Beruflich Dokumente
Kultur Dokumente
TABLE OF CONTENTS
Justification for specific dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Materials List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Flow rate calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Force calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-10
Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
Construction sequence and timeline . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12
Operation and Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13-14
MATERIALS LIST
Item
2000mm metal pipe
culverts
Portland Cement
Aggregate (concrete)
Soil
Crushed Stone (Gravel)
Wood concrete forms
Equipment Needed
120 L Gas Concrete mixer
Level (18)
Shovels (flathead)
Wheelbarrows
Amount
6 (sliced in
half)
4.556m long
Total Cost
$8615
Acquired from:
Oruro
29.0442 m3
total
8.092 m3
7 truckloads
--
--
Oruro
Oruro
Riverbed excavation
$220
Oruro
--
1
2
20-30
5
$1000
$5
$245-$365
$430bs
Oruro
Oruro
Oruro
Oruro
Notes:
Total Costs were converted from bs to $.
We overestimated on all costs by rounding up to the nearest five or zero on all
estimates. Also, we will have more than enough soil from the riverbed excavation for
filling in around the culverts.
Assumptions for culverts:
We assumed the price was in dollars and that a 2m diameter pipe would cost 1.5
more that a 1m diameter pipe. We also assumed the cost was per meter. Our cost
does not include cost of cutting or delivery.
k
2 / 3 1/ 2
Rh S
n
where k is equal to 1.0 because we're using SI units, n is the manning coefficient of
roughness, Rh is the hydraulic radius, and S is the slope of the riverbed. We used the
manning coefficient of 0.035 which is used for floodplains, pastures, and farmlands.
The hydraulic radius is equal to A/P, where A is the cross sectional area and P is the
wetted perimeter. We calculated the river's cross sectional area with AutoCAD, which
yielded an area of 18.9554 m2, as well as the wetted perimeter, which was 56.9150
m. The slope S was determined by using a point on the cross section and a point prior
to it. This equaled 0.0455 m/m.
By plugging in these numbers into Manning's formula, we found the velocity of the
river to be 2.9 m/s. We then took this velocity and plugged it into the continuity
equation: Q = AV, where Q is flow rate, A is the cross sectional area, and V is the
velocity. The final flow rate came out to be 55.5062 m3/s.
Once we determined the max flow rate of the river, we looked into figuring out the
flow rate going through the half culverts to make sure we had a sufficient number. To
do this, we used Dr. Kabala's colebrook.m file to calculate volumetric flow rate
allowed by semi-circular, 2-meter diameter culverts for our riverbed conditions.
This yielded a flow rate of 5.13568 m3/s per culvert. Based on this number, we
determined that 10.8 culverts were needed. Therefore our ultimate design has 11
half-culverts.
FORCE CALCULATIONS
10
DETAILS
Detailed description of Construction Timeline Step 4:
Our sequence for placing the culverts will be a sequential and simultaneous process.
The first stage of the process will be to set the form for the first two strip footings,
pour the concrete, place rebar, and place the first culvert in the forms. The concrete
will be poured into the first footing, securing the culvert in place. The form for the
first section of the concrete wall will be cut and placed, and the concrete for the wall
will be poured. Once the wall has had time to set, a second crew will begin filling
around the culvert with compacted soil while the first crew begins on the third strip
footing and placing the second culvert. Once the second footing has been poured
and the concrete wall has been poured and had time to set, the soil crew will follow
behind. This process will continue as the bridge is built across the river. By the time
both crews reach the other side, the strip footings, culverts, concrete wall, and
compacted soil fill will all be in place. The construction process will then continue
with the placing of the angled concrete wall/curb. (Please refer to CONSTRUCTION
SEQUENCE AND TIMELINE)
11
Task
Obtain materials on list
Have pipes cut and delivered
Dig out riverbed to achieve flat bed
Sequence for placing culverts
a. Set forms for strip footing
b. Pour concrete (partial) and place rebar
c. Place culverts in forms
d. Pour concrete in forms (securing culverts)
e. Cut and place concrete retaining wall forms(inlet & outlet)
f. Pour concrete in wall forms
g. Place soil fill between retaining walls (compacted)
5. Place angled concrete wall/curb
6. Place crushed stone to prep for roadway
7. Lay concrete roadway
1.
2.
3.
4.
12
Day
1
1
1
15
23
26
28
13
inspectors in Bolivia and the cost of materials for the future repairs necessary. There
will be no daily operation cost for the bridge.
14