Beruflich Dokumente
Kultur Dokumente
RESEARCH ARTICLE
ABSTRACT
Micro-generation is being widely promoted as a way for householders in the UK and elsewhere to take part in the Green
Revolution. Building-integrated wind turbines (BIWTs) provide a way to do this, enabling people to reduce their contribution to the problems of both climate change and decreasing fossil fuel availability. Although energy yields from
BIWTs for many householders have been shown to be low, there are still situations where such turbines can make a useful
contribution to electricity generation, e.g. in windier areas and for isolated detached buildings. The standards for the
installation of BIWTs are still being developed including those for the safe mounting of turbines on domestic buildings.
This paper investigates the current trend for mounting small wind turbines on the walls of domestic premises and compares
this with an approach which uses roof timbers. It identifies the main characteristics of building construction which affect
the integrity of such installations. European and British standards have been used to calculate wind and gravitational
loads. Finite element models are used to derive working stresses and, hence, some basic principles of good design. The
likely costs of wall and roof mounting are then compared. Installation and health and safety issues are also examined
briefly. Copyright 2010 John Wiley & Sons, Ltd.
KEYWORDS
building-integrated wind turbine; wind loads; finite element modelling
Correspondence
S. Watson, Centre for Renewable Energy Systems Technology, Electronic and Electrical Engineering Department, Loughborough
University, Ashby Road, Loughborough, LE11 3TU, UK.
E-mail: s.j.watson@lboro.ac.uk
Received 23 March 2009; Revised 26 November 2009; Accepted 29 November 2009
1. INTRODUCTION
Micro-generation is being promoted by politicians, media
and commercial organizations alike as a way for householders in the UK and elsewhere to take part in the Green
Revolution. Building-integrated wind turbines (BIWTs)
provide a way to do this, enabling people to reduce their
contribution to the problems of both climate change and
decreasing fossil fuel availability. Recent trials of BIWTs
have indicated that energy yields have been disappointing1
and simulations of expected yields in urban areas have
predicted low capacity factors.2 Nonetheless, there are
Copyright 2010 John Wiley & Sons, Ltd.
2. METHODOLOGY
The approach adopted here was firstly to understand the
loads which buildings and small wind turbines are normally subject to. A datum building geometry was defined
and has been used throughout the work; in addition, the
effects of changing some of the geometric parameters have
been evaluated. Then an understanding of material capabilities was developed in order to assess how close to the
limits building stresses are with and without a turbine
attached. And finally, finite element (FE) analysis has been
used to assess different mounting arrangements and to set
practical limits on wind turbine size and mounting
position.
658
(1)
(2)
Section 2.1.1 with a ceiling load (for a loft used for storage
only) of 0.55 kN/m2 and half of the maximum imposed
load calculated in BS 6399-3,12 which accounts for snow
loads.
2.2. Datum building geometry
A small building with internal dimensions 5 m 5 m
5 m, excluding the roof, has been selected since it is the
largest practical size where a close couple roof (i.e. one
that does not require purlins) can be made using readily
available timbers,13 and hence, the timber stresses are
relatively high.
The foundations were modelled by extending the walls
to 0.5 m below ground level. To keep the model simple,
no windows or doors were included. This is not unreasonable as apertures are generally remote from the highly
stressed regions.
Each wall used a cavity construction with two leaves
100 mm thick, separated by a 50 mm gap. These dimensions were chosen because of their common use.13 The
leaves are assumed to be joined by wall ties spaced as
recommended in BS 5628-1,5 i.e. 2.5 ties per square metre.
Using guidance from Foster,13 the ceiling joists and
rafters were spaced 0.5 m apart and measured 100 mm
deep by 50 mm thick. The ceiling joists were joined by a
binder of section 75 mm 50 mm which was joined to a
ridge board of section 175 mm 32 mm by hangers of
section 50 mm 38 mm (see Figure 1). Note the noggings
(green), which attach the end rafters to the gable ends via
steel straps12 and the wind turbine support (cyan).
Ridge Board
Hanger
Binder
Ceiling Joist
Rafter
Wall Plate,
(underside fixed to the inside skin of the non-gable wall)
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
659
660
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
4 off C,
Brackets
2 off H,
Brackets
Dual Tripod,
Triple Tripod
0.9m
1.2m
1.3m
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
661
Non-Gable Wall
3. RESULTS
3.1. Wall mounting
Unless otherwise stated, stress refers to the vertical
tensile stress. The results for the wall mounting arrange-
662
Height above
ridge (m)
Description
Support
spacing (m)
Wall
Acceptable?
2
2
2
2
2
2
5
2
2
2
2
Tripods 2
Tripods 3
Tripods 2
Tripods 2
Tripods 2
Tripods 2
Tripods 2
C Brakt 4
C Brakt 4
H Brakt 2
H Brakt 2
0.75
0.6
0.75
0.75
1.2
1.2
1.2
0.9
0.9
1.3
1.3
Non-gable
Non-gable
Non-gable
Gable
Gable
Gable
Gable
Gable
Gable
Gable
Gable
0.58
0.52
0.16
0.34
0.21
0.11
0.37
0.84
0.16
0.82
0.23
0.68
0.57
0.31
0.36
0.32
0.14
0.46
0.85
0.36
0.59
0.23
No
No
No
No
No
Yes
No
No
No
No
Yes
Figure 5. Sub-model stresses for dual tripod mount excluding bulk effects of wind and gravity.
