No Formula.
No Formula. It is sometimes
expressed as a %age of BAC.
No Formula. It is sometimes shown as
a %age of BAC or PV.
No Formula.
SV = EV PV
CV = EV AC
SPI = EV / PV
SPIC =EV / PV
CPI = EV / AC
CPIC = EV / AC
100
Project %
Complete
ETC
EAC
VAC
TCPI
100
ETC = (BAC EV) / CPI
ETC = (BAC EV)
ETC = (BAC EV) / CPIp
EAC = AC + ETC
EAC = AC + (BAC EV)
EAC = AC + (BAC EV) / CPI
EAC = BAC / CPI
EAC = AC + [(BAC EV) / (CPI * SPI)]
VAC = BAC EAC
TCPI = (BAC EV) / (BAC AC)
TCPI = (BAC EV) / (EAC AC)
Estimation
Network Diagram
Total Float
Free Float
TF = LS ES
TF = LF EF
FF = ESSuccessor ESPresent DurPresent
PV / DCF
NPV
ROI
BCR
CBR
IRR
Payback
Period
No formula. Lesser the better.
Opportunity
Cost
No formula.
E = (O + P + M) / 3
Triangular
+
=
Distribution
18
E = (O + P + 4*M) / 6
PERT
= (P O) / 6
Range Est.
R = E (n * )
Activity Var. Var = 2
Path Var.
VarPath = (Var)
Path St.
=
Deviation
1 = 68.27%
2 = 95.45%
3 = 99.73%
4 - 99.994%
5 = 99.99994%
Sigma Values 6 = 99.999999%
Communication Channels
Expected Monetary Value
EMVR
EMVP
Net Benefit
C = n*(n 1) / 2
EMVR = P * I
EMVP = EMVR
Net Benefit = EMVP Cost
Procurement
Pt. of Total
Assumption
=
+
!" #$%&
Version: 1.0a
Release Date: January 01, 2015
Budget At Completion
Planned Value
Earned Value
Actual Cost
Schedule Variance
Cost Variance
Schedule Performance Index
SPIC
CPI
CPIC
ETC
EAC
VAC
TCPI
Network Diagram
TF
FF
ES
LS
EF
LF
Dur
Estimation
Total Float
Free Float
Early Start
Late Start
Early Finish
Late Finish
Duration
E
O
P
M
SD
St. Deviation
Var
VarPath
n
Present Value
Discounted Cash Flow
Future Value
Discount Rate
Number of years
Discount Factor
Net Present Value
Return on Investment
Benefit Cost Ratio
Cost Benefit Ratio
Internal Rate of Return
Communication Channels
C
n
Procurement
Expected Value
Optimistiv Value
Pessimistic Value
Most Likely Value
PTA
Pt. of Total
Assumtion
CP
TP
TC
Explanation of Formulas
For complete explanation of formulas refer to
http://www.pmbypm.com
Copyright
This pocket is compiled by Praveen Malik and is
available without any cost at
http://www.pmbypm.com. It can be used for
individual study and may not be used for commercial
purposes. Unathorized copying, modification, or
distribution is not allowed.
Copyright 2015
http://www.pmbypm.com
Version: 1.0a
Release Date: January 01, 2015