Beruflich Dokumente
Kultur Dokumente
This article
demonstrates
how the
principles of
ISPE's C&Q
Baseline Guide
can be applied
to a cycle
development
program at a
modern biotech
manufacturing
facility.
Reprinted from
PHARMACEUTICAL ENGINEERING
Introduction
IP Cycle Development (CD) is a systematic approach of setting CIP systems to work in a manner that promotes rapid and successful execution
of Cleaning Validation (CV) activities. The
Cycle Development program is an integral part
of the overall commissioning of a facility and its
processes. It is not enough to merely confirm
tubing, valves, pumps, controllers, and instrumentation are installed as designed, functioning as specified, and within acceptable tolerances. The act of running a cleaning cycle, and
confirming the software and associated control
elements respond as expected (or functional
testing) does not constitute Cycle Development.
All of these activities are elements that must
take place prior to Cycle Development, but do
not provide for development of a cleaning cycle.
Cycle Development employs CIP skids that
have been commissioned, and through a three
Background
Cycle Development (CD) typically occurs after
CIP and support systems are mechanically
complete and prior to Cleaning Validation (CV)
execution. CD is one subset of activities within
the overall commissioning effort. The ISPE
Baseline Guide on Commissioning and Qualification (C&Q) can be applied to plan and execute an organized and efficient CD program.
Figure 1. Overview of
CD testing program and
cleaning validation
prerequisites.
CIP Circuit
Circuit
Name
Unique/
Clone
performance testing
Tank
Inlet Line
Outlet Line
Tank
Inlet Line
Outlet Line
Tank
Inlet Line
Outlet Line
Tank
Outlet Line
Tank
Outlet Line
Tank
Outlet Line
Tank
Outlet Line
B-C01
B-C02
B-C03
B-C04
B-C05
B-C06
B-C07
B-C08
B-C09
B-C10
B-C11
B-C12
B-C13
B-C14
B-C15
B-C16
B-C17
Unique
Unique
Unique
Clone
Clone
Clone
Unique
Unique
Unique
Unique
Unique
Unique
Unique
Clone
Clone
Unique
Unique
Commissioning Schedule
Budget, Pre-Delivery Inspection Plan, and Report
Factory Acceptance Plan and Report
On-Site Inspection Plan and Report
Functional Test Plan and Report
Commissioning Plan Summary Report.
Generating a Schedule
A facility test matrix can then be developed to aid in the
calculation of manpower requirements - Table B. This is
necessary for generating a realistic Commissioning Schedule
as required by the C&Q Guide.
Copyright ISPE 2004
Unique/Clone
Work-days per
Water Test Run
Work-days per
Chemical Test Run
Work-days per
Soiled Test Run
Total Work-days of
CD Field Work
Clone
Unique
Unique
Clone
Clone
Unique
Unique
Unique
Unique
Unique
Clone
Clone
Unique
Unique
Unique
Unique
Unique
0.5
1
1
0.5
0.5
1
1
1
1
1
1.5
1.5
3
3
3
3
3
0.25
0.5
0.5
0.25
0.25
0.5
0.5
0.5
0.5
0.5
0.5
0.5
1
1
1
1
1
0.25
0.5
0.5
0.25
0.25
0.5
0.5
0.5
0.5
0.5
0.5
0.5
1
1
1
1
1
1
2
2
1
1
2
2
2
2
2
2.5
2.5
5
5
5
5
5
47
55
59
44
205
B-C05
Inlet Line
B-C02
Inlet Line
B-C09
Inlet Line
B-C07
Outlet Line
B-C15
Outlet Line
B-C03
Outlet Line
B-C10
Outlet Line
B-C12
Outlet Line
B-C13
Outlet Line
B-C17
Outlet Line
B-C04
Tank
B-C14
Tank
B-C01
Tank
B-C08
Tank
B-C11
Tank
B-C12
Tank
B-C16
Tank
Total Man-days of CD Field Work in Buffer Prep
Total Man-days of CD Field Work in Fermentation
Total Man-days of CD Field Work in Media Prep
Total Man-days of CD Field Work in Purification
