TABLE OF CONTENTS

1. EXCUTIVE SUMMARY
2. BACKGROUND AND CURRENT STATUS OF Think Tech
(Engineering Consultants & Constructions (PVT) Ltd)

3. SCOPE OF CONTRACT

PURPOSE
ROLES AND RESPONSIBILITIES
CONSTRUCTION / CONTRACT ADMINIDTRATION
PROJECT CHANGE CONTROL
FIELD INSPECTION
SHARE HOLDER EXPECTATIONS
PROJECT REQUIREMENTS

4. RFP REQUIRMENRT PROCESS


PARTICIPATION TO RFP
RFP SHEDULE
RFP RELATED QUESTION/ CLARIFICATION/SUBMISSION
RFP EVALUATION PROCESS
RFP TERMS AND CONDITION
BID EXPIRATION DATE
CONFIDENTIALITY & RFP OWNERSHIP

1|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

5. PROJECT LOCATION

6. DRAWINGS

7. DESIGN SPECIFICATIONS & ESTIMATE


PRODUCT DESIGN SPECIFICATION APPROVAL

8. RESPONSE FORMAT (PROPOSAL FORMAT)

2|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

Executive Summary

Think Tech Engineering Consultant and Constructions (PVT) LTD are in need
of a professional engineering constructor (construction firm) to build a newly
proposed pedestrian bridge. This bridge is funded by Sri Lanka Institute of
Information for their bridge program project.

The purpose of this request is to provide complete construction management


and inspection to provide a completed product that performs as intended. At the
moment Think Tech Engineering Consultants and Constructions (PVT) LTD is
planning to find firm to provide constructability reviews, construction
engineering and other services associated with the construction phase of a
project.

There are six main objectives that Think Tech Engineering consultants and
constructions (PVT) Ltd wanted to be achieved by the contractors

1] Effective cost and schedule controls


2] Delivery of the overall Project at least cost for best value and within CCC
budget

3|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

3] Most cost effective, risk management strategy


4] Maximizing innovation and value engineering opportunities
5] Implementation of environmentally sensitive, sustainable practices
6] Maximizing diverse participation in the Project

Contact for one of person named below for any inquiries regarding this RFP

1. Director
Piyathilaka W.U.D
Udithadinushka@hotmail.com

2. Secretory
Bandara A.W.A.L
Anushi3314@gmail.com

4|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

BACKGROUND AND CURRENT STATUS OF Think Tech


(Engineering Consultants & Constructions (PVT) Ltd)
Think Tech Engineering Consultant and Construction Company was
implemented in 10th July 2014. Although the company is with less experience
the Director board is held by fully efficiently working people who are capable
to compete as a Consultant Company in this competitive market.
Our company`s main objective is to be the leader in this industry. As a
consultant company
The director Board and the staff is fully qualified where all the directors are
from engineering backgrounds of Electrical, electronic, mechanical and Civil
which combines a greater knowledge in constructions more effectively and in
an environmental friendly manner.
The Management of Think Tech Engineering Consultants and Construction
(PVT) Ltd is shown below.
Board of Directors: Jayasekara J.LA.H.P

(CEO)

Perera H.S.N

(CTO)

PradeepthaY.D.G

(CMO)

Piyathilaka W.U.D

(Project Manager)

Secretory

: Bandara A.W.A.L

HR Manager

: Jayashantha G.L.K.S
5|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

SCOPE OF CONTRACT
1. Purpose
Think Tech Engineering works as the consultant for SLIIT (Sri Lanka
Institute of Information Technology) to consult them for a proposed
pedestrian bridge.
The Proposed Bridge is,

4m from the bed level of the waterway


Span of1.5m
Width of 0.5m
Load carrying capacity of 700 N
Made from any kind of suitable and durable Timber.

This bridge should be constructed within 12 weeks.

2. Roles and Responsibilities


Daily operations of the project should be E mailed to the Project
Manager.

6|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

3. CONSTRUCTION / CONTRACT ADMINISTRATION


Maintaining a daily inspector's report system
Equipment must be identified sufficiently to enable determination of the
applicable rental rates and operators minimum wage.
Maintaining well organized photographic record
Monitoring construction schedules throughout the course of construction

4.

PROJECT CHANGE CONTROL


Investigation and inspection of site conditions that differ from those described
in the Contract Documents
Review and evaluation of contract change order requests and submittals
Contract change order coordination between Contractor and City
Review of submittals in support of claims and disputes, and recommendations
for resolution thereof

5. Field Inspection
Monitoring of corrective actions taken by the Contractor needed to fix work
that is not in compliance with Contract Documents.

