Beruflich Dokumente
Kultur Dokumente
Dust generated from electric arc furnaces (EAF's) employed in steelmaking plants is currently listed as a hazardous waste because of its toxic
metgllic constituents, i.e., lead (Pb), cadmium (Cd), and hexavalent chromium
(Cr 6). Disposal of the waste at controlled landfills is not only expensive,
but also has associated long-term liability concerns. Recycling of pelletized
electric arc furnace (EAF) dust from carbon and low-alloy steel production
was evaluated through a comprehensive, experimental program at a participating
steel plant. Equipment for pelletizing the dust was evaluated, and a
3-foot-diameter disc pelletizer with an 8-inch-diameter pin mixer was
selected for the pilot trials. The experimental design was comprised of
two separate blocks of testing. Block I focused on the effects of recycling
fresh pelletized EAF dust on power consumption and other important variables,
whereas Block I1 focused on conducting a fate analysis of zinc and other
heavy metals under continuous recycling conditions.
The tests demonstrated the feasibility of pelletizing and recycling
EAF dust. Power consumption increased approximately 4 percent during
recycling. No significant change occurred in the tap-to-tap heat time. An
increase in coke consumption was noted during recycling. Because plant
operating conditions precluded the availability of high zinc-bearing scrap
for the Block I1 tests, the zinc content of the dust was almost 50 percent
lower than that in Block I. despite some degree of recycle. The zinc
content of the dust, however, increased from 9 weight percent to 15 weight
percent during the short continuous recycling period. Preliminary economic
.,analyses show that the recycling option may be a favorable one for many
steel plants.
The EAF dust recycling technology is immediately applicable; it requires only specific engineering design for a given steel plant installation and the resolution of specific permitting requirements.
89
pP &-
Introduction
Each year the electric arc steelmaking industry generates approximately 500,000 tons of dusts containing valuable metallic resources such as
iron. zinc, lead, and chr0mium.l These electric arc furnaces (EAF's) are
becoming increasingly popular for the production of carbon and low-alloy
steels and currently account for about 35 percent of total steel production. EAF dust is currently listed as a hazardous waste because of the
leachability of its toxfc constituents, i.e., lead (Pb), cadmium (Cd), and
hexavalent chromium (Cr 6 ) . Its EPA-assigned hazardous waste number is
K061. Disposal is becoming costly as disposal sites become more scarce and
remote from the point of origin. Disposal costs (including transportation)
of $100 per ton of dust are quite common. Furthermore, even with current
standards of environmentally acceptable disposal, long-term liability is a
concern. This has led the steelmaking j-dustry to look to other viable
options for handling the dust.
Alternatives to the landfilling option for EAF dust management include
chemical fixation, regional recovery processes, and onsite recycling. The
major shortcomings of the various processes suggested for recovering metallic values from EXF dust have been the high capital cost of the equipment
and the need for large quantities of dust for the processes to be economical. Furthermore, the recovery processes require dusts with zinc contents
greater than 20 percent to be economical. The zinc and lead contents of
EXF dusts from carbon and low-alloy steel production typically range from
10 to 35 percent and 1 to 5 percent, respectively. FAF dust is generally
not amenable to regional recovery processes because it is generated i n
small quantities at a large number of locations, distant from industrial
centers where regional recycling might occur.
Pelletizing and recycling to the furnaces is a logical alternative for
managing EAF dust. The recycling operations should result in the generation of a dust enriched in volatile elements such as zinc and lead; this
blowdown dust stream could be removed for sale to zinc smelters. The main
advantages of the recycling process are its low capital cost, relative
insensitivity to EAF dust composition, and applicability to both mini-mills
and large mills.
An experimental program was designed to obtain data under controlled
conditions for investigation of several critical issues for the commercial
application of recycling: 1) the partitioning (upon recycling) of heavy
metals such as zinc, lead, and cadmium between the slag and the dust generate
2) the effect of recycling on energy consumption; 3) the effect on steel
quality; and 4) the economics of recycling. The tests were conducted at
the Green River Steel EAF shop in Owensboro, Kentucky, during the summer of
1985.
Green River's Owensboro site has two 65-ton electric arc furnaces
rated at 24,000 kVA each (370 kVA/ton). The furnaces produce low-alloy and
specialty carbon steels. Oxygen is injected with hand-held pipes, lime is
injected pneumatically. Three to four charges of scrap are used per heat.
The furnaces are equipped with side-draft hoods, and canopy hoods in the
roof vented to a 14-compartment baghouse that discharges into screw conveyThese conveyors ultimately join into one cross conveyor that disOKS.
charges into a flexible tube. The dust then falls about 6 feet through the
tube into a large sealed rolloff box situated on the ground. After being
filled, this box is hauled to a hazardous waste facility.
