Sie sind auf Seite 1von 14

BOLIVIA BRIDGE MANUAL

TABLE OF CONTENTS
Justification for specific dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Materials List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Flow rate calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Force calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-10
Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
Construction sequence and timeline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12
Operation and Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13-14

JUSTIFICATION FOR SPECIFIC DIMENSIONS


Culvert size:
We chose to use the 2 meter diameter culverts and cut them in half so we could have
optimal flow and reduce our material costs. The culverts will each be 4.556 m long.
This will allow for a 3.048 m roadway as well as a retaining wall with a 45 angle top,
while still allowing 0.5 m of culvert extending beyond the wall.
Width of the Roadway:
Our roadway is 3.048 meters (10ft) wide; an appropriate width for the level of traffic
of the site. Making the bridge too wide would create unnecessary costs, however a
bridge that was too narrow would not meet the purpose of the bridge. We concluded
that 10 feet would be a suitable width for the bridge.

MATERIALS LIST
Item
2000mm metal pipe
culverts
Portland Cement
Aggregate (concrete)
Soil
Crushed Stone (Gravel)
Wood concrete forms
Equipment Needed
120 L Gas Concrete mixer
Level (18)
Shovels (flathead)
Wheelbarrows

Amount
6 (sliced in
half)
4.556m long

Total Cost
$8615

Acquired from:
Oruro

29.0442 m3
total
8.092 m3
7 truckloads
--

--

Oruro
Oruro
Riverbed excavation

$220

Oruro

--

Local Scrap Wood

1
2
20-30
5

$1000
$5
$245-$365
$430bs

Oruro
Oruro
Oruro
Oruro

Notes:
Total Costs were converted from bs to $.
We overestimated on all costs by rounding up to the nearest five or zero on all
estimates. Also, we will have more than enough soil from the riverbed excavation for
filling in around the culverts.
Assumptions for culverts:
We assumed the price was in dollars and that a 2m diameter pipe would cost 1.5
more that a 1m diameter pipe. We also assumed the cost was per meter. Our cost
does not include cost of cutting or delivery.

FLOW RATE CALCULATIONS


To calculate the volumetric flow rate of the river we used Manning's formula,

k
2 / 3 1/ 2
Rh S
n

where k is equal to 1.0 because we're using SI units, n is the manning coefficient of
roughness, Rh is the hydraulic radius, and S is the slope of the riverbed. We used the
manning coefficient of 0.035 which is used for floodplains, pastures, and farmlands.
The hydraulic radius is equal to A/P, where A is the cross sectional area and P is the
wetted perimeter. We calculated the river's cross sectional area with AutoCAD, which
yielded an area of 18.9554 m2, as well as the wetted perimeter, which was 56.9150
m. The slope S was determined by using a point on the cross section and a point prior
to it. This equaled 0.0455 m/m.
By plugging in these numbers into Manning's formula, we found the velocity of the
river to be 2.9 m/s. We then took this velocity and plugged it into the continuity
equation: Q = AV, where Q is flow rate, A is the cross sectional area, and V is the
velocity. The final flow rate came out to be 55.5062 m3/s.
Once we determined the max flow rate of the river, we looked into figuring out the
flow rate going through the half culverts to make sure we had a sufficient number. To
do this, we used Dr. Kabala's colebrook.m file to calculate volumetric flow rate
allowed by semi-circular, 2-meter diameter culverts for our riverbed conditions.

This yielded a flow rate of 5.13568 m3/s per culvert. Based on this number, we
determined that 10.8 culverts were needed. Therefore our ultimate design has 11
half-culverts.

FORCE CALCULATIONS

10

DETAILS
Detailed description of Construction Timeline Step 4:
Our sequence for placing the culverts will be a sequential and simultaneous process.
The first stage of the process will be to set the form for the first two strip footings,
pour the concrete, place rebar, and place the first culvert in the forms. The concrete
will be poured into the first footing, securing the culvert in place. The form for the
first section of the concrete wall will be cut and placed, and the concrete for the wall
will be poured. Once the wall has had time to set, a second crew will begin filling
around the culvert with compacted soil while the first crew begins on the third strip
footing and placing the second culvert. Once the second footing has been poured
and the concrete wall has been poured and had time to set, the soil crew will follow
behind. This process will continue as the bridge is built across the river. By the time
both crews reach the other side, the strip footings, culverts, concrete wall, and
compacted soil fill will all be in place. The construction process will then continue
with the placing of the angled concrete wall/curb. (Please refer to CONSTRUCTION
SEQUENCE AND TIMELINE)

11

CONSTRUCTION SEQUENCE AND TIMELINE

Task
Obtain materials on list
Have pipes cut and delivered
Dig out riverbed to achieve flat bed
Sequence for placing culverts
a. Set forms for strip footing
b. Pour concrete (partial) and place rebar
c. Place culverts in forms
d. Pour concrete in forms (securing culverts)
e. Cut and place concrete retaining wall forms(inlet & outlet)
f. Pour concrete in wall forms
g. Place soil fill between retaining walls (compacted)
5. Place angled concrete wall/curb
6. Place crushed stone to prep for roadway
7. Lay concrete roadway
1.
2.
3.
4.

12

Day
1
1
1
15

23
26
28

OPERATION AND MAINTENANCE


Safety factors:
We have added safety factors in various aspects of our design. We must also consider
other failure modes for culverts and prepare for these failures in the chance that they
occur. The most common failure modes for culverts are insufficient capacity,
plugging, and embankment erosion.
Preventative Measures
Insufficient capacity:
- Install armoring and wing-walls at the entrance and outlet of the culvert to
increase pressure of the flow through culverts.
- Install a relief culvert.
Plugging:
- Install an entrance debris deflector.
- Install a sediment catch basin upstream.
- Install a relief culvert.
Embankment Erosion:
- Place riprap to reduce embankment erosion.
- Shape culvert entrance to match embankment slope.
- Construct flared end section to direct flow.
How Often:
Maintenance of the bridge will require periodic bridge inspections. At the time of
completions, an initial inspection will occur. The purpose of this inspection is to
reevaluate site conditions and identify deficiencies that may not have been identified
during construction. This includes reevaluation of erosion, debris guards, and grades
of banks.
Routine inspections will be regularly scheduled, occurring every two years during the
dry season. Inspection of equipment of bridge evaluation tools will occur first
(cleaning tools, visual aid tools, measuring equipment, safety equipment, etc.). The
bridge inspector will inspect the bridge for fractures, structural deficiencies, failures
in the metal culverts, and will identify changing conditions.
Interim inspections will occur every six months to identify any quickly changing
conditions with the bridge. These inspections may be performed by local (or district)
trained inspectors. During these inspections, the inspector should also remove any
debris from the debris guards to allow for maximum flow through the culverts.
Damage inspections will be performed as needed, generally as a result of
environmental damages, fires, collisions, or severe floods. Underwater inspections
may be performed as needed during low water seasons. Wading techniques may be
used for this inspection. In-depth inspections may also be performed to investigate
deficiencies found during routine inspections.
It will also be useful to develop in information database containing all data gathered
during bridge inspections. This will help in monitoring load-bearing capacities of the
bridge.
Operation Costs:
Cost to operate the bridge will be composed of pay for a bridge inspector and funds
for future bridge repairs. This will be proportional to the average pay rate for bridge

13

inspectors in Bolivia and the cost of materials for the future repairs necessary. There
will be no daily operation cost for the bridge.

14

Das könnte Ihnen auch gefallen