QA Activities
Requirement Analysis
Ad hoc testing
Test case development including Peer review and updates
Functional
Test lead/Coordination/status reporting efforts
Execution
UAT
UAT Support
At times, development team may need QC team to simulate the bug as it may not arise in development environment which nee
additional effort
A Group Estimate :
Comments/Remarks
10
10
10
30
7
77
40
40
81
Assumed 3 days approx for defect testing by 3 resources. Any pending open defects
based on exit critieria and stability of the product
170
17
187
40
10
66
since its highlevel and not full scope known on scenarios etc, Hence considered
25% as per TCOE process
100
30
510
73
Assumed 8hours/ day but actual productivity on testing excluding status calls,
meetings, discussions, etc considered 7 hours/day