2DL Synchronization Test :

1. Voltage phase check


( 1 ) Short 2R/1-5, 2R/3-7, Apply 100V/50HZ to 2R1-3, Close 1ZK;
( 2 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
2AN or short
1L/11-36, check that synchrometer of synchronizer and synchrometer
of
microprocessor stop at 12 oclock after synchronizer
energized;
Result : Both meter stop at 12 oclock
( 3 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12
0clock;
Result : Synchrometer of microprocessor stops at 12 oclock
( 4 ) Open 1ZK, remove wire between 2R/1-5, 2R/3-7
2. Auto synchronization test
Select DTK to Auto mode
( 1 ) Apply 100V/50HZ to 2R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 2R/5-7 for simulation of incomer PT.Close 1ZK;
( 2 ) Set synchronizer to Test Status, close 1ZK, press 2AN or short
1L/10-34. After synchronizer energized, actuate synchronizers relay
output. Measure as following :
Item
Voltage decrease
Voltage increase
Decelerate
Accelerate
Connect order

Terminal
2R/28-30
2R/24-26
2R/20-22
2R/16-18
2R/9-11

Result
Close
Close
Close
Close
Close when phase between
30

( 3 ) Set synchronizer to Work Status, reset synchronizer, to verify that


selected connect point is 2;
Result : Connect point is 2.
( 4 ) During the synchronizer operation , short 1L/18-56, to check
synchronizer ork status:
Result : Synchronizer exit
( 5 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check that
device measurement of voltage and frequency is correct. Short 1L/21-51
or press QA ( to simulate connect order ), short 2R/13-14 after close order
sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 6 ) Verify that device exit after connect order sent;
Result : Device exit
3. Manual synchronization test
Set DTK to Manual mode

Restore voltage simulation of busbar and incomer


( 1 ) Check the following :
Item
Press manual U
decrease 1SA
Press manual U increase
2SA
Press manual accelerate
3SA
Press manual decrease
4SA
Press HA

Terminal
2R/28-30

Result
Close

2R/24-26

Close

2R/20-22

Close

2R/16-18

Close

2R/9-11

Close when phase between


30

( 2 ) Remove Vg simulation, then press HA, Verify that 2R/9-11 is open;


Result : 2R/9-11 is open

3DL Synchronization Test :


1. Voltage phase check
( 1 ) Short 3R/1-5, 3R/3-7, Apply 100V/50Hz to 3R/1-3, Close 1ZK;
( 2 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
3AN or short 1L/12-38, check that synchrometer of synchronizer and
microprocessor stop at 12 0clock after synchronizer energized;
Result : Both meter stop at 12 oclock
( 3 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12 0clock:
Result : Both meter stop at 12 oclock
( 4 ) Open 1ZK, remove wire between 3R/1-5, 3R/3-7.
2. Auto Synchronization test
Select DTK to Auto mode
( 1 ) Apply 100V/50Hz to 3R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 3R/5-7 for simulation of incomer PT. Close 1ZK;
( 2 ) Setsynchronizer to Test Status, close 1ZK, press 3AN or short 1L/1238. After synchronizer energized, actuate synchronizers relay output.
Measure as following:
Item
Voltage decrease
Voltage increase
Decelerate
Accelerate
Connect order

Terminal
3R/28-30
3R/24-26
3R/20-22
3R/16-18
3R/9-11

Result
Close
Close
Close
Close
Close when phase between
30

( 3 ) Set synchronizer to Work Status, reset synchronizer, to verify that


the selected connect point is 3;
Result : Connect point is 3.
( 4 ) During the synchronizer operation, short 1L/18-56, to check
synchronizer work status;
Result : Synchronizer exit
( 5 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check that
device measurement of voltage and frequency is correct. Short 1L/21-51
or press QA ( to simulate connect order ), short 3R/13-14 after close order
sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 6 ) Verify that device exit after connect order sent;
Result : device exit
3. Manual Synchronization Test
Set DTK to Manual mode
Restore voltage simulation of busbar and incomer
( 1 ) Check the following:
Item
Press manual U
decrease 1SA
Press manual U increase
2SA
Press manual accelerate
3SA
Press manual decrease
4SA
Press HA

Terminal
3R/28-30

Result
Close

3R/24-26

Close

3R/20-22

Close

3R/16-18

Close

3R/9-11

Close when phase between


30

( 2 ) Remove Vg simulation, then press HA, Verify that 3R/9-11 is open:


Result : 3R/9-11 is open

4DL Synchronization Test:


1. Voltage phase check
( 1 ) Short 4R/1-5, 4R/3-7, Apply 100V/50Hz to 4R/1-3, Close 1ZK:
( 2 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
4AN or short 1L/13-40, check that synchrometer of synchronizer and
synchrometer of microprocessor stop at 12 oclock after synchronizer
energized;
Result : Both meter stop at 12 oclock
( 3 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12 oclock;
Result : Synchrometer of microprocesor stops at 12 oclock
( 4 ) Open 1ZK, remove wire between 4R/1-5, 4R/3-7.

