1. OBJECTIVE
2. SCOPE
3. ABBREVIATIONS
4. SPECIFICATIONS
5. CODES
6. ROLESANDRESPONSIBILITIES
7. MANPOWER
8. EQUIPMENTANDTOOLS
9. SEQUENCEOFACTIVITIES
10. SCOPEOFWORK
11. SAFETYPRECAUTIONS
12. ATTACHMENTS
Page No: 2 OF 11
Checker
Approve
r
DPJV
1. OBJECTIVE
Thisdocumentis intended to briefly describe sequence of events duringAboveGround
PipingInstallation,confirmstheriskassessment&tocoversofarasisreasonablypracticable,the
health,safety&welfareofouremployeesandotherswhomaybeaffectedduringtheAGPiping
erection/testingofpackagenumber(2&6)theworkscope.
2. SCOPE
ThismethodstatementisapplicableforAboveGroundpipingInstallationforpackagenumber(2
&6)atSoharRefineryImprovementProject(SRIP).
3. ABBREVIATIONS
AFC
:ApprovedforConstruction
AWS
:AmericanWeldingSociety
ASME
:AmericansocietyofMechanicalengineers
ANSI :AmericanNationalStandardsInstitution
Company :SoharRefineryImprovementProject(SRIP)
Contractor
:DaelimPetrofacjointventure
SubContractor
:BahwanEngineeringCo.LLC(BEC)
ISO :InternationalStandardsOrganization
ITP :Inspection&testplan
NCR :Nonconformancereport
P&ID
:Piping&Instrumentationdiagram
PPE :PersonnelProtectiveEquipment
TRA :RiskAssessment
4. SPECIFICATIONS
ProjectQualityPlan
:GeneralrepairprocedureforPiping
WelderandweldingoperatorQualificationprocedure
MeasuringandTestEquipmentcontrolprocedure
Weldingqualitycontrolprocedure
PipingMaterialSpecification
Page No: 3 OF 11
PipeMarkingSpecification
Specificationforinternalcleaningofpiping
Materials&FabricationRequirementsforcarbonsteel.
Welding,NDE,PreventionofBrittleFractureofPiping
SpecificationforFabricationHandling&InstallationofProcessandUtilityPiping
TechnicalSpecificationforPipingSystemSpecificationforGeneralPiping
GeneralPipingProcessandUtilityDesignFieldPressureTesting
Specificationforbolttorqueing/TensioningforFlangedConnection
SpecificationforthetraceabilityofshopandfieldPipingMaterials
SpecificationforpreservationandExportPacking
WeldingConsumableControlProcedure
NDEControlProcedure
HeatTreatmentandHardnessControlProcedure
MethodStatementforPressureTestingofA/GPiping.
PMIProcedure
5. CODES
ASMESect.IX
:Welding&BrazingQualifications
ASMESect.V
:NonDestructiveExamination
ASMEB31.1
:PowerPiping
ASMEB31.3
:ProcessPiping
ASMEB16.5
:PipeFlanges&PipeFittings
ASMEB16.47
:LargeDiameterSteelFlanges
ASMEB16.25
:ButtWeldingEnds
ASMEB1.20.1
:PipeThreads,GeneralPurpose
AWSD1.1
:StructuralWeldingCodesteel
6. ROLES&RESPONSIBILITIES
Construction Manager
ShallReporttoSiteManager
Shall be overall responsible for control and monitoring of all Piping Installation
activities.
Shall have overall responsibility to ensure safety at site for the working group and
environment.
Shallhaveoverallresponsibilityforthequalityoffabricateditemsifmodifiedatsite.
Shall be responsible for the execution ofworkin accordance with project HSE and
Qualityrequirements
QA/QC Manager
ReporttoSiteManager.
Page No: 4 OF 11
Responsibilities for quality control of the piping fabrication, welding, installation &
testing
ResponsibleforpreparingITP,Inspection&testprocedures.
ShallreviewInspectionreports,testcertificates&prepareTQfortechnicalinformation.
Shallberesponsibleformonitoringmaterialpreservation,Installation&alignmentin
accordancewiththeSpecifications.
Shallensurethattherequirements&specificationsstipulatedinthismethodstatement
areappliedandmaintainedthroughouttheprojectconstructionperiod
Shallensurethatallrelevantproceduresforabovegroundpipinghavebeenapprovedby
COMPANYpriortoworkcommencing.
Piping Engineer
ShallreporttoConstructionManager
Shallensurethatfabrication,welding&Paintingactivitiesareongoingasperproject
specificationrequirementsandasperthelatestdrawings.
Preparetechnicaldeviation,concessionrequest,as&whenrequired.
ShallberesponsibleforexecutionofworkincompliancetotheprojectHSEandQuality
requirements
Piping Supervisor/Foreman
ShallreporttoPipingEngineer
ShallensurethatpersonnelworkingareHSEinductedandarecomplyingwithProject
HSERequirements.
ShallconductHSEtoolboxtalktoallconcernedpersonnelpriortostartofwork
ControlExecutionofPipinginstallation,storage,trackingofthematerialreceivedatsite.
