Beruflich Dokumente
Kultur Dokumente
10
Safety
system
PSH
230
T. L. BLEVINS, M. NIXON
UC
400
(2005)
PS
220
PS
250
A. OPC server
B. Serial interface
C. DCS gateway
INTRODUCTION
The reinstrumentation of an existing process or the construction of a new plant often involves interfacing to intelligent external devices or subsystems. For example, the
safety system that protects a critical piece of equipment
may be an integral part of and is provided by the equipment
manufacturer.
Devices as a motor starter may include embedded logic,
diagnostics, and support for digital communications to access
this added information. When an existing plant is being
expanded, the process control system selected for the expansion may not be the same as that used in the existing plant.
To provide safe and efficient plant operation, it is important
to fully integrate these external devices and subsystems into
the new control system.
Integration provides the plant operator with a single window interface into all functions of the complete process.
Related process information may be included in the operator
displays. This way, the operator is provided with consistent
presentation of process alarming and trending and consistent
means of changing set points or modes of operation. This
makes it possible to provide a single login and span of control.
EXISTING SYSTEMS
When a new plant area is added or expanded, the operators
often need to know the conditions in the existing plant section
in order to maintain a coordinated operation. Similarly, the
700
2006 by Bla Liptk
OPC
server
701
OPC
server
1
OPC interface
Controller
Controller
Highway
gateway
2
Serial interface
3
Serial interface
New control system
FIG. 4.10a
Three methods of integration of an existing DCS system and a new control system can be obtained by the use of three types of interfacing:
1) OPC interface, 2) serial interface to highway gateway, or 3) serial interface to serial port.
MODBUS on
TCP
TCP
IP
Other
Other
MODBUS+/
HDLC
Physical layer
Master/Slave
Ethernet 802.3
EIA/TIA-232 or
EIA/TIA-485
Ethernet physical
layer
FIG. 4.10b
Integration of existing and new DCS systems using MODBUS interfacing.
702
Support for MODBUS continues to be strong. Most vendors have built-in support for master/slave stacks over serial
and/or TCP/IP. The Internet community can access MODBUS
at a reserved system port 502 on the TCP/IP stack.
Some manufacturers may also provide a gateway device
that can be used to interface to external systems. These
devices are often provided to connect different revisions of
equipment from the same manufacturer. Thus, such interfaces
may rely on a proprietary communication protocol and limit the
types of information that may be accessed through this interface.
OPC Interface
OPC (OLE for Process Control, where OLE stands for Object
Link Embedding) is based on Microsoft Windows COM
(Component Object Model) architecture. OPC was developed
by the OPC Foundation and provides standard software inter1
face to hardware databases. The three basic types of servers
it provides are for 1) data access, 2) alarm and events access
and 3) historical data access, as shown in Figure 4.10c.
Most modern process control systems support information exchange based on the OPC Foundations Data Access
Specification Version 3.0, March 2003. This process industry
standard was created through a collaborative effort of leading
automation suppliers and Microsoft. The specification defines
a standard set of objects, interfaces, and methods that facilitate data interoperability. Many manufacturers offer OPC
servers that may be added to older DCS systems. Where such
capability exists, it is to exchange a large number of readings
between control systems.
On the other hand, the OPC approach has several disadvantages. One is that the addition of the OPC servers may
be more costly than using a serial interface (Figure 4.10a).
These interfaces tend to be time consuming to configure
Alarm
display
Graphics
display
Trend
display
OPC Historical
OPC Alarm/Event
Alarm server
(SQL)
Trend server
(SQL)
Fieldbus
Conventional
Any
MODBUS
Most
legacy
FIG. 4.10c
The three types of OPC servers are: 1) DA, data access, 2) A&E,
1
alarm and events, and 3) HAD, historical data access.
MOTOR CONTROLS
Analog measurements and actuator signals represent only a
fraction of the total inputs and outputs of process control
systems. The remaining inputs and outputs are discrete. They
Process controller
Process controller
Low voltage
control output and
discrete status
input
703
Fieldbus
FIG. 4.10d
Traditional and fieldbus-based interfacing of motor starters.