2. Auto Synchronization Test


Select DTK to Auto mode
( 1 ) Apply 100V/50Hz to 4R/1-3 for simulation of busbar PT.Apply
adjustable voltage to 4R/5-7 for simulation of incomer PT. Close 1ZK;
( 2 ) Set synchronizer to Test Status, close 1ZK, press 4AN or short
1L/13-40. After synchronizer energized,

Actuate synchronizers relay output. Measure as following:


Item
Voltage decrease
Voltage increase
Decelerate
Accelerate
Connect order

Terminal
4R/28-30
4R/24-26
4R/20-22
4R/16-18
4R/9-11

Result
Close
Close
Close
Close
Close when phase between
30

( 3 ) Set synchronizer to Work Status, reset synchronizer, to verify that


the selected connect point is 4;
Result : Connect point is 4.
( 4 ) During the synchronizer operation, short 1L/18-56, to check
synchronizer work status;
Result : Synchronizer exit
( 5 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check that
device measurement of voltage and frequency is correct. Short 1L/21-51
or press QA ( to simulate connect order ), short 4R/13-14 after close order
sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 6 ) Verify that device exit after connect order sent:
Result : Device exit
3. Manual synchronization Test
Set DTK to Manual mode
Restore voltage simulation of busbar and incomer
( 1 ) Check the following :
Item
Press manual U
decrease 1SA
Press manual U increase
2SA
Press manual accelerata
3SA
Press manual decrease
4SA
Press HA

Terminal
4R/28-30

Result
Close

4R/24-26

Close

4R/20-22

Close

4R/16-18

Close

4R/9-11

Close when phase between


30

( 2 ) Remove Vg simulation, then press HA, Verify that 4R/9-11 is open:


Result : 4R/9-11 is open

5DL Synchronization Test:


1. Voltage Phase Check
( 5 ) Short 5R/1-5, 5R/3-7, Apply 100V/50Hz to 5R/1-3, Close 1ZK;
( 6 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
5AN or short 1L/14-42, check that synchrometer of synchronizer and
synchrometer of microprocessor stop at 12 oclock after synchronizer
energized;
Result : Both meter stop at 12 oclock
( 7 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12 oclock;
Result : Synchrometer of microprocessor stops at 12 oclock
( 8 ) open 1ZK, remove wire between 5r/1-5, 5R/3-7
2. Auto Synchronization Test
Select DTK to Auto mode
( 7 ) Apply 100V/50Hz to 5R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 5R/5-7 for simulation of incomer PT. Close 1ZK;
( 8 ) Set synchronizer to Test Status, close 1ZK, press 5AN or short
1L/14-42. After synchronizer energized, actuate synchronizers relay
output. Measure as following:
Item
Voltage decrease
Voltage increase
Decelerate
Accelerate
Connect order

Terminal
5R/28-30
5R/24-26
5R/20-22
5R/16-18
5R/9-11

Result
Close
Close
Close
Close
Close when phase between 30

( 9 ) Set synchronizer to Work Status, reset synchronizer, to verify that


the selected connect point is 5;
Result : Connect point is 5.
( 10 ) During the synchronizer operation, short 1L/18-56, to check
synchronizer work status;
Result : Synchronizer exit
( 11 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check
that device measure ment of voltage and frequency is correct. Short
1L/21-51 or press QA ( to simulate connect order ), short 5R/13-14 after
close order sent, then verify that closing time is recorded;
Result : voltage measurement is OK. Closing time can be
recorded.
( 12 ) Verify that device exit after connect order sent;
Result : Device exit
3. Manual Synchronizer Test
Set DTK to Manual mode

Restore voltage simulation of busbar and incomer


( 3 ) Check the following:
Item
Press manual U decrease
1SA
Press manual U increase
2SA
Press manual accelerate
3SA
Press manuak decrease
4SA
Press HA

Terminal
5R/28-30

Result
Close

5R/24-26

Close

5R/20-22

Close

5R/16-18

Close

5R/9-11

Close when phase between


30

( 4 ) Remove Vg simulation, then press HA, Verify that 5R/9-11 is open:


Result : 4R/9-11 is open

6DL Synchronization Test:


1. Voltage phase test
( 9 ) Short 6r/1-5, 6R/3-7, Apply 100V/50Hz to 6R/1-3, Close 1ZK;
( 10 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
6AN or short 1L/15-44, check that synchrometer of synchronizer and
synchrometer of microprocesor stop at 12 oclock after synchronizer
energized;
( 11 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12 oclock;
Result : Synchrometer of microprocessor stops at 12
oclock
( 12 ) Open 1ZK, remove wire between 6R/1-5, 6R/3-7.
2. Auto Synchronization test
Select DTK to Auto mode
( 13 ) Apply 100V/50Hz to 6R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 6R/5-7 for simulation of incomer PT. Close 1ZK;
( 14 ) Set synchronizer to Test Status , close 1ZK, press 6AN or short
1L/15-44. After synchronizer energized, actuate synchronizers relay
output. Measure as following:
Item
Connect order

