DURATION OF CONTRACT
The contract for the CIVIL WORKS FOR THE IMPROVEMENTS,
RENOVATIONS AND REHABILITATION OF BIR ANNEX BUILDING AND
BIR-RR-1 COMPOUND IN CALASIAO, PANGASINAN shall be within
one hundred forty (140) working days from receipt of Notice to Proceed.
II.
SCOPE OF WORKS
The CONTRACTOR shall cover the CIVIL WORKS FOR THE
IMPROVEMENTS, RENOVATIONS AND REHABILITATION OF BIR
ANNEX BUILDING AND BIR-RR-1 COMPOUND IN CALASIAO,
PANGASINAN which shall include but not limited to the following:
II.1
II.2
II.3
CONSTRUCTION WORKS
Air-conditioning System
2.4.11.1 Supply and installation of eleven (11) 2.0 HP, split type
Air-conditioning Units.
2.4.11.2 Supply and installation of appropriate supply lines,
conduit works including individual circuit breakers.
2.4.11.3 Supply and installation of necessary mechanical parts
(copper pipes, platforms, steel brackets/supports, rubber
insulations, condensate drains, etc.)
2.4.12
II.5
WATERPROOFING
PAINTING WORKS
SAFETY ENCLOSURES
III.
COMPONENTS
DESCRIPTION
3.1 Completion
and Acceptance
of the project in
its entirety.
3.2
Documentations
IV.
LIQUIDATED
DAMAGES
One percent (1%) of the
total contract price for
every day of delay.
TERMS OF PAYMENT
V.1 The CONTRACTOR shall be paid upon completion of the project subject
to the required Expanded Withholding Tax (EWT) of two percent (2%)
and Final Withholding Tax on VAT of five percent (5%).
V.2 Once a month, the contractor may submit a statement of work
accomplished (SWA) or progress billing and corresponding request for
progress payment for work accomplished. The procuring entitys
representative/project engineer shall check the contractors monthly
SWA and certify the amount to be paid to the contractor as progress
payments.
V.3 Progress payments are subject to retention of ten percent (10%)
referred to as the retention money. The total retention money shall
be due for release upon final acceptance.
V.4 The BIR has the right to deduct from the contractors progress billing
such amount as may be necessary to cover third party liabilities. It
must not process any progress payment unless the discovered defects
are corrected.
V.5 Payment shall be made within reasonable time from submission of the
required documents based on existing BIR issuances.
V.6 The method of payment to be followed shall be the unit price
payments which will be based on the unit prices of specific items as
applied to actual quantities accomplished according to the Statement
of Work Accomplished, and duly certified by the designated field
Project Inspector from the Department of Public Works and Highways.
V.7 Advance payment shall be made as provided in item 39 of the
Procurement of Infrastructure Projects of the Government of the
Republic of the Philippines, 4th Edition, as supplemented by COA
Circular No. 2012-001 dated June 14, 2012 upon compliance with the
conditions stated therein.
VI.
PRE-TERMINATION OF CONTRACT
VI.1
The contract for the CIVIL WORKS FOR THE IMPROVEMENTS,
RENOVATIONS AND REHABILITATION OF BIR ANNEX BUILDING AND BIRRR-1 COMPOUND IN CALASIAO, PANGASINAN may be pre-terminated
by the BIR for any violation of the terms of the contract. In case of pretermination, the CONTRACTOR shall be informed by the BIR fifteen (15)
days prior to such termination.
VI.2
In case of pre-termination, the CONTRACTOR shall be liable to an
additional liquidated damages equivalent to one percent (1%) of the
contract price as provided by the Government Accounting and Auditing
Manual (GAAM) and forfeiture of the performance Security.
VI.3
The BIR shall have the right to blacklist the CONTRACTOR in
case of pre-termination.
Prepared by:
MARIO R. FABRICANTE
Recommending Approval: