REPORT TO ACCOMPANY THE

ESTIMATE
AMOUNT Rs 2037000.00

This estimate is for Supply of MS Steel, Fabrication of Steel Structures ,Painting


and Erection of Steel Structures ,Supply of Steel and Erection of Station Earth mat
,Earth Electrodes, Earth Risers for Pole and Supply of Steel ,Fabrication, Painting of First
Primer, and First Finish coat Erection of Minor Steel Structures, Supply & Earthing of
Steel

Materials,

Providing

Earth

bore,

Erection

of

Switchgear,Strung

Bus,Isolators,Busbars,Cabling and Termination, Supply and Erection of Station Auxiliaries


etc at at Krishnapuram 110/22kv ss for the Conversion of Grid ss Under DCW Basis in
Perambalur electricity Distribution circle/Perambalur. The rates are adopted as per SSE

common cost data and current PWD schedule of rates.


This scheme has been administratively approved vide B.PNO:395 dated
03.09.2010.
The details of works involved are as follows:1) Supply of iron& steel, fabrication, first coat painting and erection of steel structures.
2) Supply of earthing materials for erection of earth mate, equipment earthing and earth
electrode.
3) Erection of Switchgears,and station auxiliaries etc.,
4) Erection of control & relay panels, Laying of cables and cable terminations.

Counter Signed

Counter Signed

EXECUTIVE ENGINEER
SUBSTATION ERECTION
TRICHY

ASSISTANT EXECUTIVE ENGINEER


SUBSTATION ERECTION
PERAMBALUR

ASSISTANT ENGINEER
SUBSTATION ERECTION-II
PERAMBALUR

TAMILNADU TRANSMISSION CORPORATION


From
K SRIDHAR B.E

To

ASSISTANT ENGINEER
SUBSTATION ERECTION-II
PERAMBALUR

ASSISTANT EXECUTIVE ENGINEER


SUBSTATION ERECTION
PERAMBALUR

Lr No:-AE/SSE-II/PBLR/FREV..KRISHNAPURAM 110/22KV SS/D


Sir,

/2012Dt 23.6.2012

SUB:-ElectricityRe-Revised Labour estimate as per cost data20112012 for the proposed Krishnapuram 110/22KV Substation into Grid ssSubmission-Regarding
Herewith I enclosed the following Estimate for the proposed Krishnapuram 110/22kv ss
into Grid Substation under the newly revised cost data for the year 2011-2012..This scheme
has been administratively approved vide B.PNO:395 dated 03.09.2010.

Sl
NAME OF WORK
No
01 Supply of MS Steel, Fabrication of

AMOUNT

Steel Structures
,Painting and Erection of Steel Structures ,Supply of Steel
and Erection of Station Earth mat ,Earth Electrodes, Earth
Risers for Pole and Supply of Steel ,Fabrication, Painting
of First Primer, and First Finish coat Erection of Minor
Steel Structures, Supply & Earthing of Steel Materials,
Providing Earth bore ,Erection of Switchgear, Strung
Bus,Isolators,Busbars,Cabling and Termination, Supply
and Erection of Station Auxiliaries etc at Krishnapuram
110/22kv ss for the Conversion of Grid ss Under DCW
Basis

Rs2037000.0
0

Copies
enclosed

Two

I request that the estimate may be forwarded for early sanction please.
K SRIDHAR
ASSISTANT ENGINEER
SUBSTATION ERECTION-II
PERAMBALUR

Endt No:-AEE/SSE/PBLR/C
/F.KRISHNAPURAM 110/22KV SS /2012Dt
Sir,
Submitted to EE/SSE/TRICHY for favour of furthur action please.

.6.2012

ASSISTANT EXECUTIVE ENGINEER


SUBSTATION ERECTION
PERAMBALUR