Terminal
6R/9-11

Result
Close when phase between
30

( 15 ) Set synchronizer to Work Status, reset synchronizer, to verify that


the selected connect point is 6;
Result : Connect point is 6

( 16 ) During the synchronizer operation. Short 1L/18-56, to check


synchronizer work status;
Result : Syncronizer exit
( 17 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check
that device measurement of voltage and frequency is correct. Short 1L/2151 or press QA ( to simulate connect order ), short 6R/13-14 after close
order sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 18 ) Verify that device exit after connect order sent;
Result : Device exit
3. Manual Synchronization Test
Set DTK to Manual mode
Restore voltage simulation of busbar and incomer
( 5 ) Check the following:
Item

Terminal
6R/9-11

Pres
s HA

Result
Close when phase between 30

( 6 ) Remove Vg simulation, then press HA, Verify that 6R/9-11 is open;


Result : 6r/9-11 is open

7DL Synchronization Test:


1. Voltage phase check
( 13 ) Short 7R/1-5, 7R/3-7, Apply 100V/50Hz to 7R/1-3, Close 1ZK;
( 14 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
7AN or short 1L/15-44, check that synchrometer of synchronizer and
synchrometer of microprocessor stop at 12 oclock after synchronizer
energized;
Result : Both meter stop at 12 oclock
( 15 ) Select DTK to Manual mode, check that syncrometer of
microprocessor stops at 12 oclock;
Result : Synchrometer of microprocessor stops at 12
oclock
( 16 ) Open 1ZK, remove wire between 7R/1-5, 7R/3-7.
2. Auto Synchronization Test
Select DTK to Auto mode
( 19 ) Apply 100V/50Hz to 7R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 7R/5-7 for simulation of incomer PT. Close 1ZK;
( 20 ) Set synchronizer to Test Status, close 1ZK, press 7AN or short
1L/15-44. After synchronizer energized, actuate synchronizers relay
output. Measure as following:
Item
Connect order

Terminal
7R/9-11

Result
Close when phase between

30
( 21 ) Set synchronizer to Work Status, reset synchronizer, to verify that
the selected connect pont is 7;
Result : Connect point is 7
( 22 ) During the synchronizer operation, short 1L/18-56, to check
synchrinizer work status;
Result : synchronizer exit
( 23 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check
that device measure ment of voltage and frequency is correct. Short
1L/21-51 or press QA ( to simulate connect order ), short 7R/13-14 after
close order sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 24 ) Verify that device exit after connect order sent;
Result : Device exit
3. Manual Synchronization Test
Set DTK to Manual mode
Restore voltage simulation of busbar and incomer
( 7 ) Check the following;
Item
Press HA

Terminal
7R/9-11

Result
Close when phase between
30

( 8 ) Remove Vg simulation, then press HA, Verify that 7R/9-11 is open:


Result : 7R/9-11 is open

8DL Synchronizer Test


1. Voltage phase check
( 17 ) Short 8R/1-5, 8R/3-7, Apply 100V/50Hz to 8R/1-3, Close 1ZK;
( 18 ) Set synchronizer to Work Status, select DTK to Auto mode, Press
8AN or short 1L/15-44, check that synchrometer of synchronizer and
synchrometer of microprocessor stop at 12 oclock after synchronizer
energized;
Result : Both meter stop at 12 oclock
( 19 ) Select DTK to Manual mode, check that synchrometer of
microprocessor stops at 12 oclock;
Result : synchrometer of microprocessor stops at 12
oclock
( 20 ) Open 1ZK, remove wire between 8R/1-5, 8R/3-7.
2. Auto Synchronization Test
Select DTK to Auto mode
( 25 ) Apply 100V/50Hz to 7R/1-3 for simulation of busbar PT. Apply
adjustable voltage to 8R/5-7 for simulation of incomer PT. Close 1ZK;

( 26 ) Set synchronizer to Test Status, close 1ZK, press 8AN or short


1L/15-44. After synchronizer energized, actuate synchronizers relay
output. Measure as following:
Item
Connect order

Terminal
8R/9-11

Result
Close when phase between
30

( 27 ) Set synchronizer to Work Status, reset synchronizer, to verify that


the selected connect point is 8;
Result : Connect point is 8
( 28 ) During the synchronizer operation, short 1L/18-56, to check
synchronizer work status;
Result : Synchronizer exit
( 29 ) Reset synchronizer. Adjust frequency and U of incomer PT. Check
that device measurement of voltage and frequency is correct. Short 1L/2151 or press QA ( to simulate connect order ), short 8R/13-14 after close
order sent, then verify that closing time is recorded;
Result : Voltage measurement is OK. Closing time can be
recorded.
( 30 ) Verify that device exit after connect order sent;
Result : Device exit
3. Manual Synchronizer Test
Set DTK to Manual mode
Restore voltage simulation of busbar and incomer
( 9 ) Check the following:
Item
Press HA

Terminal
8R/9-11

Result
Close when phase between
30

( 10 ) Remove Vg simulation, then press HA, Verify that 8R/9-11 is open;


Result : 8R/9-11 is open

Remove all short wires after the test, set DTK to exit mode,
open 1ZK, remove Vs.