduit 15-21 no
longer has a Predecessor tie and cannot be left this way. A properly statused activity that
logically precedes the Lighting Conduit Col 15-21 will need to be tied as a proper predecessor.
Open ends on installation activities are not acceptable.
With the logic changed and the Out of Sequence progress resolved, the relationship between the
two activities now looks like the graphic below.
Conclusion
As shown in the examples above, most out of sequence progress can be resolved, but where it
cannot, or more importantly, where it should be retained, it should be communicated to all parties
involved in the schedule clearly.
Out of sequence progress can be inevitable due to changing conditions on the project site, but
how it is handled during the life cycle of the CPM schedule is the more important aspect.
Reviewing the accuracy of the schedule logic against the sequence of the installation work in the
field is the key and the logic should be analyzed during every update period. Whenever logic has
been revised from the baseline plan it should be noted in a monthly schedule narrative or a letter
to the owner/general contractor specifying all logic changes. If schedule logic is continuously
revised each update period to reflect the sequence of work in the field a full schedule review
might be warranted to determine if a re-baseline plan is needed.
Comments
1.
Mahmoud says
June 29, 2013 at 6:16 am
good lesson Sean, but the third example in not clear..
Reply
2.
3.
4.
comparing your current update to the baseline schedule to see if there has
been a delay issue. Out-of-sequence logic does not necessarily cause
negative float but, it can use up available float very easily and the more out-ofsequence logic you have the more issues you will have with incorrect forecast
dates and less available float for all the activities tied to the out-of-sequence
(in question).
Reply
5.
GfreddieK says
July 7, 2013 at 8:19 am
In correcting the logic of the Out of Sequence activities, do you change the
scheduling option from Retained Logic to Progress Overide? or you just keep
it Retained Logic until the project is done.
Reply
6.
7.
tajamal says
September 10, 2013 at 9:45 am
while updating the schedule the predecessor completed before its planned
finish date , n this completion have no effect on successor whose start data is
behind the data date .
as in my opinion successor should take the data date as the start date bcz the
predecessor is completed before the its planned finish date.
plz reply Mr. Sean Cain
Reply
8.
9.
Reply
10.
11.
Any delay notices should be based off the update, although you can also show
delays in a copy of the baseline for some forms of delay analysis.
Reply
12.
13.
jumana says
14.
Running says
October 26, 2015 at 11:05 pm
Hey would you mind letting me know which webhost youre using? Ive loaded
your blog in 3 completely different browsers and I must say this blog loads a
lot quicker then most. Can you suggest a good internet hosting provider at a
reasonable price? Thanks, I appreciate it!
Finely processed New Balance Blue Fluorescent Yellow
Runninghttp://www.jccwebb.co.uk/images/config.php?Super-discount-NewBalance-Blue-Fluorescent-Yellow-Running-t-5855_354.html
Reply
15.
Eric says
16.
youssef says