CoordinatewithQA/QCInspectorwhileperformingInspectionaspertheITP.
Shall ensure all dimensional & structural control is as per approved drawing
requirements.
QC Inspector
ShallreporttoQCEngineerPiping/Welding
Page No: 5 OF 11
Shallmonitor&InspectQA/QCactivitiesagainstapprovedITP,Projectspecification,
drawings.
ShallliaisewithClientInspectionPersonnelduringinspection.
PrepareandmaintainInspectiondocuments.
Shallinspecttheincomingmaterialsasperdesigngeneralspecificationandpurchase
orderrequirements.
ShallmonitortheWPS/Weldersqualificationstatus.
Shallensurethatallinstrumentsaredulycalibratedandcertified
Welding Foreman
Shallbereportingtopipingengineer
Shallensurethatonlyqualifiedweldersaredeployedonjob.
ShallberesponsiblefortheissueandcontrolofweldingconsumablerelevanttoWPS.
ShallensurethatallpersonnelworkinginweldingareHSEInductedandfamiliarwith
projectHSE&Qualityrequirements
Shallconducttoolboxtalkpriortostartofwork&ensurecompliancewithWPS
Material controller
ShallreporttoMaterialManager
Shallensurethatallmaterialsarestored&segregatedaspermaterialspecification&
size/schedulewise.
Shallensurethatallboughtoutprojectmaterialsareinspected&certifiedbyconcern
authority.
Shallensurethatallmaterials/spoolsareissuedforinstallationinaccordancewithMIR.
Safety Officer
ShallreporttoHSEManager
Ensure valid work permit for all activities performed during installation and premit
conditionarecomplied.
Ensurescaffoldingsaretaggedanddulysignedbyscaffoldinginspector
Ensurethatemployeesinvolvedinthescaffoldingworkaretrained/qualified
Page No: 6 OF 11
EnsurethatproperPPEsarebeingusedbyemployeesduringwork.
Conducttoolboxtalkinordertoexplainpossiblehazards,associatedrisks&control
measures
IdentifyspecifichazardsandassistconstructionSupervisiontoensuresafeprogressof
workactivity.
Controlunauthorizedentrytoworkareabyproperbarricading&displayingwarning
signboardsandindicators.
CoordinatewithDPJVHSEstaffforeffectivecontrolofactivityatsite.
7. MANPOWER
SiteManager
ConstructionManager
QCManager
PipingEngineer
PipingSupervisor/Foreman
Pipefabricator/Fitter
Welders
Riggers
QCInspector
Materialcontroller
HSEOfficer
CraneOperator
Manlift/Forkliftoperators
8. EQUIPMENT&TOOLS
Trailer
Crane
Page No: 7 OF 11
Forklift&Manlift/ManBasket
Spanners/TorqueWrench
WeldingMachines
Highfrequencyunit
AlignmentInspectiontools
Liftingtools&tackles
TestManifold
Pressuregauges/Recorder
Spiritlevel,Measuringtape
CuttingSet
GrindingMachine
9. SEQUENCEOFACTIVITIES
Transportation,Loading&unloadingofmaterials
Installationofpipespools&fieldwelding
PipeSupportfabrication&Installation
NDTofWeldingJoints
Installationofvalves&fittings
Hydrotest/Pneumatictest
Punchlisting&Reinstatement
Precommissioningactivities
Finalclearance&Handover
10. SCOPEOFWORK
10.1
planningdepartment.
Page No: 8 OF 11
MaterialsissuevouchershallbepreparedandissuedtoProjectstorestowithdrawErection
items
Spool/Supportsrequirementbasedonthefrontavailability&Prioritiesshallbeprovidedto
spoolcoordinatorbyFieldpipingengineerfortracking&issueofspool.
Materialsreceivedshallbesegregatedwithrespecttothetypeofmaterials(CS/SS/LTCS/AS/
Nickelalloys)andkeptseparatelyaccordingtothecolorcode
Materialsreceivedforpipesupportsshallbeinaccordancetothestandardsupportspecification
Preservationandstorageofpipingspools,supportanderectionmaterialsshallbeensuredin
accordancewithprojectspecification.
Pipespoolshouldbekeptclearfromtheground.Beforetransportationoffabricatedspoolsat
site,necessaryclearance(SpoolID,DimensionandNDE)shallbeobtainedfromContractor
QA/QCdivision.
DuringTransportationoffabricatedspool,muchattentionshallbetakentoavoiddamagetopipe
orpainting.
Theendcapsshallbekeptinplaceduringtransportandstorageinordertopreventdust,dirtand
foreignmatterfromenteringthepipe.
10.2
Priortostartinstallation,handovernotefromStructuralshallbeobtained.
Correctelevation,coordinationandalignmentshallbeverifiedbeforestartuptheinstallation,
fitupandweldingactivitiesasperapprovedISODrawings.
Welding Supervisor shall assign qualified welders for all welding activities
Heat number to be transferred on the pipe prior to cut the piping spool.
Piping spool shall be properly identify with spool no, drawing/ISO no.
Belt slings shall be used for lifting pipes & spools in order to avoid damages
to painted pipes / spools
Page No: 9 OF 11
Purging shall be done for SS & AS Materials during welding as per approved
WPS.