663
Traditional
Traditional
Traditional
Traditional
Traditional
Traditional
Modern
664
Turbine power
(kW)
Height above
ridge (m)
Wind direction
Approx peak
stress (MPa)
Design speed
Acceptable?
1.5
0.4
1.5
0.4
1.5
0.4
1.5
2
5
2
5
2
5
2
Non-gable
Non-gable
Gable
Gable
Non-gable
Non-gable
Gable
5.8
7.9
4.4
6.1
12
17
34
1
1
1
1
2
2
1
Yes
Yes
Yes
Yes
Yes
No
No
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
7.9 MPa. Note that 30% of this stress was due to the aerodynamic drag on the support pole.
With the wind approaching the gable end, the peak
stress occurred in the rafters at the attachment points (see
Figure 7). When the bolt hole and the PSF of 1.4 were
accounted for, a realistic peak stress of 4.4 MPa was calculated for the large machine mounted 2 m above the ridge
line.
Repeating the assessment with the small turbine
mounted 5 m above the ridge gave a peak stress of
6.1 MPa. This is approximate only as much depends on
the diameter of the support pole.
The stresses have so far been assessed against the limit
parallel to the grain. This is reasonable at the ridge board,
but the rafters are at such an angle that cross grain stresses
become more important and these would increase as the
pitch angle of the roof increased. It is, therefore, recommended that some rig testing is carried out to establish
accurate limits. Alternatively, a significant reduction in
rafter stresses can be obtained by adding an additional
angled brace from the bottom of the support pole to a
position on the ridge board between the 3rd and 4th rafters.
This ensures that the non-gable wind is the limiting case.
This additional brace also markedly decreases the deflection of the wind turbine and thereby keeps the axis of blade
rotation closer to the horizontal giving better yawing
behaviour.
For the same heights above the ridge line, the roof is
capable of supporting turbines around twice the sizes of
the ones considered above. It is estimated that the large
machine could be mounted up to 4.2 m above the ridge
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
665
666
above the roof line, the size limit is around 2/3 of the large
machine, i.e. a swept area of 4 m2.
4. DISCUSSION
Computational fluid dynamics modelling from Renewable
Devices, cited in Renewable Devices,20 predicts the wind
speed over a 4 m pitched roof building where the pitch
angle is around 15o and the wind approaches perpendicular
to the building. This shows a maximum speed-up effect of
approximately 2 m s-1 but also high wind shear for 2 m
above the ridge height. However, it should be noted from
Encraft 20091 that this speed-up effect is reduced if the
building is within an urban area as opposed to an isolated
location. High wind shear generates high cyclic stresses
which reduce component life and this is in addition to
turbulence effects. As the pitch of the roof increases, wind
shear effects and turbulence are likely to increase, but
more work is required to quantify these effects. All that
can be said here is that to maximize energy capture and
turbine life, turbines should be mounted well above the
ridge. Manufacturers recommend that wind turbines be
mounted greater than 1 m above the roof line and the
height of 2 m used in this paper is commonly used. The
energy that can be captured will increase as the turbine is
mounted further above the ridgeline, but there are often
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
Figure 8. Modern trussed rafter construction: peak stress position due to turbine load only.
667
6. CONCLUSIONS
From the research presented, a number of conclusions can
be drawn:
Both the 400 W and the 1.5k W wall-mounted turbines, mounted 2 m above the ridge line, cause mortar
stresses in excess of those suggested by BS5628,5 but
so do wind alone loads calculated by BS6399.3
Of the various wall mountings considered, the dual
widely spaced tripod arrangement was the best but
gave an acceptable solution for the small (1.9 m2
swept area) turbine only. It could support the small
machine to a maximum height of 3.2 m above the
ridge line.
A traditional close couple roof was shown to be four
times as capable of absorbing the loads as the brick
wall. It could support the large (6 m2 swept area)
turbine at 4.2 m above the ridge.
A typical trussed rafter roof was capable of supporting a machine with a 4 m2 swept area 2 m above the
ridge. However, it would be possible to design a
special truss capable of supporting larger machines
and fix this to standard trusses in the usual way.
More work is needed to understand the wind strength
above domestic housing, but mounting from roof
timbers is both viable and, at a small extra initial cost,
likely to provide solutions with more structural integrity and shorter payback times than those using brick
walls.
ACKNOWLEDGEMENTS
The author would like to express his gratitude to Mr A.
Wilson of NaREC for his helpful advice. Thanks also to
Mr J. Gardiner of J G Design Services for his development
of the FE code throughout the project.
REFERENCES
5. WALL AND ROOF MOUNTING
RELATIVE COSTS
Most of the support structure for a roof-mounted machine
is internal so, compared to a wall mounting, appearance
and corrosion are less important issues. For the supports,
much use could be made of conventional scaffolding.
Besides being relatively cheap and readily available, the
mechanical integrity of scaffolding tubes and couplings is
covered by BS1139-1.124 and BS1139-2.2.25 Overall costs
for roof and wall mounting are expected to be similar.
The main difference will be in the roof modifications
which involve the cost of replacing a ridge tile with a ridge
vent.26 This is likely to add only 510% to the total cost
of installation of a roof-mounted turbine compared to a
wall-mounted device.
668
Wind Energ. 2010; 13:657669 2010 John Wiley & Sons, Ltd.
DOI: 10.1002/we
669