Total Man-days for CIP Cycle Development
Contact Time(minutes)
3 minimum
Media
3 minimum
Fermentation
5 minimum
Purification
5 minimum
Department
Buffer
Contact Time(minutes)
3 minimum
Media
3 minimum
Fermentation
5 minimum
Purification
5 minimum
Department
Contact Time(minutes)
Line Cleaning
Temperature
Ambient rinse
Ambient wash
Ambient rinse
60oC wash
Ambient rinse
60oC wash
Ambient rinse
60oC wash
Vessel Cleaning
Temperature
Ambient rinse
Ambient wash
Ambient rinse
60oC wash
Ambient rinse
60oC wash
Ambient rinse
60oC wash
TFF Cleaning
Temperature
Rinse : 5 minimum
Rinse : Ambient
All Departments
Supply Conductivity
WFI rinse
WFI wash
WFI rinse
0.6 mS
WFI rinse
0.6 mS
WFI rinse
0.3 mS
Cleaning Action
3-5x holdup volume turnover
at 5ft/sec velocity minimum
Supply Conductivity
WFI rinse
WFI wash
WFI rinse
0.6 mS
WFI rinse
0.6 mS
WFI rinse
0.3 mS
Cleaning Action
Achieve FAT sprayball ratings
for flow and pressure.
Visual confirmation that
surfaces are residue free.
SupplyConductivity
Cleaning Action
Rinse : Membrane
pressure setpoint(s) and
tangential velocity
Soak : Hold time
Recirculate wash : Membrane
pressure setpoint(s) and
tangential velocity
Soak : 30 minimum
Recirculate Wash : 10 minimum
Circuit #
B-01
B-01
B-01
B-02
B-02
B-02
Water/
Chemical/
Soil Test
Water
Chemical
Soil
Water
Chemical
Soil
P-1(gpm)
P-2(sec)
Unique Parameters
P-3(min)
P-4(gal)
Test Results
Swab
Sample (ppm)
P-5(mS)
Rinse
Sample (uS)
NA
NA
NA
NA
NA
NA
NA
NA
Date
Table D. Buffer department unique configurable parameter and test results database.
Copyright ISPE 2004
drain. Wash solutions are recirculated through the membranes back to the hold tank before being sent to the same
local drain. Therefore, the hold up volume of the process tank
will determine the length of each wash and rinse step.
Multiple rinse/wash steps may be needed to achieve desired
contact time depending on the fluid throughput.
The cleaning action for a TFF unit is defined by the
tangential flow velocity achieved across the membrane, the
required trans-membrane pressure drop, and membrane
soak time. The tangential velocity will sweep away biologic
soils. The trans-membrane pressure differential will create
flux flow through the membrane. Some membranes are
sensitive to extreme temperatures and therefore will only
accommodate ambient rinses and washes. The required tangential velocity, trans-membrane pressure drop and cleaning
solution temperature should be referenced from manufacturers recommendations or plant operating experience.
Summary
This approach to CIP Cycle Development requires implementation of the C&Q Guide, developing a detailed plan based on
equipment functional specifications, accurately scheduling
the activities, and implementing three phases of testing.
When successfully implemented, CIP cycle development will
promote a very successful cleaning validation effort, and
ultimately minimize production losses related to insufficient
cleaning cycles.
References
1. ISPE Baseline Pharmaceutical Engineering Guide, Commissioning and Qualification, Volume 5, 2001.
2. Ibid, p.30.
3. Ibid, p. 19.
4. Ibid, p.53.
5. Ibid, p.57.
6. Brunkow, R., Delucis, D., Haft, S., Hyde, J., Lindsay, J.,
McEntire, J., Murphy, R., Myers, J., Nichols, K., Terranova,
B., Voss, J., and White, E., Cleaning and Cleaning Validation: A Biotechnology Perspective, PDA, Bethesda, MD,
1996.