Beruflich Dokumente
Kultur Dokumente
Pipe Embedment
The backfill materials enveloping a buried pipe are given in
the drawing for easy identification and by their function or
location:
Foundation
A foundation is required only when the native trench
bottom does not provide a firm working platform, or the
necessary uniform and stable support for the installed pipe.
If a foundation is installed, bedding is required above the
foundation.
.18.
Bedding
In addition to bringing the trench bottom to required pipe
bottom grade, the bedding levels out any irregularities and
ensures uniform support along the pipe length. Bedding is
required when a foundation is installed, but a foundation may
not be required to install bedding.
Haunching
The embedment under the pipe haunches supports the pipe
and distributes the load. The quality of the haunching backfill
Final Backfill
Final backfill is not on an embedment material, however,
it should be free of large rocks, lumps, construction debris,
stones, stumps and any other material with a dimension
greater than 8.
Socket Welding
Extrusion Welding
Butt Welding
The most widely used method for jointing individual length
of Jain PE Pipe is by heat fusion of the pipe butt ends. This
technique, which precludes the need for specially modified
pipe end or couplers, produces an economical connection
which is as strong and as chemically resistant as the pipe. To
make a reliable and durable butt welded joint, the following
procedure is to be adopted:
i) Clean both ends with a damp cloth to dislodge any foreign
matter or dirt deposited on the pipe.
ii) Hold the pipes firmly with the clamps of a specially
designed Welding Jack.
iii) Bring both the faces to axial alignment by using support
rollers to minimise mismatch of the faces by rotating, if
necessary.
.19.
Electrofusion Joint
In this method the socket of the fitting incorporates an
electrical heating coil. When energised by an electronic
control unit, the coil causes the material around it to melt and
form an expanding pool which comes into contact with the
surface of the pipe. This causes the pipe to melt, leading to
fusion of pipe & socket. Used for Air/Gas Distribution lines.
Flanged Joint
If transition is to be made to another piping material or if
a pipe section capable of disassembly is required, then Jain
PE Pipe Ends (also called Stub-ends) are available that can be
welded to the pipe by means of heat fusion. A metal back up
flange with appropriately sized and spaced bolt holes permits
bolting to standard or specially sized flanges. In order to get
Dia
PCD
Bore
Dia
Thick
Bolt
Hole
Dia
No.of
Bolt
Holes
63
165
125
64-65
7.0
19.0
75
185
145
76-77
7.0
19.0
90
200
160
91-92
9.5
19.0
110
220
180 112-113
9.5
19.0
125
250
210 127-128
11.0
19.0
140
250
210 142-143
12.5
19.0
160
285
240 162-163
12.5
23.0
180
285
240 183-184
12.5
23.0
200
340
295 203-204
16.0
23.0
225
340
295 228-229
20.0
23.0
250
395
350 253-254
20.0
23.0
12
280
395
350 284-285
20.0
23.0
12
315
445
400 319-320
24.5
23.0
12
PE Sure-Loc Joints
Fittings
In order to facilitate a complete Piping System, Jains offer
a wide range of tailor made fittings to suit the individual
needs.
Above ground supporting:
Support spacing depends upon the allowable deflection
between supports, which in turn depends upon the pipeline,
the fluid it carries and the service temperature. Jains advise
customers that the allowable long-term deflection between
supports should not exceed 1. Recommended support
spacing may be taken from Table-11 given below.
NB
2.5
10
--
--
1.50
1.55
--
1.65
1.75
1.90
1.65
1.80
2.00
2.15
1.80
2.00
2.20
2.40
2.00
2.20
2.40
2.60
2.30
2.50
2.75
2.95
10
2.60
2.80
3.10
3.30
12
2.80
3.10
3.35
3.60
14
2.90
3.20
3.50
3.80
16
3.10
3.40
3.75
4.05
15C
38C
49C
60C
Multiplication Factor
1.01
0.95
0.85
0.8