ID

1
2
3
4
5
6
7
8
9

10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

Task Name

CATCH-UP SCHEDULE
PHQ
Preparation of As-Built Plans (PEO for
Review)
Chipping of crack surface
Work request
Concreting works
Site preparation for the concreting
Application of bonding epoxy
Concrete Pouring
Concrete Testing
Final Inspection and acceptance
Closing of punchlists and acceptance

Start

Finish

Mon 08/08/16

Thu 13/10/16

Mon 08/08/16

Mon 15/08/16

Mon 08/08/16

Sun 14/08/16

Mon 15/08/16

Tue 23/08/16

Mon 15/08/16
Tue 16/08/16
Tue 16/08/16
Tue 23/08/16

Tue 23/08/16
Tue 23/08/16

Billing
Billing Documents
Final acceptance (After 1 year)
Cert. of completion and Acceptance
Request for release of retention
BAYBAY
PCCP @ Sta. 0+360 to 0+420
Subbase course correction works and
compaction
Formworks installation
Concreting works
Concrete Testing
Line Canal
Excavation works (completed)
Boulder laying and plastering
Expansion of existing Box culvert
Submission and approval of drawings

Sat 27/08/16

Sat 27/08/16

Fri 26/08/16

Fri 26/08/16

Fri 26/08/16

Mon 15/08/16

Mon 15/08/16

Sat 27/08/16

Tue 16/08/16

Wed 17/08/16

Wed 17/08/16

Wed 17/08/16

Thu 25/08/16

Thu 25/08/16

Mon 15/08/16
Mon 15/08/16

Wed 07/09/16

53

Wed 07/09/16
Concreting of Gutter
Fri 26/08/16
Chipping of existing box culvert
(Downstream)
Rebars and fomworks installation (slab) Fri 02/09/16

54

Concreting of slab

Mon 05/09/16

Mon 05/09/16

56

Concreting of walls and top slab


Rebars and forms installation (Gutter)

Sat 10/09/16

Sat 10/09/16

Tue 13/09/16

Tue 13/09/16

Project: Catch-up schedule


Date: Wed 24/08/16

12 Sep '16
M
T
W

19 Sep '16
M
T
W

Tue 30/08/16

Mon 05/09/16

Tue 06/09/16
Sun 11/09/16

Wed 14/09/16

26 Sep '16
M
T
W

Thu 25/08/16
Sun 28/08/16
Sat 03/09/16

Tue 06/09/16
Thu 01/09/16
Sun 04/09/16
Fri 09/09/16

Mon 12/09/16
Thu 22/09/16

Task

Summary

Inactive Milestone

Duration-only

Start-only

External Milestone

Baseline Milestone

Milestone

Inactive Task

Manual Task

Manual Summary

External Tasks

Baseline

Progress

Split

Wed 17/08/16

51

Concreting of Gutter
Slope protection

Tue 13/09/16

Sun 04/09/16

59

05 Sep '16
M
T
W

Mon 15/08/16Thu 15/09/16

Sun 04/09/16

58

Mon 15/08/16Thu 15/09/16

Concreting of walls and top slab


Rebars and forms installation (Gutter)

57

Thu 18/08/16

49

Rebars and forms installation (wall and top


slab)

Thu 25/08/16

Mon 29/08/16

55

Sat 27/08/16

Mon 29/08/16

52

29 Aug '16
M
T
W

Fri 26/08/16

Concreting of slab

50

Fri 26/08/16

47

Rebars and forms installation (wall and top


slab)

Fri 26/08/16

46
48

Tue 16/08/16

Thu 18/08/16

45

Mon 15/08/16

Tue 16/08/16
Purchase of Reinforcing bars and
formworks
Thu 18/08/16
Chipping of existing box culvert
(Upstream)
Rebars and fomworks installation (slab) Fri 26/08/16

44

22 Aug '16
M
T
W

Mon 15/08/16

Thu 13/10/16

Thu 18/08/16

Mon 15/08/16

Mon 15/08/16
Tue 16/08/16

Fri 26/08/16

Sun 14/08/16

Tue 23/08/16

Fri 26/08/16

Sat 27/08/16

Tue 23/08/16

Fri 26/08/16

Fri 12/08/16

Tue 16/08/16

15 Aug '16
M
T
W

Tue 23/08/16

Tue 23/08/16

Tue 16/08/16

Tue 16/08/16

Tue 23/08/16

Mon 15/08/16

Tue 16/08/16

Fri 26/08/16

Sun 14/08/16

Mon 15/08/16

Tue 23/08/16

Fri 12/08/16

Mon 15/08/16

Final Billing
Billing Documents (Submission)
Final Acceptance (After 1 year)
Cert. of completion and Acceptance
Request for release of retention
MALINGAO
As-Built Plans (Submitted to PEO for
Review)
Punchlists works
Backfilling on sides of line canal
Backfilling on end of PCCP
Remove excess shoulder materials
Compaction of shouldering
Hairline crack repair and pockmarks
Final inspection and acceptance
Closing of punchlists and acceptance