7|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

6. SHARE HOLDER EXPECTATIONS


The proposed bridge should be constructed with all requirements given by
Think Tech Engineering Consultants and Constructions (Pvt) Ltd fulfilled.

7. PROJECT REQUIREMENTS
The evaluation of the bridge is 4m from the drainage bed level. Span of the
bridge is 1.5m and the width of the bridge is up to 0.5m (provided a person can
comfortably walk inside). Load carrying capacity is around 700N.The designer
has the freedom to choose the superstructure and the substructure is existing.
The preferred material for construction is timber and the architectural style
should contemporary. The duration of the contract is 12 weeks

8|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

RFP REQUIRMENTS PROCESS


The constructors who are willing to participate should confirm to Think Tech Engineering
Consultants and Construction s within 4 days of receiving the RFP their Intent to Respond.
A failure to confirm will be signify that a construction company is not participating in the
RFP and Think Tech Engineering Consultants and Constructions will require an immediate
return of the RFP.

All basic constructors confirming their participation should send the Intent to respond to
the attention of:

Think Tech Engineering Consultants and Constructions,


SLIIT,
Malabe, Sri Lanka

Secretory: Bandara A.W.A.L


Anushi3314@gmail.com

9|Page

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

1.)

RFP Schedule:

1.

2014/07 /31

RFP available for bidders

2.

2014/08/01

Deadline for addressing questions

3.

2014/08/03

Response to all the questions

4.

2014/08/05

Deadline receiving bids

5.

2014/08/07

Biddings to be evaluated

6.

2014/08/09

Conclusion of the contract

7.

During the 12 weeks pilot installation of the bridge has to be done

8.

Before the expiry of 12 weeks fully construction must be done.

2.) RFP related questions/submissions


All the questions related to RFP should be send to following address
Secretory: Bandara A.W.A.L
E-mail anshi3314@gmail.com
10 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

3.) RFP TERMS AND CONDITION

The construction company should fulfill all requirements of the Think Tech
Engineering Consultants and Constructions (Pvt ) Ltd.

4.) BID EXPIRATION DATE

2014/07/31
5.) RFP Ownership

This RFP is confidential and is a property of Think Tech Engineering


Consultants and Constructions (Pvt) Ltd.
Basic partners shall not include or reference this RFP in any publicity without prior
written approval from the client.

11 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

FEE PROPOSAL
1. Two copies of your proposed fee shall be submitted in a separate sealed envelope,

within the proposal package, plainly labeled Fee Proposal with the prime companys
name and the project title.

2. The fee shall include services for construction engineering/management and


coordination of environmental mitigation measures.
Think Tech Engineering Consultants and Constructions Request for Proposals
SLIIT pedestrian bridge Construction Engineering/Management

3. The fee proposal shall include a cover letter stating the actual cost-plus-fixed fee, and
separate fee schedules depicting individual project tasks, staff hours, and basic hourly
charge rates. The fee proposal shall reflect all anticipated fee increases during the
contract duration.

4. The fee proposal will be opened after Consultants have been evaluated by the proposal
committee. The Think TechEngineering will select Contractor based on qualifications.
The final contract price may be negotiated

12 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

Project Location

Construction Site:

13 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

Location where the bridge is going to be build:

Drawings
Side view:

4m
1.5m

14 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

Top View:

Timber Planes are used for the walkway on the bridge

1.5m
To have the bridge sable and strong a 2 structures are used on both side
having compressions and tensions avoiding the bride collapsing.

15 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

DESIGN SPECIFICATIONS & ESTIMATE


Mango or Coconut timber is used

Rs 5000.00

Four inch nails

Rs 400.00

Nuts and bolts

Rs 200.00

Total

Rs 5600.00

16 | P a g e

PRODUCT DESIGN SPECIFICATION APPROVAL

The undersigned acknowledge they have reviewed the SLIIT PEDESTRIAN BRIDGE
CONSTRUCTION Product Design Specification document and agree with the approach it
presents. Any changes to this Requirements Definition will be coordinated with and approved by
the undersigned or their designated representatives.

Signatures of construction firm`s CEO or CFO, Technical steward and project manager is
required.
Signature:

Date:

Print Name:
Title:
Role:

Signature:

Date:

Print Name:
Title:
Role:

Signature:

Date:

Print Name:
Title:
Role:

17 | P a g e

Think Tech
ENGINEERING CONSULTANT AND CONSTRUCTION COMPANY

RESPONSE FORMAT (PROPOSAL FORMAT)

All the bidders should submit a response format of a bidding document. For
more information visit https://www.thinktecheng.com

Thank you,
Yours faithfully,
Secretary,
Bandara A.W.A.L
Think Tech Engineering Consultants and Cnstructions.

18 | P a g e