90
91
drummed or
melt shop
weighed
prior to
Results
Results of pellet recycling were analyzed by comparison with collected
baseline data to determine the effects on heat time, power consumption,
yield, steel quality, carbon and electrode consumption, and lime and ferroalloy consumption.
The tests were conducted in two blocks. The main objective of the
Block I tests was to determine the effect of recycling fresh once-through
pellets on power consumption and other furnace variables, whereas the
primary objective of the Block I1 tests was to determine the fate of heavy
metals under continuous recycling conditions. Table I1 summarizes the data
for the heats with pellet charging In Blocks I and 11. Because the shop
operation was not continuous during the experiments, some heats were made
after the furnace had sat idle for an entire turn, whereas others were made
Immediately after the previous heat. This situation affects apparent power
use in kWh/ton and heat time regardless of pellet use. The heats are
therefore divlded into these two categories ("first heat", i.e., cold
furnace versus "not first heat", i.e., continuous operation), for more
accurate analysis. Table I11 summarizes similar data for baseline heats,
i.e., heats without pellet charging. The data for these heats were largely
obtained from the plant's heat log sheets.
During the Block I test period, both furnaces operated 16 hours per
day. During the night turn, the furnace roof was kept open and the furnaces
were allowed to cool down. The data collected during the Block I and Block
I1 tests include a variety of heats representing the normal product mix.
92
Because the plant operators were concerned about carbon loss with
pellets, they compensated for this by making carbon additions exceeding the
theoretical requirements for the pellet recycling trials. Coke consumption
during continuous operation was about 33 percent (260 lbs) higher for heats
with pellet charging although the difference does not meet the test of
statistical significance (at 5 percent level). A large portion of this
additional carbon was recovered in the bath. Electrode consumption data
were collected for the period when pellets were used in the Block I experiments and compared with the electrode consumption of the previous month.
Electrode consumption increased slightly during pellet recycling (by about
0.26 lb/net ton of steel produced).
93
In the Green River operations, pea size lime is blown into the furnace
pneumatically near the top of the furnace, above the bath line. An average
of 1.2 lb of extra lime was consumed per ton of steel produced. Comparison
of ferroalloy consumption data did not indicate any significant differences
between heats with and without pellets after adjusting for differences in
aim specifications. Observations did not reveal any noticeable change in
dust or slag generation rates due to the addition of pellets.
Economics
Table V presents the capital and annualized costs developed for three
hypothetical EAF units of different sizes. Dust generation rates for the
small, medium, and large plants were postulated to be 1,000, 3,000, and
9,000 tons per year, respectively. The economic analyses presented herein
are preliminary in nature, and must be refined for each specific plant
site. When compared to landfilling costs of $100/ton dust, the economic
analysis indicates recycling to be attractive, especially for larger plants.
Conclusions
This research has proved the concept of pelletizing EAF dust with
water only and recycling it to the furnace. The following original objectives underlying PEI's philosophy for EAF dust management have largely been
met:
'
Use of
2.
..
.
94
Element
Caa
9.17
Fea
Znb
16.7
32.1
32.9
28.2
26.9
20.9
20.6
12.9
Pbb
a
2.24
3.18
2.81
3.85
14.71
5.08
95
0.83
Comparison of data for heats with pellet charging in Blocks I and 11.
Table 11.
TOTAL OBSKRVATIONS:
14
TAPTAP
N OF CASES
MINIMU4
MAXIWIM
MBAN
STANDARD DBV
TOTAL OBSERVATIONS:
N OF CASES
MINIMU4
MAXIMlEl
MEAN
STANDARD DBV
-ED
RRS
?MI/"
14
4.830
9.670
7.319
1.217
14
536.950
670.740
616.919
40.442
TOTYIELD
NETYIELD
OPBNCRBN
14
85.550
93.800
89.909
2.752
14
79.500
93.600
86.693
3.734
14
0.070
0.471
0.270
0.120
14
0.150
NETYIBLD
OF'KNCRBN
FNAURBN
APAURBN
0.480
0.352
0.113
CoRBClwd
LBS
14
0.
3200.000
1132.143
799.425
PLLTcBllG
LBS
14
91o.oO0
2180.000
1129.286
322 .OW
24
TAPTAP
RRS
N"
24
4.500
8.000
5.872
0.953
24
493.830
672.500
560.903
37.725
PURUSW
x
24
82.500
98.900
91.231
3.656
24
65.500
93.900
85.788
5.494
24
0.050
0.860
0.349
0.203
24
0.160
0.470
0.338
0.112
CoHlcIlRO
LBS
24
1oo.oO0
2000.000
1050.000
521.703
PLLTCmG
LBS
24
100.000
2155.000
1083.542
328.019
Table 111.