Tue 23/08/16

08 Aug '16
M
T
W

Fri 26/08/16

Mon 08/08/16
Mon 15/08/16

Project Summary

Inactive Summary

Manual Summary Rollup

Finish-only

Page 1

Deadline

Baseline Summary

Manual Progress

03 Oct '16
M
T
W

10 Oct '16
M
T
W

17 Oct '16

ID

60
61
62
63
64
65
66

Task Name

Start

Wed 14/09/16
Grouted rockwall (wing wall)
Approach slab - Sta. 0+348 to 0+380 (R/S) Fri 23/09/16

Agg. Subbase preparation and FDT


Formworks installation
Concreting works
Concrete Testing
Approach slab - Sta. 0+348 to 0+380 (L/S)

67

Agg. Subbase preparation and FDT

68

Formworks installation
Concreting works
Concrete Testing
TANGKAL (PANTAON AREA)
Sta. 6+620 to 6+740 L/S
Agg. Subbase joint survey
FDT - Compaction Test
Formworks installation
Concreting works
Concrete testing
Sta. 6+480 to 6+580 R/S
Subgrade joint survey
Subgrade preparation and FDT
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Sta. 5+(440)580 to 6+000 R/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Line Canal - Sta. 5+220 to 5+480 R/S
Excavation works
Rebars and forms installation
CHB laying/Plastering
Line Canal - Sta. 5+220 to 5+400 L/S
Excavation works
Rebars and forms installation
CHB laying/Plastering
Sta. 6+020 to 6+240 L/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Wheel guard @ Sta. 5+980 to 6+020
Slope protection (Grouted riprap)
Wheel guard
Wheel guard @ Sta. 6+160 to 6+280
Slope protection (Grouted riprap)
Wheel guard
Sta. 6+240 to 6+460 R/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Sta. 6+620 to 6+740 R/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Wheel guard @ Sta. 5+960 to 6+000
Slope protection (Grouted riprap)
Wheel guard
Wheel guard @ Sta. 6+580 to 6+620
Slope protection (Grouted riprap)
Wheel guard
Wheel guard @ Sta. 6+700 to 6+740
Slope protection (Grouted riprap)