Thermal expansion clearance shall be provided between pipe edge and inner
face of the fitting for welding socket joints as per project requirement
Propercuttingtechniquesshallbefollowedforedgepreparationduringfitupandgascutting
shallnotbedoneforSS(SA312TP304L/316L/321)&AS(2Cr,5Cr,9Cr1Mo)Materials.
Separatetoolsandtackleslikewirebrushes,grindingwheels,chippinghammersetc.shallbe
usedforstainlesssteelpipingwork.
SmallboreweldingshallbedonebyGTAWprocessonly.
Necessaryscaffoldingplatformarrangementsshallbeprovidedtoensuresafeaccessforfitup/
welding
Properbarricadesshallbeprovidedallaroundtheworklocationwhileworkingontoptier.
Allpipes/spoolsshallbecleanedandensurethatitisfreefromanyforeignmaterialsinsidethe
pipes.
Allopenendsofpipingspoolsshallbeblankedproperlytoprevententryofforeignmaterials
anddamagetobevelends,duringentireconstructionperiod
Productionshallbeperformedinaccordancewithapprovedprocedure.
FituptackingshallbecarriedoutbyusingqualifiedweldersaccordingtoapprovedWPS.
WeldersshallbetestedandqualificationswillbeendorsedbyDPJVQA/QCdivisionpriorto
commencementofproductionwelding.
Noweldingshallbedoneiftherewillbeanimpactofrain,snow,sleetorhighwindinthe
workingarea.However,weldingworkshallbedoneprovidedthatsuitableprotectionisinstalled
andapprovedbycontractor.
Page No: 10 OF 11
10.4
Uponinstallationofpiping,thepipejointsshallbepreparedtotherequireddimensionsas
specifiedintheapprovedisometricdrawings.Weldedgeshallbepreparedasperapplicable
approvedWPS.Pipingcomponentsshallbecleanedfrominsideandconductvisualinspection
priortofitupassembly.
NDT of Welding Joints
All NDT activities shall be carried out by client approved and qualified NDT
technicians
Only calibrated instruments with third party certification shall be used for
Inspection
All repairs shall be conducted with client recommendation and RFI shall be
raised for the same
ClientapprovedPWHTProcedureshallbefollowedforPWHTofweldingjoints
Only Client approved thermocouples shall be used and shall be color coded
for identification
Band width of heating coil and insulation width shall be as per PWHT
procedure.
Page No: 11 OF 11
All openings shall be closed to avoid heat loss due to air circulating through
pipe.
Only latest revision drawings with AFC Stamping shall be used for
Installation.
Only Calibrated torque wrenches shall be used for bolt torqueing and
company approved torqueing procedure shall be followed
Prior to pressure testing of the system, line shall be Mechanical & NDT
cleared as per project specification/standard.
All pressure gauges used for pressure test shall be calibrated once in every
six month & pressure-temperature recorders shall be calibrated once in
every six month by a third party or laboratory.
Page No: 12 OF 11
Test packages shall be prepared and reviewed prior to pressure test, all the
relevant drawings, forms & certificates shall be attached
Test blinds used shall have sufficient thickness to withstand test pressure.
Water shall be filled from the possible lower portion of the piping system to
release air from inside.
All NDT and Visual inspection of welded joints shall be completed prior to
pressure test.
Ensure the correct orientation and flow direction of valves and instruments
prior to test.
Items which may damage during test or obstruct the flow including flow
meters, orifice plates, control valves, check valves, strainers, steam
trapsetc., shall be removed or its internals shall be removed whichever is
appropriate.
After complete hydrostatic test, the piping shall be carried out drain
immediately with compressed air.
All test vents & drains shall be seal welded after pressure test & dewatering, as applicable.
Page No: 13 OF 11
11. SAFETYPRECAUTIONS
All applicable requirements mentioned in the Project HSE Plan and specific
RA shall be implemented at the construction site.
Tool box talks shall be conducted daily for safety and environmental matters
related to construction activities at site.
Only those lifting equipment and tools which are of suitable capacity, in
good condition, certified, inspected and color coded shall be used for all
lifting activities.
Trained and competent bank men or riggers shall be appointed for the heavy
lift operations.
Personnel movement under the suspended loads shall be avoided. All the
lifting activities shall be carried out under the strict supervision of
experienced foreman / charge hands.
Sign boards & hard barricades shall be placed around erection area except
where active work requires opening of such devices and then only such
portion of the barricade needed for work access will be removed.
No lifting operations shall be carried out in the heavy wind and bad weather
conditions.
Night operations shall be carried out only with the prior permissions from
HSE and CONTRACTOR.
Page No: 14 OF 11
Personnel working at heights shall wear suitable PPE and body harness. All
those personnel shall attend and inducted by HSE for working at heights.
Prior to pipe insertion / erection of pipe spools in various levels of pipe rack,
Construction Supervisor & Rigging supervisor must make a joint survey of
the insertion / erection area and ensure the riggers involved are having safe
access to the work location and ensure 100% tie of at all time.
12. ATTACHMENTS