TAPTAI'
N OF CASES
MINIMUM
CUXIERM
MEAN
STANDARD DBV
WTAL OBSRRVATIONS:
PWRUSBD
HRS
IwH/"
28
4.670
9.083
6.777
1.211
483.220
766.090
592.898
74.942
28
T0TYIBI.D
NEMIBLD
OPBNCRBN
28
03.400
97.100
90.118
3.438
28
73.000
ToTllIBLD
FNALCRBN
%
4.799
27
0.060
1.170
0.348
0.295
27
0.110
1.070
0.381
0.271
NBTYIBLD
OPBWCRBN
FNNCRBN
96.600
87.172
coI(BcHRG
LBS
28
0.
2500.000
1078.57 1
654.532
BRS
W OF CbSBS
MINIMIM
I(AxIMIw
HEAN
STANDARD DBV
36
4.083
9.250
6.093
1.204
PWRVSBD
IR1L?/m
35
466.440
634.440
540.882
37.959
35
85.000
96.600
91.180
2.712
35
35
71.000
95.600
87.397
4.290
0.090
1.040
0.336
0.257
35
0.100
1.060
0.350
0.203
co1[BcIIRD
LBS
28
0.
0.
0.
0.
PLLTCERG
LES
35
0.
2300. 000
788.571
546.447
PWRUSEO
TDTYIELD
LBS
35
TAPTAP
TAPTAP
PLLTCmG
--
Power used ( i n k i l o w a t t - h o u r s l t o n ) ,
Y i e l d of s t e e l as tappped a5 percentage of total m e t a l l i c charge
i n c l u d i n g scrap, f e r r o a l l o y s . and p e l l e t s .
NETYIELD = Y i e l d o f prime s t e e l as poured ( i n percentage).
OPENCRBN = Opening carbon i n bath ( i n percent).
FtlALCRBN = Flr.al t a p carbon In b a t h ( i n percent).
COKECHRG
Coke charged ( i n pounds).
PLLTCHRG P e l l e t s charged ( i n pounds).
--
I.
0.
0.
0.
0.
Table IV.
712
8/26
8/27
Block I
Constituents
Range of
daily
composite
averages
8/28
8/29
Block I1
Arithmetic
mean
Phosphorus
NDa
ND'
0.03
0.03
0.04
0.02
Sulfur
0.44-1.00
0.57
0.50
0.47
0.63
0.48
Cadmium
0.01-0.02
0.02
0.01
0.02
0.02
0.02
Calcium oxide
13.4-17.5
Chromium (+3)
0.23-1.80
0.53
0.58
0.44
0.57
0.62
Chromium (+6)
NDa
N D ~
0.00
0.006
0.003
0.002
Copper
0.07-0.10
0.09
0.09
0.08
0.13
0.10
Iron
16.7-21.1
Lead
0.47-0.70
0.66
0.66
0.58
0.65
0.65
Magnesium
1.76-2.02
1.88
3.63
2.29
2.64
2.77
Manganese
2.60-3.30
3.10
5.0
3.5
4.5
4.4
Molybdenum
0.05-0.80
0.35
0.14
0.16
0.37
0.33
Nickel
0.12-0.17
0.14
0.29
0.24
0.27
0.27
Potassium
0.70-1.00
0.80
1.0
1.0
1.2
1.1
Silica (SiO,)
1.50-3.20
2.00
3.1
2.8
3.0
3.1
Sodium
0.50-0.60
0.58
0.5
0.5
0.7
0.7
<0.01
co.01
<0.01
co.01
c0.01
12.4
12.3
14.7
Vanadium
Zinc
CO.01
20.1-27.9
19.0
15.3
18.3
24.4
24.8
9.0
a Not detected.
98
. . . - ,. .. ,
. ,.
. I C * ,
15.1
21.2
18.1
26.7
16.1
28.5
Table V .
Medium
130.000
19.500
200.000
33,280
0
33,28G
0
66.560
2.000
6.000
75c
38,OOC
13.000
3,000
20,000
9,000
22,500
41,700
64,220
2.100
3.900
6.000
8,400
17.370
14.000
28,950
Total capital
Manufacturing costs
Raw material
1I
Uti 1 i t ies
Electricity
Uater
06M supplies (10: of FCl)
Lab charges (Illton)
T o t a l Manufacturing costs
25C
7.000
.___
-1 . m
2.25G
43.500
Fixed charges
Equipment payments
(5 yr loan @ 14'1)
includes working capital
Local taxes 1 insurance
(3% of FCl)
Office Management
and Administration
HOm
Other
-
Freight
10.000
85.500
i
85.50
99
90.000
232.500
41.33
30.000
124.000
25.83
BAGHOUSE
FLEXIBLE
TUBE
.......................
TEMPORARY SHELTER
I
I
EX IST I NG
ROLLOFF
BOX
Figure 1.