69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99

100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126

Project: Catch-up schedule


Date: Wed 24/08/16

Finish
Thu 22/09/16

Mon 26/09/16

Tue 27/09/16

Wed 28/09/16

Thu 13/10/16

Thu 13/10/16

Fri 30/09/16

Tue 04/10/16

Tue 04/10/16

Mon 15/08/16

Tue 04/10/16

Mon 15/08/16

Mon 15/08/16

Mon 15/08/16
Mon 15/08/16
Tue 16/08/16
Tue 30/08/16

Mon 15/08/16
Mon 15/08/16
Mon 15/08/16
Tue 16/08/16

Wed 17/08/16
Fri 19/08/16
Fri 02/09/16

Wed 17/08/16
Wed 17/08/16
Thu 18/08/16
Sun 21/08/16
Sun 04/09/16

Wed 17/08/16
Wed 17/08/16
Fri 19/08/16

Sat 20/08/16

Sat 20/08/16
Sat 20/08/16

Mon 22/08/16
Tue 23/08/16

Thu 25/08/16
Thu 25/08/16
Fri 26/08/16

Sat 27/08/16

Sun 11/09/16
Sat 27/08/16
Sat 27/08/16

Wed 31/08/16

Wed 31/08/16
Wed 31/08/16
Tue 06/09/16

Sun 28/08/16
Sun 28/08/16

Mon 29/08/16
Tue 30/08/16
Tue 13/09/16

Tue 30/08/16
Tue 30/08/16

Wed 31/08/16
Thu 01/09/16
Thu 15/09/16

Thu 01/09/16
Thu 01/09/16
Sun 04/09/16

Sun 04/09/16
Sun 04/09/16

Wed 07/09/16
Sun 04/09/16
Sun 04/09/16

15 Aug '16
M
T
W

22 Aug '16
M
T
W

29 Aug '16
M
T
W

05 Sep '16
M
T
W

12 Sep '16
M
T
W

19 Sep '16
M
T
W

26 Sep '16
M
T
W

Wed 05/10/16

Tue 30/08/16

Mon 15/08/16
Tue 16/08/16
Tue 16/08/16
Tue 30/08/16
Fri 02/09/16

Mon 15/08/16
Mon 15/08/16
Wed 17/08/16
Thu 18/08/16
Fri 19/08/16
Fri 02/09/16

Thu 08/09/16

Wed 17/08/16

Mon 22/08/16
Tue 23/08/16

Thu 08/09/16

Thu 01/09/16
Fri 19/08/16

Wed 24/08/16
Thu 01/09/16

Thu 01/09/16
Sun 21/08/16
Tue 23/08/16

Thu 01/09/16

Sun 11/09/16
Thu 25/08/16
Sat 27/08/16

Sun 28/08/16
Sun 11/09/16
Fri 02/09/16

Tue 30/08/16
Fri 02/09/16

Sat 10/09/16

Thu 08/09/16
Sat 10/09/16

Tue 13/09/16

Mon 29/08/16
Mon 29/08/16
Tue 30/08/16
Tue 13/09/16

Thu 15/09/16

Wed 31/08/16
Thu 01/09/16
Thu 01/09/16
Thu 15/09/16

Wed 07/09/16
Sat 03/09/16

Wed 07/09/16

Mon 12/09/16
Tue 06/09/16

Mon 12/09/16

Mon 12/09/16
Tue 06/09/16

Task

Summary

Inactive Milestone

Duration-only

Start-only

External Milestone

Baseline Milestone

Milestone

Inactive Task

Manual Task

Manual Summary

External Tasks

Baseline

Progress

Split

Wed 05/10/16
Mon 03/10/16

Mon 15/08/16

Thu 29/09/16

Fri 30/09/16
Wed 05/10/16

08 Aug '16
M
T
W

Thu 13/10/16

Fri 23/09/16
Thu 29/09/16

Project Summary

Inactive Summary

Manual Summary Rollup

Finish-only

Page 2

Deadline

Baseline Summary

Manual Progress

03 Oct '16
M
T
W

10 Oct '16
M
T
W

17 Oct '16

ID

127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158

Task Name

Wheel guard
Line Canal - Sta. 5+520 to 5+960 R/S
Excavation works
Rebars and forms installation
CHB laying/Plastering
Sta. 6+480 to 6+580 L/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Sta. 5+551 to 5+583 L/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Sta. 5+740 to 6+020 L/S
Agg. Subbase preparation and FDT
Formworks installation
Concreting works
Concrete Testing
Line Canal - Sta. 6+300 to 6+480 R/S
Excavation works
Rebars and forms installation
CHB laying/Plastering
Line Canal - Sta. 5+480 to 5+840 L/S
Excavation works
Rebars and forms installation
CHB laying/Plastering
Line Canal - Sta. 6+020 to 6+380 L/S
Excavation works
Rebars and forms installation
CHB laying/Plastering

Project: Catch-up schedule


Date: Wed 24/08/16

Start

Finish

Wed 07/09/16

Mon 12/09/16

Sun 04/09/16

Fri 09/09/16

Sun 04/09/16

Wed 07/09/16
Fri 09/09/16

Fri 02/09/16
Fri 02/09/16

Sun 04/09/16

Mon 05/09/16
Mon 19/09/16

Mon 05/09/16
Mon 05/09/16
Tue 06/09/16

Wed 07/09/16
Wed 21/09/16
Thu 08/09/16
Thu 08/09/16
Fri 09/09/16
Fri 09/09/16
Fri 23/09/16

Thu 08/09/16
Thu 08/09/16
Sat 10/09/16

Mon 12/09/16
Sun 11/09/16
Sun 11/09/16

Tue 13/09/16

Thu 15/09/16

Thu 15/09/16
Thu 15/09/16
Sat 17/09/16

Mon 19/09/16

08 Aug '16
M
T
W

15 Aug '16
M
T
W

22 Aug '16
M
T
W

29 Aug '16
M
T
W

05 Sep '16
M
T
W

12 Sep '16
M
T
W

19 Sep '16
M
T
W

26 Sep '16
M
T
W

Fri 23/09/16

Wed 14/09/16
Fri 23/09/16

Mon 19/09/16
Sat 03/09/16

Sun 04/09/16

Mon 05/09/16
Mon 19/09/16

Wed 21/09/16
Mon 05/09/16
Tue 06/09/16

Wed 07/09/16
Wed 21/09/16
Fri 23/09/16

Thu 08/09/16
Fri 09/09/16
Fri 09/09/16
Fri 23/09/16

Wed 21/09/16
Sat 10/09/16

Tue 13/09/16

Wed 21/09/16
Fri 30/09/16

Wed 14/09/16
Tue 20/09/16
Fri 30/09/16

Tue 04/10/16
Tue 20/09/16
Fri 23/09/16

Tue 04/10/16

Task

Summary

Inactive Milestone

Duration-only

Start-only

External Milestone

Baseline Milestone

Milestone

Inactive Task

Manual Task

Manual Summary

External Tasks

Baseline

Progress

Split

Project Summary

Inactive Summary

Manual Summary Rollup

Finish-only

Page 3

Deadline

Baseline Summary

Manual Progress

03 Oct '16
M
T
W

10 Oct '16
M
T
W

17 Oct '16