704
Hardwired
shutdown
switch
Process controller
Serial interface
Safety system
I/P
23
PT
22
Solenoid
PT
21
Process
FT
23
Blocking valves
PT
23
FIG. 4.10e
The integration of the safety instrumented system (SIS) into the overall process control system.
SIS (Figure 4.10e) to avoid the need for all process control
systems to meet SIS requirements.
As it is illustrated in this example, the process input
signals to the safety system are separate and independent
from those used by the process control system. The outputs
of the safety system are also designed to act independently
from the process control system. For example, a solenoid
valve may be placed into the air tube between the I/P converter and the control valve actuator.
In this configuration, when the SIS system requires that
the solenoid be energized, it will cause the control valve to
take up a safe position, i.e., open or closed. Also, the safety
system output may activate blocking on/off valves that stop
or divert process streams from their normal flow-paths,
regardless of the signals received from the process control
system.
As the safety system overrides the normal operation of
the throttling control valves of the process control system
and prevents the controllers from returning their controlled
variables to set point, the integral action is likely to saturate
the controllers output. The consequence of this is that when
the SIS system returns to normal, the control loop output is
still saturated and is not ready to take control.
To avoid any upsets this could cause, when the safety
system returns to normal, it also provides a status input to
the process control system. If the process control system has
maintained or memorized the controller output that existed
before the SIS episode, that output value can be automatically
set to provide smooth recovery.
The safety system status may be simply provided to the
process control system as a discrete input. However, a serial
705
Reference
1.
SIS controller
Process controller
FIG. 4.10f
The system configuration if SIS controller support is available in
the process control system.
CONCLUSIONS
Modern process control systems support a variety of communication interfaces. These may be used to integrate information from intelligent external devices, subsystems, and
existing DCS systems into the total process control system
of the plant. Where the products of several manufacturers are
used, it may be necessary to implement proxies in the controller, which can be used to map the information from these
other suppliers to its equivalent representation in the total
control system of the plant.
Bibliography
Fan, X.-G., Wang, Z., Sun, Y.-X., and Wang, L., OPC Based Ethernet Control
and Management, Information and Control, Vol. 32(2), pp. 113117,
2003.
Hoon, P. S., and Huan, Y. R., FOUNDATION Fieldbus Systems Integration Using OPC, Technical Papers ISA, Vol. 397, pp. 143152,
1999.
Janke, M., OPCPlug and Play Integration To Legacy Systems, IEEE
Conference Record Annual Pulp and Paper Industry Technical Conference, pp. 6872, 2000.
Kleines, H., Zwoll, K., and Sarkadi, J., Integration of Industrial Automation
Equipment in Experiment Control Systems via PROFIBUS
Developments and Experiences at Forschungszentrum Julich, IEEE
Transactions on Nuclear Science Ns, Vol. 47(2p1), p. 229, 2000.
Luth, J., OPC Brings XML-DA to the Factory Floor, Control Solutions,
Vol. 75(7), pp. 3436, 2002.
Macias-Hernandez, J. J., and Feliu, J. A., Dynamic Simulation and OPC,
Hydrocarbon Engineering, Vol. 8(9), pp. 5358, 2003.
OPC DA 3.00 Specification, Data Access Automation Interface Standard,
www.opcfoundation.com, 2003.
PROFIBUS Organization, Specification for PROFIBUS Device Description
and Device Integration Volume 3: FDT V1.1, Karlsruhe, Germany,
November 2000.
Spear, M., Bridging the Data Gap, Process Engineering, Vol. 81(3), p. 25,
2000.
Wang, X. Z., Garcia-Flores, R., Hua, B., and Lu, M. L., Advanced Information Systems for Process Control and Supply Chain Integration, Computer Aided Chemical Engineering, Vol. 15(A), pp. 636641, 2003.